Diesel power modules 24 MW in less than 20 days Background Located on the southeast coast of the Arab Peninsula, the Sultanate of Oman has nominal rainfall and temperatures exceeding 50°C (122°F) during the summer. The hottest months are typically from May to September, when heavy demand on the country’s power grid can cause intermittent power outages, leading to disruptive economic and social conditions. The Oman Power and Water Procurement Company contracted for seasonal back-up power solutions to support the national grid during the peak demand period. Solution APR Energy designed, installed and commissioned a fast-track, turnkey power plant to provide 24MW of peak-demand backup power via MEDCO, one of the Sultanate’s electricity distribution companies. Using our proprietary modular system of connecting generators and transformers, we were able to deploy and commission the site in less than 20 days from arrival of the equipment to the site. Local specialized contractors were used to fabricate the fuel supply system and build the interconnection infrastructure. Outcome As a standby supplement to the existing power grid, our turnkey diesel power solution provided three months of reliable backup capacity during the peak demand season. Using our proprietary modular system, we were able to fully dismantle and vacate the site in only eight days upon completion of the contract. Oman Case Study Peak Shaving Contact Information AMERICAS Jacksonville, USA +1 904 223 2278 Rio de Janeiro, Brazil +55 21 3957 9333 ASIA PACIFIC Singapore +65 6589 9140 EUROPE, MIDDLE EAST & AFRICA Dubai, UAE +971 800 2773 8224 e-mail: [email protected] www.aprenergy.com Twitter: @aprenergyplc | Linkedin: linkedin.com/company/apr-energy | Facebook: facebook.com/aprenergy | YouTube: youtube.com/aprenergy At a glance • FAST-TRACK INSTALLATION IN LESS THAN 20 DAYS • 24MW OF PEAK-DEMAND POWER • DECOMMISSIONING IN 8 DAYS Challenges • MODIFICATION OF EXISTING EQUIPMENT USED FOR THE ELECTRICAL INTERCONNECTION POINTS • SPECIALIZED FUEL AND ELECTRICITY METERING EQUIPMENT FOR COMPLETE OPERATIONAL TRANSPARENCY • MAXIMUM GENERATION AVAILABILITY REQUIRED FOR DAYTIME, EVENING PEAKS

Upload: duongtram

Post on 24-Mar-2018

224 views

Category:

Documents


3 download

TRANSCRIPT

Diesel power modules 24MW

in less than 20 days

BackgroundLocated on the southeast coast of the Arab Peninsula, the Sultanate of Oman has nominal rainfall and temperatures exceeding 50°C (122°F) during the summer. The hottest months are typically from May to September, when heavy demand on the country’s power grid can cause intermittent power outages, leading to disruptive economic and social conditions. The Oman Power and Water Procurement Company contracted for seasonal back-up power solutions to support the national grid during the peak demand period.

SolutionAPR Energy designed, installed and commissioned a fast-track, turnkey power plant to provide 24MW of peak-demand backup power via MEDCO, one of the Sultanate’s electricity distribution companies. Using our proprietary modular system of connecting generators and transformers, we were able to deploy and commission the site in less than 20 days from arrival of the equipment to the site. Local specialized contractors were used to fabricate the fuel supply system and build the interconnection infrastructure.

OutcomeAs a standby supplement to the existing power grid, our turnkey diesel power solution provided three months of reliable backup capacity during the peak demand season. Using our proprietary modular system, we were able to fully dismantle and vacate the site in only eight days upon completion of the contract.

Oman

Case StudyPeak Shaving

Contact Information

AMERICAS

Jacksonville, USA +1 904 223 2278Rio de Janeiro, Brazil +55 21 3957 9333

ASIA PACIFICSingapore +65 6589 9140

EUROPE, MIDDLE EAST & AFRICADubai, UAE +971 800 2773 8224

e-mail: [email protected] www.aprenergy.com

Twitter: @aprenergyplc | Linkedin: linkedin.com/company/apr-energy | Facebook: facebook.com/aprenergy | YouTube: youtube.com/aprenergy

At a glance

• FAST-TRACK INSTALLATION IN LESS THAN 20 DAYS

• 24MW OF PEAK-DEMAND POWER

• DECOMMISSIONING IN 8 DAYS

Challenges• MODIFICATION OF EXISTING EQUIPMENT USED FOR THE ELECTRICAL INTERCONNECTION POINTS

• SPECIALIZED FUEL AND ELECTRICITY METERING EQUIPMENT FOR COMPLETE OPERATIONAL TRANSPARENCY

• MAXIMUM GENERATION AVAILABILITY REQUIRED FOR DAYTIME, EVENING PEAKS