Page 1: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL COLLECTIONS SPACE

RICHMOND, VIRGINIA

Technical Specifications

Project Code: O-28723

July 31, 2018

Submitted by:

1011 Boulder Springs Drive, Suite 200

Richmond, Virginia 23225 Phone: 804.592.3900

Fax: 804.592.3901 www.brockenbrough.com

Job No. 15-065

Page 2: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART
Page 3: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART
Page 4: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART
Page 5: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE                    RICHMOND MAIN LIBRARY 

  LIST OF DRAWINGS ‐ 1 

LIST OF DRAWINGS   

 G‐001    Index of Drawings, Location and Vicinity Map  MD‐101  Demolition Plan M‐001    Abbreviations, Notes, Legend and Specifications M‐102    New Work Plan M‐103    Roof Plan M‐501    Details and Schedules E‐001    Abbreviations, Notes, Legend and Specifications E‐101    New Work Plan  

Page 6: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART
Page 7: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SUMMARY 011000 - 1

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Project information. 2. Work covered by Contract Documents. 3. Access to site. 4. Coordination with occupants. 5. Work restrictions. 6. Specification and Drawing conventions.

B. Related Requirements:

1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1.3 PROJECT INFORMATION

A. Project Identification: HVAC Upgrades – Special Collections Space Richmond Main Library.

1. Project Location: 101 E. Franklin Street, Richmond, VA 23219.

B. Owner: City of Richmond General Services.

1. Owner's Representative: L. Dexter Goode, LEED Green Associate Senior Capital Projects Manager 900 E. Broad Street, Richmond, VA 23219

C. Engineer: Daniel J. Woolford, PE, CEM, BEP 1011 Boulder Springs Drive, Suite 200, Richmond, VA 23225 804-592-3900

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists of the following:

Page 8: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SUMMARY 011000 - 2

1. Demolition of an existing chilled water air handling unit and provision of a new split system and other work indicated on the contract documents.

1.5 ACCESS TO SITE

A. Use of Site: Limit use of Project site to Work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine construction operations to work in areas as indicated. 2. Driveways, Walkways and Entrances: Keep driveways loading areas, and entrances

serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

B. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.

1.6 COORDINATION WITH OCCUPANTS

A. Full Owner Occupancy: Owner will occupy site and existing building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction.

2. Notify Owner not less than 72 hours in advance of activities that will affect Owner's operations.

1.7 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 8:00 a.m. to 5:00 p.m., Monday through Friday, unless otherwise indicated.

Page 9: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SUMMARY 011000 - 3

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify Owner not less than two days in advance of proposed utility interruptions. 2. Obtain Owner's written permission before proceeding with utility interruptions.

D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.

1. Notify Owner not less than two days in advance of proposed disruptive operations. 2. Obtain Owner's written permission before proceeding with disruptive operations.

E. Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor-air intakes.

F. Restricted Substances: Use of tobacco products and other controlled substances within the existing building is not permitted.

G. Employee Identification: Owner will provide identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times.

H. Employee Screening: Comply with Owner's requirements for drug and background screening of Contractor personnel working on Project site.

1. Maintain list of approved screened personnel with Owner's representative.

1.8 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products: 1. Keynoting: Materials and products are identified by reference keynotes referencing

Specification Section numbers found in this Project Manual.

Page 10: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SUMMARY 011000 - 4

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

Page 11: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SUBMITTAL PROCEDURES 013300 - 1

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Submittal schedule requirements. 2. Administrative and procedural requirements for submittals.

B. Related Requirements: 1. Section 017700 "Closeout Procedures" for submitting closeout submittals and

maintenance material submittals. 2. Section 017823 "Operation and Maintenance Data" for submitting operation and

maintenance manuals. 3. Section 017839 "Project Record Documents" for submitting record Drawings, record

Specifications, and record Product Data.

1.3 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require Engineer's responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."

B. Informational Submittals: Written and graphic information and physical samples that do not require Engineer's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."

1.4 SUBMITTAL SCHEDULE

A. Submittal Schedule: Submit, as an action submittal, a list of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by Engineer and additional time for handling and reviewing submittals required by those corrections.

Page 12: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SUBMITTAL PROCEDURES 013300 - 2

1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and Contractor's construction schedule.

2. Initial Submittal: Submit concurrently with startup construction schedule. Include submittals required during the first 60 days of construction. List those submittals required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.

3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's construction schedule.

a. Submit revised submittal schedule to reflect changes in current status and timing for submittals.

4. Format: Arrange the following information in a tabular format:

a. Scheduled date for first submittal. b. Specification Section number and title. c. Submittal Category: Action; informational. d. Name of subcontractor. e. Description of the Work covered. f. Scheduled date for Engineer's final release or approval.

1.5 SUBMITTAL FORMATS

A. Submittal Information: Include the following information in each submittal:

1. Project name. 2. Date. 3. Name of Engineer. 4. Name of Contractor. 5. Name of firm or entity that prepared submittal. 6. Names of subcontractor, manufacturer, and supplier. 7. Unique submittal number, including revision identifier. Include Specification Section

number with sequential alphanumeric identifier; and alphanumeric suffix for resubmittals.

8. Category and type of submittal. 9. Submittal purpose and description. 10. Number and title of Specification Section, with paragraph number and generic name for

each of multiple items. 11. Drawing number and detail references, as appropriate. 12. Indication of full or partial submittal. 13. Location(s) where product is to be installed, as appropriate. 14. Other necessary identification. 15. Remarks. 16. Signature of transmitter.

B. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those requested by Engineer on

Page 13: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SUBMITTAL PROCEDURES 013300 - 3

previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet.

C. Paper Submittals:

1. Place a permanent label or title block on each submittal item for identification; include name of firm or entity that prepared submittal.

2. Provide a space approximately 6 by 8 inches on label or beside title block to record Contractor's review and approval markings and action taken by Engineer.

3. Action Submittals: Submit three paper copies of each submittal unless otherwise indicated. Engineer will return two copies.

4. Informational Submittals: Submit two paper copies of each submittal unless otherwise indicated. Engineer will not return copies.

5. Additional Copies: Unless additional copies are required for final submittal, and unless Engineer observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal.

6. Transmittal for Submittals: Assemble each submittal individually and appropriately for transmittal and handling.

D. PDF Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.

1.6 SUBMITTAL PROCEDURES

A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.

1. Email: Prepare submittals as PDF package, and transmit to Architect by sending via email. Include PDF transmittal form.

a. Engineer will return annotated file. Annotate and retain one copy of file as a digital Project Record Document file.

2. Paper: Prepare submittals in paper form, and deliver to Architect.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.

3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.

4. Coordinate transmittal of submittals for related parts of the Work specified in different Sections so processing will not be delayed because of need to review submittals concurrently for coordination.

Page 14: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SUBMITTAL PROCEDURES 013300 - 4

a. Engineer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Engineer’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Engineer will advise Contractor when a submittal being processed must be delayed for coordination.

2. Resubmittal Review: Allow 15 days for review of each resubmittal.

D. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

1. Note date and content of previous submittal. 2. Note date and content of revision in label or title block and clearly indicate extent of

revision. 3. Resubmit submittals until they are marked with approval notation from Engineer’s

action stamp.

E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Engineer’s action stamp.

1.7 SUBMITTAL REQUIREMENTS

A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable. 3. Include the following information, as applicable:

a. Manufacturer's catalog cuts. b. Manufacturer's product specifications. c. Standard color charts. d. Statement of compliance with specified referenced standards. e. Testing by recognized testing agency. f. Application of testing agency labels and seals. g. Notation of coordination requirements. h. Availability and delivery time information.

4. For equipment, include the following in addition to the above, as applicable:

Page 15: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SUBMITTAL PROCEDURES 013300 - 5

a. Wiring diagrams that show factory-installed wiring. b. Printed performance curves. c. Operational range diagrams. d. Clearances required to other construction, if not indicated on accompanying Shop

Drawings.

B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Identification of products. b. Schedules. c. Compliance with specified standards. d. Notation of coordination requirements. e. Notation of dimensions established by field measurement. f. Relationship and attachment to adjoining construction clearly indicated. g. Seal and signature of professional engineer if specified.

2. Paper Sheet Size: Except for templates, patterns, and similar full-size Drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches, but no larger than 30 by 42 inches.

C. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:

1. Type of product. Include unique identifier for each product indicated in the Contract Documents or assigned by Contractor if none is indicated.

2. Manufacturer and product name, and model number if applicable. 3. Number and name of room or space. 4. Location within room or space.

1.8 CONTRACTOR'S REVIEW

A. Action Submittals and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Engineer.

1.9 ENGINEER’S REVIEW

A. Action Submittals: Engineer will review each submittal, indicate corrections or revisions required, and return it.

B. Informational Submittals: Engineer will review each submittal and will not return it, or will return it if it does not comply with requirements.

Page 16: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SUBMITTAL PROCEDURES 013300 - 6

C. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.

D. Submittals not required by the Contract Documents will be returned by Engineer without action.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 013300

Page 17: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

TEMPORARY FACILITIES AND CONTROLS 015000 - 1

SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes requirements for temporary utilities, support facilities, and security and protection facilities.

B. Related Requirements:

1. Section 011000 "Summary" for work restrictions and limitations on utility interruptions.

1.3 USE CHARGES

A. General: Installation and removal of and use charges for temporary facilities shall be included in the Contract Sum unless otherwise indicated. Allow other entities engaged in the Project to use temporary services and facilities without cost, including, but not limited to, Engineer, testing agencies, and authorities having jurisdiction.

B. Water and Sewer Service from Existing System: Water from Owner's existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations.

C. Electric Power Service from Existing System: Electric power from Owner's existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations.

1.4 INFORMATIONAL SUBMITTALS

A. Moisture- and Mold-Protection Plan: Describe procedures and controls for protecting materials and construction from water absorption and damage and mold.

B. Dust- and HVAC-Control Plan: Submit coordination drawing and narrative that indicates the dust- and HVAC-control measures proposed for use, proposed locations, and proposed time frame for their operation. Include the following:

1. Locations of dust-control partitions at each phase of work. 2. HVAC system isolation schematic drawing.

Page 18: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

TEMPORARY FACILITIES AND CONTROLS 015000 - 2

3. Location of proposed air-filtration system discharge. 4. Waste-handling procedures. 5. Other dust-control measures.

1.5 QUALITY ASSURANCE

A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.

PART 2 - PRODUCTS

2.1 EQUIPMENT

A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.

1. Locate facilities to limit site disturbance as specified in Section 011000 "Summary."

B. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.

3.2 TEMPORARY UTILITY INSTALLATION

A. General: Install temporary service or connect to existing service.

1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.

B. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking water for use of construction personnel. Comply with requirements of authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.

1. Toilets: Use of Owner's existing toilet facilities will be permitted, as long as facilities are cleaned and maintained in a condition acceptable to Owner. At Substantial Completion, restore these facilities to condition existing before initial use.

Page 19: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

TEMPORARY FACILITIES AND CONTROLS 015000 - 3

C. Isolation of Work Areas in Occupied Facilities: Prevent dust, fumes, and odors from entering occupied areas.

1. Maintain dust partitions during the Work. Use vacuum collection attachments on dust-producing equipment. Isolate limited work within occupied areas using portable dust-containment devices.

2. Perform daily construction cleanup and final cleanup using approved, HEPA-filter-equipped vacuum equipment.

D. Electric Power Service: Connect to Owner's existing electric power service. Maintain equipment in a condition acceptable to Owner.

3.3 SUPPORT FACILITIES INSTALLATION

A. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Comply with requirements of authorities having jurisdiction.

B. Existing Elevator Use: Use of Owner's existing elevators will be permitted, provided elevators are cleaned and maintained in a condition acceptable to Owner. At Substantial Completion, restore elevators to condition existing before initial use, including replacing worn cables, guide shoes, and similar items of limited life.

1. Do not load elevators beyond their rated weight capacity. 2. Provide protective coverings, barriers, devices, signs, or other procedures to protect

elevator car and entrance doors and frame. If, despite such protection, elevators become damaged, engage elevator Installer to restore damaged work so no evidence remains of correction work. Return items that cannot be refinished in field to the shop, make required repairs and refinish entire unit, or provide new units as required.

C. Existing Stair Usage: Use of Owner's existing stairs will be permitted, provided stairs are cleaned and maintained in a condition acceptable to Owner. At Substantial Completion, restore stairs to condition existing before initial use.

1. Provide protective coverings, barriers, devices, signs, or other procedures to protect stairs and to maintain means of egress. If stairs become damaged, restore damaged areas so no evidence remains of correction work.

3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION

A. Protection of Existing Facilities: Protect existing vegetation, equipment, structures, utilities, and other improvements at Project site and on adjacent properties, except those indicated to be removed or altered. Repair damage to existing facilities.

B. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction as required to comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

Page 20: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

TEMPORARY FACILITIES AND CONTROLS 015000 - 4

1. Comply with work restrictions specified in Section 011000 "Summary."

C. Tree and Plant Protection: Install temporary fencing located as indicated or outside the drip line of trees to protect vegetation from damage from construction operations. Protect tree root systems from damage, flooding, and erosion.

3.5 OPERATION, TERMINATION, AND REMOVAL

A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.

B. Maintenance: Maintain facilities in good operating condition until removal.

1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage.

C. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion.

D. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.

1. Materials and facilities that constitute temporary facilities are property of Contractor. Owner reserves right to take possession of Project identification signs.

2. At Substantial Completion, repair, renovate, and clean permanent facilities used during construction period. Comply with final cleaning requirements specified in Section 017700 "Closeout Procedures."

END OF SECTION 015000

Page 21: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

EXECUTION 017300 - 1

SECTION 017300 - EXECUTION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes general administrative and procedural requirements governing execution of the Work including, but not limited to, the following:

1. Construction layout. 2. Installation of the Work. 3. Cutting and patching. 4. Progress cleaning. 5. Starting and adjusting. 6. Protection of installed construction.

B. Related Requirements:

1. Section 011000 "Summary" for limits on use of Project site. 2. Section 013300 "Submittal Procedures" for submitting surveys. 3. Section 017700 "Closeout Procedures" for submitting final property survey with Project

Record Documents, recording of Owner-accepted deviations from indicated lines and levels, replacing defective work, and final cleaning.

4. Section 024119 "Selective Demolition" for demolition and removal of selected portions of the building.

1.3 DEFINITIONS

A. Cutting: Removal of in-place construction necessary to permit installation or performance of subsequent work.

B. Patching: Fitting and repair work required to restore construction to original conditions after installation of subsequent work.

