Page 0 Powerlink Queensland Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation Powerlink Queensland Project Assessment Draft Report 23 April 2019 Maintaining reliability of supply at Kamerunga Substation Disclaimer While care was taken in preparation of the information in this document, and it is provided in good faith, Powerlink accepts no responsibility or liability (including without limitation, liability to any person by reason of negligence or negligent misstatement) for any loss or damage that may be incurred by any person acting in reliance on this information or assumptions drawn from it, except to the extent that liability under any applicable Queensland or Commonwealth of Australia statute cannot be excluded. Powerlink makes no representation or warranty as to the accuracy, reliability, completeness or suitability for particular purposes, of the information in this document.

Upload: others

Post on 12-Oct-2019

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 0

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

Powerlink Queensland

Project Assessment Draft Report

23 April 2019

Maintaining reliability of supply at

Kamerunga Substation

Disclaimer

While care was taken in preparation of the information in this document, and it is provided in good faith, Powerlink accepts no responsibility or liability

(including without limitation, liability to any person by reason of negligence or negligent misstatement) for any loss or damage that may be incurred by

any person acting in reliance on this information or assumptions drawn from it, except to the extent that liability under any applicable Queensland or

Commonwealth of Australia statute cannot be excluded. Powerlink makes no representation or warranty as to the accuracy, reliability, completeness or

suitability for particular purposes, of the information in this document.

Page 2: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page i

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

Document Purpose

For the benefit of those not familiar with the National Electricity Rules (the Rules) and the National Electricity Market (NEM), Powerlink offers the following clarifications on the purpose and intent of this document:

1. The Rules require Powerlink to carry out forward planning to identify future reliability of supply requirements and consult with interested parties on the proposed solution as part of the Regulatory Investment Test for Transmission (RIT-T). This includes replacement of network assets in addition to augmentations of the transmission network. More information on the RIT-T process and how it is applied to ensure that safe, reliable and cost effective solutions are implemented to deliver better outcomes to customers is available on Powerlink’s website.

2. Powerlink must identify, evaluate and compare network and non-network options (including, but not limited to, generation and demand side management) to identify the ‘preferred option’ which can address future network requirements at the lowest net cost to electricity customers.

3. The main purpose of this document is to provide details of the identified need, credible options, technical characteristics of non-network options, and categories of market benefits addressed in the assessment. In particular, it encourages submissions from potential proponents of feasible non-network options to address the identified need.

Page 3: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page ii

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

Contents

Document Purpose .......................................................................................................................... i

Executive Summary ........................................................................................................................ 1

1. Introduction ............................................................................................................................. 3

2. Stakeholder engagement activities ......................................................................................... 5

2.1 Powerlink takes a proactive approach to engagement ................................................... 5

2.2 Working collaboratively with Powerlink’s Customer Panel Customer Panel ................... 5

2.3 Transmission Annual Planning Report (TAPR) – the initial stage of formal public consultation ............................................................................................................................. 5

3. Identified need......................................................................................................................... 6

3.1 Geographical and network overview ............................................................................... 6

3.2 Description of identified need .......................................................................................... 6

3.3 Assumptions underpinning the identified need................................................................ 7

3.4 Description of asset obsolescence and risks .................................................................. 7

4. Submissions received ............................................................................................................. 9

5. Required technical characteristics for non-network options ................................................... 9

5.1 Criteria for proposed network support services ............................................................... 9

6. Potential credible options to address the identified need ..................................................... 11

6.1 Material inter-network impact ........................................................................................ 13

7. Materiality of market benefits ................................................................................................ 13

7.1 Market benefits that are not material for this RIT-T assessment .................................. 13

7.2 Consideration of market benefits for non-network options ............................................ 14

8. General modelling approach adopted to assess net benefits ............................................... 14

8.1 Analysis period .............................................................................................................. 14

8.2 Discount rate ................................................................................................................. 14

8.3 Description of reasonable scenarios ............................................................................. 14

9. Cost benefit analysis and identification of the preferred option ............................................ 15

9.1 Net present values ......................................................................................................... 15

9.2 Sensitivity analysis ........................................................................................................ 16

10. Preferred option .................................................................................................................... 17

11. Conclusions ........................................................................................................................... 18

12. Draft recommendation. ......................................................................................................... 18

13. Submissions requirements .................................................................................................... 18

13.1 Submissions from non-network providers ..................................................................... 19

13.2 Assessment and decision process ................................................................................ 19

Page 4: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 1

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

Executive Summary

Introduction

Located approximately 10 kilometres north-west of Cairns, Kamerunga Substation, established in 1976, is a major injection point into the Ergon Energy distribution network. Planning studies have confirmed there is an enduring need for the substation to maintain the supply of electricity in the Cairns area.

Both the primary plant and secondary systems at Kamerunga Substation are nearing the end of their technical service lives with identified condition and obsolescence issues. The substation is also susceptible to major flooding events which could result in damage to equipment leading to loss of supply.

The condition of the primary plant and secondary systems at Kamerunga substation, along with the existing flood risk, exposes customers to the risks and consequences of an increasingly unreliable electricity supply.

There is a need for Powerlink to address this emerging risk to ensure customers in the area continue to receive safe, reliable and cost effective electricity services into the future and to meet mandated jurisdictional and National Electricity Rules’ (the Rules) obligations.

This Project Assessment Draft Report (PADR) has been prepared as part of a prescribed process under the National Electricity Rules (the Rules) for the proposed transmission investment. It contains the results of the planning investigation and cost benefit analysis of credible options, identifying the proposed preferred option for implementation in accordance with the Australian Energy Regulator’s (AER’s) Regulatory Investment Test for Transmission (RIT-T).

Options considered

Powerlink published a Project Specification Consultation Report (PSCR) with respect to maintaining reliability of supply at Kamerunga Substation to Registered Participants, the Australian Energy Market Operator (AEMO) and interested parties in September 2018. The PSCR invited submissions of credible options to replicate the services that the Kamerunga Substation provides to customers in the Cairns area, while maintaining the Rule’s reliability obligations on an enduring basis.

