2020‐10‐06 1 NVSD Capital Projects Update October 6, 2020 MAJOR CAPITAL FUNDING PROGRAMS PROJECT DESCRIPTION PROJECT LEAD PROJECT SUPPORT Seismic Mitigation Program Argyle Secondary Seismic Replacement Handsworth Secondary Seismic Replacement Mountainside Secondary Seismic Upgrade Mark Thomson Mark Thomson Tanja Kalamar James Bell James Bell James Bell School Enhancement Program Mountainside Secondary Building Envelope – Exterior Wall System Tanja Kalamar James Bell New School Program Cloverley Elementary – Provide Draft Concept Plan 60K/475 Capacity School Tanja Kalamar James Bell MINOR CAPITAL PROJECTS Building Envelope Program Dorothy Lynas Elementary Building Envelope – Upgrades James Bell Jeff Jackson Annual Facilities Grant 2020 Major Highlights Capilano / Norgate CNCP Mike Chapman Jeff Jackson Luke Smeaton Playground & Equipment Program Westview Elementary Mike Chapman Jeff Jackson Capital Project Team

Upload: others

Post on 17-Oct-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

1

NVSD Capital Projects UpdateOctober 6, 2020

MAJOR CAPITALFUNDING PROGRAMS

PROJECT DESCRIPTION PROJECT LEAD

PROJECT SUPPORT

Seismic Mitigation Program

Argyle Secondary Seismic Replacement Handsworth Secondary Seismic Replacement Mountainside Secondary Seismic Upgrade

Mark ThomsonMark ThomsonTanja Kalamar

James BellJames BellJames Bell

School EnhancementProgram

Mountainside SecondaryBuilding Envelope – Exterior Wall System

Tanja Kalamar James Bell

New School Program Cloverley Elementary – Provide DraftConcept Plan 60K/475 Capacity School

Tanja Kalamar James Bell

MINOR CAPITAL PROJECTS

Building Envelope Program

Dorothy Lynas ElementaryBuilding Envelope – Upgrades

James Bell Jeff Jackson

Annual Facilities Grant 2020 Major Highlights Capilano / Norgate CNCP

Mike Chapman Jeff JacksonLuke Smeaton

Playground & Equipment Program

Westview Elementary Mike Chapman Jeff Jackson

Capital Project Team

Page 2: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

2

Argyle SecondarySeismic Replacement

Argyle Secondary

PROJECT SCHEDULEPhase 1 – New School

Interior fit out & commissions - September/October 2020 Occupancy, furnishings & equipment - November/December 2020 Gym completion & Phase 1 closeout - November/December 2020

Phase 2 – Demolition Site property (tree barriers/sediment control) – December 2020 Hazardous materials abatement of existing school - January 2021 Demolition of existing school – March 2021

Phase 3 – Site Improvements Commence construction of new field Commence daylighting of Kilmer Creek

Page 3: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

3

Argyle Secondary – Project Phases

Phase 2 & 3 Phase 1

Argyle Secondary - Interior Layout

Page 4: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

4

Argyle Secondary - Interior Layout

Argyle – Learning Community

Page 5: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

5

Argyle Secondary – Features & Benefits

HIGHLIGHTS 1,300 student capacity 21st Century learning environment LEED® Gold equivalent Natural daylighting - lines of site to the natural environment LED dimmable lighting systems COVID Considerations Merv 13 filtration Displacement ventilation systems Touchless faucets S-Turn washroom entry’s Outdoor learning spaces Learning communities have easy access to exterior & natural

environments Rooftop patio

Argyle Secondary

Page 6: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

6

Argyle Secondary

Argyle Secondary

Page 7: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

7

Argyle Secondary

Argyle Secondary

Page 8: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

8

Argyle Secondary

Argyle Secondary

Page 9: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

9

Argyle Secondary

Argyle Secondary

Page 10: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

10

Argyle Secondary

Handsworth SecondarySeismic Replacement

Page 11: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

11

Handsworth Secondary

PROJECT SCHEDULEPhase 1 - New School Commence construction of new school – February 2020 Substantial completion of new school – July 2022 Occupancy and move-in to new school – August 2022

