December 2014
2010-2276
Table of contents
Chapter 1. Description of the Danish-German Transport Commission ............... 2
Update of interim report
Chapter 2. Description of the cross-border infrastructure and transport structure in the Jutland Corridor ............................................................................................ 4
Denmark ............................................................................................................................................................. 5
Germany ........................................................................................................................................................... 12
Chapter 3. Development in traffic in the Jutland corridor from 2000 to today. Figures and facts ........................................................................................................................... 16
Denmark ........................................................................................................................................................... 16
Germany ........................................................................................................................................................... 24
Chapter 4. Current infrastructure programmes in Denmark and Germany -Focusing on the Jutland corridor .......................................................................................... 29
Denmark ........................................................................................................................................................... 29
Germany ........................................................................................................................................................... 31
Chapter 5. Prioritised projects by the Danish-German Transport Commission ................................................................................................................................................................. 35
Chapter 6. Recommendations ................................................................................................. 37
PRELIMINARY DRAFT
[2]
Chapter 1. Description of the Danish-German Transport Commission
The Danish-German Transport Commission was founded on July 5, 2011. Its objective is to analyse
cross-border traffic with a special focus on the Jutland Corridor and to give recommendations for
improving infrastructure and the transport economy.
Membership: 12 members, Denmark and Germany are equally represented by 6 members each
Representatives from Denmark Germany
TRM (Danish Ministry of Transport) 2
Development Council South-Jutland 2
Danish Chamber of Commerce (Dansk
Erhverv)
1
Confederation of Danish Industry 1
MWVAT (Schleswig-Holstein MOT) 2
BMVI (Federal German MOT) 1
Hamburg chamber of Commerce 1
Chamber of Commerce and Industry
Schleswig-Holstein
1
WiREG (Business Development
Corporation Schleswig-Flensburg)
1
Additional experts may be invited depending on demand and/or subject.
The German Federal MOT is not a de facto permanent member of the Commission, it only participates
when issues of federal German or European policy are addressed. In case the Federal German MOT is
not taking part, its seat is taken by the Schleswig-Holstein MOT so as to ensure parity between the
Danish and the German members. To date, the Federal German MOT only took part once.
The Transport Commission has a consultative function; it will give recommendations only. The
recommendations are made by consensus and must be unanimous.
The projects described in this report vary by their stage of investigation and are thus not at the same
analytical level. Furthermore some projects focus on the construction side while others focus on the
operation side of transport initiatives. It is clear that for projects focusing on the operation of transport
it will be necessary to take commercial perspectives into account. Finally, it must be emphasised that
the decision making process for concrete projects takes place outside of the work of the commission at
ministerial level on the Danish/German side respectively.
The following procedural decisions were taken at the inaugural meeting on July 5, 2011:
- The chair shall alternate between Denmark and Germany every six months.
- There shall be two meetings within a period of six months.
To date, the Transport Commission has convened 8 times and has mainly addressed the following
subjects:
- Rail projects in Denmark, railway lines in Denmark
- Study on a fixed link between Fyn and Als
PRELIMINARY DRAFT
[3]
- Presentation of the German-Danish Business Forum
- A joint German-Danish train station
- Eco-Combi vehicles (long commercial vehicles)
- Sønderborg binational airport
- The role of Danish ports in the cross-border region, ports in Schleswig-Holstein
- Expert report on “High Speed Train in the Jutland Corridor”
- Study about Padborg as an intermodal terminal
- Combined transport terminal Neumünster
- European Train Control System (ETCS) on the line between Niebüll and Tønder
- Extension of the motorway A7
- Situation of the high bridge across Kiel Canal at Rade
- Cabotage in long-distance freight traffic
- Air freight
- Discussion of the joint interim report on Jan. 1, 2013
- Proposals for (cross-border) transport projects made by stakeholders.
PRELIMINARY DRAFT
[4]
Update of the “Interim report” from the commission
Chapter 2. Description of the cross-border infrastructure and transport structure in the Jutland Corridor
The Federal Republic of Germany and the Kingdom of Denmark have a common land border that
divides the Cimbrian peninsula, including Jutland and Schleswig - Holstein, in an east west direction.
Both states are connected by a network of roads and railway lines in a north south direction through the
so-called Jutland Corridor.
This chapter describes the existing transport infrastructure, the development of the different transport
carriers since the year 2000 as well as the concrete plans for expansion measures and cross-border
projects in the Jutland Corridor.
PRELIMINARY DRAFT
[5]
Denmark
2.1 Roads
The trunk road network - or the national road network in Denmark - plays a central role when it comes
to the flow of traffic. The trunk road network is the backbone of the key international transport
corridors throughout Denmark and helps ensure efficient traffic flows between Scandinavia and the rest
of the continent.
The backbone of the road network is made up of the so-called capital "H", i.e. roads between
Frederikshavn and Danish-German border, between Køge and Esbjerg and between Elsinore and
Rødby. See map 2.1.1. The capital “H” provides gateways to Denmark’s neighbours most notably
Germany, Sweden, Norway and the United Kingdom
Map 2.1.1 The capital “H”
Despite the fact that the trunk road network only makes up approximately 5 per cent of the total public
road network in Denmark, approximately 45 per cent of all vehicle kilometres in Denmark are driven on
the trunk road network.
The southern part of Jutland is part of the region “Southern Denmark”. In this region there are located
two motorways, which are part of the capital “H”, namely the east-west oriented Esbjergmotorvejen
(E20) between Lillebælt and Esbjerg and the north-south Sønderjyske motorway (E45) between
PRELIMINARY DRAFT
[6]
Kolding to the north and the Danish-German border at Frøslev to the south. South of the border to
Germany E45 continues as A7.
In the western part of Jutland there is one trunk road (Route 11) between Esbjergmotorvejen to the
north and the Danish-German border south of Tønder and a number of trunk roads across the region.
south of the Danish-German border Route 11 continues as B5.
A new motorway – Kliplev-Sønderborg – between Sønderjyske motorway to the West and Sønderborg
to the East opened in 2011. The 25 km 4 lane motorway was carried out as a Public Private Partnership
(PPP). The Kliplev-Sønderborg motorway was the first Danish motorway carried out as a PPP.
Map 2.1.2 shows the trunk roads in the southern part of Jutland; map 2.1.3 shows the number of
vehicles on the trunk roads in the southern part of Jutland and Table 2.1.1 shows different road types on
the trunk road network in the southern part of Jutland.
Map 2.1.2 Trunk roads in the southern part of Jutland
PRELIMINARY DRAFT
[7]
Map 2.1.3
Annual average daily traffic on the trunk roads in 2013 (all vehicles) in the southern part
of Jutland
As seen on the map the traffic load is highest on the Sønderjyske motorway (E45) between Kolding and
the Danish-German border at Frøslev.
Table 2.1.1 Different road types on the trunk road network in the southern part of
Jutland
Road type Km Road Amount (pct.)
Motorway 216 29
Expressway 114 15
Other trunk roads 414 56
Total 744 100
Regarding trunk roads there are two border crossings between Denmark and Germany, namely the
crossing at Sæd and the crossing at Frøslev. Table 2.1.2 shows the number of vehicles crossing the
border stations.
PRELIMINARY DRAFT
[8]
Table 2.1.2 Number of vehicles passing the Danish-German border on a trunk road
(2013)
Border station Number of vehicles
Sæd 5.600
Frøslev 16.500
2.2 Railway
There are two railway lines crossing the Danish-German border: Niebüll-Tønder and Padborg-
Fredericia. The railway line between Niebüll and Tønder is single tracked and with a speed limit of 100
km/h. The line between Padborg-Fredericia is double-tracked except from Vamdrup to Vojens and from
Padborg to Tinglev. The speed limit is 180 km/h in some parts of the railway with the lowest speed limit
from Padborg to Tinglev being 120 km/h.