No submissions were received in response to the PSCR that closed for consultation on 21 December 2018. As a result, no additional credible options (network or non-network) have been identified as part of the PSCR stage of this RIT-T consultation.

Powerlink proposed four credible network options in the PSCR to meet the identified need at Kamerunga Substation.

A Base Option reflecting a conventional approach to ensuring continued compliance with the secondary systems obligations in the Rules, along with a staged replacement of primary plant, serves as the basis of comparison between options. This approach involves a full secondary systems equipment replacement, housed in a new prefabricated building, and the staged replacement of selected primary plant over an eight year period.

This option has then been compared with three other options in which the secondary systems are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS) technology, or an alternative Gas Insulated Switchgear (GIS) technology, in a single stage.

Evaluation and Conclusion

The RIT-T requires that the proposed preferred option maximises the present value of net economic benefit to all those who produce, consume and transport electricity in the market compared to other credible options.

The difference between the options relates primarily to the type of technology utilised, the timing of the primary plant replacement, and the way in which each option addresses potential Woree feeder trips and flood risk.

Due to the nature of the investment, none of the credible options considered, including the proposed preferred option, are expected to give rise to material market benefits.

The credible network options and their net present value (NPV) are summarised in Table 1.

Page 5: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 2

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

Table 1: Summary of credible network options

Option Description Capital cost ($m 2018/19)

Weighted NPV ($m 2018/19)

Ranking

Base Option

Single stage secondary system replacement. Staged AIS primary plant replacement. Flood operable by October 2028

26.70 -22.03 3

Option 1

Single stage secondary system replacement. Single stage AIS primary plant replacement. Flood operable by October 2022

23.20 -22.21 4

Option 2

Single stage secondary system replacement. Single stage GIS primary plant replacement including additional switching functionality. Flood operable by October 2022

24.62 -21.41 1

Option 3

Single stage secondary system replacement. Single stage AIS primary plant replacement including additional switching functionality. Flood operable by October 2022

23.75 -21.45 2

The economic analysis shows only $0.04 million difference between the NPV of Options 2 and 3, which represents less than 0.2% of the estimates for these options, well within the expected margin of accuracy. Given this, Options 2 and 3 are considered equal as the highest ranked options in economic terms.

This PADR includes a draft recommendation to implement Option 3 as it:

satisfies the RIT-T based on the cost benefit analysis (i.e. equal lowest cost in NPV terms with consideration for estimating accuracy)

utilises existing technology within the Powerlink network, removing the need to acquire new spares and undertake additional training for personnel (compared to Option 2)

addresses the risk to electricity supply from flood inundation in a single construction phase at the current Kamerunga Substation site by October 2022

provides increased security of supply through the inclusion of circuit breakers (CBs) on the Woree feeders

Option 3 involves replacing Kamerunga’s current primary plant with new AIS equipment, installing additional circuit breakers for the Woree feeders and the full replacement of all secondary systems in a new building. All primary plant and secondary systems are to be located above the 1 in 200 year flood level. Design work would commence in early 2020, with preparatory construction activities occurring on-site in late 2020. All work would be completed by October 2022. The indicative capital cost of this option is $23.75 million in 2018/19 prices.

Submissions

Powerlink welcomes written submissions on this ‘Project Assessment Draft Report’. Submissions are particularly sought on the credible options presented.

Submissions are due on or before Friday, 7 June 2019.

Please address submissions to:

Roger Smith Manager Network and Alternate Solutions Powerlink Queensland PO Box 1193 VIRGINIA QLD 4014 Tel: (07) 3860 2328 [email protected]

Page 6: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 3

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

1. Introduction

Powerlink Queensland is a Transmission Network Service Provider (TNSP) in the National Electricity Market (NEM) that owns, develops, operates and maintains Queensland’s high-voltage electricity transmission network. This network transfers bulk power from Queensland power stations to electricity distributors Energex and Ergon Energy (part of the Energy Queensland Group), and to a range of large industrial customers.

Powerlink’s approach to asset management includes a commitment to sustainable asset management practices that ensure Powerlink provides valued transmission services to its customers by managing risk,1 optimizing performance and efficiently managing assets through the whole of asset life cycle.2

Planning studies have confirmed there is a long-term requirement to continue to supply the existing electricity services currently provided by Kamerunga Substation, to customers in the Cairns area.

The ageing primary plant and secondary systems at Kamerunga Substation are nearing the end of their technical service lives and are increasingly at risk of failure due to their deteriorated condition, with many items of equipment no longer supported by their manufacturer and limited spares available.

Studies have also shown the substation would be inundated with 1.6 metres for a 1 in 200 year event, causing extensive damage to its protection and control systems and loss of supply. This would result in a significant risk to supply in the area, while also leaving Powerlink operating Kamerunga Substation outside the recommended State Planning Policy3 guidelines for major substation infrastructure.

The requirements for initiating solutions to address the risks arising from the condition of the current network assets at Kamerunga Substation remaining in-service are set down in the National Electricity Rules (the Rules) and Powerlink must take action to address these risks within the RIT-T framework.

The proposed credible network options maintain existing electricity services to customers in the area by addressing the increasing likelihood of faults arising from the condition of Kamerunga’s ageing and obsolete primary plant and transformers, as well as the threat of flood inundation.

When developing the credible options, Powerlink has focussed on implementing cost effective solutions that ensure a reliable supply, delivering better outcomes for customers.

