overcoming the challenges of delivering large …...bishopton comms update_strategy meeting_aug17...
TRANSCRIPT
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
1
Jon Gettinby BAE Systems, Real Estate Solutions
Overcoming the challenges of delivering large complex regeneration schemes - Bishopton, Renfrewshire
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
2
• BAE Systems - Real Estate Solutions
• Overview of the Bishopton Programme • Remediation • Infrastructure • Planning obligations • Revenue
• Challenges
• Financial • Stakeholder engagement • Technical • Regulatory • Ecology • Land sales and the market
Introduction
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
3
BAE Systems - Real Estate Solutions Property lifecycle capability
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
Our vision
Our credentials How we add value to the business Our statistics
4
Real Estate Solutions
To deliver excellent, quality and affordable services across a range of service offerings that the businesses exploit to the benefit of themselves and/or the Group
25 years experience
managing the BAE Systems
property portfolio within UK and abroad
Accredited for ISO 9001, 14001
and 18001
11.6m sq. ft. of floor spaced managed by
RES
2,000 acres of land remediated over the last 15
years
165 employees working from 30
sites
~£80 million p.a. of rental
payments managed
The provision of professional services to manage and address
land contamination issues to either realise the value or manage the
property in a cost effective, responsible and environmentally
sustainable manner Co-authored UK guidance for the EA and DEFRA on explosives
manufacturing & processing
sites
Three offices in the UK including
a chemical laboratory
Delivering infrastructure projects within UK and abroad Responsible for
BAE Systems Contaminated
Land Management Programme
Decommissioning and
decontamination of contaminated
structures, especially explosives
Assessment and
remediation of land
contamination & related
geotechnical aspects
Mechanical/ Electrical, Civil & Structural Engineering
Contractor management
Project Management
High level of professional qualifications
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
5
Bishopton
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
6
• Former Royal Ordnance Factory: Original Georgetown factory dates back to 1915
• Three factories developed for propellant and explosive manufacturing in the run up to WWII - closed in 2003
• Planning achieved to remediate and redevelop in 2009
• £500m mixed use regeneration programme completing in 2034 for c.4,000 homes, retail, commercial a primary school, leisure & community facilities
Bishopton history:
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
7
Bishopton history:
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
Programme background:
8
• Outline planning permission granted 2009 – 57 conditions
• Detailed planning permission for remediation granted 2010 – 37 conditions
• Remediation started 2011
• First housing developers on site 2013
• To date 250 acres of land remediated, six housing developers & c.900 homes constructed
• Regeneration strategy completed by Scottish Executive Working Group 1999-2001
• Masterplan established by 2006
• Draft Glasgow & Clyde Development Plan 2005 included ROF Bishopton as a strategic Community Growth Area (CGA)
• Examination in public undertaken in 2007 to examine Glasgow & Clyde Structure Plan proposals – Reporter finds in favour and supports the allocation of the former ROF Bishopton site as a CGA
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
Reasons for development
9
• Redevelopment of brownfield land in a highly sustainable location, reducing need to use greenfield sites and the Green Belt in Renfrewshire
• High-profile collaborative programme involving BAE Systems, Scottish Government, Renfrewshire Council, SEPA and the local community to deliver a high-quality sustainable village community
• Mitigate environmental liabilities
• Demonstrate corporate responsibility commitments
• Site of exceptional scale in line with National Planning Policy Guidance
• Link new development with main road & rail networks
• Extensive woodland across the site utilised as a framework for a woodland park with benefits to both the community and wildlife
• Forge links between the new development and Bishopton creating a more sustainable community and a catalyst for wider regeneration
• Land owner-led programme that supports the Scottish Government’s targets for housing
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
10
Bishopton Programme: summary
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
Bishopton Programme Remediation:
11
• 2,500 tonnes of recycled steel • 160,000 tonnes of concrete • 80,000 tonnes of brick • 1.3 million tonnes of soil • Removal of six miles of road and rail
tracks • Fully documented process signed off by
regulators
• 1,900 acres to remediate and so far 250 acres remediated equivalent to 190 football pitches
• Remediation planned over seven phases from 2011 to 2034
• Remediation Sequence: 1. Decommissioning & decontamination 2. Demolition 3. Hot spot removal 4. Confidence scrape 5. Slab foundation and substructure
removal 6. Bulk earthworks 7. Validation testing and environmental
monitoring
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
12
On-Site Infrastructure • Roads • Bridges & culverts • Foul and surface water sewers • River diversions • SuDs pond construction • Pumping stations • Utilities
