PORTFOLIO COMMITTEE ON BASIC EDUCATION Presentation on: Provincial Infrastructure Programme ASIDI & SAFE 1

Upload: others

Post on 01-May-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

PORTFOLIO COMMITTEE ON BASIC EDUCATION

Presentation on:Provincial Infrastructure

ProgrammeASIDI & SAFE

1

Page 2: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

PRESENTATION OUTLINE

• Purpose

• National Development Plan

• Background

• Provincial Infrastructure Programme

• ASIDI

• SAFE

2

Page 3: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

PURPOSE

To present a progress report onInfrastructure planning anddelivery as well as SAFE to thePortfolio Committee on BasicEducation.

3

Page 4: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

NATIONAL DEVELOPMENT PLAN

“Ensure that all schools meetminimum standards forinfrastructure and commit toprogressively upgrading eachschool’s infrastructure to meetoptimum standards.”

National Planning Commission: National Development Plan, November 2011)

4

Page 5: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

NATIONAL DEVELOPMENT PLAN…

“School infrastructure backlogs have been considerablyreduced over the past 10 years. But many schoolenvironments are still not conducive to learning.The Department of Basic Education has committed itself toeradicating 496 inappropriate structures, providing basicwater to 1 257 schools, providing basic sanitation to 868schools and providing electricity to 878 schools in the2012/13 financial year. To meet these commitments, thedepartment will have to:• Find ways to deliver infrastructure and services moreefficiently and cost-effectively

• Improve the quality of information used for planning.”

National Planning Commission: National Development Plan, November 2011)

5

Page 6: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

NATIONAL DEVELOPMENT PLAN…

“Take learner safety intoaccount when planninginfrastructure.”

National Planning Commission: National Development Plan, November 2011)

6

Page 7: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

BACKGROUND• The sector provides infrastructure through three programmes; viz, the provincial

programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) aswell as the Sanitation Appropriate for Education initiative (SAFE)

• The Provincial Schools Build Programme is implemented by provinces and ittargets the provision of basic services, new schools, additions to existing schools,new and upgrading of services and maintenance. It is funded through theEducation Infrastructure Grant and the Provincial contribution through theequitable share.

• The Accelerated School Infrastructure Delivery Initiative is a programme driven bythe DBE to address school's infrastructure backlog on schools that do not meet thebasic safety norms and standards. It is funded through the Schools InfrastructureBacklogs Grant. The purpose of the programme is for the eradication of schoolsmade entirely of inappropriate structures and the provision of basic level ofwater, sanitation and electricity to schools.

• The Sanitation Appropriate for Education initiative (SAFE) is a programme driven bythe DBE to eradicate all pit latrines and other forms of unacceptable sanitation,provide safe and appropriate ablution facilities as well as address insufficient orinadequate sanitation facilities and maintenance of all ablution facilities

7

Page 8: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

KEY AREAS• Construction, maintenance, upgrading and rehabilitation of new and

existing infrastructure in education including district and circuit

accommodation;

• Provide infrastructure to match curriculum requirements;

• Replace inappropriate schools;

• Provision of basic services;

• Address damage to infrastructure caused by natural disasters;

• Extend existing schools with additional classrooms/facilities;

• Address achievement of the targets set out in the minimum norms and

standards for school infrastructure; and

• Enhance capacity to deliver infrastructure in education.

8

Page 9: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

TOTAL INFRASTRUCTURE BUDGET – 2019/20 FY

EIG

73.8%

ES

12%

SIBG

14.2%

EIG, R 10.514 bn

ES, R 1.713 bn

SIBG, R 2.027 bn

Total Budget = R 14. 255bn

EIG = Education Infrastructure GrantES = Equitable ShareSIBG = Schools Infrastructure Backlog Grant