Map 2.2.1 with 2011-data from www.bane.dk
The railway between Padborg-Fredericia is part of the Scandinavian Mediterranean Corridor. The
section is an important part of the Danish railway network, linking the western, northern and southern
parts of Denmark with Germany.
The single track section between Vamdrup and Vojens of 20 km will be upgraded to double track by the
end of 2015. This will eliminate the bottleneck problems currently limiting the capacity of the rail line
north of Tinglev. The upgrade project received EU TEN-T funding in 2012 to support the development
of the EU infrastructure. After the upgrade of the section, Tinglev-Padborg will be the last single track
PRELIMINARY DRAFT
[9]
section left to be upgraded. In the Agreement on a Modern Railway (Aftale om en moderne jernbane)
from 22. October 2009 it was agreed to construct a double track on the rail line Tinglev-Padborg.1
In 2012 it was decided to electrify the railway between Esbjerg and Lunderskov. This is the first step
towards electrification of the most important Danish rail lines. The electrification will provide a
modern, cheaper, more stable and environment friendly railway.
2.3 Ports and shipping
Denmark is home to approximately 130 sea ports that function as important nodal points in the
transport chain connecting the Danish economy to neighbouring markets.
In the south Jutland region Danish ports facilitate a wide array of services ranging from frequent feeder
services to German ports, short sea shipping of roll-on-roll-off units and transport of oil, gas and dry
bulk. In recent years ports on the West Coast of Denmark have furthermore carried out investment
programmes to facilitate the growth in the wind energy sector and the off-shore wind farms in the
Wadden Sea and North Sea specifically.
1 Ministry of Transport: Aftaler om En grøn transportpolitik, 2009.
PRELIMINARY DRAFT
[10]
Figure 2.3.1: Freight volumes between South Jutland ports and Germany in 2013 (1000 t)
Source: Statistics Denmark
The most prominent port in the South Jutland region in terms of container freight to/from Germany is
the port of Fredericia. As a feeder port to the Port of Hamburg five weekly connections operate the
route. The prominence of the Port of Fredericia is visualised in fig. 2.3.1 and in 2013 approximately
1400 tonnes of goods were transported between the Port of Fredericia and German ports.
The Port of Esbjerg - the second of the larger ports in the South Jutland region - has a significantly
smaller exchange of goods with German ports.
In general the port of Esbjerg handled almost 2,000 tonnes of goods in 2013 and represents a major
connecting point for Danish foreign trade. Even though the volume of freight between Esbjerg and
German ports remains marginal, the port of Esbjerg offers an efficient supplement to the Port of
Hamburg in terms of short sea shipping access to destinations in the United Kingdom and on the
European continent – to the benefit for the border region at large.
The ports of Rømø and Esbjerg have taken a proactive approach to accommodate the growing market
for wind energy. While Esbjerg has focussed on the shipping of wind turbines components from Danish
production facilities and on supplying services to Danish off shore wind farms, the port of Rømø
focusses on supplying services to German off shore wind farms. Both ports are distinguished by their
ability to deliver adequate port depths in the otherwise shallow waters of the Wadden Sea.
Finally, a number of small and medium sized ports also contribute to the supply of easy and efficient
access to waterborne transport in the borderland region. The ports of Kolding and Aabenraa offer
modern reception facilities and are important to the region for the supply of building materials,
foodstuff and other forms of dry bulk.
0
200
400
600
800
1000
1200
1400
1600
Aabenraa Havn Esbjerg Havn Fredericia Havn Kolding Havn
PRELIMINARY DRAFT
[11]
2.4 Aviation
Civil aviation in the EU, including domestic routes, is based on an internal market with free access for
all carriers in all EU/EEA member states. The companies decide which routes they will serve based on
their commercial considerations.
Domestic scheduled civil aviation in Denmark is concentrated to at present six routes to and from
Copenhagen Airport. Two of the routes serve Southern Jutland: Billund, 130 km from the German
border, and Sønderborg, 50 km from the border.
In 2013 approximately 135.000 passengers travelled between Copenhagen Airport and Billund Airport
and approximately 41.000 passengers travelled between Sønderborg Airport and Copenhagen Airport.
There are at present three routes linking Southern Jutland with Germany: between Billund and
Frankfurt, Munich and Düsseldorf.
The numbers of passengers from Billund and the German destinations are shown in table 2.4.1
Table 2.4.1. Numbers of passengers from Billund Airport to German destinations.
Route Passengers, 2013
Billund – Frankfurt 192.000
Billund – München 14.000
Billund –Düsseldorf 9.000
Of the larger airports in Southern Jutland, Esbjerg Airport (80 km. from the border) has only routes to
Aberdeen and Stavanger and Vojens Airport (50 km. from the border) has no routes at all.
General aviation is a flexible and important means of transport for most of the regions greater
companies. From Billund Airport there are flights to a large number of airports - especially in Europe.
From both Billund Airport and Sønderborg Airport there are a considerable number of flights to
Copenhagen Airport, and from Copenhagen there are a large number of routes to intra- and extra-
European destinations. Esbjerg Airport is essential for especially the off-shore industry.
Domestic flight routes between Danish and international airports can help to ensure a high level of
regional accessibility and will contribute to regional development, especially for remote areas where
travel time to Copenhagen is considerably shorter by plane than by train and ferry. Also the airports
become essential to the companies in relation to commercial interaction and connectivity and thereby a
key element when securing development and economic growth in the regions.
PRELIMINARY DRAFT
[12]
Germany
2.5. Roads
A 7 motorway
The most important road connection between the Scandinavian countries and Continental Europe is the
A7 motorway (European road E 45), which leads in a north south direction through all of Germany up
to Frederikshavn in the north of Denmark. In Schleswig-Holstein, the A 7 follows the route of the
historical “oxen trail”. The Schleswig-Holstein part of the motorway is 146 kilometres long, has four
lanes and a hard shoulder as required by German highway standards. The hard shoulders between the
exits Hamburg-Schnelsen-Nord and Kaltenkirchen and between Neumünster-Süd and the three-way
interchange Bordesholm can be used in cases of a high volume of traffic. The A 7 motorway crosses Kiel
Canal near Rendsburg on the Rader Bridge, a viaduct measuring 1.5 kilometres in length.
The state capital of Kiel is connected to the A 7 by the A 215 motorway at the three-way interchange
“Bordesholm” and by the A 210 at the four-way interchange Rendsburg. The A 7 is connected with
several federal highways which mainly run in an east west direction and partly in a north south
direction. In the city of Hamburg, the A 7 has mostly 6 lanes and 8 lanes in front of the Elbe Tunnel. The
three-way interchange “Hamburg-Nordwest” in the city of Hamburg connects the A 7 and the A 23
coming from Heide.
As a principal thoroughfare the A 7 absorbs a major share of the traffic running in north- south
direction with considerable transit traffic from and to Denmark and/or Scandinavia. With the
completion of the Store Bælt Link in 1997, the traffic has partially shifted from the “Vogelfluglinie” to
the A 7. There is also an increase in commuter traffic mainly in direction to and from Hamburg,
meaning that the volume of traffic keeps growing close to Hamburg. The highest volume of traffic is
close to the Elbe Tunnel with an average of 150,000 vehicles per day. Because of the traffic jams that
occur very often, the Elbe Tunnel is getting to be more of a bottleneck than ever before.
