(lapp) project management training

179
CAPITAL AREA MPO Locally Administered Projects Program (LAPP) Project Management Training March 17, 2016 9:00 AM – 12:00 PM

Upload: vandung

Post on 19-Dec-2016

265 views

Category:

Documents


5 download

TRANSCRIPT

  • CAPITAL AREA MPO

    Locally Administered Projects Program (LAPP) Project Management Training

    March 17, 2016 9:00 AM 12:00 PM

  • Trainer Introductions

    Danna Widmar Rick Lakata

    Eddie Dancausse Mike Dawson

    Tammy Richards Sheila Gibbs Rob Hanson Kathy Smith

    Chris Haire/Mohammad Mahjoub Mike Kneis

    Chris Lukasina Shelby Powell

  • Todays Agenda

    Locally Administered Projects Program Overview Program Overview TIP# and TIP/STIP Processes CMAQ Application

    Federal Considerations CMAQ NEPA Uniform Act Fiscal and Reporting

    NCDOT Processes/Contacts Local Program Management Unit Issues Environmental Documentation Design Major Projects & Minor Projects Design Contract Proposals Right of Way Issues Procurement / Award Concurrence Construction Oversight Reimbursement Procedures

    LAPP Project Delivery Requirements LAPP Project Roundtable Wrap Up

  • Locally Administered Projects Program

    Overview

  • LAPP - Introduction

    Responsibility of the MPO

    In March, 2010 the TAC directed staff to create the Locally Administered Projects Program.

    Holistic approach to identify & prioritize highly effective projects

    Efficient use of available funds

    Avoid future Federal rescissions to the maximum extent possible

    Annual modal investment mix

    Project tracking system

    Training program

  • LAPP Eligibility

    Locally- Administered By applying, the local government or NCDOT Division is committing to

    sponsor the project.

    The sponsor will be responsible for all federal and state reporting requirements.

    There will also be reporting on a regular basis required by CAMPO.

    An inter-local agreement will be required between NCDOT and the project sponsor.

    Local sponsors will be required to front all project costs, invoice NCDOT, and get reimbursed for the agreed upon federal percentage.

    Shovel Ready Timely execution of agreement to proceed. Requested phase authorized within funding year.

  • FFY17 Roadway

    Projects

    Roadway Projects TIPID Project Name Sponsoring

    Agency Requested

    Phase Total Cost Local

    Match %

    Requested CAMPO Funding

    Recommended CAMPO Funding

    Total Score

    CMAQ Eligible & Weighted Lifetime Emissions Reduction

    Program Fund

    Designated Project Manager

    Designated ROW Agent

    U-5118GB US Highway 401- NC 55 & 42 (N Main Street) and Sun (...)

    Fuquay-Varina PE, CON $858,000 20% $686,400 $686,400 58.64 No STPDA Tracy Stephenson & Matt Poling

    N/A

    U-5118JB NC 55 Bypass SuperStreet Holly Springs CON $1,500,000 20% $1,200,000 $1,200,000 58.18 No STPDA Kendra Parrish Patrick Lee - 1 Wake Co. Easement

    U-5118OA Wake Forest/Blount/Person Rd. Complete Streets Pha (...)

    Raleigh CON $1,770,000 28% $1,274,400 $1,274,400 54 No STPDA Todd Delk N/A

    U-5118FB Arendell Avenue Access Management and Operational (...)

    Zebulon ROW, CON $1,195,000 20% $956,000 $956,000 52 No STPDA Chris Ray Chris Ray - 1 parcel

    U-5927A N Judd Parkway NE Widening Improvements

    Fuquay-Varina CON $2,810,000 40% $1,686,000 $1,686,000 50.64 No STPDA Tracy Stephenson & Matt Poling

    Contracting Services

    U-5118BB Durham Road (NC98 Bus) - Operational Improvements (...)

    Wake Forest ROW, CON $2,547,615 20% $2,038,092 $2,038,092 49.1 No STPDA Candace Davis Contracting Services

    U-5928 Peakway South Salem Interchange Apex CON $5,000,000 50% $2,500,000 $2,500,000 48.55 No STPDA Russell Dalton & Adam Stephenson

    Adam Stephenson - 1 large & grading

    U-5317 Connect N Judd Parkway NW Fuquay-Varina ROW $5,900,000 50% $2,950,000 $2,950,000 36.91 No STPDA Tracy Stephenson & Matt Poling

    Contracting Services

  • FFY17 Bike/Ped

    Projects

    Bicycle & Pedestrian Projects TIPID Project Name Sponsoring

    Agency Requested

    Phase Total Cost Local

    Match Requested

    CAMPO Funding

    Recommended CAMPO Funding

    Total Score

    CMAQ Eligible & Weighted Lifetime Emissions Reduction

    Program Fund

    Designated Project Manager

    Designated ROW Agent

    C-5604OC Walnut Creek Greenway - Trailwood segment

    Raleigh ROW, CON $1,020,000 33% $683,400 $683,400 56.14 Yes - 11,610 kg CMAQ Lisa Potts Greg Pittman - 1 large parcel

    U-5530PA NC 210 S. Sidewalk Connections Angier PE, CON $522,850 20% $418,280 $418,280 53.29 No STPDA Bill Dreitzler & Jimmy Cook

    N/A

    C-5604IB White Oak Creek Greenway - MacArthur Section

    Cary CON $4,550,000 55% $2,047,500 $2,047,500 52.57 Yes - 14,463 kg CMAQ Amy Mackintosh Donna Lunsford - Rail & Hm Assoc.

    C-5604QA Main Street Improvements Youngsville PE, CON $632,500 20% $506,000 $506,000 48.71 Yes - 12,947 kg CMAQ Don Belk & Bob Clark N/A

    C-5604OD Crabtree Creek West Greenway Raleigh CON $4,550,000 66% $1,547,000 $1,547,000 43.86 Yes - 12,053 kg CMAQ Lisa Potts N/A

    C-5604JA Utley Creek Greenway Connection Holly Springs PE, ROW, CON $725,000 20% $580,000 $580,000 43.43 Yes - 38,976 kg CMAQ Kendra Parrish Patrick Lee - Minor easements

    U-5530 LA and LB

    Sam's Branch Greenway Phase 2 Clayton CON $2,136,000 20% $1,708,800 $1,708,800 42.29 Yes - 6,272 kg TAP Tim Simpson Carolina Land Acq. - 2 easements

  • LOCALLY ADMINISTERED PROJECTS PROGRAM

    Implementation Process

    Project Submission / Project Information

    & Data

    LAPP Project Selection

    LAPP Project TIP / STIP Programming

    (by phase)

    Prepare & Execute Inter-Local Agreement

    Recommended Oversight Meeting

    Design / NEPA Authorization

    Professional Services

    Recommended Scoping Meeting

    Environmental Document

    Design

    ROW Authorization ROW Acquisition ROW Certification Contract Proposal / Engineers Estimate

    Construction Authorization

    Procurement of Construction

    Services Construction

    Project Completion & Maintenance

  • TIP changes

    Amendments require CAMPO Executive Board (TAC) action - 2-3 Month Process Stand-Alone TIP Project Numbers

    Add or delete a project Change in design or scope, such as termini, number of lanes, etc. Add or substantially modify a phase of work Change in cost Change in schedule

    Group TIP Project Numbers Substantial change in cost, schedule or scope

    Modifications that require administrative approval (No TAC action)

    Minor change in funding amount

    Use different source of funds

    Small changes in project scope

  • STIP changes*

    Revisions - requires Board of Tr. (BOT) action and additional 2-3 Month Process Change Fiscal Year in which $$ to be authorized

    NOTE: FFY begins Oct 1; ends Sep 30

    Add (or modify) a Phase of work

    Add new stand alone project (not Group #s, e.g. U-5118)

    Cases NOT requiring BOT action Minor change in funding amount

    Use different source of funds

    *If LAPP funds involved, MPO must review and concur

  • CMAQ Application

  • Federal Highway Administration:

    Considerations in Project Delivery

  • CMAQ/NEPA

  • Congestion Mitigation & Air Quality Program (CMAQ)

    Federal program that provides funding for projects or programs in air quality concern areas to help achieve & maintain air quality standards

