nutmeg multi‐family residential project€¦ · the project will take access from nutmeg street...

47
Nutmeg Multi‐Family Residential Project Traffic Impact Analysis Report Prepared for: JMI Real Estate 10632 Meads Ave Orange, CA 92869 Prepared by: David Mizell, AICP Project Manager 5865 Avenida Encinas, Suite 142‐B Carlsbad, CA 92008 Draft: November 13, 2017

Upload: others

Post on 18-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

 Nutmeg Multi‐Family Residential Project 

Traffic Impact Analysis Report  

 

 

  

 

 

 

 

 

 

 

Prepared for: 

JMI Real Estate 

10632 Meads Ave 

Orange, CA 92869 

 

 

 

Prepared by: 

David Mizell, AICP 

Project Manager 

 5865 Avenida Encinas, Suite 142‐B 

Carlsbad, CA 92008 

 

 

Draft: November 13, 2017 

Page 2: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

 

Nutmeg Multi‐Family Residential 

Traffic Impact Analysis 

TABLE OF CONTENTS 

1  INTRODUCTION ......................................................................................................................................... 1 

1.1  PROJECT DESCRIPTION ....................................................................................................................................... 1 1.2  STUDY AREA .................................................................................................................................................... 3 

2  ANALYSIS APPROACH AND METHODOLOGY ............................................................................................... 5 

2.1  ANALYSIS TIMEFRAMES ...................................................................................................................................... 5 2.2  METHODOLOGY ............................................................................................................................................... 5 

2.2.1  Intersection Delay Analysis ............................................................................................................... 5 2.1.1  Roadway Segment Capacity Analysis ................................................................................................ 6 

3  EXISTING CONDITIONS ............................................................................................................................... 8 

3.1  EXISTING ROADWAY NETWORK ........................................................................................................................... 8 3.2  ALTERNATE MODES OF TRAVEL ......................................................................................................................... 10 

3.1.1  Transit Service ................................................................................................................................. 10 3.1.2  Pedestrian and Bicycle Access ......................................................................................................... 10 

3.3  TRAFFIC VOLUMES .......................................................................................................................................... 10 3.4  INTERSECTION ANALYSIS................................................................................................................................... 12 3.5  ROADWAY SEGMENT ANALYSIS ......................................................................................................................... 13 

4  PROJECT TRAFFIC ...................................................................................................................................... 14 

4.1  PROJECT DESCRIPTION ..................................................................................................................................... 14 4.2  PROJECT TRIP GENERATION .............................................................................................................................. 14 4.3  PROJECT TRIP DISTRIBUTION ............................................................................................................................. 16 4.4  PROJECT TRIP ASSIGNMENT .............................................................................................................................. 16 

5  EXISTING PLUS PROJECT CONDITIONS ....................................................................................................... 21 

6  EXISTING PLUS CUMULATIVE CONDITIONS ................................................................................................ 25 

6.1  CUMULATIVE PROJECTS ................................................................................................................................... 25 6.2  TRAFFIC VOLUMES .......................................................................................................................................... 25 6.3  INTERSECTION ANALYSIS................................................................................................................................... 30 6.4  ROADWAY SEGMENT ANALYSIS ......................................................................................................................... 30 

7  SIGNAL WARRANT ANALYSIS .................................................................................................................... 33 

8  SITE ACCESS EVALUATION ......................................................................................................................... 35 

9  SIGNIFICANT IMPACTS AND RECOMMENDED MITIGATION ....................................................................... 36 

10  SUMMARY AND CONCLUSIONS ................................................................................................................. 40 

 

Page 3: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

 

Nutmeg Multi‐Family Residential  ii 

Traffic Impact Analysis 

LIST OF EXHIBITS 

Exhibit 1‐1 Regional Project Location ........................................................................................................... 1 Exhibit 1‐2 Project Site Plan .......................................................................................................................... 2 Exhibit 1‐3 Project Study Area ...................................................................................................................... 4 Exhibit 3‐1 Existing Intersection Lane Geometry .......................................................................................... 9 Exhibit 3‐2 Existing Peak Hour Intersection and Daily Roadway Segment Volumes .................................. 11 Exhibit 4‐1 Project Trip Distribution ........................................................................................................... 17 Exhibit 4‐2 Trip Distribution at Project Driveways ...................................................................................... 18 Exhibit 4‐3 Peak Hour and Daily Project Trip Assignment .......................................................................... 19 Exhibit 4‐4 Peak Hour Trip Assignment at Project Driveways .................................................................... 20 Exhibit 5‐1 Existing Plus Project Peak Hour Intersection and Daily Roadway Segment Volumes .............. 22 Exhibit 6‐1 Cumulative Projects Location ................................................................................................... 26 Exhibit 6‐2 Peak Hour Cumulative Project Trips and Daily Roadway Segment Volumes ........................... 27 Exhibit 6‐3 Existing Plus Cumulative Without Project Peak Hour Intersection and Daily Roadway Segment Volumes ...................................................................................................................................................... 28 Exhibit  6‐4 Existing Plus Cumulative With Project Peak Hour  Intersection and Daily Roadway Segment Volumes ...................................................................................................................................................... 29 Exhibit 9‐1 Recommended Mitigation Measures ....................................................................................... 38  

LIST OF TABLES 

Table 2‐1 LOS Criteria for Intersections ........................................................................................................ 6 Table 2‐2 LOS Criteria for Roadway Segments ............................................................................................. 6 Table 3‐1 Existing Peak Hour Intersection LOS Summary ........................................................................... 12 Table 3‐2 Existing Roadway Daily Segment LOS Summary ......................................................................... 13 Table 4‐1 Trip Generation Summary ........................................................................................................... 14 Table 4‐2 Trip Generation Comparison: Proposed Project Vs. General Plan Land Uses ............................ 15 Table 5‐1 Existing Plus Project Peak Hour Intersection LOS Summary ....................................................... 21 Table 5‐2 Existing Plus Project Daily Roadway Segment LOS Summary ..................................................... 24 Table 6‐1 Cumulative Projects Trip Generation .......................................................................................... 25 Table 6‐2 Existing Plus Cumulative Conditions Without and With Project ................................................. 31 Table 6‐3 Existing Plus Cumulative Conditions Without and With Project ................................................. 32 Table 7‐1 Signal Warrant Analysis ............................................................................................................... 34 Table 9‐1 Summary of Mitigation Measures .............................................................................................. 39 Table 9‐2 Intersection Operations With Mitigation .................................................................................... 39  

   

Page 4: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

 

Nutmeg Multi‐Family Residential  iii 

Traffic Impact Analysis 

 

APPENDICES  Appendix A  Traffic Counts Data 

Appendix B  Existing Conditions Intersection LOS Worksheets 

Appendix C  Existing Plus Project Conditions Intersection LOS Worksheets 

Appendix D  Cumulative Projects Trip Distribution and Assignment 

Appendix E  Existing Plus Cumulative Without Project Intersection LOS Worksheets 

Appendix F  Existing Plus Cumulative Without Project Intersection LOS Worksheets 

Appendix G  Signal Warrant Analysis Worksheets 

Appendix H  Fair Share Contribution Calculation Worksheets / Mitigated Conditions LOS Worksheets 

   

Page 5: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

 

Nutmeg Multi‐Family Residential   1 

Traffic Impact Analysis 

 

1 INTRODUCTION 

This traffic impact analysis evaluates the traffic conditions associated with the proposed Nutmeg Multi‐

Family Residential Project (herein referred to as “the project”) located on a 6.8‐acre site along both sides 

of Nutmeg Street in the City of Escondido.  Exhibit 1‐1 illustrates the regional project location. 

1.1  Project Description 

The project proposes a density of 24 dwelling units per acre, which would yield 163 multi‐family residential 

units  on  the  6.8‐acre project  site.    The  site  to  the north of Nutmeg  Street will  be  developed with 45 

Townhome  residential units.  The  townhomes would be developed as approximately 11 2‐bedroom/2‐

bath units of 950 square feet and 34 3‐bedroom/2‐bath units of 1,350 square feet. The units would be 3‐

story with a 2‐car garage. The site to the south of Nutmeg Street would be developed with 118 Apartment 

residential units. The apartments would be developed as approximately 47 1‐bedroom/1‐bath units of 

750 square feet and 71 2‐bedroom/2‐bath units of 950 square feet. 

 

Currently the site is zoned for Commercial Office, and the project is requesting a zoning and General Plan 

Amendment  to  change  the General  Plan  and  zoning  designation  on‐site  to High Density Multi‐Family 

Residential (24 DU/AC).   

 

The project will take access from Nutmeg Street from a total of three project driveways.  Two driveways 

will be provided for the site on the north side of Nutmeg Street, and one driveway will be provided for the 

site on the south side of Nutmeg Street.  All three project access intersections will be stop‐controlled on 

the driveway approaches of the intersection.  The eastbound and westbound intersection approaches on 

Nutmeg Street will be uncontrolled at all three project access intersections.   

 

Exhibit 1‐2 illustrates the project site plan. 

Page 6: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

x

Project Site

Nutmeg Mul�-Family Residen�al TIA

Exhibit 1-1Regional Project Loca�on

Page 7: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

2972.33 3

906.47

◊◊

◊◊

◊◊

◊◊

◊◊

◊◊

◊◊

855

860

865

870

875

880

865870

875880

885890

895900

905

915

88589

089590

090591

0915

915

880

885

890

895

900

905

910

905

900

865870875880885890895900

870

875

890

895

900 895

895

900

905

885

890

895

900

900

900895

890885

880

880

885

890

895

920

925 925

930935

940945

950955

960965

970

905

910915

920925930

935940

945950

955

960

965

890

900

895

890

885

885

890

895

910

900

905

910

915

920

925

930

905

905

935

940

945

930

905

910

915

920 925

930

935

940

90590089589088

5

880

875

870

910

905

890

SOUTH PARCEL4.36 GROSS AC97 TH (22 DU/AC)

PARKING SUMMARY219 SP REQUIRED

194 SP GARAGE25 SP OPEN219 SP TOTAL

RECAREA

DETBASIN

NORTH PARCEL1.6 NET AC37 TH (23 DU/AC)

PARKING SUMMARY84 SP REQUIRED

74 SP GARAGE10 SP OPEN84 SP TOTAL

DETBASIN

Exhibit 1-2Project Site Plan

Nutmeg Multi-Family Residential TIA

Page 8: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  3 

Traffic Impact Analysis 

1.2  Study Area 

In accordance with the City of Escondido Traffic Impact Analysis Guidelines and the SANTEC/ITE Guidelines 

for Traffic Impact Studies in the San Diego Region (March 2000), all signalized intersections where 50 or 

more project‐generated trips are forecast to be added are  included in the traffic  impact analysis.   The 

proposed study area consists of the following 9 intersections and 7 roadway segments: 

Intersections 

1. N. Centre City Parkway/ N. Nutmeg Street (one‐way stop controlled)

2. N. Centre City Parkway/ W. Country Club Lane (signalized)

3. W. Country Club Lane/ N. Nutmeg Street (all‐way stop controlled)

4. N. Centre City Parkway/ S. Iris Lane (signalized)

5. N. Centre City Parkway/ W. El Norte Parkway (signalized)

6. W. El Norte Parkway/ Iris Lane (signalized)

7. N. Nutmeg Street / Project Driveway 1 (two‐way stop controlled)

8. N. Nutmeg Street / Project Driveway 2 (two‐way stop controlled)

9. N. Nutmeg Street / Project Driveway 3 (two‐way stop controlled)

Roadway Segments 

1. N. Nutmeg Street, from N. Centre City Parkway to Project Access

2. N. Nutmeg Street, from Project Access to W. Country Club Lane

3. N. Centre City Parkway, from N. Nutmeg Street to W. Country Club Lane

4. N. Centre City Parkway, from W. Country Club Lane to S. Iris Lane

5. N. Centre City Parkway, from S. Iris Lane to W. El Norte Parkway

6. S. Iris Lane, from N. Centre City Parkway to W. El Norte Parkway

7. W. El Norte Parkway, from S. Iris Lane to 1‐15

Exhibit 1‐3 illustrates the project study area. 