The A 7 is especially important for the mobility of the people from Schleswig-Holstein. For many
businesses in Schleswig-Holstein, the A 7 is the most important transport link to the relevant markets,
which are often far away. Also for this reason it is especially important that the efficiency of the A 7 be
preserved by needs-oriented extension projects. Concrete projects plans are described in Chapter 4.1.
Rader Bridge
Reconstruction work done on the bridge piers in July 2013 brought to light previously unforeseeable
extensive damage to the bridge with substantial static impact. After consultation of a testing engineer
traffic restrictions needed to be imposed at short notice so as not to risk further damage to the load-
bearing capacity of the bridge:
- closure of the bridge for vehicles over 7.5 t in both directions
- narrowing of lanes in both directions to single-lane operation
- permanent monitoring of the “trouble spot”
These traffic restrictions had serious consequences, especially for the north- and south-bound traffic
and thus for destinations in the northern part of Schleswig-Holstein and in Denmark.
PRELIMINARY DRAFT
[13]
The damaged bridge piers were repaired immediately so that the high-level bridge at Rade could
reopened for two-lane traffic in both directions on Nov. 11, 2013. For
vehicles exceeding 7.5 t however, the following restrictions are still in place:
- speed limit of 60 km/h for trucks
- ban on overtaking for trucks and a minimum distance of 25 m (also in traffic jams)
- closure of both hard shoulders still effective
- maximum load of 84 t for (approved) heavy haulages still effective
Originally the Rader Bridge had an operating life expectancy of 80 to 100 years. A static recalculation
done in mid-2014 resulted in a remaining useful life of only 12 years. A timely replacement, i.e. a new
construction crossing Kiel Canal is of utmost priority.
A 23 motorway and B 5 federal highway
In the west of Schleswig-Holstein the most important transport routes are the B 5 federal highway and -
from Heide to Hamburg - the A 23 motorway, which connect the west coast region. The B 5 crosses the
German-Danish border north of Süderlügum. It is then called European road E 11 and runs via Esbjerg
to the north of Jutland up to Aalborg. The volume of traffic towards Hamburg is increasing considerably
on the B 5 and A 23, respectively, as will be shown in the following chapter. Concrete expansion projects
are described in Chapter 4.1.
A 20 motorway
The A 20 motorway is gradually being built from east to west in order to create a highly competitive
east-west main thoroughfare - from Poland to the Netherlands. The A 20 will be connected with the A
21 motorway near Bad Segeberg, with the A 7 near Bad Bramstedt and with the A 23 near Hohenfelde. A
fixed link across the river Elbe is planned near Glücksburg and a connection with the A 26 and the A 27
in Lower Saxony. This project including the fixed link across the river Elbe has been included as an
urgent priority in the German Federal Transport Infrastructure Plan.
With the final extension of the A 20 it will be possible to circuit and decongest the busy traffic hub of
Hamburg and to improve the connection to the less developed west coast of Schleswig-Holstein. At that
point in time, the A 20 will also be an attractive transport route for the transit traffic running to and
from Denmark.
There is an agreement in the coalition contract of the political parties forming the government of
Schleswig-Holstein that the A 20 will be extended up to the A 7 in this legislative period (until 2017).
The sections west of the A 7 including the fixed link across the river Elbe will be planned nonetheless.
2.6. Railway
In Schleswig-Holstein the rail network is traditionally orientated towards the railway hub of Hamburg,
with the main lines running to Sylt ("marsh railway-line "), Flensburg ("Jutland-line"), Kiel, Lübeck and
Fehmarn ("Vogelfluglinie"). This rail network is supplemented by cross-country routes. In the Jutland
Corridor, these are the following lines: Flensburg-Kiel, Husum-Jübek-Kiel, Kiel-Lübeck, Heide-
Neumünster-Bad Oldesloe and Niebüll-Tønder and - with a more regional character - the lines Niebüll-
Dagebüll, Husum-Bad St. Peter Ording and Heide-Büsum.
In the Hamburg Metropolitan Region the lines Hamburg-Eidelstedt, Ulzburg-Norderstedt and
Elmshorn-Henstedt-Ulzburg of the AKN Eisenbahn AG as well as the suburban rail lines (S-Bahnen) to
PRELIMINARY DRAFT
[14]
Wedel and Aumühle play an important role in commuter traffic. Besides, there are rail networks for the
transport of cargo in Kiel, Lübeck and Brunsbüttel.
In the Jutland Corridor international passenger and cargo transport mainly runs on the line of the same
name. The Jutland-line running to Hamburg via Flensburg, Schleswig, Rendsburg and Neumünster is
double-tracked, electrified and constructed for a speed of 160 km/h. Near Rendsburg, the railway
crosses Kiel Canal on a high-level bridge which was built in 1913. At present, the bridge is undergoing
thorough restoration and will be dimensioned for bigger weight charges (load for each wheel of 22.5
tons). Until completion, which is planned for the year 2016, the bridge is a bottleneck because of the
speed and weight limitations. Once the bridge has been modernized, it can be crossed by 2 trains at the
same time and is expected to have an additional operating life of at least 30 years.
The Jutland-line and the marsh railway-line converge in Elmshorn. From Elmshorn and/or Pinneberg
the route is complemented with regional railway and suburban traffic. With the introduction of the
Store Bælt-Link in 1997, all of the cargo haulage by rail was shifted to the Jutland-line. This track
section has nearly reached the limits of its capacity. However, it is expected that the introduction of the
Fehmarnbelt Fixed Link will shift parts of the transit activities from the Jutland-line back to the
Vogelfluglinie and thus relieve the Jutland-line somewhat.
The Federal Transport Infrastructure Plan (“Bundesverkehrswegeplan” - BVWP) of 2003 includes a
three-tracked extension of the rail system between Elmshorn and Pinneberg as a so-called urgent need
(“Vordringlichen Bedarf”). In autumn 2010, a re-evaluation of the planned projects was undertaken
with the result that the above-mentioned extension is no longer necessary because of the anticipated
relief provided by the completion of the Fehmarnbelt Fixed Link. As an alternative to a conventional
three-tracked extension, the State of Schleswig-Holstein has suggested an improvement of the suburban
connections in this section, which would also free up capacity on the main track. This project was
submitted for the 2015 BVWP.
On the whole, the railway hub of Hamburg is a bottleneck, especially for the rail traffic running in
southern direction. The problem was studied by the BMVBS (especially in a report about the
“Development and assessment of a concept for the railway hub Hamburg of March 2009”). The report
recommends that the rail connections to the south be extended for the transport of containers and for
suburban passenger trains.
The marsh railway-line leading from Hamburg to Sylt is mainly double-tracked except for a few one-
tracked sections, designed for a speed of 140 km/h and electrified from Hamburg to Itzehoe. In Niebüll,
the marsh line is connected with the Danish railroad network via Tønder and Esbjerg by the privately
owned company Norddeutsche Eisenbahngesellschaft Niebüll GmbH (neg). A 17.7 km long, single-
tracked and non-electrified section between Niebüll and Tønder that had been closed down in 1980 was
reactivated in 1997. A few years ago, extensive reconstruction work was done on the track with financial
support from the State of Schleswig-Holstein.
2.7. Ports and shipping
There are two regular ferry services between Germany and Denmark. On the one hand, there is the so-
called “Vogelfluglinie” between the ports of Puttgarden and Rödby and, on the other, there is a ferry-
connection between the ports of List on the island of Sylt and Havneby on the island of Rømø. As this
PRELIMINARY DRAFT
[15]
report focuses exclusively on the Jutland Corridor only the line between List and Havneby will be
discussed.
