meg review at brookhaven, feb 5, 2004 : cms si tracker project: j. incandela 1 us cms silicon...
Post on 19-Dec-2015
218 views
TRANSCRIPT
MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 1
US CMS Silicon TrackerUS CMS Silicon Tracker
US LHC DetectorMaintenance and Operations
Evaluation Group Meeting
Joe Incandela
University of California Santa Barbara
US CMS Silicon Tracker Project ManagerFebruary 5, 2004
Outline:Project overview and Status
Schedule and Project Completion
Installation and Commissioning, Maintenance and Operations
R&D for upgrades
MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 2
US Silicon Tracker GroupUS Silicon Tracker Group• Fermilab (FNAL)
• L. Spiegel, S. Tkaczyk, A. Rhonzin, + technicians
• Kansas State University (KSU)
• T.Bolton, W.Kahl, R.Sidwell, N.Stanton
• University of California, Riverside (UCR)
• Gail Hanson, Gabriella Pasztor, Patrick Gartung
• University of California, Santa Barbara (UCSB)• A. Affolder, A. Allen, D. Barge, S. Burke, D. Calahan, C.Campagnari, D. Hale, (C. Hill),
J.Incandela, S. Kyre, J. Lamb, C. McGuinness, D. Staszak, L. Simms, J. Stoner, S. Stromberg, (D. Stuart), R. Taylor, D. White
• University of Illinois, Chicago (UIC)
• E. Chabalina, C. Gerber, T. Timor
• University of Kansas (KU)
• P. Baringer, A. Bean, L. Christofek, X. Zhao
• University of Rochester (UR)
• R.Demina, R. Eusebi, E. Halkiadakis, A. Hocker, S.Korjenevski, P. Tipton
• Mexico:3 institutes led by Cinvestav Cuidad de Mexico
• 2 more groups are in the process of joining us
MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 3
US ResponsibilitiesUS Responsibilities
5.4 m
2.4
m
Outer Barrel (TOB)
~105 m2
NEW:End Caps (TEC)
50% Modules for Rings 5 and 6 and
hybrid processing for Rings 2,5,6
ROD INTEGRATION
AachenKarlsruheStrasbourgZurichWien
PETALS INTEGRATION Aachen
Brussels Karlsruhe
Louvain
Lyon Strasbourg
BrusselsWien Lyon
TEC assemblyTEC assembly
CERN
Frames:
BrusselsSensors:factories
Hybrids:Strasbourg
Pitch adapter:Brussels
Hybrid:CF carrier
TK ASSEMBLYAt CERN
LouvainStrasbourg
Pisa Perugia Wien
BariPerugia
Bari FirenzeTorinoPisaPadova
TIB-TID INTEGRATION
FNAL
UCSB
TOB assembly TIB-ID assemblyAt CERN Pisa Aachen Karlsruhe. --> Lyon
Karlsruhe
Pisa
Sensor QAC
Moduleassembly
Bonding &testing
Sub-assemblies
FNAL
US CMS trackerresponsibilities
Integrationinto mechanics
KSU
FNAL UCSB
UCSB
UCSB
MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 5
Outer Barrel ProductionOuter Barrel Production
• Outer Barrel • Modules
• 4128 Axial (Installed)• 1080 Stereo (Installed)
• Rods • 508 Single-sided • 180 Double-sided
•US Tasks• All final hybrid bonding &
test• All Module assembly & test• All Rod assembly & test
• Joint Responsibilities with CERN• Installation &
Commissioning• Maintenance and Operation
~20 cm
MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 6
End Cap ConstructionEnd Cap Construction
• TEC group unable to produce all types of TEC modules. • TEC schedule was threatened.
• Central European Consortium requested US help
• We agreed to produce up to 2000 R5 and R6 modules• UCSB successfully built the R6 module above.
• Nearly ready to go on R5
MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 7
Production ImprovementsProduction Improvements• Gantry (robotic) module assembly
• Redesigned • More robust, flexible, easily
maintained• Surveying and QA
• Automated independent system (OGP)• More efficient, accurate, fail-safe
•Module Wirebonding• Developed fully automated wirebonding
• Faster and more reliable bonding • Negligible damage or rework
•Taken together:• Major increase in US capabilities• Higher quality
MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 8
Module and Rod Testing & QAModule and Rod Testing & QA
•Problems caught by US groups• Defective hybrid cables
• Vibration damage Common Mode Noise traced to ST sensors
• Faulty pipeline cells in APVs
•Rod Production• Have built 3 rods so far
• Will build and test all of the 688 rods (+10% spares) in the TOB
MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 9
Tracker ScheduleTracker Schedule
Task Name Start FinishAssembly of M200 at gantry 12/3/01 2/28/02Pre-series sensors (ST) 2/7/02 5/20/02Production sensors (ST) 5/7/02 12/23/03Start delivery of TOB sensors to gantry centers 5/21/02Frames production 7/1/02 9/3/04Start delivery of TOB frames to gantry centers 7/22/02Hybrids pre-production 2/11/02 4/1/02Assembly 400 hybrids 6/19/02 9/10/02Start delivery of 1st batch of 100 hybrids to gantry centers 4/15/02Start delivery of 2nd batch of 250 hybrids to gantry centers 7/31/02Start delivery of production hybrids to gantry centers 11/19/03TOB Module Construction* (J.I.) 1/26/04 ?First 8 production FED delivered 6/1/03Installation of TOB modules on rods 1/30/04 ?Installation of rods in mechanics 4/1/04 ?TOB complete ?
ST has not yet been officially qualified to produce sensors!
