  • New Terminal and Parking at Kansas City

    International AirportCity of Kansas City Missouri

    1/21/2020

  • Project Report January 22, 2020

    Milestones 2019/2020

    Budget

    M/WBE Status

    Safety

    Project Status

    Schedule

    3-Month Look Ahead

    1/24/20202

  • 2019 Milestones

    Validated project budget/scope and achieved the desired project total budget of $1.5B

    Obtained City Council approval of the project and financing

    Negotiated and executed the Development Agreement

    Executed Use and Lease Agreement with the signatory airlines

    Issued first traunch of project bonds

    Completed Schematic Design and 60% Design Development

    Completed demolition of existing structures

    Began construction with foundations and utility relocation construction

    Selected Baggage Handling System and executed LOI for 5 years Operation and Maintenance

    Received airlines approval of Revised GMP per the Development Agreement

    Received Municipal Arts Commission approval of the project design

    Received City Planning Commission project approval

    Began review of Terminal 60% Design Development package

    Began review of Garage 30% Schematic Design Documents

    1/24/20203

  • 2020 Planned Milestones

    Receive airlines approval of Final GMP per the Development Agreement Initiate Request for Proposal Process for Concessions Program Complete Design Development and Construction Documents for Terminal and

    Parking Structure Complete major underground utility construction and FAA ductbank Vertical building steel erection to begin in Spring Complete Terminal building structure erection Open East Flow Roadway System in Spring Begin Upper Level Roadway Construction Begin Parking Structure construction Work with Municipal Arts Commission to begin artist selections

    1/24/20204

  • 1/24/20205

  • 1/24/20206

  • 1/24/20207

  • 1/24/20208

  • 1/24/20209

  • 1/24/202010

  • February Procurements - Group 7

    Airside Civil Paving

    Low Voltage Systems Integrator

    Roofing

    Fire Suppression System

    Interior Masonry

    Rough Carpentry

    Metal Stairs/Miscellaneous Metals

    Spray Fireproofing

    1/24/202011

  • KCI New Terminal Project Update

    TIO Committee / January 22, 2020

  • Agenda

    Local Participation

    Terminal Workforce Enhancement Programs

    13 1/15/2020

  • 14

    Local Participation

    1/15/2020

  • Local Partners

    1/15/202015

    Of the 167 total subcontractors on the project:

    130

    6979

    KC Metro Subcontractors

    KCMO Subcontractors

    Certified-M/WBE Subcontractors

  • Local Partners

    1/24/202016

    Local Participation

  • 21

    Workforce Participation

    CONSTRUCTION EMPLOYMENT

    WORKFORCE PARTICIPATION GOALS

    WORKFORCE TOTALS THROUGH DEC. 31, 2019

    Minority Workforce 20.00% 16.7%

    Women Workforce 2.75% 4.20%

    We anticipate minority workforce participation to increase as additional scopes of work get underway.

    Source: B2G Now

    1/15/2020

    Local Participation

  • 22

    M/WBE Participation Verified Payments

    SERVICE TYPE FIRM TYPE

    FAIRNESS IN CONSTRUCTION/

    HRD GOALS

    EDGEMOOR DEVELOPER’S

    PLEDGE

    PAID TO DATEDEC. 31, 2019

    Professional Services

    MBE 17.0% 20.0% 16.3%

    WBE 12.0% 15.0% 10.1%

    Construction Services

    MBE 15.0% 20.0% 18.7%

    WBE 9.0% 15.0% 18.9%

    Source: B2G Now

    1/15/2020

    Local Participation

  • 19

    Terminal Workforce Enhancement Programs (TWEP)

    1/15/2020

  • TWEP

    25

    TWEP

    1/15/2020

    Pay without delay MWBE firms paid in 14 business

    days

    KC Strategic Partnership Program

    Supplier support United Rentals

    Low interest loan program Eight loans to date through MBE

    Partner Lead Bank totaling nearly $4 million.

    On-site healthcare

    Internships College and high school students

    Workforce Training Program

    Free or Subsidized Transportation to/from the Job Site

    Extended Childcare Hours

  • KC Strategic Partnership Program Six-month MBA style course

    developed and operated by Clark Construction

    54 total graduates from the first two KC SPP classes 8 graduates have

    successfully competed for KCI New Terminal contracts

    40 locally-owned companies participating in the 2019-2020 class

    10/24/201921

    TWEP

  • KC SPP Spotlight: Derrion Thomas

    10/24/201922

    TWEP

    Founder and CEO of 58 Construction

    Named company after his father, NFL Hall of Fame defensive end Derrick Thomas’s number “58”.

    About his experience as a small business owner:

    READ MORE IN THE CALL

    We are building a team, bidding on commercial projects, and I am learning a lot about what it takes to succeed in the construction business.”

