project on ongc validation
TRANSCRIPT
-
7/31/2019 Project on ONGC Validation
1/67
VALIDATION REPORT
DET
NORSKE
VERITAS
51 MWwind power projectof ONGC at Surajbari, Gujarat
in India
REPORT NO.2008-0065REVISION NO. 02
-
7/31/2019 Project on ONGC Validation
2/67
DET NORSKE VERITAS
VALIDATION REPORT
DET NORSKE VERITASCERTIFICATION AS
Veritasveien 1,1322 HVIK, NorwayTel: +47 67 57 99 00Fax: +47 67 57 99 11http://www.dnv.comOrg. No: NO 945 748 931 MVA
Date of first issue: Project No.:
17-12-2008 PRJC-105320-2008-CCS-INDA roved by: Or anisational unit:
Michael Lehmann Climate Change ServicesClient: Client ref.:
Oil and Natural Gas Corporation Limited Mr. Ashok B. Chakraborty
Project Name: 51 MW wind power project of ONGC at Surajbari, Gujarat in IndiaCountry: IndiaMethodology: ACM0002Version: 07GHG reducing Measure/Technology: Grid connected renewable electricity generationER estimate: 85 762 t CO2 per year.Size
Large ScaleSmall Scale
Validation Phases:
Desk ReviewFollow up interviewsResolution of outstanding issues
Validation Status
Corrective Actions RequestedClarifications RequestedFull Approval and submission for registrationRejected
In summary, it is DNVs opinion that the 51 MW wind power project of ONGC at Surajbari,Gujarat in India, as described in the PDD, version 04 of 16 February 2010, meets all relevantUNFCCC requirements for the CDM and all relevant host Party criteria and correctly appliesthe baseline and monitoring methodology ACM0002 version 07. DNV thus requests theregistration of the project as a CDM project activity.
Re ort No.: Date of this revision: Rev. No. Key words:
2008-0065 2010-02-22 02
Re ort title:
51 MW wind power project of ONGC atSurajbari, Gujarat in India in India
Climate ChangeKyoto ProtocolValidation
Clean Development Mechanism
Work carried out by:Shivraj Sharma, G. Murali,Ravi Kumar Prabhu
No distribution without permission from
the Client or responsible organisational unit
Work verified by:
Limited distributionKakaraparthi Venkata Raman (Draft)Anjana Sharma (Final)
Unrestricted distribution
-
7/31/2019 Project on ONGC Validation
3/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
Page i
Abbreviations
BM Build MarginCAR Corrective Action RequestCDM Clean Development MechanismCEA Central Eclectricity AuthorityCEF Carbon Emission FactorCER Certified Emission ReductionCL Clarification requestCO2 Carbon dioxideCO2e Carbon dioxide equivalentCM Combined MarginCUF Cost Utilization FactorDNV Det Norske Veritas Certification AS
DNA Designated National AuthorityDPR Detailed Project ReportEB Executive BoardEPC Engineering, Procurement and ConstructionGEDA Gujarat Energy Development agencyGETCO Gujarat Energy Transmission Corporation Ltd.GHG Greenhouse gas(es)GWP Global Warming PotentialGWh Giga Watt HourIRR Internal Rate of ReturnIPCC Intergovernmental Panel on Climate ChangekWh Kilo Watt hourMW Mega WattMP Monitoring PlanNGO Non-governmental OrganizationODA Official Development AssistanceO&M Operation and MaintenanceOM Operating MarginONGC Oil and Natural Gas Corporation Ltd.PDD Project Design DocumentPLF Plant Load FactorPPA Power Purchase AgreementSEL Suzlon Energy Limited
UNFCCC United Nations Framework Convention on Climate ChangeWEG Wind Energy Generators
-
7/31/2019 Project on ONGC Validation
4/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
Page ii
TABLE OF CONTENTS
1 EXECUTIVE SUMMARY VALIDATION OPINION ..................... .....................1
2 INTRODUCTION ....................................................................................................2
2.1 Objective 2
2.2 Scope 2
3 METHODOLOGY ...................................................................................................3
3.1 Desk Review of the Project Design Documentation 3
3.2 Follow-up Interviews with Project Stakeholders 5
3.3 Resolution of Outstanding Issues 5
3.4 Internal Quality Control 7
3.5 Validation Team 7
4 VALIDATION FINDINGS ......................................................................................8
4.1 Participation Requirements 8
4.2 Project Design 8
4.3 Baseline Determination 9
4.4 Additionality 10
4.5 Monitoring 15
4.6 Estimate of GHG Emissions 16
4.7 Environmental Impacts 16
4.8 Comments by Local Stakeholders 16
4.9 Comments by Parties, Stakeholders and NGOs 16
Appendix A: Validation Protocol
Appendix B: Certificates of Competence
-
7/31/2019 Project on ONGC Validation
5/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
1 EXECUTIVE SUMMARY VALIDATION OPINIONDet Norske Veritas Certification AS (DNV) has performed a validation of the 51 MW wind
power project of ONGC at Surajbari, Gujarat in India. The validation was performed on the
basis of UNFCCC criteria for the Clean Development Mechanism and host Party criteria, as
well as criteria given to provide for consistent project operations, monitoring and reporting.
The review of the project design documentation and the subsequent follow-up interviews have
provided DNV with sufficient evidence to determine the fulfilment of stated criteria.
The host Party is India and project participant is Oil and Natural Gas Corporation Ltd
(ONGC). No Annex I Party is involved in the project at this stage. The Host Party India fulfils
the participation criteria and has approved the project and authorized the project participant.
The DNA of India confirmed that the project assists in achieving sustainable development.
The project correctly applies ACM0002 Consolidated baseline methodology for grid
connected electricity generation from renewable sources, version 7. The project involves
generation of renewable energy by installing wind turbine generators (WTGs), which will
displace the electricity generation in the fossil fuel dominated Western regional grid of India,
thereby resulting in the reduction of GHG emissions that are real, measurable and give long-
term benefits to the mitigation of climate change.
It is demonstrated that the project is not a likely baseline scenario. Emission reductions
atributable to the project are hence additional to any that would occur in the absence of the
project activity.
The total emission reductions from the project are estimated to be on the average 85 762 tCO2e per year over the selected 7 year renewable crediting period. The emission reduction
forecast has been checked, and it is deemed likely that the stated amount is achieved given
that the underlying assumptions do not change.
The monitoring plan makes sufficient provision for monitoring relevant project and baseline
emission indicators. Detailed responsibilities and authorities for project management,
monitoring and reporting and QA/QC procedures have also been addressed.
In summary, it is DNVs opinion that the 51 MW wind power project of ONGC at Surajbari,
Gujarat in India, as described in the PDD, version 04 of 16 February 2010, meets all
relevant UNFCCC requirement for the CDM and all relevant host Party criteria and
correctly applies the baseline and monitoring methodology ACM0002, version 7. DNV thus
requests the registration of the project as a CDM project activity.
-
7/31/2019 Project on ONGC Validation
6/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
2 INTRODUCTIONOil and Natural Gas Corporation Ltd. has commissioned Det Norske Veritas Certification AS(DNV) to perform a validation of the 51 MW wind power project of ONGC at Surajbari,
Gujarat in India (hereafter called the project). This report summarises the findings of the
validation of the project, performed on the basis of UNFCCC criteria for the CDM, as well as
criteria given to provide for consistent project operations, monitoring and reporting.UNFCCC criteria refer to Article 12 of the Kyoto Protocol, the CDM modalities and
procedures and the subsequent decisions by the CDM Executive Board. This revised
validation report addresses the corrections required by the CDM Executive board in decision44 (aa) of the EB 52 meeting report.
2.1 Objective
The purpose of a validation is to have an independent third party assess the project design. Inparticular, the project's baseline, monitoring plan, and the projects compliance with relevant
UNFCCC and host Party criteria are validated in order to confirm that the project design, as
documented, is sound and reasonable and meets the identified criteria. Validation is arequirement for all CDM projects and is seen as necessary to provide assurance tostakeholders of the quality of the project and its intended generation of certified emission
reductions (CERs).
2.2 ScopeThe validation scope is defined as an independent and objective review of the project designdocument (PDD). The PDD is reviewed against the criteria stated in Article 12 of the Kyoto
Protocol, the CDM modalities and procedures as agreed in the Marrakech Accords and the
relevant decisions by the CDM Executive Board, including the approved baseline andmonitoring methodology ACM0002 version 07.
The validation is not meant to provide any consulting towards the project participants.
However, stated requests for clarifications and/or corrective actions may have provided inputfor improvement of the project design.
-
7/31/2019 Project on ONGC Validation
7/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
3 METHODOLOGYThe validation consisted of the following three phases:
I a desk review of the project design documents
II follow-up interviews with project stakeholders
III the resolution of outstanding issues and the issuance of the final validation report and
opinion.
The following sections outline each step in more detail.
