PATH - Replacement of Substations No. 8 and No. 14 – Project Reauthorizations Committee on Capital Planning, Execution and Asset Management June 27, 2019

Upload: others

Post on 09-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PATH -Replacement of Substations No. 8 and No. 14 –Project ... · Microsoft PowerPoint - PATH Board Presentation - Substations Projects (6-19) Author: jruss Created Date: 6/27/2019

PATH - Replacement of Substations No. 8 and No. 14 – Project Reauthorizations

Committee on Capital Planning, Execution and Asset ManagementJune 27, 2019

Page 2: PATH -Replacement of Substations No. 8 and No. 14 –Project ... · Microsoft PowerPoint - PATH Board Presentation - Substations Projects (6-19) Author: jruss Created Date: 6/27/2019

Background

Existing Substation No. 8Existing Substation No. 14

2

Page 3: PATH -Replacement of Substations No. 8 and No. 14 –Project ... · Microsoft PowerPoint - PATH Board Presentation - Substations Projects (6-19) Author: jruss Created Date: 6/27/2019

Scope of WorkNew Substation No. 8 Rendering

Work includes:• Traction power transformers, rectifiers

and switchgear equipment• Auxiliary systems and equipment• Decommission existing substation • New two-story steel building above

Federal Emergency Management Agency base flood elevation

3

Page 4: PATH -Replacement of Substations No. 8 and No. 14 –Project ... · Microsoft PowerPoint - PATH Board Presentation - Substations Projects (6-19) Author: jruss Created Date: 6/27/2019

PATH – Substation No. 8 - Project Cost and Schedule

– Previously Authorized: $53.9M– Requested Increase: $18.1M– Total Project Cost: $72.0M

• Construction Contract: $45.2M (Anticipated Award – July 2019)

• Overall Completion of Project – November 2023

4

Page 5: PATH -Replacement of Substations No. 8 and No. 14 –Project ... · Microsoft PowerPoint - PATH Board Presentation - Substations Projects (6-19) Author: jruss Created Date: 6/27/2019

Scope of WorkNew Substation No. 14 Rendering

Work includes:• Two story extension of existing building• Replacement of traction power

transformers, rectifiers and switchgear equipment

• Auxiliary systems and equipment• Equipment installed above Federal

Emergency Management Agency base flood elevation

5

Page 6: PATH -Replacement of Substations No. 8 and No. 14 –Project ... · Microsoft PowerPoint - PATH Board Presentation - Substations Projects (6-19) Author: jruss Created Date: 6/27/2019

PATH – Substation No. 14 - Project Cost and Schedule

– Previously Authorized: $70.6M– Requested Increase: $16.9M– Total Project Cost: $87.5M

• Construction Contract: $54.4 million (Anticipated Award – July 2019)

• Overall Completion of Project – December 2023

6

Page 7: PATH -Replacement of Substations No. 8 and No. 14 –Project ... · Microsoft PowerPoint - PATH Board Presentation - Substations Projects (6-19) Author: jruss Created Date: 6/27/2019

Economic Impacts

Substation No. 8 Replacement

• 450 direct job-years

• $35.2 million in direct wages

• $116.3 million in economic activity over the life of the project

Substation No. 14 Replacement

• 550 direct job-years

• $45.5 million in direct wages

• $140.5 million in economic activity over the life of the project

7