l egal i ssues i nvolved with the d rilling for n atural g as and the s iting of e lectric g...
TRANSCRIPT
LEGAL ISSUES INVOLVED WITH THE DRILLING FOR NATURAL
GAS AND THE SITING OF ELECTRIC GENERATING
FACILITIES IN THE STATE OF NYOCTOBER 18, 2012
Wendy A. Marsh, Esq.Hancock Estabrook, LLP
100 Madison Street, 1500 AXA Tower ISyracuse, NY 13202
Phone: (315) [email protected]
Program Overview
New York State regulation of high volume hydraulic fracturing in New York State
Municipal regulation of drilling activities
Landowners’ involvement in the drilling process
Regulation of other electric generating facilities under Article X of the NYS Public Service Law
Thoughts on the future
State Regulation
State Environmental Quality Review Act– Environmental Impact Statement – Public Comment– Findings
SEQRA History– Generic Environmental Impact Statement (GEIS) on the
Oil, Gas and Solution Mining Regulatory Program• 1992
Potential Environmental Impacts Associated with Hydrofracking
Chemicals in the process water
Noise
Traffic
Well casing problems
Etc.
SGEIS
First Supplemental Draft Generic Environmental Impact Statement (SDGEIS)– September 2009
Revised draft SDGEIS– September 2011
Public Comment Period ended on January 11, 2012
Next Step in the Process
NYSDEC Regulations
Oil, Gas, and Solution Mining Law– Application requirements– Permit Conditions– Technical requirements
Proposed regulations– Permitting process– Surface activities on state-owned lands– SPDES Permits
NYSDEC Regulations
Proposed rules released on September 28, 2011
Public comment ended on January 11, 2012
Recent requirement to study health impacts
Likely need to begin the regulatory process over
State Regulatory Process Summary
NYSDEC to complete SEQRA
NYSDEC to issue final regulations for hydrofracking activities
Litigation over SEQRA
Litigation over regulations
Some Things Can’t Be Completely Regulated Locally
Adult Entertainment
Sand and Gravel Mining
Wind Turbines
WHY CAN’T YOU REGULATE LOCALLY?
Some authority is preempted
Constitutional Law
Statutory Law
New York courts have examined this limitation
Frew Run Legal Issue
MLRL states:
“For the purposes stated herein, this title shall supersede all other state and local laws relating to the extractive mining industry; provided, however, that nothing in this title shall be constructed to prevent any local government from enacting local zoning ordinances or other local laws which impose stricter mined land reclamation standards or requirements than those found herein.”
ECL 23-2703[2]
Frew Run Holding
The Mined Land Reclamation Law does not preempt municipalities
from banning sand and gravel mining
Dryden Facts
August 2, 2011 Zoning Ordinance Amended
Ban all activities related to the exploration for, and production or storage of, natural gas and petroleum
Anschutz owned gas leases covering approximately 22,200 acres in the Town and had invested approximately $5.1 million in activities
20
Legal Issue
Is the ability to prohibit activities associated with the exploration for, and production or storage of natural gas and
petroleum
PREEMPTED BY THE OIL, GAS AND SOLUTION MINING LAW
(OGSML)?
Dryden Legal Issue
OGSML states:
“The provisions of this article shall supercede all local laws and ordinances related to the regulation of the oil, gas and solution mining industries; but shall not supercede local government jurisdiction over local roads or the rights of local government under the real property tax law”
ECL 23-0303[2]
Dryden Holding
Judge Rumsey reviewed the Frew Run Court of Appeals decision and determined:
– The supercedure clauses are “nearly identical”
– Neither contains a clear expression of legislative intent to preempt local control over land use and zoning
– The ban was upheld for the same reasons as set forth in Frew Run
Middlefield Facts
Town of Middlefield Board amended its zoning law in June 2011 to:
Prohibit “heavy industry . . . and all oil, gas or solution mining and drilling”, which, according to the court, effectively banned oil and gas drilling with the Town.
Plaintiff had two oil and gas leases
Middlefield Legal Issue
Same as Dryden:
Does OGSML prohibit local municipalities from enacting legislation which may impact upon the oil, gas and solution drilling or mining industries other than that pertaining to local roads and the municipalities’ rights under the real property law?
Middlefield Decision
Detailed review of the legislative history and intent of OGSML, to hold that it “finds no support within the legislative history leading up to and including the 1981 amendment of the ECL as it relates to the supersession clause which would support plaintiff’s position . . . .”
“[T]he state’s interests may be harmonized with the home rule of local municipalities in their determination of where oil, gas and solution drilling or mining may occur. The sate maintains control over the “how” of such procedures while the municipalities maintain control over the “where” of such exploration.”
