May 2013 LIEBE Project T. Stora 1 LIEBE Progress Report Coordination meeting – 3 rd SC CEA-Saclay, 24 th May 2013 T. Stora – EN-STI-RBS

Upload: moris-logan

Post on 18-Jan-2016

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: May 2013 LIEBE Project T. Stora 1 LIEBE Progress Report Coordination meeting – 3 rd SC CEA-Saclay, 24 th May 2013 T. Stora – EN-STI-RBS

May 2013LIEBE Project

T. Stora

1

LIEBE Progress Report

Coordination meeting – 3rd SC

CEA-Saclay, 24th May 2013

T. Stora – EN-STI-RBS

Page 2: May 2013 LIEBE Project T. Stora 1 LIEBE Progress Report Coordination meeting – 3 rd SC CEA-Saclay, 24 th May 2013 T. Stora – EN-STI-RBS

May 2013LIEBE Project

T. Stora

2

Pb/Bi loop online @ ISOLDE

Static Pb/BI target already tested once at ISOLDE

Target material Pb 44.5% / Bi 55.5% Melting point / boiling point [C] 125 / 1670 Operating temperature [C] 150-600 Target material density [kg/m3] 10.5 @ 200C; 10.2 @ 400C; 9.9@600C Thermal conductivity [W/K.m] 11.3 @ 400C Irradiation cell volume [cm3] 60 Flow rate [cm3/s] 60-200 Pump pressure [Bar] 0.1-2

Page 3: May 2013 LIEBE Project T. Stora 1 LIEBE Progress Report Coordination meeting – 3 rd SC CEA-Saclay, 24 th May 2013 T. Stora – EN-STI-RBS

May 2013LIEBE Project

T. Stora

3

Work packages

WP definition WP holder Coordinator WP1 : Coordination CERN T. StoraWP2 : Conceptual Design and simulations SCK-CEN P. SchuurmansWP3 : Construction, assembly CERN M. DeloncaWP4 : Instrumentation CERN T. MendoncaWP5 : Safety and Licensing CEA A. MarchixWP6 : Target characterization and analysis PSI D. SchumannWP7 : Radiochemistry SINP S. LahiriWP8 : Offline commissioning IPUL K. KravalisWP9 : Online operation CERN T. Mendonca

Page 4: May 2013 LIEBE Project T. Stora 1 LIEBE Progress Report Coordination meeting – 3 rd SC CEA-Saclay, 24 th May 2013 T. Stora – EN-STI-RBS

May 2013LIEBE Project

T. Stora

4

PlanningLIEBE project planning - endorsed 2nd SC, Lisbon, Oct 2012

WP Q3-12 Q4-12 Q1-13 Q2-13 Q3-13 Q4-13 Q1-14 Q2-14 Q3-14 Q4-14 Q1-15 Q2-15 2018

2 Design

1st design CFD, FEMFinal design

3 Assembl

Techn. drawings

components

Procurement

Construction

Adaptation

4 Instr. DefinitionTests@ipul/cern

software

5 SafetyCERN authorities.

Safety constraints

Risk analysis +RP

Risk analysis +RP II

Safety fileBeam permit

Waste

PIE

7 Chemist

Activation Pb/Bi

Compar MC code

Activation Pb/Bi-II

8 Offline

Test pumps IPUL

Test IPULCERN

commissioning

commissioning

Cold check-out

1 week online –

Report

CERN-wide Long Shutdown 1

6 Target charact

Release (Po…)

Inventory

9 Online

Operational parameters

Definition of onlinetests

Final report

Modif target area I

Modif target area II

Page 5: May 2013 LIEBE Project T. Stora 1 LIEBE Progress Report Coordination meeting – 3 rd SC CEA-Saclay, 24 th May 2013 T. Stora – EN-STI-RBS

May 2013LIEBE Project

T. Stora

5

Budget, Communication, etc

3 x 150 kCHF granted (2012-2014)Need spending estimates (WP 2-4)

Don’t forget the sharepoint project site:https://espace.cern.ch/isobeam/Pb-Bi-Loop/default.aspx

Page 6: May 2013 LIEBE Project T. Stora 1 LIEBE Progress Report Coordination meeting – 3 rd SC CEA-Saclay, 24 th May 2013 T. Stora – EN-STI-RBS

May 2013LIEBE Project

T. Stora

6

News from WPsWP 1 : Next project coord meeting at CEN.SCK (high power targetry workshop).Coord+SC in Kolkata Jan 2014

WP 2 : 2 designs proposed and compatible with ISOLDE environment, pumps seem to be Ok, robot handling also: to be further tested, prototyped, checked against safety,

WP 4 : slightly delayed (PSI will provide expertise, CERN holds the WP)

WP 5 : some estimates by Fluka, well on tracks for recommendations taken into account in the design

WP 6 : collections of Po done. 2 Draft publications.

WP 7 : 1st data on At and other isotopes inventories.

WP 8 : Refurbishment of Radiochemical lab in progress.IPUL ?

See following presentations

Page 7: May 2013 LIEBE Project T. Stora 1 LIEBE Progress Report Coordination meeting – 3 rd SC CEA-Saclay, 24 th May 2013 T. Stora – EN-STI-RBS

May 2013LIEBE Project

T. Stora

7

Items for SCPlanning, budget

ENSAR II

High power target workshop in SCK.CEN