proposed amendment in ec of …environmentclearance.nic.in/writereaddata/formb/modiec/...proposed...

18
F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad 1 FORM 1 FOR PROPOSED AMENDMENT IN EC OF CONSCTRUCTION HOSPITAL BUILDING PROJECT (126115.20 Sq. m) (90276.50 Sq. m as per EC+ Proposed 35738.70 Sq. m) AT U. N. MEHTA INSTITUTE OF CARDIOLOGY & RESEARCH CENTRE F.P. 202/P, T.P. 8, CIVIL HOSPITAL, ASARWA, AHMEDABAD, GUJARAT-380 016 Developed By: U. N. MEHTA INSTITUTE OF CARDIOLOGY & RESEARCH CENTRE F.P. 202/P, T.P. 8, CIVIL HOSPITAL, ASARWA, AHMEDABAD, GUJARAT-380 016 M-9825244189/9099955137, E Mail- [email protected]

Upload: lelien

Post on 04-May-2018

214 views

Category:

Documents


1 download

TRANSCRIPT

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

1

FORM 1

FOR

PROPOSED AMENDMENT IN EC OF

CONSCTRUCTION HOSPITAL BUILDING PROJECT

(126115.20 Sq. m)

(90276.50 Sq. m as per EC+ Proposed 35738.70 Sq. m)

AT

U. N. MEHTA INSTITUTE OF CARDIOLOGY &

RESEARCH CENTRE

F.P. 202/P, T.P. 8, CIVIL HOSPITAL, ASARWA, AHMEDABAD,

GUJARAT-380 016

Developed By:

U. N. MEHTA INSTITUTE OF CARDIOLOGY & RESEARCH CENTRE

F.P. 202/P, T.P. 8, CIVIL HOSPITAL, ASARWA, AHMEDABAD,

GUJARAT-380 016

M-9825244189/9099955137, E Mail- [email protected]

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

2

APPENDIX I (See paragraph – 6)

FORM 1

(I) Basic Information Sr. No.

Item Details

1 Name of the project/s Hospital Infrastructure & Building Project 2 S. No. In the schedule 8 (a) 3 Proposed capacity/area/length/tonnage to

be handled/command area/lease area/number of wells to be drilled

Hospital Construction & Building Project

1. 1000 beds

(As per last EC)

2. 140 Hostel Rooms

(121 as per EC+ 19 Proposed)

3. 38 Faculty Rooms

(20 as per EC+ 18 Proposed)

Total Built up Area: 126115.20 sq. m

( 90276.50 sq. m as per EC+ Proposed

35738.70 sq. m)

Total FSI Area : 82736.00 sq. m

( 60395.58 sq. m as per EC+ Proposed

19340.42 sq. m)

Please refer Annexure - I

4 New/Expansion/Modernization Expansion 5 Existing Capacity/Area etc. Total Plot Area: 21037 sq. m

(15420 sq. m as per EC+ Additional 5617

sq. m)

6 Category of Project i.e. ‘A’ or ‘B’ ‘B’ 7 Does it attract the general condition? If

yes, please specify No

8 Does it attract the specific condition? If yes, please specify

No

9 Location

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

3

Plot/Survey/Khasra No. FP NO.: 202/P, TPS NO. 8 Village At: Asarwa, Tehsil City District Ahmedabad State Gujarat-380016

10 Nearest railway station / air port along with distance in kms.

Railway Station: Ahmedabad(Kalupur) – 4.9 km Airport : Ahmedabad – 5.5 km

11 Nearest Town, city, District Headquarters along with distance in kms

Ahmedabad – The proposed project is within the limit of the Ahmedabad Municipal

Corporation(AMC) 12 Village Panchayats, Zilla Parishad,

Municipal Corporation, Local body (complete postal addresses with telephone nos. to be given)

At: Asarwa Taluka: City

Dist: Ahmedabad

13 Name of applicant U. N. MEHTA INSTITUTE OF CARDIOLOGY

& RESEARCH CENTRE Dr. R. K. Patel/ Dr. Pranav Sharma

15 Address for correspondence Name U. N. MEHTA INSTITUTE OF

CARDIOLOGY & RESEARCH CENTRE Designation (Owner/Partner/CEO) Director/Associate Prof. in CVTS Address FP NO.: 202/P, TPS NO. 8

