2016 Design and Construction Issues at Hazardous Waste Sites

Page 2: PowerPoint Presentation...2016 Design and Construction Issues at Hazardous Waste SitesWorld War II- Redstone Arsenal War Department - Purchased property in 1941 Chemical Warfare Service

2016 Design and Construction Issues at Hazardous Waste Sites

World War II- Redstone Arsenal

War Department- Purchased property in 1941

Chemical Warfare Service (CWS)• Huntsville Arsenal (HVA)

– Chemical agent production– Test range activities

• Gulf Chemical Warfare Depot (GCWD)– Storage, Shipping and receiving

Ordnance Department (OD)• Redstone Ordnance Plant (ROP)

– Ordnance production

Page 3: PowerPoint Presentation...2016 Design and Construction Issues at Hazardous Waste SitesWorld War II- Redstone Arsenal War Department - Purchased property in 1941 Chemical Warfare Service

2016 Design and Construction Issues at Hazardous Waste Sites

Electrical Resistance Heating (ERH) Technical Overview

Thermal Oxidizerwith Scrubber

(RSA-095 West only)

100 to 600 voltsat each electrode element

Page 4: PowerPoint Presentation...2016 Design and Construction Issues at Hazardous Waste SitesWorld War II- Redstone Arsenal War Department - Purchased property in 1941 Chemical Warfare Service

2016 Design and Construction Issues at Hazardous Waste Sites

Electrodes are installed (Photo: RSA-095 West)

◄ 12.47kV electrical service is (Photo: RSA-142)

Page 5: PowerPoint Presentation...2016 Design and Construction Issues at Hazardous Waste SitesWorld War II- Redstone Arsenal War Department - Purchased property in 1941 Chemical Warfare Service

2016 Design and Construction Issues at Hazardous Waste Sites

The electrode field and treatment area are fenced and monitored via

cameras and motion detectors.(Photo: RSA-142)

The power control unit andtreatment system are installed (Photo: RSA-053)

Page 6: PowerPoint Presentation...2016 Design and Construction Issues at Hazardous Waste SitesWorld War II- Redstone Arsenal War Department - Purchased property in 1941 Chemical Warfare Service

2016 Design and Construction Issues at Hazardous Waste Sites

Cables deliver electricity from the power control unit to the electrodes. Vapors are drawn through CPVC piping to the condenser. (Photo: RSA-096)

Page 7: PowerPoint Presentation...2016 Design and Construction Issues at Hazardous Waste SitesWorld War II- Redstone Arsenal War Department - Purchased property in 1941 Chemical Warfare Service

2016 Design and Construction Issues at Hazardous Waste Sites

After the remediation effort is complete. (Photo: RSA-096)

Page 8: PowerPoint Presentation...2016 Design and Construction Issues at Hazardous Waste SitesWorld War II- Redstone Arsenal War Department - Purchased property in 1941 Chemical Warfare Service

2016 Design and Construction Issues at Hazardous Waste Sites

Remedial GoalsFor sites with potential DNAPL in the saturated zone –

Reduce groundwater contaminant concentrations by 80%

For sites with trichloroethene (TCE) in unsaturated (vadose) zone soil –

Reduce soil concentrations to less than 5 mg/kg

* DNAPL = dense non-aqueous phase liquid

Page 9: PowerPoint Presentation...2016 Design and Construction Issues at Hazardous Waste SitesWorld War II- Redstone Arsenal War Department - Purchased property in 1941 Chemical Warfare Service

2016 Design and Construction Issues at Hazardous Waste Sites

Site TargetOperation

Period

Energy to Subsurface

(kWh)

Organics Removed

(lbs)Remedial Goal Met? Cost

RSA-053 Chlorobenzene(DNAPL)

08/17/13 to 02/10/14 3,067,200 2,945 Yes1 $2.7M

RSA-096 TCE (DNAPL & vadose soil)

10/24/13 to 01/22/14 2,362,000 2,800 Yes $2.6M

RSA-142 TCE (DNAPL & vadose soil)

03/14/14 to 08/11/14 3,327,000 5,913 No2 $5.6M

RSA-095 East

TCE (DNAPL & vadose soil)

01/07/15 to04/01/15 1,088,400 1002 Yes

RSA-095West

TCE (DNAPL & vadose soil) In Progress

10,150,00 (through Aug31)

70,000 (PID)36,000 (Lab)

to date

To be determined

1Per discussion with ADEM regarding bedrock results. 2One of 33 soil locations remains above goal.

$12.1M(combined

budget)

Page 10: PowerPoint Presentation...2016 Design and Construction Issues at Hazardous Waste SitesWorld War II- Redstone Arsenal War Department - Purchased property in 1941 Chemical Warfare Service

2016 Design and Construction Issues at Hazardous Waste Sites

• Proven effective at achieving “No Further Action” for surface media

• Focuses energy in features that contain contamination

• Remediates rapidly• Minimizes land use controls• Minimizes off-site trucking• Minimizes consumed landfill space

Page 11: PowerPoint Presentation...2016 Design and Construction Issues at Hazardous Waste SitesWorld War II- Redstone Arsenal War Department - Purchased property in 1941 Chemical Warfare Service

2016 Design and Construction Issues at Hazardous Waste Sites

Factors that affect the Remediation Cost

• Type of VOC: chlorobenzene (b.p. 132°C) is about 35% more expensive than trichloroethene (b.p. 87°C).

• Percentage reduction: a 99% TCE reduction is about 13% more expensive than a 90% TCE reduction.

• Vadose or saturated zone is the same cost. Bedrock is slightly higher cost due to drilling.

• Belowgrade installation to allow vehicle traffic adds 16%.

Page 12: PowerPoint Presentation...2016 Design and Construction Issues at Hazardous Waste SitesWorld War II- Redstone Arsenal War Department - Purchased property in 1941 Chemical Warfare Service

2016 Design and Construction Issues at Hazardous Waste Sites

Design, $135,000

Installation, $864,000

Operation, $395,000

Demobilization, $64,000

GAC and Waste, $45,000

Electricity, $218,000

Soil, Air, and GW Sampling, $58,000

Oversight and Management,

$921,000

Cost by Task

Page 13: PowerPoint Presentation...2016 Design and Construction Issues at Hazardous Waste SitesWorld War II- Redstone Arsenal War Department - Purchased property in 1941 Chemical Warfare Service

2016 Design and Construction Issues at Hazardous Waste Sites