Phase 2 - Demolition Commence demolition of existing school – September 2022 Completion of demolition of existing school – March 2023

Phase 3 – Site Improvements Commence construction of new field – April 2023 Riparian improvements at ravine – May 2023 Project final completion – July 2023

Handsworth Secondary

Phase 1

Phase 2

Page 12: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

12

Handsworth Secondary –Interior Layout

Learning Community

Page 13: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

13

Handsworth Secondary – Features & Benefits

HIGHLIGHTS 1,400 student capacity 21st Century learning environment LEED® Gold equivalent Natural daylighting - lines of site to the natural environment LED Dimmable lighting systems COVID Considerations Merv 13 filtration Displacement ventilation systems Touchless faucets S-Turn washroom entry’s

Outdoor learning spaces Learning communities have easy access to exterior & natural

environments

Handsworth Secondary

Page 14: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

14

Handsworth Secondary

Handsworth Secondary

Page 15: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

15

Handsworth Secondary

Mountainside SecondarySeismic Upgrade

Page 16: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

16

Project Funding Sources

Project is funded by the Ministry of Education Major & Minor Capital Funding Programs

Seismic Mitigation Program Seismic Upgrade

School Enhancement Program Windows and Building Envelope Replacement

Annual Facility Grant Domestic Water Piping Renewal

Project Objective & Design Principles

PROJECT OBJECTIVE

Project objective is to seismically upgrade and strengthen the building.

Seismic upgrade design is to the general intent of the Seismic Retrofit Guidelines 3rd Edition endorsed by the Engineers and Geoscientists BC and the Ministry of Education.

Page 17: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

17

Project Execution & Phasing Plan

Key FactorsSafety of the occupants during constructionConstructing within and around occupied buildingSwing space phased construction / partial occupanciesConstruction planning, material, staging, parking and accessProject location and access to vendorsCovid-19 measures to ensure safety within construction areas and

compliance within occupied school spacesDay Care

Mountainside SecondaryPROJECT SCHEDULE

Block 1A – November 2020 Phase 1 (East End of the Block) – Occupied Phase 2 (West End of the Block) – 60 % Complete

Block 1B – March 2021 Exterior Demolition – 100% complete Exterior Seismic Upgrade – 100% Complete Overall Completion to Date – 10% Complete

Block 1B –Completion September 2021

Block 2 Gymnasium – June 2021 Crawlspace – 100% Complete Cladding Renewal – 80% Complete Overall Completion to Date – 40% Complete

Block 3 Admin – August 2021 Lower Floor Demolition – 70% Complete Overall Completion to Date – 10% Complete

Project Substantial Completion - September 2021

Page 18: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

18

Project Blocks and Phases

Mountainside Secondary – Features & Benefits

HIGHLIGHTS

New envelope (insulation, cladding, operable windows) New dimmable LED lighting system New audio visual & PA system New domestic plumbing with increased handwashing capacity & touchless

faucets New electrical wiring and distribution panels Renewed architectural finishes Integrated classrooms & breakout spaces Outdoor terraced seating area New gym washroom & change rooms Improved washroom layouts ( gender neutral / accessible spaces) Improved site drainage Improved ventilation distribution and perimeter heating Touchless door openers at wheelchair accessible entry’s