This Project Assessment Draft Report (PADR) is the second step in the RIT-T process4. It:

describes the reasons why Powerlink has determined that investment is necessary (the ‘identified need’), together with the assumptions used in identifying this need

notes that no submissions were received in response to the Project Specification Consultation Report (PSCR) published on 25 September 2018

describes the credible options that Powerlink currently considers address the identified need

discusses the classes of market benefits which are not likely to be material for this RIT­T5

presents the Net Present Value (NPV), economic assessment of each of the credible options (as well as the methodologies and assumptions underlying these results)

1 Risk assessments are underpinned by Powerlink’s corporate risk management framework and the application of a range of risk assessment methodologies set out in AS/NZS ISO31000:2018 Risk Management Guidelines. 2 Powerlink aligns asset management processes and practices with AS ISO55000:2014 Asset Management – Overview, principles and terminology to ensure a consistent approach is applied throughout the life cycle of assets 3 Queensland Government, Department of Infrastructure, Local Government and Planning – State Planning Policy – State Interest Guidelines, Natural Hazards, Risks and Resilience, April 2016 4 This RIT-T consultation was commenced in September 2018 and has been prepared based on the following documents: National Electricity Rules, Version 112, 18 September 2018 and AER, Final Regulatory Investment Test for Transmission Application Guidelines, September 2017. 5 As required by clause 5.16.1(c)(iv) of the Rules.

Page 7: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 4

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

identifies and provides a detailed description, including the estimated construction timetable and commissioning date, of the credible option that satisfies the RIT-T, and is therefore the proposed preferred option

provides stakeholders with the opportunity to comment on this assessment so that Powerlink can refine the analysis (if required) as part of the Project Assessment Conclusions Report (PACR).

Figure 1.1: RIT-T process overview

This RIT-T met the requirements to apply the expedited RIT-T process. However, given the flood mitigation considerations in addition to the identified need, and the varied technology of the options, Powerlink considered that this RIT-T presented an additional opportunity for engagement and consultation with Registered Participants, the Australian Energy Market Operator (AEMO), and other interested parties. As such, exemption from issuing a PADR was not sought.

Page 8: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 5

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

2. Stakeholder engagement activities

Delivering electricity to almost four million Queenslanders, Powerlink recognises the importance of engaging with a diverse range of customers and stakeholders who have the potential to affect, or be affected by, Powerlink activities and/or investments

2.1 Powerlink takes a proactive approach to engagement

Powerlink regularly hosts a range of engagement forums and webinars, sharing information with customer and stakeholders the broader community. These engagement activities help inform the future development of the transmission network and assist Powerlink in providing services that align with the long term interests of customers. Feedback from these activities is also incorporated into a number of publically available reports

2.2 Working collaboratively with Powerlink’s Customer Panel Customer Panel

Powerlink’s Customer Panel provides a face-to-face opportunity for customers and consumer representative bodies to give their input and feedback about Powerlink’s decision making, processes and methodologies. It also provides Powerlink with another avenue to keep customers and consumers better informed, and to receive feedback about topics of relevance, including RIT-Ts.

The Customer Panel is regularly advised on the publication of Powerlink’s RIT-T documents and briefed quarterly on the status of current RIT-T consultations, as well as upcoming RIT-Ts, providing an ongoing opportunity for:

the Customer Panel to ask questions and provide feedback to further inform RIT-Ts

Powerlink to better understand the views of customers when undertaking the RIT-T consultation process.

The Customer Panel was advised of the RIT-T consultation for maintaining the reliability of supply at Kamerunga Substation in Panel meetings from April 2018.

Powerlink will continue providing updates to and request input from the Customer Panel throughout the RIT-T consultation process.

2.3 Transmission Annual Planning Report (TAPR) – the initial stage of formal public consultation

Powerlink identified in its TAPR from 2015 to 2018, an expectation that action would be required at Kamerunga Substation to maintain transfer capabilities and reliability of supply in the Far North transmission zone.6

The 2018 TAPR also highlighted that Powerlink anticipated the commencement of a RIT-T within the next 12 months.

Members of Powerlink’s Non-network Engagement Stakeholder Register (NNESR) were directly advised of the publication of the TAPR and the accompanying compendium of potential non-network solution opportunities (Appendix F), which set out the indicative non-network requirements to meet the identified need at Kamerunga Substation.

No submissions proposing credible and genuine non-network options have been received from prospective non-network solution providers in the normal course of business, in response to the publication of TAPRs or as a result of stakeholder engagement activities.

6 This relates to the standard geographic definitions (zones) identified within the TAPR.

Page 9: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 6

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

3. Identified need

This section provides an overview of the existing arrangements at Kamerunga Substation and describes the risk to supply from the assessed condition of the transmission assets.

3.1 Geographical and network overview

Kamerunga Substation is located approximately 10 kilometres north west of Cairns. It was established in 1976 and consists of a switchyard operating at 132kV7. It provides the only injection point to the 22kV network in the Cairns Northern Beaches area, including Cairns Airport and connects the Barron Gorge Power Station to the transmission network. The Far North Queensland transmission network is shown in Figure 3.1.

Figure 3.1: Far North Queensland transmission network

3.2 Description of identified need

With peak demand in the Cairns area forecast to remain at or slightly above current levels, it is vital that electricity supply be maintained to satisfy these demands and for Powerlink to meet its reliability of supply and safety obligations under the Electricity Act 1994, Electrical Safety Act 2002 and Transmission Authority8.

Powerlink’s condition assessment of the ageing assets at Kamerunga has highlighted that the majority are nearing the end of their technical service life with much of the substation’s primary plant, protection, control and supervisory systems no longer supported by their respective manufacturers.

In addition to the risks posed by ageing assets, the substation also has a significant loss of supply risk in the case of a major flood event, as it is currently not constructed to withstand a 1 in 100 year or 1 in 200 year flood. Further, the current configuration of the substation also poses a risk to the supply of electricity to the Cairns North area, and connection of the Baron Gorge Power Station to the network, should the Woree feeders trip for a fault on one of the feeders.

7 Supplied by two 132kV feeders from Woree, Kamerunga Substation connects Barron Gorge Power

Station to the network through two additional 132kV feeders. The two 132/22kV transformers are connected to Ergon Energy’s network via a 22kV underground cable. 8 Queensland Transmission Authority T01/98

Page 10: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 7

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

3.3 Assumptions underpinning the identified need

The need to invest is driven by Powerlink’s obligations to address the increasing risks to supply arising from the condition of ageing and increasingly obsolete assets as well as the potential for flood inundation at Kamerunga Substation. If not addressed, these risks can extend the time taken to recover (or even prevent recovery) from faults, due to a lack of support from manufacturers and a lack of spare parts.

