STATE TRANSPORTATION IMPROVEMENT PROJECTS Wyoming Department of Transportation Letting Events Between May 9, 2019 and May 14, 2020 Project ID Prefix Project Name Funding Intent Letting Cost N104066 SIB-ACNHPP 3 HOBACK-JACKSON/SNAKE RIVER SOUTH SECTION w/N104079 *PODI* Federal RECONSTRUCTION $49,800,000 N104079 STP-E 3 (w/ N104066) 3 HOBACK-JACKSON/ SNAKE RIVER/SOUTH SECTION/ ENHANCEMENT Federal ENHANCEMENTS/PATHWAYS/LNDSCP+ $1,700,000 N104A08 ARSCT 3 (W/104066) ARS/HOBACK- JACKSON/SNAKE RIVER SOUTH SECTION State BRIDGE CONDUIT $100,000 Sum: $51,600,000 Dist. County Plans Received Resident Squad Leader 3 Teton Yes Bob Hammond Doering Project ID Prefix Project Name Funding Intent Letting Cost N372047 NHPP 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident Squad Leader 4 Sheridan Yes Jerry Buckley Doering Project ID Prefix Project Name Funding Intent Letting Cost 4200016 STP-BR 1 (w/B191004) LARAMIE STREETS/ CURTIS/BRIDGE REHAB Federal BRIDGE REHAB $100,000 B191004 NHPP-BR 1 VARIOUS LOCATIONS/BRIDGE REHAB w/4200016 Federal BRIDGE REHAB $2,500,000 Sum: $2,600,000 Dist. County Plans Received Resident Squad Leader 1 Albany Yes Unassigned Various Yes Kevin Erickson Potter Project ID Prefix Project Name Funding Intent Letting Cost 1104015 STP-BR 1 PINE BLUFF- ALBIN/NORTH SEC/ WYO 215 Federal BRIDGE REPLACEMENT $2,200,000 Sum: $2,200,000 Dist. County Plans Received Resident Squad Leader 1 Laramie Yes Wayne Shenefelt Potter Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month May 9, 2019 Laramie May 16, 2019 March 8, 2019 April 11, 2019 9 $64,100,000 1/26 4/22/19

Upload: others

Post on 13-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

N104066 SIB-ACNHPP 3 HOBACK-JACKSON/SNAKE RIVERSOUTH SECTION w/N104079 *PODI* Federal RECONSTRUCTION $49,800,000

N104079 STP-E3 (w/ N104066) 3 HOBACK-JACKSON/SNAKE RIVER/SOUTH SECTION/ENHANCEMENT

Federal ENHANCEMENTS/PATHWAYS/LNDSCP+ $1,700,000

N104A08 ARSCT3 (W/104066) ARS/HOBACK-JACKSON/SNAKE RIVER SOUTHSECTION

State BRIDGE CONDUIT $100,000

Sum: $51,600,000

Dist. County PlansReceived Resident Squad

Leader

3 Teton Yes Bob Hammond Doering

ProjectID Prefix Project Name Funding Intent Letting Cost

N372047 NHPP 4 BURGESS JUNCTION/DAYTON/WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000

