m ultidisciplinary s enior d esign r ochester i nstitute of t echnology d resser -r and p ainted p...

24
MULTIDISCIPLINARY SENIOR DESIGN ROCHESTER INSTITUTE OF TECHNOLOGY DRESSER-RAND PAINTED POST P10459 FINAL PROJECT REVIEW 5/14/10 Team: Phil Eaton (ME) Alex Frenkel (ME) Rachel Koch (ME) Pete Lowry (ISE) Yi Xie (ISE) Faculty Guide: John Kaemmerlen

Upload: crystal-nash

Post on 02-Jan-2016

214 views

Category:

Documents


0 download

TRANSCRIPT

MULTIDISCIPLINARY SENIOR DESIGNROCHESTER INSTITUTE OF TECHNOLOGY

DRESSER-RAND PAINTED POSTP10459

FINAL PROJECT REVIEW5/14/10

Team:Phil Eaton (ME)

Alex Frenkel (ME)Rachel Koch (ME)Pete Lowry (ISE)

Yi Xie (ISE)

Faculty Guide:John Kaemmerlen

OUTLINE

Overview Results Machine Configuration Summary Cell Layout Summary Material Handling Summary Material Storage Summary Process Improvement Summary Project Evaluation Future Steps/Recommendations

PROJECT DESCRIPTION

o Problem• Liner cell is located in 3 different parts of the plant• One part is in a location that will be closed off

o Objective• Provide a detailed plan for

movement/consolidation• Maximize productivity, safety, quality, and

profitability in new layouto Stakeholders

• RIT: John Kaemmerlen, Senior Design Program• D-R: Dennis Rice, Mike Decerbo, John Woedy

• RIT MSD• December 2009-May 2010

CUSTOMER NEEDS/ENGINEERING SPECIFICATIONS

Need Metric Current Target Actual Deliverable

Machine Configuration

# Injuries 0 0 0*Specifications

PackageProcess Time 120 min 90 min (-25%) 90 min (-25%)*

Cell Layout

Travel Distance Next Slide Cutover PlanLayout

DrawingsMfg Footprint 6584 Sq Ft4608 Sq Ft

(-30%)5282 Sq Ft

(-23%)

Process Improvement

# Injuries 0 0 0*

Visual Control Boards

Lean Training

Process Time 35 Hrs 28 Hrs (-20%) 28 Hrs (-20%)*

Defect Cost $40,623 $20,311 (-50%)$20,311 (-50%)*

Material Handling

Defect Cost $6,000 0 (-100%) $0 (-100%)*

Pallet Prototype# Injuries 0 0 0*Material Storage

Space Utilization 480 Sq Ft

192 Sq Ft (-60%)

163 Sq Ft (-66%) Rack Drawings

* Estimated

TRAVEL DISTANCE SPECIFICATIONS

Liner Type Current Travel Distance

Target Actual

Lrg Prod 1890 ft 945 ft (-50%) 881 ft (53%)

Sml Prod 1952 ft 976 ft (-50%) 868 ft (54%)

Lrg Serv 2464 ft 1,232 ft (-50%)

1881 ft (24%)

Sml Serv 1745 ft 877 ft (-50%) 1046 ft (46%)

CONCEPT SUMMARY: MACHINE CONFIGURATION/FIT UP BOOTH

Need: Increase productivity and safety through analysis of alternative machines

Originally we wanted to pursue investigating the purchase of new CNC equipment, this did not happen.

The final machine configuration brought all assets from shop 21 into the new cell. As well as an additional asset from outside of liner cell The Cincinnati Gilbert will bring the porting

operation into the cell greatly reducing the travel distance currently in place to port liners outside of the cell.

FIT-UP BOOTH

Additionally we suggest the purchase construction and installation of new equipment for a fit up booth. Not only does this add value in saved time, but

added safety also is achieved.

FIT-UP BOOTH

FIT-UP BOOTH

CONCEPT SUMMARY: CELL LAYOUT All Concepts involved moving the Shop 21

Liner Cell into a new area (Either Shop 17 or 6)

Concepts considered moving the #6425 Norton Grinder, #6605 American Lathe &/or #6911 Gilbert in addition to the Shop 21 machines

Concepts considered purchasing a new Vertical Turning Lathe

Final Concepts were determined to involve using extended Shop 6 layout including the #6911 Gilbert, leaving #6425 Norton Grinder & #6605 American Lathe as is, adding Racks & a Fit-up booth, & not adding a new VTL.

CONCEPT SUMMARY: CELL LAYOUT

DESIGN SUMMARY: CELL LAYOUT The Final Layout reduces travel distance by 600-

1000 feet per liner type (an average of 45% less), saves 23% in foot print, and allows management by sight

CONCEPT SUMMARY: MATERIAL HANDLING

Standard wooden pallet

(Oak)

Small V Blocks (Oak)

Large V Block (Oak)

Method for strapping the liner to the pallet

Standard wooden pallet with adjustable V Block fixtures for different sizing/length of liners

Holes for adjustable V

Block spacing

SYSTEM TESTING RESULTS: MATERIAL HANDLING Initial inspection

There are no initial fractures in the pallet or v-blocks. 

Testing We put a liner on a pallet and held it down using a tie-down strap. We had a forklift operator move the pallet at working speed (approx. 3-4 mph):

No movement of liner

Consistent strap tension

No damage to liner/pallet

Circular Movement Forward Motion Backward Motion Stopping Short

DESIGN SUMMARY: MATERIAL HANDLING/STORAGE Vertical storage rack

reduces WIP storage footprint by 66%

Will improve cleanliness of work area and lower risk of damage since liners are organized at a central location

Resolution

Identification(Visual Controls)

Problem Long Term problems

Immediate

Problems

Hidden Problem

s

Machine D/T Board

Process Control Board

Waste Tracking Sheet

Flow Analysis Action/ Resolution board

Outputs

Higher Quality

Greater Productivity

Best Safety

PROCESS IMPROVEMENT

PROCESS CONTROL BOARD

MACHINE DOWNTIME BOARD

WASTE TRACKING SHEET

VISUAL CONTROL MANAGEMENT

Visual Control Who records Frequency Who sees

Process Control

Supervisor, Planner,

Operators Each ProcessSupervisor,

PlannerDowntime

Tracker Supervisor Each D/T OperatorsWaste

Tracker Operators Daily SupervisorAction

Resolution Supervisor DailyOperators,

Super

OBJECTIVE PROJECT EVALUATION: SUCCESS AND FAILURE

Successes Support from operators, CI team, and

management Targets met for layout and material storage Successful pallet prototype Buy-in for visual controls

Shortcomings Multiple iterations Change of scope Lack of implementation

OPPORTUNITIES/SUGGESTIONS FOR FUTURE WORK

Machine Configuration Automated equipment Involve all stakeholders in decision making process

Cell Layout Go through 3P for all layout changes Involve all stakeholders in decision making process

Process Improvement Operators: Active problem solving and reporting Supervisors: Consistent problem solving follow up Management: Support for change initiatives Limit problems to manageable amount

OPPORTUNITIES/SUGGESTIONS FOR FUTURE WORK

Material Handling: Investigate strapping options which have more

than one connection point to pallet Painting pallets to prevent loss

Material Storage Updating processes and machines to reduce WIP

storage Less need for storage if a liner is completed with little

interruption in the manufacturing process

ACKNOWLEDGEMENTS

Thank You Operators: Wayne, Gary, Roland, Dave Supervisors/Planner: John, Lori, Shane Management: Don, Mike, Chris CI team: John, Justin Maintenance: Pat, Ron

Lastly, what can we leave you?