    Jointly administered by FHWA & FTA, in conjunction with EPA

    Funding available for areas that are non-attainment or maintenance

    Eligible projects / programs include those with air quality benefit that are likely to contribute to the attainment of the standards

  • Eligible CMAQ Projects

    Congestion Reduction & Traffic Flow Improvements

    Transit & Public Transportation Improvements

    Bicycle & Pedestrian Facilities/Programs

    Transportation Control Measures (TCMs)

    Travel Demand Management

    Public Education & Outreach

    Idle Reduction

    Alternative Fuels & Vehicles

    Carpooling & Vanpooling

    Diesel Engine Retrofits & Other Advanced Truck Technologies

    Value/Congestion Pricing

  • CMAQ

    Project Submittal Process Initial Discussion with Applicants to Pre-screen Projects

    CMAQ Application

    Submitter review

    MPO/RPO Endorsement and Approval

  • CMAQ

    Interagency Review FHWA, NC Division of AQ (NCDAQ), Environmental

    Protection Agency (EPA) and Federal Transit Administration (FTA) review applications for eligibility and provide review comments to NCDOT

    Projects are not approved until comments/questions are addressed

    18

  • FHWA CMAQ Project Authorization

    CMAQ Application with Emissions Benefits

    Metropolitan Transportation Plan (MTP)/Transportation Improvement Program (TIP)/State TIP

    Right of Way Authorization

    Environmental Document

    Federal Share

    Project Completion Date

    19

  • National Environmental Policy Act (NEPA)

  • NEPA

    NEPA of 1969 (signed January 1, 1970)

    Established Natl environmental policy & goals

    Required agency disclosure of impacts of proposed actions and possible mitigation

    Created basis for environmental impact statements (EIS) for major Federal actions

    Created Council on Environmental Quality (CEQ)-monitors Federal actions, provides overall guidance, tracks trends and resources.

  • When Does NEPA Apply?

    For FHWA, basically when a project is proposed for Federal-aid Highway Funding

    Action-highway or transit project proposed for FHWA funding, but

    actions must also include activities such as multiple use permits or changes in access control that may or may not involve commitment of funds

  • What must be considered?

    Natural and built environments

    Agencies must take a hard look at consequences of actions and keep public informed

    NEPA goal: prevent uniformed decisions versus unwise ones

  • What are Classes of Actions?

    Categorical Exclusion (CE)-actions which do not individually or cumulatively have a significant effect on the human environment

    Environmental Impact Statement (EIS)-detailed written statement on major Federal actions significantly affecting the human environment

    Environmental Assessment (EA)-significance of environmental impact is not clearly established; to determine the appropriate environmental document required

  • What will be needed to receive the Federal Funds?

    Completed/approved environmental document (PCE/CE/EA/EIS)

  • Additional NEPA Resources

    Federal Aid Essentials for Local Public Agencies

    http://www.fhwa.dot.gov/federal-aidessentials/

    NCDOT Local Projects Administration https://connect.ncdot.gov/municipalities/funding/Pages/def

    ault.aspx

    Local Programs Management (LPM) Handbook Updates https://connect.ncdot.gov/municipalities/Funding/Pages/LP

    M%20Handbook.aspx

    http://www.fhwa.dot.gov/federal-aidessentials/http://www.fhwa.dot.gov/federal-aidessentials/http://www.fhwa.dot.gov/federal-aidessentials/http://www.fhwa.dot.gov/federal-aidessentials/https://connect.ncdot.gov/municipalities/funding/Pages/default.aspxhttps://connect.ncdot.gov/municipalities/funding/Pages/default.aspxhttps://connect.ncdot.gov/municipalities/funding/Pages/default.aspxhttps://connect.ncdot.gov/municipalities/Funding/Pages/LPM Handbook.aspxhttps://connect.ncdot.gov/municipalities/Funding/Pages/LPM Handbook.aspxhttps://connect.ncdot.gov/municipalities/Funding/Pages/LPM Handbook.aspx

  • CMAQ/NEPA

    Questions????

    Eddie Dancausse

    FHWA AQ Specialist

    919-747-7026

    [email protected]

  • Uniform Act

  • Essential Requirements of the Uniform Act for Local Public

    Agencies

  • Learning Outcomes

    Identify the rights conveyed in the 5th and 14th amendments to the U. S. Constitution

    State the purposes of the Uniform Act.

    Explain who must follow the Uniform Act

    Interpret when an Agency must follow the Uniform Act

    30

  • When Using Federal-aid funds,

    there are Strings Attached

    So, whats the catch?

  • 32

  • Government Property Acquisition: Some History

  • The power of any sovereign government

    to take private property without

    the consent of the owner. 34

  • U. S. Constitutional Limitations on Power of Eminent Domain

    5th Amendment

    nor shall private property be taken for public use without just compensation.

    14th Amendment

    nor shall any State deprive any person of life, liberty, or property, without due process of

    law

    35

  • Legal Authority to Acquire Property

    36

    U.S. Constitution 5th and 14th Amendments

    State Constitution

    State Laws

    State Administrative Regulation

    Federal Uniform Act

    Uniform Act Implementing Regulations

  • Uniform Act Uniform Relocation Assistance and Real Property

    Acquisition Policies Act of 1970, as amended (Public Law 91-646)

    37

  • Where can you find the law and the rules to carry out the law?

    The law is codified in 42 U.S.C. 4601

    The regulation governing the law is found in

    49 CFR 24

    http://www.ecfr.gov

    38

    http://uscode.house.gov/view.xhtml?path=/prelim@title42/chapter61&edition=prelim

  • Uniform Act Twofold Purpose

    Establish uniform and equitable land acquisition policies for Federal and federally-assisted programs.

    Ensure the uniform and equitable treatment of persons displaced from their homes, businesses or farms by Federal and federally-assisted programs.

    39

  • Who Must follow the URA?

    Any Federal department or agency in the executive branch

    Any department or Agency of a State or a political subdivision of a State

    Any entity with the authority to acquire property by eminent domain under Federal or State law

    40 40

  • When Must an Agency Follow The Uniform Act?

    When any phase of a project is federally-funded

    When real property is acquired

    When property owners and/or tenants are displaced as a direct result of land acquisition, demolition or property redevelopment

    41

  • Public Law 3.JPG

    42

    Major Components of the Uniform Act

    ../../Local Settings/Temporary Internet Files/Documents and Settings/HP_Owner/Local Settings/Temp/Temporary Directory 2 for Lisa_Barnes-1205368399691[1].zip/Public Law 3.JPG

  • Basic Requirements of 49 CFR Part 24 (URA)

    1. Appraise FMV of property to be acquired

    2. Review appraisals

    3. Offer no less than FMV, in writing

    4. Negotiate in Good Faith

    5. Avoid litigation if possible

    6. Relocate residences, businesses, others

    7. Provide relocation Advisory Services

    43

  • A Quick Review

    What rights do the 5th & 14th amendments convey?

    What is the two-fold purpose of the Uniform Act?

    Who must follow the Uniform Act?

    When must an Agency must follow the URA Act?

    What do you risk if there is non-compliance?

    44

  • 45

  • Contact Information:

    Michael Dawson

    Realty Officer FHWA NC Division

    310 New Bern Ave, Suite 424

    Raleigh, NC 27601

    919-747-7009

    [email protected]

  • Funding Obligation & Reporting

  • Project Authorization / Funds Obligation

    FHWA commitment that Federal funds are available for the project

    1.Preliminary Engineering (PE) (you have 10 years to construct the project Studies are not a good idea)

    2. Right of Way acquisition (ROW)

    3. Construction (CON)

    Required prior to incurring any expenses Work done before the date of FHWA Division authorization is NOT

    eligible for reimbursement

    Project authorizations are authorized by FHWA within 4 days of them being received in our office

    I e-mail the Division Project Manager when authorizations have been signed

  • Inactive Projects Reports

    - Projects with no activity (expenditures/invoices) for 1 year or more.

    - Once a project hits a report, we have one quarter to get the project off the list or FHWAs Finance Section is REQUIRED to deobligate the funding.

    - Remember that the Municipal Agreement states that a project must be invoiced at least once every 6 months to keep the project active and eligible for Federal funding.

