peter breen - international atomic energy agency · peter breen . peter breen ... class 5 class 4...
TRANSCRIPT
Cost Estimation Considerations for Technology
Assessment and Selection
Peter Breen
Peter Breen: Consultant
• Nuclear experience with NNB, HNP, BNG, Centrica and Exelon
• Procurement & Commercial experience e.g. Olympics, EPC, AE,
• International experience of major regulated projects
• Faithful+Gould Board Director
• F+G is part of Atkins Group of Companies
• n.triple.a - The Nuclear Atkins Assystem Alliance
Introduction
• What you would like to know when embarking on a new project?
• What should be the estimating strategy for the programme?
• Is there a link between reactor choice and the overall costs?
• Does it make any difference which technology is chosen?
• Should we consider overnight costs or whole life cost approach?
• How do we compare different technologies, commercial offers and execution
plans?
• What lessons have been learnt by others from their experience to date?
Answer in 3 Parts: Estimating, Technology Assessment and Lessons
Cost Estimation Considerations for Technology Assessment and Selection - Questions
Part 1:
Cost Estimation
A genuine assessment of outturn
costs based upon the best
information available, and the
experience and knowledge of the
project team to fill the gaps where
complete information is absent.
What is an Estimate?
• Provides the Budget for Business Case
• Selects the right Project
• Sets the Baseline
• Establishes Resources Requirement and
helps validate schedule
• Baseline for Risk and Opportunity Analysis
• Allows Challenge of Vendors’ bid
• Allows performance measurement against
the baseline
• Manages expectations and encourages
Cost Certainty
Why estimate?
Estimate
• Estimates are produced at various stages throughout the life of a project or program for a variety of purposes.
• The type of estimate to be prepared as well as the methodology used is dependent on what estimate will be used
for and how well the scope is defined.
•This presentation will describe typical estimate types and their relationship to scope development and appropriate
estimating methodologies to be used for each stage.
• The descriptions are not all-inclusive, but provide enough examples to illustrate the concept of the evolution of
estimating together with the development of scope.
Scope Development and Estimating
• It is important to understand the stages of scope development when preparing or reviewing an estimate. All
projects, whether they are conventional capital, decommissioning or operations, evolve through a series of stages
related to scope development.
•The level of design definition (% Complete) can be different for the various components
•The estimates that support this scope development can be classified into broad categories in line with industry
practices
Classifications of Estimates
10 20 30 40 50 60 70 80 90 100
Level of Project Definition (%)
100
80
60
40
20
0
-20
-40
-60
-80
-100
Est
imate
Expect
ed A
ccura
cy (
%) Class 5
Class 4
Class 3 Class 2
Class 1
Conceptual Feasibility
Budgetary Control
Check
Estimate Categories
From standard by AACE, Association for the Advancement of Cost Engineering
Project Definition – Estimate Accuracy D
Estimate
Accuracy
Design Completion
± 50%
± 25%
± 10%
± 5%
3% 15% 35% 100%
Estimate based on benchmarking, early information
Estimate based on early equipment quotes, approximate quantities, outline schedule
Estimate based on equipment fixed quotes, take offs, schedule, execution strategy, contractor prices
Detailed Design
FEED
Concept
MP
FEED = Front End Engineering Definition
MP = Master Planning
Initial Funding
Interim Funding
Final Funding
Construction
65%
Stages of Estimate Development
Estimate Master Planning
Pre-Conceptual
Conceptual
Preliminary
Option Selection Definition Installation
Purpose Concept Screening Feasibility Budget
Authorisation
Control Check Price
Basis Sketches
Proposed site
Reference to
existing facilities
Early drawings and
scope descriptions.
Basic schedule
Preliminary Design All tender packages
developed
Final fabrication
details available
% Design
Complete
3% 15% 35% 50% 100%
Accuracy L: -20% to -50%
H: +20% to +50%
L: -15% to -30%
H: +20% to +50%
L: -10% to -20%
H: +10% to +30%
L: -5% to -15%
H: +5% to +20%
L: -3% to -10%
H: +3% to +10%
Estimating Method Capacity factored,
parametric,
judgement
Equipment factored
and parametric
model
Possible tenders for
major equipment.
Quantification.
