openbim - buildingsmart · bim is a process of generating and managing building data during its...

35
Óskar Valdimarsson Iceland Sustainability by openBIM Use of openBIM on the new Iceland National Hospital to achieve strict sustainability requirements openBIM FOR A NORDIC SUSTAINABLE BUILDING INDUSTRY JANUARY 31, 2013

Upload: others

Post on 04-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

Óskar Valdimarsson Iceland

Sustainability by openBIM Use of openBIM on the new Iceland National Hospital to achieve strict sustainability requirements

openBIM FOR A NORDIC SUSTAINABLE BUILDING INDUSTRY

JANUARY 31, 2013

Page 2: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

2

!  Originally the architect and the engineer were the same person. Therefore co-ordination was easy.

!  When more complex building projects were introduced, specialization developed within the design sector.

!  This specialization meant a separation of disciplines, which called for a change in communication.

!  The separation started approx. 500 years ago.

The development of design

Page 3: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

3

!  The flow of information and knowledge between disciplines was inadequate and pushed for new approaches.

!  A need for increased integration became obvious, both in the technical and organizational fields.

!  The concept of “design teams”, “project teams” or “project offices” was introduced in an attempt to solve this problem.

The development of design

Page 4: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

4

The development of design

separation of disciplines

separation of disciplines increased integration

Page 5: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

5

!  With the introduction of “The Cloud” physical project offices might be replaced by “virtual site offices”.

!  Emphasis on sustainability and life cycle costing also pushed for increased collaboration, especially in the early stages of design.

!  A new approach was needed. !  Building Information Modeling (BIM) and Integrated

Planning and Design (ID) were introduced…..

The development of design

Page 6: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

Building Information Modeling - BIM: ! BIM is a process of generating and managing building

data during its complete lifecycle, from conceptual design through maintenance and operation of the building.

! The process is based on the involvement of all stakeholders from the earliest stages where decisions are made with all the information shared – up front.

! The product is a three-dimensional virtual model that contains detailed information about the layout of the building, its components and materials and their main characteristics.

6

Page 7: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

7

Technology

Culture Business BIM

Page 8: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

Integrated planning and design - ID: !  ID is a collaborative approach to building design

marked by the qualities of early participation by all team members.

! ID involves all stakeholders from the earliest stages where decisions are made with all the information shared – up front.

! ID stems from the environmental arena in its pursuit to create high-performing facilities, streamlining and going lean.

8

Page 9: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

9

Environment

Culture Business ID

Page 10: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

Environment

Culture Business ID

Technology

Culture Business BIM

+

=

Page 11: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

Technology & Environment

Culture Business

BIM & ID

Page 12: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

12

!  The life cycle costing approach calls for decisions at a very early stage in the design process.

!  Energy calculations, daylight considerations and other environmental issues also call for analysis to be carried out at an early stage in the design process.

!  Before the introduction of BIM these demands were difficult to meet at an early stage in the design process, since there were no “common” models.

!  For different disciplines to be able to transfer information between different software and receive feedback, openBIM with the IFC standard is a must.

BIM and ID – Excellent partners

Page 13: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

13

Page 14: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

14

Iceland National Hospital

65.000 m2 new construction

Page 15: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

15

Iceland National Hospital

Page 16: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

16

Iceland National Hospital

Page 17: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

17

!  The design team was composed of several smaller architectural firms and one larger engineering firm.

!  The team used many different software packages in their design (however, same within each building): !  MicroStation from Bentley !  ArchiCAD from Graphisoft !  Wectorworks from Nemetschek !  TEKLA !  Revit Structural and MEP from Autodesk !  …and some more

The Design Team SPITAL

Page 18: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

18

Page 19: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

19

!  The contract was for a 20% design – which is now completed.

!  All design was to be carried out in BIM from the very start – using BIM requirements from either Statsbygg or Senaatti. SPITAL chose Statsbygg´s requirements.

!  All BIM model delivery to the owner was carried out using the IFC format.