3.1 Desk Review of the Project Design Documentation
The following table lists the documentation that was reviewed during the validation:/1/ ONGC: CDM-PDD version 1 dated 8 April 2008, version 3 dated 22 June 2009 and
version 4 dated 16 February 2010
/2/ CDM Executive Board: Validation and Verification Manual. Version 01
/3/ CDM Executive Board: ACM0002, Consolidated baseline methodology for grid connectedelectricity generation from renewable sources, version 7
/4/ CDM Executive Board: Tool for the demonstration and assessment of additionality,
version 05.2.
/5/ DNA of India:Letter of Approval dated 17 April 2009
/6/ CEA: CO2Baseline Database for the Indian Power Sector dated 12 December 2007,
www.cea.nic.in
/7/ MoEF: Notification on requirement of environmental clearance, dated 14 September2006
/8/ ONGC: Notification of Award for purchase of 34 numbers of WEGs issued to Suzlon,
dated 6 November 2007
/9/ ONGC: Inviting quotations for turnkey supply of wind power project in Gujarat on 30March 2007
/10/ ONGC: Inviting tenders for CDM consultancy services, 3 July 2007
/11/ ONGC: Internal office memo on approval of the project and demonstrating CDM
awareness, 26 October 2007.
/12/ ONGC: Letter of Award to consultants "Deloitte for the CDM development of wind
power project in Gujarat, 26 October 2007.
/13/ ONGC: Awarding contracts for land lease, civil and electrical works, erection and
commissioning, 4 January 2008
/14/ GEDA: Permission for power transmission, 24 March 2008.
/15/ GEDA: Commissioning certificates of WEGs, dated 16 April 2008, 12 June 2008,and
23 October 2008,
/16/ GETCO: Agreement with ONGC for wheeling of power to installations in the state of
Gujarat, 27 May 2008.
/17/ ONGC: Invitation of tender for CDM validation of the project, 6 June 2008.
/18/ ONGC: Public notice regarding stakeholder consultation in Kutch Mitra, a local
newspaper, 9 August 2008.
/19/ ONGC: MOM of Stake holder consultation at the project site, 18 August, 2008.
-
7/31/2019 Project on ONGC Validation
8/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
/23/ ONGC order on benchmark No. MUM/PAS/PROJ/APPR/RR/2007 dated June 11,
2007/24/ SBI: Letter issued by Assistant General Manager dated 23 November 2008 regarding
interest rates for advances for the period of March 1992 to December 2008.
/25/ ONGC: Contract awarded to Suzlon Energy Limited for operation and maintenance of
wind mills dated 28 April 2009.
/26/ Uttar Gujarat Vij Company Limited: Electricity bill for supply of power to ONGC
installation dated 20 March 2007, proof for tariff.
/27/ Gujarat government Wind power policy 2007
/28/ ONGC: Estimated energy generation worked out by the independent consultants for the
bids received
/29/ ONGC letter of 13 September 2008 on price bid opening for WEGs/30/ http://www.windpowerindia.com/statest.html
/31/ ONGC: IRR spreadsheet calculations
/32/ ONGC: Test certificates of energy meters by Secure Meters Limited, dated 7 November
2007.
/33/ CEA web site: Data on hydropower stations in India
http://www.cea.nic.in/hydro/List%20of%20HE%20Stations%20in%20the%20country.pdf
/34/ GEDA: Availability of biomass in the state of Gujarat and potential for power
generation: http://www.geda.org.in/bio/bio_summarybiomass.htm
/35/ Ministry of new and renewable energy: Cost of solar energy
http://mnes.nic.in/press-releases/press-release-21042008-2.pdf/36/ ONGC: Policy on climate change and sustainability, approved by the executive
committee of the Board, dated 2 October 2007.
/37/ ONGC: Project cases, wherein internal benchmark was applied - Re-development ofMumbai High North Phase dated 24 November 2008 and Expenditure Sanction for
replacement of 12 OSV's 15 June 2007 and "Tender No L26BC07013 for construction
of water injection plant at GGS-I, Nambar, A&AA basin, Jorhat dated 18 December
2008
/38/ GERC: Tariff order for Gujarat Vij Company Limited, Case number 945 of 2008 dated
17 January 2009.
/39/ The, Directory Indian Wind Power 2007,
/40/ GEDA: Windfarm generation report of Gujarat for the year 2005-06 & 2006-07
http://geda.org.in/pdf/wind/Windfarms-PowerGeneration.pdf
/41/ UNEP Risoe Centre: Data base of CDM projects CDMpipeline.xls
/42/ ONGC: Annual report for 2007-08.
/43/ Department of Public Sector Enterprises: Revised scales of pay of board and below
board level executives in Central Public Sector Enterprises.
http://dpe.nic.in/newgl/glch04a23.pdf
/44/ Indian Income Tax Act 1961: Section 32 (Rule 5) Appendix 1 and Section 80-1A,
paragraph 2.0.
/45/ GERC: Tariff orders
http://www.gercin.org/docs/Orders/Tariff%20Orders/Year%202006/ugvcl.zip, http://www.gercin.org/docs/Orders/Tariff%20Orders/Year%202007/Tariff%20order-
-
7/31/2019 Project on ONGC Validation
9/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
3.2 Follow-up Interviews with Project Stakeholders
On 3 December 2008 DNV performed the site visit (Surajbari and Jakhav) with projectstakeholders to confirm selected information and to resolve issues identified in the documentreview. Representatives of ONGC, Suzlon, and Deloitte were interviewed. The main topics of
the interviews are summarized below.
Name Interview Topics
/47/ ONGC
Mr. Ratendra Kumar, SE(M)
Mr. Satendra Mohan, SE(P)
SUZLON
Mr. Dwijal Mamtora, Senior
Executive, Marketing
Mr. S.K. Behena, Deputy Manager
(O&M)
Deloitte
Mr. Vivek. P. Adhia, SeniorConsultant
Host country approval Emission reduction calculations and CEA
data used
Baseline selection Training and maintenance schedule
Additionality and financial analysis
Proof for CDM consideration Start date of the project
Stakeholder consultation
3.3 Resolution of Outstanding IssuesThe objective of this phase of the validation was to resolve any outstanding issues which
needed be clarified prior to DNVs positive conclusion on the project design. In order to
ensure transparency a validation protocol was customised for the project. The protocol showsin a transparent manner the criteria (requirements), means of verification and the results from
validating the identified criteria. The validation protocol serves the following purposes:
It organises, details and clarifies the requirements a CDM project is expected to meet;
It ensures a transparent validation process where the validator will document how aparticular requirement has been validated and the result of the validation.
The validation protocol consists of three tables. The different columns in these tables are
described in the figure below. The completed validation protocol for the 51 MW wind power
project of ONGC at Surajbari, Gujarat in India is enclosed in Appendix A to this report.
Findings established during the validation can either be seen as a non-fulfilment of CDMcriteria or where a risk to the fulfilment of project objectives is identified. Corrective action
requests (CAR) are issued, where:
i) mistakes have been made with a direct influence on project results;
ii) CDM and/or methodology specific requirements have not been met; oriii) there is a risk that the project would not be accepted as a CDM project or that emission
reductions will not be certified.
A request for clarification (CL) may be used where additional information is needed to fully
clarify an issue.
-
7/31/2019 Project on ONGC Validation
10/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
Validation Protocol Table 1: Mandatory Requirements for CDM Project Activities
Requirement Reference Conclusion
The requirements the
project must meet.
Gives reference to the
legislation or
agreement where the
requirement is found.
This is either acceptable based on evidence provided (OK), a
Corrective Action Request (CAR) of risk or non-compliance
with stated requirements or a request forClarification (CL)
where further clarifications are needed.
Validation Protocol Table 2: Requirement checklist
Checklist Question Reference Means of
verification (MoV)
Comment Draft and/or Final
Conclusion
The various
requirements in Table 2
are linked to checklistquestions the project
should meet. The
checklist is organised in
different sections,
following the logic of the
large-scale PDD
template, version 03 - in
effect as of: 28 July
2006. Each section is
then further sub-divided.
Gives
reference to
documentswhere the
answer to
the checklist
question or
item is
found.
Explains how
conformance with
the checklistquestion is
investigated.
Examples of means
of verification are
document review
(DR) or interview
(I). N/A means not
applicable.
The section is
used to elaborate
and discuss thechecklist question
and/or the
conformance to
the question. It is
further used to
explain the
conclusions
reached.
This is either acceptable
based on evidence
provided (OK), or acorrective action request
(CAR) due to non-
compliance with the
checklist question (See
below). A request for
clarification (CL) is used
when the validation team
has identified a need for
further clarification.
Validation Protocol Table 3: Resolution of Corrective Action and Clarification Requests
Draft report clarifications
and corrective action
requests
Ref. to checklist
question in table 2
Summary of project
owner response
Validation conclusion
If the conclusions from the
draft Validation are either
a CAR or a CL, these
should be listed in this
section.
Reference to the
checklist question
number in Table 2
where the CAR or CL is
explained.
The responses given by
the project participants
during the
communications with the
validation team should
be summarised in this
section.