9

Page 10: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

10

PROVINCIAL

INFRASTRUCTURE

PROGRAMME

Page 11: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

2019 EIG MTEF ALLOCATIONSProvinces Allocation MTEF Estimates

2019/20 2020/21 2021/22

R'000 R'000 R'000

Eastern Cape 1 585 532 1 564 208 1 685 128

Free State 833 485 722 425 778 272

Gauteng 1 474 715 1 440 169 1 551 501

KwaZulu-Natal 2 187 162 2 013 405 2 169 050

Limpopo 1 050 160 1 175 467 1 266 336

Mpumalanga 731 792 819 111 882 432

Northern Cape 639 817 505 649 544 738

North West 902 484 1 010 169 1 088 260

Western Cape 1 109 331 1 031 186 1 110 902

Unallocated - 1 184 844 1 250 010

Total 10 514 478 11 466 632 12 326 629

11

Page 12: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

INFRASTRUCTURE ALLOCATIONS 2019/20

12

Provinces EIG Equitable Share Total% of equitable share

to total budget

Eastern Cape 1,585,532 0 1,585,532 0%

Free State 833,485 16,378 849,863 1.9%

Gauteng 1,474,715 474,821 1,949,536 24.4%

KwaZulu-Natal 2,187,162 359,210 2,546,372 14.1%

Limpopo 1,050,160 1,826 1,051,986 0.2%

Mpumalanga 731,792 202,727 934,519 21.7%

North West 902,484 2,228 904,712 0.2%

Northern Cape 639,817 7,720 647,537 1.2%

Western Cape 1,109,331 648,843 1,758,174 36.9%

10,514,478 1,713,753 12,228,231

Page 13: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

TARGETS FOR THE 2019/20 FY

13

No. PROGRAMME

Target 2019/20

EC FS GP KZN LP MP NC NW WC

1 Full Service Schools 0 0 0 1 1 0 0 5 0

2 Provision/replacement of Sanitation 178 73 13 150 13 85 14 12 14

3 Provision/upgrade of Water 178 10 13 150 22 3 9 10 14

4 Provision/upgrade of Electricity 5 10 13 100 1 1 11 0 14

5 Maintenance Projects 20 27 40 370 34 29 36 48 173

6 Libraries Project 5 1 13 12 2 3 4 7 0

7 Laboratories Projects 5 4 13 12 0 1 8 7 0

8 School Halls 0 1 13 0 2 0 5 7 0

9 Technical Workshops 0 0 0 0 0 0 2 0 0

10 Nutrition Centres 5 7 13 10 9 3 5 5 15

11 Additional Classrooms 285 39 350 210 22 104 43 26 68

12 Grade R Classrooms 13 18 200 50 23 3 8 10 73

13 Administration Blocks 5 4 13 10 3 5 4 7 15

14 Provision/upgrade of fence 302 9 13 40 0 1 15 5 15

15 Provision/upgrade of sport field 0 0 13 9 1 3 5 8 15

16 Special Schools 0 0 1 2 0 1 0 0 0

17 Boarding Schools 0 0 0 2 19 0 0 0 018 Guard House 0 0 13 9 4 1 0 7 019 Natural Disasters Projects 2 0 0 150 0 0 0 0 0

Page 14: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

NEW & REPLACEMENT SCHOOLS –5 YEAR PERIOD

14

PROVINCE

FINANCIAL YEARS

TOTAL2019/20 2020/21 2021/22 2022/23 2023/24

Eastern Cape 0 1 5 3 0 9

Free State 6 3 2 4 2 17

Gauteng 7 8 7 6 6 34

KwaZulu-Natal 7 5 1 0 0 13

Limpopo 12 4 14 9 11 50

Mpumalanga 2 6 7 5 2 22

Northern Cape 3 2 11 3 5 24

North West 14 3 11 12 1 41

Western Cape 13 7 10 10 10 50

ASIDI 40 31 29 0 0 100

TOTAL 104 70 97 52 37 376

Page 15: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

OVERALL INFRASTRUCTURE EXPENDITURE – SEPTEMBER 2019

15

Total Infrastructure Spending as at end September 2019

PROVINCE

Allocated Budget

2019/20

('000)

Total Spent as at

end September

2019 ('000)

% Spent of

Allocated Budget

Eastern Cape 1,585,532 876,882 55%

Free State 849,863 337,569 40%

Gauteng 1,949,536 476,773 24%

KwaZulu-Natal 2,546,372 1,281,619 50%

Limpopo 1,051,986 254,945 24%

Mpumalanga 934,519 545,389 58%

North West 904,712 183,984 20%

Northern Cape 647,537 263,316 41%

Western Cape 1,758,174 781,989 44%

TOTAL 12 228 231 5 002 466 41%

Page 16: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

EDUCATION INFRASTRUCTURE GRANT SEPTEMBER 2019

16

Education Infrastructure Grant Expenditure as at end September 2019

PROVINCE

Allocated Budget

2019/20

('000)

EIG Transfers to

PEDs

('000)

Total Spent as at

end September

2019 ('000)