Page 9: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Mul�-Family Residen�al TIA

T:\Projects\Escondido\Nutmeg Mul�-Family Residen�al Project\06_Planning\Graphics\PDF

15INTERSTATE

ProjectSite

Nutmeg St

Centre City Pkwy

Iris L

n

El Norte Pkwy

Broadway

Country Club Ln

1

23

4

5

6

1

2 3

4

5

6

7

Exhibit 1-3Project Study Area

LegendIntersection

Roadway Segment

Project Site

#

Page 10: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  5 

Traffic Impact Analysis 

2 ANALYSIS APPROACH AND METHODOLOGY 

This section summarizes the analysis approach and methodology used to evaluate the study intersections 

and roadway segments associated with the proposed project.   

2.1  Analysis Timeframes 

In accordance with the SANTEC/ITE Guidelines for Traffic Impact Studies in the San Diego Region (March 

2000) and the City of Escondido’s Traffic Impact Study Guidelines and General Plan, this study analyzes 

the following study scenarios: 

Existing Conditions – Analysis of existing (Year 2017) traffic count volumes, intersection geometry

and existing roadway network.

Existing Plus Project Conditions – Analysis of existing traffic volumes overlaid with the forecast

project‐generated traffic.  The existing intersection geometry and roadway network were used in

this analysis.

Existing  Plus  Cumulative  Conditions  Without  Project  –  Analysis  of  existing  traffic  volumes

overlaid with traffic associated with approved or pending projects anticipated to be constructed

by the project opening year (Year 2019).

Existing Plus Cumulative Conditions With Project – Analysis of existing traffic volumes overlaid

with cumulative project traffic and traffic generated by the proposed project.

2.2  Methodology 

2.2.1  Intersection Delay Analysis 

Levels of service (LOS) were determined at the study area intersections for the AM and PM peak hours.  

The AM intersection analysis evaluates LOS during the hour with the highest vehicular traffic between 

7:00 AM and 9:00 AM.    The PM  intersection analysis  evaluates  LOS during  the hour with  the highest 

vehicular traffic between 4:00 PM and 6:00 PM.   

Intersection operations were analyzed based on the 2010 Highway Capacity Manual (HCM) methodology 

for signalized and unsignalized intersections.  The Synchro 9.1 software program was used as an interface 

for the 2010 HCM methodology.  

Signal timing data and parameters such as cycle lengths, splits, clearance intervals, etc. were obtained 

from the current signal timing sheets provided by the City and calibrated into the Synchro model.  Synchro 

reports delays, which correspond to a particular LOS, to describe the overall operation of an intersection. 

The criteria for the LOS grade designations are provided in Table 2‐1.  LOS provides a quick overview of 

how well an intersection is performing.  The City of Escondido accepts LOS D or better operations for all 

signalized and unsignalized intersections during peak traffic periods.   

Page 11: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  6 

Traffic Impact Analysis 

Table 2‐1 LOS Criteria for Intersections 

LOS 

Control Delay (sec/veh) 

Description Signalized 

Intersections (a) Unsignalized 

Intersections (b) 

A  <10  <10  Operations with very low delay and most vehicles do not stop. 

B  >10 and <20 >10 and <15Operations with good progression but with some restricted movements. 

C  >20 and <35 >15 and <25Operations where a significant number of vehicles are stopping with some backup and light congestion. 

D  >35 and <55 >25 and <35Operations where congestion is noticeable, longer delays occur, and many vehicles stop.  The proportion of vehicles not stopping declines. 

E  >55 and <80 >35 and <50Operations where there is significant delay, extensive queuing, and poor progression. 

F  >80 >50Operations that are unacceptable to most drivers, when the arrival rates exceed the capacity of the intersection. 

Source: 2010 Highway Capacity Manual (HCM). 

2.1.1 Roadway Segment Capacity Analysis 

The basis for analysis of roadway segment performance is provided by LOS standards and thresholds.  The 

LOS  analysis  considerations  include  the  functional  classification  of  the  roadway,  maximum  capacity, 

roadway  geometrics,  and  Average  Daily  Traffic  (ADT)  volumes.    The  analysis  results  provide  a  quick 

overview of whether a segment is under, approaching, or over capacity.   

A daily roadway segment analysis was conducted for all study area roadways, in accordance with the City 

of Escondido General Plan Mobility Element  and  SANTEC/ITE TIS Guidelines.    Table  2‐2  presents  the 

roadway segment capacity and LOS standards utilized by the City of Escondido.  

Table 2‐2 LOS Criteria for Roadway Segments 

Classification / Lanes 

Level of Service 

A  B  C  D  E 

Prime Arterial / 8  23,2800  37,800  51,800  62,300  70,000 

Prime Arterial / 6  20,400  32,400  44,400  53,400  60,000 

Major Road / 6  17,000  27,000  37,000  44,500  50,000 

Major Road / 4   12,600  20,000  27,400  32,900  37,000 

Collector/4 (NP)  11,600  18,500  25,300  30,400  34,200 

Collector/4 (WP)  6,800  10,800  14,800  17,800  20,000 

Local Collector / 2 NP   5,100  8,100  11,100  13,400  15,000 

Local Collector / 2 WP  3,400  5,400  7,400  8,900  10,000 

Source: City of Escondido Traffic Impact Analysis Guidelines.  NP: No Parking, WP: With Parking 

According to the City of Escondido General Plan Mobility Element Update, the City’s goal is LOS C on all 

roadways and intersections, but will accept LOS D during peak hours where LOS C cannot be attained.  

Page 12: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential   7 

Traffic Impact Analysis 

2.3  Significance Criteria 

The City of Escondido has established LOS D as  the standard  for acceptable  intersection and roadway 

segment operations except  for  roadways within  the Downtown Specific Plan area, where LOS E  is  the 

threshold for acceptable roadway and intersection operations.  

Escondido refers to the SANTEC/ITE Guidelines for Traffic  Impact Studies  (TIS)  in  the San Diego Region 

(March 2000) to determine the significance of traffic impacts in regard to requiring mitigation in the study 

area.   

The  City  of  Escondido  considers  the  following  criteria  to  determine  project‐related  significant  traffic 

impacts: 

1. Project‐related traffic results in a change in level of service from acceptable (LOS D or better) to

deficient (LOS E or F) at a study intersection or on a roadway segment; OR

2. Project‐related traffic results in an increase in delay exceeding 2.0 seconds at a study intersection

operating at  LOS D, E or F, or  results  in an  increase  in v/c  ratio exceeding 0.02 on a  roadway

segment operating at LOS D, E or F.

The first criterion would be considered a direct impact, in which the project would be fully responsible 

for mitigating the impact to restore the deficient intersection or roadway segment to an acceptable LOS.     

A cumulative  impact  is caused by the  increase  in traffic generated collectively by other development 

projects  plus  the  proposed  project  that  results  in  a  deficient  LOS.  For  intersections  and  roadway 

segments operating at a deficient LOS without the project under future conditions, increases in delay or 

v/c ratio that exceed the significance thresholds are considered cumulative impacts.  Cumulative impacts 

are  typically  mitigated  through  fair  share  contributions  toward  future  intersection  or  roadway 

improvements that would improve operations to pre‐project or better conditions.   

Page 13: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  8 

Traffic Impact Analysis 

3 EXISTING CONDITIONS 

This  section  summarizes  the  existing  roadway  network,  peak  hour  and  daily  traffic  volumes,  and 

operations at the study area intersections and roadway segments. 

3.1  Existing Roadway Network 

Nutmeg  Street  is  constructed  as  a  two‐lane  roadway  generally  oriented  in  a  north‐south  direction. 

Nutmeg Street extends from Centre City Parkway to El Norte Parkway.  South of El Norte Parkway, Nutmeg 

Street transitions to Nordahl Road. The City of Escondido General Plan Mobility Element classifies Nutmeg 

Street as a Local Collector. The posted speed limit is 25 mph between Country Club Drive and Gary Lane, 

but no speed limit is posted through the less developed area between Gary Lane and Centre City Parkway.   

Centre City Parkway is constructed as a two‐lane roadway north of Country Club Lane and transitions to 

a four‐lane road south of Country Club Lane. Centre City Parkway is generally oriented in a north‐south 

direction extending from the northern City boundary to the southern City boundary. The City of Escondido 

General  Plan  Mobility  Element  classifies  Centre  City  Parkway  as  a  Collector  from  the  northern  City 

boundary to Country Club Lane, and as a Major Road south of Country Club Lane.  The posted speed limit 

is 55 mph through the study area.  

Iris Lane is constructed as a two‐lane roadway generally oriented in a north‐south direction, extending 

south  from  Country  Club  Lane  and  terminating  at  El  Norte  Parkway.  Iris  Lane  is  classified  as  a  Local 

Collector in the City of Escondido General Plan Mobility Element.  The posted speed limit is 35 mph from 

Country Club Lane to Centre City Parkway. The posted speed limit is 30 mph from Centre City Parkway to 

El Norte Parkway.   

El Norte Parkway  is constructed as a  four‐lane to six‐lane roadway generally oriented  in an east‐west 

direction, extending from the western City boundary to Valley Parkway near the eastern City boundary.  

Within the study area, El Norte Parkway is constructed with four travel lanes between I‐15 and Iris Lane, 

and four lanes are provided east of Centre City Parkway.  El Norte Parkway is built with six travel lanes 

between Iris Lane and Centre City Parkway.  El Norte Parkway is classified as a Major Road in the Escondido 

General Plan Mobility Element.  The posted speed limit is 45 mph between I‐15 and Centre City Parkway, 

and the posted speed limit is 40 mph east of Centre City Parkway.   