1.4 INFORMATIONAL SUBMITTALS

A. Cutting and Patching Plan: Submit plan describing procedures at least 10 days prior to the time cutting and patching will be performed. Include the following information:

Page 22: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

EXECUTION 017300 - 2

1. Extent: Describe reason for and extent of each occurrence of cutting and patching. 2. Changes to In-Place Construction: Describe anticipated results. Include changes to

structural elements and operating components as well as changes in building appearance and other significant visual elements.

3. Products: List products to be used for patching and firms or entities that will perform patching work.

4. Dates: Indicate when cutting and patching will be performed. 5. Utilities and Mechanical and Electrical Systems: List services and systems that cutting

and patching procedures will disturb or affect. List services and systems that will be relocated and those that will be temporarily out of service. Indicate length of time permanent services and systems will be disrupted.

1.5 QUALITY ASSURANCE

A. Land Surveyor Qualifications: A professional land surveyor who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing land-surveying services of the kind indicated.

B. Cutting and Patching: Comply with requirements for and limitations on cutting and patching of construction elements.

1. Structural Elements: When cutting and patching structural elements, notify Architect of locations and details of cutting and await directions from Architect before proceeding. Shore, brace, and support structural elements during cutting and patching. Do not cut and patch structural elements in a manner that could change their load-carrying capacity or increase deflection.

2. Operational Elements: Do not cut and patch operating elements and related components in a manner that results in reducing their capacity to perform as intended or that results in increased maintenance or decreased operational life or safety. Operational elements include the following:

a. Primary operational systems and equipment. b. Fire separation assemblies. c. Air or smoke barriers. d. Fire-suppression systems. e. Plumbing piping systems. f. Mechanical systems piping and ducts. g. Control systems. h. Communication systems. i. Fire-detection and -alarm systems. j. Conveying systems. k. Electrical wiring systems. l. Operating systems of special construction.

3. Other Construction Elements: Do not cut and patch other construction elements or components in a manner that could change their load-carrying capacity, that results in reducing their capacity to perform as intended, or that results in increased maintenance

Page 23: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

EXECUTION 017300 - 3

or decreased operational life or safety. Other construction elements include but are not limited to the following:

a. Water, moisture, or vapor barriers. b. Membranes and flashings. c. Exterior curtain-wall construction. d. Sprayed fire-resistive material. e. Equipment supports. f. Piping, ductwork, vessels, and equipment. g. Noise- and vibration-control elements and systems.

4. Visual Elements: Do not cut and patch construction in a manner that results in visual evidence of cutting and patching. Do not cut and patch exposed construction in a manner that would, in Architect's opinion, reduce the building's aesthetic qualities. Remove and replace construction that has been cut and patched in a visually unsatisfactory manner.

C. Manufacturer's Installation Instructions: Obtain and maintain on-site manufacturer's written recommendations and instructions for installation of products and equipment.

PART 2 - PRODUCTS

2.1 MATERIALS

A. General: Comply with requirements specified in other Sections.

B. In-Place Materials: Use materials for patching identical to in-place materials. For exposed surfaces, use materials that visually match in-place adjacent surfaces to the fullest extent possible.

1. If identical materials are unavailable or cannot be used, use materials that, when installed, will provide a match acceptable to Architect for the visual and functional performance of in-place materials.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examination and Acceptance of Conditions: Before proceeding with each component of the Work, examine substrates, areas, and conditions, with Installer or Applicator present where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations.

1. Examine roughing-in for mechanical and electrical systems to verify actual locations of connections before equipment and fixture installation.

Page 24: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

EXECUTION 017300 - 4

2. Examine walls, floors, and roofs for suitable conditions where products and systems are to be installed.

3. Verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers.

B. Written Report: Where a written report listing conditions detrimental to performance of the Work is required by other Sections, include the following:

1. Description of the Work. 2. List of detrimental conditions, including substrates. 3. List of unacceptable installation tolerances. 4. Recommended corrections.

C. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.

3.2 PREPARATION

A. Existing Utility Information: Furnish information to Owner that is necessary to adjust, move, or relocate existing utility structures, utility poles, lines, services, or other utility appurtenances located in or affected by construction. Coordinate with authorities having jurisdiction.

B. Field Measurements: Take field measurements as required to fit the Work properly. Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work.

C. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.

D. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents caused by differing field conditions outside the control of Contractor, submit a request for information to Architect according to requirements in Section 013100 "Project Management and Coordination."

3.3 CONSTRUCTION LAYOUT

A. Verification: Before proceeding to lay out the Work, verify layout information shown on Drawings, in relation to the property survey and existing benchmarks. If discrepancies are discovered, notify Engineer promptly.

3.4 INSTALLATION

A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

Page 25: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

EXECUTION 017300 - 5

1. Make vertical work plumb and make horizontal work level. 2. Where space is limited, install components to maximize space available for maintenance

and ease of removal for replacement. 3. Conceal pipes, ducts, and wiring in finished areas unless otherwise indicated.

B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.

C. Install products at the time and under conditions that will ensure the best possible results. Maintain conditions required for product performance until Substantial Completion.

D. Conduct construction operations so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy.

E. Sequence the Work and allow adequate clearances to accommodate movement of construction items on site and placement in permanent locations.

F. Tools and Equipment: Where possible, select tools or equipment that minimize production of excessive noise levels.

G. Attachment: Provide blocking and attachment plates and anchors and fasteners of adequate size and number to securely anchor each component in place, accurately located and aligned with other portions of the Work. Where size and type of attachments are not indicated, verify size and type required for load conditions.

1. Mounting Heights: Where mounting heights are not indicated, mount components at heights directed by Architect.

2. Allow for building movement, including thermal expansion and contraction. 3. Coordinate installation of anchorages. Furnish setting drawings, templates, and

directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation.

H. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connections together to form hairline joints.

I. Repair or remove and replace damaged, defective, or nonconforming Work.

1. Comply with Section 017700 "Closeout Procedures" for repairing or removing and replacing defective Work.

3.5 CUTTING AND PATCHING

A. Cutting and Patching, General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay.

Page 26: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

EXECUTION 017300 - 6

1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.

B. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during installation or cutting and patching operations, by methods and with materials so as not to void existing warranties.

C. Temporary Support: Provide temporary support of work to be cut.

D. Protection: Protect in-place construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.

E. Adjacent Occupied Areas: Where interference with use of adjoining areas or interruption of free passage to adjoining areas is unavoidable, coordinate cutting and patching according to requirements in Section 011000 "Summary."

F. Existing Utility Services and Mechanical/Electrical Systems: Where existing services/systems are required to be removed, relocated, or abandoned, bypass such services/systems before cutting to prevent interruption to occupied areas.

G. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations.

1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots neatly to minimum size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.

2. Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces. 3. Concrete and Masonry: Cut using a cutting machine, such as an abrasive saw or a

diamond-core drill. 4. Excavating and Backfilling: Comply with requirements in applicable Sections where

required by cutting and patching operations. 5. Mechanical and Electrical Services: Cut off pipe or conduit in walls or partitions to be

removed. Cap, valve, or plug and seal remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after cutting.

6. Proceed with patching after construction operations requiring cutting are complete.

H. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other work. Patch with durable seams that are as invisible as practicable. Provide materials and comply with installation requirements specified in other Sections, where applicable.

1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate physical integrity of installation.

Page 27: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

EXECUTION 017300 - 7

2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will minimize evidence of patching and refinishing.

a. Clean piping, conduit, and similar features before applying paint or other finishing materials.

b. Restore damaged pipe covering to its original condition.

3. Floors and Walls: Where walls or partitions that are removed extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish, color, texture, and appearance. Remove in-place floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.

a. Where patching occurs in a painted surface, prepare substrate and apply primer and intermediate paint coats appropriate for substrate over the patch, and apply final paint coat over entire unbroken surface containing the patch. Provide additional coats until patch blends with adjacent surfaces.

4. Ceilings: Patch, repair, or rehang in-place ceilings as necessary to provide an even-plane surface of uniform appearance.

5. Exterior Building Enclosure: Patch components in a manner that restores enclosure to a weathertight condition and ensures thermal and moisture integrity of building enclosure.

I. Cleaning: Clean areas and spaces where cutting and patching are performed. Remove paint, mortar, oils, putty, and similar materials from adjacent finished surfaces.

3.6 PROGRESS CLEANING

A. General: Clean Project site and work areas daily, including common areas. Enforce requirements strictly. Dispose of materials lawfully.

1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.

2. Do not hold waste materials more than seven days during normal weather or three days if the temperature is expected to rise above 80 deg F.

3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.

a. Use containers intended for holding waste materials of type to be stored.

4. Coordinate progress cleaning for joint-use areas where Contractor and other contractors are working concurrently.

B. Site: Maintain Project site free of waste materials and debris.

Page 28: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

EXECUTION 017300 - 8

C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.

1. Remove liquid spills promptly. 2. Where dust would impair proper execution of the Work, broom-clean or vacuum the

entire work area, as appropriate.

D. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.

E. Concealed Spaces: Remove debris from concealed spaces before enclosing the space.

F. Exposed Surfaces in Finished Areas: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion.

G. Waste Disposal: Do not bury or burn waste materials on-site. Do not wash waste materials down sewers or into waterways. Comply with waste disposal requirements in Section 015000 "Temporary Facilities and Controls."

H. During handling and installation, clean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.

I. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.

J. Limiting Exposures: Supervise construction operations to ensure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.

3.7 STARTING AND ADJUSTING

A. Start equipment and operating components to confirm proper operation. Remove malfunctioning units, replace with new units, and retest.

B. Adjust equipment for proper operation. Adjust operating components for proper operation without binding.

C. Test each piece of equipment to verify proper operation. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment.

D. Manufacturer's Field Service: Comply with qualification requirements in Section 014000 "Quality Requirements."

Page 29: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

EXECUTION 017300 - 9

3.8 PROTECTION OF INSTALLED CONSTRUCTION

A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.

B. Protection of Existing Items: Provide protection and ensure that existing items to remain undisturbed by construction are maintained in condition that existed at commencement of the Work.

C. Comply with manufacturer's written instructions for temperature and relative humidity.

END OF SECTION 017300

Page 30: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART
Page 31: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

CLOSEOUT PROCEDURES 017700 - 1

SECTION 017700 - CLOSEOUT PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:

1. Substantial Completion procedures. 2. Final completion procedures. 3. Warranties. 4. Final cleaning. 5. Repair of the Work.

B. Related Requirements: 1. Section 017823 "Operation and Maintenance Data" for additional operation and

maintenance manual requirements. 2. Section 017839 "Project Record Documents" for submitting Record Drawings, Record

Specifications, and Record Product Data.

1.3 SUBSTANTIAL COMPLETION PROCEDURES

A. Contractor's List of Incomplete Items: Prepare and submit a list of items to be completed and corrected (Contractor's punch list), indicating the value of each item on the list and reasons why the Work is incomplete.

B. Procedures Prior to Substantial Completion: Complete the following a minimum of 10 days prior to requesting inspection for determining date of Substantial Completion. List items below that are incomplete at time of request.

1. Advise Owner of pending insurance changeover requirements. 2. Make final changeover of permanent locks and deliver keys to Owner. Advise Owner's

personnel of changeover in security provisions. 3. Complete startup and testing of systems and equipment. 4. Perform preventive maintenance on equipment used prior to Substantial Completion. 5. Instruct Owner's personnel in operation, adjustment, and maintenance of products,

equipment, and systems. Submit demonstration and training video recordings specified in Section 017900 "Demonstration and Training."

Page 32: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

CLOSEOUT PROCEDURES 017700 - 2

6. Advise Owner of changeover in utility services. 7. Participate with Owner in conducting inspection and walkthrough with local emergency

responders. 8. Terminate and remove temporary facilities from Project site, along with mockups,

construction tools, and similar elements. 9. Complete final cleaning requirements. 10. Touch up paint and otherwise repair and restore marred exposed finishes to eliminate

visual defects.

C. Inspection: Submit a written request for inspection to determine Substantial Completion a minimum of 10 days prior to date the Work will be completed and ready for final inspection and tests. On receipt of request, Engineer will either proceed with inspection or notify Contractor of unfulfilled requirements. Engineer will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by Engineer, that must be completed or corrected before certificate will be issued.

1. Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

2. Results of completed inspection will form the basis of requirements for final completion.

1.4 FINAL COMPLETION PROCEDURES

A. Submittals Prior to Final Completion: Before requesting final inspection for determining final completion, complete the following: 1. Certified List of Incomplete Items: Submit certified copy of Engineer's Substantial

Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by Engineer. Certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.

2. Certificate of Insurance: Submit evidence of final, continuing insurance coverage complying with insurance requirements.

B. Inspection: Submit a written request for final inspection to determine acceptance a minimum of 10 days prior to date the work will be completed and ready for final inspection and tests. On receipt of request, Engineer will either proceed with inspection or notify Contractor of unfulfilled requirements. Architect will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

1. Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

1.5 LIST OF INCOMPLETE ITEMS (PUNCH LIST)

A. Organization of List: Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.

Page 33: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

CLOSEOUT PROCEDURES 017700 - 3

1. Organize list of spaces in sequential order,. 2. Organize items applying to each space by major element, including categories for

ceiling, individual walls, floors, equipment, and building systems. 3. Include the following information at the top of each page:

a. Project name. b. Date. c. Name of Engineer. d. Name of Contractor. e. Page number.

4. Submit list of incomplete items in the following format: a. PDF electronic file to Engineer and Owner.

1.6 SUBMITTAL OF PROJECT WARRANTIES

A. Time of Submittal: Submit written warranties on request of Architect for designated portions of the Work where warranties are indicated to commence on dates other than date of Substantial Completion, or when delay in submittal of warranties might limit Owner's rights under warranty.

B. Partial Occupancy: Submit properly executed warranties within 15 days of completion of designated portions of the Work that are completed and occupied or used by Owner during construction period by separate agreement with Contractor.

C. Organize warranty documents into an orderly sequence based on the table of contents of Project Manual.

D. Warranty Electronic File: Provide warranties and bonds in PDF format. Assemble complete warranty and bond submittal package into a single electronic PDF file with bookmarks enabling navigation to each item. Provide bookmarked table of contents at beginning of document.

E. Warranties in Paper Form:

1. Bind warranties and bonds in heavy-duty, three-ring, vinyl-covered, loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8-1/2-by-11-inch paper.

2. Provide heavy paper dividers with plastic-covered tabs for each separate warranty. Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer.

3. Identify each binder on the front and spine with the typed or printed title "WARRANTIES," Project name, and name of Contractor.

F. Provide additional copies of each warranty to include in operation and maintenance manuals.

Page 34: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

CLOSEOUT PROCEDURES 017700 - 4

PART 2 - PRODUCTS

2.1 MATERIALS

A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

PART 3 - EXECUTION

3.1 FINAL CLEANING

A. General: Perform final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit to condition expected in an average commercial building cleaning and maintenance program. Comply with manufacturer's written instructions.

1. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a designated portion of Project:

a. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.

b. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits.

c. Rake grounds that are not planted, mulched, or paved to a smooth, even-textured surface.

d. Remove tools, construction equipment, machinery, and surplus material from Project site.

e. Remove snow and ice to provide safe access to building. f. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition,

free of stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces. Restore reflective surfaces to their original condition.

g. Remove debris and surface dust from limited access spaces, including roofs, plenums, shafts, trenches, equipment vaults, manholes, attics, and similar spaces.

h. Sweep concrete floors broom clean in unoccupied spaces. i. Vacuum carpet and similar soft surfaces, removing debris and excess nap; clean

according to manufacturer's recommendations if visible soil or stains remain. j. Clean transparent materials, including mirrors and glass in doors and windows.

Remove glazing compounds and other noticeable, vision-obscuring materials. Polish mirrors and glass, taking care not to scratch surfaces.

Page 35: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

CLOSEOUT PROCEDURES 017700 - 5

k. Remove labels that are not permanent. l. Wipe surfaces of mechanical and electrical equipment, elevator equipment, and

similar equipment. Remove excess lubrication, paint and mortar droppings, and other foreign substances.

m. Clean plumbing fixtures to a sanitary condition, free of stains, including stains resulting from water exposure.

n. Replace disposable air filters and clean permanent air filters. Clean exposed surfaces of diffusers, registers, and grills.

o. Clean ducts, blowers, and coils if units were operated without filters during construction or that display contamination with particulate matter on inspection.

p. Clean light fixtures, lamps, globes, and reflectors to function with full efficiency. q. Leave Project clean and ready for occupancy.

C. Pest Control: Comply with pest control requirements in Section 015000 "Temporary Facilities and Controls." Prepare written report.

D. Construction Waste Disposal: Comply with waste disposal requirements in Section 015000 "Temporary Facilities and Controls."

3.2 REPAIR OF THE WORK

A. Complete repair and restoration operations before requesting inspection for determination of Substantial Completion.

B. Repair, or remove and replace, defective construction. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment. Where damaged or worn items cannot be repaired or restored, provide replacements. Remove and replace operating components that cannot be repaired. Restore damaged construction and permanent facilities used during construction to specified condition.

1. Remove and replace chipped, scratched, and broken glass, reflective surfaces, and other damaged transparent materials.

2. Touch up and otherwise repair and restore marred or exposed finishes and surfaces. Replace finishes and surfaces that that already show evidence of repair or restoration.

a. Do not paint over "UL" and other required labels and identification, including mechanical and electrical nameplates. Remove paint applied to required labels and identification.

3. Replace parts subject to operating conditions during construction that may impede operation or reduce longevity.

4. Replace burned-out bulbs, bulbs noticeably dimmed by hours of use, and defective and noisy starters in fluorescent and mercury vapor fixtures to comply with requirements for new fixtures.

Page 36: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

CLOSEOUT PROCEDURES 017700 - 6

END OF SECTION 017700

Page 37: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

OPERATION AND MAINTENANCE DATA 017823 - 1

SECTION 017823 - OPERATION AND MAINTENANCE DATA

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for preparing operation and maintenance manuals, including the following:

1. Operation and maintenance documentation directory manuals. 2. Emergency manuals. 3. Systems and equipment operation manuals. 4. Systems and equipment maintenance manuals. 5. Product maintenance manuals.

B. Related Requirements: 1. Section 013300 "Submittal Procedures" for submitting copies of submittals for

operation and maintenance manuals.

1.3 DEFINITIONS

A. System: An organized collection of parts, equipment, or subsystems united by regular interaction.

B. Subsystem: A portion of a system with characteristics similar to a system.

1.4 CLOSEOUT SUBMITTALS

A. Submit operation and maintenance manuals indicated. Provide content for each manual as specified in individual Specification Sections, and as reviewed and approved at the time of Section submittals. Submit reviewed manual content formatted and organized as required by this Section.

1. Engineer will comment on whether content of operation and maintenance submittals is acceptable.

2. Where applicable, clarify and update reviewed manual content to correspond to revisions and field conditions.

B. Format: Submit operation and maintenance manuals in the following format:

Page 38: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

OPERATION AND MAINTENANCE DATA 017823 - 2

1. Submit on digital media acceptable to Engineer. Enable reviewer comments on draft submittals.

C. Initial Manual Submittal: Submit draft copy of each manual at least 30 days before commencing demonstration and training. Engineer will comment on whether general scope and content of manual are acceptable.

D. Final Manual Submittal: Submit each manual in final form prior to requesting inspection for Substantial Completion and at least 15 days before commencing demonstration and training. Engineer will return copy with comments.

1. Correct or revise each manual to comply with Engineer’s comments. Submit copies of each corrected manual within 15 days of receipt of Engineer's comments and prior to commencing demonstration and training.

E. Comply with Section 017700 "Closeout Procedures" for schedule for submitting operation and maintenance documentation.

1.5 FORMAT OF OPERATION AND MAINTENANCE MANUALS

A. Manuals, Electronic Files: Submit manuals in the form of a multiple file composite electronic PDF file for each manual type required.

1. Electronic Files: Use electronic files prepared by manufacturer where available. Where scanning of paper documents is required, configure scanned file for minimum readable file size.

2. File Names and Bookmarks: Bookmark individual documents based on file names. Name document files to correspond to system, subsystem, and equipment names used in manual directory and table of contents. Group documents for each system and subsystem into individual composite bookmarked files, then create composite manual, so that resulting bookmarks reflect the system, subsystem, and equipment names in a readily navigated file tree. Configure electronic manual to display bookmark panel on opening file.

1.6 REQUIREMENTS FOR EMERGENCY, OPERATION, AND MAINTENANCE MANUALS

A. Organization of Manuals: Unless otherwise indicated, organize each manual into a separate section for each system and subsystem, and a separate section for each piece of equipment not part of a system. Each manual shall contain the following materials, in the order listed:

1. Title page. 2. Table of contents. 3. Manual contents.

B. Title Page: Include the following information:

1. Subject matter included in manual.

Page 39: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

OPERATION AND MAINTENANCE DATA 017823 - 3

2. Name and address of Project. 3. Name and address of Owner. 4. Date of submittal. 5. Name and contact information for Contractor. 6. Name and contact information for Construction Manager. 7. Name and contact information for Architect. 8. Name and contact information for Commissioning Authority. 9. Names and contact information for major consultants to the Architect that designed the

systems contained in the manuals. 10. Cross-reference to related systems in other operation and maintenance manuals.

C. Table of Contents: List each product included in manual, identified by product name, indexed to the content of the volume, and cross-referenced to Specification Section number in Project Manual.

1. If operation or maintenance documentation requires more than one volume to accommodate data, include comprehensive table of contents for all volumes in each volume of the set.

D. Manual Contents: Organize into sets of manageable size. Arrange contents alphabetically by system, subsystem, and equipment. If possible, assemble instructions for subsystems, equipment, and components of one system into a single binder.

E. Identification: In the documentation directory and in each operation and maintenance manual, identify each system, subsystem, and piece of equipment with same designation used in the Contract Documents. If no designation exists, assign a designation according to ASHRAE Guideline 4, "Preparation of Operating and Maintenance Documentation for Building Systems."

1.7 OPERATION AND MAINTENANCE DOCUMENTATION DIRECTORY MANUAL

A. Operation and Maintenance Documentation Directory: Prepare a separate manual that provides an organized reference to emergency, operation, and maintenance manuals. List items and their location to facilitate ready access to desired information. Include the following:

1. List of Systems and Subsystems: List systems alphabetically. Include references to operation and maintenance manuals that contain information about each system.

2. List of Equipment: List equipment for each system, organized alphabetically by system. For pieces of equipment not part of system, list alphabetically in separate list.

3. Tables of Contents: Include a table of contents for each emergency, operation, and maintenance manual.

1.8 EMERGENCY MANUALS

A. Emergency Manual: Assemble a complete set of emergency information indicating procedures for use by emergency personnel and by Owner's operating personnel for types of emergencies indicated.

Page 40: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

OPERATION AND MAINTENANCE DATA 017823 - 4

B. Content: Organize manual into a separate section for each of the following:

1. Type of emergency. 2. Emergency instructions. 3. Emergency procedures.

C. Type of Emergency: Where applicable for each type of emergency indicated below, include instructions and procedures for each system, subsystem, piece of equipment, and component:

1. Fire. 2. Flood. 3. Gas leak. 4. Water leak. 5. Power failure. 6. Water outage. 7. System, subsystem, or equipment failure. 8. Chemical release or spill.

D. Emergency Instructions: Describe and explain warnings, trouble indications, error messages, and similar codes and signals. Include responsibilities of Owner's operating personnel for notification of Installer, supplier, and manufacturer to maintain warranties.

E. Emergency Procedures: Include the following, as applicable:

1. Instructions on stopping. 2. Shutdown instructions for each type of emergency. 3. Operating instructions for conditions outside normal operating limits. 4. Required sequences for electric or electronic systems. 5. Special operating instructions and procedures.

1.9 SYSTEMS AND EQUIPMENT OPERATION MANUALS

A. Systems and Equipment Operation Manual: Assemble a complete set of data indicating operation of each system, subsystem, and piece of equipment not part of a system. Include information required for daily operation and management, operating standards, and routine and special operating procedures.

1. Engage a factory-authorized service representative to assemble and prepare information for each system, subsystem, and piece of equipment not part of a system.

2. Prepare a separate manual for each system and subsystem, in the form of an instructional manual for use by Owner's operating personnel.

B. Content: In addition to requirements in this Section, include operation data required in individual Specification Sections and the following information:

1. System, subsystem, and equipment descriptions. Use designations for systems and equipment indicated on Contract Documents.

2. Performance and design criteria if Contractor has delegated design responsibility.

Page 41: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

OPERATION AND MAINTENANCE DATA 017823 - 5

3. Operating standards. 4. Operating procedures. 5. Operating logs. 6. Wiring diagrams. 7. Control diagrams. 8. Piped system diagrams. 9. Precautions against improper use. 10. License requirements including inspection and renewal dates.

C. Descriptions: Include the following:

1. Product name and model number. Use designations for products indicated on Contract Documents.

2. Manufacturer's name. 3. Equipment identification with serial number of each component. 4. Equipment function. 5. Operating characteristics. 6. Limiting conditions. 7. Performance curves. 8. Engineering data and tests. 9. Complete nomenclature and number of replacement parts.

D. Operating Procedures: Include the following, as applicable:

1. Startup procedures. 2. Equipment or system break-in procedures. 3. Routine and normal operating instructions. 4. Regulation and control procedures. 5. Instructions on stopping. 6. Normal shutdown instructions. 7. Seasonal and weekend operating instructions. 8. Required sequences for electric or electronic systems. 9. Special operating instructions and procedures.

E. Systems and Equipment Controls: Describe the sequence of operation, and diagram controls as installed.

F. Piped Systems: Diagram piping as installed, and identify color coding where required for identification.

1.10 SYSTEMS AND EQUIPMENT MAINTENANCE MANUALS

A. Systems and Equipment Maintenance Manuals: Assemble a complete set of data indicating maintenance of each system, subsystem, and piece of equipment not part of a system. Include manufacturers' maintenance documentation, preventive maintenance procedures and frequency, repair procedures, wiring and systems diagrams, lists of spare parts, and warranty information.

Page 42: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

OPERATION AND MAINTENANCE DATA 017823 - 6

1. Engage a factory-authorized service representative to assemble and prepare information for each system, subsystem, and piece of equipment not part of a system.

2. Prepare a separate manual for each system and subsystem, in the form of an instructional manual for use by Owner's operating personnel.

B. Content: For each system, subsystem, and piece of equipment not part of a system, include source information, manufacturers' maintenance documentation, maintenance procedures, maintenance and service schedules, spare parts list and source information, maintenance service contracts, and warranties and bonds as described below.

C. Source Information: List each system, subsystem, and piece of equipment included in manual, identified by product name and arranged to match manual's table of contents. For each product, list name, address, and telephone number of Installer or supplier and maintenance service agent, and cross-reference Specification Section number and title in Project Manual and drawing or schedule designation or identifier where applicable.

D. Manufacturers' Maintenance Documentation: Include the following information for each component part or piece of equipment:

1. Standard maintenance instructions and bulletins; include only sheets pertinent to product or component installed. Mark each sheet to identify each product or component incorporated into the Work. If data include more than one item in a tabular format, identify each item using appropriate references from the Contract Documents. Identify data applicable to the Work and delete references to information not applicable.

a. Prepare supplementary text if manufacturers' standard printed data are not available and where the information is necessary for proper operation and maintenance of equipment or systems.

2. Drawings, diagrams, and instructions required for maintenance, including disassembly and component removal, replacement, and assembly.

3. Identification and nomenclature of parts and components. 4. List of items recommended to be stocked as spare parts.

E. Maintenance Procedures: Include the following information and items that detail essential maintenance procedures:

1. Test and inspection instructions. 2. Troubleshooting guide. 3. Precautions against improper maintenance. 4. Disassembly; component removal, repair, and replacement; and reassembly

instructions. 5. Aligning, adjusting, and checking instructions. 6. Demonstration and training video recording, if available.

F. Maintenance and Service Schedules: Include service and lubrication requirements, list of required lubricants for equipment, and separate schedules for preventive and routine maintenance and service with standard time allotment.

Page 43: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

OPERATION AND MAINTENANCE DATA 017823 - 7

1. Scheduled Maintenance and Service: Tabulate actions for daily, weekly, monthly, quarterly, semiannual, and annual frequencies.

2. Maintenance and Service Record: Include manufacturers' forms for recording maintenance.

G. Spare Parts List and Source Information: Include lists of replacement and repair parts, with parts identified and cross-referenced to manufacturers' maintenance documentation and local sources of maintenance materials and related services.

H. Maintenance Service Contracts: Include copies of maintenance agreements with name and telephone number of service agent.

I. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and conditions that would affect validity of warranties or bonds.

1. Include procedures to follow and required notifications for warranty claims.

J. Drawings: Prepare drawings supplementing manufacturers' printed data to illustrate the relationship of component parts of equipment and systems and to illustrate control sequence and flow diagrams. Coordinate these drawings with information contained in record Drawings to ensure correct illustration of completed installation.

1. Do not use original project record documents as part of maintenance manuals.

1.11 PRODUCT MAINTENANCE MANUALS

A. Product Maintenance Manual: Assemble a complete set of maintenance data indicating care and maintenance of each product, material, and finish incorporated into the Work.

B. Content: Organize manual into a separate section for each product, material, and finish. Include source information, product information, maintenance procedures, repair materials and sources, and warranties and bonds, as described below.

