A BRIEF NOTES ON
ACCIDENT MANUAL
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 3/73
ACCIDENT MEANS For the purpose of Railway working,
Accident is an occurrence in the course ofworking of railway which DOES or MAY
AFFECT its engines, the Safety of the railway, rolling stock, permanent way and works,
fixed installations, passengers or servant or which affect the safety of others or which does or may cause delay to train or
loss to railway.
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 4/73
SERIOUS ACCIDENT1. For pass. Carrying trains
2. Death or
3. Serious Injury or
4. Loss of Railway Property above
Rs. 2 crores or4. In the opinion of CCRS/CRS, if an
enquiry is required
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 5/73
CLASSIFICATION OF
ACCIDENTS
1. TRAIN ACCIDENTS (Train Means)
2. YARD ACCIDENTS
3. INDICATIVE ACCIDENTS
4. EQUIPMENT FAILURE
5. UNUSUAL INCIDENTS
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 6/73
TRAIN ACCIDENTS
CONSEQUENTIAL TRAIN ACCIDENTS
OTHER TRAIN ACCIDENTS
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 7/73
EXAMPLE FOR CONSEQUENTIAL
TRAIN ACCIDENTS
1. Collision = A1 to A4
2. Fire = B1 to B4
3. Level Crossing = C1 to C4
4. Derailments = D1 to D4
5. Miscellaneous = E1
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 8/73
EXAMPLE FOR OTHER TRAIN
ACCIDENTS
B5,B6,C5 to C8 , D5 and E2
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 9/73
YARD ACCIDENTS ACCIDENTS THAT
TAKE PLACE IN
YARD NOTINVOLVING ATRAIN.
Ex:- A5, B7, C9 and
D6
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 10/73
INDICATIVE ACCIDENTS THESE ARE NOT ACCIDENTS BUT
POTENTIAL HAZARDS.
Ex:- Averted Collision F
Breach of Block Rules G
Driver Passing Stop signal at ON H
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 11/73
AVERTED COLLISIONS
IT IS A CIRCUMSTANCE UNDER
WHICH, BUT FOR THE VIGILANCESHOWN BY ANY PERSON OR
PERSONS, A COLLISION WOULDHAVE OCCURRED EITHER IN THEBLOCK SECTION OR WITHIN THE
STATION LIMITS BETWEEN TWOTRAINS OR BETWEEN A TRAINAND AN BSTRUCTION.
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 12/73
EXCEPT ON “TWO” OCCASSIONS 1. OUT SIDE STATION
LIMITS
That is the distancebetween two train(OUTSIDE STATIONLIMITS) is 400 mts.
or more.It is not an avertedcollision
WITHIN STATIONLIMITS
There is an intervening
fixed Stop Signal atdanger governing themoving train andcompliance by themoving train with theindication conveyed by
the Stop Signal avertedthe collision between thetrains or between thetrain and the obstruction.
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 13/73
BREACH OF BLOCK RULES 1.Train entering block section with improper
ATP or without ATP.
2.Train entering into sand hump or into
Catch/Slip siding.
3.Train despatched on wrong line
4.Train received on wrong line
5.Train received on to an obstructed line, not
constituting Averted Collision.
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 14/73
EQUIPMENT FAILURE Ex :- LOCO FAILURE, ROLLING STOCK
FAILURE, P/WAY FAILURE, OHE
FAILURE, S & T FAILURE, etc., “J, K, L, M”
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 15/73
UNUSUAL INCIDENTS RELATING TO LAW AND ORDER
PROBLEMS.
