mp2013: presentation by subsidy reinvestment and empowerment programme
DESCRIPTION
Presented by Nze Akachukwu Nwankpo Secretary SURE-PTRANSCRIPT
SUBSIDY REINVESTMENT
AND EMPOWERMENT
PROGRAMMEPROGRESS REPORT
MINISTERIAL PLATFORMJULY, 2013
ByNze Akachukwu Nwankpo, Secretary SURE-P
H.E. Dr. Goodluck Ebele Jonathan GCFR
President, Commander-in-Chief of the Armed Forces of the Federal Republic of Nigeria
SURE-P INTERVENTION CATEGORIES • Category 1
– Infrastructure Development Projects• Roads and Bridges• Niger Delta (East – West) Rd• Railway
• Category 2
– Social Safety Net Programmes• Community Service, Women & Youth Empowerment
Programme (Includes Graduate Internship Scheme)• Maternal Child Health (MCH)• Mass Transit • Public Works (Ferma)• Vocational Training • Culture and Tourism
SURE-P
• 21-member Committee established February 13, 2012,
• Manages the Federal Government’s 41% share of the savings from the partial reduction of subsidies on petroleum products.
• Focused on critical infrastructure projects and social safety net programmes that will directly and positively impact on the people.
• Started receiving funds from July 2012. Project funds housed in CBN, Administrative funds kept in commercial bank.
SURE-P PROCESS
• Infrastructure Projects• Proper Project Management • Effective contractor supervision • Prompt payment of contractors for certified completed
work
• Social Safety Net Programmes• Project Design and Management
• Supervision of Project Implementation Unit in MDAs
• Prompt Cash Transfer to the PIUs
Roads, Bridges and RailwaysAbuja- Lokoja (197km)Benin – Ore road (293km)Kano – Maiduguri road (544km)Onitsha – enugu (157km)2ND NIGER BRIDGE (2km)Loko – oweto bridge (2km)
NIGER DELTAEAST - WEST ROAD SECTIONS I – IV (338km)
RailwaysLagos-Jebba Rail LinePH – Maiduguri Rail LineJeba – Kano Rail LineAbuja – Kaduna Rail Line
Infrastructure Development Project
Financial Information Abuja – Lokoja (SECTION I-IV)
Section I (43Km) Contract 5862Awarded July 2006
Section II(55Km) Contract 5863Awarded July 2006
Section III(49Km) Contract 5884Awarded Sept 2006
Section IV(50Km)Contract 5885Awarded Sept 2006
Total
Contract Sum (Nbillion)
28.8 (6yrs) 31.2 25.8 31.087 116.887
SURE-P Budget 2012 (Nbillion)
7.5 7.5 5.00 5.000 25.000
SURE-P AmountPaid2012 (Nbillion)
6.829 7.50 3.29 1.392 19.011
SURE-P Budget 2013 (Nbillion) 5.250 8.00 6.50 5.250 25.000
SURE-P Amount Paid 2013 (Nbillion)
0.987 3.539 1.693 0.839 7.049
PercentageCompletion Before SURE-P
38.00% 38.00% 16.06% 16.28% N/A
Percentage Completion to date SURE-P
63.80% 73.72% 30.97% 22.26% N/A11
Financial Information Kano – Maiduguri (SECTION I-V)
SectionI(102km): Contract 5878Sept 2006
Section II(118): Contract 5879Sept 2006
Section III(96): Contract 5880Sept 2006
Section IV(96):Contract 5881
Section V(132):Contract 5869
Contract Sum(Nbillion)
55.122 65.315 45.181 51.903 67.795
SURE-P Budget 2012 (Nbillion)
4.0 4.00 4.00 4.000 4.000
SURE-P Amount Paid2012 (Nbillion)
3.714 4.00 3.194 4.000 4.000
SURE-P Budget 2013 (Nbillion) 6.000 7.00 6.30 6.000 6.200
SURE-P Amount Paid2013 (Nbillion)
3.338 1.541 2.655 3.152 3.158
PercentageCompletion Before SURE-P
33.33% 51.02% 48.07% 31.82% 36.32%
Percentage Completion to date SURE-P 36.25% 46.88% 53.80% 47.44% 40.62%13
Financial Information Benin-Ore -Shagamu(SECTION I-V)
Phase I(36km): Contract 6000May 2009
Phase II(76km): Contract 5900Dec 2009
Phase III(83km) Contract 6133Dec 2012
Sect II(98km)Contract 6012May 2009
Contract Sum(Nbillion)
12.64(3yrs) 24.266 65.223 2.498
SURE-P Budget 2012 (Nbillion)
6.0 6.00 0.00 10.50
SURE-P Amount Paid2012 (Nbillion)
1.843 4.510 9.317 0.00
SURE-P Budget 2013 (Nbillion) 7.800 5.20 7.80
-
SURE-P Amount Paid2013 (Nbillion)
0.00 0.00 3.630 -
PercentageCompletion Before SURE-P 75.11% 55.61% 0.00% 98%Percentage Completion to date SURE-P 98.20% 90.84% 17.00% 98% 14
Financial Information Onitsha – Enugu (Phase I-II) , 2nd Niger Bridge, Loko-Oweto Bridge
