King County Flood Control District
2017 Preliminary Draft Budget
and Work Program Overview Brian Murray
Water and Land Resources Division
June 30, 2016
Department of Natural Resources and Parks
Water and Land Resources Division
River and Floodplain Management Section
Discussion Overview
1. Assumptions for the 2017 Budget and CIP
2. Flood Risk Reduction “Product Families” and
Anticipated 2017 Performance Metrics
3. Operating Program Budget and Work Program
4. Emerging Issues for 2017
5. Policy Questions for Discussion
Three objectives:
• Reduce risks from flood
and channel migration
hazards
• Minimize the environmental
impacts of flood projects
• Reduce long term
maintenance costs
Flood Control District Operating Programs
How do we reduce flood risks?
1. Identify hazards
2. Assess risk and vulnerabilities
3. Build awareness of hazards
4. Develop a plan and strategy to reduce risks
5. Actions to avoid risk
6. Actions to reduce or mitigate risk
7. Evaluate, learn, and adjust
ILA Work Program Categories 1. Asset Management and
Annual Maintenance 2. Planning, Communications,
and Grants 3. Flood Hazard Assessments,
Mapping, and Technical Studies
4. Flood Preparedness, Regional Flood Warning Center, and Post Flood Recovery
5. Program Management, Supervision, Finance, and Budget
6. Program Implementation 7. Overhead / Central Costs 8. Capital Investments:
Construction and Repair, Acquisitions and Elevation
Structural Risk Reduction Performance Metrics
2017 Construction
1. Countyline Levee Setback Year 2 (White)
2. City of Renton Cedar River Gravel Removal Year 2 (Cedar)
3. Tolt Pipeline Protection (Lower Snoqualmie)
4. SE David Powell Road (Lower Snoqualmie)
5. SE Fish Hatchery Road (Lower Snoqualmie)
6. SE 19th Way (Lower Snoqualmie)
7. Milwaukee 2 – City of Kent ILA to complete acquisitions and feasibility in 2016; 2nd ILA will be necessary for design and construction (Green)
Structural Risk Reduction Performance Metrics
Final Design, Construct 2018
1. Riverbend (Cedar)
2. Nursing Home Levee
Setback (Green)
3. Lower Coal Creek
(City of Bellevue –
final design 2017;
construct 2017-
2019)
4. South Park
(Duwamish) Pump
Station (City of
Seattle)
Structural Risk Reduction Performance Metrics
60% Design, Construct 2019
1. Lower Russell
(Green)
2. South Fork
Snoqualmie I-
90 Protection
Project
(Snoqualmie)
Structural Risk Reduction Performance Metrics
30% Design, Construct 2019-2020
1. S 277th (Green)
2. Willowmoor
(Sammamish)
3. Breda Levee
Setback (Green)
Structural Risk Reduction Performance Metrics
Feasibility; Construction date TBD
1. S. 277th (Green River) feasibility only; no design or construction funding
2. Corridor 6-year Investment Strategy Implementation (assuming adoption in 2016)
a) Cedar
b) Tolt (complete feasibility in 2018)
c) South Fork Snoqualmie (start feasibility in 2018)
Interim Product Performance Metrics
• Hazard Studies
– Snoqualmie Hydrology
and Hydraulics Study
– Climate Change
Analysis with UW
– Channel Migration Zone
Mapping on Raging and
White Rivers
– Post-flood channel
monitoring
• Corridor Planning
– Middle Fork
Snoqualmie
– Cedar, South Fork
Snoqualmie, and Tolt to
be considered fall 2016
– Lower Green River
Corridor Plan and
Environmental Impact
Statement
– Capital budget
Asset Management Performance Metrics
Capital Repairs
1. Construct nine repair projects (pending Board consideration of mid-year budget revision)
2. Sammamish River Bank Repair (two sites)
3. Dutchman Revetment Repair (Lower Snoqualmie)
Asset Management Performance Metrics:
Inspections, Maintenance, and Mitigation
• Inspect infrastructure
• Inspect property
• Develop site
management plans
• Maintain property and
infrastructure
• Mitigation for past PL
84-99 maintenance
action
Flood Warning Performance Metrics
1. Flood Warning
Center
Performance
2. Flood Patrol
Performance
3. Flood information
systems
