plant site geotechnical report

366
Plant Site Geotechnical Report Rosemont Copper Project August 2009

Upload: vankhanh

Post on 02-Jan-2017

225 views

Category:

Documents


5 download

TRANSCRIPT

  • Plant Site Geotechnical Report

    Rosemont Copper Project

    August 2009

  • Plant Site Geotechnical Report Rosemont Copper Project

    Prepared for:

    4500 Cherry Creek South Drive, Suite #1040 Denver, Colorado 80246 (303) 300-0138 Fax (303) 300-0135

    Prepared by:

    3031 West Ina Road Tucson, Arizona 85741 (520) 297-7723 Fax (520) 297-7724

    Tetra Tech Project No. 114-320807

    August 2009

  • ROSEMONT COPPER PROJECT

    PLANT SITE GEOTECHNICAL REPORT

    The following document has been prepared by the staff of Tetra Tech under the direct supervision of the ENGINEER of Record, whose seal and signature appear below. The INFORMATION presented herein, were prepared in accordance with generally accepted professional engineering principles and practices.

    Expires 3/31/10

  • Plant Site Geotechnical Report Rosemont Copper Company

    TABLE OF CONTENTS

    1.0 INTRODUCTION AND BACKGROUND........................................................................... 1 1.1 Project Description ................................................................................................ 1 1.2 Scope of Work....................................................................................................... 1

    2.0 GEOTECHNICAL SITE INVESTIGATIONS ..................................................................... 2 2.1 Geotechnical Field Program.................................................................................. 2

    2.1.1 General .................................................................................................................. 2 2.1.2 Geological Mapping ............................................................................................... 2 2.1.3 Boreholes ............................................................................................................... 3 2.1.4 Field Penetration Tests .......................................................................................... 5 2.1.5 Field Hydraulic Testing .......................................................................................... 6 2.1.6 Peizometer Installation........................................................................................... 6 2.1.7 Test Pits ................................................................................................................. 6 2.1.8 Exploration and Condemnation Drilling ................................................................. 6 2.1.9 Geophysical Investigations .................................................................................... 7 2.1.10 Laboratory Testing ................................................................................................. 7 2.1.11 Field Point Load Testing ........................................................................................ 8

    3.0 INVESTIGATION FINDINGS ............................................................................................ 9 3.1 Physiographic Setting and General Geology......................................................... 9 3.2 Field Penetration Testing Results........................................................................ 12 3.3 RQD Results ....................................................................................................... 12 3.4 RMR Results ....................................................................................................... 13 3.5 Geophysical Results............................................................................................ 14

    3.5.1 Seismic Refraction Survey................................................................................... 14 3.5.2 Magnetic Survey .................................................................................................. 15

    3.6 Field Hydraulic Testing Results ........................................................................... 15 3.6.1 Packer Tests ........................................................................................................ 15

    3.7 Laboratory Testing Results.................................................................................. 16 3.8 Plant Site Area .................................................................................................... 16

    3.8.1 Location and Description ..................................................................................... 16 3.8.2 Site Conditions..................................................................................................... 17

    3.9 Primary Access Road.......................................................................................... 18 3.9.1 Location and Description ..................................................................................... 18 3.9.2 Site Conditions..................................................................................................... 18

    4.0 GEOTECHNICAL FOUNDATION RECOMMENDATIONS............................................ 19 4.1 Design Parameters.............................................................................................. 19

    4.1.1 Shear Strength ..................................................................................................... 19 4.1.2 Dynamic Shear Modulus...................................................................................... 20 4.1.3 Dynamic Youngs Modulus .................................................................................. 20

    4.2 Foundation Design .............................................................................................. 21 4.2.1 General ................................................................................................................ 21

    Tetra Tech August 2009 i

  • Plant Site Geotechnical Report Rosemont Copper Company

    4.2.2 Foundation Type .................................................................................................. 24 4.2.3 Foundation Depth ................................................................................................ 24 4.2.4 Foundation Width................................................................................................. 24 4.2.5 Foundation Bearing Materials .............................................................................. 24 4.2.6 Allowable Bearing Capacity ................................................................................. 25 4.2.7 Lateral Resistance for Foundations ..................................................................... 25

    4.3 Settlement Analysis ............................................................................................. 26 4.4 Lateral Earth Pressures....................................................................................... 26 4.5 Coefficient of Subgrade Reaction........................................................................ 26

    5.0 GENERAL RECOMMENDATIONS ................................................................................ 29 5.1 General................................................................................................................ 29 5.2 Excavation........................................................................................................... 29 5.3 Site Grading ........................................................................................................ 29

    5.3.1 Trenches .............................................................................................................. 29 5.3.2 Slopes General ................................................................................................. 30 5.3.3 Slopes Ponds.................................................................................................... 30 5.3.4 Rock Slope Stabilization ...................................................................................... 31 5.3.5 Subgrade Preparation.......................................................................................... 31 5.3.6 Compaction .......................................................................................................... 33 5.3.7 Materials............................................................................................................... 34 5.3.8 Drainage............................................................................................................... 35 5.3.9 Historic Mining Sites ............................................................................................ 35

    5.4 Access Roads ..................................................................................................... 36 5.5 Corrosive Effects on Reinforced Concrete Structures......................................... 36 5.6 Seismic Design Parameters ................................................................................ 37 5.7 Recommendations Prior to Construction............................................................. 39

    6.0 GENERAL INFORMATION ............................................................................................ 40 REFERENCES ........................................................................................................................... 41

    LIST OF TABLES

    Table 2.1 Summary of 2006-2007 Boreholes........................................................................ 4 Table 2.2 Summary of 2008 Boreholes................................................................................. 5 Table 2.3 Laboratory Testing ................................................................................................ 8 Table 3.1 Summary of SPT Testing .................................................................................... 12 Table 3.2 Summary of RQD Measurements ....................................................................... 13 Table 3.3 Summary of RMR Measurements ....................................................................... 14 Table 3.4 Estimated Material Velocities .............................................................................. 15 Table 3.5 Packer Permeability Testing Results................................................................... 16 Table 4.1 Rock Mass Material Parameters ......................................................................... 20 Table 4.2 Summary of Dynamic Youngs Modulus Values.................................................. 20 Table 4.3 Anticipated Facilities............................................................................................ 21

    Tetra Tech August 2009 ii

  • Plant Site Geotechnical Report Rosemont Copper Company

    Table 4.4 Anticipated Facilities............................................................................................ 25 Table 4.5 Lateral Earth Pressures....................................................................................... 26 Table 5.1 Summary of General Slope Recommendations .................................................. 30 Table 5.2 Summary of Pond Slope Recommendations....................................................... 31 Table 5.3 Mat Foundation Over-excavation Recommendations ......................................... 32 Table 5.4 Compaction Recommendations .......................................................................... 34 Table 5.5 General Fill Material Recommendations ............................................................. 34 Table 5.6 Pavement Design Recommendations ................................................................. 36 Table 5.7 Chemical Elements Harmful to Foundations ....................................................... 37 Table 5.8 Corrosion Testing Results ................................................................................... 37 Table 5.9 Simplified Smoothed Pseudo-Acceleration Response Spectra........................... 38

    LIST OF ILLUSTRATIONS

    Illustration 3.1 Simplified Stratigraphic Section (Anzalone, 1995) .............................................. 11 Illustration 4.1 Approximate Interrelationship between CBR, K and Soil Classifications (from ACPA, 1988) 28

    LIST OF FIGURES

    Figure 1 Title Sheet and Project Location Map Figure 2 Legend and General Notes Figure 3 Geologic Descriptions Figure 4 Geology Map Figure 5 Geotechnical Investigation Plan Figure 6 Plant Site Area Figure 7 Seismic Lines SL-2 Geologic Cross Section Figure 8 Seismic Lines SL-6 & SL-7 Geologic Cross Sections Figure 9 Seismic Lines SL-30 Geologic Cross Section Figure 10 Seismic Line SL-5 Geologic Cross Section, Sheet 1 of 2 Figure 11 Seismic Line SL-5 Geologic Cross Section, Sheet 2 of 2 Figure 12 Seismic Line SL-3 Geologic Cross Section, Sheet 1 of 2 Figure 13 Seismic Line SL-3 Geologic Cross Section, Sheet 2 of 2 Figure 14 Seismic Lines SL-4 & SL-31 Geologic Cross Sections Figure 15 Seismic Lines SL-21, SL-20, & SL-19 Geologic Cross Sections

    Tetra Tech August 2009 iii

  • Plant Site Geotechnical Report Rosemont Copper Company

    Tetra Tech August 2009 iv

    LIST OF APPENDICES

    Appendix A Site Photographs Appendix B Boring Logs Appendix B1 Tetra Tech Geotechnical Boring Logs Appendix B2 Historic Anamax and Anaconda Boring Logs Appendix C Tetra Tech Borehole Photos Appendix D Tetra Tech Test Pit Logs Appendix E Tetra Tech Test Pit Photos Appendix F Geophysical Reports Appendix F1 Zonge Geophysical Report Appendix F2 Hydrogeophysics Magnetic Survey Report Appendix G Laboratory Test Results Appendix H Calculations

  • Plant Site Geotechnical Report Rosemont Copper Company

    1.0 INTRODUCTION AND BACKGROUND

    This report presents a summary of geotechnical data and calculations specific to the proposed Plant Site facilities and Primary Access Road for the Rosemont Copper Project (Project) owned by Rosemont Copper Company (Rosemont). The Plant Site facilities consist of administration and warehouse buildings, a crusher, a milling facility, stockpiles, an SX-EW plant, various tanks and storage areas, and additional support buildings/facilities. The calculations presented in this report follow foundation and other design recommendations listed in M3 Engineering and Technology (M3) Foundation Report Technical Specification (Spec 08036-5222, Rev. P3)

    The Project site is located approximately 30 miles southeast of Tucson, west of State Highway 83 (AZ-83) on the east slope of the Santa Rita Mountains in Pima County (Figure 1). In geographical terms, the Rosemont Property location coordinates are approximately 31 50N and 110 45W. Currently, access to the property is from Interstate 10 to AZ-83 south, then west on Forest Road (FR) 231.