For individual transport from the mainland this 16-km-long ferry connection, inaugurated in 1963,
represents a popular alternative to the rail link via the Hindenburg-damm. The ferry service is operated
by Syltfahre.de, an enterprise of the FRS (Förde Reederei Seetouristik), using a double-ended ferry
called SyltExpress. The crossing takes approx. 35-40 minutes.
This report does not discuss Kiel Canal (NOK). Whereas the NOK plays a preeminent role as an
international waterway in the transport of cargo into the entire Baltic Sea region, largely to and from the
Port of Hamburg, it does not have a special function for the cross-border transport of goods in the
Jutland Corridor.
2.8. Air traffic
The airfield Flensburg-Schäferhaus is the only airfield with a cross-border function in the Schleswig-
Holstein part of the Jutland Corridor. Due to its location near the border it is also used by Danish
customers. Already founded in 1910, the airfield has three runways altogether. One of them, made of
bitumen, has a length of 1.580 m and a maximum weight-bearing capacity of 30 t. For this reason, the
airfield is well suited for business charter flights.
Air-charter enterprises offering commercial and private flights as well as sightseeing flights are located
in the vicinity of the airfield. Moreover, Germany’s largest seaplane enterprise has its seat in Flensburg.
Flight schools offer lessons for flying airplanes, gliders, ultra-light planes and seaplanes as well as for
parachuting. Aerial advertisement and hangar places are offered. Besides, an aviation-technical
company (servicing and repair of motorized aircraft) is located on the airfield as well. The fuelling
facilities provided offer AVGAS 100 LL for piston engines as well as jet A 1 (kerosene) for turboprop
aircraft and jet engines. The water aerodrome Flensburg-Sonwik on Flensburg fjord is also nearby.
Beyond the borders of Schleswig-Holstein, the airport at Hamburg-Fuhlsbüttel (Hamburg Airport) is
interesting also for Danish travellers. It offers a huge number of German and European destinations as
well as some intercontinental connections.
PRELIMINARY DRAFT
[16]
Chapter 3. Development in traffic in the Jutland corridor from 2000 to today.
Figures and facts
This chapter has its focus on the development in traffic in the Jutland corridor within the last decade.
The chapter describes the development in Denmark and Germany respectively.
Denmark:
3.1 Roads
Developments in traffic concerning roads can be analyzed by using several parameters. For example
with traffic performance calculated by the mileage of the various means of transport travels during a
period. The traffic performance thereby expresses to what extent the load of traffic affects the
infrastructure. Figure 3.1.1 shows the trend in traffic performance (driven km) in Southern Jutland. As
seen on the figure the traffic has been increased 2003 – 2013.
Figure 3.1.1 Trends in traffic performance in the Southern Jutland 2003 – 2013
(2001=index 100)
There is a fall in traffic growth in 2007 due to the financial crisis.
Map 3.1.1 indicates traffic trends based on traffic counting 2003 – 2013 at selected locations on the
trunk roads in the southern part of Jutland.
96
98
100
102
104
106
108
110
112
114
116
118
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
PRELIMINARY DRAFT
[17]
Map 3.1.1 Traffic growth at specific locations on the trunk road network in the southern
part of Jutland, 2003 – 2013.
From 2003 – 2013 there has been an increase in the number of vehicles passing the two border trunk
roads between Denmark and Germany. Figure 3.1.2 shows the trend in the number of vehicles crossing
the border and Figure 3.1.3 shows the development in truck traffic across the Danish-German border
(northbound) from 2003 – 2013.
PRELIMINARY DRAFT
[18]
Figure 3.1.2 Trends in the number of vehicles passing the Danish-German border in
Jutland 2003 - 2013 (2000 = index 100).
As seen on the figure the number of vehicles passing the Danish-German border have been relatively
stable for the crossing at Frøslev, while the amount of crossings at Sæd is increasing steadily with a
slight drop in 2013.
Figure 3.1.3. Development in truck traffic across the Danish-German border
(northbound) 2003 - 2013 (Index 100 = 2002)
Source: International Transport Danmark and estimates made by the Danish Road Directorate
0
20
40
60
80
100
120
140
160
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
Sæd
Frøslev
90,0
95,0
100,0
105,0
110,0
115,0
120,0
125,0
130,0
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
PRELIMINARY DRAFT
[19]
Figure 3.1.3. shows that after the drop in truck traffic across the Danish-German border in a
northbound direction in 2008, the level in 2013 has increased to almost that of 2007.
Overall the growth in traffic in Southern Jutland is similar to the growth in the rest of Denmark.
3.2 Railway
Freight transportation
There is an ambition to improve rail road freight transportation in Southern Jutland and across the
border. A freight terminal will be established in Esbjerg together with a rail line to the Port of Esbjerg
linking railroad freight to sea transport. Vestas has chosen the railway as the preferred way of transport
of wind mill wings from Lauchhammer in Germany to the Port of Esbjerg.
The chart below illustrates the development in freight transport (tonnes of cargo) in the period 2000-
2013. The railroad freight transit has increased by 240 per cent since 2000. The railway freight
transportation in and out of Denmark across the German border (measured in tonnes) has declined by
58 per cent in the same period.
Figure 3.2.1. Development in rail freight transport across the Danish-German border
2000-2013
Source: Statistics Denmark
According to the Danish Transport Authority2 the railway freight transit traffic will increase by 5.2 per
cent per year until the opening of the Fehmarn Belt Fixed Link. Hereafter the total growth in transit
freight through Denmark, until the establishment of double track on the German side of the border, is
expected to be 31 per cent.
2 Danish Transport Authority: Trafikplan for den statslige jernbane 2012-2027.
0
1.000
2.000
3.000
4.000
5.000
6.000
7.000
8.000
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
Thousand tonnes
Transit freight
International freight
PRELIMINARY DRAFT
[20]
With the opening of the Fehmarn Belt Fixed Link in 2022 a substantial share of transit traffic will be
directed from the route via Padborg to the route via Fehmarn. After this shift the freight traffic via
Padborg is expected to grow again until full capacity is established in the German Hinterland of the
Fehmarn Belt Fixed Link through the establishment of double track.
Passenger transportation
The intercity trains operating every two hours between Copenhagen and Flensburg are the backbone of
the railway traffic via Padborg. The trains – operated by DSB – have a German train control system. In
Flensburg there are connections to high speed regional trains to Hamburg every hour. In addition two
international trains operate across the border between Aarhus-Hamburg (-Berlin). The daily night
service operating between Copenhagen and Basel/Berlin/Prague was closed in November 2014.
Out of the 400.000 train passengers travelling across the Padborg border each year, approximately 80
per cent travel to and from Jutland and 20 per cent to and from Funen and Zealand.
On the Tønder-Niebüll rail line, regional trains cross the border every two hours. In Niebüll there are
good connections to high speed regional trains to Hamburg. The number of passengers crossing the
border by train via Tønder is 80.000 per year that support operation of regional trains3.
The map beneath depicts annual passenger trips in 1995 and 2012 and shows an increase in number of
passengers crossing the border via Padborg. It is not possible to draw conclusions on passenger
development on the rail line crossing the border via Tønder due to the lack of data from 1995.
3 Danish Transport Authority: Hearing edition of the national traffic plan.
PRELIMINARY DRAFT
[21]
Map 3.2.1. Annual passenger trips in 1995 and 2012
3.3 Ports and shipping
Traffic volumes in Southern Jutland ports can roughly be divided into two categories; freight and
passenger transport.