C. Source Information: List each product included in manual, identified by product name and arranged to match manual's table of contents. For each product, list name, address, and telephone number of Installer or supplier and maintenance service agent, and cross-reference Specification Section number and title in Project Manual and drawing or schedule designation or identifier where applicable.

D. Product Information: Include the following, as applicable:

1. Product name and model number. 2. Manufacturer's name. 3. Color, pattern, and texture. 4. Material and chemical composition. 5. Reordering information for specially manufactured products.

E. Maintenance Procedures: Include manufacturer's written recommendations and the following:

Page 44: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

OPERATION AND MAINTENANCE DATA 017823 - 8

1. Inspection procedures. 2. Types of cleaning agents to be used and methods of cleaning. 3. List of cleaning agents and methods of cleaning detrimental to product. 4. Schedule for routine cleaning and maintenance. 5. Repair instructions.

F. Repair Materials and Sources: Include lists of materials and local sources of materials and related services.

G. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and conditions that would affect validity of warranties or bonds.

1. Include procedures to follow and required notifications for warranty claims.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 017823

Page 45: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

PROJECT RECORD DOCUMENTS 017839 - 1

SECTION 017839 - PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for project record documents, including the following:

1. Record Drawings. 2. Record Specifications. 3. Record Product Data. 4. Miscellaneous record submittals.

B. Related Requirements: 1. Section 017300 "Execution" for final property survey. 2. Section 017700 "Closeout Procedures" for general closeout procedures. 3. Section 017823 "Operation and Maintenance Data" for operation and maintenance

manual requirements.

1.3 CLOSEOUT SUBMITTALS

A. Record Drawings: Comply with the following:

1. Number of Copies: Submit one set(s) of marked-up record prints. 2. Number of Copies: Submit copies of record Drawings as follows:

a. Initial Submittal:

1) Submit one paper-copy set(s) of marked-up record prints. 2) Engineer will indicate whether general scope of changes, additional

information recorded, and quality of drafting are acceptable.

b. Final Submittal:

1) Submit three paper-copy set(s) of marked-up record prints. 2) Print each drawing, whether or not changes and additional information

were recorded.

Page 46: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

PROJECT RECORD DOCUMENTS 017839 - 2

B. Record Specifications: Submit one paper copy of Project's Specifications, including addenda and contract modifications.

C. Record Product Data: Submit one paper copy of each submittal.

1. Where record Product Data are required as part of operation and maintenance manuals, submit duplicate marked-up Product Data as a component of manual.

D. Miscellaneous Record Submittals: See other Specification Sections for miscellaneous record-keeping requirements and submittals in connection with various construction activities. Submit one paper copy of each submittal.

1.4 RECORD DRAWINGS

A. Record Prints: Maintain one set of marked-up paper copies of the Contract Drawings and Shop Drawings, incorporating new and revised drawings as modifications are issued.

1. Preparation: Mark record prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to provide information for preparation of corresponding marked-up record prints.

a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.

b. Accurately record information in an acceptable drawing technique. c. Record data as soon as possible after obtaining it. d. Record and check the markup before enclosing concealed installations. e. Cross-reference record prints to corresponding photographic documentation.

2. Content: Types of items requiring marking include, but are not limited to, the following:

a. Dimensional changes to Drawings. b. Revisions to details shown on Drawings. c. Locations and depths of underground utilities. d. Revisions to routing of piping and conduits. e. Revisions to electrical circuitry. f. Actual equipment locations. g. Duct size and routing. h. Locations of concealed internal utilities. i. Changes made by Change Order. j. Changes made following Engineer’s written orders. k. Details not on the original Contract Drawings. l. Field records for variable and concealed conditions. m. Record information on the Work that is shown only schematically.

3. Mark the Contract Drawings and Shop Drawings completely and accurately. Use personnel proficient at recording graphic information in production of marked-up record prints.

Page 47: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

PROJECT RECORD DOCUMENTS 017839 - 3

4. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.

5. Mark important additional information that was either shown schematically or omitted from original Drawings.

6. Note Construction Change Directive numbers, alternate numbers, Change Order numbers, and similar identification, where applicable.

B. Record Digital Data Files: Immediately before inspection for Certificate of Substantial Completion, review marked-up record prints with Engineer. When authorized, prepare a full set of corrected digital data files of the Contract Drawings, as follows:

1. Format: Same digital data software program, version, and operating system as the original Contract Drawings.

2. Format: DWG, Version 2006, Microsoft Windows operating system. 3. Format: Annotated PDF electronic file. 4. Incorporate changes and additional information previously marked on record prints.

Delete, redraw, and add details and notations where applicable. 5. Refer instances of uncertainty to Engineer for resolution. 6. Engineer will furnish Contractor with one set of digital data files of the Contract

Drawings for use in recording information.

a. See Section 013100 "Project Management and Coordination" for requirements related to use of Architect's digital data files.

b. Architect will provide data file layer information. Record markups in separate layers.

C. Format: Identify and date each record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location.

1. Record Prints: Organize record prints into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.

2. Format: Annotated PDF electronic file. 3. Record Digital Data Files: Organize digital data information into separate electronic files

that correspond to each sheet of the Contract Drawings. Name each file with the sheet identification. Include identification in each digital data file.

4. Identification: As follows:

a. Project name. b. Date. c. Designation "PROJECT RECORD DRAWINGS." d. Name of Engineer. e. Name of Contractor.

1.5 RECORD SPECIFICATIONS

A. Preparation: Mark Specifications to indicate the actual product installation where installation varies from that indicated in Specifications, addenda, and contract modifications.

Page 48: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

PROJECT RECORD DOCUMENTS 017839 - 4

1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2. Mark copy with the proprietary name and model number of products, materials, and equipment furnished, including substitutions and product options selected.

3. Record the name of manufacturer, supplier, Installer, and other information necessary to provide a record of selections made.

4. For each principal product, indicate whether record Product Data has been submitted in operation and maintenance manuals instead of submitted as record Product Data.

5. Note related Change Orders and record Drawings where applicable.

B. Format: Submit record Specifications as annotated PDF electronic file.

1.6 RECORD PRODUCT DATA

A. Recording: Maintain one copy of each submittal during the construction period for project record document purposes. Post changes and revisions to project record documents as they occur; do not wait until end of Project.

B. Preparation: Mark Product Data to indicate the actual product installation where installation varies substantially from that indicated in Product Data submittal.

1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2. Include significant changes in the product delivered to Project site and changes in manufacturer's written instructions for installation.

3. Note related Change Orders, record Specifications, and record Drawings where applicable.

C. Format: Submit record Product Data as annotated PDF electronic file.

1. Include record Product Data directory organized by Specification Section number and title, electronically linked to each item of record Product Data.

1.7 MISCELLANEOUS RECORD SUBMITTALS

A. Assemble miscellaneous records required by other Specification Sections for miscellaneous record keeping and submittal in connection with actual performance of the Work. Bind or file miscellaneous records and identify each, ready for continued use and reference.

B. Format: Submit miscellaneous record submittals as PDF electronic file.

1. Include miscellaneous record submittals directory organized by Specification Section number and title, electronically linked to each item of miscellaneous record submittals.

Page 49: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

PROJECT RECORD DOCUMENTS 017839 - 5

1.8 MAINTENANCE OF RECORD DOCUMENTS

A. Maintenance of Record Documents: Store record documents in the field office apart from the Contract Documents used for construction. Do not use project record documents for construction purposes. Maintain record documents in good order and in a clean, dry, legible condition, protected from deterioration and loss. Provide access to project record documents for Engineer’s reference during normal working hours.

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 017839

Page 50: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART
Page 51: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

DEMONSTRATION AND TRAINING 017900 - 1

SECTION 017900 - DEMONSTRATION AND TRAINING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for instructing Owner's personnel, including the following:

1. Instruction in operation and maintenance of systems, subsystems, and equipment. 2. Demonstration and training video recordings.

1.3 INFORMATIONAL SUBMITTALS

A. Instruction Program: Submit outline of instructional program for demonstration and training, including a list of training modules and a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module. Include learning objective and outline for each training module.

B. Qualification Data: For instructor.

C. Attendance Record: For each training module, submit list of participants and length of instruction time.

1.4 QUALITY ASSURANCE

A. Instructor Qualifications: A factory-authorized service representative experienced in operation and maintenance procedures and training.

B. Preinstruction Conference: Conduct conference at Project site to comply with requirements in Section 013100 "Project Management and Coordination." Review methods and procedures related to demonstration and training including, but not limited to, the following:

1. Inspect and discuss locations and other facilities required for instruction. 2. Review and finalize instruction schedule and verify availability of educational materials,

instructors' personnel, audiovisual equipment, and facilities needed to avoid delays. 3. Review required content of instruction. 4. For instruction that must occur outside, review weather and forecasted weather

conditions and procedures to follow if conditions are unfavorable.

Page 52: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

DEMONSTRATION AND TRAINING 017900 - 2

1.5 COORDINATION

A. Coordinate instruction schedule with Owner's operations. Adjust schedule as required to minimize disrupting Owner's operations and to ensure availability of Owner's personnel.

B. Coordinate instructors, including providing notification of dates, times, length of instruction time, and course content.

C. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction program until operation and maintenance data have been reviewed and approved by Architect.

1.6 INSTRUCTION PROGRAM

A. Program Structure: Develop an instruction program that includes individual training modules for each system and for equipment not part of a system, as required by individual Specification Sections.

B. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participant is expected to master. For each module, include instruction for the following as applicable to the system, equipment, or component:

1. Basis of System Design, Operational Requirements, and Criteria: Include the following:

a. System, subsystem, and equipment descriptions. b. Performance and design criteria if Contractor is delegated design responsibility. c. Operating standards. d. Regulatory requirements. e. Equipment function. f. Operating characteristics. g. Limiting conditions. h. Performance curves.

2. Documentation: Review the following items in detail:

a. Emergency manuals. b. Systems and equipment operation manuals. c. Systems and equipment maintenance manuals. d. Product maintenance manuals. e. Project Record Documents. f. Identification systems. g. Warranties and bonds. h. Maintenance service agreements and similar continuing commitments.

3. Emergencies: Include the following, as applicable:

a. Instructions on meaning of warnings, trouble indications, and error messages.

Page 53: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

DEMONSTRATION AND TRAINING 017900 - 3

b. Instructions on stopping. c. Shutdown instructions for each type of emergency. d. Operating instructions for conditions outside of normal operating limits. e. Sequences for electric or electronic systems. f. Special operating instructions and procedures.

4. Operations: Include the following, as applicable:

a. Startup procedures. b. Equipment or system break-in procedures. c. Routine and normal operating instructions. d. Regulation and control procedures. e. Control sequences. f. Safety procedures. g. Instructions on stopping. h. Normal shutdown instructions. i. Operating procedures for emergencies. j. Operating procedures for system, subsystem, or equipment failure. k. Seasonal and weekend operating instructions. l. Required sequences for electric or electronic systems. m. Special operating instructions and procedures.

5. Adjustments: Include the following:

a. Alignments. b. Checking adjustments. c. Noise and vibration adjustments. d. Economy and efficiency adjustments.

6. Troubleshooting: Include the following:

a. Diagnostic instructions. b. Test and inspection procedures.

7. Maintenance: Include the following:

a. Inspection procedures. b. Types of cleaning agents to be used and methods of cleaning. c. List of cleaning agents and methods of cleaning detrimental to product. d. Procedures for routine cleaning. e. Procedures for preventive maintenance. f. Procedures for routine maintenance. g. Instruction on use of special tools.

8. Repairs: Include the following:

a. Diagnosis instructions. b. Repair instructions.

Page 54: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

DEMONSTRATION AND TRAINING 017900 - 4

c. Disassembly; component removal, repair, and replacement; and reassembly instructions.

d. Instructions for identifying parts and components. e. Review of spare parts needed for operation and maintenance.

1.7 PREPARATION

A. Assemble educational materials necessary for instruction, including documentation and training module. Assemble training modules into a training manual organized in coordination with requirements in Section 017823 "Operation and Maintenance Data."

B. Set up instructional equipment at instruction location.

1.8 INSTRUCTION

A. Engage qualified instructors to instruct Owner's personnel to adjust, operate, and maintain systems, subsystems, and equipment not part of a system. 1. Owner will furnish Contractor with names and positions of participants.

B. Scheduling: Provide instruction at mutually agreed-on times. For equipment that requires seasonal operation, provide similar instruction at start of each season.

1. Schedule training with Owner with at least seven days' advance notice.

C. Training Location and Reference Material: Conduct training on-site in the completed and fully operational facility using the actual equipment in-place. Conduct training using final operation and maintenance data submittals.

D. Cleanup: Collect used and leftover educational materials and give to Owner. Remove instructional equipment. Restore systems and equipment to condition existing before initial training use.

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 017900

Page 55: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SELECTIVE DEMOLITION 024119 - 1

SECTION 024119 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Demolition and removal of selected portions of building or structure. 2. Salvage of existing items to be reused or recycled.

B. Related Requirements:

1. Section 011000 "Summary" for restrictions on use of the premises, Owner-occupancy requirements, and phasing requirements.

2. Section 017300 "Execution" for cutting and patching procedures.

1.3 DEFINITIONS

A. Remove: Detach items from existing construction and dispose of them off-site unless indicated to be salvaged or reinstalled.

B. Remove and Salvage: Detach items from existing construction, in a manner to prevent damage, and store.

C. Remove and Reinstall: Detach items from existing construction, in a manner to prevent damage, prepare for reuse, and reinstall where indicated.

D. Existing to Remain: Leave existing items that are not to be removed and that are not otherwise indicated to be salvaged or reinstalled.

E. Dismantle: To remove by disassembling or detaching an item from a surface, using gentle methods and equipment to prevent damage to the item and surfaces; disposing of items unless indicated to be salvaged or reinstalled.

1.4 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

Page 56: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SELECTIVE DEMOLITION 024119 - 2

B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.

1. Carefully salvage in a manner to prevent damage and promptly return to Owner.

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For refrigerant recovery technician.

B. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property, for environmental protection, for dust control and, for noise control. Indicate proposed locations and construction of barriers.

C. Schedule of Selective Demolition Activities: Indicate the following:

1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity. Ensure Owner's building manager's and other tenants' on-site operations are uninterrupted.

2. Interruption of utility services. Indicate how long utility services will be interrupted. 3. Coordination for shutoff, capping, and continuation of utility services. 4. Use of elevator and stairs. 5. Coordination of Owner's continuing occupancy of portions of existing building and of

Owner's partial occupancy of completed Work.

D. Statement of Refrigerant Recovery: Signed by refrigerant recovery technician responsible for recovering refrigerant, stating that all refrigerant that was present was recovered and that recovery was performed according to EPA regulations. Include name and address of technician and date refrigerant was recovered.