Sum: $3,000,000

Dist. County PlansReceived Resident Squad

Leader

4 Sheridan Yes Jerry Buckley Doering

ProjectID Prefix Project Name Funding Intent Letting Cost

4200016 STP-BR 1 (w/B191004) LARAMIE STREETS/CURTIS/BRIDGE REHAB Federal BRIDGE REHAB $100,000

B191004 NHPP-BR 1 VARIOUS LOCATIONS/BRIDGEREHAB w/4200016 Federal BRIDGE REHAB $2,500,000

Sum: $2,600,000

Dist. County PlansReceived Resident Squad

Leader

1Albany Yes Unassigned

Various Yes Kevin Erickson Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

1104015 STP-BR 1 PINE BLUFF- ALBIN/NORTH SEC/WYO 215 Federal BRIDGE REPLACEMENT $2,200,000

Sum: $2,200,000

Dist. County PlansReceived Resident Squad

Leader

1 Laramie Yes Wayne Shenefelt Potter

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

May 9, 2019 Laramie May 16, 2019 March 8, 2019 April 11, 2019 9 $64,100,000

1/26 4/22/19

Page 2: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

B199003 HSIP DISTRICTS 2 & 4/SIGNALDETECTION UPGRADE Federal SIGNAL DETECTION UPGRADE $1,600,000

Sum: $1,600,000

Dist. County PlansReceived Resident Squad

Leader

SW Various Yes Jack Stone

ProjectID Prefix Project Name Funding Intent Letting Cost

B195030 STP-BR 5 VARIOUS LOCATIONS/ BRIGEREHAB/SOUTH Federal BRIDGE REHAB $1,200,000

Sum: $1,200,000

Dist. County PlansReceived Resident Squad

Leader

5 Fremont Yes None Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

P352034 STP 4 LOVELL-BURGESS JUNCTION/OBSERVATION SLIDE Federal SLIDE REPAIR $1,100,000

Sum: $1,100,000

Dist. County PlansReceived Resident Squad

Leader

4 Sheridan Yes Jerry Buckley Doering

ProjectID Prefix Project Name Funding Intent Letting Cost

B181006 STP-GM 1 VARIOUS LOCATIONS/CATTLEGUARDS Federal REPLACE CATTLEGUARDS $600,000

Sum: $600,000

Dist. County PlansReceived Resident Squad

Leader

1 Carbon Yes Jake Lonn Doering

ProjectID Prefix Project Name Funding Intent Letting Cost

TRFSN19 SCP VARIOUS LOCATIONS/LOGO SIGNS State UPGRADE LOGO SIGNS $200,000

Sum: $200,000

Dist. County PlansReceived Resident Squad

Leader

SW Various Yes Clint Lockman Potter

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

May 9, 2019 Laramie May 16, 2019 March 8, 2019 April 11, 2019 9 $64,100,000

2/26 4/22/19

Page 3: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

N403007 NHPP 2 LUSK-VAN TASSELL/WESTSECTION State RECONSTRUCTION $13,600,000

Sum: $13,600,000

Dist. County PlansReceived Resident Squad

Leader

2 Niobrara James Barnes Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

N341113 NHPP 5 WALTMAN-SHOSHONI (w/N341A03) Federal PASSING LANES $5,600,000

N341A03 ARSCT 5 (w/N341113) SHOSHONI-CASPER/TURN LANES State TURN LANES $400,000

Sum: $6,000,000

Dist. County PlansReceived Resident Squad

Leader

5 Natrona Yes Kaia Tharp DePew

ProjectID Prefix Project Name Funding Intent Letting Cost

N104092 NHPP 3 JACKSON-HOBACK/JACKSONSOUTH Federal MILL/LEVEL/OVERLAY/CLEAN PIPES $2,500,000

Sum: $2,500,000

Dist. County PlansReceived Resident Squad

Leader

3 Teton Yes Bob Hammond Doering

ProjectID Prefix Project Name Funding Intent Letting Cost

I901122 NHPPI-GM 4 I-90 VARIOUS LOCATIONS/CULVERT LINING Federal CULVERT LINING $1,900,000

Sum: $1,900,000

Dist. County PlansReceived Resident Squad

Leader

4 Sheridan John Leahy Pickett

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

July 11, 2019 Casper July 18, 2019 May 10, 2019 June 13, 2019 10 $30,900,000

3/26 4/22/19

Page 4: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

CN01064 STP-BROS 2 NATRONA COUNTY/COUNTY RD106/STRUCTURE DRD Federal BRIDGE REPLACEMENT $1,500,000

Sum: $1,500,000

Dist. County PlansReceived Resident Squad

Leader

2 Natrona Chad Aagard Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

N202069 NHPP 5 MUDDY GAP-LANDER/LANDERSOUTH Federal TURN LANE $1,500,000

Sum: $1,500,000

Dist. County PlansReceived Resident Squad

Leader

5 Fremont Erik Smith Pickett

ProjectID Prefix Project Name Funding Intent Letting Cost

N433044 HSIP 4 GILLETTE STREETS/TRAFFICSIGNAL Federal TRAFFIC SIGNAL REPLACEMENTS $1,300,000

Sum: $1,300,000

Dist. County PlansReceived Resident Squad

Leader

4 Campbell Josh Jundt Stogsdill

ProjectID Prefix Project Name Funding Intent Letting Cost

B195009 STP 5 VARIOUS LOCATIONS/DMS SIGNS Federal DMS SIGNS $1,200,000

Sum: $1,200,000

Dist. County PlansReceived Resident Squad