% Spent of

the

transferred

Amount

% Spent of

Allocated

Budget

Eastern Cape 1,585,532 990,958 876,668 88% 55%

Free State 833,485 520,928 330,546 63% 40%

Gauteng 1,474,715 921,697 428,981 47% 29%

KwaZulu-Natal 2,187,162 1,367,157 1,164,205 85% 53%

Limpopo 1,050,160 656,350 254,937 39% 24%

Mpumalanga 731,792 457,370 504,643 110% 69%

North West 902,484 564,052 183,139 32% 20%

Northern Cape 639,817 399,886 260,064 65% 41%

Western Cape 1,109,331 693,332 453,018 65% 41%

TOTAL 10 514 478 6 571 730 4 456 201 68% 42%

Page 17: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

MAINTENANCE – SEPTEMBER 2019

17

Prov No. of

Maint’nce

Projects in

2019/20 FY

Overall

Adjusted

Infrastructure

Budget

('000)

Maint’nce

Budget

('000)

%ge

Maint’nce

Budget to

Total

Total

Expenditure as

at end

September

2019

('000)

%ge

Expenditure

on Maint’nce

Relative to

Maint’nce

Budget

Eastern Cape 454 R 1,585,532 R 255,716 16% R 130,786 51%

Free State 27 R 849,863 R 158,668 19% R 39,540 25%

Gauteng 144 R 1,949,536 R 1,083,137 56% R 240,909 22%

KwaZulu-Natal 445 R 2,546,372 R 944,228 37% R 304,308 32%

Limpopo 119 R 1,051,986 R 360,106 34% R 27,249 8%

Mpumalanga 118 R 934,519 R 131,468 14% R 94,759 72%

North West 62 R 904,712 R 114,097 13% R 33,575 29%

Northern Cape 113 R 647,537 R 181,294 28% R 79,729 44%

Western Cape 173 R 1,758,174 R 646,215 37% R 287,283 44%

TOTAL 1 655 12 228 231 3 874 929 32% 1 238 138 32%

Page 18: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

PROGRESS – NEW AND REPLACEMENT SCHOOLS

18

SUMMARY OF PROJECTS COMPLTED FOR THE 2019/20 FINANCIAL YEAR

Province

TA

RG

ET

2018/1

9

NEW SCHOOLS

TA

RG

ET

2018/1

9

REPLACEMENT SCHOOLS

TO

TA

L S

CH

OO

LS

T

AR

GE

TE

D

TO

TA

L C

OM

PL

ET

ED

PR

OG

RE

SS

FIR

ST

QU

AR

TE

R

SE

CO

ND

Q

UA

RT

ER

TH

IRD

QU

AR

TE

R

FO

UR

TH

QU

AR

TE

R

TO

TA

L

FIR

ST

QU

AR

TE

R

SE

CO

ND

Q

UA

RT

ER

TH

IRD

QU

AR

TE

R

FO

UR

TH

QU

AR

TE

R

TO

TA

L

Number of Schools

Eastern Cape 1 0 0 0 4 0 0 0 5 0 0%

Free State 7 2 1 3 3 0 0 0 10 3 30%

Gauteng 4 1 1 2 1 0 0 0 5 2 40%

Kwazulu Natal 5 0 1 1 2 0 1 1 7 2 29%

Limpopo 4 1 5 6 4 1 6 7 8 13 163%

Mpumalanga 3 3 0 3 1 1 0 1 4 4 100%

Northern Cape 2 0 0 0 2 0 0 0 4 0 0%

North West 2 0 0 0 5 0 0 0 7 0 0%

Western Cape 4 2 0 2 9 0 1 1 13 3 23%

Total Number of

schools

32 9 8 0 0 17 31 2 8 0 0 10 63 27 43%

Page 19: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

IDMS REPORT 2nd QUARTER OF 2019/20 PER PROVINCE

19

ProgrammeTotal Targets for

2019/20Q2

EC FS GP KZN LP MP NC NW WC Total

Number of New Schools 32 0 1 1 1 5 0 0 0 0 8

Replacement schools 31 0 0 0 1 6 0 0 0 1 8

Full Service Schools 13 0 0 0 0 0 0 2 0 0 2

Provision/replacement of Sanitation

776 0 2 2 19 46 23 11 0 0 103

Provision/upgrade of Water 515 0 2 2 64 17 5 1 0 0 91

Provision/upgrade of Electricity

133 0 0 2 2 0 0 1 0 0 5

Maintenance Projects 727 0 0 2 25 4 14 9 0 15 69

Libraries Project 45 0 0 2 4 7 1 0 0 14

Laboratories Projects 51 0 0 2 3 2 0 0 0 9 16

School Halls 30 0 0 0 0 8 0 1 0 2 11

Technical Workshops 8 0 0 0 0 0 0 0 0 5 5

Nutrition Centres 51 0 0 0 4 0 1 0 0 0 5

Additional Classrooms 1020 0 12 0 69 34 21 7 0 15 158