“N, P, Q, R ”
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 16/73
SERIOUS DISLOCATION OF
TRAFFIC
1. On Trunk Route = 6 Hours
2. Main Line = 12 Hours
3. Branch Line = 24 Hours
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 17/73
ROUTE CLASSIFICATION
BG
Route „A‟ max.160 kmph Route „B‟ max.130 kmph
Route „C‟Suburban Trains onMetro Cities
Route „D‟ max.100 kmph
Route „E‟ less than100 kmph
MG
Route „Q‟ more than75 kmph
Route „R‟ 75 kmph
Route „S‟ less than
75 kmph
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 18/73
COMPOSITION OF ART
1. Crane
2. Hydraulic Rerailing Equipment [MFD / LUKAS]3. Engineering Equipment Van
4. Mechanical Equipment Van
5. Electrical Equipment Van6. Power and Tool Van
7. Staff kitchen car and BV
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 19/73
GENERAL TARGET TIME OF
ARTDAY - 30mts
NIGHT - 45mts
BZA………………….. 1/1 Hrs
BTTR………………… 1/1 Hrs
GTL – UBL…………. 1/1.15 Hrs RC – WD……………. 1.15/1.15 Hrs
PAK…………………… 1/1 Hrs
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 20/73
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 21/73
GENERAL TARGET TIME OFM R T
DIRECT DESPATCH 15 mts
INDIRECT DESPATCH 20 mts
SECUNDERABAD
06.00 TO 20.00 – DD - 15 mts
ID - 20 mts
20.00 TO 06.00 – DD - 20 mtsID - 20 mts
VIJAYAWADA – DD - 20 mts
ID - 25 mts
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 22/73
MOCK DRILL FOR ART
ONCE IN “THREE” MONTHS
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 23/73
INSPECTION OF MEDICAL VAN
BY ADMO - MONTHLY
BY DMO - ONCE IN 3 MONTHS
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 24/73
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 25/73
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 26/73
PERIODICAL TRAIL RUN OF
MRV
QUARTERLY ONCE BY PASSENGER
TRAIN
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 27/73
EX-GRATIATRAIN/ MANNED LC GATE ACCIDENT
1.DEATH - Rs. 50,000
2.SERIOUS INJURYUpto 30 days hospitalisation - 25,000
Upto further 6 months – 1,000/- per week
Upto further 6 months – Rs 500/- per week3.SIMPLE INJURY - Rs. 500
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 28/73
EX-GRATIAnil
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 29/73
COMPENSATIONTHROUGH RCT WITHIN ONE YEAR OF
THE INCIDENT
PART – I DEATH- Rs. 4,00,000
PART – II Rs. 4,00,000
PART – III UPTO Rs. 3,60,000
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 30/73
ACCIDENT SIRENS
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 31/73
TWO LONG
Accident in loco shed or in Trafficyard adjoining Loco Shed
ACCIDENT SIRENS
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 32/73
THREE LONG
Out Station Accident, MAIN LINEClear ART required
ACCIDENT SIRENS
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 33/73
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 34/73
FOUR LONG
Out Station Accident, MAIN LINE Blocked ART required
ACCIDENT SIRENS
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 35/73
FOUR LONG ONE SHORT
Out Station Accident, MAIN LINE Blocked ART + MRT required.
ACCIDENT SIRENS
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 36/73
DURATION OF ACCIDENT
SIREN
DURATION OF LONG SIREN - 30 SECONDS
DURATION OF SHORT SIREN - 5 SECONDS GAP BETWEEN LONG AND
LONG OR LONG AND SHORT - 5 SECONDS
REPITITION AFTER A GAP OF- 30 SECONDS
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 37/73
THRESHOLD VALUE
WITH REFERENCE TO ACCIDENT, IT
IS A MINIMUM VALUE BEYOND WHICH THE
ACCIDENT WILL BE TREATED AS HAVINGSERIOUS REPURCUSSION ON THE BASIS OFLOSS TO RAILWAY PROPERTY OR
INTERRUPTION TO COMMUNICATION
a) Threshold value of Railway Property Loss is
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 38/73
a) Threshold value of Railway Property Loss is
Fixed at Rs. 1,00,000
b) Partial or Total Interruption as given Below
INTERRUP-TION
BG: ROUTE „A‟‟B‟‟C‟OR
„D‟ SPL
BG: „D‟‟E‟SPL
MG: „Q‟ „R‟
BG: „E‟
MG: „S‟
Total 3 Hours 4 Hours 6 Hours
Or Or Or Or
Total +
Partial
6 Hours 8 Hours 12 Hours
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 39/73
OBJECTIVES TO BE ACHIEVED
1. Save Life and Alleviate suffering
2. Protect property including mails3. Provide Succor and help to other
passengers
4. Ascertain the Cause of the accident5. R estore through lines of
communication.
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 40/73
DISASTER MANAGEMENTBY GUARD AND DRIVER
DISASTER MANAGEMENT BY
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 41/73
1. Note down thetime,location, weather
etc.,
DISASTER MANAGEMENT BYGUARD AND DRIVER
DISASTER MANAGEMENT BY
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 42/73
2. Secure the loco / formation
DISASTER MANAGEMENT BYGUARD AND DRIVER
DISASTER MANAGEMENT BY
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 43/73
3. Protection of Trains – As persystem of working – SingleLine, Double Line, TwinSingle Line, Abnormal working
etc.,
DISASTER MANAGEMENT BYGUARD AND DRIVER
DISASTER MANAGEMENT BY
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 44/73
4. Giving information to SM orSCOR or TPC – By using
field/emergency telephone, walkie Talkie, IB telephone,
Gate Telephone, by stoppingtrains, by road vehicle, by
engine, by messenger.