1.6 QUALITY ASSURANCE

A. Refrigerant Recovery Technician Qualifications: Certified by an EPA-approved certification program.

1.7 FIELD CONDITIONS

A. Owner will occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted.

B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.

C. Notify Engineer of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

Page 57: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SELECTIVE DEMOLITION 024119 - 3

D. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work. 1. If suspected hazardous materials are encountered, do not disturb; immediately notify

Architect and Owner. Hazardous materials will be removed by Owner under a separate contract.

E. Storage or sale of removed items or materials on-site is not permitted.

F. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain fire-protection facilities in service during selective demolition operations.

1.8 COORDINATION

A. Arrange selective demolition schedule so as not to interfere with Owner's operations.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ASSE A10.6 and NFPA 241.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations.

B. Review Project Record Documents of existing construction or other existing condition and hazardous material information provided by Owner. Owner does not guarantee that existing conditions are same as those indicated in Project Record Documents.

C. Survey Existing Conditions and correlate with requirements indicated to determine the extent of selective demolition required.

Page 58: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SELECTIVE DEMOLITION 024119 - 4

3.2 PREPARATION

A. Refrigerant: Before starting demolition, remove refrigerant from mechanical equipment according to 40 CFR 82 and regulations of authorities having jurisdiction.

3.3 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.

B. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off utility services and mechanical/electrical systems serving areas to be selectively demolished.

1. Owner will arrange to shut off indicated services/systems when requested by Contractor.

2. Arrange to shut off utilities with utility companies. 3. If services/systems are required to be removed, relocated, or abandoned, provide

temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.

4. Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC systems, equipment, and components indicated on Drawings to be removed.

a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material.

b. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same or compatible piping material and leave in place.

c. Equipment to Be Removed: Disconnect and cap services and remove equipment. d. Equipment to Be Removed and Reinstalled: Disconnect and cap services and

remove, clean, and store equipment; when appropriate, reinstall, reconnect, and make equipment operational.

e. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove equipment and deliver to Owner.

f. Ducts to Be Removed: Remove portion of ducts indicated to be removed and plug remaining ducts with same or compatible ductwork material.

g. Ducts to Be Abandoned in Place: Cap or plug ducts with same or compatible ductwork material and leave in place.

3.4 PROTECTION

A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

1. Provide protection to ensure safe passage of people around selective demolition area and to and from occupied portions of building.

Page 59: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SELECTIVE DEMOLITION 024119 - 5

3.5 SELECTIVE DEMOLITION, GENERAL

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Proceed with selective demolition systematically, from higher to lower level. Complete selective demolition operations above each floor or tier before disturbing supporting members on the next lower level.

2. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping. Temporarily cover openings to remain.

3. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

4. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.

5. Maintain fire watch during and for at least four hours after flame-cutting operations. 6. Maintain adequate ventilation when using cutting torches. 7. Remove decayed, vermin-infested, or otherwise dangerous or unsuitable materials and

promptly dispose of off-site. 8. Remove structural framing members and lower to ground by method suitable to avoid

free fall and to prevent ground impact or dust generation. 9. Locate selective demolition equipment and remove debris and materials so as not to

impose excessive loads on supporting walls, floors, or framing. 10. Dispose of demolished items and materials promptly.

B. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

C. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse. 2. Pack or crate items after cleaning and repairing. Identify contents of containers. 3. Protect items from damage during transport and storage. 4. Reinstall items in locations indicated. Comply with installation requirements for new

materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

D. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Engineer, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.

Page 60: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SELECTIVE DEMOLITION 024119 - 6

3.6 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS

A. Concrete: Demolish in small sections. Using power-driven saw, cut concrete to a depth of at least 3/4 inch at junctures with construction to remain. Dislodge concrete from reinforcement at perimeter of areas being demolished, cut reinforcement, and then remove remainder of concrete. Neatly trim openings to dimensions indicated.

B. Concrete: Demolish in sections. Cut concrete full depth at junctures with construction to remain and at regular intervals using power-driven saw, and then remove concrete between saw cuts.

C. Masonry: Demolish in small sections. Cut masonry at junctures with construction to remain, using power-driven saw, and then remove masonry between saw cuts.

D. Concrete Slabs-on-Grade: Saw-cut perimeter of area to be demolished, and then break up and remove.

E. Roofing: Remove no more existing roofing than what can be covered in one day by new roofing and so that building interior remains watertight and weathertight.

3.7 DISPOSAL OF DEMOLISHED MATERIALS

A. Remove demolition waste materials from Project site.

1. Do not allow demolished materials to accumulate on-site. 2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces

and areas. 3. Remove debris from elevated portions of building by chute, hoist, or other device that

will convey debris to grade level in a controlled descent.

B. Burning: Do not burn demolished materials.

3.8 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

END OF SECTION 024119

Page 61: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 260519 - 1

SECTION 260519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Copper building wire rated 600 V or less. 2. Connectors, splices, and terminations rated 600 V and less.

1.3 DEFINITIONS

A. RoHS: Restriction of Hazardous Substances.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product.

1.5 INFORMATIONAL SUBMITTALS

A. Field quality-control reports.

1.6 QUALITY ASSURANCE

A. Testing Agency Qualifications: Member company of NETA.

1. Testing Agency's Field Supervisor: Certified by NETA to supervise on-site testing.

PART 2 - PRODUCTS

2.1 COPPER BUILDING WIRE

A. Description: Flexible, insulated and uninsulated, drawn copper current-carrying conductor with an overall insulation layer or jacket, or both, rated 600 V or less.

Page 62: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 260519 - 2

B. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

1. Cerro Wire LLC. 2. Encore Wire Corporation. 3. Southwire Company.

C. Standards:

1. Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and use.

2. RoHS compliant. 3. Conductor and Cable Marking: Comply with wire and cable marking according to UL's

"Wire and Cable Marking and Application Guide."

D. Conductors: Copper, complying with ASTM B 3 for bare annealed copper and with ASTM B 8 for stranded conductors.

E. Conductor Insulation:

1. Type THHN and Type THWN-2: Comply with UL 83.

2.2 CONNECTORS AND SPLICES

A. Description: Factory-fabricated connectors and splices of size, ampacity rating, material, type, and class for application and service indicated; listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and use.

B. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

1. 3M Electrical Products. 2. AFC Cable Systems; a part of Atkore International. 3. Hubbell Power Systems, Inc. 4. Ideal Industries, Inc. 5. ILSCO. 6. NSi Industries LLC. 7. O-Z/Gedney; a brand of Emerson Industrial Automation.

PART 3 - EXECUTION

3.1 CONDUCTOR MATERIAL APPLICATIONS

A. Feeders: Copper; solid for No. 10 AWG and smaller; stranded for No. 8 AWG and larger.

B. Branch Circuits: Copper. Solid for No. 10 AWG and smaller; stranded for No. 8 AWG and larger.

Page 63: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 260519 - 3

C. Power-Limited Fire Alarm and Control: Solid for No. 12 AWG and smaller.

3.2 CONDUCTOR INSULATION AND MULTICONDUCTOR CABLE APPLICATIONS AND WIRING METHODS

A. Exposed Branch Circuits, Including in Crawlspaces: Type THHN/THWN-2, single conductors in raceway.

B. Branch Circuits Concealed in Ceilings, Walls, and Partitions: Type THHN/THWN-2, single conductors in raceway.

3.3 INSTALLATION OF CONDUCTORS AND CABLES

A. Complete raceway installation between conductor and cable termination points according to Section 260533 "Raceways and Boxes for Electrical Systems" prior to pulling conductors and cables.

B. Use manufacturer-approved pulling compound or lubricant where necessary; compound used must not deteriorate conductor or insulation. Do not exceed manufacturer's recommended maximum pulling tensions and sidewall pressure values.

C. Use pulling means, including fish tape, cable, rope, and basket-weave wire/cable grips, that will not damage cables or raceway.

D. Install exposed cables parallel and perpendicular to surfaces of exposed structural members, and follow surface contours where possible.

E. Support cables according to Section 260529 "Hangers and Supports for Electrical Systems."

3.4 CONNECTIONS

A. Tighten electrical connectors and terminals according to manufacturer's published torque-tightening values. If manufacturer's torque values are not indicated, use those specified in UL 486A-486B.

B. Make splices, terminations, and taps that are compatible with conductor material and that possess equivalent or better mechanical strength and insulation ratings than unspliced conductors.

3.5 IDENTIFICATION

A. Identify and color-code conductors and cables according to Section 260553 "Identification for Electrical Systems."

B. Identify each spare conductor at each end with identity number and location of other end of conductor, and identify as spare conductor.

Page 64: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 260519 - 4

3.6 SLEEVE AND SLEEVE-SEAL INSTALLATION FOR ELECTRICAL PENETRATIONS

A. Install sleeves and sleeve seals at penetrations of exterior floor and wall assemblies. Comply with requirements in Section 260544 "Sleeves and Sleeve Seals for Electrical Raceways and Cabling."

3.7 FIELD QUALITY CONTROL

A. Perform tests and inspections.

1. Perform each of the following visual and electrical tests:

a. Inspect exposed sections of conductor and cable for physical damage and correct connection according to the single-line diagram.

b. Test bolted connections for high resistance using one of the following:

1) A low-resistance ohmmeter. 2) Calibrated torque wrench. 3) Thermographic survey.

c. Inspect compression-applied connectors for correct cable match and indentation. d. Inspect for correct identification. e. Continuity test on each conductor and cable.

B. Cables will be considered defective if they do not pass tests and inspections.

C. Prepare test and inspection reports to record the following:

1. Procedures used. 2. Results that comply with requirements. 3. Results that do not comply with requirements, and corrective action taken to achieve

compliance with requirements.

END OF SECTION 260519

Page 65: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526 - 1

SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes grounding and bonding systems and equipment.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

1.4 INFORMATIONAL SUBMITTALS

A. Field quality-control reports.

1.5 QUALITY ASSURANCE

A. Testing Agency Qualifications: Certified by NETA.

PART 2 - PRODUCTS

2.1 SYSTEM DESCRIPTION

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Comply with UL 467 for grounding and bonding materials and equipment.

2.2 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

1. Burndy; Part of Hubbell Electrical Systems. 2. ERICO International Corporation.

Page 66: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526 - 2

3. ILSCO. 4. O-Z/Gedney; a brand of Emerson Industrial Automation.

2.3 CONDUCTORS

A. Insulated Conductors: Copper or tinned-copper wire or cable insulated for 600 V unless otherwise required by applicable Code or authorities having jurisdiction.

B. Bare Copper Conductors:

1. Solid Conductors: ASTM B 3. 2. Stranded Conductors: ASTM B 8. 3. Tinned Conductors: ASTM B 33. 4. Bonding Cable: 28 kcmil, 14 strands of No. 17 AWG conductor, 1/4 inch in diameter. 5. Bonding Conductor: No. 4 or No. 6 AWG, stranded conductor. 6. Bonding Jumper: Copper tape, braided conductors terminated with copper ferrules; 1-

5/8 inches wide and 1/16 inch thick.

2.4 CONNECTORS

A. Listed and labeled by an NRTL acceptable to authorities having jurisdiction for applications in which used and for specific types, sizes, and combinations of conductors and other items connected.

B. Beam Clamps: Mechanical type, terminal, ground wire access from four directions, with dual, tin-plated or silicon bronze bolts.

C. Cable-to-Cable Connectors: Compression type, copper or copper alloy.

D. Conduit Hubs: Mechanical type, terminal with threaded hub.

PART 3 - EXECUTION

3.1 APPLICATIONS

A. Conductors: Install solid conductor for No. 8 AWG and smaller, and stranded conductors for No. 6 AWG and larger unless otherwise indicated.

3.2 EQUIPMENT GROUNDING

A. Install insulated equipment grounding conductors with all feeders and branch circuits.

B. Air-Duct Equipment Circuits: Install insulated equipment grounding conductor to duct-mounted electrical devices operating at 120 V and more, including air cleaners, heaters,

Page 67: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526 - 3

dampers, humidifiers, and other duct electrical equipment. Bond conductor to each unit and to air duct and connected metallic piping.

3.3 INSTALLATION

A. Grounding Conductors: Route along shortest and straightest paths possible unless otherwise indicated or required by Code. Avoid obstructing access or placing conductors where they may be subjected to strain, impact, or damage.

B. Bonding Interior Metal Ducts: Bond metal air ducts to equipment grounding conductors of associated fans, blowers, electric heaters, and air cleaners. Install bonding jumper to bond across flexible duct connections to achieve continuity.

3.4 FIELD QUALITY CONTROL

A. Perform tests and inspections.

B. Tests and Inspections:

1. After installing grounding system but before permanent electrical circuits have been energized, test for compliance with requirements.

2. Inspect physical and mechanical condition. Verify tightness of accessible, bolted, electrical connections with a calibrated torque wrench according to manufacturer's written instructions.

C. Grounding system will be considered defective if it does not pass tests and inspections.

D. Prepare test and inspection reports.

E. Report measured ground resistances that exceed the following values:

1. Power and Lighting Equipment or System with Capacity of 500 kVA and Less: 10 ohms. 2. Power and Lighting Equipment or System with Capacity of 500 to 1000 kVA: 5 ohms. 3. Power and Lighting Equipment or System with Capacity More Than 1000 kVA: 3 ohms.

F. Excessive Ground Resistance: If resistance to ground exceeds specified values, notify Architect promptly and include recommendations to reduce ground resistance.

END OF SECTION 260526

Page 68: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART
Page 69: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE    RICHMOND MAIN LIBRARY   

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS  260529 ‐ 1

SECTION 260529 ‐ HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 

PART 1 ‐ GENERAL 

1.1 RELATED DOCUMENTS 

A. Drawings and general provisions of the Contract, including General Conditions and Division 01 Specification Sections, apply to this Section. 

1.2 SUMMARY 

A. Section Includes: 

1. Conduit and cable support devices. 2. Mounting,  anchoring,  and  attachment  components,  including  powder‐actuated 

fasteners, mechanical expansion anchors, concrete inserts, clamps, through bolts, toggle bolts, and hanger rods. 

PART 2 ‐ PRODUCTS 

2.1 PERFORMANCE REQUIREMENTS 

A. Surface‐Burning Characteristics: Comply with ASTM E 84; testing by a qualified testing agency. Identify products with appropriate markings of applicable testing agency. 

1. Flame Rating: Class 1. 2. Self‐extinguishing according to ASTM D 635. 

2.2 SUPPORT, ANCHORAGE, AND ATTACHMENT COMPONENTS 

A. Conduit and Cable Support Devices:   Steel hangers, clamps, and associated  fittings, designed for types and sizes of raceway or cable to be supported. 