!  The owner performed model checking with Solibri, using the IFC files.

!  Contractual specifications were based on rules and forms published by the Danish bips.

The Design Contract

Page 20: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

20

Treatment center – First floor

Page 21: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

21

!  The owner made a decision – before the design work started – to seek a BREEAM environmental certification.

!  The goal is quite ambitious – the score “Excellent” which means 4 stars out of 5 possible (70% score).

!  BREEAM has not been adopted to the Icelandic conditions, so we are using BREEAM International.

!  Each one of the five buildings will have a separate environmental certificate.

Environmental Certification

Page 22: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

22

Model for space analysis

Page 23: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

23

!  At the completion of the 20% design, a BREEAM pre-score table was delivered to the owner, indicating that the “Excellent” score can be achieved.

!  Each line item in the prescribed BREEAM requirements - for the score of Excellent -has been studied, some with the aid of the BIM models.

!  The BREEAM requirements have formed the basis for the general requirements set forth in the project specifications for the contractor/design team.

The BREEAM pre-score

Page 24: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

24

Daylight requirements

Page 25: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

25

Model used for trafic studies

Page 26: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

26

The BREEAM pre-score

77 %

14 %

9 %

Health and wellbeing

Required

Optional

N/A 94 %

6 % 0 %

Management (environmental)

Required

Optional

N/A

Page 27: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

27

The BREEAM pre-score

59 %

41 %

0 %

Energy

Required

Optional

N/A 62 %

38 %

0 %

Transport

Required

Optional

N/A

Page 28: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

28

The BREEAM pre-score

43 %

43 %

14 %

Water

Required

Optional

N/A

22 %

64 %

14 %

Materials

Required

Optional

N/A

Page 29: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

29

The BREEAM pre-score

86 %

0 % 14 %

Waste

Required

Optional

N/A 60 %

30 %

10 %

Land use and ecology

Required

Optional

N/A

Page 30: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

30

The BREEAM pre-score

100 %

0 % 0 %

Pollution

Required

Optional

N/A

0 %

100 %

0 %

Innovation

Required

Optional

N/A

Page 31: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

31

The BREEAM pre-score

62 %

33 %

5 %

Total requirements

Required

Optional

N/A

Page 32: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

32

!  A score of Excellent (4 stars out of 5) in the BREEAM certification system calls for at least 70% achievement.

!  The pre-score defines 62% as required points and 33% as optional points. The contractor and his design team can select the “missing points” from the different categories. It is their choice.

!  This method leans more towards performance specifications than prescriptive specifications.

The BREEAM final score

Page 33: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

33

!  It is vital – for the development of the openBIM technology – to involve the contractors. Their feed-back is extremely important.

!  Before 2003 GCCA delivered printed drawings as a part of every tender document package. Since then we have only delivered CDs containing all documents – including drawings in the pdf format.

!  From now on we will stop delivering drawings in a pdf format, but instead we will deliver them in “richer formats”, where the contractors can retrieve more info from them – using standard free viewers downloadable from the Internet.

The Construction Site

Page 34: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

34

!  Our first project to go this route is the Center for Icelandic Studies – a 6.100 m2 building now in the tender stage.

!  All “drawings” are delivered in a “rich format”, derived from the BIM model.

!  Free courses are offered to the bidders, where they are taught how to use this new technology.

!  When a contract has been signed, GCCA will assist the contractor in taking his first steps in using these “rich drawings” for his benefit during the construction phase.

The Construction Site

Page 35: openBIM - buildingSMART · BIM is a process of generating and managing building data during its complete lifecycle, ... Revit Structural and MEP from Autodesk ! …and some more The

35

!  The design team issues – in the tender documents – the most useful or relevant “rich drawings”.

!  During the construction phase the contractor can ask for additional sections or views, all in this “rich format”.

!  The BIM model itself will not be delivered to the contractor – at least not yet – since the knowledge how to make use of it is very limited.

!  The BIM model will be updated to “as built” by the design team.

End.

The Construction Site