  • Supercircular 2 CFR Part 200

    OMB has implemented new guidance that will apply to new awards authorized on or after December 26, 2014 on Administrative Requirements, Cost Principles, and Audit Requirements for Federal awards. It is 2 CFR 200 (aka "Supercircular").

    In it, it addresses project closeout. 2 CFR 200.343 (a) - The non-Federal entity must submit, no later than 90 calendar days after the end

    date of the period of performance, all financial, performance, and other reports as required by or the terms and conditions of the Federal award.

    (b) - Unless the Federal awarding agency or pass-through entity authorizes an

    extension, a non-Federal entity must liquidate all obligations incurred under the Federal award no later than 90 calendar days after the end date of the period of performance as specified in the terms and conditions of the Federal award.

    Project end dates are now required to be entered into our project tracking/accounting system. Please ensure that all documents are received well before the 90 calendar day deadline to ensure funds are not liquidated.

  • FHWA NC LPA Review Findings

    1. Expenditures occurred before FHWA Authorization was signed

    2. Projects not competitively bid

    3. No pay records/diaries

    4. No Buy America Certification

    5. No (not enough) testing/test reports

    6. Subcontract was not authorized in writing by NCDOT (SAF Form was not sent to or signed by NCDOT)

    7. No DBE documentation

    8. NCDOT personnel were not verifying pay quantities before approving invoices

  • Locally Administered Project Reviews

    Advertisement/Bid documents

    Consultant Selection process

    Project Diaries

    Pay Record Books

    Concrete/Asphalt/ABC test results/frequencies

    Weight tickets

    Pay Estimates

    Supplemental Agreements

    Wage Rates (if applicable)

    DBE/Subcontractors

    Grading

    Traffic Control

    Erosion Control

    Signs

    Material Certifications

    Job-site Posters

    LPA/NCDOT Oversight

    Project Closeout

  • Preliminary & Project Records Reviews

    LPA Program Manager will be conducting two types of reviews:

    Compliance Assessment Reviews Headquarters Review with their checklist (30 this year)

    Records Review Will consist of a review of all project records and documentation for the project. (Open book test!)

  • Questions?

    First line of communication is NCDOT; however, if you need me:

    Tammy Richards, FHWA

    919-747-7004

    [email protected]

  • NCDOT Processes and Contacts

  • Local Project Management & Implementation

  • Our Relationship

    NCDOT has an agreement with LGA.

    Defines responsibilities of each party

    Specifies scope of work, timeframes, and funding

    CAMPO awards funding, concurs with agreement and tracks progress.

    LGA has an agreement with consultant.

    Consultant agreement is in place to deliver certain parts of the municipal agreement

    NCDOT should not be directing consultant; that is LGAs responsibility and authority.

  • Coordination

    All projects will initiate with LPMO in order to establish Agreement.

    Coordinate all reviews through your program consultant.

    Program Consultant will coordinate review through Department or advise where to go.

  • Agreement

    Cannot be initiated until funding is programmed in the STIP in correct year.

    Executed between NCDOT and the Local Governmental Agency.

    Includes provisions that LGA must comply with in order to receive reimbursement.

    Includes funding, time frames, scope of work, and responsibilities.

    Funding Authorizations cannot occur until a fully executed agreement is in place.

  • What is the Local Project System?

    The Local Project System is Simple Electronic System that Provides a Single Point for Project Communication, Storage and Status When

    Delivering a Locally Administered Project

    60

  • New Word Translations

    Application = Current PIDs (Project Information Datasheets)

    Agreement = unchanged

    Claim = Invoice

    Change Request = Revision or Authorization of Funds

    61

  • How Do I Get Started?

    Get a User ID

    Attend Training

    Start Using the New System to: Submit Application to Request an Agreement for a New Project

    Submit Documents for review on Approved Agreements

    Submit Change Requests for Approved Agreements

    Submit Claim Reimbursements for Approved Agreements

    62

  • User IDs

    Why Do We Need a User Name and Password?

    In Order to Log Into the Web-based System, a User Name and Password is Necessary to Identify the User and any Projects Associated With That LGA

    How Do I get a User Name and Password?

    Submit the Security Form Available on the LPMO Website to [email protected]

    63

  • Where Can I Find User Support?

    Help Guides and Documentation

    NCDOT Help Desk Support for Password & Technology

    NCDOT LPMO for Business Process

    Online Training Webinars (as required)

    64

  • Contact Details

    Local Programs Management Office

    Divisions 1 7:

    Sheila Gibbs

    [email protected]

    919-707-6625

    Divisions 8 14:

    Marta Matthews

    [email protected]

    919-707-6626

    65

  • Training Agenda

    User Registration

    System Logon

    General Navigation in the System

    Application Process

    View Agreement

    Document submission process

    Change Request Process

    Claim Process

    66

  • 67

  • Submit to: [email protected]

    68

    Your Info

    Your Access

    Agency Approval

  • System Logon

    Local Projects System Portal Access:

    https://partner.ncdot.gov

    Bookmark This Site for Future Reference

    Depending On Your Role Within the LGA, You May See Other Systems Available To You

    69

  • 70

  • Training Agenda

    User Registration

    System Logon

    General Navigation in the System

    Application Process

    View Agreement

    Document submission process

    Change Request Process

    Claim Process

    71

  • System Help Documentation

    Available From Any Screen

    Comprehensive and Easy to Follow

    Details for Each Action in the System

    PDF Format - Available for Easy

    Printing

    72

  • E-mail and Letters

    At Several Stages Throughout the Process, the Project Contacts Will Receive E-mails and Letters:

    The E-mails Will Alert You Of A New Item Waiting In The System: It May Include Comments, an Approval, a Return For More Information; and May or May Not Include An Attached Letter With More Information

    Nothing Will Be Sent By Regular Mail, Except For the Draft Agreement and the Executed Agreement

    73

  • Training Agenda

    User Registration

    System Logon

    General Navigation in the System

    Application Process

    View Agreement

    Document submission process

    Change Request Process

    Claim Process

    74

  • Application Process

    The Application is the LGAs Process to Request an Agreement for a Locally Administered Project

    Important To Know Before Requesting:

    Project Must Be Programmed in the STIP

    LGA Must Know the Estimated Delivery Schedule

    The Funding Source &The Amount of Funding

    75

  • Application Process

    ***IMPORTANT TO KNOW***

    This System is Only For NEW Projects That Do Not Have a Fully Executed Agreement

    Projects With an Existing Executed Agreement Cannot Be Managed in This System

    76

  • Application Process

    From the Home Screen, Select New Application

    Click the Search Button on the Next Screen:

    At This Time There is Only One Program

    System Capability Exists to Add or Refine Programs to Include Other Types of Locally Administered Projects

    We Will Provide Information at That Time

    Click on the LPMO-Application Link to Get Started

    77

  • 78

  • 79

  • 80

  • 81

  • Lets Take a Look at the Application or PID

    82

  • Submit Application

    When Application Form is Complete, Choose Submit to Send to LPMO for Review and Processing

    There is The Option to Save The Application if You

    Dont Have All the Information at That Time

    Once Saved, the Application Will Have an Application ID Assigned, Which You Can Search By, or Search Can Be Done By Tip Number

    All applications must be saved first for MPO review and approval prior to submitting to NCDOT.