Phase I Sect I (52km): Contract 5929Awarded April 2009
Phase II Sect I (49km): Contract5929AAwarded Dec 2009
Section II(56km): Contract 5988Awarded May 2009
Oju/Loko-OwetoBridge (2km)C/No.6108 Oct 2011
2nd NIGER BRIDGE AT ONITSHA (2km)Ongoing Bpp process - JB
Contract Sum(Nbillion)
5.092 (3yrs) 4.613 7.251 36.118 -
SURE-P Budget 2012 (Nbillion)
3.0 2.00 3.00 5.00 5
SURE-P AmountPaid2012 (Nbillion)
0.392 0.434 0.393 0.917 0.00
SURE-P Budget 2013 (Nbillion) 2.000 3.00 2.00 10.00 7
SURE-P Amount Paid 2013 (Nbillion)
0.00 0.00 0.00 5.151 0.00
PercentageCompletion Before SURE-P
26.10% 8.61% 33.00% 0.00% -
Percentage Completion to date SURE-P 36.66% 14.66% 45.00% 13.68% -
Financial Information EAST - WEST ROAD (SECTION I-IV)
Section I (87km): Contract 5867
Section II-I(101km): ContractID/09/03
Section II-II: Contract ID/09/02
Section III(99km):Contract 5882
Section IV (51km): Contract 5883
Contract Sum(Nbillion)
112.166 84.759 48.973 66.459 37.509
SURE-P Budget 2012 (Nbillion)
4.700 5.000 8.000 4.000
SURE-P Amount Paid2012 (Nbillion)
4.700 2.290 2.385 7.739 0.403
SURE-P Budget2013 (Nbillion) 11.670 18.00 <- 8.600 4.000
SURE-P Amount Paid2013 (Nbillion)
6.724 1.918 1.318 4.240 0.879
PercentageCompletion Before SURE-P
52.21% 23.17%18.21% 73.44% 53.55%
Percentage Completion to date SURE-P
66.52% 28.92% 27.31% 86.81% 58.45%17
PROGRESS/OPERATION REPORT FOR RAILWAYS PROJECTS/No PROJECT CONTRACTOR PROGRESS
BEFORE SURE-PINTERVENTION
PROGRESS AS AT JUL 2013
ORIGINAL CONTRACT SUM
AMOUNT PAID TO DATE BY SURE-P
REMARKS
1Lagos-JebbaRehabilitation
Costain West Africa
100% N12.293bn N11.6Bn
Funded the completion of Western Line that enabled Train movement from Lagos-Kano
2PH - Makurdi Railway Rehabilitation Project
Esser W.A 25% 42% N19.165bn N3.482Bn
Contractor fully on-site and achieving significant improvement with steady funding
3
Makurdi - Kanfanchan -Kuru - Jos & Kanfanchan - Kaduna Junction Railway Rehabilitation Project
Messrs CGGC 6% 30% N19.165bn N3.758Bn
Contractor fully on-site and achieving significant improvement with steady funding
4Kuru - Maiduguri Railway Rehabilitation Project
LINGO 5% 14% N23.720bn N2.522Bn
Contractor fully on-site and achieving significant improvement with steady funding
19
20
PROGRESS/OPERATION REPORT FOR RAILWAYS PROJECT
S/No PROJECT CONTRACTOR PROGRESS BEFORE SURE-P
INTERVENTION
PROGRESS AS AT JUL
2013
ORIGINAL CONTRACT
SUM
AMOUNT PAID TO DATE BY
SURE-P
REMARKS
5Abuja (Idu) - Kaduna Railway Modernisation Project
CCECC 35% 65% N136.39bn
N6.457Bn (Contractor)
N794Mn (Consultant)
Project completion fast tracked to present level of 65%
6
Design, Supply and Installation of Signaling on the Eastern Line (Port Harcourt - Maiduguri)
Ansaldo 5% 40% N5.6bnN502,423,809.6
3
7Jebba- Kano Addendum
Yet to be awarded
20
Community Service Scheme
• CSWYE through the Community Service Scheme (CSS) has engaged One Hundred and Nineteen thousand (119,000) beneficiaries spread across various communities in the country.
• This number is made up of over Eight Thousand (8000) beneficiaries that were deployed in twelve states during the Pilot stage.
• Three Thousand ( 3, 000) beneficiaries were also deployed in each
of the state of the country and FCT apart from Plateau state which has Two Thousand, Two Hundred and Seventy Two (2,272) beneficiaries. The remaining Seven Hundred and Twenty Eight beneficiaries for Plateau is expected to be deployed by middle of August 2013.
Social Safety Net Programmes
Community Service Scheme
• These beneficiaries who are deployed in communities where they come from are engaged in different community services thereby helping in maintaining social infrastructure in these communities.
• Each of these beneficiaries is paid monthly stipend of Ten Thousand (N10,000) naira which is a form of social safety net for the beneficiaries.
• The Scheme spends about N1.2Billion every month to pay the beneficiaries their monthly stipends.