DISASTER MANAGEMENT BYGUARD AND DRIVER
DISASTER MANAGEMENT BY
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 45/73
5 Assistance to Public – Luggage, Drinking Water,Snacks, food Packets,
beverages, Transport, etc.,
DISASTER MANAGEMENT BYGUARD AND DRIVER
DISASTER MANAGEMENT BY
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 46/73
6 Medical Assistance - Render First Aid, Identify
doctors traveling by train, take Assistance of any Para medical
staff inform railway hospital,civil hospital, private nursing
homes and clinics etc.,
DISASTER MANAGEMENT BYGUARD AND DRIVER
DISASTER MANAGEMENT BY
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 47/73
7. Preserve clues if any - Do not disturb any clues,
preserve the suspected
material, etc.,
DISASTER MANAGEMENT BYGUARD AND DRIVER
DISASTER MANAGEMENT BY
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 48/73
8 In case of fire accident - Savelife, isolate the coach, put outthe fire, use fire Extinguishers,
bring down pantograph, put offlights, fans from the terminals.
DISASTER MANAGEMENT BYGUARD AND DRIVER
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 49/73
GUARD AND DRIVER TO PREPARE
SPECIMEN FORM IN ACC –
3
DO NOT LEAVE THE ACCIDENT
SPOT TILL RELEIVED.
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 50/73
ACCIDENT MANAGEMENTBY STATION MASTERS
ACCIDENT MANAGEMENT BY
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 51/73
1. PROTECTION - Note down
the position of signals, put backthe Signals to prevent furthermishap, protect adjacent lines,note the position of points, lockthe block instrument, put lineblocked caps/collars/pins
ACCIDENT MANAGEMENT BYSTATION MASTERS
ACCIDENT MANAGEMENT BY
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 52/73
2. COLLECTION OF INFORMATION Time of Accident, location, gauge,
single/double/Twin single Line,signalling system, gradient, tractionetc.,Train/trains involved, type of
stock involved, nature of accident,casualties/injuries, advise to allconcerned
ACCIDENT MANAGEMENT BYSTATION MASTERS
ACCIDENT MANAGEMENT BY
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 53/73
3. MEDICAL RELIEF - Call for
MRT/ART, crane, Arrangefirst aid. Inform Doctors,
Hospitals, etc., Arrange totransport injured, shelterfor injured.
ACCIDENT MANAGEMENT BYSTATION MASTERS
4 ACTION IN CASE OFACCIDENT MANAGEMENT BY
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 54/73
4. ACTION IN CASE OFSABOTAGE
Preserve clues, Advise DistrictMagistrate, S P of Police,CSC(Railway) GRP, LODGE
FIR WITH GRP OFJURISDICTION
Wait for police clearance Arrange forvideography/photography,
etc.,
ACCIDENT MANAGEMENT BYSTATION MASTERS
ACCIDENT MANAGEMENT BY
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 55/73
5. ASSISTANCE TO PASSENGERS -Drinking water, catering etc.,
Issue of free telegrams, Issue offree Passes, Arranging STDfacility, Arranging alternative
means of Transport andprotection of luggage etc.,
ACCIDENT MANAGEMENT BYSTATION MASTERS
ACCIDENT MANAGEMENT BY
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 56/73
6. PARCELS, MAILS, GOODS
ETC., Arrange for stocking,protection, preservevaluable Documents, cash,etc.,arrange tarpaulins.
ACCIDENT MANAGEMENT BYSTATION MASTERS
ACCIDENT MANAGEMENT BY
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 57/73
7. EX-GRATIA -
Arrange for ex-gratiapayment on the spot asper Extant rules.
ACCIDENT MANAGEMENT BYSTATION MASTERS
ACCIDENT MANAGEMENT BY
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 58/73
8. INFORMATION BOOTH
Open Information booth for givinginformation to Public, names ofdead/injured. Location where they are
treated, announcing through P.Asystem regarding diversion /cancellation / regulation of trains.Ensure continuous manning of the
booth
ACCIDENT MANAGEMENT BYSTATION MASTERS
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 59/73
STATION MASTER TOPREPARE SPECIMEN IN ACC. FORM - I
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 60/73
DISTANCE IS 400 mts or MORE
OUTSIDE STATION LIMITS
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 61/73
A station with mechanicalmode of locking, not
having anyelectrical/mechanicalsupport
WITHIN STATION LIMITS
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 62/73
A station with mechanicalmode of locking, not
having anyelectrical/mechanicalsupport
WITHIN STATION LIMITS
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 63/73
TRAIN MEANS
AS PER G & SR
Train means anengine with orwithout vehiclesattached, or any selfpropelled vehiclewith or without a
trailer, which cannotbe readily lifted offthe track.
AS PER ACC.MANUA A trains is a set of vehicles,
empty or loaded, worked by
locomotive, or any other selfpropelled unit, which cannotbe readily lifted off the trackand running under aparticular number or a
distinct name from fixedpoint of departure to a fixeddestination.