Leader

5 Various Yes Kaia Tharp DePew

ProjectID Prefix Project Name Funding Intent Letting Cost

CN06066 STP-BROS 1 CARBON COUNTY/ COUNTY RD/SAVERY CREEK ROAD Federal BRIDGE REPLACEMENT $1,000,000

Sum: $1,000,000

Dist. County PlansReceived Resident Squad

Leader

1 Carbon Yes Jake Lonn Crosby

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

July 11, 2019 Casper July 18, 2019 May 10, 2019 June 13, 2019 10 $30,900,000

4/26 4/22/19

Page 5: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

I254166 NHPPI-GM 2 I-25 VARIOUS LOCATIONSCULVERT CLEANING Federal CULVERT CLEANING $400,000

Sum: $400,000

Dist. County PlansReceived Resident Squad

Leader

2 Various Yes Chad Aagard Doering

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

July 11, 2019 Casper July 18, 2019 May 10, 2019 June 13, 2019 10 $30,900,000

5/26 4/22/19

Page 6: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

P433041 STP 4 GILLETTE-MONTANA STATE LINE/WHITETAIL CREEK Federal WIDEN & OVERLAY $11,200,000

Sum: $11,200,000

Dist. County PlansReceived Resident Squad

Leader

4 Campbell Yes Josh Jundt DePew

ProjectID Prefix Project Name Funding Intent Letting Cost

N372046 NHPP 4 DAYTON-RANCHESTER Federal MILL & OVERLAY $2,800,000

Sum: $2,800,000

Dist. County PlansReceived Resident Squad

Leader

4 Sheridan Jerry Buckley Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

P111013 STP 3 LAZEART JUNCTION-KEMMERER/MUDDY CREEK State MILL & OVERLAY $2,600,000

Sum: $2,600,000

Dist. County PlansReceived Resident Squad

Leader

3 Uinta Yes Damon Newsome Kladianos

ProjectID Prefix Project Name Funding Intent Letting Cost

0401037 STP 1 DIXON-ENCAMPMENT/SAVERY/WYO 70/WEST Federal MILL/OVERLAY/SEAL COAT $2,100,000

Sum: $2,100,000

Dist. County PlansReceived Resident Squad

Leader

1 Carbon Aaron Spenny Crosby

ProjectID Prefix Project Name Funding Intent Letting Cost

0807007 STP 2 TORRINGTON/HUNTLEY ROAD/EAST SECTION/WY 92 Federal WIDEN/MILL/OVERLAY $2,000,000

Sum: $2,000,000

Dist. County PlansReceived Resident Squad

Leader

2 Goshen Buck Klemola Kladianos

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

August 8, 2019 Laramie August 15, 2019 June 7, 2019 July 11, 2019 9 $22,900,000

6/26 4/22/19

Page 7: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

B199005 HSIP DISTRICTS 3 & 5/NO PASSINGPENNANT SIGNS Federal NO PASSING PENNANT SIGNING $1,000,000

Sum: $1,000,000

Dist. County PlansReceived Resident Squad

Leader

SW Various Daniel McGillivray Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B199006 HSIP DISTRICTS 1 & 3/NO PASSINGPENNANT SIGNS Federal NO PASSING PENNANT SIGNING $700,000

Sum: $700,000

Dist. County PlansReceived Resident Squad

Leader

SW Various Daniel McGillivray Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B194023 STP-GM 4 VARIOUS LOCATIONS/SPOTSAFETY IMPROVEMENTS Federal SPOT SAFETY IMPROVEMENTS $300,000

Sum: $300,000

Dist. County PlansReceived Resident Squad

Leader

4 Various Jerry Buckley DePew

ProjectID Prefix Project Name Funding Intent Letting Cost

DR16226 DR 1 CHEYENNE/I-80/PARSLEY BLVD/BRIDGE State STRUCTURE REPAIR $200,000

Sum: $200,000

Dist. County PlansReceived Resident Squad

Leader

1 Laramie None Potter

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

August 8, 2019 Laramie August 15, 2019 June 7, 2019 July 11, 2019 9 $22,900,000

7/26 4/22/19

Page 8: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

I802205 NHPPI3 GRANGER-GREEN RIVER/LABARGE INTERCHANGE WEST/WBL

Federal MILL, OVERLAY & BRIDGE REPAIR $9,500,000

Sum: $9,500,000

Dist. County PlansReceived Resident Squad

Leader

3 Sweetwater Clint Lockman Doering

ProjectID Prefix Project Name Funding Intent Letting Cost

N121111 HIP 3 KEMMERER-GRANGER JUNCTION/KEMMERER EAST Federal MILL AND OVERLAY $3,900,000

Sum: $3,900,000

Dist. County PlansReceived Resident Squad

Leader

3 Lincoln Yes Jennifer Hoffman Stogsdill

ProjectID Prefix Project Name Funding Intent Letting Cost

I251168 HIP-PM1 CHEYENNE- CHUGWATER/RANDALL AVE-HORSE CREEKINTERCHANGE

Federal SLAB REPAIR/GRIND SEAL $3,800,000

Sum: $3,800,000

Dist. County PlansReceived Resident Squad

Leader

1 Laramie Wayne Shenefelt Doering

ProjectID Prefix Project Name Funding Intent Letting Cost

B185002 NHPP-GM5 RIVERTON STREETS/MAINSTREET/ADA UPGDRADES (w/N303057)