Powerlink’s obligations as a TNSP9 require it to maintain (including repair and replace if necessary) its transmission grid to ensure the adequate, economic, reliable and safe transmission of electricity, including the ability to meet peak demand if a major element of the network was to fail. For Kamerunga, this includes ensuring the ongoing availability of its primary switchgear and instrument transformers to ensure the ongoing reliable supply of electricity to customers.

Under the Rules, Powerlink is also required to provide sufficient primary protection systems and back-up protection systems to ensure that a fault of any type anywhere on its transmission system is automatically disconnected.10 In the event of an unplanned outage, the Power System Security Guidelines published by AEMO, require that the primary network assets must be taken out of service within 24 hours.11

It follows that the increasing likelihood of faults arising from the condition of ageing assets and their obsolescence compels Powerlink to undertake reliability corrective actions at Kamerunga Substation if it is to continue meeting the standards for reliability of supply and comply with the obligations for protection system availability, as set out in the Rules.

The State Planning Policy12 also requires Powerlink design, locate and operate its substations to avoid adverse impacts on the community during and immediately following a 1 in 200 year flood event.

3.4 Description of asset obsolescence and risks

Kamerunga Substation consists of two 132/22kV power transformers and associated 132kV bays, four 132kV feeder bays, and associated secondary systems. It was established in 1976 with the two transformers being replaced in 1990 and 1996 respectively.

The majority of primary plant including circuit breakers, earth switches, disconnectors, bus bars and surge arrestors date back to the late 1970s, and present an increasing risk of failure with very few spares available and no manufacturers’ support for repairs. The circuit breakers in both transformer bays are of particular concern given their age, condition and consequences of failure.

The circuit breakers in transformer bay 1 were manufactured in 1981 and installed on site in 1984. These circuit breakers have had increased failure rates due to frequent issues with the air compressors. The circuit breakers in transformer bay 2 have been in service since 1976 and are showing significant age related degradation resulting in slower clearance times and an increased risk of failure to operate. In both cases, these circuit breakers are no longer supported by their manufacturers.

The increasing risk to the reliability of the primary plant has the potential to directly impact supply, while the lack of spares and manufacturer support increases significantly the timeframe to rectify such failures and restore the network to a resilient state.

Furthermore, the absence of any dedicated circuit breakers on the Woree feeders means a trip to either of these results in maintenance crews having to be despatched to site to manually isolate the faulted line.

9 Schedule 5.1a System Standards and 5.1.2 Network Reliability of the Rules, and Queensland Transmission Authority T01/98 10 Clause S5.1.9(c) of the Rules requires that faults are automatically disconnected in accordance with clause S5.1.9 (e) or clause S5.1.9(f) 11 AEMO Power System Operating Procedure SO_OP_3715 – Power System Security Guidelines (the Rules require AEMO to develop and publish Power System Operating Procedures pursuant to clause 4.10.1(b) of the Rules, which Powerlink must comply with per clause 4.10.2(b)). 12 Queensland Government,Department of Infrastructure, Local Government and Planning – State Planning Policy – state interest guidelines, Natural hazards, risks and resilience, April 2016

Page 11: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 8

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

In addition to the increased risk to supply due to the deteriorated condition of the primary plant, the site also has inherent design issues. Due to the age of the site, the switchyard was not designed to meet current electrical clearance distances. This is managed on site through temporary earthworks. The control building at Kamerunga has only a single 125V DC supply, impacting the reliability and security of the secondary systems.

The majority of the secondary system equipment at Kamerunga Substation was installed over 20 years ago and is now at or reaching the end of its technical service life. The equipment is no longer supported by the respective manufacturers and spare parts are no longer available. Consequently, these secondary systems are maintained with an increasingly limited stock of spare parts and without manufacturer support for repairs.

The lack of manufacturer support and spare equipment, and the reliability of the ageing equipment are becoming an unacceptable risk to ongoing reliable supply of electricity to the local community. Additionally, most devices are located in corridor type panels that present space constraints and potential safety issues during maintenance activities.

Powerlink uses an asset health index rating to categorise at-risk secondary systems equipment, based upon the equipment functional failure rate (i.e. failure to operate as intended), the environmental condition where the assets are installed and the equipment physical and effective age.

Health indices are modelled in the range from zero (0) to ten (10), where zero represents new assets and ten indicates that the asset requires immediate action to address its increasing risk of unreliable operation. The impact of equipment obsolescence is also considered when determining the recommended action.

A summary of health index scores and recommended actions for each group of secondary systems at Kamerunga is set out in Table 3.1.

Table 3.1: Summary of secondary system health index scores at Kamerunga Substation

Bay Construction year

Health index range (average)

Description

22kV Earthing Transformers

1990-2010 3.0-10.0

(7.7)

Majority of equipment is obsolete, with insufficient spares to support ongoing operation.

Remedial action required

Transformer Bays

1990-2002 6.7 – 10

(8.7)

50% of equipment has a health index of 10, and is subject to increasing failure rates.

Majority is obsolete, with insufficient spares to support ongoing operation.

Remedial action required

Feeder Bays 1998 and 2006 4.9 – 8.6

(6.6)

Majority of equipment is obsolete, with insufficient spares to support ongoing operation.

Remedial action required

Metering Bays 1999-2014 3.3-8.2

(6.0)

Interface switches are obsolete. Equipment is located in constrained corridor panels.

Remedial action required

Non-bay secondary systems(incl SCADA & OpsWAN)

1997-2005 6.8-10

(8.9)

Majority of equipment is obsolete, with insufficient spares to support ongoing operation.