Exhibit 3‐1 illustrates the existing lane geometrics and controls at the study intersections. 

Page 14: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Mul�-Family Residen�al TIA

T:\Projects\Escondido\Nutmeg Mul�-Family Residen�al Project\06_Planning\Graphics\PDF

15INTERSTATE

ProjectSite

Nutmeg St

Centre City Pkwy

Iris L

n

El Norte Pkwy

Broadway

Country Club Ln

1

23

4

5

6

LegendIntersection

Project Site Signalized Intersection

Stop Control

Lane Geometry#

Exhibit 3-1Exis�ng Intersec�on Lane Geometry

Iris Ln

CCP

CCP = Centre City Pkwy

Page 15: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  10 

Traffic Impact Analysis 

3.2  Alternate Modes of Travel 

In addition to the vehicular roadway network, alternative modes of travel are provided within the study 

area and described in more detail below. 

3.1.1 Transit Service 

North County Transit District (NCTD) operates the local transit service within the City of Escondido. There 

are currently no transit facilities within walking distance (1/4 of a mile) of the proposed project site. Transit 

service is available along Country Club Lane. Routes 358/359 operates from Escondido Transit Center to 

the  intersection of El Norte Parkway/Country Club Lane. Headways  for east and westbound travel are 

every hour for both the AM and PM weekday peak hours. Route 358/359 does not operate on Saturdays, 

Sundays, or holidays.    

3.1.2 Pedestrian and Bicycle Access 

There are currently Class II bike lanes provided on both sides of the north leg of the intersection of Centre 

City Parkway / Nutmeg Street along Centre City Parkway. There are no bicycle facilities provided on North 

Nutmeg Street near the project location.  

There are no sidewalks provided along Centre City Parkway near the project site or along North Nutmeg 

Street near the project location. 

3.3  Traffic Volumes 

Traffic volumes at the study area intersections were collected in September 2017 for the AM peak period 

(7:00 AM to 9:00 AM) and PM peak period (4:00 PM to 6:00 PM) during typical weekday conditions with 

schools in session.  Daily volumes on the study area roadway segments were also collected in September 

2017 over a 24‐hour period in both directions of travel.  

Exhibit 3‐2 illustrates the existing conditions peak hour traffic volumes at the study intersections and daily 

traffic volumes on the study roadway segments.  Appendix A contains the traffic count data sheets. 

Page 16: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

N. Centre City Parkway @ N. Nutmeg StreetN. Centre City Parkway @ W. Country Club 

LaneW. Country Club Lane @ N. Nutmeg Street

X,XXX  = ADT Volume

27  /  132

123  /  104

729  /  612

161  /  115

130  /  2

3

2  /  2

174  /  4

7

128  /  96

0  /  1

0  /  1

106  /  183

225  /  481

91  /  226153  /  141

1  /  0

335  /  380

129  /  72

13  /  35

51  /  30

45  /  111

12  /  1

0

59  /  182

194  /  273

548  /  181 139  /  6

0

7  /  4

132  /  509

11  /  15

326  /  137

34  /  161

145  /  300

N. Centre City Parkway @ S. Iris Lane

206  /  74

387  /  125

1176  /  347

59  /  1

8

773  /  712

W. El Norte Parkway @ S. Iris Lane

2

325  /  147

19  /  33

3

514  /  252

280  /  105

9  /  5

4

181  /  281

9  /  8

10  /  1

6

309  /  623

135  /  197

4

Existing Peak Hour Intersection and Daily Roadway Segment Volumes

Exhibit 3‐2

5  /  7

1103  /  248

258  /  231

xx / yy = AM / PM Peak‐Hour Turning 

Movement Volumes

8  /  34

2  /  3

6

13  /  1

4

Nutmeg Multi‐Family Residential TIA

331  /  3

4

260  /  656

86  /  376

954  /  182

2  /  1

931  /  256

5

1

5  /  13

288  /  138

80  /  3

2

1  /  3

56  /  145

168  /  404

635  /  952

T:\Projects\JM

I Real Estate\17.0571 Nutm

eg Residen

tial\06_P

lanning\Analysis\Excel‐Calcs\[Tu

rning Movemen

t Volumes.xlsx]EX

 Fig

4  /  0

34  /  44

172  /  365

283  /  200

536  /  866

313  /  5

4

N. Centre City Parkway @ W. El Norte

Parkway

4  /  8

LEGEND

Page 17: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  12 

Traffic Impact Analysis 

3.4  Intersection Analysis 

Table 3‐1 displays the LOS analysis results for the study intersections under Existing Conditions.  Appendix 

B contains the intersection LOS worksheets.

Table 3‐1 Existing Peak Hour Intersection LOS Summary 

Intersection  Control Peak Hour 

Existing Conditions 

Delay (a)  LOS 

1  N. Centre City Parkway/ N. Nutmeg Street  TWSC AM  45.3  E 

PM  25.4  D 

2  N. Centre City Parkway/ W. Country Club Lane Signal AM  35.8  D 

PM  24.3  C 

3  W. Country Club Lane/ N. Nutmeg Street  AWSC AM  29.9  D 

PM  39.2  E 

4  N. Centre City Parkway/ S. Iris Lane Signal AM  35.7  D 

PM  17.7  B 

5  N. Centre City Parkway/ W. El Norte Parkway Signal AM  60.3  E 

PM  59.0  E 

6  W. El Norte Parkway/ Iris Lane Signal AM  27.1  C 

PM  26.0  C 

Notes: Deficient intersection delay and LOS indicated in bold.  AWSC: All‐Way Stop Control; TWSC: Two‐Way Stop Control 

(a) Seconds of delay are reported as the average control delay for the entire intersection at signalized intersections and the worst minor‐street movement delay at stop‐controlled intersections. 

As shown in Table 3‐1, the study intersections currently operate at an acceptable LOS (LOS D or better) 

during the peak hours except for the following intersections that currently operate at a deficient LOS E or 

F during the peak hours: 

N. Centre City Parkway/ N. Nutmeg Street (AM: LOS E);

W. Country Club Lane/ N. Nutmeg Street (PM: LOS E); and

N. Centre City Parkway/ W. El Norte Parkway (AM: LOS E, PM: LOS E).

Page 18: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  13 

Traffic Impact Analysis 

3.5  Roadway Segment Analysis 

Table 3‐2 summarizes the daily operations of the study area roadway segments under Existing Conditions.  

As shown in Table 3‐2, all study roadway segments are currently operating at acceptable levels of service 

based on the existing daily volumes and roadway classifications.   

Table 3‐2 Existing Roadway Daily Segment LOS Summary 

Roadway Segment  Classification 

LOS E 

Capacity  ADT 

v/c 

Ratio  LOS 

N. Nutmeg Street

N. Centre City Pkwy to Project Access Local Collector (2)  15,000  2,210  0.147  A 

 Project Access to W Country Club Ln  Local Collector (2)  15,000  2,992  0.199  A 

N. Centre City Parkway

N. Nutmeg Street to W. Country Club Lane Collector (2)*  20,000  7,947  0.397  B 

W. Country Club Lane to S. Iris Lane Major Road (4)  37,000  15,886  0.429  B 

S. Iris Lane to W. El Norte Parkway Major Road (4)  37,000  18,379  0.497  A 

S. Iris Lane

N. Centre City Parkway to W. El Norte Parkway Local Collector (2)  15,000  6,621  0.441 B 

W. El Norte Parkway

S. Iris Lane to 1‐15 Major Road (4)  37,000  27,239  0.736 C 

V/C = Volume to Capacity 

*Centre City Parkway is classified as a 4‐lane Collector per the City’s General Plan, but transitions from 4 lanes to 2 lanes north of the I‐15 ramps immediately north of Country Club Lane.  The “Collector With Parking” ADT capacity threshold of 20,000 was applied to this segment of Centre City Parkway to reflect the lower daily capacity with 2 lanes versus 4 lanes.

Page 19: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  14 

Traffic Impact Analysis 

4 PROJECT TRAFFIC 

This section describes the proposed project, forecast trip generation, trip distribution, and assignment of 

trips on the adjacent roadway network.  

4.1  Project Description 

The project proposes a density of 24 dwelling units per acre, which would yield 163 multi‐family residential 

units on  the 6.8‐acre project  site.   The site  to  the north of Nutmeg Street will be developed with 45‐

Townhome  residential units.  The  townhomes would be developed as approximately 11 2‐bedroom/2‐

bath units of 950 square feet and 34 3‐bedroom/2‐bath units of 1,350 square feet. The units would be 3‐

story with a 2‐car garage. The site to the south of Nutmeg Street would be developed with 118 Apartment 

residential units. The apartments would be developed as approximately 47 1‐bedroom/1‐bath units of 

750 square feet and 71 2‐bedroom/2‐bath units of 950 square feet.  

Project access will be provided from a total of three driveways.  Two driveways will be provided for the 

site on the north side of Nutmeg Street, and one driveway will be provided for the site on the south side 

of Nutmeg Street.   

4.2  Project Trip Generation 

To determine the trips forecast to be generated by the proposed project, SANDAG trip generations rates 

(April 2002) were utilized in accordance with SANTEC/ITE Traffic Study Guidelines. Table 4‐1 summarizes 

the  trip  generation  rates  used  for  the  proposed  condominium  units  and  summarizes  the  forecast 

generated by the proposed project.  

As shown in Table 4‐1, the proposed project is forecast to generate approximately 1,068 trips per day, 

which includes approximately 85 AM peak hour trips and approximately 100 PM peak hour trips. 

Table 4‐1 Trip Generation Summary 

TRIP GENERATION RATES 

Land Use  Rate 

AM PEAK HOUR  PM PEAK HOUR 

% of ADT  In:Out Ratio 

% of ADT  In:Out Ratio 

Apartments  6  Trips  /  DU  8%  0.20  :  0.80  9%  0.70  :  0.30 

Condominiums  8  trips  /  DU  8%  0.20  :  0.80  10%  0.70  :  0.30 

TRIP GENERATION CALCULATIONS 

Land Use  Amount  ADT 

AM PEAK HOUR  PM PEAK HOUR 

Total  In  Out  Total  In  Out 

Apartments  118  DU  708  56  11  45  64  45  19 

Condominiums  45  DU  360  29  6  23  36  25  11 

Total Project Trips  1,068  85  17  68  100  70  30 

Source:  SANDAG (Not So) Brief Guide of Vehicular Traffic Generation Rates for the San Diego Region, April 2002. 

DU = Dwelling Unit 

Page 20: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  15 

Traffic Impact Analysis 

As previously discussed, the project site was previously approved for a commercial office use.   Table 4‐2 

provides  a  comparison  in  trip  generation  between  the  previously  approved  commercial  use  and  the 

proposed 163 units. 