Page 19: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

19

Progress Photos Block 1A – Academic

Progress Photos Block 1A – Academic

Page 20: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

20

Progress Photos Block 1A – Academic

Progress Photos Block 1A – Academic

Page 21: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

21

Progress Photos Block 1A – Academic

Progress Photos Block 1A – Academic Interior

Page 22: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

22

Progress Photos Block 1A – Academic Interior

Progress Photos Block 1A – Academic Interior

Page 23: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

23

Progress Photos Block 1A – Academic Interior

Progress Photos Block 1A – Academic Interior

Page 24: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

24

Progress Photos Block 1A – Academic Interior

Progress Photos Block 1B – Academic

Page 25: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

25

Progress Photos Block 1B – Academic

Progress Photos Block 2 - Gymnasium

Page 26: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

26

Progress Photos Block 2 - Gymnasium

Progress Photos Block 2 - Gymnasium

Page 27: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

27

Progress Photos Block 3 – Administration

Progress Photos Block 3 – Administration

Page 28: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

28

Progress Photos Block 3 – Administration

Progress Photos Block 3 – Administration

Page 29: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

29

Progress Photos Block 3 – Administration

Cloverley Elementary Concept Plan

Page 30: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

30

Cloverley Elementary

History of Cloverley Elementary School

1961 to 1982 – Cloverley Elementary School was a public school 1982 to 2010 – building was leased to a series of different organizations 2010 to 2014 – building was temporarily returned to service during seismic

upgrade and renovation of Ridgeway Elementary School and Queen Mary Elementary School

After 2014 – the school is vacant and based on facility condition assessment done in 2017 considered beyond useful life

2020 – 5-Year Capital Plan submission identified need for 60K/475E school on the Cloverley site

Ministry of Education requested that the NVSD proceed with preparation of Concept Plan by December 1, 2020

Approval Process and Potential Schedule

Approval Process and Potential Schedule

Long Range Facility Plan - Complete Concept Plan - December 1, 2020 Project Definition Report* - Summer 2021 Capital Project Funding Agreement* Certificate of Approval* Retain Consulting Team Project Design and Permitting Project Tendering Construction

* Requires Ministry of Education approvals prior to proceeding to the next phase.

Page 31: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

31

Cloverley Elementary

Concept Plan Due December 2020

Consultants Consultant - DA Architecture Geotechnical and Environmental – Thurber Engineering Ltd. HazMat Survey – Kinetic OHS Services Ltd. Quantity Surveyor – James Bush & Associates Ltd.

Cloverley Elementary

Page 32: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

32

Cloverley Elementary

Cloverley Elementary

Page 33: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

33

Cloverley Elementary

Cloverley Elementary

Page 34: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

34

Cloverley Elementary

Cloverley Elementary

Page 35: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

35

Cloverley Elementary

Dorothy Lynas Elementary Building Envelope Project

Page 36: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

36

Dorothy Lynas Elementary

Dorothy Lynas Elementary

Project ScopeProactive renewal of aging building envelope details. The project largely focuses on the exterior perimeter face of the building and select fire walls exposed to weather elements.

Highlights at Completion: New concealed gutters & associated wood framing New metal panel fascia New windows (gym, multipurpose room) New “rain-screen” envelope on exposed stucco clad walls Improved building envelope lifecycle Reduced maintenance costs

Page 37: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

37

Dorothy Lynas Elementary

PROJECT SCHEDULENorth

Phase 1– September 2020 Administration / Main Entrance

Phase 2– October & November 2020 Kindergarten / Gymnasium Classroom Blocks

Completion: November 20, 2020

Phase 1

Phase 2

Dorothy Lynas

Dorothy Lynas Elementary

Page 38: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

38

Dorothy Lynas Elementary

Dorothy Lynas Elementary

Page 39: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

39

Dorothy Lynas Elementary

ANNUAL FACILITIES GRANT

Page 40: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

40

AFG Projects Overview

Purpose of the Annual Facilities Grant Increase the economic life of facility assets through proactive

lifecycle replacement of base building components.

Prevent premature deterioration of school assets.