B. Mounting,  Anchoring,  and  Attachment  Components:  Items  for  fastening  electrical  items  or their supports to building surfaces include the following: 

1. Powder‐Actuated Fasteners: Threaded‐steel stud, for use  in hardened portland cement concrete,  steel,  or wood, with  tension,  shear,  and  pullout  capacities  appropriate  for supported loads and building materials where used. 

2. Mechanical‐Expansion  Anchors:  Insert‐wedge‐type,  zinc‐coated  steel,  for  use  in hardened  portland  cement  concrete,  with  tension,  shear,  and  pullout  capacities appropriate for supported loads and building materials where used. 

Page 70: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE    RICHMOND MAIN LIBRARY   

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS  260529 ‐ 2

3. Concrete  Inserts:  Steel  or malleable‐iron,  slotted  support  system  units  are  similar  to MSS Type 18 units and comply with MFMA‐4 or MSS SP‐58. 

4. Clamps  for Attachment  to  Steel  Structural Elements: MSS SP‐58 units  are  suitable  for attached structural element. 

5. Through Bolts: Structural type, hex head, and high strength. Comply with ASTM A 325. 6. Toggle Bolts:  All‐steel springhead type. 7. Hanger Rods: Threaded steel. 

PART 3 ‐ EXECUTION 

3.1 APPLICATION 

A. Comply with the following standards for application and  installation requirements of hangers and supports, except where requirements on Drawings or in this Section are stricter: 

1. NECA 1. 2. NECA 101 3. NECA 102. 

B. Comply with requirements for raceways and boxes specified in Section 260533 "Raceways and Boxes for Electrical Systems." 

C. Maximum Support Spacing and Minimum Hanger Rod Size  for Raceways: Space supports  for EMT and RMC as required by NFPA 70. Minimum rod size shall be 1/4 inch in diameter. 

D. Spring‐steel clamps designed for supporting single conduits without bolts may be used for 1‐1/2‐inch  and  smaller  raceways  serving  branch  circuits  and  communication  systems  above suspended ceilings, and for fastening raceways to trapeze supports. 

3.2 SUPPORT INSTALLATION 

A. Comply with NECA 1  and NECA 101  for  installation  requirements  except  as  specified  in  this article. 

B. Strength of Support Assemblies: Where not  indicated, select sizes of components so strength will  be  adequate  to  carry  present  and  future  static  loads  within  specified  loading  limits. Minimum  static  design  load  used  for  strength  determination  shall  be weight  of  supported components plus 200 lb. 

C. Mounting and Anchorage of Surface‐Mounted Equipment and Components: Anchor and fasten electrical  items and  their supports  to building structural elements by  the  following methods unless otherwise indicated by code: 

1. To Wood: Fasten with lag screws or through bolts. 2. To New Concrete: Bolt to concrete inserts. 

Page 71: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE    RICHMOND MAIN LIBRARY   

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS  260529 ‐ 3

3. To Masonry: Approved toggle‐type bolts on hollow masonry units and expansion anchor fasteners on solid masonry units. 

4. To Existing Concrete: Expansion anchor fasteners. 5. Instead  of  expansion  anchors,  powder‐actuated  driven  threaded  studs  provided with 

lock washers and nuts may be used in existing standard‐weight concrete 4  inches thick or greater. Do not use for anchorage to lightweight‐aggregate concrete or for slabs less than 4 inches thick. 

6. To Steel:  Beam clamps (MSS SP‐58, Type 19, 21, 23, 25, or 27), complying with MSS SP‐69. 

7. To Light Steel: Sheet metal screws. 8. Items Mounted on Hollow Walls and Nonstructural Building Surfaces: Mount cabinets, 

panelboards,  disconnect  switches,  control  enclosures,  pull  and  junction  boxes, transformers, and other devices on slotted‐channel racks attached to substrate. 

D. Drill holes for expansion anchors in concrete at locations and to depths that avoid the need for reinforcing bars. 

3.3 PAINTING 

A. Touchup: Clean field welds and abraded areas of shop paint. Paint exposed areas immediately after erecting hangers and  supports. Use  same materials as used  for  shop painting. Comply with SSPC‐PA 1 requirements for touching up field‐painted surfaces. 

1. Apply paint by brush or spray to provide minimum dry film thickness of 2.0 mils. 

B. Galvanized  Surfaces:  Clean  welds,  bolted  connections,  and  abraded  areas  and  apply galvanizing‐repair paint to comply with ASTM A 780. 

END OF SECTION 260529 

Page 72: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART
Page 73: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE    RICHMOND MAIN LIBRARY   

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS  260533 ‐ 1

SECTION 260533 ‐ RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 

PART 1 ‐ GENERAL 

1.1 RELATED DOCUMENTS 

A. Drawings and general provisions of the Contract, including General Conditions and Division 01 Specification Sections, apply to this Section. 

1.2 SUMMARY 

A. Section Includes: 

1. Metal conduits, tubing, and fittings. 2. Boxes. 

1.3 DEFINITIONS 

A. GRC: Galvanized rigid steel conduit. 

1.4 INFORMATIONAL SUBMITTALS 

A. Source quality‐control reports. 

PART 2 ‐ PRODUCTS 

2.1 METAL CONDUITS, TUBING, AND FITTINGS 

A. Manufacturers:  Subject  to  compliance with  requirements,  available manufacturers  offering products that may be incorporated into the Work include, but are not limited to the following: 

1. AFC Cable Systems; a part of Atkore International. 2. Allied Tube & Conduit; a part of Atkore International. 3. Electri‐Flex Company. 4. O‐Z/Gedney; a brand of Emerson Industrial Automation. 5. Western Tube and Conduit Corporation. 6. Wheatland Tube Company. 

B. Listing and Labeling: Metal conduits, tubing, and fittings shall be listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application. 

C. GRC: Comply with ANSI C80.1 and UL 6. 

Page 74: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE    RICHMOND MAIN LIBRARY   

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS  260533 ‐ 2

D. EMT: Comply with ANSI C80.3 and UL 797. 

E. FMC: Comply with UL 1; zinc‐coated steel. 

F. LFMC: Flexible steel conduit with PVC jacket and complying with UL 360. 

G. Fittings for Metal Conduit: Comply with NEMA FB 1 and UL 514B. 1. Fittings for EMT: 

a. Material:  Steel or die cast. b. Type:  Setscrew or compression. 

2. Expansion Fittings: PVC or steel to match conduit type, complying with UL 651, rated for environmental  conditions  where  installed,  and  including  flexible  external  bonding jumper. 

H. Joint Compound for GRC: Approved, as defined  in NFPA 70, by authorities having  jurisdiction for  use  in  conduit  assemblies,  and  compounded  for  use  to  lubricate  and  protect  threaded conduit joints from corrosion and to enhance their conductivity. 

2.2 BOXES 

A. Manufacturers:  Subject  to  compliance with  requirements,  available manufacturers  offering products that may be incorporated into the Work include, but are not limited to the following: 

1. Crouse‐Hinds, an Eaton business. 2. RACO; Hubbell. 3. Thomas & Betts Corporation; A Member of the ABB Group. 

B. General Requirements for Boxes: Boxes installed in wet locations shall be listed for use in wet locations. 

C. Sheet Metal Outlet and Device Boxes: Comply with NEMA OS 1 and UL 514A. 

D. Cast‐Metal Outlet  and  Device  Boxes:  Comply with NEMA FB 1,  ferrous  alloy,  Type FD, with gasketed cover. 

E. Small Sheet Metal Pull and Junction Boxes: NEMA OS 1. 

F. Cast‐Metal Access, Pull, and Junction Boxes: Comply with NEMA FB 1 and UL 1773, galvanized, cast iron with gasketed cover. 

PART 3 ‐ EXECUTION 

3.1 RACEWAY APPLICATION 

A. Outdoors: Apply raceway products as specified below unless otherwise indicated: 

Page 75: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE    RICHMOND MAIN LIBRARY   

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS  260533 ‐ 3

1. Exposed Conduit:  GRC. 2. Connection  to Vibrating Equipment  (Including Transformers and Hydraulic, Pneumatic, 

Electric Solenoid, or Motor‐Driven Equipment):  LFMC. 3. Boxes and Enclosures, Aboveground: NEMA 250, Type 4. 

B. Indoors: Apply raceway products as specified below unless otherwise indicated: 

1. Exposed, Not Subject to Physical Damage:  EMT. 2. Exposed, Not Subject to Severe Physical Damage:  EMT. 3. Exposed and Subject  to Severe Physical Damage:   GRC. Raceway  locations  include  the 

following: 

a. Mechanical rooms. 

4. Concealed in Ceilings and Interior Walls and Partitions:  EMT. 5. Connection  to Vibrating Equipment  (Including Transformers and Hydraulic, Pneumatic, 

Electric Solenoid, or Motor‐Driven Equipment): FMC, except use LFMC  in damp or wet locations. 

6. Damp or Wet Locations:  GRC. 7. Boxes: NEMA 250, Type 1, except use NEMA 250, Type 4 stainless steel in damp or wet 

locations. 

C. Minimum Raceway Size:  3/4‐inch trade size. 

D. Raceway Fittings: Compatible with raceways and suitable for use and location. 

1. Rigid Steel Conduit: Use threaded rigid steel conduit fittings unless otherwise indicated. Comply with NEMA FB 2.10. 

2. EMT: Use setscrew or compression, steel fittings. Comply with NEMA FB 2.10. 3. Flexible  Conduit:  Use  only  fittings  listed  for  use  with  flexible  conduit.  Comply  with 

NEMA FB 2.20. 

3.2 INSTALLATION 

A. Comply with NECA 1 and NECA 101 for  installation requirements except where requirements on  Drawings  or  in  this  article  are  stricter.  Comply  with  NECA 102  for  aluminum  conduits. Comply with NFPA 70  limitations  for  types of  raceways  allowed  in  specific occupancies  and number of floors. 

B. Keep raceways at least 6 inches away from parallel runs of flues and steam or hot‐water pipes. Install horizontal raceway runs above water and steam piping. 

C. Complete raceway installation before starting conductor installation. 

D. Comply with requirements in Section 260529 "Hangers and Supports for Electrical Systems" for hangers and supports. 

Page 76: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE    RICHMOND MAIN LIBRARY   

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS  260533 ‐ 4

E. Conceal conduit and EMT within finished walls, ceilings, and floors unless otherwise indicated. Install conduits parallel or perpendicular to building lines. 

F. Support conduit within 12 inches of enclosures to which attached. 

G. Stub‐ups to Above Recessed Ceilings: 

1. Use EMT or RMC for raceways. 2. Use a conduit bushing or insulated fitting to terminate stub‐ups not terminated in hubs 

or in an enclosure. 

H. Threaded  Conduit  Joints,  Exposed  to Wet,  Damp,  Corrosive,  or  Outdoor  Conditions:  Apply listed compound to threads of raceway and fittings before making up joints. Follow compound manufacturer's written instructions. 

I. Raceway Terminations at Locations Subject to Moisture or Vibration: Use  insulating bushings to protect conductors including conductors smaller than No. 4 AWG. 

J. Terminate  threaded  conduits  into  threaded hubs or with  locknuts on  inside  and outside of boxes or cabinets. Install bushings on conduits up to 1‐1/4‐inch trade size and insulated throat metal bushings on 1‐1/2‐inch trade size and larger conduits terminated with locknuts.  

K. Install  raceways  square  to  the  enclosure  and  terminate  at  enclosures with  locknuts.  Install locknuts hand tight plus 1/4 turn more. 

L. Do not rely on locknuts to penetrate nonconductive coatings on enclosures. Remove coatings in  the  locknut area prior  to assembling conduit  to enclosure  to assure a  continuous ground path. 

M. Cut  conduit  perpendicular  to  the  length.  For  conduits  2‐inch  trade  size  and  larger,  use  roll cutter or a guide to make cut straight and perpendicular to the length. 

N. Install pull wires in empty raceways. Use polypropylene or monofilament plastic line with not less than 200‐lb tensile strength. Leave at least 12 inches of slack at each end of pull wire.  

O. Install raceway sealing fittings at accessible  locations according to NFPA 70 and fill them with listed sealing compound. For concealed raceways, install each fitting in a flush steel box with a blank cover plate having a finish similar to that of adjacent plates or surfaces. Install raceway sealing fittings according to NFPA 70. 

P. Install devices  to seal  raceway  interiors at accessible  locations. Locate seals so no  fittings or boxes are between the seal and the following changes of environments. Seal the interior of all raceways at the following points: 

1. Where conduits pass  from warm  to cold  locations,  such as boundaries of  refrigerated spaces. 

2. Where otherwise required by NFPA 70. 

Q. Comply with manufacturer's written instructions for solvent welding RNC and fittings. 

Page 77: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE    RICHMOND MAIN LIBRARY   

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS  260533 ‐ 5

R. Expansion‐Joint Fittings: 

1. Install  in  each  run  of  aboveground  RMC and  EMT  conduit  that  is  located  where environmental  temperature  change may  exceed  100  deg F  and  that  has  straight‐run length that exceeds 100 feet. 

2. Install  type  and quantity of  fittings  that  accommodate  temperature  change  listed  for each of the following locations: a. Outdoor Locations Exposed to Direct Sunlight:  155 deg F temperature change. 

3. Install  fitting(s)  that provide expansion and  contraction  for at  least 0.000078  inch per foot of length of straight run per deg F of temperature change for metal conduits. 

4. Install  expansion  fittings  at  all  locations  where  conduits  cross  building  or  structure expansion joints. 

5. Install each expansion‐joint fitting with position, mounting, and piston setting selected according  to manufacturer's written  instructions  for  conditions  at  specific  location  at time of installation. Install conduit supports to allow for expansion movement. 

S. Flexible Conduit Connections: Comply with NEMA RV 3. Use a maximum of 72 inches of flexible conduit  for  equipment  subject  to  vibration,  noise  transmission,  or  movement;  and  for transformers and motors. 

T. Mount  boxes  at  heights  indicated  on  Drawings.  If  mounting  heights  of  boxes  are  not individually indicated, give priority to ADA requirements. Install boxes with height measured to center of box unless otherwise indicated. 

U. Fasten junction and pull boxes to or support from building structure. Do not support boxes by conduits. 

3.3 SLEEVE AND SLEEVE‐SEAL INSTALLATION FOR ELECTRICAL PENETRATIONS 

A. Install sleeves and sleeve seals at penetrations of exterior  floor and wall assemblies. Comply with  requirements  in  Section 260544  "Sleeves  and  Sleeve  Seals  for  Electrical Raceways  and Cabling." 

3.4 PROTECTION 

A. Protect coatings, finishes, and cabinets from damage and deterioration. 

1. Repair  damage  to  galvanized  finishes  with  zinc‐rich  paint  recommended  by manufacturer. 

END OF SECTION 260533 

Page 78: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART
Page 79: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING 260544 - 1

SECTION 260544 - SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Sleeves for raceway and cable penetration of non-fire-rated construction walls and floors.