As shown in Table 4‐2, the proposed project would generate approximately 968 fewer daily trips, 200 

fewer AM peak hour trips, and 165 fewer PM peak hour trips than the previously approved uses for the 

site.   

Table 4‐2 Trip Generation Comparison: Proposed Project Vs. General Plan Land Uses 

TRIP GENERATION RATES 

Land Use  Rate 

AM PEAK HOUR  PM PEAK HOUR 

% of ADT  In:Out Ratio 

% of ADT  In:Out Ratio 

Apartments  6  trips  /  DU  8%  0.20  :  0.80  9%  0.70  :  0.80 

Condominiums  8  trips  /  DU  8%  0.20  :  0.80  10%  0.70  :  0.50 

Commercial Office  300  trips  /  acre  14%  0.90  :  0.10  13%  0.20  :  0.80 

TRIP GENERATION CALCULATIONS 

Land Use  Amount  ADT 

AM PEAK HOUR  PM PEAK HOUR 

Total  In  Out  Total  In  Out 

Proposed Project 

Apartments  118  DU  708  56  11  45  64  45  19 

Condominiums  45  DU  360  29  6  23  36  25  11 

TOTAL PROJECT TRIPS  1,068  85  17  68  100  70  30 

General Plan Land Use 

Commercial Office  6.8  acres  2,036  285  257  28  265  53  212 

TOTAL TRIPS  2,036  285  257  28  265  53  212 

Net Difference (Project – GPLU)  ‐968  ‐200  ‐240  +40 ‐165  +17 ‐182 

Source:  SANDAG (Not So) Brief Guide of Vehicular Traffic Generation Rates for the San Diego Region, April 2002. 

DU = Dwelling Unit 

Page 21: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  16 

Traffic Impact Analysis 

4.3  Project Trip Distribution 

The project trip distribution was developed based on existing travel patterns and access to the major road 

networks in the study area. Considerations including local land use and local roadway network/freeway 

access were used in determining the trip distribution. The following list shows the general trip distribution 

assumed to and from the project site: 

20 percent to/from the west

10 percent to/from the north

70 percent to/from the south

Exhibit 4‐1  illustrates the trip distribution for the proposed project at the study intersections.  The trip 

distribution at the project driveways is illustrated in Exhibit 4‐2.   

4.4  Project Trip Assignment 

Based on the trip distribution shown in Exhibit 4‐1, project trips were assigned to the study area roadway 

network.  Exhibit 4‐3 illustrates the AM/PM peak hour project trip assignment at the study intersections 

and the daily project trip assignment on the study roadway segments.  The AM/PM peak hour project trip 

assignment at the project driveways is illustrated in Exhibit 4‐4.  

Page 22: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

The naming convention for intersections is North / South @ East / West

N. Centre City Parkway @ N. Nutmeg Street N. Centre City Parkway @ W. Country Club Lane

0%  /  (0%)

0%  /  (0%) 25%  /  (0%)

0%  /  (0%)

6

0%  /  (0%) 0%  /  (0%)

Exhibit 4‐1

Project Trip Distribution

32%  /  (0%)

0%  /  (0%) 0%  /  (0%)

5%  /  (0%) 3%  /  (0%)

10%  /  (0%)

0%  /  (0%) 0%  /  (0%)

0%  /  (0%)

0%  /  (0%)

0%  /  (0%)

0%  /  (0%)

27%  /  (0%)

0%  /  (0%)

0%  /  (0%)

0%  /  (0%)

0%  /  (0%) 0%  /  (0%) 0%  /  (0%) 0%  /  (0%)5%  /  (5%)

0%  /  (20%)

0%  /  (10%)

0%  /  (0%)

0%  /  (25%)

0%  /  (35%)

0%  /  (0%)

LLeg

0%  /  (0%)

28%  /  (0%)

60%  /  (0%)

0%  /  (0%)

0%  /  (0%)

0%  /  (0%)

0%  /  (0%)

60%  /  (0%)

0%  /  (0%)

20%  /  (0%)

0%  /  (65%)

0%  /  (0%)

1 2 3

0%  /  (0%) 0%  /  (0%) 0%  /  (0%)

0%  /  (0%)

0%  /  (0%)

0%  /  (0%)

0%  /  (0%) 0%  /  (0%)

Nutmeg Multi‐Family Residential TIA

0%  /  (0%) 0%  /  (0%)

4

0%  /  (0%) 0%  /  (0%)0%  /  (0%)

N. Centre City Parkway @ S. Iris Lane

T:\Projects\JM

I Real Estate\17.05

71 Nutm

eg Residential\06_

Planning\Analysis\Excel‐Calcs\[Tu

rning Movement Volumes_3 Driveways.xlsx]Proj D

ist Fig

5%  /  (0%)

0%  /  (0%)

0%  /  (0%)

0%  /  (0%)

0%  /  (60%)

0%  /  (0%)

0%  /  (5%) 0%  /  (0%)

0%  /  (3%)

5

0%  /  (27%)

0%  /  (5%)

0%  /  (25%)

0%  /  (0%)

W. El Norte Parkway @ S. Iris Lane

0%  /  (0%)

N. Centre City Parkway @ W. El Norte Parkway

W. Country Club Lane @ N. Nutmeg Street

xx%= Trip Distribution Percentage

xx% / (yy%) = Inbound % /Outbound %

LEGEND

10%

25

5%

30%

8%

2%

Page 23: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Exhibit 4‐2

Trip Distribution at Project Driveways

xx / yy = AM / PM Peak‐Hour Project Trips            

0%  /  (0%) 20%  /  (0%) 0%  /  (0%)

0%  /  (46%)

0%  /  (58%)

0%  /  (0%)

0%  /  (0%)

5%  /  (0%) 5%  /  (0%)

25%  /  (0%)

0%  /  (0%)

0%  /  (0%)

5%  /  (12%)

0%  /  (25%) 12%  /  (5%) 58%  /  (0%)

0%  /  (0%) 46%  /  (0%) 0%  /  (0%)

12%  /  (0%) 0%  /  (0%) 12%  /  (0%)

0%  /  (5%)

0%  /  (12%)

0%  /  (0%)

0%  /  (0%)

0%  /  (5%)

0%  /  (12%)

T:\Projects\JM

I Real Estate\17.0571 Nutm

eg Residential\06_P

lanning\Analysis\Excel‐Calcs\[Tu

rning Movement Volumes_3 Driveways.xlsx]Dwy DIst Fig

N. Nutmeg St. @ Project Driveway 1 N. Nutmeg St. @ Project Driveway 2 N. Nutmeg St. @ Project Driveway 3

7 8 9

0%  /  (20%)

Nutmeg Multi‐Family Residential TIA

LEGEND

7

89

Page 24: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

N. Centre City Parkway @ N. Nutmeg Street N. Centre City Parkway @ S. Iris Lane

X,XXX  = ADT Volume

xx / yy = AM / PM Peak‐Hour Project Trips         

Exhibit 4‐3

Peak Hour and Daily Project Trip Assignment

0  /  0 0  /  0 0  /  0

0  /  00  /  0

0  /  0

5  /  19

0  /  0 0  /  0

0  /  0

0  /  0 0  /  0

4  /  18

0  /  0 0  /  0

0  /  0 0  /  0

1  /  4 1  /  2

2

0  /  0

0  /  0

0  /  0

5  /  22

0  /  0

44  /  20 0  /  0 0  /  0 0  /  0

0  /  0

0  /  0

2  /  7

0  /  0 0  /  0

0  /  00  /  0

10  /  42

0  /  0

0  /  0 0  /  0

0  /  0

10  /  42

0  /  0

0  /  0

W. Country Club Lane @ N. Nutmeg StreetN. Centre City Parkway @ W. Country Club 

Lane

T:\Projects\JM

I Real Estate\17.0571 Nutm

eg Residen

tial\06_P

lanning\Analysis\Excel‐Calcs\[Tu

rning Movemen

t Volumes_3

 Driveways.xlsx]Proj A

ssign Fig

1  /  4

0  /  0

0  /  0

0  /  0

41  /  18

0  /  0

3  /  2 0  /  0

2  /  1

5

18  /  8

3  /  2

17  /  8

0  /  0

W. El Norte Parkway @ S. Iris LaneN. Centre City Parkway @ W. El Norte

Parkway

0  /  0

0  /  0

6

1

Nutmeg Multi‐Family Residential TIA

0  /  04  /  6

14  /  6

7  /  3

0  /  0

17  /  8

24  /  11

3  /  14 5  /  20

0  /  0 0  /  0

3 4

0  /  0

0  /  0 0  /  0

LEGEND

Page 25: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential TIA

N. Nutmeg St. @ Project Driveway 1

T:\Projects\JM

I Real Estate\17.0571 Nutm

eg Residential\06_P

lanning\Analysis\Excel‐Calcs\[Tu

rning Movement Volumes_3 Driveways.xlsx]Dwy Vol Fig

N. Nutmeg St. @ Project Driveway 2 N. Nutmeg St. @ Project Driveway 3

3  /  2

0  /  0

8  /  4

0  /  0

0  /  0 8  /  32 0  /  0

7 8 9

2  /  8 0  /  0 2  /  8

17  /  8 5  /  10 10  /  413  /  2

8  /  4

1  /  4 0  /  0 1  /  4

4  /  18

0  /  0

0  /  0 9  /  8

14  /  6

3  /  14 0  /  0

31  /  14 39  /  17

0  /  0

0  /  0

xx / yy = AM / PM Peak‐Hour Project Trips            

Exhibit 4‐4

Peak Hour Trip Assignment at Project Driveways

LEGEND

7

89

Page 26: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  21 

Traffic Impact Analysis 

5 EXISTING PLUS PROJECT CONDITIONS 

This section provides a summary of operations at the study area intersections and roadway segments with 

the addition of project traffic. 

5.1  Traffic Volumes 

Exhibit 5‐1  illustrates the Existing Plus Project peak hour traffic volumes at the study intersections and 

daily traffic volumes at the study roadway segments.  

5.2  Intersection Analysis 

Table  5‐1  displays  the  LOS  analysis  results  for  the  study  intersections  under  the  Existing  Plus  Project 

scenario. Appendix C contains the intersection LOS worksheets. 

