PLANNING & MANAGING

PRODUCTION FOR

SHIP REPAIR

Page 2: Planning & Managing Ship Repair - sparusa.com

Fundamental Project Tasks

• Identify Scope Of Work

• Identify Material Requirements

• Identify Technical Requirements

• Identify Organization Responsibilities

Page 3: Planning & Managing Ship Repair - sparusa.com

Develop Master Plan From Major

Spec Items

Strip OutStructural

Machinery

PipingElectrica l

HV ACOutfitPaint

Services

0.00

50.0

0

100.

00

150.

00

Page 4: Planning & Managing Ship Repair - sparusa.com

Identify Spec Items By Ship Zone

Super StructureExterior

MachinerySpaces Tanks

ForwardSection

Page 5: Planning & Managing Ship Repair - sparusa.com

•Strip Out (Access Areas)

•Hull Work (Structural Units)

•Outfit (Compartments)

•Electrical (Decks & Verticals)

•Painting (Decks, Tanks, & Exterior)

Categories of Ship Zones:

Page 6: Planning & Managing Ship Repair - sparusa.com

Develop Work Orders

•Ship Work

•Shop Work

•Subcontract Work

•Material

•Drawings

•Manpower

Page 7: Planning & Managing Ship Repair - sparusa.com

Time-Phasing Ship & Shop Work

Repair

AssembleFabricate

Install

Install

Test

Zone Strip

Out

Page 8: Planning & Managing Ship Repair - sparusa.com

Sequence On-Board Work by Ship

Zone or Area

1. Sequence areas to minimize traffic and enhance

flow of men and materials.

2. Consolidate like-work in an area where applicable.

It saves time and allows workers to be more

productive.

3. Avoid trade (craft) conflicts.

4. Sequence work in logical order, starting from rip-

out & uncover to hot work, outfit, fixtures, and

cleanup.

Page 9: Planning & Managing Ship Repair - sparusa.com

Steel Hot Work

Pipe Work

HVAC Work

Electrical Cables

Linings & Bulkheads

Paint & Deck Covering

Outfit & Furnishings

Fixtures & Breakables

Ship Zone Outfit

Work Type Scheduling

Ceilings & Doors

Maintain Clear AccessAlleys for Men & Materials

Groom & Clean

Scheduling

requires the

proper sequencing

of work and

related project

activities.

Page 10: Planning & Managing Ship Repair - sparusa.com

Schedule work to ensure that

work orders can be started

with all required equipment,

manpower and materials

ready on hand.

Page 11: Planning & Managing Ship Repair - sparusa.com

Sequence & Link Work Packages

To Tests & Trials

Shop - Ship

UpperDeck

Shop - Ship

LowerDeck

Shop - Ship

MainDeck

TESTS

Page 12: Planning & Managing Ship Repair - sparusa.com

Impose Schedule Constraints On

Plan

•Trade Manpower Constraints

•Shop Constraints

•Waterfront Constraints

•Vendor Delivery Constraints

•Technical Data Delivery Constraints

•Other Contract Constraints

Page 13: Planning & Managing Ship Repair - sparusa.com

Execute Plan & Update Plan

•Issue Purchase Orders

•Receive & Palletize Material

•Issue Drawings & Technical Data

•Issue Work Packages

•Execute Work Packages

•Close Out Completed Work

•Update Schedules

Page 14: Planning & Managing Ship Repair - sparusa.com

Time Charge Discipline

Ensure all workers charge their hours to

authorized work orders.

EVERY DAY, WITHOUT EXCEPTION

Time charges may be logged either directly

into PERCEPTION or onto hard copy

time sheets.

Page 15: Planning & Managing Ship Repair - sparusa.com

Ensure all time charges are entered into

PERCEPTION EVERY DAY, WITHOUT

EXCEPTION.

Ensure all time charge errors are corrected

before the end of following day WITHOUT

EXCEPTION.

Page 16: Planning & Managing Ship Repair - sparusa.com

Material Control Discipline

Ensure all contract material is logged

against authorized work orders

WITHOUT EXCEPTION.

Ensure all contract material withdraws

are entered into PERCEPTION EVERY

DAY WITHIOUT EXCEPTION.

Page 17: Planning & Managing Ship Repair - sparusa.com

Manage Change Orders

Establish strict procedures for performing

change orders.

Page 18: Planning & Managing Ship Repair - sparusa.com

Before work begins, ensure for all changes

orders

1. That they are authorized by the ship

owner

2. That work orders have been set up for

time charging and material issues.

3. That schedules have been considered

and integrated within on-going work

to minimize delays and disruptions.

Page 19: Planning & Managing Ship Repair - sparusa.com

PERCEPTION specifically tags

all change orders so that exact

shipyard costs in time and

materials are clearly identified

and that these costs can be

recorded immediately and

without delay.

Page 20: Planning & Managing Ship Repair - sparusa.com

Measure & Report Performance

•Progress Measurement

•Labor Cost Performance & Forecast

•Material Cost Performance & Forecast

•Schedule Impact Analysis

•Resource Requirements Re-Evaluation

•Technical Requirements Re-Evaluation

Page 21: Planning & Managing Ship Repair - sparusa.com

Modify Plan To Work Around

Problems

Re-Schedule For Delays & New

Work

•Alternative Production Methods

•Subcontracted Additional Resources

•Alternative Vendor Selections

•Revised Supervision Plan

•Modified Manpower Requirements

Page 22: Planning & Managing Ship Repair - sparusa.com

Generate Billing Invoices

PERCEPTION can generate billing invoices

at any time.

PERCEPTION records all shipyard contract

costs on a real-time basis:

a) As soon as time charges are entered

b) As soon as material withdraw

transactions are entered.

Page 23: Planning & Managing Ship Repair - sparusa.com

Billing invoices can indicate both actual

labor and material cost transactions as

well as other miscellaneous costs

manually entered.

Invoices can specify milestone payments,

handling charges, mark-ups, taxes,

special service fees, credits, etc.

Page 24: Planning & Managing Ship Repair - sparusa.com

Lessons Learned

•Evaluate Competitive Bid Performance

•Evaluate Schedule Performance

•Evaluate Cost Performance

•Evaluate Quality Of Service

•Evaluate Response To Problems

•Identify Non-Value Work

•Revise Future Bid Strategy

Page 25: Planning & Managing Ship Repair - sparusa.com

PERCEPTION

An integrated shipyard management

system

•Contract Estimating

•Planning & Scheduling

•Labor Work Orders & Time Charge Management

•Purchasing & Inventory Control

•Contract Cost & Schedule Performance Reporting

A Microsoft Windows PC-Based Client/Server System