OptiX RTN 300 Installation and Link Commissioning
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page3
Objectives
Upon completion of this course, you will be able to: Describe the relation among the different parts of RTN
300
Know the hardware installation of RTN 300
Perform the Radio Link commissioning
Know the installation key point
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page4
Contents
1. OptiX RTN 300 System Hardware Structure
2. Installation Preparation
3. Antenna Installation
4. RTN 300/Hybrid Coupler and Related Cable
Installation
5. PI and Related Cable Installation
6. Loading NE data and installation checking
7. Link Commissioning
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page5
System Hardware Structure There are many kinds of the RTN 300
installation scenario. Select an appropriate
installation scenario before installing the RTN
300.
Direct mount, power over Ethernet
Direct mount, DC power supply
Split mount, power over Ethernet
Split mount, DC power supply
1+1 Protection (RTN 900 Required)
1+1 Protection (Optical Splitter Required)
Networked with RTN 900
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page6
Direct mount, power over Ethernet
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page7
Direct mount, DC power supply
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page8
Split mount, power over Ethernet
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page9
Split mount, DC power supply
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page10
1+1 Protection (RTN 900 Required)
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page11
1+1 Protection (Optical Splitter
Required)
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page12
Networked with RTN 900
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page13
Antennas
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page14
RTN 300
Electrostatic discharge
Radiation
Warning labels
High temperature
Ground screw
Name plate
GE port Combo portP&E port
DC power port
RSSI test portUSB portNMS port Antenna port
Position pin
Front view
Front view of port
Rear view
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page15
Hybrid Coupler
Antenna port
Standby tributary port
Main tributary port
Pin slot
Conversion bracket
Main fixture
Standby fixture
Top viewSide view
Front view
Split mounting bracket
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page16
Cables
Base of grounding clip
OT terminal
PGND cableFlexible waveguide
Positive
Negative
Cable connector
Cable sheath
Brown: 0 V power ground cable
Blue: -48 V power ground cable
DC power cable
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page17
Cables (Cont.)
Connector
Main label
View A
P&E label
View B View
A
Connector
Main label
MGMT labelP&E label
View B
View C
RJ45 connector RJ45
connector
View A
SFP20 male connector
XPIC cable
12-core P&E cable
8-core P&E cable
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page18
Cables (Cont.)
View B
View B
RJ45 connector
Multimeter port
Main label
RSSI port cable
Waterproof socket for outdoor fibers
LC/PC connector
Outdoor cable
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page19
PI(Indoor Power Injector)
Mounting ear for installation in cabinets or on wall
Ground screw
Mounting ears
Mounting ear for installation in cabinets or on wall
Front view of PI panel
Side view
PI auxiliary mounting bracket
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page20
PI(Outdoor Power Injector)Front view (with the cover
closed) Front view (with the cover opened)
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page21
Contents
1. OptiX RTN 300 System Hardware Structure
2. Installation Preparation
3. Antenna Installation
4. RTN 300/Hybrid Coupler and Related Cable
Installation
5. PI and Related Cable Installation
6. Loading NE data and installation checking
7. Link Commissioning
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page22
Preparation
Document
XX Network Plan
XX Engineering Design
XX Equipment Room Layout Plan
OptiX RTN 300 Radio Transmission System
Installation Guide
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page23
Preparation (Cont.)
Tools Category Description
Common
tools
Measuring
50-m tape, 5-m measuring tape, 400-mm level meter, marker
Drilling Percussion drill, accessory drill bits, vacuum cleaner
Fixing Cross tip screwdriver, flat-tip screwdriver, adjustable wrench (10', 12', 17', 19', 24', one for each), socket wrench
Bench Sharp-nose pliers, electrical knife
Hoisting 100-m hoisting rope, 100-m stretching rope, pulley
Auxiliary Brush, tweezers, paper knife, hand bellows, electric iron, tin wire, crowbar
Special tools ESD gloves, wire punch tool, telescope, socket-head wrench
Instruments Multi-meter, GPS, north-stabilized indicator
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page24
Preparation (Cont.)
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page25
Preparation (Cont.)
Checking Installation Conditions
Installation Conditions of the PI
Installation Conditions of the Antenna/RTN 300/Hybrid
coupler
Lightning-Proof and Grounding System
Power System
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page26
Contents
1. OptiX RTN 300 System Hardware Structure
2. Installation Preparation
3. Antenna Installation
4. RTN 300/Hybrid Coupler and Related Cable
Installation
5. PI and Related Cable Installation
6. Loading NE data and installation checking
7. Link Commissioning
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page27
Installing the antenna procedure
Change the polarization direction of antenna
Install the anti-fall bracket
Hoist the antenna
Install the antenna
Align the antenna
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved.
Pole Installation
Page28
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved.