 Table 5‐1 Existing Plus Project Peak Hour Intersection LOS Summary 

Intersection  Control Peak Hour 

Existing Conditions 

Existing Plus Project  Change 

in Delay Delay (a)  LOS  Delay (a)  LOS 

1 N. Centre City Parkway/ N. NutmegStreet

TWSC AM  45.3  E  54.9  F  9.6 

PM  25.4  D  32.1  D  6.7 

2 N. Centre City Parkway/ W. Country ClubLane

Signal AM  35.8  D  37.3  D  1.5 

PM  24.3  C  25.1  C  0.8 

3  W. Country Club Lane/ N. Nutmeg Street  AWSC AM  29.9  D  34.2  D  4.3 

PM  39.2  E  42.9  E  3.7 

4  N. Centre City Parkway/ S. Iris Lane Signal AM  35.7  D  36.6  D  0.9 

PM  17.7  B  17.9  B  0.2 

5 N. Centre City Parkway/ W. El NorteParkway

Signal AM  60.3  E  60.4  E  0.1 

PM  59.0  E  58.3  E  ‐0.7 

6  W. El Norte Parkway/ Iris Lane Signal AM  27.1  C  27.9  C  0.8 

PM  26.0  C  26.4  C  0.4 

7  N. Nutmeg Street/Project Driveway 1 OWSC AM 

DNE 11.1  B  ‐ 

PM  9.4  A  ‐ 

8  N. Nutmeg Street/Project Driveway 2 OWSC AM 

DNE 9.6  A  ‐ 

PM  9.6  A  ‐ 

9  N. Nutmeg Street/Project Driveway 3 OWSC AM 

DNE 11.2  B  ‐ 

PM  9.6  A  ‐ 

Notes: Deficient intersection delay and LOS indicated in bold.  Increase in delay in bold indicates a project‐related significant impact.  

DNE = Does not exist. AWSC: All‐Way Stop Control; TWSC: Two‐Way Stop Control; OWSC: One‐Way Stop Control (a) Seconds of delay are reported as the average control delay for the entire intersection at signalized intersections and the worst minor‐street movement delay at stop‐controlled intersections. 

Page 27: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

N. Centre City Parkway @ N. Nutmeg Street N. Centre City Parkway @ W. Country Club Lane W. Country Club Lane @ N. Nutmeg Street N. Centre City Parkway @ S. Iris Lane

xx / yy = AM / PM Peak‐Hour Turning 

Movement Volumes

Exhibit 5‐1

283  /  200 5  /  13 2  /  3

13  /  14536  /  866

172  /  365

265  /  675

86  /  376 635  /  952

5  /  7 X,XXX  = ADT Volume

Existing Plus Project Peak Hour Intersection and Daily Roadway Segment Volumes

314  /  645

135  /  197

48  /  20 129  /  72 51  /  30 11  /  15

181  /  281

9  /  54

36  /  168

145  /  300 194  /  273

10  /  16

729  /  612 773  /  712

288  /  138 8  /  34

154  /  145

64  /  202

1  /  3

14  /  50

132  /  509

7  /  4 335  /  380

45  /  111

235  /  523

106  /  183

16  /  49

387  /  125

1 2 3 4

12  /  10

0  /  1 128  /  96 19  /  33 9  /  8

0  /  1 514  /  252 548  /  181 206  /  74165  /  121

144  /  29

181  /  50

59  /  18

156  /  68

1200  /  358

326  /  137

T:\Projects\JM

I Real Estate\17.05

71 Nutm

eg Residential\06_

Planning\Analysis\Excel‐Calcs\[Tu

rning Movement Volumes_3 Driveways.xlsx]EXP Fig

332  /  38

954  /  182

2  /  1

313  /  54

972  /  274

2  /  2

30  /  134 56  /  145

82  /  33

5

1121  /  256

261  /  233

342  /  155

1  /  0

W. El Norte Parkway @ S. Iris Lane

280  /  105

123  /  104

6

N. Centre City Parkway @ W. El Norte Parkway

34  /  44 172  /  422

92  /  228

Nutmeg Multi‐Family Residential TIA

LEGEND

Page 28: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  23 

Traffic Impact Analysis 

As  shown  in  Table  5‐1,  consistent  with  existing  conditions,  the  following  study  intersections  would 

continue operating at deficient LOS (LOS E or F) during the peak hours with the addition of project‐related 

traffic to existing traffic volumes: 

N. Centre City Parkway/ N. Nutmeg Street (AM: LOS F);

W. Country Club Lane/ N. Nutmeg Street (PM: LOS E); and

N. Centre City Parkway/ W. El Norte Parkway (AM: LOS E, PM: LOS E).

The forecast increase in delay to the following two intersections would exceed the significance threshold 

of 2.0 seconds: 

N. Centre City Parkway/ N. Nutmeg Street (AM and PM); and

W. Country Club Lane/ N. Nutmeg Street (AM only).

Although  the  intersection  of  W.  Country  Club  Lane/N.  Nutmeg  Street  is  forecast  to  operate  at  an 

acceptable LOS D during the AM peak hour, the project‐related increase in delay during the AM peak hour 

would exceed City’s significance threshold for LOS D operations.  Therefore, the project would result in 

significant  impacts  at  the  two  above‐listed  intersections  under  Existing  Plus  Project  conditions  and 

mitigation measures are required.   

The analysis results shown in Table 5‐1 indicate that the forecast delay at the intersection of N. Centre 

City Parkway/ W. El Norte Parkway would decrease with the addition of project‐related traffic to existing 

AM and PM peak hour traffic volumes.  The reason for the decrease in overall intersection delay is because 

project‐related traffic would be added to non‐critical movements during the peak hours.    

5.3  Roadway Segment Analysis 

Table 5‐2 summarizes the daily operations of the study area roadway segments under Existing Plus Project 

conditions.  As shown in Table 5‐2, consistent with existing conditions, all study roadway segments will 

continue operating at acceptable levels of service under Existing Plus Project conditions.

Page 29: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential   24 

Traffic Impact Analysis 

Table 5‐2 Existing Plus Project Daily Roadway Segment LOS Summary 

Roadway Segment  Classification LOS E 

Capacity 

Existing  Existing Plus Project 

 in V/C 

Signifi‐ cant? ADT 

v/c Ratio  LOS  ADT 

v/c Ratio  LOS 

N. Nutmeg Street

N. Centre City Pkwy to Project Access Local Collector (2)  15,000  2,210  0.147  A  2,958  0.197  A  0.050  No 

 Project Access to W Country Club Ln  Local Collector (2)  15,000  2,992  0.199  A  3,312  0.221  A  0.021  No 

N. Centre City Parkway

N. Nutmeg Street to W. Country Club Lane Collector (2)*  20,000  7,947  0.397  B  8,641  0.432  B  0.035  No 

W. Country Club Lane to S. Iris Lane Major Road (4)  37,000  15,886  0.429  B  16,527  0.447  B  0.017  No 

S. Iris Lane to W. El Norte Parkway Major Road (4)  37,000  18,379  0.497  B  18,737  0.506  B  0.010  No 

S. Iris Lane 

N . Centre City Parkway to W. El Norte Parkway  Local Collector (2)  15,000  6,621  0.441  B  6,904  0.460  B  0.019  No 

W. El Norte Parkway

S. Iris Lane to 1‐15 Major Road (4)  37,000  27,239  0.736  C  27,506  0.743  D  0.007  No 

V/C = Volume to Capacity

*Centre City Parkway is classified as a 4‐lane Collector per the City’s General Plan, but transitions from 4 lanes to 2 lanes north of the I‐15 ramps immediately north of Country Club Lane.  The “CollectorWith Parking” ADT capacity threshold of 20,000 was applied to this segment of Centre City Parkway to reflect the lower daily capacity with 2 lanes versus 4 lanes.

Page 30: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  25 

Traffic Impact Analysis 

6 EXISTING PLUS CUMULATIVE CONDITIONS 

6.1  Cumulative Projects 

To determine the Existing Plus Cumulative conditions  in the project study area, forecast project traffic 

associated with City of Escondido approved or pending projects was added to existing traffic volumes. The 

City of Escondido provided a list of 13 cumulative projects that would generate traffic into the study area 

by the project opening year.   

The  list  of  cumulative  projects  and  the  trips  generated  by  each  project  are  presented  in  Table  6‐1.  

Appendix D provides the trip distribution and daily trips for each of the cumulative projects on the study 

roadway segments.  

Table 6‐1 Cumulative Projects Trip Generation 

ID # 

Project Name Daily  Trips 

AM Peak Hour  PM Peak Hour 

Total  Inbound  Outbound  Total  Inbound  Outbound 

1  Hidden Valley Ranch  1,790  143  43  100  179  125  54 

2  Zenner  400  32  10  22  40  28  12 

3  1221 Gamble St  30  2  1  1  3  2  1 

4  Escondido Country Club‐ The Villages  3,920  314  94  220  392  274  118 

5  Hubbard  120  10  3  7  12  8  4 

6  Pradera   700  56  17  39  70  49  21 

7  Baker Conway  140  11  3  8  14  10  4 

8  Jungman Specifc Plan  688  688  79  55  24  81  30 

9  Meadowbrook  396  32  6  26  36  25  11 

10  Champine Manor  30  1  1  0  2  1  1 

11  Calvin Christian  140  7  4  3  11  5  6 

12  United Reformed Church  157  8  5  3  13  7  6 

13  Starbucks  1,801  283  147  136  157  82  76 

TOTAL CUMULATIVE PROJECT TRIPS  10,312  978  389  589  1,010  647  363 

As presented in Table 6‐1, the cumulative projects within the City of Escondido are forecast to generate 

approximately  10,312  trips  per  day,  which  includes  approximately  978  AM  peak  hour  trips  and 

approximately  1,010 PM peak hour trips.   Exhibit 6‐1 shows the locations of the cumulative projects. 

Exhibit 6‐2  illustrates  the peak hour and daily  cumulative project  trips  at  the  study  intersections  and 

roadway segments. 

6.2  Traffic Volumes 

To determine the Existing Plus Cumulative operating conditions in the study area, the cumulative project 

trips were added to the existing traffic volumes at the study intersection and roadway segment locations. 

Exhibit  6‐3  illustrate  the  peak  hour  and  daily  traffic  volumes  at  the  study  intersections  and  roadway 

segments  under  Existing  Plus  Cumulative Without  Project  conditions.    Existing  Plus  Cumulative With 

Project conditions peak hour and daily traffic volumes at the study intersections and roadway segments 

are illustrated in Exhibit 6‐4.   