    1.1 Project Description The Project will be developed as an open pit mine with a milling and processing plant for approximately 546 million tons (Mt) of sulfide ore, concurrent with copper leaching of approximately 75 Mt of oxide ore, in approximately 20 to 25 years of production. Tailings from the milling process will be dewatered using conventional tailings thickeners and then further dewatered using a filtration process before being transported to a designated dry stack disposal facility. Waste rock quantities of about 1,232 Mt will be generated as part of the mining operation. The production numbers stated are from the 2008 in-fill drilling campaign and vary slightly from the 2007 feasibility study and Mine Plan of Operations.

    Open pit mining techniques will be used to mine and access the ore, including the non-ore/waste materials. Overburden and the waste materials will be transported by haul truck to the Waste Rock Storage Area, the perimeter buttresses, or wherever fill/rock is needed onsite. Sulfide ores will be hauled to a crusher, crushed, and subsequently conveyed to a mill for further processing. As indicated above, tailings generated from the milling process will be placed in a dry stack tailings facility. Thickener underflow slurry will be pumped to the filter plant where moisture content will be reduced from 40 to 50% water by weight to about 15 to 20% moisture. From the filter plant, the tailings will then be transported and placed by conveyor in the tailings storage area.

    1.2 Scope of Work In August of 2006, Rosemont (a subsidiary of Augusta Resource Corporation) authorized Tetra Tech (previously known as Vector Arizona) to complete a geotechnical investigation on patented claims and fee lands in support of feasibility-level designs of a Heap Leach Pad and associated ponds, Dry Stack Tailings Facilities, Plant Site facilities, a Waste Rock Storage Area, and various water management facilities. In March of 2008, the Coronado National Forest (CNF) granted approval to complete an additional geotechnical investigation by Tetra Tech and a hydrogeological investigation by Errol L. Montgomery & Associates, Inc. on forest service land.

    The Geotechnical Study Report issued by Tetra Tech in 2007 (Tetra Tech, 2007b) summarized results from the 2006-2007 geotechnical investigation. The Geotechnical Addendum report issued by Tetra Tech in 2009 (Tetra Tech, 2009) presented findings from both the 2006-2007 and 2008 geotechnical investigations. This report presents a summary of geotechnical data specific to the Plant Site Facilities and Primary Access Road from both investigations.

    Tetra Tech August 2009 1

  • Plant Site Geotechnical Report Rosemont Copper Company

    2.0 GEOTECHNICAL SITE INVESTIGATIONS

    Figure 1 shows the general location of the Rosemont Project and Figure 2 provides general nomenclature associated with the geotechnical investigation program. Figure 3 provides a detailed description of each geologic unit shown on the subsequent figures. The geology of the entire Project site is shown on Figure 4, and an overview of the site investigation work is shown on Figure 5. Figure 6 illustrates the location of several geological/geotechnical cross sections generated in the Plant Site area. The Plant Site facility layouts presented in Figure 6 are based on Drawing File 000-CI-007 Rev No. P4 provided by M3 on June 16th, 2009. Cross section profiles in Figures 7 through 15 are based on facility pad limits and elevations contained in Drawing Files 000-CI-008 to 000-CI-010 Rev P2 provided by M3 on July 20th, 2009. The geotechnical information presented on the figures includes data collected from both the 2006 and 2008 investigations.

    2.1 Geotechnical Field Program

    2.1.1 General Initial geotechnical site investigations were conducted between November 2006 and March 2007. This initial site investigation included borehole drilling, test pit excavations, surface geology mapping, field penetration and hydraulic testing, geotechnical logging of boreholes, seismic refraction surveys, and laboratory testing of selected samples. A total of ten (10) boreholes, 33 test pits, and 18 miles of seismic refraction lines were conducted during this initial phase of the work. The boreholes and test pits were confined to the limits of private land (patented claims and fee lands) while the seismic refraction survey was conducted on both private and forest service land.

    From May 2008 through July of 2008, Tetra Tech conducted a second geotechnical investigation that included borehole drilling, field penetration and hydraulic testing, geotechnical logging of boreholes, peizometer installations, magnetic surveys, and laboratory testing of selected samples. A total of 19 boreholes were completed at 15 drill sites located on forest service land. Due to the restricted amount of ground disturbance allowed on the forest service land, 13 of the 15 drill sites were located along existing dirt roads. Two (2) new access roads were constructed in order to reach drill sites located within the Plant Site area and the footprint of the proposed Primary Crusher.

    Appendix A presents photographs of existing conditions at the Plant Site area taken during site investigations.

    2.1.2 Geological Mapping The base geological map for the Project area (Figure 4) was derived from a study completed by the Arizona Geological Survey (Johnson and Ferguson, 2006). Geological data in peripheral areas was obtained from published mapping completed by the United States Geological Survey (Drewes, 1971 and Drewes, 2002). Fieldwork implemented by Tetra Tech included mapping of bedrock outcrops and the extent of surficial materials within the Plant Site and Heap Leach areas. Mapping completed by Tetra Tech personnel and consultants included: identifying rock types, delineating the extent of geologic contacts, and mapping structural orientations of the bedrock and faults. The resulting geology map is presented on Figure 4. The descriptions for each geologic unit shown on this map are presented on Figure 3.

    A detailed discussion of the regional site seismicity is contained in the Geologic Hazards Assessment (Tetra Tech, June 2007a).

    Tetra Tech August 2009 2

  • Plant Site Geotechnical Report Rosemont Copper Company

    2.1.3 Boreholes Both surficial materials and rock materials recovered during the drilling process were logged geotechnically using a combination of the Unified Soil Classification System (USCS) for soils and the United States Bureau of Reclamation (USBR) field manual for rock. Borehole logs consist of a geotechnical description of the material, measurements of total recovery, Standard Penetration Tests (SPT), and the Rock Quality Designation (RQD). Geotechnical descriptions contain standard notations for rock and soil types; strength or relative density (in the case of granular soils), the spacing of fractures, and the condition of the fractures (planarity, roughness, and nature of infill and wall alteration).

    2.1.3.1 2006-2007 Investigation (Private Land) In the 2006-2007 geotechnical investigation, a total of 877 feet from ten (10) boreholes were drilled throughout the entire Project site (Figure 5). As shown on Figure 6, one (1) borehole (VABA-07-01) was drilled within the Plant Site area, northeast of the Coarse Ore Stockpile. One (1) borehole (VABH-06-07) was drilled north of the proposed alignment of the Primary Access Road (Figure 5).

    All of the boreholes were drilled with a CME-75HD truck mounted rig. Surficial materials were drilled using hollow stem augers. Once bedrock was encountered, NQ3 wireline coring techniques were implemented. The boreholes drilled during the 2006-2007 drilling program are summarized in Table 2.1. Logs and photographs of the soil/core samples for boreholes completed within or adjacent to the Plant Site area and Primary Access Road are presented in Appendix B1 and Appendix C, respectively. Borehole data collected for the other facilities, such as the Dry Stack Tailings, Waste Rock Storage Area, and Heap Leach Pad can be found in the Geotechnical Addendum Report (Tetra Tech, 2009).

    Tetra Tech August 2009 3

  • Plant Site Geotechnical Report Rosemont Copper Company

    Table 2.1 Summary of 2006-2007 Boreholes

    Borehole No.

    Completion Depth (ft)

    Depth to Bedrock (ft) Location Description Facility Area

    VABH-06-01 102.2 At surface Top of small hill north of Rosemont Ranch. Dry Stack Tailings

    VABH-06-02 101 85 Floodplain of wash south of Rosemont Ranch Waste Rock Storage Area

    VABH-06-03 156 27 Floodplain of wash at Rosemont Junction Dry Stack Tailings

    VABH-06-04 166.5 45 In small drainage near corrals at Rosemont Ranch Heap Leach

    VABH-06-05 20 Not encountered In small drainage (14 feet from VABH-06-04) Heap Leach

    VABH-06-06 50 Not encountered Floodplain of wash near white tank at Rosemont Ranch Waste Rock Storage Area

    VABH-06-07 81 40 Along dirt road at Hidden Valley Ranch North of Primary

    Access Road

    VABH-06-08 56 At surface Western side of proposed pit Potential Quarry Site

    VABH-06-09 46 At surface Northeastern side of proposed pit Potential Quarry

    Site VABH-07-01 99 At surface Along hillside Plant Site

    2.1.3.2 2008 Investigation (Forest Service Land) In the 2008 geotechnical investigation, a total of 827 feet from 19 boreholes were drilled throughout the entire Project site (Figure 5.) As shown on Figure 6, four (4) of the boreholes (TTBH-08-02, TTBH-08-09, TTBH-08-10, and TTBH-08-15) were drilled within or adjacent to the Plant Site area. One (1) borehole (TTBH-08-03) was drilling along the proposed alignment of the Primary Access Road (Figure 5).