Federal ADA UPGRADES $2,000,000

N302053 HIP 5 RIVERTON STREETS/MAINSTREET Federal MILL & OVERLAY $1,200,000

N303057 NHPP 5 (w/B185002) 5 RIVERTONSTREETS/MAJOR & MAIN Federal INTERSECTION MOD/SIGNAL $500,000

Sum: $3,700,000

Dist. County PlansReceived Resident Squad

Leader

5 Fremont Robert Scheidemantel DePew

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

September 12, 2019 Sheridan September 19, 2019 July 12, 2019 August 15, 2019 7 $27,000,000

8/26 4/22/19

Page 9: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

N311097 HIP 5 CODY STREETS/US 14/16/20 Federal CONC GRIND/SEAL/ISO SLAB/ADA $3,300,000

Sum: $3,300,000

Dist. County PlansReceived Resident Squad

Leader

5 Park Todd Frost Pickett

ProjectID Prefix Project Name Funding Intent Letting Cost

B183012 STP-BR 3 VARIOUS LOCATIONS/BRIDGEREHAB Federal BRIDGE REHAB $1,900,000

Sum: $1,900,000

Dist. County PlansReceived Resident Squad

Leader

3 Various Yes Damon Newsome Pickett

ProjectID Prefix Project Name Funding Intent Letting Cost

PEG1951 PEG 5 VARIOUS LOCATIONS/STOCKPILE/19 State STOCKPILE $900,000

Sum: $900,000

Dist. County PlansReceived Resident Squad

Leader

5 Various Michael E. Miller Potter

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

September 12, 2019 Sheridan September 19, 2019 July 12, 2019 August 15, 2019 7 $27,000,000

9/26 4/22/19

Page 10: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

N432055 NHPP 4 DOUGLAS-GILLETTE/WRIGHTSECTION W/N432056 Federal WIDEN TO 5-LANE/OVERLAY $15,500,000

N432056 NHPP-RF 4 (w/ N432055) WRIGHT-GILLETTE/ROW FENCE Federal REPLACE ROW FENCE $400,000

Sum: $15,900,000

Dist. County PlansReceived Resident Squad

Leader

4 Campbell Yes Josh Jundt Doering

ProjectID Prefix Project Name Funding Intent Letting Cost

I254155 NHPPI 2 CASPER-KAYCEE/HORSE RANCHCREEK NORTH Federal MILL/LEVEL/2" OVERLAY $6,900,000

Sum: $6,900,000

Dist. County PlansReceived Resident Squad

Leader

2 Natrona Yes Chad Aagard DePew

ProjectID Prefix Project Name Funding Intent Letting Cost

P261029 SCP-TC 1 LARAMIE-WOODS LANDING/HARMONY/WYO 230 State MILL/OVERLAY/SEAL COAT $4,800,000

Sum: $4,800,000

Dist. County PlansReceived Resident Squad

Leader

1 Albany Yes Steve Cook Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

I805178 NHPPI 1 LARAMIE- CHEYENNE/TELEPHONECANYON Federal HPWC/BRIDGE REHAB $4,000,000

Sum: $4,000,000

Dist. County PlansReceived Resident Squad

Leader

1 Albany Steve Cook Potter

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

October 10, 2019 Rock Springs October 17, 2019 August 9, 2019 September 12, 2019 10 $35,000,000

10/26 4/22/19

Page 11: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

B202009 STP-PM 2 VARIOUS LOCATIONS/CRACKSEAL Federal CRACK SEAL $1,000,000

Sum: $1,000,000

Dist. County PlansReceived Resident Squad

Leader

2 Various Buck Klemola Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B203017 STP-PM 3 VARIOUS LOCATIONS/CRACKSEAL Federal CRACK SEAL $900,000

Sum: $900,000

Dist. County PlansReceived Resident Squad

Leader

3 Various Clint Lockman Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B201002 STP-PM 1 VARIOUS LOCATIONS/CRACKSEAL Federal CRACK SEAL $500,000

Sum: $500,000

Dist. County PlansReceived Resident Squad

Leader

1 Albany Steve Cook Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

N202075 NHPP-GM 5 VARIOUS LOCATIONS SOUTHHALF CULVERT CLEANING Federal CULVERT CLEANING & SIPHON $500,000

Sum: $500,000

Dist. County PlansReceived Resident Squad

Leader

5 Fremont Erik Smith Doering

ProjectID Prefix Project Name Funding Intent Letting Cost

B205013 STP-PM 5 VARIOUS LOCATIONS/CRACKSEAL Federal CRACK SEAL $300,000

Sum: $300,000

Dist. County PlansReceived Resident Squad

Leader

5 Various Erik Smith Potter

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

October 10, 2019 Rock Springs October 17, 2019 August 9, 2019 September 12, 2019 10 $35,000,000

