part v s4/iee control phase from dmaic and application...
TRANSCRIPT
6/6/2013
1
Part V
S4/IEE Control Phase
from DMAIC
and Application Examples
Introduction
• This part (Chapters 34-44) addresses the implementation
of a control plan, along with other DMAIC tools.
• Project success at one point in time does not necessarily
mean that the changes will stick after the project leader
moves on to another project. Because of this. the control
phase is included in DMAIC.
• This part also describes engineering process control, 50-
foot-level control charts, pre-control, and error-proofing
(poka-yoke).
6/6/2013
2
Introduction
• This part also discusses reliability assessments, pass/fail
functional testing, and application examples, which have
broader implementation possibilities than often initially
perceived.
• Within this part of the book, the DMAIC control steps,
which are described in Section A.1 (part 5) of the
Appendix, are discussed.
• A checklist for the completion of the control phase is:
Introduction
Control Phase Checklist
Description Question
Tool/Methodology
Process Map/
SOPS/
FMEA/
Mistake Proofing
Control Plan
• Were process changes and procedures documented with
optimum process settings?
• Were mistake proofing options considered?
• Were control charts created at the 50-foot level on
appropriate KPlVs?
• Was the appropriate control chart used for the input
variable data type?
• Is the sampling plan sufficient?
• Is a plan in place to maintain the 30,000-foot-level control
chart using this metric and the process capability/
performance metric as operational metrics?
• Has the responsibility for process monitoring been assigned?
• Is there a reaction plan for out-of-control conditions?
6/6/2013
3
Introduction
Control Phase Checklist
Description Question
Tool/Methodology
Assessment • Were any process improvements made?
• lf so, were they statistically verified with the appropriate
hypothesis tests?
• Did you describe the change over time on a 30,000-foot leveI
control chart?
• Did you calculate and display the change in process capability/
performance metric (in units such as ppm)?
• Have you documented and communicated the improvements?
• Have you summarized the benefits and annualized financial
benefits?
Introduction
Control Phase Checklist
Description Question
Tool/Methodology
Communication
Plan
• Has the project been handed off to the process owner?
• Are the changes to the process and improvements being
communicated appropriately throughout the organization?
• Is there a plan to leverage project results to other areas of the
business?
Team
Team Members • Were all contributing members of the team acknowledged and
thanked?
Change
Management
• Has the team considered obstacles to making this change last?
• Has the project success been celebrated?
6/6/2013
4
Introduction
Control Phase Checklist
Description Question
Next Phase
Final Approval
and Closure
• Is there a detailed plan to monitor KPIV and KPOV metrics over
time to ensure that change is sustained?
• Have all action items and project deliverables been completed?
• Has a final project report been approved?
• Was the project certified and the financial benefits validated?
• Has the project database been updated?
Chapter 34
Short-Run and
Target Control Charts
6/6/2013
5
Introduction
• A control chart is often thought to be a technique to control
the characteristics or dimensions of products, the thought
being that a controlled process will yield products that are
more consistent.
• It is typically more useful to focus on key product
characteristics and their related process parameters than on
a single product characteristic.
• Brainstorming techniques can help with this selection
activity.
• The most effective statistical process control (SPC) program
uses the minimum number of charts and at the same time
maximizes their usefulness.
Introduction
• General application categories for short-run charts include the
following:
• Insufficient parts in a single production run
• Small lot sizes of many different parts
• Completion time that is too short for the collection and
analysis of data, even though the production size is large
• If standard control limits are used when there are only a small
number of subgroups, there is a greater likelihood of
erroneously rejecting a process that is actually in control.
• Pyzdek (1993) includes tables that can be used to adjust
control limits when there are a small number of subgroups.
The examples included here do not consider this adjustment.
6/6/2013
6
34.1 S4/IEE Application Examples:
Target Control Charts
• Transactional 30,000-foot-level metric: An S4/IEE project
was to reduce DSO for invoices. Instead of total DSO for an
invoice, could make comparison to different due dates.
• Transactional and manufacturing 30,000-foot-level metric:
An S4/IEE project was to improve customer satisfaction for a
product or service. Could combine satisfaction surveys that
have different criteria or scales (1-5 versus 1-10).
34.1 S4/IEE Application Examples:
Target Control Charts
• Manufacturing 30,000-foot-level metric: An S4/IEE project
was to improve the process capability/performance metrics
for the diameter of a plastic part from an injection-molding
machine. Could compare different diameter parts off the
same molding machine by plotting differences relative to
center of specification.
• Product DFSS: An S4/IEE project was to improve the
process capability/performance metrics for the number of
daily problem phone calls received within a call center. Can
record differences to optimum number of calls that could
handle because of different call center sizes.
6/6/2013
7
34.2 Difference Chart
(Target Chart / Nominal Chart)
• Difference charts (also known as target chart and nominal
chart) permit the visualization of underlying process even
though it has short runs of differing products.
• The nominal value that is to be subtracted from each value
observed is specific to each product. This value can either
be a historic grand mean for each product or a product
target value.
• Specification targets depend upon the type of specification.
Symmetrical bilateral tolerances such as 1.250 0.005
would have the nominal value as the target. Unilateral
tolerances such as 1.000 maximum could have any desired
value-for example, 0.750.
34.2 Difference Chart
(Target Chart / Nominal Chart)
• Historical targets focus on the actual target value of the
process with less emphasis on specifications.