Appeals
Both decisions at the Supreme Court level
Both appealed to the Third Department
No decisions yet from the Third Department
City of Binghamton
Elvin Jeffrey, Vestal Gas Coalition, Arena Hotel Corporation, Nelson Holdings Ltd., and Binghamton-Conklin Gas Coalition
Steering Committee v. Matthew T. Ryan, in his official Capacity as Mayor, City of Binghamton, and The City
Council, City of Binghamton
Broome County Supreme CourtIndex No. CA2012-001254
RJI No: 2012-0695-MOctober 2, 2012
Binghamton Facts
City Council enacted “Prohibition of Gas and Petroleum Exploration and Extraction Activities, Underground Storage of Natural Gas, and Disposal of Natural Gas or Petroleum Extraction, Exploration, and Production Waste” in December 2011
Binghamton Legal Issue
Was the prohibition merely a moratorium?
Court held that Respondent City failed to provide any evidentiary proof that would provide a justification, based upon the health and safety of the community, for the banning of gas exploration, storage and extraction.”
The law was held to be a moratorium, and the City must satisfy the well established legal requirements that show a dire emergency; that the moratorium is reasonably calculated to alleviate a crises; and that they are taking steps to solve the problem.
Binghamton Decision
Local law overturned because it failed to meet the criteria for a properly enacted moratorium
The Judge did agree with the holdings in the previous cases that the OGSML did not preempt the local law
Litigation
Courts decide on SEQRA Process and NYSDEC regulations
Courts decide the preemption arguments
Economic Reality
Wind Energy Regulation :What can be learned?
Law of the past:
SEQRA Review at local level
Site Plan / Special Use Permit issued at local level
License / Host Community Agreement at local level
Potential Wind Environmental Impacts
Visual Impacts Shadow Flicker Noise Impacts Wetlands Birds and Bats Habitat Agricultural Impacts Traffic Property value Archeological Etc.
ARTICLE X OF THE PUBLIC SERVICE LAW
Applies to Siting of Major Electrical Generating Facilities– 25 MW or Greater
NYS Board on Electric Generation Siting and the Environment reviews projects and grants or denies “Certificate of Environmental Compatibility and Public Need”
ARTICLE X OF THE PUBLIC SERVICE LAWSITING BOARD
5 Permanent Members are the Chair of the Department of Public Service, Commissioners of DEC, DOH, and Economic Development, and the Chair of NYSERDA
2 ad hoc public members from municipality where facility is proposed
ARTICLE X OF THE PUBLIC SERVICE LAW
SUPERSESSION PROVISION Siting Board may grant a Certificate in
contravention of local law if it determines that the law is “unreasonably burdensome in view of the existing technology or the needs of or costs to taxpayers”
Stop Shopping - No other state or local permits required for certified facility
ARTICLE X OF THE PUBLIC SERVICE LAW PRELIMINARY SCOPING STATEMENT
Need to identify the local laws and regulations to be preempted by the Siting Board
Notice to the residents in the municipality where facility is proposed 3 days before filing of the scoping document
ARTICLE 10 OF THE PUBLIC SERVICE LAWPUBLIC PARTICIPATION
- “To facilitate the pre-application and application processes and enable citizens to participate in decisions that affect their health and safety and the environment, the department and such person shall provide opportunities for citizen involvement.”
- “Such opportunities shall encourage consultation with the public early in the pre-application and application processes.”
- “The primary goals of the citizen participation process shall be to facilitate communication between the applicant and interested or affected persons. The process shall foster the active involvement of the interested or affected persons.”
ARTICLE 10 OF THE PUBLIC SERVICE LAWINTERVENOR ACCOUNT
Preliminary scoping statement shall be accompanied by a fee in an amount equal to $350 for each thousand kilowatts . . . but no more than $200,000
to defray pre-application expenses incurred by municipal and local parties for expert witness, consultant, administrative and legal fees
Not for litigation
ARTICLE X OF THE PUBLIC SERVICE LAWAPPLICATION
Fee in an amount equal to $1,000 for each 1000 kW of capacity, not to exceed $400,000 for intervenor fund
ARTICLE 10 OF THE PUBLIC SERVICE LAWDECISIONS
The Siting Board shall make the final decision upon the record
The Siting Board shall not grant a CECPN without making explicit findings:
- Probable environmental impacts - Beneficial addition or substitution of capacity- Project is in public interest- Adverse environmental effects will be minimized or
avoided to the maximum extent practicable- EJ impacts avoided, offset, or minimized
What Does This Mean?
Municipalities will continue to bear the burden of the visual impacts, but not have the financial benefits afforded in the Host Community Agreements
Decisions about siting are no longer local decisions that are ultimately made by the majority of the voters in a municipality
Q & A
Wendy A. Marsh, Esq.Hancock Estabrook, LLP
100 Madison StreetSyracuse, New York 13202
(315) 565-4500 [email protected]
www.hancocklaw.com