procurement ivan chavez
TRANSCRIPT
1
Ivan ChavezGeneral Engineer
Overview of CommonProcurement and Contract
Administration Issues
October 24, 2012
24CFR 85.36Procurement Policy
approved by boardconforms to applicable federal, state and local law and regulations
covers all phases of procurement activity from award to close out
Procurement Handbook 7460.8 r2PIH Notices
Regulatory and Administrative Requirements
Prepare Cost Estimate and Price Analysis for each procurement action, including modification Cost Estimate: before soliciting bids or
proposals Price Analysis: after bids are received
Determine method of procurement to ensure cost is reasonable
Confidential
Procurement Planning
Use for Non-Competitive Proposals
Procurement under other types is not feasible
After solicitation, number of sources or competition is determined to be inadequate
An emergency situation existsHUD approves
Non-competitive proposals must be justified in writing
Contract Modifications
Independent Cost EstimateClear description of proposed workBroken down by labor and materialFixed priceEstimate of time of completionAdditional work must be part of original
scope of work Above $100,000 must be submitted to
HUD
Payments to Contractors
Must have construction progress schedule in place To ensure that scheduled dates and amount of work
to be completed are reasonable and consistent with contractProgress payments based on approved schedule of amounts
Request for payment on form HUD-51001, periodic estimate for partial payment
Contractor has submitted all certified payroll reports
Inspections
Frequent inspection of workCritical part of contract to ensure:
Workmanship is acceptableMaterials are installed as specified in contract
Conduct warranty inspectionsFinal inspection includes punch list
items
Contract Closeout
Following final inspection, contractor submits notarized contractor’s release which includes certification that:
Work was completed in accordance with construction documents
Total amount due the contractor and a separate stated amount for each unsettled claim against the HA
Contract Closeout (cont)
Documentation noting that HA is released of all claims
Wages paid to laborers or mechanics were consistent with the wage rate requirements and there are no outstanding claims for unpaid wages
Davis Bacon Requirements
Ensure weekly payrolls are received/reviewed
Complete HUD’s 11(employee interview)
Documentation
Must contain sufficient documentation to detail complete history of contracts
Critical component of contract administration in the event of litigation
12
Following your own procurement
policy is a requirement,
not a choice.