    83

  • Returned Application

    Your Application May Be Returned If We Need Additional Information or Clarification

    Log Into the System, Go to Change Application to Make the Change and Re-submit

    We May Reject an Application If a Project Is Not Programmed an the STIP, We Will Request That You Come Back When it is

    84

  • Approved Application

    Once Your Application is Approved, LPMO Will Prepare Your Agreement

    All Contacts on the Application Will Be Notified, by Email, that Agreement Will Come by Mail

    Two Copies of Agreement Will be Mailed to the Person Identified on the Application as the Agreement Contact

    The Process For Drafting, Mailing & Executing an Agreement is Generally 3 4 Months

    85

  • Agreement Execution Process

    LGA Will Sign Agreements and Send Back to LPMO for Execution by NCDOT

    LPMO Will Mail One Fully Executed Agreement to the LGA for Their Records

    An E-mail Will Notify the LGA That the Agreement Has Been Executed Along With the Next Steps

    86

  • Training Agenda

    User Registration

    System Logon

    General Navigation in the System

    Application Process

    View Agreement

    Document submission process

    Change Request Process

    Claim Process

    87

  • View Agreement

    Click View Agreement/Submit Documentation and Then Hit Search

    Most of You Will Only Have One Agreement to View; Larger Cities Might Have Several Projects

    The Agreement Overview Screen Gives You Details of the Project Very Quickly

    88

  • 89

  • 90

  • 91

  • 92

  • Training Agenda

    User Registration

    System Logon

    General Navigation in the System

    Application Process

    View Agreement

    Document Submission Process

    Change Request Process

    Claim Process

    93

  • Submit Documentation

    On Agreement Overview Screen, Click on the Link Submit Documents

    Select Document Type From Dropdown List

    Name the Document and Add Any Notes

    Change the Status to Submit

    Click On Back and Save at the Top of the Agreement Overview Screen

    94

  • 95

  • 96

  • Attach Documentation

    97

  • 98

  • Training Agenda

    User Registration

    System Logon

    General Navigation in the System

    Application Process

    View Agreement

    Document Submission Process

    Change Request Process

    Claim Process

    99

  • Submit Change Request

    Change Requests are Used to Ask For:

    Additional Funding on a Phase (Within the Limits of the Executed Agreement)

    To Move to the Next Phase, for Example, From ROW to Construction

    Request a Supplemental Agreement (The MPO/ Department Has Allocated Additional Funds; Change in Project Scope; Change in Responsibilities)

    100

  • Submit Change Request

    Go To System Home Page

    Select Submit Change Request

    Search and Select Your Project

    Open Change Request Form

    IMPORTANT:

    If Requesting A New Phase Of Funding, Then LGA Must Enter Estimated Let Date In Comments.

    101

  • 102

  • 103

  • 104

  • 105

  • 106

  • Training Agenda

    User Registration

    System Logon

    General Navigation in the System

    Application Process

    View Agreement

    Document Submission Process

    Change Request Process

    Claim Process

    107

  • Submit Reimbursement Request (Claim)

    Claims (Reimbursement Requests) Will be Submitted Through the Local Project Management System

    Select New Reimbursement Claim

    Search and Select Your Project

    Open the Reimbursement Claim Form

    The LGA Cannot Request More Reimbursement Than Has Been Authorized and is Available on Each WBS Element

    If Funding Needs to Be Moved, Then You Must Submit a Change Request

    108

  • 109

  • 110

  • 111

  • 112

  • 113

  • New Website

    https://connect.ncdot.gov/municipalities/Funding/

    https://connect.ncdot.gov/municipalities/Funding/

  • PE FUNDING

    AUTHORIZATION

    Occurs after the Agreement is fully executed

    PE Authorization is based on estimate provided by LGA

    LGA will request PE funding in the new Project Management Tool

    LGA will be notified in the Project Management Tool once PE funds have been authorized

    Any work occurring before authorization will not

    be eligible for reimbursement.

  • Professional Services

    All professional services must be pre-qualified by

    NCDOT for the requested work codes.

    Eligible Activities:

    Preliminary Engineering (conceptual plans, env.

    planning, design, surveys)

    Right of Way (preparation of plats, appraisals, review

    of appraisals)

    Construction (construction administration, engineering

    & inspections)

  • Procurement

    Requirements for any Professional Services

    must be publicly announced.

    Services must be selected on the basis of

    qualifications.

    LGA is responsible for this phase, with

    NCDOT providing review and concurrence

    of tasks, man-hours and rates.

  • Process

    Develop an RFQ using template provided by

    NCDOT and submit for review through the new

    system.

    Develop an estimate of costs*

    Advertise or otherwise solicit for professional

    services

    This should not occur until after PE Funding

    Authorization is received.

    Review and select most qualified consultant.

    Optional Scoping Meeting based on scope and scale

    of project.

  • Process contd

    Request a cost proposal from selected consultant

    Tasks, personnel, man-hours, rates, and overhead

    Submit letter in the Project Management Tool with overview of selection process (use template) and include proposal from consultant.

    Allow one month for review and comments or concurrence by NCDOT.

    Same process should be followed for construction administration/engineering & inspection

  • IMPORTANT

    NCDOT policy prohibits same consultant

    for design and CEI.

    Request for exception to policy must be

    made in writing to LPMO.

    Reviewed and approved/denied by the

    Construction Unit.

    If approved, cannot automatically extend

    PE contract to cover CEI must undergo

    new solicitation.

  • LPM Organization

    Sheila Gibbs

    Program Consultant

    Divisions 1 7:

    919-707-6625

    [email protected]

    mailto:[email protected]

  • Project Development and Environmental Analysis Unit

    (PDEA)

    NEPA Compliance

  • Minor Projects

    1. Programmatic Categorical Exclusion (PCE)

    2. Other Laws and Regulations

  • Programmatic Categorical Exclusion

    Most Locally Administered Projects are categorically excluded from NEPA

    Document that the project is an approved CE action

    Perform a level of environmental investigation to verify there is no potential for significant project impacts

  • Other Laws and Regulations

    Section 4(f) Transportation Act

    Public Areas and Historic Resources

    Section 106 Historic Act

    Historic Resources

    SHPO Concurrence

    Section 7 Endangered Species Act

    Federally Protected Species

  • NCDOT PROGRAMMATIC CATEGORICAL EXCLUSION ACTION CLASSFICIATION

    FORM

  • TYPE I CATEGORICAL EXCLUSION ACTIVITIES

    Construction of bicycle and pedestrian lanes, paths, and facilities.

    Landscaping

    Installation of fencing, signs, pavement markings, small passenger shelters, traffic signals, and railroad warning devices.

    Emergency repairs under 23 USC 125 (Governor Declared Emergency)

    Replacement of Guardrail

  • TYPE II ACTIVITIES

  • PCE FORM CONTINUED

  • PCE FORM CONTINUED

    ECOLOGICAL

    1.Will the project have a substantial impact on any unique or important natural resource?

    2.Does the project involve habitat where federally listed endangered or threatened species may occur?

    3.Does the project involve waters classified as Outstanding Water Resources (OWR) and/or High Quality Waters (HQW)?

    4.Does the project involve any known underground storage tanks (USTs) or hazardous materials sites?

  • PCE FORM CONTINUED

    Permits and Coordination

    1. If the project involves the acquisition of right of way, is the amount of right of way acquisition considered minor?

    2. Will the project have an effect on structures/properties eligible for listed on the National Register of Historic Places?

  • PCE FORM CONTINUED

  • PCE FORM CONTINUED

  • PCE FORM CONTINUED

  • Major Projects

    Environmental Assessments/Finding of No Significant Impact

    Environmental Impact Statements

    Merger Process

    Scoping Meetings

    Public Outreach

  • COMMON ISSUES

    Natural Resources Technical Report- qualified person

    Right of Way Permanent and Temporary

    Early Scoping USFWS, SHPO

    Preliminary Plans

    Geotechnical Review

    Public Involvement

    Signatures

    Detailed Descriptions

    Location Map, aerial photo

    Review Time

  • Early scoping: US Fish & Wildlife Service

    Gary Jordan [email protected]

    NC State Historic Preservation Office

    Renee Gledhill-Earley [email protected]

  • PDEA

    Rob Hanson, PE

    Eastern Section Head

    Divisions 16,8:

    919-707-6024

    [email protected]

    mailto:[email protected]

  • Engineering Major Projects: Raleigh Office-Roadway

    Design Unit

    Minor Projects: Division Office

    Chris Haire, PE, CPM

    Mohammed Mahjoub, EI

    Mike Kneis, PE

  • Project Design

    Whats minor? Simple design, no complicating issues.

    Whats major? Closed Drainage systems, culverts, other structures things a design unit in Raleigh must review.

    All projects to use the NCDOT 2012 Standard Specifications and Standard Drawings.

    Project Plan Consistency - Title Sheet of project plans to have WBS Element numbers and STIP number. All other plan sheets to have STIP number.

  • Project Review Time

    MINOR

    Email or Paper Submittal

    Short Review Time usually within 2 weeks

    But..there are dozens of projects (not just LAPP projects), and typically 1 reviewer!