11/26 4/22/19

Page 12: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

W413005 CMP-PM 3 WYOMING 13/CRACK SEAL State CRACK SEAL $200,000

Sum: $200,000

Dist. County PlansReceived Resident Squad

Leader

3 Uinta Clint Lockman Potter

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

October 10, 2019 Rock Springs October 17, 2019 August 9, 2019 September 12, 2019 10 $35,000,000

12/26 4/22/19

Page 13: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

N103103 NHPP 3 THAYNE-ALPINE/ETNA NORTH *PODI* Federal WIDEN 5 LANES $21,600,000

Sum: $21,600,000

Dist. County PlansReceived Resident Squad

Leader

3 Lincoln Yes Darrin Robinson DePew

ProjectID Prefix Project Name Funding Intent Letting Cost

0510001 SCP 2 (w/N431035) DOUGLAS-GILLETTE/DOUGLA NORTH/SERVICE ROAD State RESURFACING $300,000

B202032 STP 2 (w/N431035) DOUGLAS-GILLETTE/DOUGLAS NORTH State RESURFACE $1,000,000

N431035 NHPP2 DOUGLAS-GILLETTE/DOUGLASNORTH/WY59 BYPASS W/B202032,N431036, 0510001

Federal MILL/OVERLAY/AUX&PASSING LANES $12,000,000

N431036 STP-E 2 (w/ N431035) DOUGLAS-GILLETTE/DOUGLAS NORTH Federal GATEWAY SIGN $100,000

Sum: $13,400,000

Dist. County PlansReceived Resident Squad

Leader

2 Converse Yes James Barnes Doering

ProjectID Prefix Project Name Funding Intent Letting Cost

N853092 NHPP 2 LINGLE-LUSK/RAWHIDE SECTION Federal MILL/OVERLAY $5,900,000

Sum: $5,900,000

Dist. County PlansReceived Resident Squad

Leader

2 Goshen Buck Klemola Pickett

ProjectID Prefix Project Name Funding Intent Letting Cost

N343044 NHPP 5 THERMOPOLIS STREETS/US 20/WYO 789 Federal MILL/OVRLY/CHIP SEAL/ADA/DRAIN $3,900,000

Sum: $3,900,000

Dist. County PlansReceived Resident Squad

Leader

5 Hot Springs Yes Kaia Tharp Kladianos

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

November 14, 2019 Laramie November 21, 2019 September 13, 2019 October 17, 2019 8 $53,500,000

13/26 4/22/19

Page 14: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

P182032 SCP-TC 1 CRESTON JUNCTION-BAGGS/MUDDY CREEK NORTH State MILL/OVERLAY/SEAL COAT $3,500,000

Sum: $3,500,000

Dist. County PlansReceived Resident Squad

Leader

1 Carbon Yes Jake Lonn Kladianos

ProjectID Prefix Project Name Funding Intent Letting Cost

0302089STP-BR

4 BUFFALO-GILLETTE/WILDCATCREEK w/ 0302090 Federal BRIDGE REPLACEMENT $1,500,000

0302090 4 (w/ 0302089) BUFFALO-GILLETTE/RAWHIDE CREEK Federal BRIDGE REPLACEMENT $1,800,000

Sum: $3,300,000

Dist. County PlansReceived Resident Squad

Leader

4 Campbell Josh Jundt Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B201006 STP-BR 1 VARIOUS LOCATIONS BRIDGEREHAB Federal EPXY OVRLY/EXPANSION/MINOR REH $1,000,000

Sum: $1,000,000

Dist. County PlansReceived Resident Squad

Leader

1 Laramie Wayne Shenefelt Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

CN18058 STP-BROS 4 CROOK COUNTY/BELLE FOURCHEBRDG/DXQ Federal BRIDGE REPLACEMENT $900,000

Sum: $900,000

Dist. County PlansReceived Resident Squad

Leader

4 Crook Preston Beckstead Pickett

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

November 14, 2019 Laramie November 21, 2019 September 13, 2019 October 17, 2019 8 $53,500,000