2. Sleeve-seal fittings. 3. Grout. 4. Silicone sealants.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product.

PART 2 - PRODUCTS

2.1 SLEEVES

A. Wall Sleeves:

1. Steel Pipe Sleeves: ASTM A 53/A 53M, Type E, Grade B, Schedule 40, zinc coated, plain ends.

B. Sleeves for Conduits Penetrating Non-Fire-Rated Gypsum Board Assemblies: Galvanized-steel sheet; 0.0239-inch minimum thickness; round tube closed with welded longitudinal joint, with tabs for screw-fastening the sleeve to the board.

2.2 SLEEVE-SEAL FITTINGS

A. Description: Manufactured plastic, sleeve-type, waterstop assembly made for embedding in concrete slab or wall. Unit shall have plastic or rubber waterstop collar with center opening to match piping OD.

Page 80: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING 260544 - 2

2.3 GROUT

A. Description: Nonshrink; recommended for interior and exterior sealing openings in non-fire-rated walls or floors.

B. Standard: ASTM C 1107/C 1107M, Grade B, post-hardening and volume-adjusting, dry, hydraulic-cement grout.

C. Design Mix: 5000-psi, 28-day compressive strength.

D. Packaging: Premixed and factory packaged.

2.4 SILICONE SEALANTS

A. Silicone Sealants: Single-component, silicone-based, neutral-curing elastomeric sealants of grade indicated below.

B. Silicone Foams: Multicomponent, silicone-based liquid elastomers that, when mixed, expand and cure in place to produce a flexible, nonshrinking foam.

PART 3 - EXECUTION

3.1 SLEEVE INSTALLATION FOR NON-FIRE-RATED ELECTRICAL PENETRATIONS

A. Comply with NECA 1.

B. Sleeves for Conduits Penetrating Above-Grade Non-Fire-Rated Concrete and Masonry-Unit Floors and Walls:

1. Interior Penetrations of Non-Fire-Rated Walls:

a. Seal annular space between sleeve and raceway or cable, using joint sealant appropriate for size, depth, and location of joint.

b. Seal space outside of sleeves with mortar or grout. Pack sealing material solidly between sleeve and wall so no voids remain. Tool exposed surfaces smooth; protect material while curing.

2. Size pipe sleeves to provide 1/4-inch annular clear space between sleeve and raceway or cable unless sleeve seal is to be installed.

3. Cut sleeves to length for mounting flush with both surfaces of walls. Deburr after cutting.

C. Aboveground, Exterior-Wall Penetrations: Seal penetrations using steel pipe sleeves and mechanical sleeve seals. Select sleeve size to allow for 1-inch annular clear space between pipe and sleeve for installing mechanical sleeve seals.

Page 81: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING 260544 - 3

3.2 SLEEVE-SEAL-FITTING INSTALLATION

A. Assemble fitting components of length to be flush with both surfaces of concrete slabs and walls. Position waterstop flange to be centered in concrete slab or wall.

B. Secure nailing flanges to concrete forms.

C. Using grout, seal the space around outside of sleeve-seal fittings.

END OF SECTION 260544

Page 82: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART
Page 83: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

IDENTIFICATION FOR ELECTRICAL SYSTEMS 260553 - 1

SECTION 260553 - IDENTIFICATION FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Color and legend requirements for raceways, conductors, and warning labels and signs. 2. Bands and tubes. 3. Tapes. 4. Tags. 5. Cable ties.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Comply with ASME A13.1.

B. Comply with NFPA 70.

C. Adhesive-attached labeling materials, including label stocks, laminating adhesives, and inks used by label printers, shall comply with UL 969.

D. Thermal Movements: Allow for thermal movements from ambient and surface temperature changes.

1. Temperature Change: 120 deg F, ambient; 180 deg F, material surfaces.

2.2 COLOR AND LEGEND REQUIREMENTS

A. Raceways and Cables Carrying Circuits at 600 V or Less:

1. Black letters on an orange field. 2. Legend: Indicate voltage.

Page 84: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

IDENTIFICATION FOR ELECTRICAL SYSTEMS 260553 - 2

B. Color-Coding for Phase- and Voltage-Level Identification, 600 V or Less: Use colors listed below for ungrounded branch-circuit conductors.

1. Color shall be factory applied or field applied for sizes larger than No. 8 AWG if authorities having jurisdiction permit.

2. Colors for 480/277-V Circuits:

a. Phase A: Brown. b. Phase B: Orange. c. Phase C: Yellow.

3. Color for Neutral: White. 4. Color for Equipment Grounds: Green.

2.3 BANDS AND TUBES

A. Snap-around, Color-Coding Bands: Slit, pretensioned, flexible, solid-colored acrylic sleeves, 2 inches long, with diameters sized to suit diameters and that stay in place by gripping action.

2.4 TAPES

A. Marker Tapes: Vinyl or vinyl-cloth, self-adhesive wraparound type, with circuit identification legend machine printed by thermal transfer or equivalent process.

B. Self-Adhesive Vinyl Tape: Colored, heavy duty, waterproof, fade resistant; not less than 3 mils thick by 1 to 2 inches wide; compounded for outdoor use.

2.5 TAGS

A. Metal Tags: Brass or aluminum, 2 by 2 by 0.05 inch, with stamped legend, punched for use with self-locking cable tie fastener.

B. Write-on Tags:

1. Polyester Tags: 0.015 inch thick, with corrosion-resistant grommet and cable tie for attachment.

2. Marker for Tags: Permanent, waterproof, black ink marker recommended by tag manufacturer.

2.6 CABLE TIES

A. General-Purpose Cable Ties: Fungus inert, self-extinguishing, one piece, self-locking, and Type 6/6 nylon.

1. Minimum Width: 3/16 inch.

Page 85: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

IDENTIFICATION FOR ELECTRICAL SYSTEMS 260553 - 3

2. Tensile Strength at 73 Deg F according to ASTM D 638: 12,000 psi. 3. Temperature Range: Minus 40 to plus 185 deg F. 4. Color: Black, except where used for color-coding.

B. UV-Stabilized Cable Ties: Fungus inert, designed for continuous exposure to exterior sunlight, self-extinguishing, one piece, self-locking, and Type 6/6 nylon.

1. Minimum Width: 3/16 inch. 2. Tensile Strength at 73 Deg F according to ASTM D 638: 12,000 psi. 3. Temperature Range: Minus 40 to plus 185 deg F. 4. Color: Black.

C. Plenum-Rated Cable Ties: Self-extinguishing, UV stabilized, one piece, and self-locking.

1. Minimum Width: 3/16 inch. 2. Tensile Strength at 73 Deg F according to ASTM D 638: 7000 psi. 3. UL 94 Flame Rating: 94V-0. 4. Temperature Range: Minus 50 to plus 284 deg F. 5. Color: Black.

PART 3 - EXECUTION

3.1 PREPARATION

A. Self-Adhesive Identification Products: Before applying electrical identification products, clean substrates of substances that could impair bond, using materials and methods recommended by manufacturer of identification product.

3.2 INSTALLATION

A. Verify and coordinate identification names, abbreviations, colors, and other features with requirements in other Sections requiring identification applications, Drawings, Shop Drawings, manufacturer's wiring diagrams, and operation and maintenance manual. Use consistent designations throughout Project.

B. Install identifying devices before installing acoustical ceilings and similar concealment.

C. Verify identity of each item before installing identification products.

D. Coordinate identification with Project Drawings, manufacturer's wiring diagrams, and operation and maintenance manual.

E. Apply identification devices to surfaces that require finish after completing finish work.

F. System Identification for Raceways and Cables under 600 V: Identification shall completely encircle cable or conduit. Place identification of two-color markings in contact, side by side.

Page 86: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

IDENTIFICATION FOR ELECTRICAL SYSTEMS 260553 - 4

1. Secure tight to surface of conductor, cable, or raceway.

G. Auxiliary Electrical Systems Conductor Identification: Identify field-installed alarm, control, and signal connections.

H. Snap-around Color-Coding Bands: Secure tight to surface at a location with high visibility and accessibility.

I. Marker Tapes: Secure tight to surface at a location with high visibility and accessibility.

J. Self-Adhesive Vinyl Tape: Secure tight to surface at a location with high visibility and accessibility.

1. Field-Applied, Color-Coding Conductor Tape: Apply in half-lapped turns for a minimum distance of 6 inches where splices or taps are made. Apply last two turns of tape with no tension to prevent possible unwinding.

K. Metal Tags:

1. Place in a location with high visibility and accessibility. 2. Secure using cable ties appropriate for the installation environment.

L. Write-on Tags:

1. Place in a location with high visibility and accessibility. 2. Secure using cable ties appropriate for the installation environment.

M. Cable Ties: General purpose, for attaching tags, except as listed below:

1. Outdoors: UV-stabilized nylon. 2. In Spaces Handling Environmental Air: Plenum rated.

3.3 IDENTIFICATION SCHEDULE

A. Install identification materials and devices at locations for most convenient viewing without interference with operation and maintenance of equipment. Install access doors or panels to provide view of identifying devices.

B. Identify conductors, cables, and terminals in enclosures and at junctions, terminals, pull points, and locations of high visibility. Identify by system and circuit designation.

C. Accessible Raceways and Metal-Clad Cables, 600 V or Less, for Service, Feeder, and Branch Circuits, More Than 30 A and 120 V to Ground: Identify with self-adhesive vinyl tape applied in bands.

1. Locate identification at changes in direction, at penetrations of walls and floors, at 50-foot maximum intervals in straight runs, and at 25-foot maximum intervals in congested areas.

Page 87: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

IDENTIFICATION FOR ELECTRICAL SYSTEMS 260553 - 5

D. Accessible Fittings for Raceways and Cables within Buildings: Identify the covers of each junction and pull box of the following systems with self-adhesive labels containing the wiring system legend and system voltage. System legends shall be as follows: 1. "POWER."

E. Power-Circuit Conductor Identification, 600 V or Less: For conductors in vaults, pull and junction boxes, manholes, and handholes, use snap-around color-coding bands to identify the phase.

1. Locate identification at changes in direction, at penetrations of walls and floors, at 50-foot maximum intervals in straight runs, and at 25-foot maximum intervals in congested areas.

F. Control-Circuit Conductor Identification: For conductors and cables in pull and junction boxes, manholes, and handholes, use write-on tags with the conductor or cable designation, origin, and destination.

G. Control-Circuit Conductor Termination Identification: For identification at terminations, provide self-adhesive labels with the conductor designation.

H. Auxiliary Electrical Systems Conductor Identification: Self-adhesive vinyl tape that is uniform and consistent with system used by manufacturer for factory-installed connections.

1. Identify conductors, cables, and terminals in enclosures and at junctions, terminals, and pull points. Identify by system and circuit designation.

END OF SECTION 260553

Page 88: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART
Page 89: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

ENCLOSED SWITCHES AND CIRCUIT BREAKERS 262816 - 1

SECTION 262816 - ENCLOSED SWITCHES AND CIRCUIT BREAKERS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Nonfusible switches. 2. Molded-case circuit breakers (MCCBs). 3. Enclosures.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of enclosed switch, circuit breaker, accessory, and component indicated. Include nameplate ratings, dimensioned elevations, sections, weights, and manufacturers' technical data on features, performance, electrical characteristics, ratings, accessories, and finishes.

1. Enclosure types and details for types other than NEMA 250, Type 1. 2. Current and voltage ratings. 3. Short-circuit current ratings (interrupting and withstand, as appropriate). 4. Detail features, characteristics, ratings, and factory settings of individual overcurrent

protective devices, accessories, and auxiliary components.

B. Shop Drawings: For enclosed switches and circuit breakers.

1. Include plans, elevations, sections, details, and attachments to other work. 2. Include wiring diagrams for power, signal, and control wiring.

1.4 INFORMATIONAL SUBMITTALS

A. Field quality-control reports.

1.5 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For enclosed switches and circuit breakers to include in emergency, operation, and maintenance manuals.

Page 90: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

ENCLOSED SWITCHES AND CIRCUIT BREAKERS 262816 - 2

1. In addition to items specified in Section 017823 "Operation and Maintenance Data," include the following:

a. Manufacturer's written instructions for testing and adjusting enclosed switches and circuit breakers.

1.6 QUALITY ASSURANCE

A. Testing Agency Qualifications: Accredited by NETA.

1. Testing Agency's Field Supervisor: Currently certified by NETA to supervise on-site testing.

1.7 FIELD CONDITIONS

A. Environmental Limitations: Rate equipment for continuous operation under the following conditions unless otherwise indicated:

1. Ambient Temperature: Not less than minus 22 deg F and not exceeding 104 deg F. 2. Altitude: Not exceeding 6600 feet.

1.8 WARRANTY

A. Manufacturer's Warranty: Manufacturer and Installer agree to repair or replace components that fail in materials or workmanship within specified warranty period.

1. Warranty Period: One year(s) from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 GENERAL REQUIREMENTS

A. Source Limitations: Obtain enclosed switches and circuit breakers, overcurrent protective devices, components, and accessories, within same product category, from single manufacturer.

B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by an NRTL, and marked for intended location and application.

C. Comply with NFPA 70.

Page 91: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

ENCLOSED SWITCHES AND CIRCUIT BREAKERS 262816 - 3

2.2 NONFUSIBLE SWITCHES

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

1. Eaton. 2. General Electric Company. 3. Siemens Industry, Inc. 4. Square D; by Schneider Electric.

B. Type HD, Heavy Duty, Three Pole, Single Throw, 600-V ac, 1200 A and Smaller: UL 98 and NEMA KS 1, horsepower rated, lockable handle with capability to accept three padlocks, and interlocked with cover in closed position.

C. Accessories:

1. Equipment Ground Kit: Internally mounted and labeled for copper and aluminum ground conductors.

2. Neutral Kit: Internally mounted; insulated, capable of being grounded and bonded; labeled for copper and aluminum neutral conductors.

3. Isolated Ground Kit: Internally mounted; insulated, labeled for copper and aluminum neutral conductors.

4. Lugs: Mechanical type, suitable for number, size, and conductor material.

2.3 MOLDED-CASE CIRCUIT BREAKERS

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

1. Eaton. 2. General Electric Company. 3. Siemens Industry, Inc. 4. Square D; by Schneider Electric.

B. Circuit breakers shall be constructed using glass-reinforced insulating material. Current carrying components shall be completely isolated from the handle and the accessory mounting area.