This section should summarise
the validation teams
responses and final
conclusions. The conclusions
should also be included in
Table 2, under Final
Conclusion.
Figure 1 Validation protocol tables
-
7/31/2019 Project on ONGC Validation
11/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
3.4 Internal Quality Control
The validation report underwent technical review. The technical review was performed by atechnical reviewer qualified in accordance with DNVs qualification scheme for CDMvalidation and verification.
3.5 Validation TeamRole/Qualification Type of involvement
Last Name First Name Country Deskr
eview
Sitevi
sit/Interviews
Reporting
Superv
isionofwork
Technicalreview
Expert
input
Project Manager/
CDM validator
Govindarajulu
Kaliaperumal
Murali India
GHG auditor Prabhu Ravi Kumar India GHG auditor Sharma Shivraj India
TechnicalReviewer (Draft)
Kakaraparthi VenkataRaman
India
TechnicalReviewer (Final)
Sharma Anjana India
The qualification of each individual validation team member is detailed in Appendix B to this
report.
-
7/31/2019 Project on ONGC Validation
12/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
4 VALIDATION FINDINGSThe findings of the validation are stated in the following sections. The validation criteria(requirements), the means of verification and the results from validating the identified criteria
are documented in more detail in the validation protocol in Appendix A.
The final validation findings relate to the project design as documented and described in therevised and resubmitted project design documentation, version 03, 16 February 2010.
4.1 Participation Requirements
The project participant is the public sector undertaking Oil and Natural Gas Corporation
Ltd. of the host Party India. Host Party India meets all the requirements for participating in a
CDM project. The Ministry of Environment and Forests, the DNA of India has approved theproject with a letter of approval dated 17 April 2009 /5/, which also confirms that the project
assists in achieving sustainable development in India. No Annex I Party has yet beenidentified for the project.
The validation did not reveal any information that indicates that the project can be seen as a
diversion of official development assistance (ODA) funding towards India.
4.2 Project DesignThe project activity is the installation of 34 Wind Electricity Generators (WEGs) of 1500kWaggregating to an installed capacity of 51 MW. The entire power generated from the wind
farm is being exported to the Gujarat state grid which is a part of the western regional
electricity grid. The power generated by the project will be wheeled through the grid tovarious installations of ONGC within the state of Gujarat to meet the power requirements of
these installations.
All the WEGs installed under the project are supplied by Suzlon. The installation,
commissioning, operation and maintenance of the WTGs are in the scope of M/s Suzlon. The
technology used in the project activity is indigenously available in India and no transfer of
technology is envisaged. Proposed project is expected to export 95.56 GWh per year after 4%wheeling charges, at a plant load factor (PLF) of 22.28%. The power generated from the
project is wheeled through the state grid which is part of the western regional grid thereby
replacing an equivalent amount of fossil fuel based power generation. Therefore, the project
activity results in an equivalent amount of CO2 emission reduction which otherwise wouldhave resulted from fossil fuel combustion. The power generated by the project will be used to
meet the power consumption of various ONGC installations in Gujarat, which are presentlyconsumers of the local grid.
The expected operational lifetime of the project technology is 20 years, which has been
verified from the inter office memo of ONGC /11/ and is deemed reasonable for a new windmill. The starting date of the project activity has been indicated as 6 November 2007 which is
the date of the purchase order for supply of the 34 Suzlon make 1500 KW WEGs/8/.
The project has selected a renewable crediting period of 7 years starting from the date of
registration of the project, which is expected to be 1 November 2009. The project is estimatedto reduce 85 762 t CO2e per year for the duration of the crediting period chosen.
-
7/31/2019 Project on ONGC Validation
13/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
4.3 Baseline Determination
The project applies the approved consolidated baseline methodology ACM0002, version 7titled Consolidated baseline methodology for grid-connected electricity generation fromrenewable sources/3/. The methodology is applicable to the project since the project activity
involves grid-connected wind energy generation and the geographic and system boundaries
for the relevant electricity grid can be clearly identified and information on the characteristicsof the grid is available.
Four alternatives to the project activity have been considered as the baseline scenario. These
arei) project activity without CDM benefits;
ii) continuation of current scenario of power generation from existing grid-connected
power plants;
iii)
project activity based on other renewable energy sources like hydropower, solarenergy and biomass
iv) The proposed project activity is taken up as a fossil fuel based project.
Alternative i) - Project activity without CDM revenue is a potential baseline scenario.
Alternative ii) - Continuation of current scenario i.e. generation of same amount ofelectricity in the state grid does not involve any investment neither face any barrier and
hence, is an attractive option in the absence of project activity.
Alternative iii) PP has carried out analysis of power generation units based on renewable
energy sources and the results are as follows:a) Hydropower generation: The state of Gujarat lacks hydro resources for setting up
small and medium scale hydropower plants. According to the data published by CEA/33/, there are only 5 hydropower stations in Gujarat, all of them with installed
capacities of 240 MW and above.
b) Biomass based power generation: According to report of Gujarat Energy DevelopmentAgency (GEDA) /34/ the installed capacity of the biomass based power projects in the
state is only 0.5 MW and the report also indicates that it is not feasible to transport the
biomass to faraway locations. Based on the above mentioned statements it has beenverified that the availability of surplus biomass in the state is limited to support power
plants. .
c)
Solar Energy based power generation: The solar power generation is yet to gainground in the country because of the high cost. According to the data available in theministry of new and renewable energy website, the cost of setting up 1MW solar plant
is in the range of INR 160 to 200 million and the generation cost is around INR 12 to
15 per unit /35/Based on the above analysis, none of the renewable energy based power generation units
can be considered as credible alternatives for the project developer in the absence of
project activity.
Alternative iv) - Fossil fuel based power generation unit: The fossil fuel based power plant
was not considered by PP because of its commitment to develop alternative energy
sources. ONGCs Policy on climate change and sustainability /36/ states that We shalldevelop and invest in advanced low carbon technologies to meet growing demand for
affordable energy products while improving security of supply and reducing
-
7/31/2019 Project on ONGC Validation
14/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
Thus alternatives iii) and iv) are eliminated due to the non-availability of other renewable
sources in Gujarat and the commitment of the project proponent to take up environmentfriendly and pollution free energy production, respectively.
This leaves only alternates i) and ii) for further analysis. Both alternatives are in
compliance with the laws and regulations of India and might be considered as baseline
scenarios. However, as discussed in the section 4.4. below, the proposed project activity(without CDM income alternative i) faces barriers compared to other alternative i.e.
continuation of current practice (alternative ii) which does not require any investment.
Hence, alternative (ii) has been selected as a baseline scenario. The selected baseline
scenario is also in line with the approved baseline methodology ACM0002.
DNV considers the list of realistic and credible alternatives to be complete.
As the project activity supplies electricity to the Gujarat state electricity grid which forms a
part of the western region electricity grid, the baseline for this project activity is a function ofthe generation mix of the western region grid. The selection of the western region grid as the
grid system boundary for the project activity is in line with the EB guidance for large
countries such as India. In line with the guidance provided in the methodology, the weightsfor OM and BM have been taken as 75:25. The OM emission factor in the CEA database is
calculated ex-ante using the simple OM approach based on the generation-weighted average
emissions per electricity unit over a three year period of 2004-2005, 2005-2006 and 2006-2007. The BM emission factor is calculated ex-ante based on 20% most recent capacity
additions in the grid based on net generation as described in ACM0002 version 07. The
operating margin has been determined to be 0.99 kg CO2e/kWh and the build margin to be0.59 kg CO2e/kWh. Taking the weight of OM:BM as 75:25, the combined margin emission
coefficient for the western grid of India has been calculated at 0.89 kg CO2e/kWh. These
values have been sourced from data by the Central Electricity Authority (CEA) of the
Ministry of Power, Government of India /6/.
CEA has published a database of carbon dioxide emission factors from the power sector in
India based on detailed authenticated information obtained from all operating power stationsin the country. This CO2 baseline database provides information about the OM and BM
factors of all the regional electricity grids in India. DNV confirms that the database is an
official publication of the Government of India for the purpose of CDM baselines. Theselected sources and gases are justified for the project activity.
4.4 AdditionalityThe additionality of the project activity is demonstrated using the Tool for demonstration of
additionality, version 5. /4/
4.4.1 CDM consideration and continued action to secure CDM statusThe chronology of events and the evidences provided to demonstrate the prior consideration
of the CDM and the real and continued actions undertaken to secure CDM status are given
below:
CDM was seriously considered in the decision to proceed with the project activity inaccordance with EB41 annex 46 and was evidenced through the four activities listed below
-
7/31/2019 Project on ONGC Validation
15/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
c) Internal office memo of ONGC demonstrating CDM awareness, 26 October 2007 /11/.
d) Letter of Award to consultants "Deloitte" for the CDM development of wind powerproject in Gujarat, 26 October 2007 /12/.e) Notification of Award (NoA) for purchase of 34 numbers of WEGs issued to Suzlon /8/
on 6 November 2007, which is the start date of the project.