14/26 4/22/19

Page 15: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

I806209 NHPPI 1 CHEYENNE/PINE BLUFFS/HILLSDALE SECTION *PODI* Federal LVL/OVRLY/SEALCOAT/REPL 2 STRC $21,600,000

Sum: $21,600,000

Dist. County PlansReceived Resident Squad

Leader

1 Laramie Kevin Erickson Stogsdill

ProjectID Prefix Project Name Funding Intent Letting Cost

B202010 STP-BR 2 VARIOUS LOCATIONS/BRIDGEREHAB Federal BRIDGE REHAB $5,300,000

Sum: $5,300,000

Dist. County PlansReceived Resident Squad

Leader

2 Various Tim Rasnake Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

N852004SCP-TC

1 CHEYENNE- TORRINGTON/GUNBARREL NORTH W/ N852005 State MILL/OVERLAY/SEAL COAT $2,000,000

N852005 1 (w/ N852004) CHEYENNE-TORRINGTON/GUN BARREL NORTH State MILL/OVERLAY/SEAL COAT $2,200,000

Sum: $4,200,000

Dist. County PlansReceived Resident Squad

Leader

1 Laramie Wayne Shenefelt Pickett

ProjectID Prefix Project Name Funding Intent Letting Cost

B201004 STP-PM 1 VARIOUS LOCATIONS/SLABREPAIR Federal SLAB REPAIR $1,500,000

Sum: $1,500,000

Dist. County PlansReceived Resident Squad

Leader

1 Laramie Kevin Erickson Potter

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

December 11, 2019 Sheridan December 18, 2019 October 10, 2019 November 13, 2019 5 $33,800,000

15/26 4/22/19

Page 16: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

B203019 STP-BR 3 VARIOUS LOCATIONS/BRIDGEREHAB/NORTH Federal BRIDGE REHAB $1,200,000

Sum: $1,200,000

Dist. County PlansReceived Resident Squad

Leader

3 Various Daniel McGillivray Potter

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

December 11, 2019 Sheridan December 18, 2019 October 10, 2019 November 13, 2019 5 $33,800,000

16/26 4/22/19

Page 17: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

I254160 NHPPI 2 CASPER MARGINAL/STRUCTURESw/I254165 *PODI* Federal REMOVE AND REPLACE STRUCTURES $23,300,000

I254165 STP-E 2 (w/ I254160) CASPER /I-25/WALSHDRIVE Federal ENHANCEMENTS $500,000

Sum: $23,800,000

Dist. County PlansReceived Resident Squad

Leader

2 Natrona Chad Aagard Pickett

ProjectID Prefix Project Name Funding Intent Letting Cost

N332033 NHPP 5 MEETEETSE-CODY/CODY SOUTH Federal LEVEL/OVERLAY/CHIP SEAL/ISO RE $5,500,000

Sum: $5,500,000

Dist. County PlansReceived Resident Squad

Leader

5 Park Todd Frost Kladianos

ProjectID Prefix Project Name Funding Intent Letting Cost

0104064 SCP-TC 1 LARAMIE HERRICK LANE/WYO 12 State OVERLAY/SEAL COAT $4,400,000

Sum: $4,400,000

Dist. County PlansReceived Resident Squad

Leader

1 Albany Kory Cramer Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B203016 STP-PM 3 VARIOUS LOCATIONS/CONTRACTPATCH Federal CONTRACT PATCH $2,800,000

Sum: $2,800,000

Dist. County PlansReceived Resident Squad

Leader

3 Various Clint Lockman Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B202011 STP-PM 2 VARIOUS LOCATIONS/CONTRACTPATCH Federal CONTRACT PATCHING $2,500,000

Sum: $2,500,000

Dist. County PlansReceived Resident Squad

Leader

2 Various Jack Stone Potter

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

January 9, 2020 January 16, 2020 November 8, 2019 December 12, 2019 11 $48,200,000

17/26 4/22/19

Page 18: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

B201003 STP-PM 1 VARIOUS LOCATIONS/CONTRACTPATCHING Federal CONTRACT PATCHING $2,200,000

Sum: $2,200,000

Dist. County PlansReceived Resident Squad

Leader

1 Carbon Wayne Shenefelt Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B203018 STP-PM 3 VARIOUS LOCATIONS/CHIP SEAL Federal CHIP SEAL $2,100,000

Sum: $2,100,000

Dist. County PlansReceived Resident Squad

Leader

3 Various Clint Lockman Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

PEG2031 PEG 3 VARIOUS LOCATIONS/STOCKPILE/20 State STOCKPILE $1,600,000

Sum: $1,600,000

Dist. County PlansReceived Resident Squad

Leader

3 Various Jennifer Hoffman Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B202008 STP-PM 2 VARIOUS LOCATIONS/CHIP SEAL Federal CHIP SEAL $1,500,000