    All 19 boreholes were completed using CME-75HD track and truck mounted rigs. Overburden materials were drilled using hollow stem augers in all but three (3) of the boreholes. Those holes were drilled using an air hammer method called TUBEX due to the presence of large boulders and cobbles within the Gila Conglomerate located within the Waste Rock Storage Area. NQ3 wireline coring techniques were used to collect samples of bedrock in all boreholes. The 2008 drilling program is summarized in Table 2.2. Logs and photographs of the soil/core samples for boreholes completed within or adjacent to the Plant Site area and Primary Access Road are presented in Appendix B1 and Appendix C, respectively. Borehole data collected for the other facilities, such as the Dry Stack Tailings, Waste Rock Storage Area, and Heap Leach Pad can be found in the Geotechnical Addendum Report (Tetra Tech, 2009).

    Tetra Tech August 2009 4

  • Plant Site Geotechnical Report Rosemont Copper Company

    Table 2.2 Summary of 2008 Boreholes

    Borehole No. Completion Depth (ft) Depth to

    Bedrock (ft) Location

    Description Facility Area

    TTBH-08-01 115.5 Not encountered Top of hill East of Dry Stack

    Tailings TTBH-08-02 198.5 29.5 Along hillside Plant Site

    TTBH-08-03 126.5 9.0 In saddle Primary Access Road

    TTBH-08-04 101 Not encountered Top of ridge Waste Rock Storage

    Area

    TTBH-08-05 39 Not encountered Top of ridge Waste Rock Storage

    Area

    TTBH-08-05A 115 Not encountered Top of ridge Waste Rock Storage

    Area TTBH-08-06 122 49.5 Top of ridge Dry Stack Tailings

    TTBH-08-07 123 15.3 In wash East of Dry Stack Tailings TTBH-08-08 123.3 13 In wash Dry Stack Tailings

    TTBH-08-08A 14 14 In wash Dry Stack Tailings

    TTBH-08-08B 15 15 In wash Dry Stack Tailings

    TTBH-08-08C 14.7 14.7 In wash Dry Stack Tailings

    TTBH-08-09 97 24.5 In wash Plant Site / Dry Stack Tailings TTBH-08-10 123 14 In wash Plant Site

    TTBH-08-11 123.5 54 In wash Dry Stack Tailings

    TTBH-08-12 123.5 14.5 Side of ridge Dry Stack Tailings

    TTBH-08-13 113.5 Not encountered Top of ridge Waste Rock Storage

    Area

    TTBH-08-14 110.25 Not encountered Top of ridge Waste Rock Storage

    Area TTBH-08-15 200.75 At surface Top of hill Plant Site

    2.1.4 Field Penetration Tests Standard Penetration Tests (SPT) were conducted for soils that were encountered within the boreholes. The SPTs were performed using either a Modified California Sampler (2 inch ID) or a Split Spoon Sampler (1.5 inch ID) and a 140 pound hammer. Samples obtained during the testing were logged using USCS methods, and selected samples were sent to a laboratory for further analyses. Blow counts obtained from the SPT testing were corrected to SPT N-values using published correlations. Corrected blow counts are presented and discussed in Section 3.7.

    Tetra Tech August 2009 5

  • Plant Site Geotechnical Report Rosemont Copper Company

    2.1.5 Field Hydraulic Testing During the 2006-2007 site investigation, packer testing was performed in five (5) bedrock zones within three (3) boreholes. Falling head tests were also conducted in unconsolidated alluvium materials in two (2) boreholes. However, none of the packer or falling head tests completed in 2006-2007 were located in boreholes within the Plant Site area.

    During the 2008 site investigation, packer testing was performed in eight (8) bedrock zones within four (4) boreholes. Falling head tests were conducted in unconsolidated alluvium materials in four (4) boreholes. Packer testing was completed in only two (2) of the boreholes within the Plant Site area.

    The packer tests conducted at the site are essentially constant head permeability tests used to estimate the hydraulic conductivity of the bedrock. After the test zone was isolated using two (2) inflatable packers, water was injected at a constant pressure into a pipe which transmitted the water through the packer and into the open borehole. Hydraulic conductivity was then computed using the test pressure, steady flow rate, and geometric information (e.g. hole radius, length of test interval, etc.). Packer testing results are discussed in Section 3.7 and shown on the applicable borehole logs in Appendix B1.

    Hydraulic conductivities of overburden or unsaturated media were estimated from falling head test data. Falling head tests were conducted by filling the borehole with water and measuring the change in water level over time. The hydraulic conductivity was then calculated using the Field Permeability Test Methods with Applications to Solution Mining by Woodward-Clyde Consultants (August 1977). Since falling head testing was not completed within the Plant Site area, results of the testing can be found in the Geotechnical Addendum Report (Tetra Tech, 2009).

    2.1.6 Peizometer Installation During the 2008 site investigation, one (1) borehole (TTBH-08-08C) was completed as a piezometer. This borehole is located on the upstream side of a small concrete check dam within McCleary Canyon. The piezometer was installed within the alluvium material above bedrock and was screened between 9.7 to 14.7 feet. This piezometer is located within the footprint of the Dry Stack Tailings Facility. Thus, additional information regarding the piezometer can be found in the Tetra Tech Geotechnical Addendum Report published in February of 2009. All other holes where abandoned according the Arizona Department of Water Resources (ADWR) methods.

    2.1.7 Test Pits In 2006-2007, a total of 33 test pits were excavated using a John Deere 200C LC track hoe. As shown on Figure 6, six (6) of the 33 test pits were completed within the Plant Site area and stratigraphic logs for these test pits are included in Appendix D. A representative photograph for each of these test pits are provided in Appendix E. When the test pits were completed, samples from selected locations where sent for laboratory testing to obtain material properties for use in design analyses. No test pits were completed during the 2008 site investigation and no test pits where completed along the Primary Access Road.

    2.1.8 Exploration and Condemnation Drilling Over 70 exploration/condemnation holes drilled by Rosemont and previous owners were used by Tetra Tech to determine lithologic units. The original hand written logs were transcribed into gINT (a geo-data management and reporting program) by Tetra Tech. Twenty-two of the exploration/condemnation holes were located within the Plant Site area (Figure 6) or near the

    Tetra Tech August 2009 6

  • Plant Site Geotechnical Report Rosemont Copper Company

    proposed alignment of the Primary Access Road (Figure 5). Only the transcribed logs for these 22 boreholes are provided in Appendix B2.

    2.1.9 Geophysical Investigations A total of 31 seismic refraction profiles encompassing 18 miles were completed across the Project site in December 2006 through January 2007 by Zonge Geosciences, Inc. using refraction tomography methods. The seismic refraction profiles were created in designated areas to determine the substratum morphology in the proposed facility locations. Six (6) shear wave sounding locations were completed using refraction microtremeter methods. These soundings were completed within low-lying drainages in order to complete a liquefaction analysis. Figure 5 illustrates the location for all of the seismic refraction lines and shear wave soundings collected at the Project site. Figure 6 shows the locations of the seismic refraction lines and shear wave soundings completed within the Plant Site area. Appendix F1 contains a portion of the final report and results produced by Zonge for the geophysical investigation. Only data relevant to the Plant Site area is included in Appendix F1.

    The geophysical data was incorporated into the geologic/geotechnical cross sections provided on Figures 7 through 15. Section 3.6 summarizes the overall results of the geophysical investigation findings.

    Ten (10) magnetic profiles totaling approximately 40,000 feet were conducted across the Plant Site in October of 2008 by Hydrogeophysics, Inc (HGI). The purpose of this study was to better define the geologic contacts occurring within the area. The two (2) magnometers used to conduct the survey included both a Geometrics G-856 and a G-858. The G-856 magnometer functioned as the base station, while the G-858 was used as a roving magnometer to collect the magnetic data. The roving magnometer was transported along ten (10) parallel lines spaced approximately 265 feet apart from each other. Detailed maps of the magnetic survey layout, profiles, and analysis produced by HGI are included in Appendix F2.

    2.1.10 Laboratory Testing The laboratory testing program was comprised of determining the grain size distribution, Atterberg limits, modified Proctor, and shear strength of select samples. The testing was conducted to analyze the suitability of on-site soil and rock as foundation materials and in slope cuts and fills. Testing was generally performed according to American Society for Testing and Materials (ASTM) standards. Soil samples from selected test pits and boreholes were taken to the Physical Resource Engineering (PRE) Lab in Tucson, Arizona for standard index testing. Soil samples that underwent direct shear testing were sent either to the University of Arizona Geotechnical Lab in Tucson, Arizona or Kleinfelder in Tempe, Arizona. A summary table and copies of laboratory testing results from samples collected throughout the entire Project site are included in Appendix G. Further analyses and discussion of the results is provided in Section 3.8.

    The results from the sieve analyses and Atterberg Limits were used to classify each material type according to the Unified Soil Classification System. Modified (ASTM D1557) Proctor tests were performed to determine the optimum moisture content and corresponding maximum dry unit weight of selected samples.

    Selected pieces of rock core samples were collected and sent to Call and Nicholas, Inc. in Tucson, Arizona or Advanced Terra Testing in Lakewood, Colorado for uniaxial compression strength and point load testing. A summary table showing borehole ID, depth within the hole, and test type is included in Appendix G. This summary table provides data collected from all of the boreholes competed throughout the entire Project site.

    Tetra Tech August 2009 7

  • Plant Site Geotechnical Report Rosemont Copper Company

    Table 2.3 summarizes the tests that were conducted for both the soil and rock samples.

