meg review at brookhaven, feb 5, 2004 : cms si tracker project: j. incandela 1 us cms silicon...

17
MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation Group Meeting Joe Incandela University of California Santa Barbara US CMS Silicon Tracker Project Manager February 5, 2004 Outline: Project overview and Status Schedule and Project Completion Installation and Commissioning, Maintenance and Operations R&D for upgrades

Post on 19-Dec-2015

218 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation

MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1

US CMS Silicon TrackerUS CMS Silicon Tracker

US LHC DetectorMaintenance and Operations

Evaluation Group Meeting

Joe Incandela

University of California Santa Barbara

US CMS Silicon Tracker Project ManagerFebruary 5, 2004

Outline:Project overview and Status

Schedule and Project Completion

Installation and Commissioning, Maintenance and Operations

R&D for upgrades

Page 2: MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation

MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 2

US Silicon Tracker GroupUS Silicon Tracker Group• Fermilab (FNAL)

• L. Spiegel, S. Tkaczyk, A. Rhonzin, + technicians

• Kansas State University (KSU)

• T.Bolton, W.Kahl, R.Sidwell, N.Stanton

• University of California, Riverside (UCR)

• Gail Hanson, Gabriella Pasztor, Patrick Gartung

• University of California, Santa Barbara (UCSB)• A. Affolder, A. Allen, D. Barge, S. Burke, D. Calahan, C.Campagnari, D. Hale, (C. Hill),

J.Incandela, S. Kyre, J. Lamb, C. McGuinness, D. Staszak, L. Simms, J. Stoner, S. Stromberg, (D. Stuart), R. Taylor, D. White

• University of Illinois, Chicago (UIC)

• E. Chabalina, C. Gerber, T. Timor

• University of Kansas (KU)

• P. Baringer, A. Bean, L. Christofek, X. Zhao

• University of Rochester (UR)

• R.Demina, R. Eusebi, E. Halkiadakis, A. Hocker, S.Korjenevski, P. Tipton

• Mexico:3 institutes led by Cinvestav Cuidad de Mexico

• 2 more groups are in the process of joining us

Page 3: MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation

MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 3

US ResponsibilitiesUS Responsibilities

5.4 m

2.4

m

Outer Barrel (TOB)

~105 m2

NEW:End Caps (TEC)

50% Modules for Rings 5 and 6 and

hybrid processing for Rings 2,5,6

Page 4: MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation

ROD INTEGRATION

AachenKarlsruheStrasbourgZurichWien

PETALS INTEGRATION Aachen

Brussels Karlsruhe

Louvain

Lyon Strasbourg

BrusselsWien Lyon

TEC assemblyTEC assembly

CERN

Frames:

BrusselsSensors:factories

Hybrids:Strasbourg

Pitch adapter:Brussels

Hybrid:CF carrier

TK ASSEMBLYAt CERN

LouvainStrasbourg

Pisa Perugia Wien

BariPerugia

Bari FirenzeTorinoPisaPadova

TIB-TID INTEGRATION

FNAL

UCSB

TOB assembly TIB-ID assemblyAt CERN Pisa Aachen Karlsruhe. --> Lyon

Karlsruhe

Pisa

Sensor QAC

Moduleassembly

Bonding &testing

Sub-assemblies

FNAL

US CMS trackerresponsibilities

Integrationinto mechanics

KSU

FNAL UCSB

UCSB

UCSB

Page 5: MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation

MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 5

Outer Barrel ProductionOuter Barrel Production

• Outer Barrel • Modules

• 4128 Axial (Installed)• 1080 Stereo (Installed)

• Rods • 508 Single-sided • 180 Double-sided

•US Tasks• All final hybrid bonding &

test• All Module assembly & test• All Rod assembly & test

• Joint Responsibilities with CERN• Installation &

Commissioning• Maintenance and Operation

~20 cm

Page 6: MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation

MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 6

End Cap ConstructionEnd Cap Construction

• TEC group unable to produce all types of TEC modules. • TEC schedule was threatened.

