Minutes of Field Visits in Upper Kunduz sub-basin
(Bamyan)
Project: Rehabilitation of AqRhabat Dam and in-canal works in Ahut, Haidarabad, Juljulac, Dokani, Saidabad canals and canals under Sarequltopchi river in Bamyan District, ref.No: EuropeAid/133110/L/WKS/AF Place of Visits: AqRhabat Dam, Ahut, Haidarabad, Juljulac, Dokani, Saidabad canals and canals under Sarequltopchi river, Bamyan District Upper Kunduz Sub-Basin (NO1). Date of Visit: 26 and 27August, 2012 Time: 8:00 -16:00 hrs.
SN Issue/Question raised Clarification by P-ARBP TA
1 Can we change the volumes of
the project works? For example:
If, in one canal, the canal lining is
100 metres, can we make that 95
or 105 metres after the survey?
The drawing and design available along with the tender documents are merely a concept design and drawing. The successful Tenderer is required to carry out the detailed survey and verify the proposed structures in the field as site conditions and community needs may have changed. The survey must be approved by the supervisor prior to start of the detailed design.
The contractor will prepare the detailed design and
Bill of Quantities (BoQ) for the structure and submit
for approval of the Supervisor.
This final design of the structures may suffer
changes from the initial concept design & drawings,
such as the length of the canal lining etc. Please
refer also to Vol. 5, Design document & drawings of
Tender Document.
2 Period of the project work is 24
months, we should finish the
works in this limit time, so winter
season included in these 24
months or no?
Winter season is also included in this 24 month
period.
3 Haidar Abad and Said Abad
canals have more problems of
diversion of irrigation water. In this
case, how can we divert the
water?
Based upon the field situation, the contractor had to
decide a suitable water diversion work e.g. the use
of plastic pipes. For diversion, a lump amount is
included in the tendered BOQ.