Civil Hospital, Asarwa, Ahmedabad, GUJARAT

Pin Code 380016 E-mail [email protected] Telephone No. (M9825244189/9099955137 Fax No. 07922682092

16 Details of Alternative Sites examined, if any. Location of this site should be shown on a topo sheet.

No

17 Interlinked Projects Yes 18 Whether separate application of

interlinked project has been submitted? Yes GPCB CC&A has been granted

19 If yes, date of submission Existing facility has been granted CC&A on dated 2/7/2011 with validity 6/6/2016 And Authorization of BMW has been

granted on dated 20/11/2014 with validity up to 31/06/2017

20 If no, reason - 21 Whether the proposal involves

approval/clearance under: if yes, details of the same and their status to be given. (a) The Forest (Conservation Act, 1980?

No

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

4

(b) The Wildlife (Protection) Act, 1972? © The C.R.Z Notification, 1991?

22 Whether there is any Government Order/Policy relevant/relating to the site?

UNMICRC is a TRUST Copy is attached

23 Forest land involved (hectare) None 24 Whether there is any litigation pending

against the project and/ or land in which the project is propose to be set up? (a) Name of the Court (b) Case No. (c) Orders/direction of the Court, if any and its relevance with the proposed project.

None

(II) Activity

1. Construction, operation or decommissioning of project involving action, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

Sr. No.

Information /checklist confirmation YES/NO

Details thereof (with approximate quantities/rate, wherever possible) with source of information data

1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of local land use plan)

No The proposed hospital building project will be developed at F.P. No. 202/P, T.P.S. NO.:8, Asarwa, Ahmedabad Gujarat-380016.

1.2 Clearance of existing land, vegetation and buildings?

Yes Existing facility is having GPCB clearance

1.3 Creation of new land use? No - 1.4 Pre-construction investigation e.g. bore

house, soil testing? Yes The soil analysis report is

carried out. 1.5 Construction work

Yes The proposed project is

comprise of – Hospital building project [Basement 1 & 2,

GF + 8 Floor]

Hostel building,

[Basement 1 & 2 + GF + 10

Floor]

1.6 Demolition works? Yes 1308.13 Sq. m of existing old building

1.7 Temporary sites used for construction Yes -

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

5

works or housing of construction works? 1.8 Above ground building, structures or

earth works including liner structures, cut and ill or excavations

Yes Total Built Up Area for the

proposed building is

126115.20 sq. m (Existing

90276.50 sq. m + 35738.7 sq.

m)

These buildings are high rise building as per GDCR Norms.

1.9 Underground works including mining or tunneling?

No -

1.10 Reclamation works? No - 1.11 Dredging? No - 1.12 Offshore structures? No - 1.13 Production and manufacturing

processes? No It is a Hospital construction

and building project. 1.14 Facilities for storage of goods or

materials? Yes Construction materials like

steel, cement, sand, bricks etc will be procured from local market and will be temporarily stored at site.

1.15 Facility for treatment or disposal of solid waste or liquid effluent?

Yes Wastewater STP is proposed of 400 KLD and AMC sewerage line is the mode of disposal of sewage at the time of operation phase. Please refer Annexure II The Municipal solid waste generated during operation phase will consist of: Organic Waste: Waste vegetable and food @ 2.5 MT/Month Inorganic waste: Papers, cartons, thermocol, plastic, polythene bags, glasses etc. 5 Kg/Month The hospital Waste medical waste @ 25.0 MT/Month shall be disposed off to the BMW disposal facility.

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

6

The solid waste generation shall approximately 2000 kgs/day. The non recyclers solid waste generated will be transferred to the nearest collection point of AMC.

1.16 Facility for long term housing of operational workers?

Yes Hostel Rooms & Faculty Rooms is proposed

1.17 New road, rail or sea traffic during construction or operation?

Yes Road traffic will increase due to the various construction activities and also in the operation phase because of increased population due to proposed project.

1.18 New road rail. Air waterborne or other transport infrastructure including new or altered routes and station, ports airport etc.

No -

1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements?

Yes Road traffic will increase due to the various construction activities and also in the operation phase because of increased population due to proposed project.