  • Three-week program that results in direct placement into job after graduation

    Benefits: $400 weekly stipend

    RideKC passes

    Access to extended childcare hours

    Start Date: Jan. 20, 2020

    Graduation: Feb. 7, 2020

    1/15/202023

    TWEP

    Workforce Training ProgramPROGRAM OVERVIEW

    WTP class participates in an OSHA 10-hour safety training

  • 1/15/202024

    CONSTRUCTION INDUSTRY

    Missouri Prevailing Wage 101

    Introduction to Trades

    History of Labor

    Construction Math

    HANDS-ON TRAINING

    Scissor Lift Training

    Hand & Power Tool Training

    Crane & Hand Signaling Training

    WORKPLACE READINESS

    Communication & Networking

    Time Management

    Workforce Respect & Awareness

    Financial Literacy

    SAFETY AND FIRST AID

    OSHA 10 Training

    CPR Training

    AED Training

    TWEP

    Workforce Training ProgramPROGRAM CURRICULUM

  • 1) APPLICATION DAYS Dec. 11 & 14 at the Full

    Employment Council

    Over 600 candidates applied through the Full Employment Council

    Completing FEC processes, ACT WorkKeys Applied Math Assessment, and the WTP Application

    1/15/202025

    TWEP

    Workforce Training ProgramRECRUITMENT PROCESS

  • 2) PRE-SCREEN INTERVIEWS Dec. 30, Jan. 3 & 6 at the Full Employment Council

    The eligible candidates (eligible to work in U.S. and met scores/education requirements for trades they applied) were interviewed by Community Workforce Agreement Advisory Committee members

    3) SUBCONTRACTOR INTERVIEWS Jan. 13 and 14 at the Morning Star Missionary Baptist Church

    The top candidates, based on pre-screen interviews, were interviewed by the trades and subcontractors on the project.

    1/15/202026

    TWEP

    Workforce Training ProgramRECRUITMENT PROCESS

  • 4) SELECTION Jan. 15

    Selected subcontractors’ top candidates to enter the first session.

    All chosen candidates passed a drug screen.

    Began program this past Monday, January 20.

    1/15/202027

    TWEP

    Workforce Training ProgramRECRUITMENT PROCESS

  • ORIGIN

    1/15/202028

    Kansas City, MO65%

    MissouriNon-KCMO

    23%

    Kansas12%

    TWEP

    Workforce Training ProgramDEMOGRAPHIC BREAKDOWN

  • GENDER

    1/15/202029

    Male85.5%

    Female13.8%

    Did not disclose0.7%

    TWEP

    Workforce Training ProgramDEMOGRAPHIC BREAKDOWN

  • Black, 59.9%

    White, 25.2%

    Two or More Races, 5.8%

    Hispanic or Latino, 4.0%I do not wish to disclose, 3.9%

    American Indian or Alaskan Native, 0.9%

    Asian, 0.4%

    1/15/202030

    RACE

    TWEP

    Workforce Training ProgramDEMOGRAPHIC BREAKDOWN

  • 1/15/202031

    AGE

    < 18 18 - 29 30 - 39 40 - 49 50 - 60> 60

    TWEP

    Workforce Training ProgramDEMOGRAPHIC BREAKDOWN

  • Free or Subsidized Transportation

    1/15/202032

    TWEP

    NEW East Village Transit Center

  • Terminal Workforce Enhancement Programs

    1/15/202033

    TWEP

  • This is the slide title space. Describe the above photo.Further description of the above photo. For example, This image was captured on 4/30/2019 by the project camera mounted on the Air Traffic Control tower shows the start of demolition of the Terminal A parking garage. Demolition of the Terminal A building will begin on 5/20/2019.

    1/24/202034

    This is a photo and caption slide. Photo(s) will exist inside the yellow box. For photos or other information that needs to cover the full slide, see the next page.

    Do not exceed the dimensions of this box with any image, table, chart of graph.

    Font for the title is Trebuchet MS size 14Fond for the additional text is Trebuchet MS size 12

    Stay Tuned

    kci-edgemoor.com

    cwcjv.comBusiness & Employment Opportunities

    buildkci.com

    KCI-Edgemoor

    KCIAirport

    BuildKCI

    @kciedgemoor

    @kciairport

    @BuildKCI

    New Terminal and Parking at Kansas City International AirportProject Report January 22, 2020Slide Number 3Slide Number 4Slide Number 5Slide Number 6Slide Number 7Slide Number 8Slide Number 9Slide Number 10February Procurements - Group 7KCI New Terminal Project UpdateAgendaSlide Number 14Local PartnersLocal PartnersWorkforce ParticipationSlide Number 18Slide Number 19TWEPKC Strategic Partnership ProgramKC SPP Spotlight: Derrion ThomasSlide Number 23Slide Number 24Workforce Training ProgramSlide Number 26Slide Number 27Slide Number 28Slide Number 29Slide Number 30Slide Number 31Free or Subsidized TransportationTerminal Workforce Enhancement ProgramsThis is the slide title space. Describe the above photo.