Some approximate
estimating
Contracts for major
equipment. Detailed
quantities
Based on bids,
variations, final
quantities
Top down Top Down Bottom Up Bottom up Bottom up
AACE Class Class 5 Class 4 Class 3 Class 2 Class 1
Typical Preliminary Schedule Overview
COM
Design Certification
Site Specific Engineering
Full Capital Authorisation
Construction
Site Prep
Site Prep
UNIT 1
UNIT 2
Construction
01 02 03 04 05 06 07 08 09 10 11 12
COM
72 Months
48 Months
18 months 42 Months
18 Months 42 Months
8 Months
7 Months
Ground Breaking
First Concrete
Fuel Load COD
Ground Breaking
First Concrete
Fuel Load
COD
Estimates
Initiate
Technology Procurement
Design Certification
Concept Feasibility Preliminary Sanction Installation
• Are benchmarks appropriate to this project?
• Have comparison projects been normalized?
• Have deviations to the benchmark set been rationalized
/ explained
• Does the comparison fit with project expectations /
charter
Benchmarking
•There is an unbreakable link between the scope, schedule, and execution methodology
with the estimate.
•There is a fundamental need for quantification to help determine the cost and schedule be it
the design man-hours, volume of concrete, meters of pipes, electrical I/O points;
Standardised key units for benchmarking
Time related costs
Need for bottom up estimating
Validation of schedule thru’ required effort for activities
Productivity calculations for different locations
•The site layout impacts the quantities in terms of civil works, mechanical and electrical
distribution
•The extent to which shared facilities are already on site
•The Quantification can be used to determine the target cost
Quantification
Typical Estimate Summary
CONSTRUCTION COSTS
Site Preparation
Site Platform
Off site infrastructure Costs
Temporary Construction Services ( set up)
Planning Application Conditions
Nuclear Construction & Commissioning
Civils
Nuclear Steam Supply System
Turbine / Generation
Balance of Plant
Grid Reinforcement
Temporary Construction Services ( maintain)
Architect Engineer
Owners Management
Owners Scope Costs
Start up
Operational Licence
Operator Recruitment, Training and Staffing
Start up purchases inc Spares
Owner Management & Engineering Support
Strategic Spares
DEVELOPMENT COSTS
Management & General Items
Owners Project Management Team
Engineering & Consultant Support
Delivery Partner Costs Pre-Construction
Long Lead Equipment Early Payments
Land Purchases
PR / Communications
Corporate Responsibility Costs
Generic Authorisations & Licences
Generic Design Assessment
Site Specific Authorisations & Licences
Site Specific Design
Site Specific Investigations
Environmental Impact Statement
Planning Application
Nuclear Site Licence
ALLOWANCES
Escalation
Risk
ANNUAL OPERATIONAL COSTS
Operator / Staffing Costs
Materials & Services
Centralised Functions Costs
Sustaining Capex
Outages
General Items inc. Business Rates & Taxes
T&D
Grid Charges
Fuel costs
First Fuel load
Fuel Costs - Front End
Fuel Cost - Back End
Decommissioning Fund
Detailed estimate
22... 22 Reactor plant equipment
22.221.. 22 221 Reactor equipment
22.221.1. 22 221 1 Reactor vessel
22.221.1.11 22 221 1 11 Reactor vessel and accessories
22.221.1.12 22 221 1 12 Closure head and attachments
22.221.1.13 22 221 1 13 Studs, fasteners, seals and gaskets
22.221.1.14 22 221 1 14 Calandria tubes and fittings
22.221.1.15 22 221 1 15 Pressure tubes and fittings
22.221.1.16 22 221 1 16 Insulation
22.221.1.17 22 221 1 17 Tools (stud tensioning device), accessories and handling equipment
22.221.2. 22 221 2 Reactor vessel internals (excluding fuel assemblies, reflector materials, moderators and reactivity control components)
22.221.2.21 22 221 2 21 Core tank or barrel container or moderator tank
22.221.2.22 22 221 2 22 Core baffles, core shrouds, distributors, orifices, throttles and strainers
22.221.2.23 22 221 2 23 Upper core structure
22.221.2.24 22 221 2 24 Control rod guide assemblies
22.221.2.25 22 221 2 25 Feedwater distributor
22.221.2.26 22 221 2 26 Steam separators and driers
22.221.2.27 22 221 2 27 Guides, channels, holders, etc., for irradiation specimen
22.221.2.28 22 221 2 28 Tools, accessories, handling and storage equipment
22.221.3. 22 221 3 Reactor vessel support structures
22.221.3.31 22 221 3 31
Reactor pressure vessel supports, brackets, sealings, pipe supports or others, including shielding materials if they are integral parts of the support
structure
22.221.4. 22 221 4 Reactor control devices and other core installations
22.221.4.41 22 221 4 41 Control rod drive mechanism (magnetic, hydraulic, motor driven, others)
22.221.4.42 22 221 4 42 Control assemblies, drive shafts, etc.