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 64/73
A 1 TO A 4
A1 – Collision involving a train carrying passengersresulting in loss of human life or railway propertyexceeding 25 lakhs.
A2 – Collision involving a train NOT carryingpassengers, resulting loss of human life or lossrailway property exceeding 25 lakhs.
A3 – Collision involving a train carrying passengers,
not falling under A1 above. A4 – Collision involving a train NOT carrying
passengers, not falling under A2 above.
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 65/73
B1 TO B4
B1 – Fire in a train carrying passengers, resulting inloss of human life and damage to RailwayProperty of value exceeding 25 lakhs.
B2 – Fire in a train NOT carrying passengers,resulting in loss human life and or damage toRailway property of value exceeding 25lakhs.
B3 – Fire in a train carrying passengers not falling
under B1 above. B4 – Fire in a train NOT carrying passengers not
falling under B2 above.
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 66/73
C1 TO C4
C1 – Trains carrying passengers running into road traffic and orroad traffic running into such trains at manned levelcrossings.
C2 – Trains NOT carrying passengers running into road traffic
and or road traffic running into such trains at manned levelcrossings.
C3 – Trains carrying passengers running into road traffic and orroad traffic running into such trains at unmanned level
crossings
C4 – Trains NOT carrying passengers running into road trafficand or road traffic running into such trains at unmannedlevel crossings.
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 67/73
D1 TO D4
D1 – Derailment of a train carrying passengers resulting in lossof human life and or damage to railway property of thevalue exceeding Rs. 25 lakhs.
D2 – Derailment of train NOT carrying passengers resulting inloss of human life and or damage to railway property ofthe value exceeding Rs. 25 lakhs.
D3 – Derailment of a train carrying passengers, not falling underD1 above.
D4 – Derailment of a train NOT carrying passengers not fallingunder D2 above.
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 68/73
E1
Trains running over or against anyobstruction including fixed structure
other than included under class Cresulting in loss of human life and orgrievous hurt and or damage to railway
property and or interruption to traffic ismore than the threshold value.
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 69/73
B5,B6,C5 to C8 , D5 and E2 B5 – Fire in a train carrying passengers not falling under B1 or B3
B6 – Fire in a train NOT carrying passengers not falling under B2 or B4
C5 – Trains carrying passengers running into road traffic and or road trafficrunning into such trains at manned level crossings but not falling under C1
C6 – Trains NOT carrying passengers running into road traffic and or roadtraffic running into such trains at manned level crossings but not falling underC2.
C7 – Trains carrying passengers running into road traffic and or road trafficrunning into such trains at unmanned level crossings but not falling under C3.
C8 – Trains NOT carrying passengers running into road traffic and or road traffic
running into such trains at unmanned level crossing but not falling under C4. D5 – Derailment of a train NOT carrying passengers not falling either under De
or D4 .
E2 – Trains running into any obstruction including fixed structure but notcovered up under class C or E1.
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 70/73
A5, B7, C9 and D6
A5 – Other collisions i.e collisions occurring in shunting,marshalling yards, loco yards and siding etc, but notinvolving a train.
B7 – Fire occurring in shunting, marshalling yards, loco yards
and siding etc, involving rolling stock but not involvinga train.
C9 – Shunting engine with or without vehicles or loose vehiclesrunning into road traffic and or road traffic running intoshunting engine with or without vehicles or loose vehicles,at level crossings.
D6 – Other derailments, i.e, derailments occurring in shunting,marshalling yards, loco yards and siding etc, but notinvolving a train.
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 71/73
F, G, H F1 – Averted collision between trains at least one of which is carrying passengers.
F2 – Averted collision between a train carrying passengers and an obstruction.
F3 – Averted collision between trains NOT carrying passengers.
F4 – Averted collision between trains NOT carrying passengers and
an obstruction. G1 – Trains carrying passengers, entering a block section without any authority or
without a proper Authority to proceed.
G2 – Trains NOT carrying passengers, entering a block section without any authority orwithout a proper Authority to proceed.
G3 – Trains received on a blocked line, not constituting an averted collision
G4 – Train received on or entering a wrong line at a station or catch siding or slip siding or
sand hump etc., H1 – Train carrying passengers running past a stop signal at danger without proper authority.
H2 – Trains NOT carrying passengers running past a stop signal at danger without properauthority.
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 72/73
J, K, L, M
J – Failure of Engine and Rolling Stock
K – Failure of Permanent way
L – Failure of Electrical Equipment
M – Failure of Signalling andTelecommunication
8/14/2019 PPT ON ACC.MANUAL.ppt
http://slidepdf.com/reader/full/ppt-on-accmanualppt 73/73
N, P, Q, R
N- Train Wrecking
P – Causalities
Q – Other incidents
R - Miscellaneous