    Table 2.3 Laboratory Testing

    Test Name Test Method Gradation ASTM D6913 & D422

    Minus 200 Sieve ASTM D1140 Atterberg Limits ASTM D4318

    Natural Moisture Content & Dry Density ASTM D2216 & D2937

    Modified Proctor (Compaction) ASTM D1557 Standard Proctor (Compaction) ASTM D698B

    Direct Shear (3 points) ASTM D3080 Unconfined Compressive Strength ASTM D7012

    Point Load Test ASTM D5731

    2.1.11 Field Point Load Testing During the 2006-2007 site investigation, point load testing from select core samples was conducted in the field by Tetra Tech. The testing was completed using a hydrologic point load tester rented from Call and Nicholas, Inc. A summary table showing borehole ID, depth within the hole, and test results is provided in Appendix G. Uniaxial compression strength was calculated for each point load test using International Society for Rock Mechanics (ISRM) methods. The calculation methods and results are also provided in Appendix G.

    Tetra Tech August 2009 8

  • Plant Site Geotechnical Report Rosemont Copper Company

    3.0 INVESTIGATION FINDINGS

    3.1 Physiographic Setting and General Geology The Project site lies within the southern portion of the Basin and Range physiographic province, an extensional terrain characterized by discontinuous northwest to northeast-trending mountain ranges separated by broad, thick, fault-controlled alluvial basins. This region can be subdivided into the Sonoran Desert sub-province and Mexican Highland sub-province. Located in western and south-central Arizona, the Sonoran Desert sub-province is generally defined by low mountain ranges and broad, mostly undissected valleys. The Mexican Highland sub-province of southeastern Arizona and southwestern New Mexico is characterized by greater average altitudes, local relief, and basin dissection. The southern portion of the Basin and Range physiographic province is separated from the Colorado Plateau by the Transitional zone, which is characterized by rugged relief, variably dissected alluvial basins, large mountain ranges, and plateau remnants. Located in the Mexican Highland sub-province, the Rosemont Project is situated in the northern portion of the Santa Rita Range, near the boundary separating the two (2) sub-provinces (Menges and Pearthree, 1989).

    The Santa Rita Range and its northern continuation, the Empire Mountains, represent an easterly to southeasterly tilted, south-southwest elongated, structural horst, which extends from Pantano Wash south to Sonoita Creek. Its western boundary is coincident with the Santa Rita Fault, a north to northeast trending normal fault zone. The Santa Rita Fault has juxtaposed Tertiary and Quaternary sediments of the Santa Cruz River Basin in its western hanging wall against Precambrian to Mesozoic units of its eastern structural footwall. This structural horst can be subdivided into three (3) structural domains: the Southern Santa Rita Range, Northern Santa Rita Range, and Empire Mountains. Located south of the northwest trending Sawmill Canyon Fault Zone, the Southern Santa Rita Range is primarily underlain by a complex assemblage of Mesozoic sediments and volcanics cut by large Mesozoic stocks, which are unconformably overlain by Tertiary volcanics. North of the Sawmill Canyon Fault zone, the Precambrian Continental Granodiorite is unconformably overlain by a steep, east dipping succession of Paleozoic marine sediments, which are normally unconformably overlain by late Jurassic to early Cretaceous sediments of the Bisbee Group. The Bisbee Group is a thick (>2,500 meters) succession of dominantly non-marine clastic sediments, which occupies a series of extensional fault-bounded basins throughout much of southeastern Arizona (Dickinson, 1989). A similar easterly dipping section of Paleozoic and Mesozoic sediments is exposed in the Empire Mountains, which is separated from the northern end of the Santa Rita Range by a moderately southeast tilted, complexly faulted assemblage of rhyolitic volcanics and related sediments, exposed in the late Cretaceous Mount Fagan Caldera.

    The Rosemont Project area is underlain by a north striking, steep, easterly tilted section of Cambrian to Permian miogeosynclinal marine sediments (quartzite, limestone, and dolomite). Recent evaluation of core derived from historic exploration programs at Rosemont suggests that the Bisbee Group structurally overlies the Paleozoic section within the upper plate of an east dipping, low angle fault zone. At this locality, Mesozoic sediments of the Bisbee Group include the Glance Conglomerate, Willow Canyon Formation, and the Apache Canyon Formation. The Glance Conglomerate is composed of a limestone-pebble conglomerate. It is stratigraphically overlain by a thick, monotonous succession of arkosic (feldspathic) sandstone and conglomerate of the Willow Canyon Formation. Arkosic clastics of the Willow Canyon Formation grade upward into the Apache Canyon Formation, a shale and silty mudstone dominated sequence containing subordinate amounts of interbedded dark-gray, thin-bedded, micritic limestone and sandstone.

    Tetra Tech August 2009 9

  • Plant Site Geotechnical Report Rosemont Copper Company

    The northeastern portion of the Rosemont Project area lies within the Mount Fagan Caldera, a complexly faulted, late Cretaceous dominantly rhyolitic volcanic center, which was subsequently tilted 30 to 50 degrees to the southeast by late Tertiary Basin and Range extensional tectonism. A dissected alluvial fan, exposed along the eastern flank of the Santa Rita Range, is characterized by a gently, southeast tilted sequence of Miocene to Pliocene sands and gravels of the Gila Conglomerate. The Gila Conglomerate unconformably overlies Mesozoic sediments and volcanics of the Bisbee Group and Mount Fagan Caldera in the southeastern portion of the Rosemont Project area.

    Emplacement of Laramide quartz latite porphyry stocks (~56 million years) resulted in the development of large zones of copper-bearing skarn, which host the mineral resource at Rosemont as well as several other smaller occurrences within the Rosemont-Helvetia mining district. Tectonic history of this region includes at least two (2) periods of extensional (late Jurassic to early Cretaceous and late Tertiary) deformation and one (1) period of compressional (late Cretaceous to early Eocene) deformation, which have resulted in the districts complex structural setting.

    A simplified stratigraphic section of the Precambrian through early Cretaceous strata at Rosemont (Anzalone, 1995) is shown in Illustration 3.1. Please note that not all of the geologic formations present at the Rosemont site are listed in this simplified stratigraphic section.

    Tetra Tech August 2009 10

  • Plant Site Geotechnical Report Rosemont Copper Company

    Illustration 3.1 Simplified Stratigraphic Section (Anzalone, 1995)

    Tetra Tech August 2009 11

  • Plant Site Geotechnical Report Rosemont Copper Company

    3.2 Field Penetration Testing Results Within or adjacent to the Plant Site area and the proposed alignment of the Primary Access Road, the four (4) major overburden materials present include topsoil, colluvium, younger alluvium, and older alluvium. SPTs were performed using a Modified California Sampler (2 inch ID) or a Split Spoon Sampler and 140 pound hammer. Blow counts generated from the testing were corrected to SPT N-values using published correlations. Table 3.1 presents the approximate depths to dense and very dense material as indicated by SPT N-values. As shown in the table, dense to very dense materials were encountered in the boreholes. Additionally, the SPT sampling indicates that very dense materials occur at depths ranging from 5 to 25 feet below ground surface (bgs).

    Table 3.1 Summary of SPT Testing

    Borehole No. Depth to Medium

    Dense (ft) SPT N 10 - 30

    Depth to Dense (ft)

    SPT N 30 - 50

    Depth to Very Dense (ft)

    N >50 Facility Area

    VABH-06-07 - 5 25 North of Primary Access Road TTBH-08-02 - - 10 Plant Site

    TTBH-08-03 - - 5 Primary Access Road

    TTBH-08-09 - 5 10 Plant Site / Dry Stack Tailings TTBH-08-10 - 5 10 Plant Site

    3.3 RQD Results Rock Quality Designation (RQD) was measured and calculated by Tetra Tech for rock core derived from all boreholes in which rock coring was completed. RQD (%) values were calculated by summing the length of core greater than or equal to four (4) inches and then dividing by the total core run length. RQD values represent rock conditions and the physical characteristics of the rock mass. They are also helpful in determining the strength, deformation, and permeability of the rock. Table 3.2 summarizes the average, maximum, and minimum RQD values determined for borehole locations within or adjacent to the Plant Site area and the proposed alignment of the Primary Access Road. An RQD equal to zero (0) indicates that all of the rock core segments were less than four (4) inches for the entire run. RQD value for each core run is provided in the borehole logs in Appendix B.1.

    Tetra Tech August 2009 12

  • Plant Site Geotechnical Report Rosemont Copper Company

    Table 3.2 Summary of RQD Measurements

    Borehole No.

    Average RDQ (%)

    Maximum RQD (%)

    Minimum RQD (%)

    Geologic Formation Facility Area

    VABH-06-07 65 95 17 Mount Fagan North of Primary Access

    Road VABH-07-01 20 55 0 TTBH-08-02 24 72 0

    Willow Canyon Plant Site

    TTBH-08-03 57 100 0 Mount Fagan Primary Access Road

    TTBH-08-09 13 37 0 Plant Site / Dry Stack Tailings TTBH-08-10 66 98 0 TTBH-08-15 4 43 0

    Willow Canyon

    Plant Site

    The bedrock present within the Plant Site area includes an andesite flow unit and sedimentary rocks from the Willow Canyon Formation. The average RQD values for the Willow Canyon sedimentary rocks in this area ranged from 4% to 66%. RQD values for the andesite are not currently available since none of the completed boreholes intersected the unit. The bedrock present along the proposed alignment of the Primary Access Road includes the andesite flow unit and sedimentary rocks from the Willow Canyon Formation and the Mount Fagan Group. The average RQD values for the Mount Fagan Group in this area ranged from 57% to 65%.