    MAJOR

    Paper copies and electronic plans, pdfs and Microstation files sent to Roadway Design

    Several weeks due to multiple reviewing units and internal coordination

    Is it a complete set of plans and specifications?

    Check with the Division Office or Roadway Design on

    the submission of electronic and hard copy plans. Email

    is the easiest way to transmit electronic plans.

    September is the big due month, so everything takes

    longer due to shear volume.

  • Major Projects

    Scoping Meeting Recommended with NCDOT, Municipality & Consultant prior to execution of Consultant Contract

    Corridor Modeling 25%, 75% (R/W), 90% & 100% Plan Reviews U & R type designated STIP projects to be submitted to NCDOT Plan

    Checking at 100% final review Final Contract Documents to be reviewed by NCDOT Proposals & Contracts Project Plan Submittals Roadway; Geotechnical; Structures Retaining

    Walls, Bridges, Culverts; Pavement Design; Hydraulics; Utilities; TMPs; Signing & Delineation; Signals; with Design, Safety, Maintenance and Future Expandability in mind.

    Municipal Project Design & Review Criteria NCDOT - Roadway Design Consultant Coordination Guidelines https://connect.ncdot.gov/projects/Roadway/RoadwayDesignAdministrativeDocuments/ Roadway%20Design%20Consultant%20Coordination%20Guidelines.pdf

    NCDOT Municipal/Developer Guidelines Submittals for Plan Reviews https://connect.ncdot.gov/projects/Roadway/RoadwayDesignAdministrativeDocuments/Municipal- Developer%20Submittals%20Guideline.pdf

    Planning Document (PCE, CE, EA, etc.) progresses concurrently with design plans. Some projects go through the Merger Process.

  • Major Projects

    NCDOT Point of Contact Division Office or Roadway Design

    FHWA delegates authority to NCDOT to review and approve project designs on and off its maintained system

    Who will maintain? NCDOT or Municipality

    Project to be built with long term maintenance and expandability in mind Project not to require immediate repairs or action by NCDOT or Municipality

    Potential Project Problems Betterments, Design Issues, Sufficient R/W for Construction, Project proceeding to next level without prior approvals from the Department, Project starts out as a LAPP Project then becomes an Encroachment Project

    Communication & Collaboration A successful project is the result of the Municipality, Consultant , NCDOT & FHWA working together as a Team

  • Contract Proposal

    Contract Proposal Use Line-Up Sheet see LPMO Handbook for more

    information

    Check effective dates for Specs when updating proposals.

    Do NOT use AIA, EJCDC or SCO Specs often causes conflict.

    Division or Contract Standards will approve

    Need Line Item Estimate at this point for goal setting

  • Specialty or Proprietary Items

    Avoid if at all possible.

    If using name brand items, must list 3 brands and also or equivalent.

    Specialty Items MUST be approved well in advance of letting. i.e. trash cans on a streetscape project where matching existing trashcans on previous projects is desired. Approval could take several weeks!

  • Contract Proposal

    New Website for Local Governments

    https://connect.ncdot.gov/municipalities/Pages/Bid-Proposals-for-LGA.aspx

    S te p b y s te p p r o c e s s f o r d ev e l o p i n g b i d p r o p o s a l s

    C h e c k l i s t s

    FAQs

    L i n k s to o t h e r r e s o u r c e s

    F i r s t t i m e u s e r s g u i d e

    http://www.ncdot.org/doh/preconstruct/ps/specifications/specifications_provisions.htmlhttp://www.ncdot.org/doh/preconstruct/ps/specifications/specifications_provisions.htmlhttp://www.ncdot.org/doh/preconstruct/ps/specifications/specifications_provisions.htmlhttp://www.ncdot.org/doh/preconstruct/ps/specifications/specifications_provisions.htmlhttp://www.ncdot.org/doh/preconstruct/ps/specifications/specifications_provisions.htmlhttp://www.ncdot.org/doh/preconstruct/ps/specifications/specifications_provisions.htmlhttp://www.ncdot.org/doh/preconstruct/ps/specifications/specifications_provisions.htmlhttp://www.ncdot.org/doh/preconstruct/ps/specifications/specifications_provisions.htmlhttp://www.ncdot.org/doh/preconstruct/ps/specifications/specifications_provisions.htmlhttp://www.ncdot.org/doh/preconstruct/ps/specifications/specifications_provisions.html

  • COMMON ISSUES

    Issues weve seen: Issuing an RFQ for Design before PE Authorization

    ADA or EJCDC front end documents instead of NCDOT

    Specs causes conflicts!

    No PE funds requested if Reimbursable phases are only

    R/W and/or Const. DOT still needs to review and

    approve PS&E this costs money.

  • Project Engineers

    Major Projects:

    Chris Haire

    Mohammad Mahjoub

    Minor Projects:

    Division 4 Jerry Page, PE

    Division 5 Mike Kneis, PE

    Division 6 Jerry Bradley, PE

  • Right of Way

    Division Office:

    Authorization & Certification

    Raleigh Office:

    Appraisal Review

  • Right of Way Acquisition

    GETTING STARTED

    MUNICIPAL AGREEMENT o MUST BE SIGNED

    o READ RIGHT OF WAY SECTIONS FOR ADHERENCE

    o MUST BE SUBMITTED WITH VALUATIONS/APPRAISALS

    CONSTRUCTION PLANS o IDENTIFY THE EXISTING RIGHT OF WAY LIMITS

    o PREFER A PARCEL NUMBER, OWNERS NAME, DEED REFERENCE, AND PIN

    o MUST BE APPROVED AND SUBMITTED WITH VALUATIONS/APPRAISALS

  • Right of Way Acquisition

    APPRAISALS/VALUATIONS o ALL APPRAISALS AND VALUATIONS MUST BE APPROVED BY

    NCDOT PRIOR TO OFFERS

    o WAIVER VALUATIONS CAN BE USED FOR VALUES $10,000.00 OR LESS

    o OWNERS HAVE A RIGHT TO REQUEST AN APPRAISAL REGARDLESS OF VALUE

    o VALUES IN EXCESS OF $10,000 MUST BE APPRAISED BY NCDOT RECOMMENDED REVIEW APPRAISERS AND REVIEWED BY NCDOT AREA 2 APPRAISAL DEPARTMENT

    o OWNERS MUST KNOW THEY HAVE A RIGHT TO ACCOMPANY THE APPRAISER

    o RECOMMEND DEPOSITING APPRAISALS FOR JUST COMPENSATION NOT CLAIM REPORTS IN CONDEMNATION CASES.

  • Right of Way Acquisition

    NEXT STEPS FOLLOW THE UNIFORM ACT OF 1970

    o REQUIRED ADHERENCE IF ONE DOLLAR OF FEDERAL FUNDS IS INVOLVED IN THE PROJECT

    MAKE OFFERS

    o ALL OFFERS MUST BE MADE IN WRITING

    WAIVER FORMS

    o MUST BE SIGNED BY PROPERTY OWNERS FOR ALL DONATIONS

    o MUST ALWAYS BE SIGNED BY THE LPA

    CLEAR TITLE

    o IT IS THE REPONSIBILITY OF THE LPA TO SECURE CLEAR TITLE OF THE LANDS ACQUIRED FOR CONSTRUCTION AND THAT MAY BE CONVEYED TO THE NCDOT

    CONDEMNATIONS

    o PROPERTY OWNER RIGHTS MUST BE APPLIED

  • 1. Copy of the signed municipal agreement 2. Submit all waiver valuations for just compensation approval prior to offer

    a. ALL NON-APPRAISED VALUES OF $10,000.00 OR BELOW (WAIVER EVALUATIONS) MUST BE APPROVED

    BY THE DIVISION RIGHT OF WAY OFFICE i. Include the explanation of the determined values ii. Comparable information if used

    3. Copy of Certified Appraisals for values that exceed $10,000.00 a. ALL APPRAISALS MUST BE REVIEWED BY AN NCDOT RECOMMEND REVIEWER AND THEN

    APPROVED BY THE AREA RIGHT OF WAY APPRAISAL OFFICE 4. Letter requesting certification (Use the municipal agreement as a guide)

    a. Explanation of utility relocation b. Explanation of displaced person(s) and/or improvement relocation c. Explanation of purchases prior to funding d. Explanation if all work is being performed in existing right of way

    5. Signed waiver forms from LPA 6. You may elect to have the owner sign the waiver form except during donations 7. Copy of approved plans

    a. Plans should show existing right of way b. Parcel numbers, ownership name, deed, and PIN preferred on plans

    8. Copy of recorded agreements (Clear title is the responsibility of the LPA) 9. Copy of recorded plats 10. Copy of offer letter provided to property owner 11. Copy of Memorandum of Action with the deposited amount 12. The Uniform Relocation Act must be followed.

