need assessment documents for ipds nad210115.pdf · new feeder feeder bifurcation augmentation of...

13
Need Assessment Documents for IPDS

Upload: buinhi

Post on 08-Apr-2018

219 views

Category:

Documents


1 download

TRANSCRIPT

Need Assessment Documents

for

IPDS

Why NAD is required?

• To asses the gap in sub-transmission & Distribution network of the State and for deciding the broad scope of work to be covered under IPDS to achieve its goal i.e.

24x7 Power for All

AT&C loss reduction as per trajectory finalized by MoP

Providing access of electricity to all urban households.

• To asses the need of a state, preferably the NAD of all statutory towns in concerned state to be prepared by utilities.

• NAD shall contain all relevant information along with justifications to substantiate the proposed scope of work and cost estimates.

• States should clearly priorities the requirement in NAD, to facilitate nodal agency to arrive at broad scope of work to be covered under the scheme and the total cost.

2

Scope of Nodal Agency on NAD

3 3

1. Nodal agency will asses the total requirement of fund in state as

proposed in NAD.

2. To bring the requirement under available budget, nodal agency

needs the NAD of all statutory towns in a state.

3. Nodal agency will scrutinise the requirement, based on priority

decided by utilities in NAD & based on loss reduction potential of

the proposed work.

4. With above, nodal agency, in consultation with concerned

utilities in a state, will arrive at broad scope of work to be

covered under the scheme and the total cost.

Preparation of NAD

4 4

1. NAD to be prepared circle/zone/utility wise.

2. Separate BoQ sheet to be filled for each town.

3. For R-APDRP towns, information of sanctioned qty/cost, executed

& to-be executed qty/cost to be filled along with additional

requirement under IPDS.

4. Commercial information of the circle/zone/utility covering all the

statutory towns to be filled.

5. Name of the Nodal officer at HQ & site officer / town in-charge at

circle/zone to be given at the time of NAD.

Scope of work covered under NAD

• 33/11 KV or 66/11 KV Sub Station: New sub-station Additional Transformer Capacity Enhancement Renovation & Modernisation

• 33KV/11 KV/LT feeders: New feeder Feeder Bifurcation Augmentation of feeder

• Distribution Transformer New Distribution Transformer R&M of DT Capacity enhancement of LT sub-station

• HVDS • Capacitor Bank

Scope of work covered under NAD

• Aerial Bunched Cables- HT & LT

• Under-ground cables- HT & LT

• Solar Panels with (in Govt establishment)

• Metering at all points:

Feeders

Boundary Point

Distribution Transformers

Existing consumers including meter pillar box.

Prepaid / smart meters in Govt. establishment

AMI, Smart meters (in SCADA towns)

• Any other work required for strengthening of sub-transmission & Distribution network

After finalisation of NAD…..

7 7

1. After finalisation of broad scope of work in NAD, utility to prepare DPR.

2. These DPRs, duly recommended by the Distribution Reforms Committee (DRC)

at the State level, will be submitted by the utilities to the Nodal agency.

3. Nodal Agency will separately provide comparable costs sourced from CPSUs for

major equipment for reference of the utility. These reference rates shall be

used as ceiling rates for sanctioning of the projects.

4. While formulating DPRs, utility shall necessarily consult the public

representatives including Member of Parliament. Utility shall furnish a

certificate to this effect while submitting DPRs to Nodal Agency.

5. Nodal agency will appraise the DPRs & put up to monitoring committee for

approval.

Changes in IPDS w.r.t. earlier schemes

Project Management Agency (PMA)

Appoint PMA (preferably utility-wise) to assist in project management for ensuring timely implementation of project.

100% grant for PMA limited to 0.5% of cost of works.

Select PMA from CPSUs or through open bidding as per their policy.

Preferably same PMA for both IPDS & DDUGJY for better coordination, operational efficiency and cost optimization.