    3.4 RMR Results The quality of the rock mass was characterized via geotechnical logging of the core samples and scanline mapping of outcrops. International Society for Rock Mechanics (ISRM) recommendations aided in the characterization. Relevant properties such as hardness, weathering, degree of breakage, joint condition, and RQD were recorded. These parameters were used to determine the rock mass rating (RMR) developed by Bieniawski (1989). This classification system considers five (5) parameters related to the intact rock condition and rock mass quality and allocates a rating for each of the parameters. These ratings are summed to obtain an RMR value. Detailed calculations for the RMR values are presented in Appendix H.

    The parameters used are:

    Strength of intact rock (uniaxial compressive strength and/or point load testing);

    Drill core quality, RQD;

    Spacing of discontinuities;

    Condition of discontinuities (persistence, aperture, roughness, infilling, and weathering); and

    Groundwater condition.

    Tetra Tech August 2009 13

  • Plant Site Geotechnical Report Rosemont Copper Company

    Bieniawskis (1989) rock mass quality is broken into five (5) groups based on the sum of the indices. The ratings for each group can facilitate the comparison of the rock conditions between boreholes or at different depths. The five (5) groups are:

    Very Poor Rock: RMR < 21

    Poor Rock: RMR 21 40

    Fair Rock: RMR 41 60

    Good Rock: RMR 61 80

    Very Good Rock: RMR > 80

    The average, maximum, and minimum RMR values for applicable boreholes are presented Table 3.3. RMR values for the Mount Fagan Group and sedimentary rocks from the Willow Canyon Formation were obtained from the logged core samples. A RMR value for the andesite present within the Plant Site area was obtained from scanline mapping of outcrops and was calculated to be 47. The average RMR results for the Mount Fagan Group ranged from 58 to 62 and the Willow Canyon sedimentary rocks ranged from 22 to 48.

    Table 3.3 Summary of RMR Measurements

    Borehole No.

    Average RMR

    Maximum RMR

    Minimum RMR

    Geologic Formation Facility Area

    VABH-06-07 62 72 48 Mount Fagan North of Primary Access

    Road VABH-07-01 48 56 43 TTBH-08-02 22 42 0

    Willow Canyon Plant Site

    TTBH-08-03 58 72 47 Mount Fagan Primary Access Road

    TTBH-08-09 41 47 36 Plant Site / Dry Stack Tailings TTBH-08-10 45 56 30 TTBH-08-15 37 47 29

    Willow Canyon

    Plant Site

    3.5 Geophysical Results

    3.5.1 Seismic Refraction Survey Velocities from the refraction data were correlated to material types by Tetra Tech using boreholes and test pits located on or near the seismic lines. Table 3.4 lists the estimated velocity values for general material types found on-site. The rippability of rock can also vary according to the size and type of excavation equipment being used. For velocities greater than or equal to 9,000 ft/sec, blasting may be required or a Caterpillar Multi or Single Shank No. 9 Ripper may be able to excavate the rock material (Caterpillar Performance Handbook, 2004). These material velocities were also incorporated into the geologic/geotechnical cross sections provided on Figures 7 through 15.

    Tetra Tech August 2009 14

  • Plant Site Geotechnical Report Rosemont Copper Company

    Table 3.4 Estimated Material Velocities

    Velocity (ft/sec) Material Type 0 3,000 Soil (unconsolidated material)

    3,000 6,000 Cemented soil / soft rock 6,000 9,000 Bedrock (rippable)

    > 9,000 Bedrock (non-rippable)

    3.5.2 Magnetic Survey A magnetic survey of the Plant Site area was conducted in order to delineate the contact of the andesitic flow unit. The survey consisted of ten (10) parallel magnetic profiles approximately 4,000 feet long, spaced approximately 265 feet apart. The results of the magnetic survey are presented in a technical memorandum from Hydrogeophysics in Appendix F2. In this memorandum, the ten (10) magnetic profiles are shown in a series of graphical plots displaying the magnetic field relative to the geographical location. Additionally, a contour plot was generated from the magnetic data to illustrate the change in magnetic fields across the Plant Site area.

    The findings indicate that the andesite does not have a significant contrast relative to the adjacent arkosic sedimentary rocks. An estimation of the andesite boundary was determined by small deviations in the data and is sketched on the contour plot provided in Appendix F2. The contour plot also indicates a widespread magnetic low along the western portion of the site, while the eastern portion is characterized by a widespread magnetic high. This may be a result of a change in soil types across the area or a stronger magnetic anomaly at depth. Six (6) magnetic targets were identified at shallow depths ranging from 50 to 75 feet bgs. These targets are shown on the contour plot. The surface geology at each target was examined to assess the lithologic characteristics of these anomalies. However, no apparent correlation was found between them.

    3.6 Field Hydraulic Testing Results

    3.6.1 Packer Tests Double packer testing was performed in each of the major geologic formations found throughout the Project site. Packer testing was initially scheduled for TTBH-08-09 rather than TTBH-08-15. However, the core barrel became lodged within hole TTBH-08-09, thus preventing packer testing. Table 3.5 summarizes the packer testing results for the boreholes within or adjacent to the Plant Site area. In-situ permeability testing in the Plant Site area was conducted in the sedimentary rocks within the Willow Canyon Formation and ranged in depth from 61.5 to 187.6 feet bgs. The permeability of the sedimentary rocks within this area ranged from no recordable flow to 10-7 feet/second (ft/s).

    Tetra Tech August 2009 15

  • Plant Site Geotechnical Report Rosemont Copper Company

    Table 3.5 Packer Permeability Testing Results

    Borehole No. Testing Interval (ft) Estimated

    Permeability (ft/s) Rock Type Geologic

    Formation

    61.5 71.6 No Flow * Conglomerate TTBH-08-10

    91.5 101.6 9.69E-07 ** Sandstone and Conglomerate TTBH-08-15 177.5 187.6 1.66E-08 Arkosic Sandstone

    Willow Canyon

    * Flow was less than 1 gallon per hour during packer testing. ** Artesian flow of 0.5 gpm observed before and during packer testing.

    3.7 Laboratory Testing Results Gradations and Atterberg limits were performed on soil samples collected from boreholes and test pits. Test results were used to classify each material type according to the Unified Soil Classification System. In general, the four (4) major overburden materials present within or adjacent to the Plant Site area and the proposed alignment of the Primary Access Road include topsoil, colluvium, younger alluvium, and older alluvium. The topsoil, if present, was generally classified as sandy clay with gravel to silty sand. The colluvium encountered contained mostly sands and gravels with varying amount of silts and clay. The younger alluvium (Holocene) occurs mostly in the major low-lying drainages and floodplains while the older alluvium (Pleistocene) is exposed in upland drainages. The younger alluvium is generally classified as sand within the active drainages and as a sand with silt, gravel, and trace cobbles within the floodplains. The older alluvium was not encountered in any of the competed boreholes. However, published geologic descriptions of the unit describe it as a sandy gravel with trace amounts of boulders.

    Natural dry density and moisture content tests were performed on younger alluvium derived from within the footprint of the Waste Rock Storage and Dry Stack Tailings Facilities. These tests were also preformed on the highly weathered sedimentary rocks of the Willow Canyon Formation derived from within the Plant Site area. These materials also underwent direct shear testing in order to evaluate in-situ shear strength parameters.

    Unconfined compressive and point load tests were performed on competent rock core samples. The average uniaxial compressive strength (UCS) values for materials derived from the Mount Fagan Group and sedimentary rocks from the Willow Canyon Formation where found to be 5,614 and 2,918 pounds per square inch (psi), respectively. These average values were calculated using USC test results from boreholes throughout the Project site.

    All of the above mentioned test results are provided in Appendix G and on applicable borehole logs in Appendix B1.

    3.8 Plant Site Area

    3.8.1 Location and Description The proposed Plant Site area is located northeast of the Open Pit and directly west of the North Dry Stack Tailings Facility (Figure 6). The Mine Truck Shop is located on the southern portion of the Plant Site area and directly west of the Process Water (PW) Pond. The Primary Crusher is located south of the Truck Shop on the eastern edge of the Open Pit. These facilities are

    Tetra Tech August 2009 16

  • Plant Site Geotechnical Report Rosemont Copper Company

    located within the McCleary and Wasp Canyon drainages. Groundwater elevations within the area range from approximately 4,900 to 5,100 feet above mean sea level (amsl).

    3.8.2 Site Conditions A total of five (5) geotechnical borings, five (5) test pits, three (3) miles of seismic refraction surveys, and 4,000 feet of magnetic surveys were completed within or adjacent to the Plant Site area. The geology in the area is illustrated on Figure 6. As shown on the figure, the majority of the facilities are underlain by the Willow Canyon Formation. The Willow Canyon Formation is characterized as an arkosic (feldspathic) sandstone and argillaceous sandstone, with equal to subordinate amounts of vuggy, silty mudstone. Additionally, an interval of volcaniclastic pebble-cobble conglomerate is present below the sequence of andesitic lava flows. As shown on Figure 6, a few facilities are located on the andesite flow and the older and younger alluvium. The delineation of the andesite in this area was refined by field mapping and magnetic survey results.