Graduate Internship Scheme
• This Scheme which hopes to provide mentorship and upgrade the skills of Nigerian graduate has at today engaged One Thousand Eight Hundred and Twenty Three (1,823) Interns.
• These Interns are currently being mentored and provided some skills by various firms across the country.
• The interns presently are being paid a monthly stipend of N18, 000.
MCH Infrastructure & Human Resource of Health
• In 2012, in collaboration with State and Local Government authorities, we selected 500 Primary Health Care Centres(PHC) and 125 General Hospitals (GH) across the 36 states of the country and FCT.
• So far, Construction of 313 boreholes are ongoing at the PHCs
• Renovation of 74 PHCs are Ongoing • Contracting Process concluded for 336 PHCs. • Recruited 6,630 health care workers comprising of ;
– 1,304 midwives;– 2,254 community health extension workers (CHEWs); and – 3,072 female village health workers (VHWs)
• In 2013, We are adding 700 PHCs to the 500 of 2012, and 175 GHs to the 125 of 2012.
• Additional 700 PHCs -> Total = 1,200 PHCs
• Additional 175 GHs -> Total = 300 GHs
• Additional 1,500 midwives -> Total = 2,804
• Additional 2,800 CHEWs -> Total = 5,054
• Additional 4,200 VHWs -> Total = 7,272
Drugs, Kits and Equipment
• The 500 PHCs and 125 GHs across the country were supplied cumulatively with 1.8Billion naira worth of Drugs, Mama Kits, VHW kits, health commodities and medical equipments.
• 600Million naira worth of Buffer stock for Drugs,
Mama Kits, VHW kits, health commodities have been procured and stored in zonal medical stores to stamp out “out of stock syndrome”.
MCH Outcome
• Growing number of health workers are now providing quality antenatal, skilled birth delivery and postnatal services to pregnant women and their babies in SURE-P facilities across the country.
• 223,786 pregnant women have received antenatal care services in SURE-P MCH supported facilities
• 28,435 deliveries have been taken by skilled birth attendants in these same facilities
• 19,514 new acceptors of family planning have been recorded in these same facilities
Conditional Cash Transfer (CCT)• We have successfully launched the Conditional Cash Transfer (CCT)
Pilot Programme in Health Centre FCT. This will pay beneficiaries Five thousand Naira (N5,000)
• In 5 primary health care (PHC) centres in FCT, a total of 2,150beneficiaries have been enrolled into the programme as at 30th
June, 2013 as follows:
• Inauguration of State CCT Steering Committees has occurred in the Federal Capital Territory (FCT) and 8 pilot states namely Anambra, Bauchi, Bayelsa, Ebonyi, Kaduna, Niger, Ogun and Zamfara States
• Beneficiaries are now being enrolled in the pilot PHC facilities in the 8 other pilot states
MASS TRANSIT
• The SURE-P funds for Mass Transit is managed by The
Infrastructure Bank (TIB), they are responsible for monitoring the
loans and payment to suppliers and operators.
• Total Number of Buses – 809 valued at 9.1Billion Naira
• Total Number of Transport Operators – 19
• Sector – Private from six geo- political zones of Nigeria, including Abuja and Lagos.
• SURE-P released to Infrastructure Bank – 8.9Billion Naira
FERMA/ PUBLIC WORKS
1. Presently active on 40 Federal Roads :- across all states of the Federation
2. Currently engaging 12,400 (10,000 workmen, 2400 Supervisors) young Nigerians from neighbouring communities of selected roads
4. District (Community)Roads Maintenance Programme –Currently implementing pilot scheme in 3 states (Anambra, Kano, Zamfara) employing 20 Supervisors 500 workmen, 500km of roads in each State
5. Budget: N4 Billion (January – June 2012)N4 Billion (July – December 2013)
TECHNICAL VOCATIONAL EDUCATION AND TRAINING (TVET)
Effective Start Date: May 27, 2013• Annual Budget N8.6billion
Achievements to Date:• Received applications from 44,000 youths for skills training.• Undertook infrastructure assessment visits to 8 FG Institutions•.Plans for 2013:1. Conclude all rehabilitation works in all the 8 Federal Government Training
Centers3. Equip and retool the 8 Federal Government training Centers by September, 2013.
4. Conclude training of 6,250 client based Trainees by end of 2013 in the following client centers including NRC, NAPTIN, FERMA,
5. Commence training of 8000 youth through the citizens based component of the TVET program by August, 2013
• CULTURE AND TOURISM
For 2013, SURE-P plans on intervening in Culture and Tourism
Planning Phase – 50%
Social Safety Net Programmes
MONITORING & EVALUATION OF SURE-P PROJECTS & PROGRAMMES
SURE-P has a robust institutional framework for ensuring the quality and value for money aspect of its interventions in Infrastructure Projects and Social Safety Net Programmes.
The SURE-P M&E Team works closely with the National Planning Commission (M&E Department) and supported by DFID consultants, to ensure that all SURE-P interventions are accorded the necessary scrutiny to meet required standards of project and programme delivery.
Through this partnership, the Nigerian Taxpayer can be confident that SURE-P is at the fore-front of enabling the transformation of public sector service delivery and maximizing value for money.