Freight
In general, Danish ports also felt the consequences of the global economic downturn. Activity in ports
and the amount of freight volumes handled entered into a downward trend in the years 2008-2010.
After three consecutive years of reduced activity, the pattern appeared to be changing in 2011 as freight
volumes grew. However in 2012 volumes decreased slightly again but grew in 2013, albeit cautiously
(fig. 3.3.1).
PRELIMINARY DRAFT
[22]
Fig. 3.3.1: Development in freight volumes in Danish ports (1000 t)
Source: Statistics Denmark
In terms of the transport of goods between Southern Jutland ports and Germany, the impact of the
economic downturn is less apparent. Although 2008 did coincide with a slight downwards trend in
goods volumes, the development in the subsequent years appears to be less of a result of the general
economic climate. According to fig. 3.3.2 the transport of goods between Southern Jutland ports and
Germany are more or less on par with the situation before the global economic downturn.
The port of Fredericia stands out as the port with the largest freight volumes with a growth exceeding
that of 2008. After a significant increase in freight volumes in 2010, volumes dropped in 2011, but have
since then increased in the two succeeding years and have almost reached the volume of 2010.
0
10000
20000
30000
40000
50000
60000
70000
80000
90000
100000
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
Development in freight volumes in Danish ports (1000 t)
PRELIMINARY DRAFT
[23]
Fig. 3.3.2: Development in freight volumes between Southern Jutland ports and Germany
(1000 t)
Source: Statistics Denmark
Passenger transport
The ferry service from the port of Esbjerg to the island of Fanø is the busiest domestic service in
Denmark. In 2013 the ferry service handled almost 1.6 million passengers and more than 300.000
private cars.
South Jutland is also home to a second domestic ferry link between the island of Als (Fynshav) and
Funen (Bøjden). The Fynshav-Bøjden link represents an important alternative to the fixed link across
the Little Belt and provides a shortcut to Funen for the border region.
In addition to the domestic Southern Jutland ferry lines, an international route operates between the
island of Rømø (Havneby) and Sylt (List). The 2013 traffic volumes of the Rømø-Sylt link are listed in
table 3.3.1. A sizeable passenger transport and the substantial accommodation of bicycles are indicative
of the importance of the ferry link to local communities and not least with regard to tourism.
Table 3.3.1: Transport volumes, Rømø-Sylt
2013
Passengers 321.000
Cars 49.509
Busses 1.301
Lorries 8.642
Bicycles 8.141
Source: Statistics Denmark
0
200
400
600
800
1000
1200
1400
1600
1800
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
Development in freight volumes between Southern Jutland ports and Germany (1000 t)
Aabenraa Havn
Esbjerg Havn
Fredericia Havn
Kolding Havn
PRELIMINARY DRAFT
[24]
3.4 Air traffic – The case of Sønderborg Airport
Sønderborg Airport is owned by Sønderborg Kommune (municipality). The airport was historically tied
to the Danish airline Cimber (later Cimber Sterling) which had its head office at the airport and for 46
years served the route to and from Copenhagen until its bankruptcy in May 2012.
The route was immediately taken over by the Danish carrier DAT. In 2013 Air Alsie stated up on the
route instead of DAT. In 2013 the airport had about 43.000 passengers whereof about 41.000 used the
only scheduled route to and from Copenhagen.
As part of its development plans, in 2010 the airport engaged a consultancy firm to report on the
possibilities for changing the airport into a “binational” Danish/German airport, or for other co-
operative arrangements, with the main purpose of attracting more passengers from the German side of
the border to the existing route to Copenhagen and to new routes that might be created. Within 1 ½
driving hour from the airport live 1.6 million people, whereof 40 per cent in Germany. The analysis has
received support from the EU’s European Regional Development Fund.
PRELIMINARY DRAFT
[25]
Germany
3.5. Development in road traffic
The development of traffic volume in the Jutland Corridor is shown in the following figures. The maps
based on Germany-wide traffic counts present the average traffic per day (Monday to Sunday)
expressed in number of vehicles per day. These counts distinguish between:
- KFZ = all types of motor vehicles and
- SV = the share of heavy vehicle traffic (more than 12 tons in weight and busses).
Traffic count in the year 2000:
PRELIMINARY DRAFT
[26]
Traffic count in the year 2005:
PRELIMINARY DRAFT
[27]
Traffic count in the year 2010:
As regards the A7 motorway, it can be concluded that the volume of traffic has risen between the years
2000 and 2010. The rise in traffic volume is above average especially in the area close to the border,
whereas it is the more moderate the further south one gets. But still, this trend is no indication of the
efficiency of this particular road section given that the absolute congestion rate is higher than in the
north. Consequently, the capacity of the A7 motorway north of the interchange A7 / A215 can be
considered to be adequate. Merely individual road sections, as for example the area of the Rader
Hochbrücke, the high-level bridge near Rendsburg, are critical at certain times. South of the above-
mentioned motorway interchange, traffic capacity levels are exceeded regularly, especially in the area
around Neumünster and in the metropolitan area of Hamburg.
A similar development is to be noted as regards the motorway A 23 and the federal highway B 5,
respectively: over-proportional increases can be observed in the area close to the border; whereas
towards the south the increases of traffic are more moderate. Problems on the B 5 are mainly caused by
tourist and agricultural traffic in the summer months, especially in the section between Tönning and
Bredstedt. South of Heide the quantity of traffic reaches a volume that warrants the profile of a
motorway.
In general terms, it can be concluded that there has only been a moderate increase in heavy vehicle
traffic in Schleswig-Holstein. Again, a disproportionate rise can be noted in the area close to the border.
3.6. Development in rail traffic
PRELIMINARY DRAFT
[28]
Currently, there are two border crossings between Schleswig-Holstein and Denmark used by local
passenger traffic (SPNV), namely Flensburg - Padborg and Niebüll - Tønder. Via the respective train
stations on the Danish side of the border there are through trains from Flensburg to Kolding, Odense,
Roskilde and Copenhagen as well as from Niebüll to Esbjerg.
The border crossing at Flensburg - Padborg is used by the SPNV as well as by international long-
distance passenger and cargo traffic. While the state is responsible for the SPNV as a so-called
“Aufgabenträger”, i.e. operator, it does not have any immediate influence on long-distance traffic,
because that is run commercially by Deutsche Bahn AG (DB AG) and the Danish state rail (DSB).
For long-distance transport 2 pairs of trains (Hamburg-Århus and Berlin-Århus) are offered by DB AG
und DSB. For local passenger traffic, the so-called SPNV, the State of Schleswig-Holstein provides 9
pairs of trains, offering a connection every two hours. The trains mostly run directly from Flensburg to
Copenhagen, with Danish IC3 multiple unit trains being used for this line. These trains featuring a
standard appropriate for long-distance travel also serve as a substitute in this function. A considerable
increase in the number of passengers travelling daily was achieved since the DSB took over operations
in 2011, with the number rising from nearly 250 passengers per day to more than 400 passengers per
day.
The border-crossing Niebüll - Tønder was reopened in the past few years for the “SPNV” and the offer of
transport options is being extended step by step. Currently, there are 10 pairs of trains crossing the
border on workdays and 7 on weekends. The railway company Arriva, a foreign subsidiary of the DB AG,
provides the service, which is mainly used by German pupils attending the Danish high school in
Tønder. The number of passengers using this line is rising steadily and demand is particularly high in
summertime due to the tourists. It has been possible to step up demand substantially since the year
2006. As a model of good cross-border cooperation the
Danish Trafikstyrelsen is in charge of this section of the line.