    Checklist-Right of Way Acquisition

    Brad Lopp,

    Area Appraiser, NCDOT

    Right of Way Unit

    3509 Haworth Street, Suite 400

    Raleigh, NC 27609

    (919) 571-4191 or [email protected]

    K. M. Smith,

    Division Right of Way Agent, NCDOT

    Division of Highways (Div. 5)

    815 Stadium Drive

    Durham, NC 27704

    (919) 220-4700 Or [email protected]

  • Right of Way Certification

    CERTIFICATION REQUEST SUBMISSION PACKAGES

    CHECKLIST IS AVAILABLE ON THE CAMPO WEBSITE

    PROJECT SUBMISSION MAY TAKE 2-8 WEEKS TO BE REVIEWED

  • Right of Way

    Certification

    All acquisition must be in conformance with the

    Uniform Act, whether ROW Acquisition is being

    reimbursed with Federal funds or not.

    Certification is done by the Division ROW Agent:

    Div 4 Lloyd Johnston

    Div 5 K. M. Smith

    Div 6 Raphael A. Marshall

    Certification ensures that LPA has control of all

    ROW needed for project.

  • Construction

  • Construction

    Advertising and Letting a Construction Contract can only occur after Construction funds are authorized.

    Construction Administration is accomplished by the LGA in accordance with the NCDOT Construction Manual.

    NCDOT will provide oversight through the Division Office or a Resident Engineers Office.

    NCDOT must accept the final project before final reimbursement can be made.

  • Construction Authorization

    Items Needed:

    R/W Certification

    Approved NEPA document

    Approved Plans and Proposal

    Approved Line Item Estimate

    Next Step by NCDOT:

    LADA memo and Request Memo internally at NCDOT, Request to FHWA

  • Concurrence in Award

    Items Needed:

    Bid tabs

    All forms filled out by bidders

    Letters of Intent from listed DBE subs

    Resolution from Council OR proof of delegation to Manager, etc.

    Letter from Town requesting Concurrence

  • Construction

    Issues weve seen: Advertising before Construction Authorization

    Waiting too long between Authorization and

    Advertising

    Issuing NTP before NCDOT Concurrence in Award

    Inspection and Testing costs over 15% of Construction

    cost

    Releasing Contractor before NCDOT acceptance of

    Project

  • Construction Inspection/Oversight

    Your Responsibilities: Daily Inspection/Observation Testing by NCDOT Certified Inspectors at frequency required by

    DOT Specs. Get Change Orders approved by NCDOT PRIOR to the contractor

    doing the work, even if its only for time. Must be on NCDOT Form 880LG

    Oversight NCDOT Responsibilities: Answer your questions Review Change Orders and Claims. Audit

  • Invoices to NCDOT

    Reimbursement Request (up to 80% of elig. expenses) (See LPM Handbook for complete procedure) 1. Cover letter to NCDOT: Basic project information Amounts paid by project work phase Bills paid by LGA (summary of invoices) Phase-specific items (e.g., material testing QA & QC rpt) 2. Actual invoices from consultants 3. Subcontractor payment report 4. Evidence of LGAs payments to consultants and contractors

  • Contractor bills the Local

    Agency

    Local Agency pays the contractor

    Local Agency submits reimbursement request to

    NCDOT

    State pays Local Agency

    Contractor does work

    State Submits voucher to FHWA

    FHWA sends to Treasury

    Treasury sends check to

    State

    LAPP Reimbursement Request Process

  • Reimbursement

    Can occur throughout the project as costs are incurred, but must occur at least once every 6 months

    LGA pays full invoice from designer, contractor, CEI firm, etc. ; NCDOT reimburses agreed upon % of eligible costs up to amount in agreement.

  • Reimbursement

    Final Reimbursement will not occur until project is complete, accepted by NCDOT, and all reporting and other requirements have been accomplished.

    DOT will bill LGA fo r the local match on all DOT charges to the project or any expenditures over the agreement amount, at the end of the project.

  • Reimbursement

    Issues weve seen: Invoices without all supporting documents

    Not Invoicing NCDOT every 6 months

    Sales Tax not deducted before Reimbursement

    Request (Dept of Revenue, not NCDOT, reimburses

    your sales tax)

  • DIVISION 5

    Mike Kneis, PE

    Project Manager

    919-220-4600

    [email protected]

    mailto:[email protected]

  • LAPP Project Delivery Requirements

  • LAPP Project Delivery Requirements

    Reporting and Communications

    Scope, Funding and Schedule Changes

    CAMPO LAPP Deadlines

    Holistic approach to identify & prioritize highly effective projects

    Efficient use of available funds

    Avoid future Federal rescissions to the maximum extent possible

    Annual modal investment mix

    Project tracking system

    Training program

  • Project Reporting Requirements

    In addition to the requirements associated with receiving federal funding, the MPO will also require regular reporting on projects funded through the LAPP.

    Applicants are required to provide monthly updates to the MPO outlining where the project is in the timeline toward funding obligation of all phases awarded for the project. This includes NEPA, plan and right-of-way submittals.

    More frequent communications are required if project location, schedule or funding changes are likely to occur.

    Applicant are also required to include CAMPO on key date communications toward implementation of the project, such as bidding, ground breaking and opening ceremonies.

    References to funding in communications should include: Federal funds were provided for this project by the Capital Area Metropolitan Planning Organization through the Federal Highway Administration.

  • Scope, Funding and Schedule Changes

    All LAPP Awarded projects are funded with CAMPO STPDA and TAPDA Appropriations and NC CMAQ Allocations. Funds are programmed (not yet guaranteed).

    CAMPO over-programs because some projects get delayed or cancelled.

    Obligation Ceiling is the net available funding. Funds obligated by FHWA are committed to the

    project. FFY (Oct 1-Sept 30): Funding Balance.

    CFFY Carry Forward Current Year

    Appropriations

    Total Appropriations Net Available Funding Obligation or

    Committed Amount

    Funding Balance

    Fund $ $ $ $ $ $

    1500/2713M301R Transp Alt. Prog >200K Raleigh 1,661,763.00 1,661,763.00 1,495,586.70 1,495,586.70

    1500/2713M3E1R Transp Alt. Prog >200K Raleigh - Ext. 670,899.00 670,899.00 603,809.10 603,809.10

    1500/2731L230R STP >200K POPULATION-RALEIGH 37,071.59 37,071.59 33,364.43 36,485.00 -3,120.57

    1500/2731L23ER STP >200K POP-RALEIGH-SAFETEA-LU EXT 356,621.00 356,621.00 320,958.90 -194,507.00 515,465.90

    1500/2731L23RR STP >200K POPULATION-RALEIGH-RE 449,401.41 449,401.41 404,461.27 449,401.00 -44,939.73

    1500/2731M230R Urban Over 200K Population-Raleigh 9,127,968.00 -1,004,000.00 8,123,968.00 7,311,571.20 1,329,572.00 5,981,999.20

    1500/2731M23ER Urban Over 200K Population-Raleigh Ext. 8,224,102.00 8,224,102.00 7,401,691.80 649,600.00 6,752,091.80

    11,632,825.00 7,891,001.00 19,523,826.00 17,571,443.40 2,270,551.00 15,300,892.40Result