Efforts to secure CDM status in parallel with the physical implementation was shown by thefollowing sequence that was consider satisfactory by DNV:
a) Awarding contract for land lease, civil and electrical works, erection and
commissioning, 4 January 2008 /13/.b) Permission from GEDA for power transmission, 24 March 2008 /14/.
c) Commissioning of first set of WEGs, 4 April 2008 /15/
d)
Agreement with GETCO for wheeling of power to various installations of ONGC inGujarat, 27 May 2008 /16/.
e) Invitation of tender for CDM validation of the project, 6 June 2008 /17/.
f) Public notice in local newspaper on stakeholder consultation, 9 August 2008 /18/.
g) Stake holder consultation at the project site, 18 August, 2008 /19/.h) Commissioning of last set of WEGs, 29 September 2008 /15/.
i) Notification of award (NOA) for CDM validation the project 27 October 2008 /20/.
j) Host Country Approval meeting at the National CDM authority, New Delhi on 17November 2008./21/.
k) Start of validation (global stakeholder consultation) on 4 November 2008.
l) Receipt of host country approval, 17 April 2009 /5/.
4.4.2 Identification of alternatives to project activityTwo alternatives to the project activity have been considered as the baseline scenario. These
are i) project activity without CDM benefits and ii) continuation of current scenario of power
generation from existing grid-connected power plants. Both alternatives are in compliancewith the laws and regulations of India and might be considered as baseline scenarios.
However, as discussed in the following sections of this report, the project without CDMbenefits faces barriers in implementation.
4.4.3 Investment analysis: Choice of approachTo demonstrate the additionality of the project, the project proponent has calculated the IRR
of the project for a period of 20 years.The project generates revenues without CDM and the alternative of grid based electricity
generation does not involve any investment on the part of the project participant. Therefore, a
benchmark analysis is considered suitable for demonstrating the additionality of the project.
4.4.4 Investment analysis: Benchmark selectionONGC being a government of India public sector undertaking has an established benchmark
of 12 % post tax return on the investment for the development projects, according to ONGC
order No. MUM/PAS/PROJ/APPR/RR/2007 dated June 11, 2007 /23/. This internalbenchmark has been consistently applied by the project participant for other projects also.
This has been verified by DNV in project casesRe-development of Mumbai High North Phase
dated 24 November 2008/37/ andExpenditure Sanction for replacement of 12 OSV's 15 June2007 internal benchmark was used for acceptance of projects and project case "Tender NoL26BC07013 for construction of water injection plant at GGS-I, Nambar, A&AA basin,
-
7/31/2019 Project on ONGC Validation
16/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
The lending rate of the largest bank in India State Bank of India (SBI) at the time of taking
decision to go ahead with the project was 12.75% /24/. The internal benchmark of ONGC istherefore deemed to be conservative when compared with the applicable bank lending rate atthe time of decision making for the project. The applied benchmark is thus comparable to the
benchmark that would apply to a different entity potentially developing this project.
4.4.5 Investment analysis: Input parameters
DNV has verified the input parameters for the financial analysis, which were mainly sourced
from the approval note of the 51 MW wind energy project of Oil and Natural Gas CorporationLtd. (ONGC) dated 26 October 2007 /11/, submitted to the management of ONGC. The
investment decision of the project activity was taken by the management comprising of the
General Manager (Finance & Accounts), the Executive Director (Corporate Finance) and theDirector (Finance). The note elaborates in detail the project activity parameters like the total
project cost, O&M cost and the internal rate of return (IRR). The ultimate approval for the
project was provided by the Chairman and Managing Director on 26 October 2007, based onthe recommendation of the above mentioned management team.
The input parameters used in the investment analysis has been sourced from the approval
note, and has been cross checked with publicly available sources and actual invoices, in line
with paragraph 109 of the VVM.
Input parameter
used in the
financial analysis
Source of input value used by
DNV for verification
Source of input value used by
DNV for cross checking
Project cost Project approval note /11/ Notification of award of contract to
Suzlon dated 6 November 2007
(project starting date) /8/.
O&M costs Project approval note /11/ O&M contract entered into between
ONGC and Suzlon Energy Limiteddated 28 April 2009 /25/.
Cost of 2 ONGC
officers for project
supervision
Project approval note /11/ Revised scales of pay of board and
below board level executives in
Central Public Sector Enterprises,from the official website of
Department of Public SectorEnterprises /43/.
GEDA certification
fee and lease rental
Project approval note /11/ Notification of award of contract to
Suzlon dated 6 November 2007 /8/.
Tax benefits:
Accelerateddepreciation @ 80%
& Corporate tax @
33.99%
Project approval note /11/ Indian Income Tax Act 1961,
Section 32 (Rule 5) Appendix 1 andSection 80-1A, paragraph 2.0 /44/.
PLF of 22.28% Project approval note /11/ Report of the third party consultant
/28/, engaged by ONGC for
evaluation of offers received againstopen tender call. This is in line with
the guidance on PLF, EB 48
-
7/31/2019 Project on ONGC Validation
17/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
company). The estimated PLF as
suggested by the consultant wasused in the commercial evaluation
of the offers received.
4% Wheeling
charges
Gujarat government wind power
policy 2007
Gujarat government wind power
policy 2007 /27/.
Tariff Project approval note Electricity bill of ONGC for the
month of October 2007 /26/.
The incentives in the form of accelerated depreciation and tax holidays from the Governmentof India for the renewable energy projects have been taken into consideration for the financial
analysis. The estimates of project cost and O&M costs were further verified from the actual
costs incurred from the following documents and deemed appropriate. Contracts for supply of the equipments for verification of equipment cost /8/
Contracts for erection and commissioning /13/
Contracts for operation and maintenance, for verification of O&M costs /25/
The input parameters were verified to be valid at the time of decision making and hence inline with the VVM requirements, and section 6 of the Guideline on Investment Analysis, EB
41 Annexure 45, which states the Input values used in all investment analysis should be valid
and applicable at the time of the investment decision taken by the project participant.
4.4.6 Investment analysis: Calculation and conclusionThe IRR calculations were provided in a spreadsheet and verified by DNV. The project IRR
was verified to be 10.59% which is less than the benchmark IRR of 12%. The assumptionsand the source documents used for the financial calculations have also been verified. Theproject IRR increases to 12.69% with CDM benefits and thus makes the project feasible.
4.4.7 Investment analysis: Sensitivity analysisA sensitivity analysis has been carried out for the parameters PLF, project cost, operational
cost and tariff which contribute to more than 20% of revenues or costs to check the robustnessof the financial analysis. The level of variation assumed for the sensitivity analysis has been
suitably justified with relevant documents pertaining to the presented analysis and has been
verified by DNV, such as
The basis for the assumed annual electricity generation/ plant load factor (PLF) of
22.28% in the PDD is based on the estimated generation figures of the machinesprovided by the machine supplier, and ratified by the external independent consultant
/28/ engaged by ONGC for evaluation of bids received against the tender for windmills. It was observed that with an increase of 10%, the plant load factor works out to
be 24.5 % and the project IRR of 12.73% is crossing the benchmark of 12.0%.
The PLF used in the financial analysis is sourced from the third party (MP Wind farms
Limited) assessment of the wind potential in the region /28/. The PLF was also usedfor evaluating the various offers received by ONGC against the open tender call. DNV
has verified the third party assessment report and the letter informing the bidders that
the estimated PLF will be the basis for the evaluation of the tender. Thus the PLF of
the project activity is in line with the guidance on PLF as per paragraph 4 and 5 of
Annex 11, EB 48.
DNV has also cross checked the PLF against the Gujarat Electricity Regulatory
5
-
7/31/2019 Project on ONGC Validation
18/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
25.68% respectively, a standard CUF of 23% is stated for all the wind energy projects
in Gujarat for tariff calculation.DNV has also verified from the Directory Indian Wind Power 2007 /39/, Page 50
which reports the annual average power generation in four locations in Gujarat (Dhankin district Rajkot, Kalyanpur, Lamba and Navadra in district Jamnagar), that the
highest CUF is 14.5%. The report is attached as Annex II to this response. Further,
DNV has verified the wind-farm generation report for the year 2006-07 from theofficial web site of Gujarat energy development authority (GEDA) /46/, which states
the average capacity utilization of wind mills in Gujarat during 2006-07 to be 9% with
the highest at 18.8 % in the Kutch district where the project activity is located. The
figures for the year 2005-06 given in the report for locations in Kutch are still lower.DNV has concluded that a variation of +10% from 22.28% is unlikely after scrutiny of
the above mentioned data.
Hence it is DNVs opinion that the selection of the PLF of the project activity of
22.28%, which a) has been estimated by third party consultants, b) has been the basisfor the evaluation of the offers and c) the financial analysis, is reasonable.