Sum: $1,500,000

Dist. County PlansReceived Resident Squad

Leader

2 Various Tim Rasnake Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B201001 STP-PM 1 VARIOUS LOCATIONS/CHIP SEAL Federal CHIP SEAL $1,000,000

Sum: $1,000,000

Dist. County PlansReceived Resident Squad

Leader

1 Various Kevin Erickson Potter

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

January 9, 2020 January 16, 2020 November 8, 2019 December 12, 2019 11 $48,200,000

18/26 4/22/19

Page 19: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

CN19036 STP-BROS 3 UINTA COUNTY/SULPHUR CREEK/STRUCTURE FKL Federal BRIDGE REPLACEMENT $800,000

Sum: $800,000

Dist. County PlansReceived Resident Squad

Leader

3 Uinta Damon Newsome Potter

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

January 9, 2020 January 16, 2020 November 8, 2019 December 12, 2019 11 $48,200,000

19/26 4/22/19

Page 20: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

B204025 STP-BR 4 VARIOUS LOCATIONS/BRIDGEREHAB Federal BRIDGE REHAB $3,500,000

Sum: $3,500,000

Dist. County PlansReceived Resident Squad

Leader

4 Various Josh Jundt Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B201005 STP-BR 1 VARIOUS LOCATIONS/BRIDGEREHAB Federal BRIDGE REHAB $3,400,000

Sum: $3,400,000

Dist. County PlansReceived Resident Squad

Leader

1 Laramie Wayne Shenefelt Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

I251170 HSIP 1 CHEYENNE MARGINAL/STRIPINGTAPE Federal STRIPING TAPE $1,600,000

Sum: $1,600,000

Dist. County PlansReceived Resident Squad

Leader

1 Laramie Wayne Shenefelt Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B209028 HSIP STATEWIDE/VARIOUS LOCATIONS/EPOXY STRIPING Federal EPOXY STRIPING $1,100,000

Sum: $1,100,000

Dist. County PlansReceived Resident Squad

Leader

SW Various None Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

W258025 HSIP2 CASPER STREETS/WYOMINGBLVD/GANNET DRIVE TOYELLOWSTONE STREET

Federal INTERSECTION MARKINGS $500,000

Sum: $500,000

Dist. County PlansReceived Resident Squad

Leader

2 Natrona None Potter

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

February 13, 2020 February 20, 2020 December 13, 2019 January 16, 2020 7 $10,700,000

20/26 4/22/19

Page 21: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

B201007 HSIP 1 THERMOPLASTIC MARKINGS Federal THERMOPLASTIC MARKING $300,000

Sum: $300,000

Dist. County PlansReceived Resident Squad

Leader

1 Various Wayne Shenefelt Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B202012 HSIP 2 THERMOPLASTIC MARKINGS Federal THERMOPLASTIC MARKING $300,000

Sum: $300,000

Dist. County PlansReceived Resident Squad

Leader

2 Various Chad Aagard Potter

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

February 13, 2020 February 20, 2020 December 13, 2019 January 16, 2020 7 $10,700,000

21/26 4/22/19

Page 22: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

N302054 NHPP 5 DUBOIS-DIVERSION DAM Federal LEVEL/OVRLY/CHIPSEAL/ROW FENCE $5,300,000

Sum: $5,300,000

Dist. County PlansReceived Resident Squad

Leader

5 Fremont Yes Robert Scheidemantel DePew

ProjectID Prefix Project Name Funding Intent Letting Cost

N202072 NHPP 5 MUDDY GAP-LANDER/BEAVER RIM Federal MILL/2" OVERLAY/CHIP SEAL/MISC $3,600,000

Sum: $3,600,000

Dist. County PlansReceived Resident Squad

Leader

5 Fremont Erik Smith Stogsdill

ProjectID Prefix Project Name Funding Intent Letting Cost

B205014 STP-BR 5 VARIOUS LOCATIONS/BRIDGEREHAB Federal BRIDGE REHABILITATION $3,300,000

Sum: $3,300,000

Dist. County PlansReceived Resident Squad

Leader

5 Various Kaia Tharp Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B152040 STPU 2 CONVERSE COUNTY/BROWNFIELD ROAD/ROBIN ROAD Federal RECONSTRUCTION $2,600,000