  • Scope, Funding and Schedule Changes U-5501 SR 1650 (REEDY CREEK ROAD), NC 54 (NE MAYNARD ROAD) TO SR 16 45488.1.1 U-5501 - PE - CARY Prel Engr 11/03/2011 REL ACPT # WAKE 1500/2731L23ER STP >200K POP-RALEIGH-SAFETEA-LU EXT 160,000.00 152,783.57 160,000.00 152,783.57 U-5501 SR 1650 (REEDY CREEK ROAD), NC 54 (NE MAYNARD ROAD) TO SR 16 45488.1.1 U-5501 - PE - CARY Prel Engr 11/03/2011 REL ACPT # WAKE 1500/2731M230R Urban Over 200K Population-Raleigh 200,000.00 112,039.02 200,000.00 112,039.02

    U-5501 SR 1650 (REEDY CREEK ROAD), NC 54 (NE MAYNARD

    ROAD) TO SR 16 Result 360,000.00 264,822.59 360,000.00 264,822.59

    U-5503 MORRISVILLE - SR 3014 (MORRISVILLE-CARPENTER

    ROAD) FROM WEST 45490.1.1 CLOSED U-5503 - PE - MORRISVILLE Prel Engr 12/20/2011 REL ACPT # WAKE 1500/# 1500/Not assigned 0.00 23,654.62

    U-5503 MORRISVILLE - SR 3014 (MORRISVILLE-CARPENTER

    ROAD) FROM WEST 45490.1.1 CLOSED U-5503 - PE - MORRISVILLE Prel Engr 12/20/2011 REL ACPT # WAKE 1500/2731L23ER STP >200K POP-RALEIGH-SAFETEA-LU EXT 45,500.00 45,500.00 45,500.00 45,500.00

    U-5503 MORRISVILLE - SR 3014 (MORRISVILLE-CARPENTER

    ROAD) FROM WEST 45490.1.1 CLOSED U-5503 - PE - MORRISVILLE Prel Engr 12/20/2011 REL ACPT # WAKE 1500/2731M230R Urban Over 200K Population-Raleigh 147,000.00 147,000.00 147,000.00 147,000.00

    U-5503 MORRISVILLE - SR 3014 (MORRISVILLE-CARPENTER

    ROAD) FROM WEST 45490.3.F1 U-5503 - CON - MORRISVILLE Construction 01/08/2014 REL ACPT # WAKE 1500/# 1500/Not assigned 0.00 102,009.70

    U-5503 MORRISVILLE - SR 3014 (MORRISVILLE-CARPENTER

    ROAD) FROM WEST 45490.3.F1 U-5503 - CON - MORRISVILLE Construction 01/08/2014 REL ACPT # WAKE 1500/2731M230R Urban Over 200K Population-Raleigh 665,000.00 665,000.00 665,000.00 665,000.00

    U-5503 MORRISVILLE - SR 3014 (MORRISVILLE-CARPENTER

    ROAD) FROM WEST Result 857,500.00 983,164.32 857,500.00 857,500.00

    U-5504 RALEIGH - SR 1009 (LAKE WHEELER ROAD) FROM SR

    1009-1370 (TRY 45491.3.1 CLOSED U-5504 - CON - RALEIGH Construction 12/04/2012 CLSD ACPT 05/13/2015 WAKE 1500/2702999 Local Government Match_Statewide 4,470.13 4,470.13

    U-5504 RALEIGH - SR 1009 (LAKE WHEELER ROAD) FROM SR

    1009-1370 (TRY 45491.3.1 CLOSED U-5504 - CON - RALEIGH Construction 12/04/2012 CLSD ACPT 05/13/2015 WAKE 1500/2731L23ER STP >200K POP-RALEIGH-SAFETEA-LU EXT 679,290.00 679,290.00 679,290.00 679,290.00

    U-5504 RALEIGH - SR 1009 (LAKE WHEELER ROAD) FROM SR

    1009-1370 (TRY 45491.3.1 CLOSED U-5504 - CON - RALEIGH Construction 12/04/2012 CLSD ACPT 05/13/2015 WAKE 1500/7101999 FHWA Construction State Match HTF 483.50 483.50

    U-5504 RALEIGH - SR 1009 (LAKE WHEELER ROAD) FROM SR

    1009-1370 (TRY Result 684,243.63 684,243.63 679,290.00 679,290.00

    U-5514 CAPITAL BOULEVARD FROM SR 2041 (SPRING FOREST

    ROAD) TO SR 35 55055.1.1 U-5514 - PE - RALEIGH Prel Engr 12/13/2012 REL ACPT # WAKE 1500/2731M230R Urban Over 200K Population-Raleigh 448,000.00 91,094.44 448,000.00 91,094.44

    U-5514 CAPITAL BOULEVARD FROM SR 2041 (SPRING FOREST

    ROAD) TO SR 35 55055.3.1 U-5514 - CON - RALEIGH Construction 09/23/2015 REL # WAKE 1500/2731M23ER Urban Over 200K Population-Raleigh Ext. 413,000.00 123.06 413,000.00 123.06

    U-5514 CAPITAL BOULEVARD FROM SR 2041 (SPRING FOREST

    ROAD) TO SR 35 Result 861,000.00 91,217.50 861,000.00 91,217.50

    U-5515 WAKE FOREST - SR 1930 (STADIUM DRIVE), 1933 (WEST

    NORTH AVEN 55056.1.1 U-5515 - PE - WAKE FOREST Prel Engr 04/11/2013 REL ACPT # WAKE 1500/# 1500/Not assigned 0.00 35,060.18

    U-5515 WAKE FOREST - SR 1930 (STADIUM DRIVE), 1933 (WEST

    NORTH AVEN 55056.1.1 U-5515 - PE - WAKE FOREST Prel Engr 04/11/2013 REL ACPT # WAKE 1500/2731M230R Urban Over 200K Population-Raleigh 235,400.00 235,400.00 235,400.00 235,400.00

    U-5515 WAKE FOREST - SR 1930 (STADIUM DRIVE), 1933 (WEST

    NORTH AVEN 55056.2.F1 U-5515 - R/W - SR 1930 WAKE FOREST Right of Way 11/10/2015 REL # WAKE 1500/2731M23ER Urban Over 200K Population-Raleigh Ext. 479,000.00 0.00 479,000.00 0.00

    U-5515 WAKE FOREST - SR 1930 (STADIUM DRIVE), 1933 (WEST

    NORTH AVEN Result 714,400.00 270,460.18 714,400.00 235,400.00

    U-5520 GARNER - CONSTRUCT IMPROVEMENTS ON I-40 / US 70

    EASTBOUND RA 44091.3.F1 U-5520 - CON - I-40/US 70 INTERCHANGE Construction 09/16/2013 REL ACPT # WAKE 1500/2731M230R Urban Over 200K Population-Raleigh 2,600,000.00 2,444,091.45 2,600,000.00 2,444,091.45

    U-5520 GARNER - CONSTRUCT IMPROVEMENTS ON I-40 / US 70

    EASTBOUND RA Result 2,600,000.00 2,444,091.45 2,600,000.00 2,444,091.45

    U-5529 SR 1115 (AVENT FERRY ROAD), WEST OF SR 1101

    (PINEY GROVE - 44107.1.F1 U-5529 - PE - SR 1115 (AVENT FERRY ROAD) Prel Engr 11/25/2013 REL ACPT # WAKE 1500/2731M230R Urban Over 200K Population-Raleigh 144,000.00 105,879.39 144,000.00 105,879.39

    U-5529 SR 1115 (AVENT FERRY ROAD), WEST OF SR 1101

    (PINEY GROVE - Result 144,000.00 105,879.39 144,000.00 105,879.39

    U-5530AA APEX - OLD RALEIGH ROAD FROM LAKE PINE DRIVE TO

    CARY LIMITS 44111.1.F7 U-5530AA - PE - APEX Prel Engr 01/14/2014 REL ACPT # WAKE 1500/2731M230R Urban Over 200K Population-Raleigh 14,000.00 26.63 14,000.00 26.63

    U-5530AA APEX - OLD RALEIGH ROAD FROM LAKE PINE DRIVE TO

    CARY LIMITS 44111.3.F7 U-5530AA - CON - APEX Construction 10/15/2014 REL ACPT # WAKE 1500/2702999 Local Government Match_Statewide 810.96 810.96