The following table shows the development of the average number of passengers per day in cross-border
passenger traffic, i.e. SPNV:
Railway line 2003 2006 2010 2011 2012 2013
Tønder - Süderlügum 57 98 131 112 133 132
Padborg - Flensburg 267 252 262 420 420 391
Altogether, cross-border passenger rail-traffic which started from a low level is developing very
successfully. In order to support this trend, there are plans to extend both connections to run on an
hourly basis in the medium- to long-term.
3.7. Development in shipping
Ferry services between List/Sylt and Havneby/Rømø have developed as follows (expressed in tons):
2000 2010 2011 2012 2013
Transshipment 53,654 t 59,994 t 92,634 t* 86,546 98,036
Passengers 415,467 421,072 389,563 295,411 323,672
PRELIMINARY DRAFT
[29]
Increase in quantity because of some bigger building projects on the island of Sylt
3.8. Development of freight traffic
In the area of the A 7 motorway border crossing at Ellund the average everyday quantity of traffic (dtV)
has risen from approx. 12,400 vehicles in 2005 to 16,200 in 2010. The share of trucks is approx. 25%. In
the area of the B 5 federal highway/ border to Denmark the dtV has risen from 4,283 motor vehicles in
2000 to 5,771 vehicles in 2010, with the share of trucks being approx. 4% (Source: Traffic count in
2010). In 2008, the cross-border volume of freight traffic in the area of Germany/ Northern border-
region and Denmark amounted to 23.7 million tons by truck and 6.2 million tons by rail (Source: CB
Log of Oct. 14, 2010).
3.9. Development of air traffic
In the year 2000, some 16,600 flight movements were counted on the airfield Flensburg-Schäferhaus
(takeoffs and landings by airplanes). The number amounted to 13,200 in the year 2005 and 12,900 in
2011.
At the airport of Hamburg-Fuhlsbüttel approx. 165,000 flight movements and some 10 million
passengers were counted in 2000. In 2005, the number of flight movements dropped to about 156,000
(with 10.7 million passengers) and in the year 2013 there were 144,000 aircraft movements (with 13.5
million passengers).
A survey done at Hamburg airport in 2013 revealed that app. 110,000 Danish passengers used the
airport (journey from Denmark and flight from / to Hamburg, without transit passengers from
Copenhagen). Thus, the share of Danish passengers was less than 1%.
PRELIMINARY DRAFT
[30]
Chapter 4. Current infrastructure programmes in Denmark and Germany -Focusing
on the Jutland corridor.
Denmark
The Jutland corridor is the backbone of the Jutland infrastructure system. In the Danish road system,
the Jutland corridor is represented mainly by the E45 motorway in Eastern Jutland, which has provided
a high level of mobility and economic development in the region. However, the growth in traffic causes
increasing congestion on parts of E45, which will be one of the key issues for the future infrastructure to
handle.
Within the last few years, several initiatives have been carried out for the benefit of the motorists on
E45. In 2013, the most trafficked stretch at Vejle was expanded, and in 2014 the capacity at Kolding was
enlarged by inclusion of the emergency lanes. With the political transport agreement of 24 June 2014 it
was decided to allocate DKK 38.9 million for the construction of a third southbound lane south of the
Limfjord Tunnel at Aalborg, where the accessibility is currently challenged. Furthermore, approx. DKK
100 million was given in grants to four new interchanges at Skanderborg, Kolding, Aarhus and Horsens.
In addition, several road projects in the Jutland corridor are ready to be initiated, when the funding is
provided. This is the case for an extension of the motorway between Fredericia and Kolding and a Third
Limfjord Fixed Link at Aalborg, which have both been analyzed at the EIA level.
With regard to the long-term development strategies, the Jutland corridor has been part of a broader
planning effort, which has identified large-scale infrastructure demands in the years after 2020 and
major strategic options for further infrastructure investments beyond 2020 (the strategic analyses).
This work was initiated by a broad political agreement in 2009 and finalized in the spring 2014 with a
summary report.
The strategic analyses have identified two main long-term development strategies for
north/southbound road capacity in Jutland:
Further development of the motorway capacity in the E45 corridor
Different models for establishment of a new motorway corridor in Central Jutland
The analyses show that the cheapest and most effective way to deal with the growing congestion
problems in East Jutland in 2030 will be a gradual expansion of the E45 corridor. Environmentally, it
will be relatively little intrusive to expand the highway in the existing corridor. But in terms of traffic, it
will be disturbing for road users in the periods in which construction work is in progress.
Another strategy is to establish a new motorway corridor though Central Jutland, e.g. the so-called
“Hærvejsmotorvej”. A new motorway corridor through Central Jutland can both absorb some of the
traffic from the E45 and connect some Central and West Jutland towns that are not currently connected
to the motorway network. The strategic analyses show that especially the central corridor
(“Hærvejsmotorvejen”), can postpone the needs for expansions of the E45. However, the project is very
extensive and expensive with a construction budget of DKK 15-20 billion. The full relief impact in
relation to E45 requires that the new motorway is fully established, which is estimated to take at least 15
PRELIMINARY DRAFT
[31]
years. In addition, even with a fully established Central Jutland motorway, congestion will still occur in
some sections of E45
Overall, the report concludes that irrespective of the chosen long-term development strategy in Jutland,
it will be necessary to expand the stretches of the E45, which are already congested at present.
In recent years there has also been invested heavily in upgrading the existing rail infrastructure in
Denmark. The political accord states that the train must be a viable alternative to the car, and most of
the traffic growth in the future must be absorbed by public transport.
Investments have also been made in the European Rail Traffic Management System (ERTMS) that will
harmonize the European signal systems and make all Danish rail transport more efficient. Installation
will start on early deployment lines in 2016 for testing in commercial service before the main roll-out of
the new signalling system. The new signalling system will be implementet before the end of 2021 with
an overlap between lines, prioritised according to the traffic level, with roll-out taking place first on the
most heavily used lines.
It has been decided to upgrade the single track section between Vamdrup and Vojens of 20 km. to
double tracks. The upgrade will be finalised ultimo 2015 and will eliminate the bottleneck between
Vamdrup and Vojens.. It has also been decided to electrify the railway between Esbjerg and Lunderskov.
This is the first step towards electrification of the most important Danish rail lines. The electrification
will provide a modern, cheaper, more stable and environment friendly railway.
Furthermore investments will be made in a program focussing on repairing and replacing rail tracks
and bridges in order to improve the reliability.
In January 2014 the Danish government agreed with the parliament on the so-called “Train Fund
Denmark”, which will modernize the Danish railway system dramatically. Denmark will spend almost
€4 billion – from harmonization of the taxes on oil from the North Sea – with the purpose of building
new tracks for high speed trains and the electrification of the main rail-system. According to the plan,
Denmark will invest in 90 km [55 miles] new high-speed double-track lines. Additionally, existing lines
will be upgraded and almost 600 km [370 miles] of tracks will be electrified. The Train Fund will result
in massive investments in the railway system, which will also benefit the transport corridors to
Germany.
Train Fund Denmark will be realized in the middle of the 2020’s according to the plan.
Finally ports play a key role in terms of Danish international trade. The main share in terms of volume
of all imports and exports is transported by ship. This makes ports a central node for freight transport
also providing intermodal transport.
PRELIMINARY DRAFT
[32]
Germany
In principle, federal transport routes in Germany are planned and financed by the federal level (Bund).