Antenna Assembly
Page29
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page30
Before Hoisting the Antenna
Check the height and the position of the antenna, it should comply with the design document
Determine the azimuth of the
antenna by compass, GPS or
telescope
Verify the type and polarization
of the antenna
Adjust the polarization type of
the antenna if necessary
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved.
Antenna Polarization Adjustment
Page31
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved.
Coupler Polarization Adjustment
Page32
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page33
Before Hoisting the Antenna (Cont.) Install the anti-fall bracket
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page34
Hoisting the Antenna
Bind the hoisting rope on one of
the hoisting ring
Use one or two stretching ropes,
bind then on the antenna
Persons on top may hoist the
antenna by pull the rope on the
pulley
Caution: Nobody standing under
the steel tower when hoisting
and installing the antenna.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page35
Installing the Antenna
Spread anti-seize grease on
the bolts and remove the
hoisting rings
side strut
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved.
Antenna & ODU Installation(separately)
Page36
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved.
Antenna & ODU Installation(together)
Page37
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page38
Antenna Installation Criteria
1 Installation height and position and
polarization are right.
2 Fixation and side strut and well.
3 Antenna identifier is clear.
Mark site number
Please pay attention to cable fixation
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page39
Contents
1. OptiX RTN 300 System Hardware Structure
2. Installation Preparation
3. Antenna Installation
4. RTN 300/Hybrid Coupler and Related Cable
Installation
5. PI and Related Cable Installation
6. Loading NE data and installation checking
7. Link Commissioning
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page40
Contents
4. RTN 300/Hybrid Coupler and Related Cable
Installation
4.1 Installing RTN 300
4.2 Installing hybrid coupler
4.3 Installing the cables of RTN 300
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page41
Installing the RTN 300 on the antenna Remove the dustproof caps ① on the feeds of RTN 300
and antenna.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page42
Installing the RTN 300 on the antenna (Cont.) Change the polarization direction of the RTN 310 to the
same as that of the antenna. Vertical polarization direction (default) Horizontal
polarization direction
The arrow points to the H mark
Horizontal polarization direction
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page43
Installing the RTN 300 on the antenna (Cont.) Install the RTN 300 on the antenna.
Screwing-stop surfaceInstallation surface
If the screwing-stop surface of the capative screw is in complete contact with the installation surface of the bolt hole, the captive screw is tightened.
Apply vaseline to the exterior ⑥ of the feed. Do not apply vaseline on the end face ⑤ of the feed.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page44
Installing combiners onto the antenna Change the polarization direction of a combiner.
Horizontal polarizer
Vertical polarizer
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page45
Installing combiners onto the antenna (Cont.) Install combiners onto the antenna.
The polarization direction of the combiner should be the same as that of the antenna feed.
Apply vaseline to the O ring ⑤. Do not apply vaseline on the end face ④of the antenna port.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page46
Installing the RTN 300 on a combiner Mount the RTN 300 onto a combiner.
Apply anti-seize greaze to the long bolt.
Ensure this side is up.
Check whether the elastomer is fixed.
Ensure this side is up.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page47
Installing the RTN 300 on a split-mount installation bracket Install the RTN 300 on a split-mount installation
bracket. To remove the conversion bracket, loose the elastomer on the main fixture and take the conversion bracket off the main fixture.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page48
Installing the combiner on a split-mount installation bracket Install the combiner on a split-mount installation
bracket.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page49
Installing flexible waveguides
Install flexible waveguides.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page50
Installing the PGND cable of the RTN 300 Install the PGND cable of the RTN 300
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page51
Waterproofing the outdoor connections ofthe cables Waterproof the outdoor connections of the cables.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page52
Installing the P&E cable
Install and lay out the P&E cable.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page53
Installing the DC power cable of the RTN 300 Install and lay out the DC power cable of the RTN
300.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page54
Installing the outdoor fibers of RTN 300 Install the outdoor fibers of RTN 300.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page55
Installing the XPIC cable
Install the XPIC cable.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page56
Contents
1. OptiX RTN 300 System Hardware Structure
2. Installation Preparation
3. Antenna Installation
4. RTN 300/Hybrid Coupler and Related Cable
Installation
5. PI and Related Cable Installation
6. Loading NE data and installation checking
7. Link Commissioning
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page57
PI and Related Cable Installation
Installing the outdoor PI
Installing the indoor PI
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page58
Installing the outdoor PI of RTN 300 Open the cover of the PI
Step1
Step2
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page59
Installing the outdoor PI of RTN 300(Cont.) Install PI
cables
Connected to the power supply device
Connected to one FE/GE (electrical) service
Connected to the P&E port of RTN 380
Connected to the NMS
P&E
MGMT
Wire clip
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page60
Installing the outdoor PI of RTN 300(Cont.) Close the cover of the PI and tighten all
screws on the cover.