Grade R Classrooms 266 0 3 4 4 5 4 4 0 2 26

Administration Blocks 52 0 0 1 6 55 1 2 0 65

Provision/upgrade of fence 387 0 1 1 30 16 2 3 0 0 53

Provision/upgrade of sport field

28 0 0 0 0 0 0 0 0 0 0

Special Schools 3 0 0 0 0 0 0 0 0 0 0

Boarding Schools 31 0 0 0 1 0 0 0 0 0 1

Guard House 30 0 0 0 2 0 1 0 0 0 3

Natural Disasters Projects 185 0 0 0 17 0 4 0 0 0 21

Page 20: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

PROJECT DISTRIBUTION

20

Prov No. of Projects

Budgeted for

PROGRESS

Planning Construction Close-out

EC2,916 1,197 445 1274

FS152 40 112 0

GT 290 216 61 13

KZ 1,311 520 420 371

LP 682 174 387 121

MP 624 409 140 75

NC 405 235 140 30

NW 265 93 64 108

WC 98 69 26 3

TOTAL

6,743

2,953 1,795 1,995

37% 35% 28%

Page 21: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

HUMAN RESOURCES

21

Provnce

No of Approved

Posts Filled Not Filled Progress %

Eastern Cape 63 42 21 67%

Free State 78 50 28 64%

Gauteng 101 83 18 82%

KwaZulu-Natal 74 71 3 96%

Limpopo 65 49 16 75%

Mpumalanga 113 97 16 86%

North West 54 30 24 56%

Northern Cape 81 43 38 53%

Western Cape 54 45 9 83%

Total Weight 683 510 173 75%

Page 22: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

CAPACITATION PLANS – REQUIRED SKILLS SET

Quantity Surveyors

11% Architects9%

Elec.Engineers2%

Civil Engineers 3%

GIS Specialists1%

Town & Regional Planners

5%

Ed. Facility Planners

9%

Works Inspectors

33%

Finance and administration

27%

22

Page 23: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

23

Reports Submission Date Compliance

Final U-AMP for 2019/20 Due 30 March 2019 This is the final plan for all programmes to be implemented over the

period of at least 10 years.

Monthly IRM reports 22 Day of each month This report captures all infrastructure projects being implemented in the

financial year and seeks to present the financial and non financial

progress of projects

End of Year Reports for 2018/19 Due 31 May 2019 The main purpose of the end-of-year report is to measure progress made

by the programme against the objectives and outcomes set, focusing

mainly on the previous financial year

Draft U-AMP 2020/21 Due 28 June 2019 This is a draft plan for all infrastructure programmes to be implemented

over the period of at least 10 years.

Infrastructure Programme Management

Plan (IPMP) & CPS

Due 30 August 2019 The IPMP & CPS is an infrastructure programme management plan

which includes the construction procurement strategy for infrastructure

programmes or projects envisaged to commence within the period for the

medium term expenditure framework (MTEF period). The plan specifies

how the infrastructure programme will be executed, monitored and

controlled.

Human Resource Reports 22 Days after end of each Quarter This report seeks to measure progress of the implementation of the

DoRA Human Resource Strategy. It report provides progress on the filling

of posts on the approved establishment for the infrastructure unit of the

affected provincial department

Non-Financial Performace Reports Due 30 days after end of each Quarter The purpose of this report is to measure quarterly progress made by the

programme against the objectives and outcomes set for the specific

financial year.