    U-5530AA APEX - OLD RALEIGH ROAD FROM LAKE PINE DRIVE TO

    CARY LIMITS 44111.3.F7 U-5530AA - CON - APEX Construction 10/15/2014 REL ACPT # WAKE 1500/2731M230R Urban Over 200K Population-Raleigh 140,000.00 104,957.76 140,000.00 104,957.76

    U-5530AA APEX - OLD RALEIGH ROAD FROM LAKE PINE DRIVE TO

    CARY LIMITS Result 154,810.96 105,795.35 154,000.00 104,984.39

    U-5530AB APEX - ALONG THE WEST SIDE OF TINGEN ROAD

    FROM THE APEX ELEM 44111.1.F3 U-5530AB - PE - APEX Prel Engr 01/14/2014 REL ACPT # WAKE 1500/2702999 Local Government Match_Statewide 336.22 336.22

    U-5530AB APEX - ALONG THE WEST SIDE OF TINGEN ROAD

    FROM THE APEX ELEM 44111.1.F3 U-5530AB - PE - APEX Prel Engr 01/14/2014 REL ACPT # WAKE 1500/2731M230R Urban Over 200K Population-Raleigh 336.00 336.00 336.00 336.00

    U-5530AB APEX - ALONG THE WEST SIDE OF TINGEN ROAD

    FROM THE APEX ELEM 44111.1.F3 U-5530AB - PE - APEX Prel Engr 01/14/2014 REL ACPT # WAKE 1500/7101999 FHWA Construction State Match HTF 0.21 0.21

    U-5530AB APEX - ALONG THE WEST SIDE OF TINGEN ROAD

    FROM THE APEX ELEM 44111.2.F3 U-5530AB - R/W - APEX Right of Way 04/29/2014 REL ACPT # WAKE 1500/2702999 Local Government Match_Statewide 105.37 105.37

    U-5530AB APEX - ALONG THE WEST SIDE OF TINGEN ROAD

    FROM THE APEX ELEM 44111.2.F3 U-5530AB - R/W - APEX Right of Way 04/29/2014 REL ACPT # WAKE 1500/2731L23ER STP >200K POP-RALEIGH-SAFETEA-LU EXT 7,473.00 7,473.00 7,473.00 7,473.00

    U-5530AB APEX - ALONG THE WEST SIDE OF TINGEN ROAD

    FROM THE APEX ELEM 44111.2.F3 U-5530AB - R/W - APEX Right of Way 04/29/2014 REL ACPT # WAKE 1500/7101997 FHWA State Match FY15 Transfer 0.37 0.37

    U-5530AB APEX - ALONG THE WEST SIDE OF TINGEN ROAD

    FROM THE APEX ELEM 44111.3.F3 U-5530AB - CON - APEX Construction 08/07/2014 REL ACPT # WAKE 1500/2702999 Local Government Match_Statewide 1,803.28 1,803.28

    U-5530AB APEX - ALONG THE WEST SIDE OF TINGEN ROAD

    FROM THE APEX ELEM 44111.3.F3 U-5530AB - CON - APEX Construction 08/07/2014 REL ACPT # WAKE 1500/2731L23ER STP >200K POP-RALEIGH-SAFETEA-LU EXT 4,527.00 1,469.00 4,527.00 1,469.00

    U-5530AB APEX - ALONG THE WEST SIDE OF TINGEN ROAD

    FROM THE APEX ELEM 44111.3.F3 U-5530AB - CON - APEX Construction 08/07/2014 REL ACPT # WAKE 1500/2731M230R Urban Over 200K Population-Raleigh 77,664.00 77,664.00 77,664.00 77,664.00

    U-5530AB APEX - ALONG THE WEST SIDE OF TINGEN ROAD

    FROM THE APEX ELEM 44111.3.F3 U-5530AB - CON - APEX Construction 08/07/2014 REL ACPT # WAKE 1500/7101999 FHWA Construction State Match HTF 0.78 0.78

    U-5530AB APEX - ALONG THE WEST SIDE OF TINGEN ROAD

    FROM THE APEX ELEM Result 92,246.23 89,188.23 90,000.00 86,942.00

    U-5530GA FUQUAY-VARINA - PARK-DEPOT GREENWAY TRAIL IN

    THE TOWN'S OLD 44111.1.F8 U-5530GA - PE - FUQUAY-VARINA Prel Engr 03/11/2014 REL ACPT # WAKE 1500/2713M301R Transp Alt. Prog >200K Raleigh 85,000.00 73,670.89 85,000.00 73,670.89

    U-5530GA FUQUAY-VARINA - PARK-DEPOT GREENWAY TRAIL IN

    THE TOWN'S OLD Result 85,000.00 73,670.89 85,000.00 73,670.89

    U-5530GB FUQUAY-VARINA - BRIDGE STREET PEDESTRIAN

    IMPROVEMENTS; CONST 44111.1.11 U-5530GB - PE - FUQUAY-VARINA Prel Engr 12/03/2015 REL ACPT # WAKE 1500/2731M230R Urban Over 200K Population-Raleigh 84,000.00 58.21 84,000.00 58.21

    U-5530GB FUQUAY-VARINA - BRIDGE STREET PEDESTRIAN

    IMPROVEMENTS; CONST Result 84,000.00 58.21 84,000.00 58.21

  • January May 2016 Public Involvement TIP & STIP Amendment Process CMAQ Applications Executive Board adopts project list Training for LAPP selected project managers

    February September 2016

    Municipal Agreements signed by local gov. Municipal Agreements signed by NCDOT FTA Request for Draft Grant # for Transit Flex Projects SEPTEMBER 15, 2016: ALL AGREEMENTS MUST BE SIGNED OR FUNDS MAY BE

    PROGRAMMED TO ANOTHER SHOVEL READY PROJECT THIS IS A CRITICAL DEADLINE

    October 1, 2016 September 30, 2017

    FFY 17 LAPP Funds Obligated SEPTEMBER 15, 2017: FINAL CHANCE FOR FFY2017 TRANSIT FUNDS TO BE FLEXED

    TO FTA AND FFY2017 ROADWAY AND BIKE/PED PROJECT TO RECEIVE AUTHORIZATION THIS REQUIRES FINAL SUBMITTALS TO NCDOT IN JUNE THROUGH JULY, 2017

    LAPP - FFY 17 Deadlines

  • June 2017

    Target deadline for obligation of all LAPP funds

    Consideration given to reprogramming funds that are not anticipated to be obligated before October

    October 2017

    All unobligated funds for LAPP projects eligible for de-programming

    NOTE: Upon obligation of funds for any particular project phase, the applicant has the obligation year plus two more years to complete the project and expend the funds authorized for that project phase.

    NOTE: Since funds are anticipated to be over-programmed (i.e., more funds will be programmed for projects than may be actually available for projects) annually, applicants are encouraged to achieve obligation as quickly as possible for each phase requested through LAPP.

    LAPP - FFY 17 Deadlines

  • Typical Project Delivery Steps

    Agreement

    -------------Preliminary Engineering Authorization------------- Procuring Professional Services

    Environmental Document (required)

    Location and Design Approval (required)

    -------------Right of Way Authorization------------- Right of Way Acquisition

    Utility Relocation

    Right of Way Certification (required)

    Contract Proposal and Estimate (PS&E) (required)

    -------------Construction Authorization------------- Advertise and Let Construction Contract

    Construction & Administration

    Final Inspection (required) Final Reimbursement

  • LADA: Location and Design Approval

    Must have this signed from NCDOT to request ROW Authorization (to start ROW)

    NEPA Environmental Documentation

    PCE, EA, FONSI, EIS

    Must have this signed by FHWA to request ROW Authorization (to start ROW) or CON Authorization.

    ROW Certification

    Must have this signed from NCDOT to request CON Authorization (to start CON)

    PSE: Plans, Specifications and Estimates

    Must submit these in final revised format to NCDOT to request CON Authorization (to start CON)

    LAPP Key Approvals Terminology

  • LAPP Project Roundtable Q&A

  • Contacts:

    CAMPO

    919-996-4000

    [email protected] [email protected] [email protected]

    http://www.campo-nc.us/lapp.html

    Questions?

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]://www.campo-nc.us/lapp.htmlhttp://www.campo-nc.us/lapp.htmlhttp://www.campo-nc.us/lapp.html

  • ADJOURN