    Five (5) boreholes (VABH-07-01, TTBH-08-02, TTBH-08-09, TTBH-08-10, and TTBH-08-15) were completed within or adjacent to the Plant Site area. Borehole VABH-07-01 is located on a hillside approximately 150 feet west of the proposed Coarse Ore Stockpile. The Willow Canyon Formation encountered in VABH-07-01 was a moderately to highly weathered tuffaceous siltstone with an average RMR of 48. Borehole TTBH-08-02 is located on a hillside approximately 150 feet west of the proposed Mill Building. The Willow Canyon Formation encountered in TTBH-08-02 was a moderately weathered to decomposed arkosic sandstone and conglomerate with an average RMR of 22. Borehole TTBH-08-09 is located within the McCleary Canyon drainage approximately 170 feet north of the Settling Basin. The Willow Canyon Formation encountered in TTBH-08-09 was a slightly to moderately weathered arkosic sandstone with an average RMR of 41. Borehole TTBH-08-10 is located within the McCleary Canyon drainage 1,070 feet northeast of the Change House. The Willow Canyon Formation encountered in TTBH-08-10 was an unweathered to slightly weathered sandstone and conglomerate with an average RMR of 45. During drilling of TTBH-08-10, an artesian flow rate of 0.5 gpm was encountered, thus reducing the average RMR from 59 to 45. Borehole TTBH-08-15 is located on a hilltop 150 feet north of the Primary Crusher. The Willow Canyon Formation encountered in TTBH-08-15 was moderately weathered with slightly weathered to decomposed zones. The rock type ranged from an arkosic to a quartz sandstone and had an average RMR of 37.

    The depth to bedrock within the Plant Site area is estimated to range from less than one (1) foot to 30 feet. The topsoil, if present, ranged from one (1) to three (3) feet thick in test pits completed throughout the entire Project site and Plant Site area. Colluvium was encountered at depths ranging from eight (8) to 50 feet across the entire Project site and eight (8) feet within the Plant Site area. The younger alluvium ranged in depth from 14 to 54 feet across the entire Project site and 15 to 25 feet within the Plant Site area. Although the older alluvium has not be encountered in any of the completed boreholes, seismic refraction data indicate the depth may range from 10 to 25 feet within the Plant Site area.

    Several geological/geotechnical cross sections were developed through the Plant Site (Figure 6) and are provided on Figures 7 through 15. The cross sections show the interpreted subsurface geology, SPT values, measured velocities from the seismic survey, and facility pad elevations proposed by M3. As shown on the geologic cross sections presented on Figures 7 through 15, three (3) of the proposed facility pads intercept non-rippable rock. These facilities include the Concentrate Thickeners (Figure 9), the Reclaim Conveyor (Figure 10), and the Truck Shop (Figure 14). Additionally, the edge of the access road north of the Concentrate Filtration Plant (Figure 8) is

    Tetra Tech August 2009 17

  • Plant Site Geotechnical Report Rosemont Copper Company

    within a few feet of non-rippable rock. Due to the variable nature of rock, it is unknown if other facility pads located between seismic lines will encounter non-rippable rock.

    3.9 Primary Access Road

    3.9.1 Location and Description The Primary Access Road will provide access to the Project site from AZ-83. It is located north of the Dry Stack Tailings Facility as shown on Figure 4. Groundwater elevations along the roads alignment range from approximately 4,400 to 5,100 feet amsl.

    3.9.2 Site Conditions One (1) geotechnical boring is located along the alignment of the Primary Access Road and one (1) boring is located 1,650 feet north of the road (Figure 5). Seismic refraction (SL-30) was completed along the centerline of the original alignment of the Primary Access Road. The new alignment of the road is shown on Figure 5 and is about 500 to 2,600 feet south of the seismic survey. The Primary Access Road is mostly underlain by the Mount Fagan Group. The Mount Fagan Group contains sedimentary breccias with subordinate amounts of volcaniclastic siltstone and sandstone and a crystal rich to lithic tuff. As the Primary Access Road nears the Plant Site area, the road is underlain by the Willow Canyon Formation. As previously mentioned, the Willow Canyon Formation is characterized as an arkosic (feldspathic) sandstone and argillaceous sandstone, with equal to subordinate amounts of vuggy, silty mudstone. Additionally, an interval of volcaniclastic pebble-cobble conglomerate is present below the sequence of andesitic lava flows.

    Borehole TTBH-08-03, completed along the alignment of the Primary Access Road, contained eight (8) feet of colluvium prior to encountering bedrock consisting of the Mount Fagan Group. At this borehole, the Mount Fagan Group was an unweathered to slightly weathered volcaniclastic sandstone/conglomerate and a crystal rich to lithic tuff. The average RMR value for the borehole was 58. Borehole VABH-06-07, completed 1,650 feet north of the alignment of the Primary Access Road, contained 40 feet of alluvium prior to encountering bedrock from the Mount Fagan Group. At this borehole, the Mount Fagan Group was an unweathered to slightly weathered sedimentary breccia with an average RMR of 62.

    The geological/geotechnical cross section generated through small segments of the Primary Access Road near the Plant Site area is shown on Figures 8 and 9. The cross section illustrates the interpreted subsurface geology and measured velocities from the seismic survey. The depth to non-rippable rock along the alignment of the seismic survey completed north of the roads current alignment ranged from zero to 70 feet bgs.

    Tetra Tech August 2009 18

  • Plant Site Geotechnical Report Rosemont Copper Company

    4.0 GEOTECHNICAL FOUNDATION RECOMMENDATIONS

    The geotechnical recommendations discussed in this section are based on the borings drilled, the subsurface conditions observed, the results of laboratory and field testing, and Tetra Techs experience in the area. The observations made and the samples collected for testing are believed to be representative of the Plant Site area. However, soil and geologic conditions can vary significantly between borings. These variations may not become evident until additional exploration or excavation is performed. If the subsurface conditions are different from what is described in this report, the changed conditions should be evaluated by the geotechnical engineer and designs adjusted or alternate designs selected.

    4.1 Design Parameters The following design parameters are provided to aid in the design of the Plant Site facilities.

    4.1.1 Shear Strength Rock mass shear strength parameters were obtained following the Hoek & Brown (1980) failure criteria. These parameters were adapted to account for the condition of fracturing within the rock mass. The shear strength calculations were performed using RocLab v.1.021 software by Rocscience, Inc.

    The results of direct shear tests preformed on highly weathered sandstone/conglomerate of the Willow Canyon Formation were used in the design calculations presented in the following sections. The RocLab strength estimation method was correlated with laboratory testing on two (2) samples of remolded Willow Canyon Formation material. One (1) sample was tested at drop-density (uncompacted) to simulate in-situ poor-quality Willow Canyon Formation. The other sample was remolded and tested at 95% of its maximum dry density at optimum moisture content to give an indication of the strength of reworked foundation materials in the Plant Site area. Both tests showed similar results.

    Laboratory and in-situ testing and classification results were used to calculate the geotechnical parameters needed for the bearing capacity and settlement calculations. Tests from boreholes located within the sedimentary rocks of the Willow Canyon Formation (VABH-07-01, TTBH-08-02, TTBH-08-09, TTBH-08-10, and TTBH-08-15) were used due to their proximity to the Plant Site facilities. The field and in-situ test results utilized in the design calculations include: RQD, RMR, and SPT. Laboratory tests include: UCS (unconfined compressive strength), point load, Youngs Modulus, and Poissons ratio.

    Table 4.1 presents the rock material properties used in the calculations. The Modulus of Deformation was derived from the Serafim and Pereira method detailed in the U.S. Army Corps of Engineer (USACE) Rock Foundation Engineering Manual (EM 1110-1-2908, 1994) and is based on the rocks RMR. The Serafim and Pereira method correlated well with average laboratory values of Youngs Modulus and was slightly more conservative. Due to the highly fractured nature of the rock, cohesion was neglected.

    Tetra Tech August 2009 19

  • Plant Site Geotechnical Report Rosemont Copper Company

    Table 4.1 Rock Mass Material Parameters

    Geologic Formation/ Rock Type

    Density,

    (lb/ft3)

    UCS (psi)

    RMR

    Modulus of Deformation,

    Ed (psi)

    Shear Modulus

    Gm (psi)

    Poissons Ratio,

    Angle of Internal Friction,

    (deg)

    Willow Canyon Formation Sedimentary Rocks 157 3,560 22 4.35 x 10

    5 4.60 x 105 0.205 31.3

    4.1.2 Dynamic Shear Modulus The dynamic shear modulus was evaluated from the static shear modulus considering the dynamic value is two (2) to three (3) times greater than the static modulus. Therefore, the dynamic shear modulus for foundations located on bedrock should be 9.20 x 105 to 1.38 x 106.

    4.1.3 Dynamic Youngs Modulus The dynamic Youngs Modulus (also known as the dynamic compression modulus) was calculated from shear wave velocities measured during the geophysical investigation of the Project site, average unit weights determined from laboratory testing, and Poissons ratio. Poissons ratio for the Willow Canyon sedimentary rocks selected for use in calculating the dynamic Youngs Modulus was determined to be an average of two (2) laboratory test values (0.268 and 0.209). A third laboratory test value (0.139) was not used in the calculation of the average as it was deemed too low and not representative of the observed bedrock materials.

    It is important to note that calculated modulus values are based on site-wide geotechnical/geophysical data available and limited geotechnical laboratory testing on samples of the Willow Canyon formation. More accurate values of the dynamic Youngs modulus will require site-specific geotechnical/ geophysical investigations and laboratory testing. Table 4.2 summarizes the estimated values of the dynamic Youngs Modulus for various material types. Detailed calculations are provided in Appendix H.

    Table 4.2 Summary of Dynamic Youngs Modulus Values

    Materials Dynamic Youngs Modulus, E (psi)

    Unconsolidated Sediments 8.19E03 Cemented Sediments 1.68E05

    Weathered/Fractured Bedrock (Willow Canyon sedimentary rocks)

    1.02E06

    Competent Bedrock (Willow Canyon sedimentary rocks)

    2.18E06

    Based on the results of the geotechnical field investigation (including geophysical surveys), we anticipate the subgrade below the mill and crusher will consist of weathered Willow Canyon sedimentary bedrock. We recommend using a dynamic modulus of 1.02E06 psi for the design

    Tetra Tech August 2009 20

  • Plant Site Geotechnical Report Rosemont Copper Company

    of these facilities. If bedrock conditions are found to be different than those anticipated, Tetra Tech should be notified so that the estimate for the Dymanic Youngs modulus can be revised.