• Central European Consortium requested US help

• We agreed to produce up to 2000 R5 and R6 modules• UCSB successfully built the R6 module above.

• Nearly ready to go on R5

Page 7: MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation

MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 7

Production ImprovementsProduction Improvements• Gantry (robotic) module assembly

• Redesigned • More robust, flexible, easily

maintained• Surveying and QA

• Automated independent system (OGP)• More efficient, accurate, fail-safe

•Module Wirebonding• Developed fully automated wirebonding

• Faster and more reliable bonding • Negligible damage or rework

•Taken together:• Major increase in US capabilities• Higher quality

Page 8: MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation

MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 8

Module and Rod Testing & QAModule and Rod Testing & QA

•Problems caught by US groups• Defective hybrid cables

• Vibration damage Common Mode Noise traced to ST sensors

• Faulty pipeline cells in APVs

•Rod Production• Have built 3 rods so far

• Will build and test all of the 688 rods (+10% spares) in the TOB

Page 9: MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation

MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 9

Tracker ScheduleTracker Schedule

Task Name Start FinishAssembly of M200 at gantry 12/3/01 2/28/02Pre-series sensors (ST) 2/7/02 5/20/02Production sensors (ST) 5/7/02 12/23/03Start delivery of TOB sensors to gantry centers 5/21/02Frames production 7/1/02 9/3/04Start delivery of TOB frames to gantry centers 7/22/02Hybrids pre-production 2/11/02 4/1/02Assembly 400 hybrids 6/19/02 9/10/02Start delivery of 1st batch of 100 hybrids to gantry centers 4/15/02Start delivery of 2nd batch of 250 hybrids to gantry centers 7/31/02Start delivery of production hybrids to gantry centers 11/19/03TOB Module Construction* (J.I.) 1/26/04 ?First 8 production FED delivered 6/1/03Installation of TOB modules on rods 1/30/04 ?Installation of rods in mechanics 4/1/04 ?TOB complete ?

ST has not yet been officially qualified to produce sensors!

We find serious quality and/or robustness issues

As a result production schedule is slipping!

Fortunately we have increased our capacity.

Page 10: MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation

MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 10

Current situationCurrent situation

• US production readiness• Both production lines can produce 15 modules per day.

• UCSB recently completed 75 modules in one week.• FNAL about to perform a similar exercise

• This is almost double our initial expectations and could be exceeded for short periods.

• Components• All components are procured by European groups

• Hybrids now look ok. Deliveries at high rates• Frames, rod frames etc. all coming in ok

• ST sensors are a serious concern• Possible evidence of deterioration over time• Attempting to move production to Hamamatsu Photonics Corp.

• Situation is ‘delicate’ vis-à-vis the ST contract

• Delays…

Page 11: MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation

MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 11

Project end & Transition to M&OProject end & Transition to M&O

• We assume we will be needed to cover at least half of the effort of installation and commissioning (I&C) of the TOB.

• Installation/testing of rods in wheels (April 04 – ?).• 2-4 FTE Sr. Physicists, 7 Post-docs, students.

• Testing modules on rods before installation.• Limited system tests.

• 1 FTE Engineer (base).• Rod & Module repairs, cooling system, mechanics.

• Laboratory space and equipment for testing and repairs.• For maintenance and operation (M&O) of the TOB we want a

team that could provide continuous support in all 6 areas of operation.

• In late 2005, large M&O support team must be in place.• We estimate 12 physicists at CERN together with

continued engineering and technical support & associated M&S and operating costs for maintaining a small laboratory space for testing and repairs.

Page 12: MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation

MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 12

M&O for Tracker Outer Barrel*M&O for Tracker Outer Barrel*1. Operation 3-4 phys., 1 tech.

• 24/7 on-call to avoid dead time.• Includes Leadership: to organize

overall effort, make executive decisions for effort allocation and interpretation of diagnostics results.