• Applications include situations where the target value is preferred over the specification or there is a single specification
(maximum or minimum) limit. • General application rules of the difference chart are:
• Constant subgroup size
• Twenty data points for control limits
• Same type of measurement • Similar part-to-part range
• If the average ranges for the products are dramatically different or the types of measurements are different, it is better to use a
Z chart.
6/6/2013
8
34.3 Example 34.1:
Difference Chart
• Table 34.1 shows the measurements from three parts designated as a, b, and c that have different targets. The
subgroup measurements for each part are designated as M1, M2, and M3. Measurement shifts from the target are
designated as M1 shift, M2 shift, and M3 shift. The method for
calculating these control limits is similar to that for typical 𝑥 and
𝑅 charts. • The control chart in Figure 34.1 indicates that the process is in
control/predictable. Process capability/performance metric assessments can also be made from these data.
34.3 Example 34.3 Difference Chart
Seq. Part Target M1 M2 M3 M1Shift M2Shift M3Shift 𝑥 R
1 a 3.250 3.493 3.496 3.533 0.243 0.246 0.283 0.257 0.040
2 a 3.250 3.450 3.431 3.533 0.200 0.181 0.283 0.221 0.102
3 b 5.500 6.028 5.668 5.922 0.528 0.168 0.422 0.373 0.360
4 b 5.500 5.639 5.690 5.634 0.139 0.190 0.134 0.154 0.056
5 b 5.500 5.790 5.757 5.735 0.290 0.257 0.235 0.261 0.055
6 b 5.500 5.709 5.743 5.661 0.209 0.243 0.161 0.204 0.082
7 c 7.750 8.115 7.992 7.956 0.365 0.242 0.206 0.271 0.159
8 c 7.750 7.885 8.023 8.077 0.135 0.273 0.327 0.245 0.192
9 c 7.750 7.932 8.078 7.958 0.182 0.328 0.208 0.239 0.146
10 c 7.750 8.142 7.860 7.934 0.392 0.110 0.184 0.229 0.282
11 c 7.750 7.907 7.951 7.947 0.157 0.201 0.197 0.185 0.044
12 c 7.750 7.905 7.943 8.091 0.155 0.193 0.341 0.230 0.186
6/6/2013
9
34.3 Example 34.3 Difference Chart
34.4 Z Chart (Standardized Variables Control Chart)
• With this Z chart, multiple processes can be examined at the
same time.
• A chart can even be set up to track a part as it goes through
its manufacturing operation.
• This charting technique can be used to monitor the same
chart measurements that have different units of measure
and standard deviations. The control limits are also fixed, so
that they never need recomputing (the plot points are
standardized to the limits, typically 3 units).
6/6/2013
10
34.4 Z Chart (Standardized Variables Control Chart)
• Caution should be exercised when applying these charts
because more calculations are required for each point.
• In addition, they require frequent updating of historical
process values.
• Also, the value that is tracked on the chart (𝑍 value) is not
the unit of measure (e.g., dimension of a part), and the user
can become distant from individual processes.
• This charting technique is based on the transformation
𝑍 =𝑆𝑎𝑚𝑝𝑙𝑒 𝑠𝑡𝑎𝑡𝑖𝑠𝑡𝑖𝑐 − 𝑃𝑟𝑜𝑐𝑒𝑠𝑠 𝑎𝑣𝑒𝑟𝑎𝑔𝑒
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 𝑠𝑡𝑎𝑑𝑎𝑟𝑑 𝑑𝑒𝑣𝑖𝑎𝑡𝑖𝑜𝑛
• The method can apply to both attribute and continuous data,
but only the 𝑍𝑚𝑅 chart will be shown here.
34.4 Z Chart (Standardized Variables Control Chart)
• Short-run charts can pool and standardize data in various ways. The most general way assumes that each part or batch produced by a process has a unique average and standard deviation. If the average and standard deviation can be obtained, the process data can be standardized by subtracting the mean and dividing the result by the standard deviation.
• When using a 𝑍𝑚𝑅 chart, consider the following when determining standard deviation: • When all output has the same variance regardless of
size of measurement, consider using a pooled estimate of the standard deviation across all runs and parts to obtain a common standard deviation estimate.
6/6/2013
11
34.4 Z Chart (Standardized Variables Control Chart)
• When the variance increases fairly constantly as the measurement size increases, consider using a natural log transformation to stabilize variation.
• When runs of a particular part or product have the same variance, consider using an estimate that combines all runs of the same part or product to estimate standard deviation.
• When you cannot assume that all runs for a particular product or part have the same variance, consider using an independent estimate for standard deviation from each run.
34.5 Example 34.2: 𝑍𝑚𝑅 Chart
• The observations were taken in a
paper mill for different grades of
paper made in short runs.
• The ZmR chart was calculated
where standard deviation was
determined by pooling all runs of
the same part.
• The chart shows no out-of-control
condition. MeanA 1.7847
StddevA 0.0673
MeanB 1.5015
StddevB 0.0527
MeanC 1.3917
StddevC 0.0429
Seq. Grade Thickness Z 1 B 1.435 -1.2628 2 B 1.572 1.3388 3 B 1.486 -0.2943 4 A 1.883 1.4603 5 A 1.715 -1.0346
6 A 1.799 0.2129 7 B 1.511 0.1804 8 B 1.457 -0.8450 9 B 1.548 0.8830
10 A 1.768 -0.2475 11 A 1.711 -1.0940 12 A 1.832 0.7029 13 C 1.427 0.8245 14 C 1.344 -1.1123 15 C 1.404 0.2878
6/6/2013
12
34.5 Example 34.2: 𝑍𝑚𝑅 Chart