Further, to avoid conflict of interest, PMA should not be:

– TPIEA-EA, TPIEA-IT, engaged under RAPDRP in respective state.

– IPDS executing agency in respective state.

– Beneficiary utilities themself or their subsidiaries/JVs as PMA

Project Implementation

Projects implemented by Turnkey award through e-tender by utility.

Execution on partial turnkey/departmental basis permitted with approval of Monitoring Committee

Utility to follow Procurement Policy, Standard Bidding Doc and Technical Specs. to be circulated by Nodal agency.

Projects to be awarded within 6 months and to be completed in maximum time limit of 30 months (award & implementation) from date of sanction.

Dedicated team required for implementation of projects

If utility fails to award within 9 months of release of first tranche of grant, project will be deemed as closed/cancelled and grant released shall be refunded by utility within 3 months.

Approved or awarded cost whichever is less, be eligible for grant.

Any cost overrun, not eligible for grant and shall be borne by utility.

Changes in IPDS w.r.t. earlier schemes

Quality Assurance and Inspection:

Utility responsible & accountable for assuring quality.

QA and Inspection (QA&I) Plan to be an integral part of contract agreement with turnkey contractor or equipment supplier/vendor and erection agency.

Utility to ensure quality of material supplied as per QA&I Plan.

Implementation of scheme in particular district to be reviewed periodically by District Vigilance and Monitoring Committee.

Concurrent and post implementation Evaluation

Nodal Agency to formulate an appropriate mechanism for concurrent and post implementation evaluation of scheme and appoint Third Party Concurrent Evaluating Agency (TPCEA) for carrying out inspections on sample basis.

Changes in IPDS w.r.t. earlier schemes

New/ Aug./R&M of existing S/S incl GIS & associated 66/33/22/11 KV lines

New/ Aug. of existing HT lines for reorientation/re-alignment

New/ R&M of existing DTs along with associated LT lines

Installation of Capacitors

U/G cables in densely populated areas of tourism and religious importance

High voltage distribution system (HVDS)

Aerial Bunched Cable for theft prone areas

IT Applications

Enterprise Resource Planning (ERP)

Addl HW in towns, GPS based GIS survey of assets, and integration with DC/DR and CCC, Incremental up-gradation at DC/DR exc. revenue exp

(Scope of IT extended to statutory towns population ≥ 5000 (Census 2011). In 1st phase towns population ≥ 15000 (5000 for sp cat states to be taken

Scope of works (Strengthening of ST&D)

Metering • New static consumer meters, replacement of faulty & electro-mech

meters. • AMR for feeders, DTs and high load consumers • Pillar Box, service cables and accessories for relocation of meters

outside consumer premises • Installation of prepaid / smart meters in Govt. establishment • AMI, Smart meters in SCADA towns (estb. under R-APDRP). • Boundary meters for ring fencing of non-RAPDRP towns

(population>5000 Others • IT enablement & dist. network strengthening under “R-APDRP”

component as per ongoing RAPDRP scheme and applicable guidelines • Optical fiber missing links under NOFN to connect all 33 & 66 KV grid sub

stations/ billing offices/Regional/Circle/Zonal offices of Discoms • Provisioning of Solar Panel on Govt. buildings including Net-metering • National Power Data Hub at CEA • Training & Capacity Building

Scope of works (Metering & others)

List of items not eligible to be covered under the scheme

• Works already covered under other schemes of Govt. of India.

• AMI in the towns where SCADA is not planned under R-APDRP

• Civil works other than sub station

• Service lines to new consumer

• GIS survey of consumers

• Cost of land for sub-stations

• Compensation towards right of way

• Distribution Automation

• Office equipment / fixtures

• Spares (Other than mandatory spares prescribed by the manufacturer)

• Tools and Plants (T&P)

• Vehicles

• Salaries and Establishment Expenditure

Integrated Power Development Scheme (IPDS)

Items not covered