New Ringgold Middle School
Project SlideshowAugust 26, 2017
![Page 2: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/2.jpg)
Aerial Photo from West
Provided by Hudson Group – Taken 8.16.2017
![Page 3: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/3.jpg)
Aerial Photo from North
Provided by Hudson Group – Taken 8.16.2017
![Page 4: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/4.jpg)
Aerial Photo from East
Provided by Hudson Group – Taken 8.16.2017
![Page 5: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/5.jpg)
Aerial Photo from South
Provided by Hudson Group – Taken 8.16.2017
![Page 6: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/6.jpg)
Building Areas
Provided by Hudson Group – Taken 7.29.2017
![Page 7: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/7.jpg)
1st Floor - Area A
![Page 8: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/8.jpg)
Reception Desk Installation – Admin Area - 1st Floor – Area A
![Page 9: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/9.jpg)
Final Cleaning– 1st Floor – Area A
Admin Area
Cafeteria
Corridor
![Page 10: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/10.jpg)
Work Progress – 1st Floor - Area A
Remaining Work to Complete:• Reception Desk Installation in Admin Area• Food Service Equipment Remaining Installation Items• Architect/Engineer Punchlist (Wednesday, August 30, 2017)• Ansul System Inspection (Thursday, August 31, 2017)• Final Electrical Inspection (Thursday, August 31, 2017)• Final Plumbing Inspection (Thursday, August 31, 2017)• Final Cleaning
![Page 11: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/11.jpg)
2nd Floor – Area A
![Page 12: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/12.jpg)
Circulation Desk Installation – Media Center - 2nd Floor - Area A
![Page 13: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/13.jpg)
Final Cleaning– 2nd Floor – Area A
STEM Classroom
Science Classroom
Corridor
![Page 14: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/14.jpg)
Work Progress – 2nd Floor - Area A
Remaining Work to Complete:• Circulation Desk Installation in Media Center• Contractor Punchlist Items• Final Cleaning
![Page 15: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/15.jpg)
1st Floor - Area B
![Page 16: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/16.jpg)
Final Cleaning– 1st Floor – Area B
Classroom
Science Classroom
Corridor
![Page 17: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/17.jpg)
Work Progress – 1st Floor - Area B
Remaining Work to Complete:• Architect/Engineer Punchlist (Wednesday, August 30, 2017)• Final Electrical Inspection (Thursday, August 31, 2017)• Final Plumbing Inspection (Thursday, August 31, 2017)• Final Cleaning
![Page 18: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/18.jpg)
2nd Floor - Area B
![Page 19: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/19.jpg)
Final Cleaning– 2nd Floor – Area B
Classroom
Corridor
![Page 20: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/20.jpg)
Work Progress – 2nd Floor - Area A
Remaining Work to Complete:• Contractor Punchlist Items• Final Cleaning
![Page 21: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/21.jpg)
1st Floor - Area C
![Page 22: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/22.jpg)
Final Cleaning– 1st Floor – Area C
Classroom
Science Classroom
Corridor
![Page 23: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/23.jpg)
Work Progress – 1st Floor - Area C
Remaining Work to Complete:• Architect/Engineer Punchlist (Wednesday, August 30, 2017)• Final Electrical Inspection (Thursday, August 31, 2017)• Final Plumbing Inspection (Thursday, August 31, 2017)• Final Cleaning
![Page 24: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/24.jpg)
2nd Floor - Area C
![Page 25: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/25.jpg)
Final Cleaning– 2nd Floor – Area C
Classroom
Science Classroom
Corridor
![Page 26: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/26.jpg)
Work Progress – 2nd Floor - Area C
Remaining Work to Complete:• Contractor Punchlist Items• Final Cleaning
![Page 27: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/27.jpg)
1st Floor - Area D
![Page 28: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/28.jpg)
Mural & Ceramic Tile Installation – Area D
![Page 29: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/29.jpg)
Ceramic Tile Installation – Area D
![Page 30: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/30.jpg)
Casework Installation – Area D
![Page 31: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/31.jpg)
Ceiling Grid Installation – Area D
![Page 32: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/32.jpg)
Ceiling Tile Installation – Area D
![Page 33: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/33.jpg)
Ceiling Tile Installation – Band & Choral Rooms – Area D
![Page 34: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/34.jpg)
Acoustical Panel Installation – Area D
BandGym
Auditorium
![Page 35: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/35.jpg)
Wood Panel Installation - Auditorium – Area D
![Page 36: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/36.jpg)
Storefront Installation – Gym Entrance – Area D
![Page 37: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/37.jpg)
VCT Installation – Area D
![Page 38: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/38.jpg)
Gym Floor Installation – Area D
![Page 39: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/39.jpg)
Light Fixture Installation – Area D
![Page 40: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/40.jpg)
Duct Sock Installation – Gym - Area D
![Page 41: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/41.jpg)
GRD Installation – Restrooms - Area D
![Page 42: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/42.jpg)
Ductwork Insulation – Area D
![Page 43: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/43.jpg)
Interior Work Progress – 1st Floor - Area DWork Completed• Electrical Rough In• Gym Speaker Installation• Gym Sound System Installation• Plumbing Rough In• Plumbing Piping Insulation• Plumbing Fixture Installation• HVAC Piping Installation• HVAC Ductwork Installation• Sprinkler Piping Installation• Rolling Grille Installation• Locker Bases• Locker Installation• Translucent Panel Installation• Window Installation• Cement Board InstallationWork in Progress• Light Fixture Installation• HVAC Insulation Installation• HVAC Controls• Sprinkler Head Installation• Stage Equipment Installation
• Support for Acoustical Panels• Auditorium Acoustical Panel Installation• Auditorium Chair Installation• Locker Installation• Bulkhead Installation• Interior Door Frame Installation• Block Filler• Drywall Installation• Toilet Partition Installation• Display Case Installation• Painting• Exterior Door Installation• Ceramic Tile Installation• Gym Equipment Installation• Toilet Accessory Installation• Ceiling Grid Installation
• Wood & Metal Door Installation• Auditorium Wood Panel Installation• Signage Installation• Ceiling Tile Installation• VCT Installation• Gym Floor Installation
![Page 44: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/44.jpg)
EIFS Installation
Gym Entrance
Loading Dock
![Page 45: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/45.jpg)
Concrete Sidewalk Installation
HS Entrance 2
Along West Roadway
![Page 46: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/46.jpg)
Concrete Sidewalk at Retaining Walls 4A & 4B
![Page 47: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/47.jpg)
Concrete Curbs
![Page 48: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/48.jpg)
Placing Topsoil
![Page 49: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/49.jpg)
Asphalt Binder Course
![Page 50: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/50.jpg)
Guard Rail Installation
![Page 51: Project Slideshow August 26, 2017 - Ringgold School District · 2017-08-29 · Project Slideshow August 26, 2017. Aerial Photo from West Provided by Hudson Group – Taken 8.16.2017](https://reader033.vdocuments.net/reader033/viewer/2022060500/5f1a1a2d77451b2c0005e365/html5/thumbnails/51.jpg)
• Complete Countertop Sink Installation • Complete Casework Installation• Complete Countertop Installation• Complete Food Service Equip. Installation• Finish Ceiling Tile Installation – Area D• Complete Flooring Installation – Area D• Finish Gym Wood Floor Installation• Stage Floor Installation • Complete Metal Door Installation• Complete Wood Door Installation• Finish Site Concrete• Asphalt Paving • Continue Installing Topsoil• Site Landscaping
Scheduled Work for Next Few Weeks