Remedial action required

Page 12: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 9

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

Poor asset condition increases the risk of secondary system faults, while obsolescence increases the time needed by Powerlink to rectify the faults, potentially up to several weeks as panel wiring and test plans are needed on an individual basis. The inability to repair, replace, or otherwise resolve secondary system faults can have operational consequences, as this reduces the overall resilience of the transmission network to subsequent forced outages.

The Kamerunga Substation site is also susceptible to flooding events and was originally designed with insufficient drainage. The substation is located in low-lying terrain, in tropical North Queensland, which is subject to heavy rainfall and cyclonic events. Studies have shown that the substation would be inundated with 1.25 metres of water during a 1 in 100 year flood event and 1.6 metres for a 1 in 200 year event, resulting in extensive damage it its protection and control systems and loss of supply. The current risk of inundation at the substation also leaves Powerlink operating Kamerunga Substation outside the recommendations of the State Planning Policy guidelines13.

Notwithstanding the assessed condition of the asset, Powerlink’s ongoing operational maintenance practices are designed to monitor plant condition and ensure any emerging safety risks are proactively managed.

Taking into consideration the most recent analysis and understanding of the risks arising from the condition of the primary plant and secondary systems at Kamerunga Substation remaining in-service, the proposed network solution has been deferred by approximately 16 months to October 2022 compared to the possible commissioning date of June 2021 as noted in Powerlink’s 2018 Transmission Annual Planning Report (TAPR).

4. Submissions received

Powerlink published a PSCR in September 2018 seeking submissions from Registered Participants, AEMO and interested parties on the credible options presented, and for any alternative credible network and non-network options that could replicate the support that Kamerunga Substation provides the Ergon Energy 22kV network in meeting the Rule’s reliability obligations on an enduring basis.

There were no submissions received in response to the PSCR that was open for consultation until 21 December 2018.

As a result, at this stage of the RIT-T consultation, Powerlink is not aware of any:

non-network options that could be adopted, either in full or in conjunction with a network option to meet or defer the identified need of October 2022 or

additional credible options that could deliver a material market benefit.

This PADR provides a further opportunity for submissions from all stakeholders and for providers of feasible non-network or network options to submit details of their proposals for consideration.

5. Required technical characteristics for non-network options

The information provided in this section is intended to enable interested parties to formulate and propose genuine and practicable non-network solutions such as, but not limited to, local generation and Demand Side Management (DSM) initiatives.

5.1 Criteria for proposed network support services

A non-network solution that avoids replacement of the primary plant and secondary systems at Kamerunga Substation would need to replicate the functionality, capacity and reliability of the substation on an enduring basis.

Any non-network option able to provide supply to the 22kV network of up to a peak 60MW, and up to a peak 900MWh per day on a continuous basis would allow for the decommissioning of the

13 Queensland Government, Department of Infrastructure, Local Government and Planning – State Planning Policy – state interest guidelines, Natural hazards, risks and resilience, April 2016

Page 13: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 10

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

Kamerunga substation and bridging of the Woree to Kamerunga Feeders to the Kamerunga to Barron Gorge Feeders.

Powerlink has identified the following common criteria that must be satisfied if any proposed non-network solutions are to meet supply requirements14.

Size and location

Proposed solutions must be large enough, individually or collectively, to provide the size of injection or demand response set out above from the end of 2022. The level of support is however dependent on the location, type of network support and load forecasts.

Due to the bulk nature of the transmission network, aggregation of sub 10MW non-network solutions will be the sole responsibility of the non-network provider.

Notwithstanding the location of any solution, each proposal would require assessment in relation to technical constraints pertinent to the network connection, such as other intra-regional transfer limits, fault level or quality of supply impacts of operation.

Operation

A non-network option would need to be capable of operating continuously 24 hours per day over a period of years.

If a generation service is proposed (either standalone or in conjunction with other services), such operation will be required regardless of the pool price15.

Proponents of generation services are advised that network support payments are intended for output that can be demonstrated to be additional to the plant’s normal operation in the NEM.

Reliability

Proposed services must be capable of reliably meeting electricity demand under a range of conditions and, if a generator must meet all relevant National Electricity Rules requirements related to grid connection.

Powerlink has obligations under the National Electricity Rules, its Transmission Authority and connection agreements to ensure supply reliability is maintained to its customers. Failure to meet these obligations may give rise to liability. Proponents of non-network options must also be willing to accept any liability that may arise from its contribution to a reliability of supply failure.

Timeframe and certainty

Proposed services must be able to be implemented in sufficient time to meet the identified need using proven technology and, where not already in operation, provision of information in relation to development status such as financial funding and development timeline to support delivery within the required timeframe must be provided.

Duration

The agreement duration for any proposed service will provide sufficient flexibility to ensure that Powerlink is pursuing the most economic long run investment to address the primary plant and secondary systems condition risks at Kamerunga Substation.

Powerlink welcomes submissions from potential proponents who consider that they could offer a credible non-network option that is both economically and technically feasible.

15 The National Electricity Rules prevent a generator that is providing network support from setting the market price.

Page 14: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 11

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

6. Potential credible options to address the identified need

Powerlink identified four credible options in the PSCR and has further considered these four options as part of this PADR. These options are outlined in Table 6.1.

Table 6.1: Credible Options

Option Description

Indicative capital cost

($million, 2018/19)*

Indicative annual O&M costs

($million, 2018/19)

Base Option

Full secondary systems replacement with prefabricated building and partial AIS primary plant replacement on existing foundations and structures. Primary plant established at current flood level. Commission by October 2021

Replace Barron Gorge 132kV feeder circuit breakers. Commission by October 2024

Replace remaining AIS primary plant using new foundations and raised structures. Fit new foundations and raised structures to primary plant installed in 2021. All primary plant established to comply with 1 in 200 year flood level. Flood operable by October 2028. Commission by October 2028

26.70 0.20

Option 1

Single stage secondary system replacement. Single stage AIS primary plant replacement. Flood operable by October 2022.

Commission by October 2022

23.20 0.19

Option 2

Single stage secondary system replacement. Single stage GIS primary plant replacement including additional switching functionality. Flood operable by October 2022.