22.221.4.43 22 221 4 43 In-core instrumentation (mechanical equipment)
22.221.4.44 22 221 4 44 Primary and secondary neutron sources
22.221.4.45 22 221 4 45 Burnable poison (if not an integral part of the fuel)
22.221.4.46 22 221 4 46 Boron fast shutdown system (for boric acid see account 27)
22.221.5. 22 221 5 Moderator system excluding moderator/reflector materials
22.221.5.51 22 221 5 51 Piping
22.221.5.52 22 221 5 52 Valves and fittings
22.221.5.53 22 221 5 53 Supports (piping related)
22.221.5.54 22 221 5 54 Insulation
22.221.5.55 22 221 5 55 Circulation pumps, including motors, supports, fixtures
22.221.5.56 22 221 5 56 Tanks, including supports, fixtures
22.221.5.57 22 221 5 57 Heat exchangers
IAEA Economic Evaluation of Bids for Nuclear Power Plants 1999 Edition;
edited
Estimating Behaviours
- Do not estimate in a vacuum
- Engage the project team
- Actively listen to the broader view
- Treat the development of the estimate as a team effort with
shared ownership
- Encourage fierce challenges
- Do not take it personally
Estimating Best Practices Explored
Part 2:
Technology
Assessment
& Selection
• What is being procured - NSSS, full power plant or component packages?
• Who is providing the scope?
• Overall Timescale is protracted
• Need for a procurement strategy and roadmap
Consider early design / early works agreement / early vendor involvement
Consider impact on the Owner procurement / commercial team capability
• Establish a clear mechanism for evaluation of offers at each offer
• Expect differing offers in terms of Technology, Commercial and Execution
• Consider a QRA to provide for risks in order to compare differences between bids
Technology Procurement and Selection
Challenges
Business Case / Best
Deal
Site(s) Specifics External
Influences
Managing Procurement
Strategic Drivers
Vendors / Delivery Teams
Develop an Assessment process that recognises challenges
• Overall Cost / NPV/ LUEC
• Political Influences
• Finance Influences including equity participation
• Experience of a Technology / Vendor
• Certainty of delivery (cost time quality) around the supply chain, the technology in the
individual location
• Technical, Commercial and Execution aspects of options available
• Certainty of operation including long term service capability, fuel supply, grid and
waste management considerations.
• Overall capacity / output / availability / life
• Programme deadlines
Objective is an evidence based decision
Basis of Technology Assessment and Selection
• Limited number of available technologies / Vendors
• Vendors order book / backlog
• Owner’s Project Delivery Strategy for the integration of NI, CI and BOP
• The site specific layout
• Schedule / Programme impacts of the choice of reactor on in country licensing
• Familiarisation of the operator base
• Extent of prefabrication to minimise construction programme
• How the technology projects integrates into the overall programme eg Grid, fuel...
Technology Assessment Considerations
Vendor Evaluation Criteria
• Capital Cost based on NPV
• Operating costs including fuel over time
• Decommissioning Costs
• Compliance with the Specification - Yes or No
• Cash Flow
Factual Evidence for Decision
Whole Life Costs
• Clear identification of the Parties, division of responsibilities, liabilities, capabilities
and capacity to deliver.
• Availability of the plant over planned life / validation of vendor claims.
• Net Output.
• Life expectancy.
