path -replacement of substations no. 8 and no. 14 –project ... · microsoft powerpoint - path...
TRANSCRIPT
PATH - Replacement of Substations No. 8 and No. 14 – Project Reauthorizations
Committee on Capital Planning, Execution and Asset ManagementJune 27, 2019
Background
Existing Substation No. 8Existing Substation No. 14
2
Scope of WorkNew Substation No. 8 Rendering
Work includes:• Traction power transformers, rectifiers
and switchgear equipment• Auxiliary systems and equipment• Decommission existing substation • New two-story steel building above
Federal Emergency Management Agency base flood elevation
3
PATH – Substation No. 8 - Project Cost and Schedule
– Previously Authorized: $53.9M– Requested Increase: $18.1M– Total Project Cost: $72.0M
• Construction Contract: $45.2M (Anticipated Award – July 2019)
• Overall Completion of Project – November 2023
4
Scope of WorkNew Substation No. 14 Rendering
Work includes:• Two story extension of existing building• Replacement of traction power
transformers, rectifiers and switchgear equipment
• Auxiliary systems and equipment• Equipment installed above Federal
Emergency Management Agency base flood elevation
5
PATH – Substation No. 14 - Project Cost and Schedule
– Previously Authorized: $70.6M– Requested Increase: $16.9M– Total Project Cost: $87.5M
• Construction Contract: $54.4 million (Anticipated Award – July 2019)
• Overall Completion of Project – December 2023
6
Economic Impacts
Substation No. 8 Replacement
• 450 direct job-years
• $35.2 million in direct wages
• $116.3 million in economic activity over the life of the project
Substation No. 14 Replacement
• 550 direct job-years
• $45.5 million in direct wages
• $140.5 million in economic activity over the life of the project
7