The main strategic planning instrument encompassing all transport modes is the Federal Transport
Infrastructure Plan (BVWP), which classifies projects into the categories “urgent need” (Vordringlicher
Bedarf) and “additional need” (Weiterer Bedarf). However, the BVWP is not a finance plan, meaning
that even projects classified as an urgent need do not "automatically" get their funding. The existing
BVWP from the year 2003 has been underfinanced for years now because of the gap between the
financial need and the actually available funds of the federal transport budget.
Essentially, the BVWP decided by the Federal Government only has the nature of a recommendation.
However, the plan was taken up by German Parliament (Bundestag) for the federal railways and the
major federal roads in the so-called "needs plan" (Bedarfsplan), which is an annex to both the Federal
Railway Extension Act (Bundesschienenwegeausbaugesetz (BSchwAG) and the Federal Trunk Road
Extension Act (Fernstraßenausbaugesetz (FStrAbG). These two laws provide that 5-year plans be drawn
up for the concrete realisation of the needs plan. For this purpose, the Federal Ministry of Transport
and Digital Infrastructure (BMVI) compiles so-called “investment framework plans”
(Investitionsrahmenplan - IRP) for a period of 5 years. The current IRP is valid for the period from 2011
to 2015.
At present, the BMVI is working on an update of the BVWP which shall be applicable from 2015. The
following bullet points summarize the current status of the procedure:
The BMVI presented its basic concept in the spring of 2014.
A new traffic forecast for the period up to the year 2030 has been available since the summer
of 2014.
The period for submission of projects is over. The projects will be reviewed by the BMVI
and/or their external consultants on the basis of defined criteria (cost-benefit criteria etc.)
The BMVI intends to draft an overall plan from these separate projects and to discuss this
draft in the federal cabinet.
The main problem which transport infrastructure planning is faced with is that the federal transport
budget has been structurally underfunded for many years. Only roughly one half of the projects
included in the urgent need category of the 2003 BVWP could be realised to date. The condition of the
existing transport infrastructure has deteriorated Germany-wide. As a result, the BMVI announced in
its basic concept that the maintenance of the existing infrastructure shall have absolute priority. In
terms of expansion, priority shall be accorded to the removal of traffic bottlenecks and to the major axes
and freight traffic corridors.
State roads (Landesstraßen) are essentially financed by the state budget and municipal roads and lanes
by the municipalities and counties. For municipal building projects the federal state and the state of
Schleswig-Holstein grant subsidies under certain conditions according to the German Community
Transport Financing Act (Gemeindeverkehrsfinanzierungsgesetz (GVFG).
In the following the most important extension projects are presented.
PRELIMINARY DRAFT
[33]
4.1. Roads
Upgrading of the A 7 motorway
Because of the growing traffic volume the A 7 motorway will be expanded between the interchange at
Bordesholm and the Elbtunnel in Hamburg from four to six or eight lanes, respectively.
In Schleswig-Holstein the expansion is planned on a length of 65 kilometres. This expansion project
costing about € 372 million is included in the “urgent need” category (Vordringlicher Bedarf) of the
BVWP as well as in the IRP 2011-2015. It will be executed in a public-private partnership as a so-called
availability model (Verfügbarkeitsmodell), meaning that besides the expansion, the private company
also takes over maintenance and operation services for a period of 30 years. A monthly remuneration is
paid for these services. Furthermore, bonus-penalty regulations have been agreed upon. The project
also contains a basic renewal of the existing lanes. To avoid delays as far as possible, 2 lanes per
direction can be used by vehicles during the construction period. Therefore, the expansion work will be
done on one side only, while the traffic runs on the other side.
Legally binding plan approval notices have been granted for all construction sections in Schleswig-
Holstein. A construction consortium was awarded the contract after completion of the tendering
procedure. Construction work is scheduled to begin at the end of 2014 and to be completed after four
years in 2018.
In the city of Hamburg 3 sections are planned for the expansion to 6 or 8 lanes, partly with coverings.
Work on the construction in Hamburg-Schnelsen began in the middle of 2014; the last section in
Hamburg-Othmarschen will be finished in 2025.
The need to build a substitute for the Rader high bridge by the year 2026 at the latest was already
discussed in Chapter 2.1.
Extension of the A 20 motorway
To provide relief for the Hamburg Elbtunnel along the A 7 motorway, a northwest bypass of Hamburg
including a new link across the river Elbe will be realised by the A 20 motorway being built in
different sections. The A 20 - coming from Mecklenburg-Vorpommern - is already being used by traffic
east of Bad Segeberg. The A 20 motorway with all its sections - albeit in different realization categories
– is part of the IRP 2011-2015.
The plan approval decision for the adjoining sections between Weede and Wittenborn (south of Bad
Segeberg with the connection to the A 21 motorway) was ruled to be unlawful and unenforceable by the
Federal Administrative Court in Leipzig. The Federal Administrative Court has decided in favour of the
claims filed by several conservation groups and one community. According to the ruling, the errors
found are not of such a quality that the plans as a whole must be called into question a priori. As part of
the further procedure, the State of Schleswig-Holstein is conducting more extensive fauna studies and is
assessing alternate routings especially in terms of their environmental compatibility
The impact of the above-mentioned court decision on the following sections of the motorway from
Wittenborn up to the river Elbe and for the fixed link across the Elbe itself must also be evaluated and
considered in the pan approval procedure. The Schleswig-Holstein Ministry of Transport assumes that
there will be a delay of approx. 2 years because of this reworking of the project.
PRELIMINARY DRAFT
[34]
Funding needs to be secured for all but one (between Hohenfelde and Sommerland) of the adjoining
sections (west of Wittenborn). As for the fixed link across the river Elbe, the Schleswig-Holstein
Ministry of Transport has proposed a funding model like those used for the Oresund and Fehmarnbelt
fixed links, where a state-run planning company implements the project, guaranteeing the debt service
by a state guarantee and thus enabling the raising of low-interest credits.
Extension of the A 23 motorway and the B 5 federal highway
Several extension projects are planned for the A 23 and B 5. The new bridge across the river Stör was
completed in June 2010. Demolition work on the old bridge has been carried out since October 2011.
The extension of the A 23 motorway from Itzehoe-South to Itzehoe-North (a four lane-expansion of the
B 5 to the A 23) has been started. Completion of the entire segment including a newly built second
bridge across the river Stör is scheduled for 2015.
The section of the B5 between Itzehoe and Wilster-West is being upgraded to three lanes. The first
construction stage was completed in April 2014. The plan approval procedure is currently under way for
the second construction phase. An upgrade of the highway between Wilster-West and Brunsbüttel is the
long-term aim as soon as the two above-mentioned sections have been completed.
In the area of the B 5 between Tönning and Husum planning for a three-lane-traffic management
system has begun. The objective is to enhance road safety and to be able to better manage peaks in
seasonal traffic. The plan approval procedure has been initiated for the first section. The construction
plans for sections 2 to 4 are currently being drawn up.
To boost the competitiveness of the west coast area, the BVWP-project “B 5 bypass Hattstedt –
Bredstedt” will be realised in addition. The plan approval notice was granted on March 30, 2012, but is
pending at court. At present, a plan revision procedure is being carried out. The project is included in
the IRP.
The state government is of the opinion that the current traffic volume and the traffic volume expected in
the medium-term do not warrant a four-lane motorway-like expansion of the B 5 federal highway north
of Heide up to the Danish border, as is demanded by the region.