MONITORING OF THE PROVINCIAL PROGRAMME

Page 24: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

24

PBS 2019/20 ASSESSMENT PROCESSWeighting for the 2019/20 assessment process (R1.185 billion)

Focus Area Documents / Reports Weight

End of the year evaluation report 20%

Human Resource Capacitation 5%

Infrastructure Reporting Model 40%

User-Asset Management Plans 15%

Infrastructure Programme Management Plans

and;

Construction Procurement Strategy

Performance

Planning20%

TOTAL WEIGHT 100%

Page 25: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

PROJECT COMPLETIONS | STORMS RIVER PRIMARY

25

Implementing Agent: Department of Public Works

Allocated budget: R 51.1 million

Construction Period: 33 monthsProject completed: January 2019

Page 26: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

PROJECT COMPLETIONS | SIVE SPECIAL SCHOOL

26

Implementing Agent: Independent Development Trust

Allocated budget: R124 million

Construction Period: 54 monthsProject completed: June 2018

Page 27: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

NOKUTHULA LSEN SCHOOL

27

Page 28: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

OLIVENHOUTBOSCH SECONDARY SCHOOL

28

Page 29: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

MANDLA MTHETHWA SCHOOL OF EXCELLENCE

29

Page 30: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

Thembisa Special School

• Project experiencing intermittent stoppages

30

COMMUNITY DISRUPTIONS

Page 31: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

31

Page 32: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

32

2019/20 2020/21 2021/22

R'000 R'000 R'000

ASIDI 1 327 048 996 036 1 038 937

SAFE 700 000 800 000 1 300 000

TOTAL 2 027 048 1 796 036 2 338 937

MTEF BUDGET ALLOCATIONS

Page 33: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

OVERALL PERFORMANCE

33

2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 TargetedCompleted Q1 Q2 Q3 Q4 Deviation

Inapp

Structures- 17 36 59 52 16 14 21 229 40 14 8 6 -26

Sanitation 41 89 161 152 38 41 32 207 834 311 73 46 27 -238

Water 16 64 135 317 90 35 42 205 957 432 53 39 14 -379

Electricity 148 101 39 18 0 66 0 372

Past Performance

Electricity Scope Completed

Current Financial Year 2019/20

Sub-

Programme

Complete

d since

Inception

Page 34: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

DU NOON PRIMARY

34

Page 35: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

PHOTOS : CLARKSON/AMAMFENGU

35

Page 36: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

| 3

6

CONSTRUCTION PROGRESS – ASIDI 15

Siyavuya JPS

Sihlahleni JSS Mbekweni HS

Sifonondile JPS

Page 37: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

| 3

7

CONSTRUCTION PROGRESS – ASIDI FREE STATE

BHEKIZULU JSS

HERMANA PS EBENHAUSER

INTERMEDIATE

TWEESPRUIT PS

Page 38: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

2019/20 APP : PROGRAMME 4Strategic Objective Programme Performance

Indicator Medium-term targets

2019/20 2020/21 2021/22

4.2 Provide basic infrastructure services (water, sanitation, electricity) and replace schools built using inappropriate materials on an annual basis in order to improve the conditions under which learners are taught

4.2.1 Number of new schools built and completed through ASIDI 40 31 29

4.2.2 Number of schools provided with sanitation facilities through ASIDI. 717 691 995

4.2.3 Number of schools provided with water through ASIDI. 225 125 0

38

Page 39: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

2019/20 APP : PROGRAMME 4QUARTERLY TARGETS

39

Quarterly Targets

Programme Performance IndicatorAnnual Target

2019/201st 2nd 3rd 4th

Number of new schools built and completed through ASIDI 40 8 5 12 15

Number of schools provided with sanitation facilities through

ASIDI717 120 147 210 240

Number of school provided with water through ASIDI 225 147 25 35 18

Page 40: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

INAPPROPRIATE STRUCTURES

40

<25% 25%-49% 50%-74% >75%

DBSA 114 3 4 5 2 2 13 98

IDT 31 3 0 0 5 3 8 20

CDC 31 0 2 2 1 2 7 24

DRPW 16 0 0 0 0 0 0 16

NDPW 20 1 3 2 2 7 14 5

DBE# 29 29 29

DBE# 57 57 27 5 8 4 8 25 5

Sub-Total - 298 63 14 17 14 22 67 168

IDT 6 - - - - 2 2 4

DBSA 19 - - - 1 1 18

FSDoE 5 - 0 2 3 - 5 0

Sub-Total - 30 0 0 2 3 3 8 22

KZN Adopt-A-School 3 - - - - - - 3

WC WCED 25 - - - - - - 25

MP DBSA 5 - - - - - - 5

NW DBSA 2 - - - - - - 2

NC DBSA 1 - - - - - - 1

LP DBSA 3 - - - - - - 3

Total 367 63 14 19 17 25 75 229

Projects in

Construction

No of

Projects

Complete

d

 FS

Provinces

 