We find serious quality and/or robustness issues
As a result production schedule is slipping!
Fortunately we have increased our capacity.
MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 10
Current situationCurrent situation
• US production readiness• Both production lines can produce 15 modules per day.
• UCSB recently completed 75 modules in one week.• FNAL about to perform a similar exercise
• This is almost double our initial expectations and could be exceeded for short periods.
• Components• All components are procured by European groups
• Hybrids now look ok. Deliveries at high rates• Frames, rod frames etc. all coming in ok
• ST sensors are a serious concern• Possible evidence of deterioration over time• Attempting to move production to Hamamatsu Photonics Corp.
• Situation is ‘delicate’ vis-à-vis the ST contract
• Delays…
MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 11
Project end & Transition to M&OProject end & Transition to M&O
• We assume we will be needed to cover at least half of the effort of installation and commissioning (I&C) of the TOB.
• Installation/testing of rods in wheels (April 04 – ?).• 2-4 FTE Sr. Physicists, 7 Post-docs, students.
• Testing modules on rods before installation.• Limited system tests.
• 1 FTE Engineer (base).• Rod & Module repairs, cooling system, mechanics.
• Laboratory space and equipment for testing and repairs.• For maintenance and operation (M&O) of the TOB we want a
team that could provide continuous support in all 6 areas of operation.
• In late 2005, large M&O support team must be in place.• We estimate 12 physicists at CERN together with
continued engineering and technical support & associated M&S and operating costs for maintaining a small laboratory space for testing and repairs.
MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 12
M&O for Tracker Outer Barrel*M&O for Tracker Outer Barrel*1. Operation 3-4 phys., 1 tech.
• 24/7 on-call to avoid dead time.• Includes Leadership: to organize
overall effort, make executive decisions for effort allocation and interpretation of diagnostics results.
• Interface with experiment and rest of CMS admin. (1 FTE of overhead).
2. DAQ – 2-3 phys., 0.5-1.0 Eng., 2 tech.• Front end and upper level modules.
• FEDs and EB managers.• Diagnostics, testing,
repairs, re-testing, swapping of critical DAQ modules.
3. Radiation protection and cooling 2-3 phys. 0.5-1.0 engineer, 1-2 tech.• Monitoring, repair.• System issues: cooling tech present
at all times dealing with problems as they arise.
4. Power supplies. 1-2 phys, 1-2 tech.• Startup crucial. Techs needed for
testing all supplies prior to installation, then retest after installation.
• Safety interlock issue. A serious ongoing maintenance issue.
5. Monitoring and calibration databases 1-2 physicists at CERN.
• Need some resident presence for calibrations.
• CDF does this remotely and sees remote calibration control to be a serious problem.
• We expect a much larger population (possibly students) will work remotely.
• Need to catch problems in data and in calibration techniques.
• Significant effort to maintain good channel list.
6. Alignment 1-2 phys., ½ tech.• Laser alignment runs, hardware
maintenance.• Offline alignment and monitoring of
alignment constants.
*Based upon Run 2 Tevatron silicon experience
MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 13
M&O Cost EstimateM&O Cost Estimate
Silicon Tracker M&O Cost Estimate FY02-FY08 Total $1,250,735 AY$
050
100150200250300350400450500
FY02 FY03 FY04 FY05 FY06 FY07 FY08
AY
$k
Labor
M&S
MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 14
US CMS SITRK M&O ResourcesUS CMS SITRK M&O Resources
•Manpower on Base• All Post-docs and one engineer.
• Too early to identify by name.
• Post-docs mainly redirected from other programs or the production effort but expect a small number of new positions could be requested.
•Manpower on Project• All technicians and non-base engineering.
US CMS Silicon Tracker M&O Resources
02468
101214161820
FY02 FY03 FY04 FY05 FY06 FY07 FY08
FT
E's
Technicians
Engineers
Physicists
MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 15
Response to April ‘03 ReviewResponse to April ‘03 Review
“The manpower and M&O cost estimate for the TOB are internally consistent, but should be reviewed by the collaboration management to see if adequate resources are available within U.S. CMS or the CMS collaboration at large, given the CDF Run II experience.”
Response:
Our main goal is to have at least the minimum required to have a continuous presence in all 6 areas of operation of the microstrip tracker. We do not need to have more than this because all other tracker subsystems will provide manpower and the operation of the tracker as a whole will be shared by everyone, due to the commonality of the electronics from front-end to DAQ.
Note however, we do not want to have less than this since we could not have significant involvement in all of the main areas of operation.
Finally, several new groups have joined and we will encourage them to add some support to our presence at CERN.
MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 16
Upgrade R&D IssuesUpgrade R&D Issues
• CMS silicon has limited lifetime.• 10 years of operation (we hope).
• Further, possibly higher luminosity running will require more rad-hard silicon than currently exists.
• R&D for current silicon took many years.
• Expect to participate in future efforts at least at the level of prototyping and testing silicon or silicon-alternative designs.
• 60k$ per year M&S (not included in current budgets)
• Now preparing a proposal at this level for FY04
MEG Review at Brookhaven, Feb 5, 2004 : CMS Si Tracker Project: J. Incandela 17
Summary & ConclusionsSummary & Conclusions
• US Groups now responsible for building and testing more than half of the silicon strip tracker
• We are ready for high throughput.
• Most components ok and in high rate production.• ST sensor issue is serious: no clear solution in sight
• We are still planning to complete the project in FY05
• Based on CDF/D0 experience, significant resources will be needed for I&C and M&O.
• We estimate ~12 post-docs plus engineering and technical support to allow US to have significant involvement in all aspects of operations