4.2. Railway
The following expansion projects are planned for the Jutland Corridor:
- upgrading and modernisation of the railway station in Elmshorn with the construction of a
fourth platform line
- improvement of the suburban rail connection from Hamburg to Elmshorn including an
expansion to three tracks between Elmshorn and Pinneberg.
The projects are incorporated in the urgent need category of the BVWP – albeit in a somewhat different
configuration (cf. Section 2.2). However, financing has not been secured as yet.
Work on the design and permit planning for a continuous double-track upgrade and electrification of
the A1 line between Hamburg-Eidelstedt and Kaltenkirchen operated by AKN is currently in progress.
The new line “S 21” will enable rapid transit from Kaltenkirchen to Hamburg Central Station.
PRELIMINARY DRAFT
[35]
As regards the marsh railway line, the State of Schleswig-Holstein wishes to achieve a complete double-
track extension and electrification of the line between Itzehoe and Westerland. For this purpose, the
project has been submitted to the Federal MOT for inclusion in the BVWP, the Federal Transport
Infrastructure Plan.
Currently, there are no plans to extend the Niebüll-Tønder line.
4.3. Shipping
To the best of the State Government’s knowledge no extension projects are planned for cross-border
traffic.
4.4. Air traffic
To the best of the State Government’s knowledge no extension projects are planned for the airfield at
Flensburg-Schäferhaus.
PRELIMINARY DRAFT
[36]
Chapter 5. Prioritised projects by the Danish-German Transport Commission
In the previous chapters the interim report from the Danish-German Transport Commission was
updated. In chapter 5 the projects which the members of the commission have prioritised will be
described. The projects are categorised into different categories according to geography and mode of
transport. To each project a fact sheet has been made, which gives a short introduction to the most
important facts about the project. This chapter lists the different fact sheets according to the category
the fact sheet has been ascribed to.
The fact sheets focus on either the Danish or the German side, but several of the projects are cross-
border by nature. When possible the fact sheets from the Danish/German side of a related project will
follow one another.
Fact sheets are categorized into railway/road and western/mid-eastern corridor as listed in the table on
the following page. Projects which cannot meaningfully be ascribed to any of the above categories are
categorized as “other”.
The western corridor
The south-western part of Jutland and north-western part of Germany are connected with the
summerhouse area on the west coast both by Route 11/B5 running from Esbjerg to Heide and the rail
line Bramming – Tønder – Niebüll. Thus this road and railway section is of great importance for the
local traffic as well as for tourists visiting the West coast during holidays.
The mid/eastern corridor
The E45/A7 represents the international connection between Norway and part of Sweden and the rest
of Europe and serves much of the national northbound and southbound traffic and passenger flows
through Jutland to Germany and to the rest of Europe. The E45/A7 produces a high level of mobility
and economic development in the region. The motorway serves several types of traffic, which are all
growing in volume. This goes for commuter traffic, traffic within and between regions and international
traffic flow towards Germany and Europe.
The railway running from Hirtshals – Aalborg – Aarhus –Hamburg is of great importance to both
passenger traffic as well as freight traffic. More than half of the trailers arriving by ferry in Hirsthals are
destined south of the Danish-German border and is therefore highly relevant for the Scandinavian rail
freight corridor between Hirtshals and Hamburg.
All fact sheets are shown in appendix A to E.
PRELIMINARY DRAFT
[37]
Western corridor Mid/eastern corridor
Roads Upgrade/extensions
of Route 11/B5 New motorway through central Jutland
Expansion of the A 7 motorway to six lanes from the
interchange at Bordesholm to the Danish border
Construction of a bridge to replace the Rader Bridge
Establishment of a Danish-German mobility
management system for steering traffic guidance
measures while expansion work is in progress on
the A 7 motorway
Extension of the A 20 motorway with a fixed link
across the river Elbe west of Hamburg at Glückstadt
B 199 –Bypass around Handewitt
East-West connections in Schleswig-Holstein
Railway Upgrade Bramming-
Tønder - Niebüll
Improvement of the
railway services
along the westcoast
Extension of marsh
railway-line
Improvements on the Scandinavian rail freight
corridor Hirtshals-Hamburg
Double track and high speed Aarhus-Hamburg
Extensions in the intermodal terminal in Padborg
Jutland-railwayline: Improvement of the transport-
services
Jutland-railwayline: shortening of passage time
Cooperation between the combined transport
terminals of Padborg and Neumünster
Replacement of the high level rail bridge in
Rendsburg by a new structure
Other Standardisation of signalling system in Germany and Denmark
Speed upgrade of the rail line Sønderborg-Tinglev
Common Danish-German railway station
Cross-border shipping in the fjord of Flensburg
Logistics
Airtraffic: Use of aiports in Sønderborg and Billund for German customers
Extension of electro-mobility
PRELIMINARY DRAFT
[38]
Chapter 6. Recommendations The members of the Danish-German Transport Commission agree that not all of the proposed projects
can be achieved within a short period of time. The recommendations from the commission are therefore
categorised into short/medium term, long term and very long term achievements.
The recommendations of the Danish-German Transport Commission are listed below.
1. Proposals for objectives implementable in the short or medium term
Expansion of the A 7 motorway from the interchange at Bordesholm to the Elbtunnel in Hamburg:
Establishment of a Danish-German mobility management system for steering traffic guidance measures.
Construction of the A 20 motorway (some sections in the long-term).
Upgrade of the A 23 motorway and the B 5 federal highway: - Closure of the gap near Itzehoe - Expansion to three lanes between Itzehoe and Wilster-West (2nd construction phase) - Expansion to three lanes between Tönning and Husum (partly long-term as well) - Bypass construction between Hattstedt and Bredstedt
Construction of a bypass around Handewitt (B 199 federal highway realignment)
Improvements of the Scandinavian rail freight corridor Hirtshals-Hamburg
Speed upgrade of the rail line Sønderborg-Tinglev
Extensions in the intermodal terminal in Padborg
Speed upgrade of the railway line Bramming-Tønder-Niebüll
Jutland rail line: - Expansion of the long-distance rail services on the Jutland line (second daily ICE-connection) - Expansion of the single-tracked sections in Denmark (between Tinglev and Padborg as well as
between Vanderup and Vojens)
Cross-border passenger shipping on the inner Flensburg Fjord.
Intensified use of the airports at Sønderburg and Billund by potential customers from Schleswig-Holstein
2. Proposals for objectives implementable in the long term
Upgrade of Route 11/24
Construction of a replacement for the Rader high level bridge as part of the A 7 Motorway.
Construction of the A 20 motorway (western sections, fixed link across the Elbe river).
Expansion of the B 5 federal highway: - Expansion of the section from Wilster-West to Brünsbüttel to three lanes
PRELIMINARY DRAFT
[39]
- Expansion of the section between Tönning and Husum to three lanes.
Establish a common Danish-German railway station
Double track, high speed and electrification on the Aarhus-Hamburg rail line
Jutland rail line: Construction of a replacement for the high level rail bridge at Rendsburg
Cooperation between the Padborg and Neumünster rail logistics terminals.
Standardization of signaling technology (ETCS).
Marsh railway line: Expansion to an uninterrupted double-tracked, electrified line
3. Proposals for objectives implementable in the very long term
Construction of a new motorway through central Jutland
Expansion of the A 7 motorway to six lanes from the interchange at Bordesholm to the Danish border.
B 5 federal highway: Expansion to three lanes from Husum to the Danish border (if there are substantial increases in traffic volume and the E 11 is also expanded in Denmark).
For a description of the recommended projects see appendix A-E