Implementing

Agents (IA)

Projects

being

Implement

ed

Construction ProgressDesign

&

Procur

ement

 EC

Tender Cancelled. Projects to be Re-Tendered

Page 41: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

SANITATION PROGRESS

41

<25 % 25% - 49% 50% - 74% >75%

LP 437 - - 2 18 37 57 380

EC 298 17 6 1 14 17 38 243

FS 39 27 - - - - - 12

KZN 116 - 3 3 4 - 11 105

NC 13 - - - - - - 13

NW 18 8 - - - - - 10

GP 14 - - - - - - 14

MP 38 - - - - - - 38

WC 19 - - - - - - 19

TOTALS 992 52 9 6 36 54 106 834

No of

Projects

Completed

Construction ProgressPlanning,

Design &

Procurement

Projects

being

Implemented

PROVINCESProjects in

Construction

Page 42: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

WATER PROGRESS

42

<25 % 25% - 49% 50% - 74% >75%

EC520 21 1 - 7 150 158 341

MP36 - - - - - - 36

FS67 14 - - - - - 53

GP0 - - - - - - -

KZN224 6 3 1 - - 4 214

LP364 - 2 14 12 35 62 302

NC5 - - - - - 5

NW3 - - - - - - 3

WC3 - - - - - 3

TOTALS 1 222 41 6 15 19 185 224 957

No of

Projects

Completed

Construction ProgressPlanning,

Design &

Procurement

Projects being

implementedPROVINCES

Projects in

Construction

Page 43: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

• Effective monitoring of the provision of infrastructure Professional ServiceProviders (PSP’s) and Implementing Agents (IA’s) that the Department ofBasic Education and provinces are utilizing for the implementation of theinfrastructure programme.

• Monitoring addresses planning, budgeting, expenditure, procurement andproject management. These are interrogated and a sample of projects arevisited. Based on the findings from these visits, remedial actions aredevised with the province and monitored by the DBE.

• Monitoring deals with both programme and project matters;• Programme matters include:- The pattern of overall expenditure being achieved;- Comparisons of expenditure to projected cash flows;- Progress being made with key groups of projects [eg. Water, sanitation,

libraries, laboratories, Grade R]- Management of the portfolio of projects [ie evidence that the programme

of projects is being managed effectively through the project cycle];

MONITORING

43

Page 44: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

• At the Project level the focus is on ensuring:

- that PSP appointments are being made;

- that planning and design processes are progressing;

- that the tender process for the appointment of contractors is progressing, that

construction is progressing satisfactorily, [i.e. on programme, on budget, at

acceptable quality…]; and

- that projects are being handed over and closed out and that final accounts are

being wrapped up.

MONITORING (CONT.…)

44

Page 45: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

CHALLENGES & REMEDIAL ACTIONS

45

CHALLENGE NATURE OF CHALLENGE

REMEDIAL ACTION

1.

• Declining/ no allocation of the Equitable Share toward Infrastructure Delivery poses pressure on the Education Infrastructure Grant.

• Delay payment to contractors resulting in sites been abandon.

Budget/ Finance • PEDs are to allocate Equitable Share.• Delay projects on pre-construction stage to

commence to construction, whilst awaiting for adjustments.

• Monitor the submission of the invoices of the work done by the IA to ensure that work on ground is equivalent to the expenditure.

• PEDs and the IA to reconcile figures on monthly bases.

2.

• Lack of Programme Management System with reliable data information to enhance the planning and delivery of the required Infrastructure timeously

IT • Deployment and the implementation of a transversal system (EFMS) by all the PEDs to manage the data.

• PEDs to increase the IT capacity to house the system.

3.

• Excessive number of schools requiring maintenance

Planning • Re-alignment and reprioritisation of all the projects earmarked for maintenance to comply with the DoRA condition of the 30% allocation towards the programme.

• PEDs to ensure that projects are assessed to avoid duplications or over emphasis on the same schools.

4.

• Non- compliance with SCM processes resulting in irregular expenditure by the Implementing Agent

Procurement • PEDs to conduct quarterly audits to ensure compliance on all the process.

Page 46: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

CHALLENGES & REMEDIAL ACTION (….CONTINUE)

46

CHALLENGE NATURE OF CHALLENGE

REMEDIAL ACTION

5.