C. Circuit breakers shall have a toggle operating mechanism with common tripping of all poles, which provides quick-make, quick-break contact action. The circuit-breaker handle shall be over center, be trip free, and reside in a tripped position between on and off to provide local trip indication. Circuit-breaker escutcheon shall be clearly marked on and off in addition to providing international I/O markings. Equip circuit breaker with a push-to-trip button, located on the face of the circuit breaker to mechanically operate the circuit-breaker tripping mechanism for maintenance and testing purposes.

Page 92: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

ENCLOSED SWITCHES AND CIRCUIT BREAKERS 262816 - 4

D. The maximum ampere rating and UL, IEC, or other certification standards with applicable voltage systems and corresponding interrupting ratings shall be clearly marked on face of circuit breaker.

E. MCCBs shall be equipped with a device for locking in the isolated position.

F. Lugs shall be suitable for 140 deg F rated wire on 125-A circuit breakers and below.

G. Standards: Comply with UL 489 and NEMA AB 3, with interrupting capacity to comply with available fault currents.

H. Thermal-Magnetic Circuit Breakers: Inverse time-current thermal element for low-level overloads and instantaneous magnetic trip element for short circuits. Adjustable magnetic trip setting for circuit-breaker frame sizes 250 A and larger.

I. Adjustable, Instantaneous-Trip Circuit Breakers: Magnetic trip element with front-mounted, field-adjustable trip setting.

J. Features and Accessories:

1. Standard frame sizes, trip ratings, and number of poles. 2. Lugs: Mechanical type, suitable for number, size, trip ratings, and conductor material. 3. Key Interlock Kit: Externally mounted to prohibit circuit-breaker operation; key shall be

removable only when circuit breaker is in off position.

2.4 ENCLOSURES

A. Enclosed Switches and Circuit Breakers: UL 489, NEMA KS 1, NEMA 250, and UL 50, to comply with environmental conditions at installed location.

B. Enclosure Finish: The enclosure shall be gray baked enamel paint, electrodeposited on cleaned, phosphatized steel (NEMA 250 Type 1) and a brush finish on Type 304 stainless steel (NEMA 250 Type 4-4X stainless steel).

C. Conduit Entry: NEMA 250 Types 4, 4X, and 12 enclosures shall contain no knockouts.

D. Enclosures designated as NEMA 250 Type 4, 4X stainless steel, 12, or 12K shall have a dual cover interlock mechanism to prevent unintentional opening of the enclosure cover when the circuit breaker or switch is ON and to prevent turning the circuit breaker or switch ON when the enclosure cover is open.

Page 93: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

ENCLOSED SWITCHES AND CIRCUIT BREAKERS 262816 - 5

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine elements and surfaces to receive enclosed switches and circuit breakers for compliance with installation tolerances and other conditions affecting performance of the Work.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

1. Commencement of work shall indicate Installer's acceptance of the areas and conditions as satisfactory.

3.2 ENCLOSURE ENVIRONMENTAL RATING APPLICATIONS

A. Enclosed Switches and Circuit Breakers: Provide enclosures at installed locations with the following environmental ratings.

1. Indoor, Dry and Clean Locations: NEMA 250, Type 1. 2. Outdoor Locations: NEMA 250, Type 4X. 3. Indoor Locations Subject to Dust, Falling Dirt, and Dripping Noncorrosive Liquids:

NEMA 250, Type 12.

3.3 INSTALLATION

A. Coordinate layout and installation of switches, circuit breakers, and components with equipment served and adjacent surfaces. Maintain required workspace clearances and required clearances for equipment access doors and panels.

B. Comply with NFPA 70 and NECA 1.

3.4 IDENTIFICATION

A. Comply with requirements in Section 260553 "Identification for Electrical Systems."

1. Identify field-installed conductors, interconnecting wiring, and components; provide warning signs.

2. Label each enclosure with engraved metal or laminated-plastic nameplate.

3.5 FIELD QUALITY CONTROL

A. Perform tests and inspections.

B. Tests and Inspections for Switches:

Page 94: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

ENCLOSED SWITCHES AND CIRCUIT BREAKERS 262816 - 6

1. Visual and Mechanical Inspection:

a. Inspect physical and mechanical condition. b. Inspect anchorage, alignment, grounding, and clearances. c. Verify that the unit is clean. d. Verify blade alignment, blade penetration, travel stops, and mechanical

operation. e. Inspect bolted electrical connections for high resistance using one of the two

following methods:

1) Use a low-resistance ohmmeter.

a) Compare bolted connection resistance values to values of similar connections. Investigate values that deviate from those of similar bolted connections by more than 50 percent of the lowest value.

2) Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or NETA ATS Table 100.12.

a) Bolt-torque levels shall be in accordance with manufacturer's published data. In the absence of manufacturer's published data, use NETA ATS Table 100.12.

f. Verify correct phase barrier installation. g. Verify lubrication of moving current-carrying parts and moving and sliding

surfaces.

2. Electrical Tests:

a. Perform resistance measurements through bolted connections with a low-resistance ohmmeter. Compare bolted connection resistance values to values of similar connections. Investigate values that deviate from adjacent poles or similar switches by more than 50 percent of the lowest value.

b. Measure contact resistance across each switchblade fuseholder. Drop values shall not exceed the high level of the manufacturer's published data. If manufacturer's published data are not available, investigate values that deviate from adjacent poles or similar switches by more than 50 percent of the lowest value.

c. Perform insulation-resistance tests for one minute on each pole, phase-to-phase and phase-to-ground with switch closed, and across each open pole. Apply voltage in accordance with manufacturer's published data. In the absence of manufacturer's published data, use Table 100.1 from the NETA ATS. Investigate values of insulation resistance less than those published in Table 100.1 or as recommended in manufacturer's published data.

C. Tests and Inspections for Molded Case Circuit Breakers:

1. Visual and Mechanical Inspection:

Page 95: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

ENCLOSED SWITCHES AND CIRCUIT BREAKERS 262816 - 7

a. Verify that equipment nameplate data are as described in the Specifications and shown on the Drawings.

b. Inspect physical and mechanical condition. c. Inspect anchorage, alignment, grounding, and clearances. d. Verify that the unit is clean. e. Operate the circuit breaker to ensure smooth operation. f. Inspect bolted electrical connections for high resistance using one of the two

following methods:

1) Use a low-resistance ohmmeter.

a) Compare bolted connection resistance values to values of similar connections. Investigate values that deviate from those of similar bolted connections by more than 50 percent of the lowest value.

2) Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or NETA ATS Table 100.12.

a) Bolt-torque levels shall be in accordance with manufacturer's published data. In the absence of manufacturer's published data, use NETA ATS Table 100.12.

2. Electrical Tests:

a. Perform resistance measurements through bolted connections with a low-resistance ohmmeter. Compare bolted connection resistance values to values of similar connections. Investigate values that deviate from adjacent poles or similar switches by more than 50 percent of the lowest value.

b. Perform insulation-resistance tests for one minute on each pole, phase-to-phase and phase-to-ground with circuit breaker closed, and across each open pole. Apply voltage in accordance with manufacturer's published data. In the absence of manufacturer's published data, use Table 100.1 from the NETA ATS. Investigate values of insulation resistance less than those published in Table 100.1 or as recommended in manufacturer's published data.

c. Perform a contact/pole resistance test. Drop values shall not exceed the high level of the manufacturer's published data. If manufacturer's published data are not available, investigate values that deviate from adjacent poles or similar switches by more than 50 percent of the lowest value.

d. Perform insulation resistance tests on all control wiring with respect to ground. Applied potential shall be 500-V dc for 300-V rated cable and 1000-V dc for 600-V rated cable. Test duration shall be one minute. For units with solid state components, follow manufacturer's recommendation. Insulation resistance values shall be no less than two megohms.

3. Correct malfunctioning units on-site, where possible, and retest to demonstrate compliance; otherwise, replace with new units and retest.

Page 96: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY

ENCLOSED SWITCHES AND CIRCUIT BREAKERS 262816 - 8

D. Enclosed switches and circuit breakers will be considered defective if they do not pass tests and inspections.

E. Prepare test and inspection reports.

1. Test procedures used. 2. Include identification of each enclosed switch and circuit breaker tested and describe

test results. 3. List deficiencies detected, remedial action taken, and observations after remedial

action.

3.6 ADJUSTING

A. Adjust moving parts and operable components to function smoothly, and lubricate as recommended by manufacturer.

END OF SECTION 262816

Page 97: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE    RICHMOND MAIN LIBRARY   

CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY  280513 ‐ 1

SECTION 280513 ‐ CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY 

PART 1 ‐ GENERAL 

1.1 RELATED DOCUMENTS 

A. Drawings and general provisions of the Contract, including General Conditions and Division 01 Specification Sections, apply to this Section. 

1.2 SUMMARY 

A. Section Includes: 1. Fire alarm wire and cable. 

1.3 INFORMATIONAL SUBMITTALS 

A. Field quality‐control reports. 

PART 2 ‐ PRODUCTS 

2.1 PERFORMANCE REQUIREMENTS 

A. Surface‐Burning Characteristics: Comply with ASTM E 84; testing by a qualified testing agency. Identify products with appropriate markings of applicable testing agency. 

1. Flame‐Spread Index:  25 or less. 2. Smoke‐Developed Index:  50 or less. 

B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application. 

2.2 FIRE ALARM WIRE AND CABLE 

A. Manufacturers:  Subject  to  compliance with  requirements,  available manufacturers  offering products that may be incorporated into the Work include, but are not limited to the following: 

1. Allied Wire & Cable Inc. 2. CommScope, Inc. 3. Genesis Cable Products; Honeywell International, Inc. 4. West Penn Wire. 

Page 98: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE    RICHMOND MAIN LIBRARY   

CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY  280513 ‐ 2

B. General Wire and Cable Requirements: NRTL  listed and  labeled as  complying with NFPA 70, Article 760. 

C. Signaling Line Circuits: Twisted, shielded pair, not less than No. 18 AWG. 

1. Circuit  Integrity Cable: Twisted shielded pair, NFPA 70, Article 760, Classification CI, for power‐limited  fire alarm signal service Type FPL. NRTL  listed and  labeled as complying with UL 1424 and UL 2196 for a two‐hour rating. 

D. Non‐Power‐Limited Circuits: Solid‐copper conductors with 600‐V rated, 75 deg C, color‐coded insulation, and complying with requirements in UL 2196 for a two‐hour rating. 

1. Low‐Voltage Circuits: No. 16 AWG, minimum, in pathway. 2. Line‐Voltage Circuits: No. 12 AWG, minimum, in pathway. 3. Multiconductor Armored Cable: NFPA 70, Type MC, copper conductors, Type TFN/THHN 

conductor  insulation,  copper  drain  wire,  copper  armor with  outer  jacket  with  red identifier stripe, NTRL listed for fire alarm and cable tray installation, plenum rated. 

PART 3 ‐ EXECUTION 

3.1 INSTALLATION OF HANGERS AND SUPPORTS 

A. Comply with requirements in Section 260529 "Hangers and Supports for Electrical Systems" for installation of supports for cables. 

3.2 WIRING METHOD 

A. Install wiring in metal pathways and wireways. 

1. Minimum conduit size shall be 3/4 inch. Fire Alarm wiring shall not share conduits with other building wiring systems. 

2. Comply  with  requirements  in  Section  260533  “Raceways  and  Boxes  for  Electrical Systems”. 

B. Install cable, concealed in accessible ceilings, walls, and floors when possible. 

3.3 INSTALLATION OF CONDUCTORS AND CABLES 

A. Comply with NECA 1 and NFPA 70. 

B. Conductors:  Size  according  to  system manufacturer's written  instructions  unless  otherwise indicated. 

C. Do not install conductors and cables that are wet, moisture damaged, or mold damaged. 

D. General Requirements for Cabling: 

Page 99: MAIN BRANCH LIBRARY HVAC UPGRADES SPECIAL … · 2018-11-09 · HVAC UPGRADES – SPECIAL COLLECTIONS SPACE RICHMOND MAIN LIBRARY SUMMARY 011000 - 1 SECTION 011000 - SUMMARY PART

HVAC UPGRADES – SPECIAL COLLECTIONS SPACE    RICHMOND MAIN LIBRARY   

CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY  280513 ‐ 3

1. Terminate  all  conductors;  no  cable  shall  contain  unterminated  elements.  Make terminations only at  indicated outlets,  terminals, and cross‐connect and patch panels. Leave a minimum of 6  inches of slack at outlet  terminations and coil  loosely  into box after termination on outlet fitting. 

2. Cables may  not  be  spliced.  Secure  and  support  cables  at  intervals  not  exceeding  30 inches and not more than 6 inches from cabinets, boxes, fittings, outlets, racks, frames, and terminals. 

3. Maintain minimum cable bending radius during installation and termination of cables. 4. Do not  install bruised, kinked, scored, deformed, or abraded cable. Do not splice cable 

between  termination,  tap,  or  junction  points.  Remove  and  discard  cable  if  damaged during installation and replace it with new cable. 

3.4 FIRE ALARM WIRING INSTALLATION 

A. Comply with NECA 1 and NFPA 72. 

B. Wiring Method: 

1. Cables  and  pathways  used  for  fire  alarm  circuits,  and  equipment  control  wiring associated with the fire alarm system, may not contain any other wire or cable. 

2. Fire‐Rated Cables: Use of two‐hour, fire‐rated fire alarm cables, NFPA 70, Types MI and CI, is permitted. 

3. Signaling  Line  Circuits:  Power‐limited  fire  alarm  cables may  be  installed  in  the  same cable or pathway as signaling line circuits. 

C. Wiring  within  Enclosures:  Separate  power‐limited  and  non‐power‐limited  conductors  as recommended by manufacturer. Install conductors parallel with or at right angles to sides and back of  the enclosure. Bundle,  lace, and  train conductors  to  terminal points with no excess. Connect conductors  that are  terminated,  spliced, or  interrupted  in any enclosure associated with  the  fire alarm system  to  terminal blocks. Mark each  terminal according  to  the system's wiring diagrams. Make all connections with approved crimp‐on terminal spade lugs, pressure‐type terminal blocks, or plug connectors. 

D. Cable  Taps:  Use  numbered  terminal  strips  in  junction,  pull,  and  outlet  boxes,  cabinets,  or equipment enclosures where circuit connections are made. 

E. Color Coding: Color  code  fire  alarm  conductors differently  from  the  normal  building power wiring. Use one color code for alarm circuit wiring and another for supervisory circuits. Color code  audible  alarm‐indicating  circuits differently  from  alarm‐initiating  circuits. Use different colors  for visible alarm‐indicating devices. Paint  fire alarm system  junction boxes and covers red. 

F. Wiring  to Remote Alarm Transmitting Device: 1‐inch conduit between  the  fire alarm control panel  and  the  transmitter.  Install  number  of  conductors  and  electrical  supervision  for connecting wiring as needed to suit monitoring function. 

END OF SECTION 280513