The project has been contracted on a turn key basis to Suzlon Energy Limited by theproject proponent ONGC Ltd. /13/&/25/. It was also observed that if the project costgoes down by 10% then the IRR touches the benchmark of 12.0%. However, this is
not a likely scenario in DNVs opinion as the project has been contracted on a turn key
basis and the project cost is not likely to have any increase or decrease. The turn key
price of INR 3072.8 million constitutes 98.6% of the total project cost, which points tothe fact that 10% reduction in project cost is not plausible.
It was also observed that if the O&M cost goes down by 10% then the IRR touches thebenchmark of 12.0%. ONGC has signed a long term fixed rate O&M contract with
Suzlon for a period of 20 years /25/ and the same rates were used for financial
analysis. Therefore, any chances of reduction in O&M costs is not plausible
The applicable industrial tariff of INR 4.05 + 15% surcharge for ONGC at the time ofdecision making has been used in the investment analysis of the project activity. This
has been verified from the energy bill for the month of October 2007 from Uttar
Gujarat Vij Company Ltd.
The HT industrial consumer tariff for the period from 2002-03 to 2010-11 as per thetariff orders of GERC sourced from their official web site /45/ is stated hereunder:
- For the years 2002-03, 2003-04, 2004-05 and 2005-06: INR 4.10
- For the year 2006-07 and 2007-08: INR 4.05- For the year 2008-09, 2009-10 and 2010-11: INR 4.15
The tariff trend in Gujarat over the period of 9 years from 2002-03 to 2010-11 showsthat the increase in tariff for the period is only 1.22%. Since the industrial tariff in
Gujarat is one of the highest in India and a number of large scale power plants with
better efficiency are due for commissioning in the near future, the tariff increase infuture is expected to be small and no significant changes are expected. Based on the
assessment of the above mentioned sources, it was DNV opinion that the increase in
-
7/31/2019 Project on ONGC Validation
19/67
-
7/31/2019 Project on ONGC Validation
20/67
-
7/31/2019 Project on ONGC Validation
21/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
Comment by:
Accredited NGO Party StakeholderInserted on:
Subject:
Comment:
1. As the PDD clearly states that the power will be wheeled to different assests of ONGC the
benchmark used in the PDD is not applicable. Please refer to Additionality tool version 05 that states
that "Only in the particular case where the project activity can be implemented by the project
participant, the specific financial/economic situation of the company undertaking the project activity
can be considered". As the same wind based energy can be supplied by other party to ONGC internal
benchnmark cannot be applied. DOE is requested to check the suitability of benchmark during
validation process.
2. The power tariff has been taken as 4.05 Rs/kWh. Is the basis of this value taken from PPA? If yesthan it is not correct value applied for financial analysis. As wind energy supplied to ONGC assestsand it is displacing the assest electricity the cost of electricity to the assests have to be used in financial
analysis. DOE is requested to check the basis of this parameter in financial analysis.
3. As per the latest guidance on investment analysis the sensitivity has to be done for positive as well
as negative variation. The Generation parameter has only be varied towards negative variation. As
evident from many Wind Projects installed in India the generation value fluctuates based on the Wind
speed and also seasons and the generation can also increase than the value committed by the supplier.
This parameter have to be varied for positive side atleast towards +10% as stated in the guidance and
than it has to be compared against suitable benchmark.
Submitted by: Mahendra Jadhava
Comment by:
Accredited NGO Party Stakeholder
Inserted on:
Subject:
Comment:
1. How road network of area has been increased due to this particular project as mentioned in
social aspect because other windmills are also in same area?
2. What is total energy requirement of all ONGC operations as listed in PDD? Whether this
weather based wind energy will certainly fulfill electricity demands of all location round the year?
3. What would be impact of negative environmental conditions in area upon project? What
would be alternatives?
4. How many skilled/unskilled people from surrounding area were employed at this project
during commissioning and operation?
5. Whether NOC from state departments has been issued to this project?
6. Whether local villagers would be beneficiary of CDM revenue earned by company? Any plan
has been develop to earmark certain fund from CDM revenue for community welfare to improve
social well being of local people?
From
Hiral Mehta/Mahesh Pandya
Environmental Engineers
-
7/31/2019 Project on ONGC Validation
22/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
Submitted by: paryavaranmitra
.
The response received from the project participant to the comments:
S.No. Comments from GlobalStakeholder Process (GSP)
PP Response
A Stakeholder : Mahendra Jadhava
1 As the PDD clearly states that thepower will be wheeled to differentassets of ONGC the benchmark usedin the PDD is not applicable. Please
refer to Additionality tool version 05that states that "Only in the particularcase where the project activity can beimplemented by the projectparticipant, the specificfinancial/economic situation of thecompany undertaking the projectactivity can be considered". As thesame wind based energy can besupplied by other party to ONGCinternal benchmark cannot be applied.DOE is requested to check thesuitability of benchmark during
validation process.
The project activity replaces the grid based powergeneration which is being used by the projectproponent in the absence of the project activity. Thisgrid based power is now being replaced by captive
power generation by ONGC using wind energy. Ascaptive generation of power for own requirements canbe done by ONGC in this case, thus the use of theinternal benchmark is appropriate.
The benchmark used by the project proponent is acommon benchmark applicable to ONGCdevelopment projects and the ONGC Circular No.MUM/PAS/PROJ/APPR/RR/2007 dated June 11,2007 is submitted as Annexure II to establish thisinternal benchmark. Thus, the internal benchmark hasbeen applied correctly and in line with the guidance ofthe CDM Executive Board as provided in the
Additionality Tool, Version 5.2, Clause 13.
2 The power tariff has been taken as4.05 Rs/kWh. Is the basis of this valuetaken from PPA? If yes than it is notcorrect value applied for financialanalysis. As wind energy supplied toONGC assests and it is displacing theassest electricity the cost of electricityto the assests have to be used infinancial analysis. DOE is requested tocheck the basis of this parameter in
financial analysis.
As the project baseline is the grid power purchased bythe ONGC assets, the power tariff considered for thefinancial analysis is the power tariff applicable to theseassets. The power tariff considered for financial analysisis the power tariff drawn from the electricity bills of theONGC assets. Copy of the power bill is submitted as
Annexure XXIV to the validator at Dehradun visit.Thus, the power tariff used is Rs.4.05 Rs./Kwh + 15%surcharge = Rs.4.66 Rs./Kwh.
3 As per the latest guidance oninvestment analysis the sensitivity hasto be done for positive as well asnegative variation. The Generationparameter has only be varied towardsnegative variation. As evident frommany Wind Projects installed in Indiathe generation value fluctuates basedon the Wind speed and also seasonsand the generation can also increase
than the value committed by thesupplier. This parameter have to be
varied for positive side atleast towards
The sensitivity analysis has been conducted for theentire range between +10% to -10% of threeparameters Capex, Opex and Generation in the updatedPDD. The results of the sensitivity analysis arepresented in Section B.5 of the updated PDD.
-
7/31/2019 Project on ONGC Validation
23/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
1 How road network of area has beenincreased due to this particular projectas mentioned in social aspect becauseother windmills are also in same area?
Section A.2 of the PDD states that The projectactivity requires additional investment to be made to setup the wind turbines, including additional infrastructurelike approach roads, substations, transport ofconstruction materials, etc. by way of which the projectis leading to development of additional sectors,generation of new jobs and avenues of employment forthe local people. The project proponent has set up 34machines in an underdeveloped area in District Kutch.
The road network in the area is largely underdeveloped.To establish this project activity, ONGC has signed acontract with the equipment supplier for machinesupply, land, infrastructure, civil works for erection andcommissioning of the project activity. Please see
submitted Annexures V and VI. The contract price isinclusive of the internal roads and approach roads thatSuzlon would need to construct / pay fees to localauthorities to construct. Thus, the project proponenthas funded the road network that is being used for theproject activity.
2 What is total energy requirement of allONGC operations as listed in PDD?
Whether this weather based windenergy will certainly fulfill electricitydemands of all location round the
year?
Section 4.3 of the PDD lists out the percentage ofelectricity that would be wheeled to each asset locationfrom each machine. The electricity demands of theselocations will be met from the project activity as long asthe project activity generates wind power and it is
wheeled to the asset locations. The plant load factorused to calculate the estimated generation from theproject activity has already factored in the inherentintermittent nature of wind power.
3 What would be impact of negativeenvironmental conditions in area uponproject? What would be alternatives?
The wind potential pattern of the project area has beenmapped out by responsible agencies and it is expectedthat the wind potential as estimated would not changesubstantially within the next twenty years (the lifetimeof the project activity).The only environmentalcondition to have a negative impact on the projectactivity is the case of zero or less than 5m/s wind
speed. However, since Surajbari area in District Kutchis an identified wind power site, the probability of thissite not having any wind speeds is remote.
4 How many skilled/unskilled peoplefrom surrounding area were employedat this project during commissioningand operation?
During the construction phase, 38 skilled and 152unskilled locals were employed in the project. Duringthe operation phase, 14 unskilled locals are employed.
5 Whether NOC from state departmentshas been issued to this project?
The clearances received for the project activity havebeen submitted as Annexure-X (GEDA Transferpermission) and Annexure-XI (Chief ElectricalInspector Certificate) at Dehradun.