1.20 New or diverted transmission lines or pipelines?

Yes Drainage line to be shifted

1.21 Impoundment, damming. Culver ting. Realignment or other changes to the hydrology of watercourses or aquifers?

Yes AMC water supply line is the source of water during operation phase.

1.22 Stream crossing? No - 1.23 Abstraction or transfer of water from

ground or surface waters? No During operation phase the

whole water requirement will be met through AMC water supply. 4 Nos. of percolation well will be constructed for the ground water recharging as per the GDCR Norms.

1.24 Changes in water bodies or the land Surface affecting drainage or run-off?

Yes The project involves construction of paved areas and hence the quantity of runoff will increase due to infiltration. This runoff will be collected through a well – designed surface water drain

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

7

and will be used for recharging aquifers.

1.25 Transport of personnel or material for construction, operation or Decommissioning?

Yes Transportation of construction material will be by truck.

1.26 Long-term dismantling, decommissioning, or restoration works?

No -

1.27 Ongoing activity during decommissioning which could have an impact on the environment?

No -

1.28 Influx of people to an area in either temporarily or permanently?

No -

1.29 Introduction of alien species? No - 1.30 Loss of native species or genetic

diversity? No -

1.31 Any other actions? No -

2. Use of Natural resources for construction or operation of the project (such as land, water material or energy any resources which are non-renewable or in short supply):

Sr. No.

Information/checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data

2.1 Land especially undeveloped or agricultural land (ha)

Yes The Hospital & Hostel building will be constructed on undeveloped land.

2.2 Water (expected source & competing users)

Yes During operation phase the water requirement will be met through AMC water and existing bore well. Please refer Annexure II for water consumption.

2.3 Minerals No - 2.4 Construction material-stone,

aggregates, and/soil (expected source-MT)

Yes Aggregates – 44120 sq. m Sand – 21000 sq. m

2.5 Forests and timber (sources MT) Yes Wood will be used for the furniture if required.

2.6 Energy including electricity and fuels (source, competing users) Units. Fuel (MT) energy (MW)

Yes The project would require about total 4800 KW (existing building load 1400 KW and proposed building load 1000 KW + 2400 KWA = 3400 KWA) Electric power during operation

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

8

phase which is sourced from Torrent Power Ltd.

2.7 Any other natural resources (appropriate standards units)

No -

3. Uses, Storage, Transport, Handling or production of substances or materials, which

could be harmful to production to human health or the environment or raise concern about actual or perceived risks to human health Sr. No. Information/checklist

confirmation Yes/No Details there of (with

approximate quantities/rates, Wherever possible) with source of information data

3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora fauna and water supplies)

No -

3.2 Changes in occurrence of diseases of affect disease vectors (e.g. insect or water borne disease)

No -

3.3 After the welfare of people (e.g. by changing living condition?

Yes During operation phase, direct – indirect employment will be generated which will uplift the socio – economic of the area.

3.4 Vulnerable groups of people who could be affected by the projects e.g. hospital patients, children, the elderly etc.

No -

3.5 Any other cause No - 4. Production of solid waste during construction or operation or decommissioning

MT/month): Sr. No. Information/checklist

confirmation Yes/No Details there of (with

approximate quantities/rates, Wherever possible) with source of information data

4.1 Spoil, overburden or mine waste No - 4.2 Municipal waste (domestic and or

commercial wastes) Yes The Municipal solid waste

generated during operation phase will consist of: Organic Waste: Waste vegetable and food @ 2.5 MT/Month Inorganic waste: Papers, cartons, thermocol,

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

9

plastic, polythene bags, glasses etc. 5 Kg/Month The hospital Waste medical waste @ 25 MT/Month shall be disposed off to the BMW disposal facility. The solid waste generation shall approximately 2000 kgs/day. The non recyclers solid waste generated will be transferred to the nearest collection point of AMC.

4.3 Hazardous waste (as per Hazardous waste Management rules)

Yes As per GPCB Norms

4.4 Other industrial process waste No - 4.5 Surplus project No - 4.6 Sewage sludge or other sludge from

effluent treatment Yes Sewage sludge will be

generated as the entire quantity of sewage will be treated in proposed STP and it shall dispose off into Municipal Solid Waste disposal site/TSDF site.