• Interface with experiment and rest of CMS admin. (1 FTE of overhead).

2. DAQ – 2-3 phys., 0.5-1.0 Eng., 2 tech.• Front end and upper level modules.

• FEDs and EB managers.• Diagnostics, testing,

repairs, re-testing, swapping of critical DAQ modules.

3. Radiation protection and cooling 2-3 phys. 0.5-1.0 engineer, 1-2 tech.• Monitoring, repair.• System issues: cooling tech present

at all times dealing with problems as they arise.

4. Power supplies. 1-2 phys, 1-2 tech.• Startup crucial. Techs needed for

testing all supplies prior to installation, then retest after installation.

• Safety interlock issue. A serious ongoing maintenance issue.

5. Monitoring and calibration databases 1-2 physicists at CERN.

• Need some resident presence for calibrations.

• CDF does this remotely and sees remote calibration control to be a serious problem.

• We expect a much larger population (possibly students) will work remotely.

• Need to catch problems in data and in calibration techniques.

• Significant effort to maintain good channel list.

6. Alignment 1-2 phys., ½ tech.• Laser alignment runs, hardware

maintenance.• Offline alignment and monitoring of

alignment constants.

*Based upon Run 2 Tevatron silicon experience

Page 13: MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation

MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 13

M&O Cost EstimateM&O Cost Estimate

Silicon Tracker M&O Cost Estimate FY02-FY08 Total $1,250,735 AY$

050

100150200250300350400450500

FY02 FY03 FY04 FY05 FY06 FY07 FY08

AY

$k

Labor

M&S

Page 14: MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation

MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 14

US CMS SITRK M&O ResourcesUS CMS SITRK M&O Resources

•Manpower on Base• All Post-docs and one engineer.

• Too early to identify by name.

• Post-docs mainly redirected from other programs or the production effort but expect a small number of new positions could be requested.

•Manpower on Project• All technicians and non-base engineering.

US CMS Silicon Tracker M&O Resources

02468

101214161820

FY02 FY03 FY04 FY05 FY06 FY07 FY08

FT

E's

Technicians

Engineers

Physicists

Page 15: MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation

MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 15

Response to April ‘03 ReviewResponse to April ‘03 Review

“The manpower and M&O cost estimate for the TOB are internally consistent, but should be reviewed by the collaboration management to see if adequate resources are available within U.S. CMS or the CMS collaboration at large, given the CDF Run II experience.”

Response:

Our main goal is to have at least the minimum required to have a continuous presence in all 6 areas of operation of the microstrip tracker. We do not need to have more than this because all other tracker subsystems will provide manpower and the operation of the tracker as a whole will be shared by everyone, due to the commonality of the electronics from front-end to DAQ.

Note however, we do not want to have less than this since we could not have significant involvement in all of the main areas of operation.

Finally, several new groups have joined and we will encourage them to add some support to our presence at CERN.

Page 16: MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation

MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 16

Upgrade R&D IssuesUpgrade R&D Issues

• CMS silicon has limited lifetime.• 10 years of operation (we hope).

• Further, possibly higher luminosity running will require more rad-hard silicon than currently exists.

• R&D for current silicon took many years.

• Expect to participate in future efforts at least at the level of prototyping and testing silicon or silicon-alternative designs.

• 60k$ per year M&S (not included in current budgets)

• Now preparing a proposal at this level for FY04

Page 17: MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1 US CMS Silicon Tracker US LHC Detector Maintenance and Operations Evaluation

MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 17

Summary & ConclusionsSummary & Conclusions

• US Groups now responsible for building and testing more than half of the silicon strip tracker

• We are ready for high throughput.

• Most components ok and in high rate production.• ST sensor issue is serious: no clear solution in sight

• We are still planning to complete the project in FY05

• Based on CDF/D0 experience, significant resources will be needed for I&C and M&O.

• We estimate ~12 post-docs plus engineering and technical support to allow US to have significant involvement in all aspects of operations