Tighten all screws on the cover (4.8±0.14 N·M).
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page61
Installing the outdoor PI of RTN 300(Cont.) Optional: Install the PI on a wall
a. Mark and drill holes in the wall.
Drilling positions
Mounting holes
Drill Ф8 holes to a depth of 52 to 60 mm.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page62
Installing the outdoor PI of RTN 300(Cont.) Optional: Install the PI on a wall
b. Install the PI on the wall.
Small flat washer
Big flat washer
Nut
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page63
Installing the outdoor PI of RTN 300(Cont.) Optional: Install the PI on a pole or a tower
Holes for installing a hose clamp
Step1
Step2 Step3
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page64
Installing the outdoor PI of RTN 300(Cont.) Install the PGND cable of the PI
Connect the OT terminal of the PGND cable to the ground nut.
PGND cable
Remove the anticorrosion paint and oxide layer at the ground point. After the connection is complete, waterproof and rustproof the ground point.
Install the base of ground clip.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page65
Installing the indoor PI of RTN 300
Installing the indoor PI on the auxiliary installation bracket
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page66
Installing the indoor PI of RTN 300 (Cont.) PI of RTN 300 can be installed in
19-Inch Cabinet
ETSI Cabinet
Wall
Outdoor Cabinet
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page67
Installing the indoor PI in an 19-Inch Cabinet
Install the PI in an 19-Inch Cabinet
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page68
Installing the indoor PI in an 19-Inch Cabinet (Cont.) Install the PI in an 19-Inch Cabinet
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page69
Installing the indoor PI in an ETSI Cabinet Install the PI in an ETSI Cabinet
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page70
Installing the indoor PI in an ETSI Cabinet (Cont.) Install the PI in an ETSI Cabinet
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page71
Installing the indoor PI on the wall Install the PI on the wall
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page72
Installing the indoor PI in an Outdoor Cabinet
Install the PI in the cabinet.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page73
Installing the cables of PI
Install the P&E cable of the PI
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page74
Installing the cables of PI (Cont.) Install an outdoor fiber on the PI.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page75
Installing the cables of PI (Cont.) Install the power cable of the PI
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page76
Powering on the RTN 300
With power over Ethernet
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page77
Powering on the RTN 300 (Cont.) With DC
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page78
Powering on the RTN 300 (Cont.) Networked with the RTN 900
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page79
Contents
1. OptiX RTN 300 System Hardware Structure
2. Installation Preparation
3. Antenna Installation
4. RTN 300/Hybrid Coupler and Related Cable
Installation
5. PI and Related Cable Installation
6. Loading NE data and installing checking
7. Link Commissioning
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page80
Loading NE Data
By Using the USB Flash Drive
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page81
Loading NE Data (Cont.)
By Using the Web LCT
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page82
Checking the Installation
Check the installation of antennas, combiners,
and RTN 300s
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page83
Checking the Installation (Cont.) Check the cables of RTN 300
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page84
Checking the Installation
Check the PI
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page85
Contents
1. OptiX RTN 300 System Hardware Structure
2. Installation Preparation
3. Antenna Installation
4. RTN 300/Hybrid Coupler and Related Cable
Installation
5. PI and Related Cable Installation
6. Loading NE data and installation checking
7. Link Commissioning
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page86
Connecting WebLCT to the Equipment Procedure
1. Start the laptop and
log in to the operating
system.
2. Set the IP address of
the laptop.
3. Connect the site to
the Web LCT in an
appropriate way
according to the
configurations of each
site.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page87
Connecting WebLCT to the Equipment (Cont.) Procedure
1. On the desktop, double-click the Start Web LCT icon.
The system displays the USER LOGIN window of the Web
LCT.
2. Enter the values of User Name and Password,
and click Login.
User Name: admin Password:
Changeme_123
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page88
Creating NEs by using the search method Procedure
In NE List, click NE Search. Then, the Search NE
dialog box is displayed.
After the Web LCT finds the NEs to be managed, click
End Search.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page89
Creating NEs by using the search method (Cont.) Procedure (Cont.)
Select the NE that needs to be added and click Add
NE.
A dialog box is displayed, indicating that the NE is
added successfully.
Click OK.A new NE is already added to the NE list.
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page90
Synchronizing NE Time
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page91
Changing NE Attribute
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page92
Setting NE Communication Parameters
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page93
Configuring a Single-Hop Radio Link
①
②
③
④
Copyright © 2014 Huawei Technologies Co., Ltd. All rights reserved. Page94
Summary
OptiX RTN 300 system hardware installation and link
commissioning
Antenna installation
RTN 300 and related cables installation
PI and related cables installation
Loading the data and installation checking
Link commissioning