6 Whether local villagers would bebeneficiary of CDM revenue earned by
The benefits from CDM have boosted the IRR of theproject activity to commit the project proponent to go
-
7/31/2019 Project on ONGC Validation
24/67
DET NORSKE VERITAS
DNV report No: 2008-0065, rev. 02
VALIDATION REPORT
increased business opportunities for the local people asmore people related to the project come to visit theproject site.
How DNV has considered the comments received in its validation:
ONGCs responses are considered acceptable in the light of the explanations given. Since theproject is connected to the local grid and the power generated will be used for meeting
ONGCs own electricity consumption, applying an internal benchmark of ONGC is
considered appropriate. Also, it was verified that the internal benchmark has been consistently
applied across for other projects. Moreover, as mentioned under section 4.4.4, the lending rateof the largest bank in India State Bank of India (SBI) at the time of taking decision to go
ahead with the project was 12.75% /24/. The internal benchmark of ONGC is thereforedeemed to be conservative when compared with the applicable bank lending rate at the timeof decision making for the project. The applied benchmark is thus comparable to the
benchmark that would apply to a different entity potentially developing this project.
The power tariff (4.05 Rs./kWh + 15% surcharge) applicable to the ONGC installations isevidenced by the monthly bills from Uttar Gujarat Vij Company Ltd. /26/. Sensitivity analysis
has been done for +/- 10% variation in the applicable parameters, as per the EB guidelines.
This has been detailed in section 4.4.7 of this report.
The construction of road network to the project activity has been included the EPC contractfor setting up of the WEGs, which is verified from the purchase order placed on Suzlon.
The estimated power generation is based on the PLF evaluated by an independent consultant
and is likely to meet the power requirement of the ONGC installations listed in the PDD.
Negative environment conditions in the area are unlikely to affect the project activity.
The project employed 38 skilled and 152 unskilled locals during the construction phase and
14 unskilled locals in the operation phase, as confirmed by ONGC.
The project has obtained all the applicable statutory approvals.
The project will result in overall development of the area through construction of roadnetwork and employment generation.
-
7/31/2019 Project on ONGC Validation
25/67
DET NORSKE VERITAS
APPENDIX A
CDM VALIDATION PROTOCOL
-
7/31/2019 Project on ONGC Validation
26/67
DET NORSKE VERITAS
CDM Validation Protocol Report No.2008-0065, rev. 02
Table 1 Mandatory Requirements for Clean Development Mechanism (CDM) Project A
Requirement Reference Co
About Parties
1. The project shall assist Parties included in Annex I in achieving
compliance with part of their emission reduction commitment under
Art. 3.
Kyoto Protocol Art.12.2 Th
an
2. The project shall assist non-Annex I Parties in contributing to the
ultimate objective of the UNFCCC.
Kyoto Protocol Art.12.2. OK
3. The project shall have the written approval of voluntary participation
from the designated national authority of each Party involved.
Kyoto Protocol
Art. 12.5a,
CDM Modalities and
Procedures 40a
CA
Th
ho
OK
4.
The project shall assist non-Annex I Parties in achieving sustainable
development and shall have obtained confirmation by the host country
thereof.
Kyoto Protocol Art. 12.2,
CDM Modalities and
Procedures 40a
OK
5. In case public funding from Parties included in Annex I is used for the
project activity, these Parties shall provide an affirmation that such
funding does not result in a diversion of official development assistance
and is separate from and is not counted towards the financial
obligations of these Parties.
Decision 17/CP.7,
CDM Modalities and
Procedures Appendix B, 2
OK
Th
inf
pro
of
(O
6. Parties participating in the CDM shall designate a national authority for
the CDM.
CDM Modalities and
Procedures 29
Th
AuN
M
7. The host Party and the participating Annex I Party shall be a Party to
the Kyoto Protocol.
CDM Modalities 30/31a Th
the
-
7/31/2019 Project on ONGC Validation
27/67
DET NORSKE VERITAS
CDM Validation Protocol Report No.2008-0065, rev. 02
Requirement Reference Co
20
8. The participating Annex I Partys assigned amount shall have been
calculated and recorded.
CDM Modalities and
Procedures 31b
NA
9. The participating Annex I Party shall have in place a national system
for estimating GHG emissions and a national registry in accordance
with Kyoto Protocol Article 5 and 7.
CDM Modalities and
Procedures 31b
NA
About additionality
10.Reduction in GHG emissions shall be additional to any that would
occur in the absence of the project activity, i.e. a CDM project activity
is additional if anthropogenic emissions of greenhouse gases by sources
are reduced below those that would have occurred in the absence of the
registered CDM project activity.
Kyoto Protocol Art. 12.5c,
CDM Modalities and
Procedures 43
CL
OK
About forecast emission reductions and environmental impacts
11.The emission reductions shall be real, measurable and give long-term
benefits related to the mitigation of climate change.
Kyoto Protocol Art. 12.5b CA
OK
For large-scale projects only
12.Documentation on the analysis of the environmental impacts of theproject activity, including transboundary impacts, shall be submitted,
and, if those impacts are considered significant by the project
participants or the Host Party, an environmental impact assessment in
accordance with procedures as required by the Host Party shall be
carried out.
CDM Modalities andProcedures 37c
OK
About small-scale project activities (if applicable)
13.The proposed project activity shall meet the eligibility criteria for small
scale CDM project activities set out in 6 (c) of the Marrakech
Accords and shall not be a debundled component of a larger project
Simplified Modalities and
Procedures for Small Scale
CDM Project Activities
NA
-
7/31/2019 Project on ONGC Validation
28/67
DET NORSKE VERITAS
CDM Validation Protocol Report No.2008-0065, rev. 02
Requirement Reference Co
activity. 12a,c
14.The proposed project activity shall confirm to one of the project
categories defined for small scale CDM project activities and use the
simplified baseline and monitoring methodology for that project
category.
Simplified Modalities and
Procedures for Small Scale
CDM Project Activities 22e
NA
15.If required by the host country, an analysis of the environmental
impacts of the project activity is carried out and documented.
Simplified Modalities and
Procedures for Small Scale
CDM Project Activities 22c
NA
About stakeholder involvement
16.Comments by local stakeholders shall be invited, a summary of these
provided and how due account was taken of any comments received.
CDM Modalities and
Procedures 37b
OK
17.Parties, stakeholders and UNFCCC accredited NGOs shall have been
invited to comment on the validation requirements for minimum 30
days, and the project design document and comments have been made
publicly available.
CDM Modalities and
Procedures 40
OK
Other
18.The baseline and monitoring methodology shall be previously approved
by the CDM Executive Board.
CDM Modalities and
Procedures 37e
OK
19.A baseline shall be established on a project-specific basis, in a
transparent manner and taking into account relevant national and/or
sectoral policies and circumstances.
CDM Modalities and
Procedures 45c,d
OK
20.
The baseline methodology shall exclude to earn CERs for decreases inactivity levels outside the project activity or due to force majeure. CDM Modalities andProcedures 47 OK
21.The project design document shall be in conformance with the
UNFCCC CDM-PDD format.
CDM Modalities and
Procedures Appendix B, EB
Decision
OK
-
7/31/2019 Project on ONGC Validation
29/67
DET NORSKE VERITAS
CDM Validation Protocol Report No.2008-0065, rev. 02
Requirement Reference Co
22.Provisions for monitoring, verification and reporting shall be in
accordance with the modalities described in the Marrakech Accords
and relevant decisions of the COP/MOP.
CDM Modalities and
Procedures 37f
OK
-
7/31/2019 Project on ONGC Validation
30/67
DET NORSKE VERITAS
* MoV = Means of Verification, DR= Document Review, I= Interview
CDM Validation Protocol Report No.2008-0065, rev. 02
Table 2 Requirements Checklist
CHECKLIST QUESTION Ref. MoV* COMMENTS
A. General Description of Project ActivityThe project design is assessed.
A.1. Project Boundaries
Project Boundaries are the limits and borders defining the
GHG emission reduction project.
A.1.1. Are the projects spatial boundaries
(geographical) clearly defined?/1/ DR/I Yes, the projects spatial
defined. The project site is loc
Jakhau and Budiya in Abdasa
A.1.2. Are the projects system boundaries (components
and facilities used to mitigate GHGs) clearly
defined?
/1/
/6/
DR/I The project system boundar
defined and consist of the 34 W
make and each having a capac
The spatial boundary also
Western regional grid of Ind
project is connected. India
which earlier had 5 regional
reorganized in to two region
and NEWNE) vide the CE
version 04 released on 8the S
Hence the project activity is c
NEWNE regional grid as per
data.
PDD is to be corrected to refle
A.2. Participation RequirementsReferring to Part A, Annex 1 and 2 of the PDD as well
as the CDM glossary with respect to the terms Party,
Letter of Approval, Authorization and Project
Participant.