• Late appointment of service providers(contractors) by the Implementing Agentfor projects that were already planned anddesigned in previous financial years.

• IA’s lack of capacity resulting in extensionof times, variations orders and delayedoccupation of the asset,

• Inaccurate reporting and poor project andprogramme management.

• Contractors lack of capacity resulting inpoor quality of infrastructure.

• The IAs not meeting the milestone andexpenditure targets as per IPIPs

• The contractual obligations not carried outas per the signed SLA with theimplementing agents

Programme/ Project Management

• Approval of projects for implementation by the PED’s prior to the commencement of implementation.

• The internal capacity through works inspectorsclosely monitors the projects under implementation.

• Monthly progress meeting with IA’s to improve on reporting and to mitigate any challenges.

• Stricter enforcement of timeframes as proposed by FIPDM schedule and the projects reassigned to IA’s that have the capacity to delivery.

• Amendment of the SLA’s to ensure that all engagements are regulated in order to be able to enforce of penalties on non-performing.

• Withdrawing and re-allocation of projects to other performing Implementing Agents.

• Project disruptions by Business Forumsand Local Communities

• Volatility of the construction industry leading to many companies going under and others filing for Business Rescue

Programme/ Project Management

• Continuous engagement with Local Community and Political Leadership to address the identified challenges.

• Effective and close project monitoring and forecasting of trends

Page 47: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative
Page 48: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

BACKGROUND• The audit revealed that 3898 (desktop study) schools

still have inappropriate sanitation facilities.

• An allocation of R2.8 billion has been allocated for the SAFE Initiative over the MTEF as follows:

– 2019/20 : R700 000 000.00

– 2010/21 : R800 000 000.00

– 2021/22 : R1 300 000 000.00

• The SAFE Initiative will be implemented through:

– Provincial EIG allocation

– Partnerships/Donations

– SAFE Initiative Allocation

48

Page 49: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

49

AUDIT (PIT LATRINES)

Page 50: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

AUDIT: KWAZULU-NATAL

Page 51: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

AUDIT: EASTERN CAPE

Page 52: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

FINANCIAL REPORT – SAFE ALLOCATION

52

IA No. of Projects

Estimated Total Budget

Paidto date

Invoice at hand Comments

DBSA 240 R 256, 197,789.95 R 0 R 126 410 728.11 Awaiting supporting documents from the IA. (Tranche payment)

DEA 58 R 63 729 187.69 R 0 R0 DEA is awaiting for National Treasury to approve deviation from normal procurement process before any invoice can be generated.

The MvulaTrust

187 R 268 531 197.17 R 0 R 11 847 646.58 Awaiting supporting documents from the IA.(Assessment reports - Planning)

NECT 121 R 100 685 316.15 R 0 R 40 274 126 .46 Awaiting National Treasury approval to extend the scope of work for NECT. (Tranche payment)

TOTAL 606 R 689 143 490.96 R 0 R 178 532 501.15 26% of invoice at hand

Page 53: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

PROGRESS ON VERIFICATION

53

Province No. ofSchools

Verification Balance Comments

Verified PIT ProperSanitation

EC 1598 359 305 54 1239 Further verification to commence mid October.

FS 156 0 - - 156* No verification will be carried-out as theprovince is implementing all the projects.

KZN 1365 335 255 80 668 (1030)

362 Schools will not be verified, the provincehas allocated the projects to be implementedwith EIG allocation.

LP 507 259 217 42 248 All the schools will be verified by the end ofOctober

MP 127 88 - - 39* 39 Schools will not be verified, the province isimplementing all the projects with EIGallocation.

NW 145 137 66 71 8 Verification to be completed by 8 October.

TOTAL 3898 1205 843 247 2136

• FS & MP all the schools will be implemented with the EIG.

• 606 of the 843 schools are currently under implementation.

Page 54: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

PROJECTS UNDER IMPLEMENTATIONSAFE ALLOCATION & EIG

54

Province No. of Projects Planning Construction

EC 262 262 0

FS 148 80 68

KZN 402 372 30

LP 162 162 0

MP 33 4 29

Total 1007 880 127

• 880 Projects are currently under planning and design phase.

• 127 Projects are currently under construction.

Page 55: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

COMPLETED PROJECTS Province No. of Projects Donor EIG & ASIDI

EC 11 4 7

FS 29 29

KZN 93 2 91

LP 35 3 32

MP 20 9 11

TOTAL 188 18 170

55

• To date 188 Schools have been provided with adequate sanitation.