Commission by October 2022

24.63 0.08

Option 3

Single stage secondary system replacement. Single stage AIS primary plant replacement including additional switching functionality. Flood operable by October 2022.

Commission by October 2022

23.75 0.12

*The original capital cost of the options in the PSCR were inadvertently labelled as 2017/18 prices. These costs have been re-labelled as 2018/19 prices and remain unchanged for all but Option 2. Option 2 has been further refined to include the additional costs arising from the adoption of a different substation technology in the Powerlink network.

All credible options address the risks arising from the condition of the ageing secondary systems and primary plant, as well as the risk of flood inundation. Options 1, 2 and 3 address flood operability by 2022, while the Base Option results in the substation becoming flood operable by 2028. Both the Base Option and Option 1 retain the current switching capabilities in that they do not include circuit breakers (CBs) on the Woree feeders.

Page 15: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 12

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

None of these options has been discussed by the Australian Energy Market Operator (AEMO) in its most recent National Transmission Network Development Plan (NTNDP).16

Additional options that have been considered but not progressed, due to not being either economically or technically feasible, were identified in the PSCR.

Any recovered primary plant with a remaining technical service life will be retained as spares for the network.

The primary plant to be installed under each option again reflects the exclusion of circuit breakers on the Woree feeders under the Base Option and Option 1, as well as the substitution of current live tank circuit breakers with dead tank circuit breakers with integrated current transformers under all but the Base Option.

Table 6.2: Primary Plant to be installed under each network option

Surge

Arrestors Current

Transformers Voltage

Transformers

Live-Tank Circuit

Breakers

Dead-Tank Circuit

Breakers Isolators

Earth Switches

Base 18 12 12 5 - 9 3

Option 1 18 12 12 - 5 9 3

Option 2 18 12 12 - 7 9 3

Option 3 18 12 12 - 7 9 3

Secondary systems are essentially the same for each option, with the exception of no circuit breaker protection on the Woree Feeders under the Base Option and Option 1. (See Table 6.3)

Table 6.3: Secondary systems equipment to be replaced or modified

System Type

Protection and control systems 4x 132kV feeder systems

2x 132kV transformer systems

2x earthing transformers

1x bus Coupler system

2x 132kV bus zone systems

Telecommunications systems 2x multiplexor systems

Metering 2x transformer systems

2x feeder systems

Non-bay 1x operational wide area network system

2x site infrastructure panels

Remote end substation protection systems 4x remote end feeder protection systems

16 Clause 5.16.4(b)(4) of the Rules requires Powerlink to advise whether the identified need and or solutions are included in the most recent NTNDP. At the time of commencement of this RIT-T in September 2016, the 2016 NTNDP was the most recent published version.

Page 16: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 13

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

6.1 Material inter-network impact

Powerlink does not consider that any of the credible options being considered will have a material inter-network impact, based on AEMO’s screening criteria.17

7. Materiality of market benefits

Powerlink does not consider the proposed works at Kamerunga Substation will provide any market benefits, due to the nature of the project. The AER has recognised that if the proposed investment will not have an impact on the wholesale market, then a number of classes of market benefits will not be material in the RIT-T assessment, and so do not need to be estimated18.

7.1 Market benefits that are not material for this RIT-T assessment A discussion of each market benefit under the RIT-T is discussed below:

changes in patterns of generation dispatch: replacement of existing assets by itself does

not affect transmission network constraints or affect transmission flows that would change patterns of generation dispatch. The inclusion of additional circuit breakers on the Woree Feeders will have an immaterial impact on generation dispatch in the area. It follows that changes in patterns of generation dispatch are not material to the outcome of the RIT-T assessment.

changes in voluntary load curtailment: replacement of existing assets by itself does not affect prices in the wholesale electricity market. It follows that changes in voluntary load curtailment will not be material for the purposes of this RIT-T.

changes in involuntary load shedding: the credible options under consideration will not lead to unserved energy so it follows that changes in involuntary load shedding are not material to the outcome of the RIT-T assessment.

changes in costs for other parties: the effect of replacing the ageing assets under the credible options considered are localised to the substation they are located at and do not affect the capacity of transmission network assets and therefore is unlikely to change generation investment patterns (which are captured under the RIT-T category of ‘costs for other parties’).

differences in the timing of expenditure: credible options for asset replacement do not affect the capacity of transmission network assets, the way they operate, or transmission flows. Accordingly, differences in the timing of expenditure of unrelated transmission investments are unlikely to be affected.

changes in network losses: credible options are not expected to provide any changes in network losses as replacing the ageing assets has no material effect on the characteristics of the asset.

changes in ancillary services cost: there is no expected change to the costs of Frequency Control Ancillary Services (FCAS), Network Control Ancillary Services (NCAS), or System Restart Ancillary Services (SRAS) due to credible options under consideration. These costs are therefore not material to the outcome of the RIT-T assessment.

competition benefits: Powerlink does not consider that any of the credible options will materially affect competition between generators, and generators’ bidding behaviour and, consequently, considers that the techniques required to capture any changes in such behaviour would involve a disproportionate level of effort compared to the additional insight it would provide.

17 In accordance with Rules clause 5.16.4(b)(6)(ii). AEMO has published guidelines for assessing whether a credible option is expected to have a material inter-network impact. 18 AER, Final Regulatory Investment Test for Transmission Application Guidelines, September

2017, version 2, page 13.

Page 17: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 14

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

option value: Powerlink does not consider that the identified need for the options considered in this RIT-T is affected by uncertain factors about which there may be more clarity in future. Consequently, option value is not a relevant consideration for this RIT-T.

7.2 Consideration of market benefits for non-network options

Powerlink notes that non-network options may impact the wholesale electricity market (for example by displacing generation output). Accordingly, it is possible that several of the above classes of market benefits will be material where there are credible non-network options, depending on the specific form of the option.