    4.2 Foundation Design

    4.2.1 General Foundation design recommendations for the proposed facilities in the Plant Site area are based on the subsurface conditions observed, field and laboratory test results, engineering analysis, and Tetra Techs experience in the area.

    The proposed Rosemont Plant Site includes numerous facilities, including administration and warehouse buildings, a crusher, a milling facility, stockpiles, an SX-EW plant, various tanks and storage areas, and additional support buildings/facilities. Table 4.3 summarizes the proposed facilities, including existing grade, proposed grade, resultant maximum cut, and the range of anticipated bearing pressures provided by M3 on September 22, 2008.

    Table 4.3 Anticipated Facilities

    Facility1

    Proposed Pad

    Elevation1 (feet)

    Max Existing

    Elevation2 (feet)

    Maximum Cut

    (feet)

    Anticipated Max Bearing

    Pressure3 (psf)

    Explosives Magazine 5,470 5,500 30 2,000 - 4,000

    Primary Crusher 5,050 5,095 45 10,000 - 12,000

    Mill Building if on rock 10,000 - 12,000

    Mill Building if not on rock

    5,025 5,070 45 4,000 - 8,000

    Pebble Crushing Facility 5,090 5,105 15 2,000 - 4,000

    Flotation Building 5,035 5,056 21 2,000 - 4,000

    Concentrate Thickeners 4,980 5,035 55 2,000 - 4,000

    Concentrate Filter Plant 5,040 5,083 43 2,000 - 4,000

    Concentrate Storage and Loadout Building 5,020 5,030 10 2,000 - 4,000

    Solvent Extraction 5,070 5,080 10 2,000 - 4,000

    Solvent Extraction Tank Farm 5,005 5,020 15 2,000 - 6,000

    Electrowinning 5,037 5,050 13 2,000 - 4,000

    Tailings Thickeners 4,959 4,990 31 2,000 - 6,000

    Tailings Filter Plant 4,980 5,040 60 2,000 - 4,000

    Fresh / Fire Water Tank 5,185 5,190 5 2,000 - 4,000

    Tetra Tech August 2009 21

  • Plant Site Geotechnical Report Rosemont Copper Company

    Tetra Tech August 2009 22

    Facility1

    Proposed Pad

    Elevation1 (feet)

    Max Existing

    Elevation2 (feet)

    Maximum Cut

    (feet)

    Anticipated Max Bearing

    Pressure3 (psf)

    Main Electric Substation 5,110 5,140 30 2,000 - 4,000

    Acid Storage 5,027 5,034 7 2,000 - 4,000

    Reagent Building 5,020 5,060 40 2,000 - 4,000

    Admin. Building 4,980 5,000 20 2,000 - 4,000

    Change House 4,987 5,030 43 2,000 - 4,000

    Warehouse 4,995 5,005 10 2,000 - 4,000

    Mine Truck Shop 5,020 5,080 60 2,000 - 4,000

    Truck Wash 5,020 5,074 54 2,000 - 4,000

    Light Vehicle Fuel Station 5,029 5,030 1 2,000 - 4,000

    Laboratory 5,090 5,103 13 2,000 - 4,000

    Guard Shack and Truck Scale 5,000 5,020 20 2,000 - 4,000

    Notes: 1) Proposed facility names and pad elevations were obtained from Drawing Files 000-CI-008, 000-CI-009, and

    000-CI-010 (Rev No. P2) provided by M3 on July 20, 2009.

    2) Existing ground elevations were obtained from the Rosemont Copper Project 2 and 10 AutoCAD topographic map dated April 24, 2009 (produced by Cooper Aerial). The elevations listed in Table 4.3 correspond to the highest elevation within each area. Please note that the figures provided in this report are based on the Cooper Aerial AutoCAD topographic map published in August of 2006. Therefore, some conflicts may exist between the elevations listed in Table 4.3 and the figures.

    3) Anticipated Maximum Bearing Pressures were provided by M3 in an e-mail dated September 22, 2008.

    It should be noted that only general ranges of anticipated bearing pressures for the various facilities were provided and that no total or differential settlement tolerances were provided for any of the facilities.

    It is anticipated that the subgrade for the majority of the proposed facilities will consist of competent to decomposed sedimentary rocks of the Willow Canyon Formation. Some facilities (most notably the tailings thickener tanks) straddle the geologic contact between the sedimentary rocks and the andesite flow unit within the Willow Canyon Formation. Tetra Tech has advised M3 and Rosemont of the benefit to relocating the facilities so they do not straddle geologic contacts. This will reduce the likelihood of any differential settlement negatively impacting the facilities. Recommendations for additional geotechnical work is presented in Section 5.7.

    A preliminary groundwater contour map generated by Errol. L. Montgomery and Associates indicates that the groundwater level within the area of the proposed Plant Site is at an approximate elevation between 4,900 to 5,100 feet amsl. Some of the proposed pad elevations indicated in Table 4.3 are within this elevation range. Therefore, it is anticipated that

  • Plant Site Geotechnical Report Rosemont Copper Company

    groundwater may be encountered during excavation and that dewatering of the excavations during construction may be required. Pad and foundation perimeter drains should be designed as needed to collect and convey groundwater away from the facilities. Due to the nature of the site geology, some field engineering may be necessary during construction to properly control groundwater.

    For the recommendations presented herein, foundation conditions are assumed to be drained (as recommended in Section 5.3.8) with a groundwater table located below the base of the footing. If foundation conditions are different than described, Tetra Tech should be notified so that appropriate adjustments can be made to the calculations and recommendations.

    Tetra Tech August 2009 23

  • Plant Site Geotechnical Report Rosemont Copper Company

    4.2.2 Foundation Type The proposed facilities may be constructed on conventional shallow foundations consisting of continuous and/or spread footings (if required) with slab-on-grade floors. Several of the structures, including the mill, thickeners, crusher, and the solvent extraction tank farm should be constructed on mat foundations. Liquid storage tanks should be constructed on mat foundation systems.

    Tetra Tech anticipates that the mill and crusher will be subject to vibrating loads. The loads produced by grinding mills are generally considered a mixed load, a combination of impact and rotation. Vibratory equipment may be constructed on shallow, isolated mat-type foundation systems. Sufficient foundation mass should be provided to control vibration and resonance. The following considerations should be taken in the design of these facilities:

    Resonance conditions shall be avoided;

    Vibrating amplitudes shall be tolerable by personnel;

    Vibrating amplitudes shall not interfere with the correct operation of the machinery; and

    Damage to adjacent structures shall be avoided.

    Foundations bearing on deep, unconsolidated sediments should be designed in accordance with Site Class D requirements of the International Building Code (2006). Foundations constructed in areas where the depth to bedrock is less than 40 feet should be designed in accordance with Site Class C requirements. Foundations bearing on hard, unweathered, competent bedrock should be designed in accordance with Site Class B requirements.

    4.2.3 Foundation Depth Pima County indicates (Appendix H) that for elevations greater than 4,000 feet amsl, the frost depth should be considered to be 24 inches. Therefore, foundations should bear at least two (2) feet below the lowest adjacent grade for frost protection. Mat foundations for vibratory equipment may need to be constructed with greater embedment to control vibration and resonance. If the foundation consists of hard, competent bedrock, and at the discretion of the geotechnical engineer, the foundation bearing depth may be decreased to one (1) foot below finished pad grade.

    Foundation over-excavation may be required for foundations bearing on unconsolidated sediments as discussed in Section 5.3.5.

    4.2.4 Foundation Width Spread footings should have a minimum width of 18 inches.

    4.2.5 Foundation Bearing Materials Shallow foundation systems should bear on a minimum of one (1) foot of properly compacted structural fill. Additional over-excavation and structural fill requirements are provided in Section 5.3.5.

    We recommend placing a minimum of four (4) inches of properly compacted base course below concrete slabs to provide a firm, stable subgrade, promote even curing of the concrete, and aid in the drainage of groundwater away from the foundation (see drainage recommendations in Section 5.3.8). The base course may be considered part of the recommended structural fill below the slabs.

    Tetra Tech August 2009 24

  • Plant Site Geotechnical Report Rosemont Copper Company

    4.2.6 Allowable Bearing Capacity Conventional shallow foundation systems bearing on a properly prepared subgrade (as discussed in Section 5.3.5) may be designed for the allowable bearing capacities summarized in Table 4.4. Detailed calculations for the allowable bearing capacity are provided in Appendix H.

    Table 4.4 Anticipated Facilities

    Load Type Load, P

    Minimum Footing Dimension Range,

    B* (ft)

    Allowable Bearing Capacity

    (psf) Wall/Continuous P7.5 k/ft B2.5 2,500 Wall/Continuous 7.54.25 3,500

    Column/Spot P25 k B3 2,500 Column/Spot 25

  • Plant Site Geotechnical Report Rosemont Copper Company

    Lateral resistance for foundations is controlled by the sliding resistance between the foundation and the subgrade soil. A friction value of 0.40 may be used in the design of foundations bearing on properly compacted structural fill and/or competent bedrock.

    4.3 Settlement Analysis Based on the conventional, shallow foundation systems bearing on a properly prepared subgrade and designed as recommended in this report, the maximum total settlement is anticipated to be less than inch and differential settlement is anticipated to be less than inch. Settlement should consist of deformation of the bedrock due to dead loads and will likely occur during construction.