Pass-Through and Consulting to Others
Performance Metrics
• Grant program
agreements and
payments
• Flood Hazard
Certification
Development Review
• Large Wood Hazard
Inspections
• Cedar Programmatic
Large Wood Mgmt
1. Asset Management and Maintenance
1. Increase maintenance
crew time for
completed projects and
800+ acres of property
2. Levee access road
maintenance on SF
Snoqualmie
3. Noxious weed
management
4. Black River Pump
Station
2. Planning, Communications, and Grants
1. 2018 Flood Plan
Update
2. Community Rating
System (CRS)
participation
3. Grant applications
3. Flood Hazard Studies, Mapping
1. Climate Change analysis (contract with UW)
2. Snoqualmie Hydrology and Hydraulics Evaluation
3. Raging River CMZ Final Map
4. White River CMZ Final Map
5. USGS Sediment Study on White River (Cost-Share)
6. $300,000 for post-flood channel monitoring (if needed)
4. Flood Preparedness, Flood Warning Center,
and Post-Flood Recovery
1. Annual flood
preparedness
campaign by October 1
2. Flood alert system
3. USGS gauges
4. Sandbag program
5. Flood warning center
and patrols ($430,000
for flood response if
needed)
5. Program Management, Supervision,
Finance, and Budget
1. Financial management, accounting
2. Audits by State, FCD, grantors, and internal quarterly contract audits
3. Capital program oversight
4. Management and Administration
6. Program Implementation
1. Cedar Large Wood Management programmatic HPA
2. Work program coordination with other agencies and stakeholders
3. Community inquiries
4. ILA development
5. Support for Basin Technical Committee, Advisory Committee, and Board of Supervisors
2017 Operating Budget Key Changes
1. Increased crew time for maintenance of levees, revetments, and property
2. Enhanced flood warning system for SF Skykomish and White, expansion of sandbag program
3. Flood Plan Update consultant support
4. USGS Sediment Study on White River
5. Cedar River Large Wood Programmatic HPA
6. Increase outreach costs for printing and mailing
Notes:
• King County Overhead / Central Costs (note that capital fund pays proportional share of these costs)
• Note: Budget includes $730,000 in expenditures that are flood-dependent (flood warning and patrol, post-flood channel monitoring)
Emerging Issues for 2017-2022
1. Interim SWIF projects added to CIP following based
on February 2016 Board resolution
2. Lower Green River Corridor Plan and Environmental
Impact Statement added to capital project list
3. Prepare for 2018 King County Flood Hazard
Management Plan Update
Policy Question: Flood Damage Repairs
How can the District respond to critical flood damage
repairs without slowing progress on other projects and
programs?
Options might include additional reliance on other
agencies (such as King County Roads Services
Division or other jurisdictions), staff positions to back-
fill work while repairs are completed, on-call
consultant and contractor resources, or deferring
other work program products.
Policy Question: Fund Balance Reserve
Should project expenditures in later years of the
capital program be deferred to ensure that the
minimum cash balance target of $8 million is achieved
throughout the 6-year planning window?
Or is it sufficient to monitor and adjust in future years
if necessary to maintain the required fund balance?
Policy Question: Non-Structural Mitigation
As part of the 2017 budget process we are seeking
input on how to prioritize mitigation of the remaining
420 structures that have been identified, and also on
the appropriate timeframe to implement this body of
work.
What is the appropriate pace of implementation for
non-structural flood mitigation work? If the pace of
implementation were increased from 10-12 per year,
what other milestones should be deferred?
Questions?
Brian Murray, Environmental
Programs Managing Supervisor
(206) 477-4782
www.kingcounty.gov/rivers