No credible non-network options were identified as part of the consultation process on the PSCR, however where credible non-network options are identified as part of the consultation process on this PADR, Powerlink intends on assessing the materiality of market benefits arising from these options. Where the market benefits are considered material, these will be quantified as part of the RIT-T assessment of these options.

8. General modelling approach adopted to assess net benefits

8.1 Analysis period

The RIT-T analysis has been undertaken over a 35-year period, from 2020 to 2054. A 35-year period takes into account the size and complexity of the primary plant and secondary systems.

As the replacement plant will have different residual values by 2054 under each option, terminal values have been calculated to offset these variations.

8.2 Discount rate

Under the RIT-T, a commercial discount rate is applied to calculate the net present value (NPV) of costs and benefits of credible options. Powerlink has adopted a real, pre-tax commercial discount rate of 5.90%19 as the central assumption for the NPV analysis presented in this report.

Powerlink has tested the sensitivity of the results to changes in this discount rate assumption, and specifically to the adoption of a lower bound discount rate of 3.47%20 and an upper bound discount rate of 8.33%.

8.3 Description of reasonable scenarios

The RIT-T analysis is required to incorporate different reasonable scenarios to estimate market benefits. The scenarios must be appropriate to the credible options under consideration.

The choice of reasonable scenarios must reflect any variables or parameters that21:

are likely to affect the ranking of the credible options, where the identified need is reliability corrective action

are likely to affect the ranking of the credible options, or the sign of the net economic benefits of any of the credible options, for all other identified needs.

As all cash flows being discounted relate to regulated network costs and there are no material market benefits identified, Powerlink has applied weightings to the final NPV ranking that reflect that the low discount rate scenario is the most appropriate for the discounting of costs.

Full modelling parameters are outlined in Table 8.1

19 The indicative commercial discount rate is calculated on the assumption that a private investment in the electricity sector would hold an investment grade credit rating, a return on equity and a debt gearing ratio equal to an average firm on the Australian stock exchange. 20 A discount rate of 3.47 per cent is based on the AER’s Final Decision for Powerlink’s 2017-2022 transmission determination, which allowed a nominal vanilla WACC of 6.0 per cent and forecast inflation of 2.45 per cent that implies a real discount rate of 3.47 per cent. See AER, Final Decision: Powerlink transmission determination 2017-2022 | Attachment 3 – Rate of return, April 2017, p 9. 21 AER, Final Regulatory Investment Test for Transmission, June 2010, version 1, paragraph 16, p. 7

Page 18: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 15

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

Table 8.1: Modelling Parameters

9. Cost benefit analysis and identification of the preferred option

9.1 Net present values

Table 9.1 summaries the NPVs for each credible option under high, central and low discount rates scenarios.

Table 9.1 NPV ($m) for scenarios

Option High Central Low

Base Option -19.46 -21.93 -24.68

Option 1 -20.43 -22.14 -24.05

Option 2 -21.33 -21.52 -22.39

Option 3 -20.05 -21.46 -22.85

The Base Option is ranked first in NPV terms (i.e. least negative NPV) under the high discount rate, while Options 2 and 3 rank first under the low and central discount rate respectively. Option 3 is the most consistently high ranking option in that it ranks either first or second across all scenarios considered.

Table 9.2 shows more detail on the comparison of the NPVs under the weighted discount rate scenario.

Table 9.2: Weighted NPV, NPV relative to Base Option ($m) and Ranking

Option Weighted NPV

($m)

Weighted relative NPV ($m)

Ranking

Base Option -22.03 - 3

Option 1 -22.21 -0.178 4

Option 2 -21.41 0.612 1

Option 3 -21.45 0.573 2

Under the weighted scenario, Option 2 is ranked first in NPV terms, followed closely by Option 3. The economic analysis shows only $0.04 million difference between the NPV of Options 2 and 3 which represents less than 0.2% of the capital expenditure estimates for these options, well within the expected margin of accuracy. Given this, Options 2 and 3 are considered equal as the highest ranking options under the weighted scenario.

High Central Low

Discount rate 8.33% 5.90% 3.47%

Weighted 0.33 0.33 0.33

Operational Risk

Operational risk costs due to absence of Woree circuit breakers modelled as follows:

Base Option and Option 1 – entire analysis period

Options 2 and 3 – until 2022

Flood Risk Flood risk recovery costs included in Base Option until 2028

Page 19: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 16

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

Figure 9.1 provides a breakdown of capital and maintenance costs (i.e. routine and corrective maintenance) for the weighted scenario and highlights the similarity in NPV terms of Options 2 and 3.

Figure 9.1: Weighted NPV component for each credible option (NPV $m, 2018/19)

9.2 Sensitivity analysis

Powerlink has investigated the following sensitivities on key assumptions:

a lower discount rate of 3.47% as well as a higher rate of 8.33%

a 25% increase/decrease in capital costs using a central discount rate.

As illustrated in Figure 9.2 and 9.3, the sensitivity analysis for the NPV of the options relative to the Base Option shows that varying the discount rate and the capital cost impacts the ranking.

As shown previously in Table 9.1, Figure 9.2 identifies that Option 3 delivers the lowest net cost under central discount rates, while Option 2 and the Base Option deliver the lowest net cost under low and high discount rates respectively (with Option 3 ranked second in both these cases).

Figure 9.2 Sensitivity Analysis for Discount Rate

Page 20: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 17

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

Figure 9.3 shows that varying the sensitivity of the options to capital costs results in Option 3 delivering the lowest net cost should the capital cost of the options vary between approximately 80% and 125%, while Option 2 is only marginally better than Option 3 if the capital costs are less than 80% of their estimated values.

Figure 9.3 Sensitivity Analysis for Capital Cost

10. Preferred option

Based on the conclusions drawn from the NPV analysis and the rules requirements relating to the proposed replacement of transmission network assets, it is recommended that Option 3 be implemented to address the risks associated with the condition of the ageing infrastructure at Kamerunga Substation. Option 3 ranks first or second in all NPV scenarios and when the sensitivity analysis for capital costs and discount rates is taken into account, making it the most consistent high ranking option.