4.7 Construction or demolition waste Yes 1308.13 sq. m 4.8 Redundant machinery or equipment No -

4.9 Contaminated soils or other materials

No -

4.10 Agriculture waste No - 4.11 Other solid waste No - 5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr): Sr. No. Information/checklist

confirmation Yes/No Details there of (with

approximate quantities/rates, Wherever possible) with source of information data

5.1 Emissions from combustion of fossil fuels from stationary or mobile sources

No -

5.2 Emission from production processes No - 5.3 Emissions from materials handling

including storage or transport rules) No -

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

10

5.4 Emissions from construction activities including plants and equipment

No -

5.5 Dust or orders from handling of materials including construction materials, sewage and waste

Yes Dust suppression by spraying of water and covered shed to be provided for cement unloading activity to minimize the dust emission. The sewage effluent generated during the construction phase shall be disposed off to the AMC drainage and at the operation phase sewage shall treat in to proposed STP and black treated water shall discharge to drainage line of AMC.

5.6 Emissions from incineration of waste

No -

5.7 Emission from burning of waste in open air (e.g. slash materials, construction debris)

No -

5.8 Emissions from any other sources No - 6. Generation of Noise, vibration, Emissions of Lights and Heat. Sr.No. Information/checklist

confirmation Yes/No Details there of (with

approximate quantities/rates, Wherever possible) with source of information data

6.1 From operation of equipment e.g. engines, ventilation plant, crushers.

No -

6.2 From Industrial or similar processes No - 6.3 From construction or demolition Yes Dust suppression by spraying

of water and covered shed to be provided for cement unloading activity to minimize the dust emission.

6.4 From blasting or piling No - 6.5 From construction or operational

traffic Yes During operational activities

noise will be generated due to traffic but there will not be any significant increase in the noise due to the proposed project.

6.6 From lighting or cooling system Yes Lubrication will be carried out for rotation machinery.

6.7 From any other sources No -

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

11

7. Risk of accidents during construction or operation of the Project, which could affect human or the environment.

Sr. No. Information/checklist confirmation

Yes/No Details there of (with approximate quantities/rates, Wherever possible) with source of information data

7.1 From handling, storage, use or spillage of hazardous materials

Yes Existing authorization is

granted

7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge)

Yes Sewage will be treated in STP and black treated water discharged through drainage line of AMC and gray water shall use for flushing and gardening and chilling plant.

7.3 By deposition of pollutants emitted to air, into the land or into water

No -

7.4 From any other source No - 7.5 Is there a risk of long term build up

of pollutants in the environment from these sources?

No All EMS components shall run round the clock, and in case of failure of any of the system there will be safe storage arrangement, which will help for safe storage of waste/effluent. In case of closed till the system gets operational.

8. Risk of accidents during construction or operation of the project, which could

affect human of the environment Sr. No. Information/checklist

confirmation Yes/No Details there of (with

approximate quantities/rates, Wherever possible) with source of information data

8.1 From explosions, spillages, handling, use or production of hazardous substances

No -

8.2 From any other causes No - 8.3 Could the project be affected by

natural disasters causing environmental damage (e.g. floods, earthquakes, landsides, cloudburst etc.)?

Yes Project area is categorized in the Seismic Zone III which is classified as having a fairly medium probability of earthquake shocks.

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality.

Sr. No. Information/checklist Yes/No Details there of (with

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

12

confirmation approximate quantities/rates, Wherever possible) with source of information data

9.1 Lead to development of supporting facility ancillary development or development stimulated by the project which could have impact on the environment e.g.

Supporting infrastructure (roads, power supply, wastewater treatment, etc.

Housing development Supply industry

Others

Yes This is a hospital building and construction project which will lead to the further development of surrounding area and satisfied the need of health center as per the increased population of city.

9.2 Lead to after-use of the site, which could have impact on the environment.

No -

9.3 Set a precedent for later development

No -

9.4 Have cumulative effects due to proximity to other existing or planned project with similar effects.

No -

(III) Environmental Sensitivity Sr. No. Areas Name/Id

entity Aerial distance (with 15 km) proposed project location

boundary 1. Areas protected under international

conventions, national or local legislation for their ecological landscape, cultural or other related value

No -

2 Areas which are important or sensitive for ecological reasons –Wetlands, waster courses or other water bodies coastal zone, biospheres, mountains, forests

No -

3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting foraging, resting, over wintering, migration.