Page 31: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Mul�-Family Residen�al TIA

T:\Projects\Escondido\Nutmeg Mul�-Family Residen�al Project\06_Planning\Graphics\PDF

15INTERSTATE

ProjectSite

Nutmeg St

Centre City Pkwy

Iris L

n

El Norte Pkwy

Broadway

Country Club Ln

1

23

4

5

6

4

9 11

1

2

3

5

76

10

12

8

13

Exhibit 6-1Cumula�ve Projects Loca�on

LegendIntersection

Cumulative Project

Project Site

##

Page 32: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

N. Centre City Parkway @ N. Nutmeg Street N. Centre City Parkway @ W. Country Club Lane W. Country Club Lane @ N. Nutmeg Street N. Centre City Parkway @ S. Iris Lane

7  /  3

  /  

  /  

/

335  /  43

/

2  /  7

32  /  135 14 

  /  

  /  

3  /  14

0  /  0 15  /  7

3 4

0  /  00  /  0 21  /  12 0  /  0 0  /  0

0  /  0 11  /  6 41  /  79 29  /  159  /  26

0  /  0

0  /  0

0  /  0

0  /  0

55  /  30

Nutmeg Multi‐Family Residential TIAT:\Projects\JM

I Real Estate\17.05

71 Nutm

eg Residential\06_

Planning\Analysis\Excel‐Calcs\[Tu

rning Movement Volumes.xlsx]CUMPROJ Fig

0  /  0

12  /  17

0  /  0

9  /  27

7  /  6

0  /  0

0  /  0 22  /  12

N. Centre City Parkway @ W. El Norte Parkway W. El Norte Parkway @ S. Iris Lane

29  /  16

26  /  13

15  /  7

41  /  44

0  /  0

8  /  18

7  /  4

106  /  71

0  /  0

5 6

1 2

0  /  0 7  /  4

0  /  0

0  /  0

17  /  10

0  /  0 5  /  13

21  /  45

7  /  6

7  /  4

0  /  0 40  /  22 22  /  12 0  /  0

67  /  47

9  /  27

0  /  0

0  /  0 18  /  37

xx / yy = AM / PM Peak‐Hour Cumulative    

Project Trips

66  /  92

0  /  0

27  /  15 0  /  0

2  /  7

0  /  0

28  /  49

X,XXX  = ADT Volume

Exhibit 6‐2

Peak Hour Cumulative Project Trips and Daily Roadway Segment Volumes

0  /  0

20  /  20 0  /  0

14  /  8 43  /  49

110  /  139

29  /  16

10  /  31

12  /  34

6 /  17 14  / 8

141  /  79

LEGEND

Page 33: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

N. Centre City Parkway @ N. Nutmeg Street N. Centre City Parkway @ W. Country Club Lane W. Country Club Lane @ N. Nutmeg Street N. Centre City Parkway @ S. Iris Lane

Nutmeg Multi‐Family Residential TIAT:\Projects\JM

I Real Estate\17.05

71 Nutm

eg Residential\06_

Planning\Analysis\Excel‐Calcs\[Tu

rning Movement Volumes.xlsx]EXC Fig

331  /  34

966  /  199

2  /  1

1

1  /  3

4  /  8

149  /  519

9  /  8

0  /  1 525  /  258 589  /  260 235  /  89

2  /  2 287  /  109 326  /  137 402  /  132

139  /  60

1231  /  377

12  /  10

0  /  1 149  /  108 19  /  33

322  /  81

938  /  262

170  /  141

130  /  23

174  /  47

59  /  18

232  /  487

113  /  187 248  /  328

2 3 4

27  /  132 78  /  157 13  /  35 66  /  186

109  /  48

1129  /  261

273  /  238

366  /  191

1  /  0

131  /  122

159  /  158 105  /  234

137  /  204

4  /  0 169  /  94 73  /  42 11  /  15

N. Centre City Parkway @ W. El Norte Parkway W. El Norte Parkway @ S. Iris Lane

18  /  81

34  /  161

145  /  300 212  /  310

10  /  16

337  /  672

7  /  4 340  /  393

66  /  156

870  /  691 879  /  783

315  /  153 8  /  34

5 6

5  /  7

2  /  3

13  /  14

xx / yy = AM / PM Peak‐Hour Turning 

              Movement Volumes

Exhibit 6‐3

48  /  52 211  /  453

646  /  1005

201  /  381

270  /  687

98  /  410 701  /  1044

303  /  220 5  /  13

X,XXX  = ADT Volume

Existing Plus Cumulative Without Project Peak Hour Intersection and Daily Roadway Segment Volumes

LEGEND

Page 34: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

N. Centre City Parkway @ N. Nutmeg Street W. Country Club Lane @ N. Nutmeg Street N. Centre City Parkway @ S. Iris Lane

5  /  7

2  /  3

13  /  14

xx / yy = AM / PM Peak‐Hour Turning 

              Movement Volumes

Exhibit 6‐4

48  /  52 215  /  471

646  /  1005

201  /  381

275  /  706

98  /  410 701  /  1044

303  /  220 5  /  13

Existing Plus Cumulative With Project Peak Hour Intersection and Daily Roadway Segment Volumes

X,XXX  = ADT Volume

315  /  153 8  /  34

5 6

870  /  691 879  /  783

160  /  162 106  /  236

137  /  204

48  /  20 169  /  94 73  /  42 11  /  15

N. Centre City Parkway @ W. El Norte Parkway W. El Norte Parkway @ S. Iris Lane

18  /  81

36  /  168

145  /  300 212  /  310

10  /  16

342  /  694

7  /  4 340  /  393

66  /  156

30  /  134 78  /  157 16  /  49 71  /  206

111  /  49

1147  /  269

276  /  240

383  /  199

1  /  0

131  /  122

144  /  29

181  /  50

59  /  18

242  /  529

113  /  187 248  /  328

2 3 4

T:\Projects\JM

I Real Estate\17.05

71 Nutm

eg Residential\06_

Planning\Analysis\Excel‐Calcs\[Tu

rning Movement Volumes_3 Driveways.xlsx]EXCP Fig

332  /  38

966  /  199

2  /  1

1

1  /  3

14  /  50

149  /  519

9  /  8

0  /  1 525  /  258 589  /  260 235  /  89

2  /  2 287  /  109 326  /  137 402  /  132

156  /  68

1255  /  388

12  /  10

0  /  1 149  /  108 19  /  33

322  /  81

Nutmeg Multi‐Family Residential TIA

979  /  280

N. Centre City Parkway @ W. Country Club 

Lane

174  /  147

LEGEND

Page 35: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  30 

Traffic Impact Analysis 

6.3  Intersection Analysis 

Table  6‐2  displays  the  LOS  analysis  results  for  the  study  intersections  under  Existing  Plus  Cumulative 

conditions without and with the proposed project.  Appendix E contains the intersection LOS worksheets 

for Existing Plus Cumulative conditions without the project, and the Existing Plus Cumulative With Project 

conditions intersection LOS worksheets are provided in Appendix F. 

As shown in Table 6‐2, the following three study intersections are forecast to operate at a deficient LOS E 

or F during the peak hours under Existing Plus Cumulative conditions both without and with the proposed 

project: 

N. Centre City Parkway/ N. Nutmeg Street (AM: LOS F);

W. Country Club Lane/ N. Nutmeg Street (AM: LOS E, PM: LOS F); and

N. Centre City Parkway/ W. El Norte Parkway (AM: LOS E, PM: LOS E).

The forecast increase in delay to the following two intersections would exceed the significance threshold 

of 2.0 seconds: 

N. Centre City Parkway/ N. Nutmeg Street; and

W. Country Club Lane/ N. Nutmeg Street.

Therefore,  the project would  result  in  significant  impacts  at  the  two  above‐listed  intersections  under 

Existing Plus Cumulative With Project conditions, and mitigation measures are required.   

The analysis results shown in Table 6‐2 indicate that the forecast delay at the intersection of N. Centre 

City Parkway/ W. El Norte Parkway would decrease with the addition of project‐related traffic to existing 

PM peak hour traffic volumes.  The reason for the decrease in overall intersection delay is because project‐

related traffic would be added to non‐critical movements during the peak hours.     

6.4  Roadway Segment Analysis 

Table  6‐3  summarizes  the  daily  operations  of  the  study  area  roadway  segments  under  Existing  Plus 

Cumulative  conditions  without  and  with  the  proposed  project.    As  shown  in  Table  6‐3,  three  study 

roadway segments are forecast to operate at an acceptable LOS D or better under Existing Plus Cumulative 

conditions both without and with the proposed project.   

Page 36: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  31 

Traffic Impact Analysis 

Table 6‐2 Existing Plus Cumulative Conditions Without and With Project 

Peak Hour Intersection LOS Summary 

Intersection  Control Peak Hour 

EXC Without Project 

EXC With  Project  Change 

in Delay Delay (a)  LOS  Delay (a)  LOS 

1 N. Centre City Parkway/ N. NutmegStreet

TWSC AM  48.2  E  58.3  F  10.1 

PM  27.1  D  34.8  D  7.7 

2 N. Centre City Parkway/ W. Country ClubLane

Signal AM  42.2  D  44.0  D  1.8 

PM  28.8  C  30.4  C  1.6 

3  W. Country Club Lane/ N. Nutmeg Street  AWSC AM  39.1  E  43.9  E  4.8 

PM  52.8  F  56.8  F  4.0 

4  N. Centre City Parkway/ S. Iris Lane Signal AM  42.3  D  44.2  D  1.9 

PM  19.1  B  19.3  B  0.2 

5 N. Centre City Parkway/ W. El NorteParkway

Signal AM  61.4  E  61.5  E  0.1 

PM  60.7  E  60.0  E  ‐0.7 

6  W. El Norte Parkway/ Iris Lane Signal AM  31.9  C  34.4  C  2.5 

PM  28.2  C  28.7  C  0.5 

7  N. Nutmeg Street/Project Driveway 1 OWSC AM 

DNE 11.1  B  ‐ 

PM  9.4  A  ‐ 

8  N. Nutmeg Street/Project Driveway 2 OWSC AM 

DNE 9.6  A  ‐ 

PM  9.6  A  ‐ 

9  N. Nutmeg Street/Project Driveway 3 OWSC AM 

DNE 11.2  B  ‐ 

PM  9.6  A  ‐ 

Notes: Deficient intersection delay and LOS indicated in bold.  Increase in delay in bold indicates a project‐related significant impact.  

DNE = Does not exist. AWSC: All‐Way Stop Control; TWSC: Two‐Way Stop Control; OWSC: One‐Way Stop Control 

EXC = Existing Plus Cumulative (a) Seconds of delay are reported as the average control delay for the entire intersection at signalized intersections and the worst minor‐street movement delay at stop‐controlled intersections. 