-
7/31/2019 Project on ONGC Validation
31/67
DET NORSKE VERITAS
* MoV = Means of Verification, DR= Document Review, I= Interview
CDM Validation Protocol Report No.2008-0065, rev. 02
CHECKLIST QUESTION Ref. MoV* COMMENTS
A.2.1. Which Parties and project participants are
participating in the project?
/1/ DR/I India is the host party and O
Gas Corporation Limited (Project participant.
A.2.2. Have all involved Parties provided a valid and
complete letter of approval and have all
private/public project participants been authorized
by an involved Party?
/1/
/5/
DR/I The LoA from the DNA, In
provided.
A.2.3. Do all participating Parties fulfil the participation
requirements as follows:
- Ratification of the Kyoto Protocol
- Voluntary participation
- Designated a National Authority
/1/
/5/
DR/I The Designated National Au
is Ministry of Environmental
India ratified the Kyoto P
August 2002.
The letter of approval is to be
A.2.4. Potential public funding for the project from
Parties in Annex I shall not be a diversion of
official development assistance.
/1/ DR/I No public funding has been
project activity.
A.3. Technology to be employed
Validation of project technology focuses on the project
engineering, choice of technology and competence/
maintenance needs. The validator should ensure that
environmentally safe and sound technology and know-how isused.
A.3.1. Does the project design engineering reflect
current good practices?/1/ DR/I The wind turbines have been
and erected by Suzlon Energ
turbines are designed for cut i
and cut out speed of 20m
-
7/31/2019 Project on ONGC Validation
32/67
DET NORSKE VERITAS
* MoV = Means of Verification, DR= Document Review, I= Interview
CDM Validation Protocol Report No.2008-0065, rev. 02
CHECKLIST QUESTION Ref. MoV* COMMENTS
features of the project include
electromechanical pitch sysblade and via Suzlon-Fle
These features indicate
proponents intention for
engineering design and practic
The Purchase order has b
during the site visit.
A.3.2. Does the project use state of the art technology or
would the technology result in a significantly
better performance than any commonly used
technologies in the host country?
/1/ DR/I The Project utilizes
manufactured equipments
generation.
A.3.3.Does the project make provisions for meeting
training and maintenance needs?/1/ DR/I The operation and maintenanc
is contracted to the man
suppliers of the equipment Su
training is not envisaged.
A.4. Contribution to Sustainable Development
The projects contribution to sustainable development is
assessed.
A.4.1. Has the host country confirmed that the project
assists it in achieving sustainable development?/1/
/5/
DR/I The letter of approval fr
confirming that the proje
achieving sustainable develop
be provided for verification.
The host country LoA needs
B.1.1. Will the project create other environmental or
social benefits than GHG emission reductions?/1/ DR/I Yes. Apart from GHG reducti
envisages following benefits:
The project will help t
dependence on fossil fu
-
7/31/2019 Project on ONGC Validation
33/67
DET NORSKE VERITAS
* MoV = Means of Verification, DR= Document Review, I= Interview
CDM Validation Protocol Report No.2008-0065, rev. 02
CHECKLIST QUESTION Ref. MoV* COMMENTS
generation.
The project activity employment opportun
construction and operation
B. Project Baseline
The validation of the project baseline establishes whether the
selected baseline methodology is appropriate and whether the
selected baseline represents a likely baseline scenario.
B.1. Baseline Methodology
It is assessed whether the project applies an appropriate
baseline methodology.
B.1.2. Does the project apply an approved methodology
and the correct version thereof?
/1/
/3/
DR/I The project correctly applie
baseline methodology Consomethodology for grid-conne
generation from renewable
0002, version 07 for larg
projects.
B.1.3. Are the applicability criteria in the baseline
methodology all fulfilled?/1/
/6/
DR/I The applicability criteria is dis
The project activity is the
modification/retrofit of
plant/unit.
The project activity is the in
MW wind energy based powe
The geographic and systfor the relevant electrici
clearly identified and info
characteristics of the grid
The geographic and system
the western regional grid (WR
-
7/31/2019 Project on ONGC Validation
34/67
DET NORSKE VERITAS
* MoV = Means of Verification, DR= Document Review, I= Interview
CDM Validation Protocol Report No.2008-0065, rev. 02
CHECKLIST QUESTION Ref. MoV* COMMENTS
been clearly identified. The
the characteristics of the WThis however needs to be co
line with the latest CEA bifurc
B.2. Baseline Scenario Determination
The choice of the baseline scenario will be validated with
focus on whether the baseline is a likely scenario, and
whether the methodology to define the baseline scenario
has been followed in a complete and transparent manner.
B.2.1. What is the baseline scenario? /1/ DR/I The baseline scenario as per th
is that in the absence of the p
electricity would have been g
existing or by new additions idominated grid.
B.2.2. What other alternative scenarios have been
considered and why is the selected scenario the
most likely one?
/1/ DR/I Other alternatives for the pro
mentioned below:
Alternative 1: The proposed
not undertaken as a CDM proj
Alternative 2: No project activ
However, the PP is requested
justify on the other alternative
fossil fuel, renewable sources
and state why these are not
scenarios.B.2.3. Has the baseline scenario been determined
according to the methodology?/1/ DR/I Yes, the baseline scenar
determined according to the
However CL-1 needs to be ad
B.2.4. Has the baseline scenario been determined using /1/ DR/I Refer to B.2.2
-
7/31/2019 Project on ONGC Validation
35/67
DET NORSKE VERITAS
* MoV = Means of Verification, DR= Document Review, I= Interview
CDM Validation Protocol Report No.2008-0065, rev. 02
CHECKLIST QUESTION Ref. MoV* COMMENTS
conservative assumptions where possible?
B.2.5. Does the baseline scenario sufficiently take into
account relevant national and/or sectoral policies,
macro-economic trends and political aspirations?
/1/ DR/I Yes, national and sectoral pol
taken into account.
B.2.6. Is the baseline scenario determination compatible
with the available data and are all literature and
sources clearly referenced?
/1/ DR/I Yes.
B.4.1. Have the major risks to the baseline been
identified?/1/ DR/I The baseline scenario has b
using conservative assumption
B.3. Additionality Determination
The assessment of additionality will be validated with
focus on whether the project itself is not a likely baseline
scenario.
B.3.1. Is the project additionality assessed according to
the methodology?/1/
/4/
/31/
/23/
/28/
/30/
DR/I The assessment and demon
additionality has been done a
additionality tool, version 5.2.
Step 1a: Define alternatives
activity:
Alternative 1: The proposed
not undertaken as a CDM proj
Alternative 2: No project a
continuation of the presen
drawing power from the grid.
Both alternatives are realistic
the project activity.
-
7/31/2019 Project on ONGC Validation
36/67
DET NORSKE VERITAS
* MoV = Means of Verification, DR= Document Review, I= Interview
CDM Validation Protocol Report No.2008-0065, rev. 02
CHECKLIST QUESTION Ref. MoV* COMMENTS
Step 1b: Consistency with m
and regulations: Both alternatives are in complianc
and regulations.
Step 2: Investment Analysis:
The benchmark analysis has b
demonstrate the additionality
The internal rate of return (
considered as the benchmark p
The project proponent, ON
sector undertaking and has
internal benchmark (hurdle (post tax) for developmenta
document confirming the inte
ONGC Order
MUM/PAS/PROJ/APPR/RR/
June, 2007, Para 3.1.has been
is reasonable compared to th
benchmark. The order also cl
target IRR for acceptance
proposals (development proje
be considered at a minimum
(post tax). However, in resp
with IRR of less than 12% right to reject such projects wo
vest with the Corporate Manag
The IRR of the project act
calculated to be at 10.59%
revenues) and lower than the
-
7/31/2019 Project on ONGC Validation
37/67
DET NORSKE VERITAS
* MoV = Means of Verification, DR= Document Review, I= Interview
CDM Validation Protocol Report No.2008-0065, rev. 02
CHECKLIST QUESTION Ref. MoV* COMMENTS
12% and hence project is
attractive.The following need to be
evidence.
a) The appropriateness of
selected
As per the EB 41, Annex 45, P
is also requested to demon
internal benchmark has be
applied by the company for at
relation to similar projects
financial statements, and
evidence on the acceptance a
project with this benchmark (h
b) It also needs to be clarifi
load factor used in the IRR c
PDD states the PLF as 22.2
consultants recommendation
worksheet uses a PLF of 23.4
also to be justified as the GE
11 August 2006 states the CU
site to be 25.68%.
c) The PP is requested
application of MAT to the
and ONGC and also on the vused in the calculation. It al
clarified if the MAT is to be
entire 20 years or till the time
holiday exists.
d) O& M values used for O
-
7/31/2019 Project on ONGC Validation
38/67
DET NORSKE VERITAS
* MoV = Means of Verification, DR= Document Review, I= Interview
CDM Validation Protocol Report No.2008-0065, rev. 02
CHECKLIST QUESTION Ref. MoV* COMMENTS
justified with a split-up.