    4.4 Lateral Earth Pressures Table 4.5 provides the equivalent fluid weights for the design of earth retaining walls or below grade structures. The equivalent fluid weights for backfill materials are based on laboratory test data. The active condition is when the wall moves away from the soil, and the passive condition is when the wall moves into the soil. The at-rest condition is when the wall does not move. Detailed calculations for the lateral earth pressures are provided in Appendix H.

    Table 4.5 Lateral Earth Pressures

    Condition Equivalent Fluid Weight, On-site

    Granular Soil (pcf) Active 40

    Passive 270 At-Rest 60

    The active and at-rest conditions provided in the table should be increased by ten (10) pounds per cubic foot (pcf) and the passive condition decreased by ten (10) pcf for seismic design. This assumes a horizontal ground acceleration of 0.11g which represents a two (2) percent probability of exceedance in a 50-year period.

    It should be recognized that the above values account for the lateral earth pressures due to soil and level backfill conditions and do not account for hydrostatic pressures. Lateral loading should be increased to account for surcharge loading if structures are placed above the wall and are within a horizontal distance equal to the height of the wall.

    Care should be taken to prevent percolation of surface water into the backfill material adjacent to the walls. The risk of hydrostatic build-up can be reduced by placing subdrains behind the walls consisting of free-draining gravel wrapped in a filter fabric (Mirafi 140N or equivalent). In addition, weep holes may be provided every ten (10) feet at the base of walls to assist in the drainage of water.

    4.5 Coefficient of Subgrade Reaction The coefficient of subgrade reaction, also known as the modulus of subgrade reaction or subgrade modulus, is the relationship between settlement and bearing pressure. It is used for non-rigid methods of mat foundation analysis. Confidence in this number should be tempered by

    Tetra Tech August 2009 26

  • Plant Site Geotechnical Report Rosemont Copper Company

    the fact that the modulus is dependent on all of the following, not all of which are possible to take into account in the calculations (Coduto, 2001).

    Width of the loaded area;

    Shape of the loaded area;

    Depth of the loaded area below ground surface;

    Position of the load; and

    Time.

    Tetra Tech estimated the subgrade modulus of overburden soils using a relationship developed by the American Concrete Pavement Association (ACPA) (1988) which correlates subgrade CBR values to the subject modulus (see Illustration 4.1).

    Based on the results of laboratory testing, the average CBR for overburden soils is approximately 14 percent. For a rigid pavement supported by a properly compacted subgrade, a modulus of approximately 225 pounds per cubic inch (pci) may be used. Estimates of the modulus of additional materials may be determined from Illustration 4.1.

    Tetra Tech August 2009 27

  • Plant Site Geotechnical Report Rosemont Copper Company

    Illustration 4.1 Approximate Interrelationship between CBR, K and Soil Classifications (from ACPA, 1988)

    Tetra Tech August 2009 28

  • Plant Site Geotechnical Report Rosemont Copper Company

    5.0 GENERAL RECOMMENDATIONS

    5.1 General This section lists general recommendations for the following design aspects:

    Excavation;

    Site grading and subgrade preparation;

    Drainage;

    Retaining structure design parameters;

    Seismic design parameters; and

    Corrosion resistance.

    5.2 Excavation Foundation construction will involve excavations in both soil and rock. Excavation of the on-site soils and weathered bedrock may be accomplished with conventional excavation equipment. Excavations that extend into hard, competent bedrock will likely require the use of heavy-duty excavation equipment and possibly blasting.

    Based on the grading plan provided by M3, the proposed building pad elevations range from approximately 4,960 to 5,185 feet amsl. Based on the geophysical data obtained for the underlying rock, the elevations for non-rippable rock varied from 4,970 to 5,100 feet amsl throughout the Plant Site area (Appendix F1). From the geologic cross sections presented on Figures 7 through 15, three (3) of the proposed facility pads intercept non-rippable rock. These facilities include the Concentrate Thickeners (Figure 9), the Reclaim Conveyor (Figure 10), and the Truck Shop (Figure 14). Additionally, the edge of the access road north of the Concentrate Filtration Plant (Figure 8) is within a few feet of non-rippable rock. Due to the variable nature of rock, it is unknown if other facility pads located between seismic lines will encounter non-rippable rock.

    5.3 Site Grading Tetra Tech should review the final grading plan prior to construction to verify that the recommendations provided in this report are applicable to the proposed grading.

    Groundwater encountered during site grading should be managed by the contractor, using grading, pumping, and other best management practices. Water should not be allowed to accumulate in excavations or along slopes. The presence of water will greatly decrease the stability of excavations and slopes. If this condition exists, the geotechnical engineer should be contacted to provide additional slope grading/stabilization recommendations.

    5.3.1 Trenches In accordance with Occupational Safety and Health Administration (OSHA) standards, rock comprised of the Willow Canyon Formation encountered within the proposed Plant Site area is generally soft rock and would be categorized as a Type B soil. The overburden or alluvium material is typically a granular soil containing sand and gravel and would be categorized as a Type C soil. Rippable rock encountered at depths ranging from 20 to 50 feet bgs in the Plant Site area would be classified as Stable Rock. Trench excavation should follow the recommendations provided in the OSHA Technical Manual, Section V, Chapter 2.

    Tetra Tech August 2009 29

  • Plant Site Geotechnical Report Rosemont Copper Company

    5.3.2 Slopes General Permanent slopes should be designed by an engineer licensed in the state of Arizona. The recommendations for permanent slopes provided in this section are preliminary and are provided to aid in the development of final slope designs.

    Table 5.1 summarizes general recommendations for the construction of slopes at the Plant Site, based on Tetra Techs observations and experience. Slopes may be constructed to heights greater than the maximum individual slope height provided the slope does not exceed two (2) times the maximum individual slope height and a bench is provided at mid-height of the total slope. Water should not be allowed to pond on the benches and the benches should be graded to direct water away from slope faces. If saturation of the slope occurs, the factor of safety of the slope will decrease and may result in slope failure. Tetra Tech recommends implementing strict surface water management practices.

    Table 5.1 Summary of General Slope Recommendations

    Slope Type Material

    Temporary Slopes

    Permanent Slopes

    Maximum Individual

    Slope Height (ft)

    Bench Required Between

    Slopes (ft) Cut On-site Soil 1.25H:1V 1.5H:1V 20 10 Cut On-site Soil 1.25H:1V 2H:1V 40 10 Cut Soft Rock 1H:1V 1.25H:1V 35 10 Cut Competent, Stable Rock Vertical 0.5H:1V 45 10 Fill Approved Grading Fill 1.25H:1V 1.5H:1V 20 10 Fill Approved Grading Fill 1.25H:1V 2H:1V 40 10

    These values are considered to be preliminary and should be re-evaluated in the field when the excavations are carried out, taking into account the safety of the personnel involved. A qualified geotechnical engineer should be retained to design all temporary and permanent slopes. Slopes steeper than those recommended in Table 5.1 will generally require shoring or other methods of stabilization. Bedrock joint and/or fracture orientation in the slopes may require shallower slope angles. Benches should be provided as required if the slope height exceeds 20 feet. Fill slopes should be constructed by overbuilding and then cutting back to the desired slope.

    If water is encountered in excavations, proper dewatering measures should be implemented and flatter slopes should be used. Tetra Tech should be contacted to provide additional recommendations if this condition is encountered.

    Buildings and load bearing structures should be set-back from the crest of a slope a distance equal to or greater than the total height of the slope; however, the set-back need not exceed 40 feet. Building set-back from the toe of a slope should be at least the total height of the slope or a maximum distance of 15 feet.

    5.3.3 Slopes Ponds Permanent slopes should be designed by an engineer licensed in the state of Arizona. The recommendations for slopes provided in this section are preliminary and are provided to aid in the development of final slope designs.

    Tetra Tech August 2009 30

  • Plant Site Geotechnical Report Rosemont Copper Company

    Table 5.2 summarizes general recommendations for the construction of slopes for geosynthetically-lined ponds at the Plant Site, based on Tetra Techs observations and experience.

    Table 5.2 Summary of Pond Slope Recommendations

    Slope Type Material Slope Maximum Slope Height (ft) Cut On-Site Soil 2H:1V 40 Cut Soft Rock 2H:1V 35 Cut Competent, Stable Rock 2H:1V 45 Fill Approved Grading Fill 2H:1V 40

    Pond liner system stability should be evaluated on a site-specific and design-specific basis. The recommendations herein are general and do not apply to pond liners that will receive soil or other protective covers, will be trafficked with equipment, or be subjected to any type of loading other than hydrostatic.

    Fill slopes should be constructed by overbuilding and then cutting back to the desired slope.

    5.3.4 Rock Slope Stabilization For weathered and fractured bedrock, there is some potential for localized instability. In such cases, careful inspection during excavation is recommended in order to detect unstable zones and as a result, localized stabilization may be required. Methods of stabilization may include the following, either singly or in combination:

    scaling of loose material from the exposed surface;

    rock bolting;

    wire mesh placement;

    shotcreting; and

    construction of intermediate benches.

    5.3.5 Subgrade Preparation Prior to placing fill in a building pad, foundation, engineered slope, roadway, or parking areas, vegetation and soil containing roots and organics should be removed. In addition, any undocumented fill, loose soils, and deleterious/organic materials should be removed. Subsequent to grubbing, the exposed subgrade should be scarified to a depth of at least eight (8) inches, properly moisture conditioned, and compacted to meet the recommendations provided in Section 5.3.6. At the discretion of the geotechnical engineer, scarification and compaction of the subgrade is