Page 37: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential    32 

Traffic Impact Analysis 

Table 6‐3 Existing Plus Cumulative Conditions Without and With Project 

Daily Roadway Segment LOS Summary 

Roadway Segment  Classification LOS E 

Capacity 

EXC Without Project  EXC With Project 

 in V/C 

Signifi‐ cant? ADT 

v/c Ratio  LOS  ADT 

v/c Ratio  LOS 

N. Nutmeg Street

N. Centre City Pkwy to Project Access Local Collector (2)  15,000  2,210  0.147  A  2,958  0.197  A  0.050  No 

 Project Access to W Country Club Ln  Local Collector (2)  15,000  2,992  0.199  A  3,312  0.221  A  0.021  No 

N. Centre City Parkway

N. Nutmeg Street to W. Country Club Lane   Collector (2)  20,000  8,425  0.421  B  9,119  0.456  B  0.035  No 

W. Country Club Lane to S. Iris Lane   Major Road (4)  37,000  16,744  0.453  B  17,385  0.470  B  0.017  No 

S. Iris Lane to W. El Norte Parkway  Major Road (4)  37,000  19,356  0.523  B  19,714  0.533  B  0.010  No 

S. Iris Lane

N. Centre City Parkway to W. El Norte Parkway Local Collector (2)  15,000  7,199  0.480  B  7,482  0.499  B  0.019  No 

W. El Norte Parkway

S. Iris Lane to 1‐15 Major Road (4)  37,000  29,658  0.802  D  29,925  0.809  D  0.007  No 

EXC = Existing Plus Cumulative 

V/C = Volume to Capacity 

*Centre City Parkway is classified as a 4‐lane Collector per the City’s General Plan, but transitions from 4 lanes to 2 lanes north of the I‐15 ramps immediately north of Country Club Lane.  The “Collector With Parking” ADT capacity threshold of 20,000 was applied to this segment of Centre City Parkway to reflect the lower daily capacity with 2 lanes versus 4 lanes 

Page 38: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  33 

Traffic Impact Analysis 

7 SIGNAL WARRANT ANALYSIS 

A signal warrant analysis was conducted at the following two (2) unsignalized intersections to determine 

if existing and/or future traffic volumes at the intersections would justify installation of traffic signals: 

N. Centre City Parkway/ N. Nutmeg Street

W. Country Club Lane/ N. Nutmeg Street

The signal warrant analysis for N. Centre City Parkway/ N. Nutmeg Street and W. Country Club Lane/ N. 

Nutmeg Street was performed all analysis scenarios without and with the proposed project.   

The signal warrant analysis was performed in accordance with the 2014 California Manual on Uniform 

Traffic Devices (MUTCD).   The signal warrants,  if satisfied, provide  justification for the  installation of a 

traffic signal, but would not require the installation of a signal. The following individual signal warrants 

from Chapter 4C (Traffic Control Signal Needs Studies) of the 2014 California MUTCD were performed in 

this study: 

Warrant 3: Peak Hour (Part A and Part B)

Satisfaction of either Part A or Part B satisfies the Peak Hour Warrant.  Due to the all‐way stop control at 

the W. Country Club Lane/ N. Nutmeg Street  intersection,  traffic speeds were not considered and the 

conservative “70% Factor” threshold was not applied at that intersection.   

The “70% Factor” threshold was applied to the N. Centre City Parkway/ N. Nutmeg Street intersection 

since the posted speed limit on N. Center Centre City Parkway (55 mph) exceeds 40 mph.   

The findings of the traffic signal warrant analysis are summarized in Table 7‐1. Appendix G contains the 

signal warrant worksheets. 

Table 7‐1 shows that at the intersection of N. Centre City Parkway/ N. Nutmeg Street, either Part A or Part 

B (or both) of the peak hour warrant were satisfied under the following analysis scenarios: 

Existing Conditions (PM: Part B)

Existing Plus Project Conditions (AM/PM: Part B)

Existing Plus Cumulative Without Project Conditions (PM: Part B)

Existing Plus Cumulative With Project Conditions (AM/PM: Part B)

Table 7‐1 also shows that at the intersection of W. Country Club Lane/ N. Nutmeg Street, either Part A or 

Part B (or both) of the peak hour warrant were satisfied under the following analysis scenarios: 

Existing Conditions (AM: Part B; PM: Parts A and B)

Existing Plus Project Conditions (AM: Part B; PM: Parts A and B)

Existing Plus Cumulative Without Project Conditions (AM: Part B; PM: Parts A and B)

Existing Plus Cumulative With Project Conditions (AM/PM: Part A; AM/PM: Part B)

Page 39: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  34 

Traffic Impact Analysis 

Table 7‐1 Signal Warrant Analysis 

Intersection Peak Hour 

Peak Hour Warrant 

Existing  Existing + Project  Ex+Cum w/o Project  Ex+Cum w/ Project 

Part A  Part B  Part A  Part B  Part A  Part B  Part A  Part B 

N. Centre City Parkway/ N. Nutmeg Street AM  NO  NO  NO YES NO  NO  NO YES 

PM  NO  YES  NO YES NO YES NO YES

W. Country Club Lane/ N. Nutmeg Street AM  NO  YES NO YES NO  YES  YES  YES 

PM  YES  YES  YES  YES  YES  YES  YES  YES 

Source: California MUTCD 2014 Edition 

Ex+Cum = Existing Plus Cumulative 

Page 40: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  35 

Traffic Impact Analysis 

8 SITE ACCESS EVALUATION 

As previously described, the project will  take access from Nutmeg Street from a total of three project 

driveways.    Two driveways will be provided  for  the  site on  the north  side of Nutmeg Street,  and one 

driveway  will  be  provided  for  the  site  on  the  south  side  of  Nutmeg  Street.  All  three  project  access 

intersections will be stop‐controlled on the driveway approaches of the intersection.  The eastbound and 

westbound  intersection approaches on Nutmeg Street will  be uncontrolled  at  all  three project  access 

intersections.   

Based on the results of the HCM intersection analysis, the unsignalized project driveway intersections at 

N. Nutmeg Street are forecast to operate at acceptable levels of service (LOS D or better) during the peak

hours under all analysis scenarios with the project. Therefore, no operational impacts are anticipated at

the project access intersections.

The driveway serving the southern parcel (Driveway 2) would be located near the center of the horizontal 

curve on Nutmeg Street to provide the minimum line of sight needed from the driveway.  The westerly 

driveway serving the northern parcel (Driveway 1) would be located approximately 100 feet west of the 

southern  parcel  driveway.    The  easterly  driveway  serving  the  northern  parcel  (Driveway  3) would  be 

located approximately 100 feet west of Centre City Parkway.   

There  is  no  posted  speed  limit  on  Nutmeg  Street  between  Gary  Lane  and  Centre  City  Parkway,  but 

according to the City’s Street Design Standards, the design speed for a Local Collector street is 35 mph. 

The minimum intersection corner sight distance needed for a design speed of 35 mph is approximately 

385 feet according to the Caltrans Highway Design Manual (6th Edition, 2012).     

Vehicles turning left to enter or exit Driveway 3 may be blocked by queuing on the eastbound approach 

of the Centre City Parkway/Nutmeg Street intersection. In addition, the close proximity of Driveway 3 to 

the Centre City Parkway/Nutmeg Street intersection may result in safety issues due to the relatively high 

number of  vehicles on  southbound Centre City Parkway  turning  right onto westbound Nutmeg Street 

during the AM peak hour.  For these reasons, it is recommended that access to Driveway 3 be limited to 

right‐turn in only.   

Page 41: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  36 

Traffic Impact Analysis 

9 SIGNIFICANT IMPACTS AND RECOMMENDED MITIGATION 

As presented earlier  in  this  report,  the City of Escondido considers the following criteria  to determine 

project‐related significant traffic impacts: 

1. Project‐related traffic results in a change in level of service from acceptable (LOS D or better) to

deficient (LOS E or F) at a study intersection or on a roadway segment; OR

2. Project‐related traffic results in an increase in delay exceeding 2.0 seconds at a study intersection

operating at  LOS D, E or F, or  results  in an  increase  in v/c  ratio exceeding 0.02 on a  roadway

segment operating at LOS D, E or F.

The proposed project’s  traffic  impacts and  recommended mitigation measures are described  in detail 

below: 

Existing Plus Project Conditions: Significant Impacts and Recommended Mitigation 

The results of the Existing Plus Project Conditions analysis show that the addition of project‐related traffic to 

the existing traffic volumes at the following two intersections would result in significant impacts: 

N. Centre City Parkway/ N. Nutmeg Street

W. Country Club Lane/ N. Nutmeg Street

Therefore, mitigation measures are  required at  the  two above‐listed  intersections under Existing Plus 

Project conditions.  Because the two intersections are currently operating at a deficient LOS E during the 

peak  hours,  it  is  recommended  that  the  project  contribute  its  fair  share  toward  the  cost  of  the 

recommended mitigation measures.   

Existing Plus Cumulative With Project Conditions: Significant Impacts and Recommended Mitigation 

The findings of the Existing Plus Cumulative With Project Conditions analysis show that the addition of 

project‐related traffic to the following two intersections would result in significant impacts:  

N. Centre City Parkway/ N. Nutmeg Street

W. Country Club Lane/ N. Nutmeg Street

Therefore, mitigation measures are  required at  the  two above‐listed  intersections under Existing Plus 

Cumulative With Project conditions. 

The following improvements are recommended to mitigate the identified significant impacts under Existing 

Plus Project and Existing Plus Cumulative Plus Project conditions: 

Page 42: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  37 

Traffic Impact Analysis 

MITIGATION MEASURE 1: N. Centre City Parkway/ N. Nutmeg Street 

Contribute a fair share toward the cost of installing a traffic signal at the intersection.

Contribute  a  fair  share  toward  the  cost  of  restriping  the  southbound  approach  to  provide  a

dedicated left‐turn lane.

Contribute  a  fair  share  toward  the  cost  of  constructing  a  dedicated  right‐turn  lane  on  the

southbound approach of the intersection.

MITIGATION MEASURE 2: W. Country Club Lane/ N. Nutmeg Street 

Contribute a fair share toward the cost of installing a traffic signal at the intersection.

Contribute  a  fair  share  toward  the  cost  of  restriping  the  southbound  approach  to  provide  a

shared left‐turn/through lane and a dedicated right‐turn lane.

The recommended improvements as described above are also illustrated graphically in Exhibit 9‐1. 

Table  9‐1  summarizes  the  recommended  mitigation  measures  for  the  identified  locations  that  are 

significantly impacted by the proposed project.  

The project’s fair share contributions were calculated by dividing the project trips by the total increase in 

traffic forecast through the intersection from Existing Conditions to Existing Plus Cumulative With Project 

Conditions.   

The fair share contributions for the  identified mitigation measures are provided  in Table 9‐1.   The fair 

share  contribution  calculation  worksheets  and  HCM  worksheets  with  the  recommended  mitigation 

measures are provided in Appendix H. 

Intersection  operations  with  the  recommended mitigation measures  are  presented  in  Table  9‐2.    As 

shown in Table 9‐2, the recommended mitigation measures would improve operations at the significantly 

impacted intersections to an acceptable LOS D or better during the peak hour(s) in which the impact is 

forecast to occur.   