Option 3:

satisfies the RIT-T based on the cost benefit analysis (i.e. equal lowest cost in NPV terms under the weighted discount rate scenario with consideration of estimating accuracy, and lowest cost in NPV terms under the central discount rate)

utilises existing technology within the Powerlink network, removing the need to acquire and store new spares, and to undertake additional training for personnel (compared to Option 2)

addresses the risk to electricity supply from flood inundation in a single construction phase at the current Kamerunga Substation site by October 2022

provides increased security of supply through the inclusion of circuit breakers on the Woree feeders.

Option 3 is therefore considered to satisfy the requirements of the RIT-T and is the preferred option.

The RIT-T project for Option 3 involves replacing Kamerunga’s current primary plant with new AIS equipment, installing additional circuit breakers for the Woree feeders and the full replacement of all secondary systems in a new building. All plant and secondary systems are to be located above the 1 in 200 year flood level.

Page 21: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 18

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

11. Conclusions

The following conclusions have been drawn from the analysis presented in this report:

Powerlink has identified condition risks arising from the ageing primary plant and secondary systems equipment at Kamerunga Substation requiring action.

TNSPs must maintain (including repair and replace if necessary) their transmission grid to ensure the adequate, economic, reliable and safe transmission of electricity, including the ability to meet peak demand if a major element of the network was to fail.

S5.1.9(c) of the Rules requires a TNSP to provide sufficient primary protection systems and back-up protection systems (including breaker fail protection systems) to ensure that a fault of any type anywhere on its transmission system is automatically disconnected.

TNSPs must also ensure that all protection systems for lines at a voltage above 66kV are well maintained so as to be available at all times other than for short periods (less than eight hours), while the maintenance of a protection system is being carried out.

The increasing likelihood of faults associated with the condition of the ageing primary plant and secondary systems equipment at Kamerunga Substation compels Powerlink to undertake reliability corrective actions if it is to continue meeting the reliability standards set out in the Rules.

Studies were undertaken to evaluate four credible options; all four credible options were evaluated in accordance with the AER’s RIT-T.

Powerlink published a PSCR in September 2018 requesting submissions from Registered Participants, AEMO and interested parties on the credible options presented, including alternative credible non-network options, which could address the condition risks at Kamerunga Substation.

There were no submissions received in response to the PSCR, which was open for consultation until 21 December 2018. As a result, no additional credible options that could deliver a material market benefit have been identified as part of this RIT-T consultation.

12. Draft recommendation.

Based on the conclusions drawn from the NPV analysis and the Rules requirements relating to the proposed replacement of transmission network assets, it is recommended that Option 3 be implemented to address the risks associated with the condition of the ageing infrastructure at Kamerunga Substation.

Option 3 involves replacing Kamerunga’s current primary plant with new AIS equipment, installing additional circuit breakers for the Woree feeders and the full replacement of all secondary systems in a new building. All primary plant and secondary systems are to be located above the 1 in 200 year flood level.

The estimated capital cost is $23.75 million (2018/19 prices). Powerlink is the proponent of the proposed preferred option.

Design and construction activities would be expected to commence in early 2020, with completion of the project in October 2022.

13. Submissions requirements

Powerlink invites submissions and comments in response to this PADR from Registered Participants, AEMO, potential non-network providers and any other interested parties.

Submissions should be presented in a written form and should clearly identify the author of the submission, including contact details for subsequent follow-up if required. If parties prefer, they may request to meet with Powerlink ahead of providing a written response.

Page 22: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Page 19

Powerlink Queensland

Project Assessment Draft Report: Maintaining reliability of supply at Kamerunga Substation

13.1 Submissions from non-network providers

This is not a tender process – submissions are requested so that Powerlink can fulfil its regulatory obligations to analyse non-network options. In the event that a non-network option appears to be a genuine and practicable alternative that could satisfy the RIT-T, Powerlink will engage with that proponent or proponents to clarify cost inputs and commercial terms.

Submissions from potential non-network providers should contain the following information:

details of the party making the submission (or proposing the service)

technical details of the project (capacity, proposed connection point if relevant, etc.) to allow an assessment of the likely impacts on future supply capability

sufficient information to allow the costs and benefits of the proposed service to be incorporated in a comparison in accordance with AER RIT-T guidelines

an assessment of the ability of the proposed service to meet the technical requirements of the Rules

timing of the availability of the proposed service

other material that would be relevant in the assessment of the proposed service.

As the submissions will be made public, any commercially sensitive material, or material that the party making the submission does not want to be made public, should be clearly identified.

It should be noted that Powerlink is required to publish the outcomes of the RIT­T analysis. If parties making submissions elect not to provide specific project cost data for commercial-in-confidence reasons, Powerlink may rely on cost estimates from independent specialist sources.

13.2 Assessment and decision process

Powerlink intends to carry out the following process to assess what action, if any, should be taken to address future supply requirements:

Part 1 PSCR Publication 25 September 2018

Submissions due on the PSCR

Have your say on the credible options and propose potential non-network options.

21 December 2018

Part 2 PADR Publication

Powerlink’s response to submissions received and assessment of any viable non-network options for potential inclusion in final solution

23 April 2019

Submissions due on the PADR 7 June 2019

Part 3 Publication of the PACR

Powerlink’s response to any further submissions received and final recommendation on the preferred option for implementation.

July/August 2019

Powerlink reserves the right to amend the timetable at any time. Amendments to the timetable will be made available on the Powerlink website (www.powerlink.com.au).

Page 23: Project Assessment Draft Report - powerlink.com.au · are all fully replaced in a single stage and the primary plant replaced with either the current Air Insulated Switchgear (AIS)

Contact us

Registered office 33 Harold St Virginia

Queensland 4014 Australia

Postal address: GPO Box 1193 Virginia

Queensland 4014 Australia

Contact: Roger Smith

Manager Network and Alternate Solutions

Telephone (+617) 3860 2328

(during business hours)

Email [email protected]

Internet www.powerlink.com.au