Page 56: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

CHALLENGES / REMEDIAL ACTIONSCHALLENGES REMEDIAL ACTION

• Planning and implementing within the same year is the major cause of delay.

• All the projects for the next financial year will be allocated to the IAs at the beginning of the fourth quarter, for planning to commence within the current financial year.

• To ensure that implementationcommences at the beginning of the financial year.

• The procurement process is delaying the commencement of construction.

• Project monitoring to ensure that all projects are completed in time and the quality is up to standard.

• Increase the capacity to monitor project implementation.

Page 57: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

57

SEKANEKAMOYI PRIMARY SCHOOL

PROJECT PHOTOS

Page 58: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

58

MAMAILA PRIMARY SCHOOL

PROJECT PHOTOS

Page 59: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

59

PAAPA PRIMARY SCHOOL

PROJECT PHOTOS

Page 60: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

60

TSHINANGE PRIMARY SCHOOL

PROJECT PHOTOS

Page 61: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

61

RAMOTLHATSWANE PRIMARY SCHOOL

PROJECT PHOTOS

Page 62: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

62

SEKANEKAMOYI PRIMARY SCHOOL

PROJECT PHOTOS

Page 63: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

DEDENI JSS - SANITATION

63

Page 64: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

64

ASSUPOL DONATION

Ntlhodumela PS

Maaphoko LPS Govani

Govani PS

Page 65: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

PLANNING, DELIVERY AND MAINTANANCE

▪ Integrated National School Infrastructure Sector Plan: All schools in the country profiled in

terms of their infrastructure needs in line with Norms and Standards;

▪ Revise Education Infrastructure Delivery Model: This delivery model will address:

▪ Expediting delivery of infrastructure projects,

▪ Controlling the cost of providing education infrastructure and;

▪ Improve Contracts Management Processes;

• Standard Floor Layout Plans and Technical Specifications : Develop standardised plans

and specifications for all Education Facilities (Primary Schools, Secondary Schools, Learner

Boarding Facilities, District and Circuit Offices);

• Establishment of an Education Infrastructure Planning & Management Agency / Bureau:

Infra Bureau/Agency to be set up at national level to centrally facilitate and co-ordinate all the

macro and micro planning processes, implementation, monitoring and evaluation of all

infrastructure projects in the Basic Education Sector.

PLANS TO IMPROVE INFRASTRUCTURE PLANNING AND DELIVERY

65

Page 66: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

• Revise project prioritization model to use condition

assessment as a determinant for Project Priority List.

• Utilization of data from STATS SA , like population trends

at a local level, to ensure that size of schools built

addresses the current and future population dynamics;

• Review of SLA’s/MOA’s with IA’s to impose penalties for

non-compliance with progress delivery, deduct management

fees for non compliance or withdraw projects as a result of

poor performance.

• Strengthen Contract Management and Monitoring

processes on infrastructure delivery.

PLANNING, DELIVERY AND MAINTANANCE

66

Page 67: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

• Strengthen internal Technical Capacity to implement projects, ensuring:

- Qualified and Professionally Registered key personnel;

- Accredited Project Managers;

• Employee retention strategies for attracting and retention of built

environment professionals:

– Revise remuneration scales for professionals;

– Improve working conditions and provision of tools of trade;

• Increase the use of alternative building technologies for quicker

construction;

• Benchmark with other role players like independent schools to reduce

the cost of building schools;

PLANNING, DELIVERY AND MAINTANANCE

67

Page 68: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

FUNDING AND PARTNERSHIPS• Provinces to ensure that sufficient funding is allocated to the Equitable Share

and ring fence such funding for infrastructure;

• Condition Grant allocations (EIG) to be ring-fenced and used solely for the

intended purpose, as a condition of the grant;

• EIG Funding allocations to be per project on the basis of an approved Business

Case and progress on projects implemented;

• Diversified funding modalities for school infrastructure:

• Public-Private Partnerships (Build, Operate & Transfer – BOT);

• Donor and Grant funding;

• Rand-for-Rand Public-Private Partnerships;

• Partnerships with Institutions of Higher Learning and Non-governmental Organizations.

68

Page 69: PORTFOLIO COMMITTEE ON BASIC EDUCATION€¦ · programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative

RECOMMENDATION

It is recommended that thePortfolio Committee discussesthe progress report onInfrastructure planning anddelivery as well as SAFE.

69