Page 43: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Mul�-Family Residen�al TIA

T:\Projects\Escondido\Nutmeg Mul�-Family Residen�al Project\06_Planning\Graphics\PDF

15INTERSTATE

ProjectSite

Nutmeg St

Centre City Pkwy

Iris L

n

El Norte Pkwy

Broadway

Country Club Ln

1

23

4

5

6

Exhibit 9-1Recommended Mi�ga�on Measures

LegendIntersection

Project Site

Recommended Tra�c Signal

Existing Lane Geometry#RecommendedImprovement

Page 44: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  39 

Traffic Impact Analysis 

Table 9‐1 Summary of Mitigation Measures 

Intersection Peak Hour 

Scenario Impacted 

Recommended Mitigation 

Project Responsibility  

(%) EXP  EXCP 

N. Centre City Parkway/N. Nutmeg Street

AM  X  X  Contribute a fair share toward the cost of installing a traffic signal, restriping the southbound approach to provide a dedicated left‐turn lane, and constructing a dedicated right‐turn lane on the southbound approach.   

AM: 66.7% PM: 71.6% PM  X  X 

W. Country Club Lane/ N. Nutmeg Street

AM  X  X  Contribute  a  fair  share  toward  the  cost  of  installing  a  traffic  signal  and  restriping  the southbound approach to provide a shared left‐turn/through lane and a dedicated right‐turn lane. 

AM: 15.8% PM: 15.4% PM  X 

Note: Deficient intersection operation shown in bold. (1) Seconds of delay per vehicle. 

(2) The higher peak hour fair share percentage is the recommended fair share contribution toward the cost of implementing the mitigation measures.

Table 9‐2  Intersection Operations With Mitigation 

Intersection Peak Hour 

Without Mitigation 

Recommended Mitigation 

With Project  With Mitigation Without  

Project With  Project 

Delay (1) –

LOS Delay 

(1) –LOS 

Delay (1) – LOS

Existing Plus Project Conditions 

N. Centre City Parkway/N. Nutmeg Street

AM  45.3 ‐ E  54.9 ‐ F  Contribute a fair share toward the cost of  installing a traffic signal, restriping the southbound  approach  to  provide  a  dedicated  left‐turn  lane,  and  constructing  a dedicated right‐turn lane on the southbound approach.   

14.6 ‐ B 

PM  25.4 ‐ D  32.1 ‐ D  15.8 ‐ B 

W. Country Club Lane/ N. Nutmeg Street

AM  29.9 ‐ D  34.2 ‐ D  Contribute a fair share toward the cost of installing a traffic signal and restriping the southbound approach to provide a shared left‐turn/through lane and a dedicated right‐turn lane.   

27.0 ‐ C 

PM  39.2 ‐ E  42.9 ‐ E  28.9 ‐ C 

Existing Plus Cumulative With Project Conditions 

N. Centre City Parkway/N. Nutmeg Street

AM  48.2 ‐ E  58.3 ‐ F  Contribute a fair share toward the cost of  installing a traffic signal, restriping the southbound  approach  to  provide  a  dedicated  left‐turn  lane,  and  constructing  a dedicated right‐turn lane on the southbound approach.   

14.8 ‐ B 

PM  27.1 ‐ D  34.8 ‐ D  16.0 ‐ B 

W. Country Club Lane/ N. Nutmeg Street

AM  39.1 ‐ E  43.9 ‐ E   Contribute a fair share toward the cost of installing a traffic signal and restriping the southbound approach to provide a shared left‐turn/through lane and a dedicated right‐turn lane. 

28.8 ‐ C 

PM  52.8 ‐ F  56.8 ‐ F  31.8 ‐ C (1) Seconds of delay per vehicle. 

Page 45: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  40 

Traffic Impact Analysis 

10 SUMMARY AND CONCLUSIONS 

This  traffic  impact  analysis  evaluates  the  traffic  conditions  associated  with  the  proposed  “Nutmeg 

Residential” multi‐family residential project (herein referred to as “the project”) located on a vacant site 

along the east side of I‐15, east of N. Centre City Parkway and north and south of N. Nutmeg Street in the 

City of Escondido.   The project proposes a Multi‐Family Site Development Plan to construct 163 multi‐

family residential units on approximately 6.8 acres. 

The  site  to  the  north  of  Nutmeg  Street  will  be  developed  with  45  Townhome  residential  units.  The 

townhomes would be developed as approximately 11 2‐bedroom/2‐bath units of 950 square feet and 34 

3‐bedroom/2‐bath units of 1,350 square feet. The units would be 3‐story with a 2‐car garage. The site to 

the south of Nutmeg Street would be developed with 118 Apartment residential units. The apartments 

would  be  developed  as  approximately  47  1‐bedroom/1‐bath  units  of  750  square  feet  and  71  2‐

bedroom/2‐bath units of 950 square feet. 

Project access will be provided from a total of three driveways.  Two driveways will be provided for the 

site on the north side of Nutmeg Street, and one driveway will be provided for the site on the south side 

of Nutmeg Street.  

The project  is  forecast  to generate approximately 1,068 average weekday trips,  including 85 AM peak 

hour trips and 100 PM peak hour  trips.   A comparison  in  trip generation was performed between the 

currently  proposed  project  and  the  previously  approved  commercial  uses,  which  revealed  that  the 

proposed project is forecast to generate 968 fewer daily trips, 200 fewer AM peak hour trips, and 165 

fewer PM peak hour trips than the previously approved uses.  

The results of the existing conditions analysis showed that the study intersections currently operate at 

acceptable LOS except for the following intersections that currently operate at a deficient LOS E or F during 

the peak hours: 

N. Centre City Parkway/ N. Nutmeg Street (AM: LOS E);

W. Country Club Lane/ N. Nutmeg Street (PM: LOS E); and

N. Centre City Parkway/ W. El Norte Parkway (AM: LOS E, PM: LOS E).

The existing conditions roadway segment analysis results showed that all study roadway segments are 

currently operating at acceptable LOS based on daily traffic volumes and roadway capacity. 

Under  Existing  Plus  Project  conditions,  the  study  intersections  are  forecast  to  continue  operating  at 

acceptable LOS except for the following intersections:  

N. Centre City Parkway/ N. Nutmeg Street (AM: LOS F);

W. Country Club Lane/ N. Nutmeg Street (PM: LOS E); and

N. Centre City Parkway/ W. El Norte Parkway (AM: LOS E, PM: LOS E).

Page 46: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  41 

Traffic Impact Analysis 

The forecast  increase in delay associated with project‐related traffic to the following two intersections 

would exceed the significance threshold of 2.0 seconds: 

N. Centre City Parkway/ N. Nutmeg Street (AM: LOS F); and

W. Country Club Lane/ N. Nutmeg Street (PM: LOS E).

 Therefore, the project would not result in significant impacts at the two above‐listed intersections under 

Existing Plus Project conditions and mitigation measures are not required.   

The results of the roadway segment analysis under Existing Plus Project conditions showed that consistent 

with existing conditions, all study roadway segments are forecast to continue operating at acceptable LOS. 

To determine the Existing Plus Cumulative conditions  in the project study area, forecast project traffic 

associated with City of Escondido approved or pending projects was added to existing traffic volumes. The 

cumulative projects within the City of Escondido are forecast to generate approximately 10,312 trips per 

day, which includes approximately 978 AM peak hour trips and approximately 1,010 PM peak hour trips. 

The  results  of  the  Existing  Plus  Cumulative  conditions  analysis  showed  that  the  following  five  study 

intersections are forecast to operate at a deficient LOS E or F during the peak hours both without and with 

the proposed project: 

N. Centre City Parkway/ N. Nutmeg Street (AM: LOS F);

W. Country Club Lane/ N. Nutmeg Street (PM: LOS E); and

N. Centre City Parkway/ W. El Norte Parkway (AM: LOS E, PM: LOS E).

The forecast  increase in delay associated with project‐related traffic to the following two intersections 

would exceed the significance threshold of 2.0 seconds: 

N. Centre City Parkway/ N. Nutmeg Street (AM: LOS F); and

W. Country Club Lane/ N. Nutmeg Street (PM: LOS E).

Therefore,  the project would  result  in  significant  impacts  at  the  two  above‐listed  intersections  under 

Existing Plus Cumulative With Project conditions, and mitigation measures are required.   

The results of the roadway segment analysis under Existing Plus Cumulative conditions showed that the 

study roadway segments are forecast to operate at acceptable LOS both without and with the proposed 

project.   

The signal warrant analysis results showed that at the intersection of N. Centre City Parkway/ N. Nutmeg 

Street, either Part A or Part B (or both) were satisfied under the following analysis scenarios: 

Existing Conditions (PM: Part B)

Existing Plus Project Conditions (AM/PM: Part B)

Existing Plus Cumulative Without Project Conditions (PM: Part B)

Existing Plus Cumulative With Project Conditions (AM/PM: Part B)

Page 47: Nutmeg Multi‐Family Residential Project€¦ · The project will take access from Nutmeg Street from a total of three project driveways. Two driveways will be provided for the site

Nutmeg Multi‐Family Residential  42 

Traffic Impact Analysis 

The signal warrant analysis results also show that at the intersection of W. Country Club Lane/ N. Nutmeg 

Street, either Part A or Part B (or both) were satisfied under the following analysis scenarios: 

Existing Conditions (AM: Part B; PM: Parts A and B)

Existing Plus Project Conditions (AM: Part B; PM: Parts A and B)

Existing Plus Cumulative Without Project Conditions (AM: Part B; PM: Parts A and B)

Existing Plus Cumulative With Project Conditions (AM/PM: Part A; AM/PM: Part B)

The results of the site access evaluation showed that no operational impacts are anticipated at the project 

driveway intersections.  Due to the potential for queued vehicles on the eastbound approach of the Centre 

City Parkway/Nutmeg Street intersection to block left‐turn access at Driveway 3, it is recommended that 

access to Driveway 3 be limited to right‐turn in only.  The right‐turn only restriction is also recommended 

due to the close proximity of Driveway 3 to Centre City Parkway and the relatively high number of vehicles 

on southbound Centre City Parkway turning right onto westbound Nutmeg Street during the AM peak 

hour.   

To mitigate the project’s significant impacts under Existing Plus Project and Existing Plus Cumulative With 

Project conditions, the following mitigation measures are recommended:  

MITIGATION MEASURE 1: N. Centre City Parkway/ N. Nutmeg Street 

Contribute a fair share toward the cost of installing a traffic signal at the intersection.

Contribute  a  fair  share  toward  the  cost  of  restriping  the  southbound  approach  to  provide  a

dedicated left‐turn lane.

Contribute  a  fair  share  toward  the  cost  of  constructing  a  dedicated  right‐turn  lane  on  the

southbound approach of the intersection.

MITIGATION MEASURE 2: W. Country Club Lane/ N. Nutmeg Street 

Contribute a fair share toward the cost of installing a traffic signal at the intersection.

Contribute  a  fair  share  toward  the  cost  of  restriping  the  southbound  approach  to  provide  a

shared left‐turn/through lane and a dedicated right‐turn lane.