presentation for health and safety coordination cern safety coordination mission and role m. arnaud,...
TRANSCRIPT
Presentation for health and safety coordination
CERN Safety CoordinationMission and Role
M. Arnaud, C. Bedel, J. Etheridge, E. Paulat
CERN Safety; who is Responsible?
M. Arnaud, C. Bedel, J. Etheridge, E. Paulat
M. Arnaud, C. Bedel, J. Etheridge, E. Paulat
1998 Start of safety Coordination at CERN (CERN/TIS-GS/98-
10)2000
Start of the dismantling of the LEP, working for an out side work package contractor under TIS responsibility
2004 Internalization within the then TS Department
2007 Transferred to departments BE, EN, PH,
2009 Appointment of a fourth safety coordinator for GS
M. Arnaud, C. Bedel, J. Etheridge, E. Paulat
The Safety Coordination is involved from the conception stage and they are consulted if there are major modifications to be carried out.
There by ensuring that prevention is built in where ever possible.
This improves the working conditions, reduce risks, improves the quality of the work and therefore save time and money.
We take part in all phases of the operations we are involved, CERN wide.
M. Arnaud, C. Bedel, J. Etheridge, E. Paulat
A. The function and the name:“Safety Coordinator at
CERN" applies only to category A work
B. The security for category B work remains the responsibility of contracts managers (in each
group) and work supervisors
M. Arnaud, C. Bedel, J. Etheridge, E. Paulat
To protect everyone working on CERN sites.We take into account all the risks, resulting
from co-activity and successive activities.We ensure that the general principles of
prevention are implemented .We endeavor to prevent incidents and
accidents.Our work is based upon the information
provided by CERN staff members, collaborators, users, work package contractors…
M. Arnaud, C. Bedel, J. Etheridge, E. Paulat
How does the Safety coordination operate
All work, tests, interventions, are:Planned. A notice to start work are issued (AOC) and
signed A Health and Safety Protection Plan is produced,
issued and commented upon.(PPSPS, Pdp, PCTS)Work package analyses meetings are arranged
DIMR, consignations, hot work permit, IS 37 etc.A Joint Inspection is then carried outSite visit are carried throughout the duration of
the works