Step 2d: Sensitivity Analysis:The sensitivity analysis h
considering the parameters of
a) Capex Capital Expen
project
b) Opex - Operating expense
c) Generation - Electricity g
project.
considering an variation of +
% in Capex and Opex value
on 10 % to 20 % in gener
decrease of the IRR for the proThe sensitivity analysis is to
considering increase in g
analysis is also to be ca
variations at which the IR
benchmark and also justify w
is not likely.
Step 3: Barrier Analysis:
As per the PP, after conduc
analysis, the CDM project
financially attractive, the
discussed the Barrier AnalysisStep 4: Common Practice Ana
Step 4a: Analyze other activ
the proposed project activity:
The PP has provided inform
-
7/31/2019 Project on ONGC Validation
39/67
DET NORSKE VERITAS
* MoV = Means of Verification, DR= Document Review, I= Interview
CDM Validation Protocol Report No.2008-0065, rev. 02
CHECKLIST QUESTION Ref. MoV* COMMENTS
power generation capacity o
respective state along capacities.
As per the information, In
potential of 45195 MW o
against which only 5340.6
utilized. Thus only 4.2 %
installed capacity for pow
(including fossil fuel based po
For the case of Gujarat sta
gross potential for wind pow
9675 MW and out of that o
has been utilized as of 31/03/2
The data provided for install
Gujarat state needs to be upda
The PP is requested to also
reference of gross potentia
capacity from more authentic
Step 4b: Discuss any similar
occurring:
As argued by the PP, a cou
energy based power proje
independent power projects
capacity similar to the pr
activity in Gujarat. Howe
projects are being impleme
projects. Its because IPPs o
not financially attractive with
The PP is requested to provi
-
7/31/2019 Project on ONGC Validation
40/67
DET NORSKE VERITAS
* MoV = Means of Verification, DR= Document Review, I= Interview
CDM Validation Protocol Report No.2008-0065, rev. 02
CHECKLIST QUESTION Ref. MoV* COMMENTS
many projects are implemen
out such project how implemented keeping CDM in
It is also to be clarified as
projects of similar capacity a
location are CDM projects o
CDM revenues?
B.3.2. Are all assumptions stated in a transparent and
conservative manner?/1/ DR/I Refer to B.3.1
B.3.3. Is sufficient evidence provided to support the relevance
of the arguments made?/1/ DR/I Refer to B.3.1
B.3.4.
If the starting date of the project activity is before the
date of validation, has sufficient evidence been provided
that the incentive from the CDM was seriously
considered in the decision to proceed with the project
activity?
/1/
/8/
DR/I The starting date of the pro
stated to be 06 November 200
of Award for the project activ
And it is before the start of va
The serious consideration of
CDM has been demonstrated
note mentioning the expected
less than the benchmark and
revenue from CDM project,
been implemented.
Chronological order of evconceptualization of the proj
approaching the DOE for v
with reasons for delay need
with supporting evidences.
B.4. Calculation of GHG Emission Reductions Project
-
7/31/2019 Project on ONGC Validation
41/67
DET NORSKE VERITAS
* MoV = Means of Verification, DR= Document Review, I= Interview
CDM Validation Protocol Report No.2008-0065, rev. 02
CHECKLIST QUESTION Ref. MoV* COMMENTS
emissions
It is assessed whether the project emissions are statedaccording to the methodology and whether the
argumentation for the choice of default factors and values
where applicable is justified.
B.4.2. Are the calculations documented according to the
approved methodology and in a complete and
transparent manner?
/1/ DR/I There are no project emission
activity.
B.4.3. Have conservative assumptions been used when
calculating the project emissions?/1/ DR/I Refer to B.4.1
B.4.4. Are uncertainties in the project emission estimates
properly addressed?/1/ DR/I Refer to B.4.1
B.5. Calculation of GHG Emission Reductions Baselineemissions
It is assessed whether the baseline emissions are stated
according to the methodology and whether the
argumentation for the choice of default factors and values
where applicable is justified.
B.3.5. Are the calculations documented according to the
approved methodology and in a complete and transparent
manner?
/1/
/6/
DR/I Baseline emissions have bee
the product of net electricity
Western regional grid by the
per year and grid emissionWestern regional grid, wh
obtained from the official
Central Electricity authority
Baseline Database for the
Sector User Guide - Version 3
-
7/31/2019 Project on ONGC Validation
42/67
DET NORSKE VERITAS
* MoV = Means of Verification, DR= Document Review, I= Interview
CDM Validation Protocol Report No.2008-0065, rev. 02
CHECKLIST QUESTION Ref. MoV* COMMENTS
Baseline emission factor fo
regional grid is established exthe approved methodology us
margin approach consisting
margin and 25% build margin
combined margin emission co
southern regional grid of I
determined to be 0.89 t CO
operating margin has been e
1.00 t CO2/MWh and the bui
0.59 tCO2/MWh.
The PP needs to apply the la
the CEA database for fixin
factor.
B.3.6. Have conservative assumptions been used when
calculating the baseline emissions?/1/ DR/I Yes. The chosen baseline is
with the baseline methodology
B.3.7. Are uncertainties in the baseline emission estimates
properly addressed?/1/ DR/I There are no uncertainties
emissions.
B.6. Calculation of GHG Emission Reductions Leakage
It is assessed whether leakage emissions are stated
according to the methodology and whether the
argumentation for the choice of default factors and values
where applicable is justified.
B.6.1. Are the leakage calculations documented
according to the approved methodology and in a
complete and transparent manner?
/1/ DR/I For Wind based energy gen
Project the PP do not nee
leakage in applying this metho
-
7/31/2019 Project on ONGC Validation
43/67
DET NORSKE VERITAS
* MoV = Means of Verification, DR= Document Review, I= Interview
CDM Validation Protocol Report No.2008-0065, rev. 02
CHECKLIST QUESTION Ref. MoV* COMMENTS
B.6.2.
Have conservative assumptions been used whencalculating the leakage emissions?
/1/ DR/I NA
B.6.3. Are uncertainties in the leakage emission
estimates properly addressed?/1/ DR/I NA
B.7. Emission Reductions
The emission reductions shall be real, measurable
and give long-term benefits related to the mitigation
of climate change.
B.7.1. Are the emission reductions real, measurable and
give long-term benefits related to the mitigationof climate change.
/1/ DR/I The project activity is expec
emission reduction of 85 762 through out the first creditin
years.
This figure is to be recalcu
latest grid emission factors p
CEA.
B.8. Monitoring Methodology
It is assessed whether the project applies an appropriate
monitoring methodology.
B.8.1. Is the monitoring plan documented according to
the approved methodology and in a complete and
transparent manner?
/1/
/3/
DR/I The monitoring plan documen
approved consolidate method
0002, version 07 and in
transparent manner.
The monitoring of the
generated is not clear in the P
to be elaborated conside
uploading meter is not de
-
7/31/2019 Project on ONGC Validation
44/67
DET NORSKE VERITAS
* MoV = Means of Verification, DR= Document Review, I= Interview
CDM Validation Protocol Report No.2008-0065, rev. 02
CHECKLIST QUESTION Ref. MoV* COMMENTS
project activity.
B.8.2.
Will all monitored data required for verificationand issuance be kept for two years after the end of
the crediting period or the last issuance of CERs,
for this project activity, whichever occurs later?
/1/ DR/I Yes, all monitored data verification and issuance will
years after end of the crediting
B.9. Monitoring of Project Emissions
It is established whether the monitoring plan provides for
reliable and complete project emission data over time.
B.9.1. Does the monitoring plan provide for the
collection and archiving of all relevant data
necessary for estimation or measuring the
greenhouse gas emissions within the projectboundary during the crediting period?
/1/ DR/I Being a wind power proj
emissions are expected to occu
B.9.2. Are the choices of project GHG indicators
reasonable and conservative?/1/ DR/I NA
B.9.3. Is the measurement method clearly stated for each
GHG value to be monitored and deemed
appropriate?
/1/ DR/I NA
B.9.4. Is the measurement equipment described and
deemed appropriate?/1/ DR/I NA
B.9.5. Is the measurement accuracy addressed and
deemed appropriate? Are procedures in place on
how to deal with erroneous measurements?
/1/ DR/I NA
-
7/31/2019 Project on ONGC Validation
45/67
DET NORSKE VERITAS
* MoV = Means of Verification, DR= Document Review, I= Interview
CDM Validation Protocol Report No.2008-0065, rev. 02
CHECKLIST QUESTION Ref. MoV* COMMENTS
B.9.6. Is the measurement interval identified and
deemed appropriate?
/1/ DR/I NA
B.9.7. Is the registration, monitoring, measurementand
reporting procedure defined?/1/ DR/I NA
B.9.8. Are procedures identified for maintenance of
monitoring equipment and installations? Are the
calibration intervals being observed?
/1/ DR/I NA
B.9.9. Are procedures identified for day-to-day records
handling (including what records to keep, storage
area of records and how to process performance
documentation)
/1/ DR/I NA
B.10.Monitoring of Baseline Emissions
It is established whether the monitoring plan provides for
reliable and complete baseline emission da