• Exclusions from offer made by vendor become Owner responsibilities
• Priced Risks
Cost risks retained by Owner and those shared with vendor
Schedule risk allowance (e.g. Design, Licences, Delivery)
Assessment of Risks to be included in decision
The selection of the technology is largely dependent of the approach taken to risk by the Owner and Vendor
Risk Assessment
Identification Quantification Management
Project Documentation Specialist Input
Objectives Workshops Risk Groups Risk Datable Previous Experience WBS
IDENTIFY
Risk Reporting Historic Risk Data Risk Management Plan
MINIMISE Prioritised Risks
Risk Categories Risk Classifications
CLASSIFY Risks
Probability Analysis key Sensitivities Key Criticalities
QUANTIFY Classified Risks
Risk Probability Impact Analysis
GRADE Quantified Risks
AVOID
Project Execution Strategy Risk Limitation Strategy
Key Performance Indicators Control
Contingency Provision
REVIEW
• NSSS systems cost 20 – 30% of the total project costs
• The NSSS also influences other aspects such as Balance of NI, BoP, fuel, number of
operators
•The total cost of the NSSS will reflect the maturity of the technology and the extent of
design & licensing already complete. First of a kind has a premium price
• Life expectancy may differ moving from 30 to 60 years
• Claims made by the vendors should be verified and base assumptions understood
Reactor Costs
Indicative Roadmap to Evidence Based Decision
Procurement Planning
Request for Information
Dialogue
Negotiation
Request for Quotation
Early Design / Works Agreement
Revised Offer(s)
Final Negotiations
Contract Award
How many bidders? Selection of Preferred Bidder(s) How many EDA or EWA?
Part 3:
Lessons Learnt
1. There needs to be a robust economic business case for developing new nuclear.
2. The cost to develop a scheme to full authorisation is expensive to the Owner.
3. Do not under estimate the impact on the Owner of resources needed to develop a scheme, select a
vendor while interfacing with Regulators, Grid, Decommissioning authority, Permits and
Government.
4. Owner resources need to be clear on their remit, process and procedures.
5. Owners need to have a clear decision making process between any JV companies.
6. Develop a clear procurement strategy with roadmap route to contract for Vendor.
7. Maintain competition between vendors for as long as possible.
8. Establish Early Contractor Involvement with the Preferred Bidders for site specific designs.
9. Clarify the in country regulatory requirements (particularly in respect of safety systems); site
specific issues, such as geology and Planning restrictions.
10. Selecting Most Economically Advantageous Tender needs to be underpinned with a strong risk
management process.
11. Consider establishing bid evaluation criteria that is based on cost and priced risks.
12. Contractors have more confidence in productivity on CI & BOP compared with the NI and BNI -
this is due to understanding of the regulator requirements in country.
Learning to Date
13. Having robust contracting arrangements are essential as are those that adopt contracting
strategies that promote constructive relationships, rather than adversarial ones, between
parties.
14. Contractors’ willingness to take on Risk is limited.
15. Contract negotiations with vendors and delivery teams are protracted.
16. Agreement of pricing mechanism with escalation provision given term is a challenge.
17. The bidding costs are expensive to the supply chain who fear projects that do not go ahead.
18. Security of information is imperative.
19. Provide a central team location with good IT.
20. Owners need to take the lead - the costs of project risk rest with the Owner. Their
leadership is critical to success and it is Owners that should ensure that best practice is
used on their projects.
21. Use integrated project teams from the start of the project.
22. Allow sufficient time and resources for planning and engineering design and for appointing
contractors based primarily on competency. Supplement Owner team with industry experts.
23. Recognise the shortage of good supervisory staff and particular skilled staff – welders,
planners, project managers and engineering designers – develop proposals to mitigate.
24. Nuclear projects need early, proactive and collaborative action by Owners, vendors,
contractors, the workforce, unions and Governments
Learning to date continued..
25. The Owner’s licensing manager arrangements need to be reflected in the contract.
26. The vendors need to understand the procurement process to commit to the bidding process.
27. The first estimate prepared is the most important one. Accuracy range should be stated.
28. Use career professionals to estimate.
29. Develop a clear set of assumptions addressing issues such as productivity levels, logistics,
local labour v travelling v accommodated personnel, economic conditions escalation.
30. Develop a Policy for Foreign Exchanges / Currency Hedging.
31. Adopt coding system before preparing estimating to allow for analysis.
32. Quantities drive prices.
33. Instil good behaviour and attitude within the project team to respect the budget.
34. Link the scope, schedule and estimate to the procurement strategy – this is the basis for
control including change management. Control scope with change management.
35. Commissioning Costs & Start-up costs are considerable and should be capitalised.
36. Be aware that the benefit of a low cost on-shore base for some aspects can be out
weighted by expensive off-shore resources.
Learning to date continued..
• Remember the cost differential between NSSS technologies may be a small part of the
overall programme and whole life cost.
• Estimate at appropriate stages – instigate a change management process and trend
estimate development
• Consider linking the scope, schedule, budget and procurement contracts.
• Consider seeking to increase the level of Certainty of the costs (ie reduce Risk) at
opportune stages of the project.
• Always state the estimate accuracy.
Summary Considerations
Thank You