AFG Project Categories

Roof Replacements

Site Servicing Site Upgrades Loss Prevention Projects Asbestos Abatement Disabled Access Electrical System Facility Upgrades Functional Improvements Health and Safety Upgrades Mechanical System Upgrades

Page 41: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

41

AFG 2020/21 Budget

Budget AllocationsAsbestos Abatement  $18K

Disabled Access $44K

Electrical Upgrade $6K

Facility Upgrade $812K

Functional Improvement $89K

Health & Safety Upgrade $202K

Mechanical System Upgrade $839K

Roof Replacement $427K

Site Servicing $120K

Site Upgrades $274K

$2.831M

AFG – Asbestos Abatement

Braemar

Upper Lynn

Cleveland

Larson

Page 42: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

42

AFG – Disabled Access

Lynnmour – new accessible washroom

AFG – Disabled Access Canyon Heights – exterior accessibility upgrades

Page 43: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

43

AFG – Facility Upgrades

Exterior Envelope Renewal Floor Renewals/Interior Finishing

AFG – Facility Upgrades

Exterior Painting

Page 44: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

44

AFG – Functional Improvements

Classroom & administration office renovations

AFG – Health & Safety Upgrades

Fire alarm upgrades (Boundary, Larson, Lynnmour, Lucas)

Site tree inventories

Corridor handwashing sinks

Sutherland bleacher guardrails

Page 45: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

45

AFG – Mechanical Systems

Plumbing system renewals

HVAC system upgrades and renewals

Norgate boiler and heat pumps Larson portable furnaces and classroom zone valves Windsor and Sutherland server room AC units

AFG – Roofing Replacements

Cheakamus - Administration building Boundary - Sections 9 & 10 Brooksbank - Section 6A Sherwood Park - Section 2B Lucas Centre - Lunch Room & Carpentry Seymour Heights - Portable 16

Page 46: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

46

AFG – Roofing Replacements

AFG – Roofing Replacements

Page 47: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

47

AFG – Site Servicing

Lynnmour drainage upgrade – design complete, ready for tendering

AFG – Site Upgrades

Playgrounds - surfacing, drainage, swing mats

Field top dressing

Asphalt and walkway repairs

Retaining walls

Fencing

Page 48: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

48

AFG – Site Upgrades

Capilano Boiler and HVAC

Achieved 25% greenhouse gas reduction ≈ 16 tCO2e per year

Capilano Elementary Annual Emissions

Page 49: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

49

Norgate Heating Plant Upgrade

Boiler system renewal Low-carbon electrification pilot Safety and comfort improvements

Norgate Heating Plant Upgrade

Targeting 50% greenhouse gas reduction ≈ 35 tCO2e per year ≈ 7 passenger vehicles off the road for a year

Target

Norgate Elementary Annual Emissions

Page 50: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

50

Norgate Heating Plant Upgrade

New boilers and piping New supplementary electric heat pumps

New hydronic coils in rooftop units

Norgate Heating Plant Upgrade

Roof access improvements for safety and convenience

Additional zone control for occupant comfort

Page 51: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

51

Playground Equipment Program (PEP)

Third year of annual PEP grant program.

Provides specific funding to procure new playground equipment that is inclusive and universally accessible in design.

Universally designed play spaces include adventure-style playground equipment that is designed to meet a range of elementary aged students’ needs regardless of ability.

Playground Equipment Program (PEP)

2018/19 Norgate Elementary $105k PEP Grant

Page 52: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

52

Playground Equipment Program (PEP)

2019/20 Larson Elementary $105k PEP Grant

Playground Equipment Program (PEP)

2020/21 Westview Elementary $125k PEP Grant RFP Closing date October 23, 2020 RFP will be used to seek an additional $75k CNV Grant

Page 53: NVSD Capital Projects Update October 6, 2020 · 2020. 10. 8. · Rooftop patio Argyle Secondary. 2020‐10‐06 6 Argyle Secondary Argyle Secondary. 2020‐10‐06 7 Argyle Secondary

2020‐10‐06

53

Thank You