Sum: $2,600,000

Dist. County PlansReceived Resident Squad

Leader

2 Converse James Barnes DePew

ProjectID Prefix Project Name Funding Intent Letting Cost

B205031 STP-GM 5 VARIOUS LOCATIONS GUARDRAIL Federal GUARDRAIL $800,000

Sum: $800,000

Dist. County PlansReceived Resident Squad

Leader

5 Fremont Robert Scheidemantel Potter

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

March 12, 2020 March 19, 2020 January 10, 2020 February 13, 2020 7 $16,600,000

22/26 4/22/19

Page 23: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

B215001 STP-RF 5 VARIOUS LOCATIONS/SOUTHDISTRICT/FENCING Federal RIGHT OF WAY FENCING $600,000

Sum: $600,000

Dist. County PlansReceived Resident Squad

Leader

5 Fremont Robert Scheidemantel Stogsdill

ProjectID Prefix Project Name Funding Intent Letting Cost

B183033 SSP-TO 3 I-80/US 89/ROAD CLOSURE &LUMINAIRES State ROAD CLOSURE/LUMINAIRES $400,000

Sum: $400,000

Dist. County PlansReceived Resident Squad

Leader

3 Various Yes Jennifer Hoffman

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

March 12, 2020 March 19, 2020 January 10, 2020 February 13, 2020 7 $16,600,000

23/26 4/22/19

Page 24: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

B123014 STPU-RO 3 ROCK SPRINGS STS/INTERCHANGE ROAD w/ I802220 Federal RECONSTRUCTION $10,800,000

I802220 INFRA3 (w/ B123014) ROCK SPRINGS/I-80INTERCHANGE & INTERCHANGEROAD

Federal RECONST/INTERCHANGE/BRIDGE $11,500,000

Sum: $22,300,000

Dist. County PlansReceived Resident Squad

Leader

3 Sweetwater Peter Stinchcomb DePew

ProjectID Prefix Project Name Funding Intent Letting Cost

B193020 STP 3 VARIOUS LOCATIONS/ITS Federal VLS/RWIS/WEB CAM/FLASHING SIGN $1,000,000

Sum: $1,000,000

Dist. County PlansReceived Resident Squad

Leader

3 Various Peter Stinchcomb Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

I805181 HSIP 1 I-80/SIGN UPGRADE Federal SIGN UPGRADES $900,000

Sum: $900,000

Dist. County PlansReceived Resident Squad

Leader

1 Albany None Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B209029 HSIP STATEWIDE/CORRIDOR PENNANTSIGNING Federal PENNANT SIGNING $900,000

Sum: $900,000

Dist. County PlansReceived Resident Squad

Leader

SW Various None Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B209030 HSIP STATEWIDE/SIGN UPGRADE Federal NEW/UPGRD WARNING/GUIDE SIGNS $500,000

Sum: $500,000

Dist. County PlansReceived Resident Squad

Leader

SW Various None Potter

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

April 9, 2020 April 16, 2020 February 7, 2020 March 12, 2020 8 $26,500,000

24/26 4/22/19

Page 25: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

B203021 HSIP 3 THERMOPLASTIC MARKINGS Federal THERMOPLASTIC MARKINGS $300,000

Sum: $300,000

Dist. County PlansReceived Resident Squad

Leader

3 Various None Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B204027 HSIP 4 THERMOPLASTIC MARKINGS Federal THERMOPLASTIC MARKING $300,000

Sum: $300,000

Dist. County PlansReceived Resident Squad

Leader

4 Various Jerry Buckley Potter

ProjectID Prefix Project Name Funding Intent Letting Cost

B205015 HSIP 5 THERMOPLASTIC MARKINGS Federal THERMOPLASTIC MARKINGS $300,000

Sum: $300,000

Dist. County PlansReceived Resident Squad

Leader

5 Various Michael E. Miller Potter

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

April 9, 2020 April 16, 2020 February 7, 2020 March 12, 2020 8 $26,500,000

25/26 4/22/19

Page 26: May 9, 2019 May 16, 2019 9 $64,100,000 · 2019-04-22 · 4 BURGESS JUNCTION/DAYTON/ WHITE CROSS SLIDE Federal SLIDE REPAIR $3,000,000 Sum: $3,000,000 Dist. County Plans Received Resident

STATE TRANSPORTATION IMPROVEMENT PROJECTSWyoming Department of TransportationLetting Events Between May 9, 2019 and May 14, 2020

ProjectID Prefix Project Name Funding Intent Letting Cost

N361068 NHPP 5 WORLAND-BUFFALO/TENSLEEPEAST Federal MILL/OVERLAY/CHIP SEAL $3,100,000

Sum: $3,100,000

Dist. County PlansReceived Resident Squad

Leader

5 Washakie Michael E. Miller Crosby

Scheduled Letting To Be Held At Award Date Due Date PS&E Advertising Date Total Projects Total for Month

May 14, 2020 May 21, 2020 March 13, 2020 April 16, 2020 1 $3,100,000