m. karppinen te-msc-ml on behalf of s. atieh, p. cruikshank, m. duret, j-c. perez, v. parma, t....

14
M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J- C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve DN200 Status 05/03 Sectors 1-2, 3-4, 5-6, 6-7 05-Mar-09 1 M. Karppinen TE-MSC-ML

Upload: isabel-glenn

Post on 14-Jan-2016

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve

M. Karppinen TE-MSC-MLon behalf of

S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia,

S107, S108, Dubna teams

Pressure relief valve DN200 Status 05/03

Sectors 1-2, 3-4, 5-6, 6-7

05-Mar-091

M. Karppinen TE-MSC-ML

Page 2: M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve

Cold sectors, new (temporary) relief scheme

2

Keep existing 2 DN90 relief devices Mount relief springs on 5 DN100 vac. flanges Mount relief springs on 8 DN100 BPM flanges Mount relief springs on 4 DN63 cryo.instr. flanges

Cross section increase: x 10

PTQVQV QV QVQV SVSV

Q D D QD D D QD D D QD D D QD

SV SVSV SV SV

2 kg/s

20 kg/s

40 kg/s

DP1

1.5

2

2.5

3

3.5

4

0 20 40 60 80 100 120

Vac

encl

osur

e P

[bar

]

Vac enclosure He T [K]

3.32.8

V. Parma Chamonix 2009

L.Tavian

Pressure for MCI still high and well above 1.5 bars design pressure

Reinforced ground fixations for SSS with vacuum barriers are being studied (see O. Capatina’s talk)

Further testing of support posts and vacuum barriers to assess next structural limit

05-Mar-09M. Karppinen TE-MSC-ML

Page 3: M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve

Warm sectors: New overpressure relief scheme

3

Keep existing 2 DN90 relief devices Mount relief springs on 4 DN100 blank flanges Add 12 DN200 new relief devices (1 per dipole)

Cross section increase: x 33

PTQVQV QV QVQV SVSV

Q D D QD D D QD D D QD D D QD

SV SV SV SV SV SV SV SV SV SV SV SV SV SV SV SV SV

V. Parma Chamonix 2009

2 kg/s20 kg/s

40 kg/s

DP

1

1.1

1.2

1.3

1.4

1.5

1.6

0 20 40 60 80 100 120

Vac

encl

osur

e P

[bar

]

Vac enclosure He T [K]L.Tavian05-Mar-09M. Karppinen TE-MSC-ML

Page 4: M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve

Special cases

4

Mid-arc vacuum sub-sectors: ½ length insulation vacuum sub-

sector (~100 m) 6 dipoles only 6 DN200 relief

devices 2 SSS 4 DN100

2 kg/s

20 kg/s

40 kg/s

11.21.41.61.8

22.22.4

0 20 40 60 80 100 120

Vac

encl

osur

e P

[bar

]

Vac enclosure He T [K]

6 DN200 + 4 DN100

L.Tavian

>1.8 bars install 12 x DN200 (2 per MB)

DS zones: 20% shorter insulation vacuum sub-

sector (~170 m) 8 dipoles only 8 DN200 relief

devices 4 SSS (Q11-Q8), [5 around Pt.3-7

(Q7)] ~ 8 DN100

2 kg/s

20 kg/s

40 kg/s

11.11.21.31.41.51.61.7

0 20 40 60 80 100 120

Vac

encl

osur

e P

[bar

]

Vac enclosure He T [K]

8 DN200 + 8 DN100

Marginal, >1.5 bars, if T>80K install 12 x DN 200

L.Tavian

V. Parma Chamonix 2009

05-Mar-09M. Karppinen TE-MSC-ML

Page 5: M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve

DN200 Std. Location

05-Mar-09M. Karppinen TE-MSC-ML5

Courtesy of T. Renaglia

Page 6: M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve

Relief valve: detailed view

6

Top position is best for safety (personnel, H/W). IFS end best for flow conductance through thermal shield (large

openings). Interconnection sleeve (W bellow) need to be opened to protect MLI

(fire risk due to hot metal chips).

T. Renaglia

05-Mar-09M. Karppinen TE-MSC-ML

Page 7: M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve

05-Mar-09M. Karppinen TE-MSC-ML7

Courtesy of T. Renaglia

DN200 Point-6 (8xMB)

Page 8: M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve

05-Mar-09M. Karppinen TE-MSC-ML8

Protective measuresProtective measures

Opening W bellows

Protection of the IC

IFS covers

MLI protection

Page 9: M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve

DN200 Status: Preparation Personnel:

Three contracts: S107 (6+1), S108 (6+1), ATLAS-Dubna collaboration (6) 2 teams of 3 (1 welder + 2 mechanics) per sector. Dedicated FSU (S108) team of 10 persons opening and closing W bellows.

Material & Tooling: All tools and equipment available. 420 nozzles delivered. Blank flanges expected W10 (TBC) Issues with the cutting machines: Modifications to improve the reliability in

progress. In parallel looking for alternative solutions. Machine for in-situ rectification of the sealing surface being commissioned.

Quality control: Visual inspection of the welds being done by external welding inspectors. Dimensional control of the valves (flatness of the sealing surface) Local leak detection equipment tested and qualified. Inspections underway. Leak testing of vacuum sectors after closing the W bellows.

9M. Karppinen TE-MSC-ML 05-Mar-09

Page 10: M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve

05-Mar-09M. Karppinen TE-MSC-ML10

M. Duret, P. Lambert, J-F. Rakotoarison

Core drilling machinesCore drilling machines

T. Renaglia

Page 11: M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve

05-Mar-09M. Karppinen TE-MSC-ML11

Local Leak detectionLocal Leak detection

Rubber sealRubber sealP. Cruikshank

Page 12: M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve

05-Mar-09M. Karppinen TE-MSC-ML12

J-C Perez & T. Sahner

In-situ rectification of the sealing surface

In-situ rectification of the sealing surface

Flatness spec < 0.3 mmFlatness spec < 0.3 mm

Page 13: M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve

DN200 Status: Installation

All magnets marked and the paint stripped off in the arcs and DS. W-bellow opening synchronized with the valve installation.

Installation status (3/3/09):Surface 25 magnets (29 valves)Sector 1-2 34 magnets (44 valves)Sector 3-4 19 magnets (25 valves)Sector 5-6 22 magnets (28 valves)=========================== TOTAL: 100 magnets (126 valves)

13M. Karppinen TE-MSC-ML 05-Mar-09

Page 14: M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve

DN200 Installation Schedule (27 Feb)

14M. Karppinen TE-MSC-ML 05-Mar-09

  TotalSector

1-2Sector

3-4Sector

5-6Sector

6-7Remarks

W6 2   2     Surface

W7 11   9     Surface

W8 34 9 11 3   Surface & Tunnel

W9 87 21 12+6 14   Surface & Tunnel

W10 157 30 20 20    

W11 235 30 24 24    

W12 313 30 24 24    

W13 391 30 24 24    

W14 473 18 24 24 16  

W15 551   12 24 42  

W16 634     11 72  

W17 672       38  

SUM   168 168 168 168  

Contract   DUBNA S-107 S-108 ALL