Off Site Infrastructure • Motorway junction • Local road improvements • Drainage network reinforcement • Power upgrades / reinforcement
Bishopton Programme Infrastructure:
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
13
Infrastructure on site to date • 4.5Km of roads within the development
• Two foul water pumping stations and 4.2Km of
associated rising mains
• Two bridges have been constructed; a 47m span bridge over the electrified railway and a 14m span bridge over the Craigton Burn
• 4.2Km of foul water sewers and 5.7Km of surface water sewers incl. seven SuDs ponds
• 18Km of power cables, six substations and four gas governors
• 4.5Km of gas and water pipework
Bishopton Programme Infrastructure:
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
14
• Revenue derived from the sale of remediated land for residential and commercial uses
• The site contains a total of c.400 acres of land which can be sold
• 115 acres of land sold to-date
• c. 900 houses constructed
• Contracts being finalised for retail and commercial plots
Bishopton Programme Revenue:
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
15
• Delivery of the Section 75 planning obligations • Affordable housing • Primary school • Health centre • Bus services • Road capacity improvements • Park & ride facilities • Recreation & amenity • Community contributions & support
• Provision of structural landscaping for the
development including 1,300 acres country park, on-site parks and amenity space
• Maintenance of the strategic infrastructure until adoption
Bishopton Programme Real Estate Management:
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
16
Cost model • Huge up front cost • Long-term 30+ year investment • No grants/funding • High risk
• No guarantee on revenue • Low cost delivery certainty
Reporting • Programme performance (1) • Project performance (5-8) • Work package performance (100+) • Governance through multiple layers of management • Risk management
Commercial • Procurement • Formal engineering contracts • Contract administration • Disputes
Challenges: Finance
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
17
Community engagement • Bishopton Community Council • Dargavel Residents Association • Bishopton Community Development Trust • Bishopton Action Group • Representatives of the medical practice • Community Centre Association • Bishopton Sports and Social Club • Government ministers • Elected members • Council officers • Media
Community engagement • Community Liaison Group meetings • Attendance at other community meetings • Quarterly newsletters • Monthly bulletins • Freephone contact number
Challenges: Stakeholder engagement
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
18
Site assessment & remediation • Size and time-frame of the project (30 years) • Quantum of SI and data
• 15,885 samples and 953,100 analytes • Highly variable and complex superficial geology
• Technical skill sets/project management capability • Re-phasing/alignment of remediation works &
reporting Infrastructure • Design of surface water, foul, power, roads, bridges • Implementation of design to construction • Developer interfaces • Infrastructure maintenance and adoption • Energy requirements
• Ground source heat pumps • Car charging stations
Design • Creating a development fit for the future Programme • Integration of all elements of the programme
Challenges: Technical
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
19
Leveraging support & SME • Environmental health – contaminated land • SEPA officers • Highways • Planning • Strategy • Housing • Property • Education • Transport Scotland • Health and Safety Executive • Scottish Natural Heritage • BSI/internal governance
Challenges: Regulatory
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
20
• Eight protected species on the site: • Barn Owls; Little Ringed Plovers; Kingfishers;
Crossbills; Badgers (12 Clans); Otters; Bats; Brook Lampreys
• Dedicated ecological management team
• Ecological management is a significant risk mitigation
strategy for the programme
• Otter, badger and bat species management Licences issued by Scottish Natural Heritage to protect, displace and relocate these mammals
Challenges: Ecology
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
Challenges: Land sales & market
21
Local issues
• Developing a new ‘sense of place’ • Creating the environment for change • Engaging others with the vision for the future
• Community • Developers
• Finite number of houses that can be constructed and sold each year • Smaller Scottish house developer market • Retail/commercial limited by extent of development • Politics
Macro issues
• Housing market stability
• Brexit • Indyref2
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
Concluding remarks
22
• Land owner-led, exemplar brownfield regeneration project, bringing land back into beneficial use for the next generation
• Regular and continued stakeholder engagement, collaboration and active involvement
• Implementing the right infrastructure to support the development up front
• Very positive progress of the development benefitting both the Bishopton and Dargavel Village communities
• Provides a sustainable and effective housing supply until 2034, taking the pressure off
greenfield site development
• The regeneration programme needs to be resilient and viable to provide confidence for long-term progressive strategic housing delivery
BAE SYSTEMS PROPREITARY Unpublished work ©2018 BAE Systems. All Rights Reserved BAE SYSTEMS is a registered trademark of BAE Systems plc
Thank you
23
Questions