THE MUSIAL GROUP ARCHITECTURE
Mayor Lawrence D. QuattroneCouncil President Steven MisiuraCouncil Member Joshua JacksonCouncil Member Patricia EganCouncil Member Charles “Lee” StultsCouncil Member Susan BluthCouncil Member Dimitri Musing
Chief Frank Gendron
1 JULY 2019
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
PROJECT TEAM
Noel S. Musial, A.I.A., PP NCARBPresident
Noel S. Musial II, AIAProject Manager
Larry Lane, AIAProject Architect
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
2
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
YOUR VISION BOARD
3
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
YOUR VISION ACTIVITY BLOCKS
4
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
PUBLIC PRIORITIES
5
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
6
PUBLIC PRIORITIES
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
7
PUBLIC PRIORITIES
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
8
PUBLIC PRIORITIES
Public Input
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
9
PUBLIC PRIORITIES
• Exterior Sculpture Garden
• Interior Art Gallery
• Public Meeting Rooms
• Access to Nearby Paths to Park and Foot Path
• Display Historic Items, such as the Bell from the Existing School House
• Example to the Community of a Sustainable Design
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
Two schemes were developed after interviewing the future users of the facility
10
The police department will adjoin the existing building.
The existing building will house the municipal functions
1. Scheme One: Police will be a one story building.
2. Scheme Two: Police will be a two story building.
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
SPACE REQUIREMENTS FOR THE TWO SCHEMES
11
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
SPACE REQUIREMENTS FOR DEPARTMENTSSCHEME 1
12
Additional space will be requiredfor file archives
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
SPACE REQUIREMENTS FOR DEPARTMENTSSCHEME 2
13
Additional space will be requiredfor file archives
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
SCHEME 1: SITE PLAN
14
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
SCHEME 1: FIRST FLOOR
15
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
SCHEME 1: SECOND FLOOR
16
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
SCHEME 1: BASEMENT
17
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
SCHEME 2: SITE PLAN
18
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
SCHEME 2: FIRST FLOOR
19
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
SCHEME 2: SECOND FLOOR
20
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
SCHEME 2: BASEMENT
21
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
SCHEME 2: BUILDING SECTION
22
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
SCHEME 2
23
SCHEME 2
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
SCHEME 2
24
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
SCHEME 2
25
THE MUSIAL GROUP ARCHITECTURE
HIGHTSTOWN BOROUGH MUNICIPAL FACILITIES
COST ESTIMATES
26
THE MUSIAL GROUP ARCHITECTURE
191 Mill LaneMountainside, NJ 07092p. 908.232.2860 f. 908.232.2845www.themusialgroup.com
27