No -

4 Inland, coastal, marine or underground waters

No -

5 States, National boundaries No - 6 Routes or facilities used by the

public for access to recreation or other tourist, pilgrim areas]

- Public transportation

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

13

7 Defense installations No - 8 Densely populated or built-up area No - 9 Areas occupied by sensitive man-

made land uses (hospitals, schools, places of worship, community facilities)

Yes For hospital & community

10 Areas containing important, high quality or scarce resources (ground water resources, surface resource, forestry, agriculture, fisheries tourism, minerals)

No -

11 Areas already subjected to pollution or environmental damage (Those where existing legal environmental standards are exceeded.)

No -

12 Areas susceptible to natural hazard which could cause the project to present environmental problems.(earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climates condition)

No -

III) Proposed Terms of Reference for EIA studies:

As per the EIA Notification, 14th September 2006 of MoEF, New Delhi, no EIA required as the built up area is < 1,50,000/- Sq. m. even though it will be conducted as the TOR issued by SEAC. “I hereby given undertaking that the data and information given in the application and

enclosures are true to the best of my knowledge and belief and I am aware that if any part

of the data and information submitted is found to be false or misleading at any stage, the

project will be rejected and clearance give, if any to the project will be revoked at our risk

and cost.”

Date: September 15, 2016 Signature of the applicant

Place: Ahmedabad

(DIRECTOR)

Name: U. N. MEHTA INSTITUTE OF CARDIOLOGY & RESEARCH CENTRE Full Address: F.P. No. 202/P, T.P.S. NO.:8,

Asarwa, Ahmedabad, Gujarat-380016

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

14

ANNEXURE – I

AREA STATEMENT

Description Details

Existing as per approved EC

Proposed Additional

After proposed Additional

Net Plot Area Total Plot Area:

15420 sq. m

Total Plot Area:

5617 sq. m

Total Plot Area:

21037 sq. m

Built up Area Total Built up Area:

90276.50 sq. m

Total Built up Area:

35738.7 sq. m

Total Built up Area:

126115.20 sq. m

Area, FSI Provided

Total FSI Area :

63395.58 sq. m

Total FSI Area :

19340.42 sq. m

Total FSI Area :

82736.00 sq. m

Common Plot 797.52 m2 797.52 m2 797.52 m2

Green Belt Area Provided

480 m2 480 m2

480 m2

Parking Area Permissible

17266.06m2

17266.06m2

17266.06m2

Parking Area Provided

17303.51m2 17303.51m2

17303.51m2

Ground Floor Area

3698.38 m2 3698.38 m2 3698.38 m2

No. of Units 1000 beds

+

121 Hostel Rooms

+

20 Faculty Rooms

1000 beds

+

19 Hostel Rooms

+

18 Faculty Rooms

1000 beds

+

140 Hostel Rooms

+

38 Faculty Rooms

Visitors 1500 80 1580

Nos. of Blocks 5

- 3

Area for Green Belt

480 m2 - 480 m2

No. of Trees Planning

120 - 120

Max. Height of the Building

41.90 - 41.90

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

15

ANNEXURE –II

WATER AND WASTEWATER DETAILS

Water and Wastewater Details (Operation Phase)

Source: Existing Bore well & Ahmedabad Municipal Corporation (AMC)

Sr. No.

Purpose Water Consumption

(KL/day)

Wastewater Generation

(KL/day)

Remarks

1 After Proposed: Domestic 650 Beds x 450 Lit/day = 292.5 KL/day 500 Auditoriums x 15 Lit. = 7.500 KL/Day 290 Staff permanent x 135 Lit. = 39.150 54 MCI x 340 Lit. = 22.500 1580 Visitors x 45 Lit=71.100 Auditorium & Cafeteria etc.=67.25

500.0

400.0

Wastewater will be 80% of the requirement

2 Other (Fire make up, Cooling Tower, Chiller, DG Set and Plantation)

205 - -

Total 705.0 400.0 - Mode of Disposal: Domestic wastewater generation shall reuse in flushing, chilling plant and plantation and part of the treated sewage shall dispose off through AMC drainage line.

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

16

ANNEXURE –IIII

KEY PLAN

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

17

SITE PLAN

F.P. No. 202/P, T.P.S. NO.:8, UNMICRC , Ahmedabad

18

GOOGLE IMAGE