    GOVERNMENT OF RAJASTHAN

    WATER RESOURCES DEPARTMENT

    QUALITY CONTROL MANUAL

    March  –  2011

    Chief Engineer

    Water Resources Department

    Rajasthan, Jaipur

  • 8/15/2019 Quality Control Manual WRD

    2/211

     

  • 8/15/2019 Quality Control Manual WRD

    3/211

    PREFACE 

    Status of water in Rajasthan is critical and complex. Ground water table is depleting

    at fast rate across the state due to over exploitation. The availability of water is also

    decreasing regularly due to abnormal growth of population. After independence,

    major concentration was extended to water sector and 90% of state's water is utilized

     by irrigated agriculture. But the major concerns in water sector are sustainability,

     productivity, water management, pricing etc.

    It will be our endeavor that the works are executed with strict quality standards

    confirming to technical specifications with deployment of good constructionmodalities. To achieve the objectives of an effective Quality Control Monitoring and

    Quality Assurance Management System, an independent quality control unit has

     been established and made operational. The important aspect is to develop quality

    concept and capacity of field engineers to be continuously vigilant on quality

    control. Accordingly a manual to promote procedure and guidelines of quality

    control systems on the works of Water Resources Department has been prepared,

    after detailed discussions and feedback experience from the prevailing practices.

    The manual shall provide in depth understanding of the need of quality control,

    including prescribing the tests required to be conducted for the materials during

    construction and placement activities along-with post construction scenario. The

    manual is designed to introduce various formats to be followed at various stages or

    construction to achieve proper quality control and to transmit necessary reports. It

    also provides an opportunity for the engineering personnel for deployment of their

    skills in quality control procedures to increase useful life of structures being

    constructed in confirmation with the international standards.

    Although every care has been taken to check mistakes and misprints, yet it is

    difficult to claim perfection. Any errors, omissions and suggestions for the

    improvement and corrections in the Quality Control Manual are most welcome from

    all the quarters, which may please be sent to the undersigned.

  • 8/15/2019 Quality Control Manual WRD

    4/211

    Quality Control Manual for Water Resources Department has been made under

    valuable guidance and support of the Committee officers Sh.P.L.Solanki, Chief

    Engineer Quality Control & Vigilance, Jaipur and Sh.G.R.Bhansali, Chief Engineer

    SWRPD, Jaipur .Their valuable support for the finalization of Quality Control

    Manual applicable to the construction works of Water Resources Department by

    Sh. Narendra Mertia SE & TA and his team is thankfully acknowledged.

    Date: 17th March, 2011 (Kundan Lal)Place: JAIPUR   Chief Engineer

    Water Resources Department

    Rajasthan, Jaipur

  • 8/15/2019 Quality Control Manual WRD

    5/211

    INDEX

    CHAPTER NO. PARTICULARS PAGE

    NO.

    LIST OF INDIAN STANDARDS (i)-(iii)

    CHAPTER-I QUALITY ASSURANCE AND CONTROL 1

    CHAPTER-II ORGANISATIONAL SET-UP 5

    CHAPTER-III GENERAL FUNCTIONS OF LABORATORIES 8

    CHAPTER-IV DUTIES OF STAFF INCHARGE OFLABORATORIES

    16

    CHAPTER-V DUTIES OF FIELD STAFF IN RELATION TOQUALITY OF WORKS

    20

    CHAPTER-VI CO-ORDINATIONS 24

    CHAPTER-VII QUALITY ASSURANCE 27

    CHAPTER-VIII O.K. CARDS 29

    CHAPTER-IX TESTS TO BE PERFORMED ON MATERIALS 39

    CHAPTER-X LIST OF EQUIPMENT FOR CEMENT ANDCONCRETE TESTING

    41

    CHAPTER-XI FORMATS OF TEST RESULTS 43

    CHAPTER-XII IMPORTANT SPECIFICATIONS 58

    CHAPTER-XIII FREQUENCY OF TESTING 96

    CHAPTER-XIV MONITORING THROUGH CONTROL CHARTS 102

    CHAPTER-XV COMPILATION OF QUALITY CONTROL DATA 107

    CHAPTER-XVI  PROCEDURE FOR EXECUTING EARTH WORK 108

    CHAPTER-XVII PROCEDURE FOR EXECUTING CONCRETELINING 

    112

    CHAPTER-XVIII PROCEDURE FOR EXECUTING RCC WORK &CONCRETE FOR STRUCTURES 

    117

    CHAPTER-XIX PROCEDURE FOR SHOT-CRETING AND

    GUNITING 

    122

    CHAPTER-XXDETERMINATION OF FIELD MOISTURE & DRYDENSITY OF COMPACTED EARTH FILL

    129

    CHAPTER-XXIDETERMINATION OF FIELD DENSITY BYSAND REPLACEMENT METHOD

    130

    CHAPTER-XXIICHECK LIST FOR QUALITY CONTROL UNIT

    132

    ANNEXURE-I SKETCH SHOWING THE ROLES ANDRESPONSIBILITY MATRIX

    139

    ANNEXURE-II ORGANISATIONAL CHART 142

    ANNEXURE-III SKETCH SHOWING CONSTRUCTION –  JOINTIN LINING 143

  • 8/15/2019 Quality Control Manual WRD

    6/211

    ANNEXURE-IV INSPECTION OF TESTING ACTIVITIES 144

    ANNEXURE-V-A SKETCH SHOWING AIR –  WATER GUN 145

    ANNEXURE-V-B AIR –  MORTAR GUN 146

    ANNEXURE-VI ILLUSTRATIVE SKETCH SHOWINGTREATMENT OF CANAL PRISM IN EXPANSIVESOILS WITH CNS MATERIALS

    147

    ANNEXURE-VII TYPICAL CROSSECTION OF A DISTRIBUTARYWITH C.N.S. SUB GRADE

    148

    ANNEXURE-VIII CURVE SHOWING RELATION BETWEENSPECIMEN SIZE AND STRENGTH OFCONCRETE CORE

    149

    ANNEXURE-IX DATA OF THE CORES TAKEN FROM IN SITUCONCRETE CANAL LINING

    150

    ANNEXURE-X ILLUSTRATION OF PREPARATION OFCONTROL CHARTS FOR CEMENT AND

    CONCRETE

    151

    ANNEXURE-XI GRAPH SHOWING CORRECTION FACTOR FORHEIGHT/ DIAMETER RATIO OF A CORE

    161

    ANNEXURE-XII STATEMENT SHOWING CAPACITY OF PAVERAND MECHANICAL TRIMMER

    162

    ANNEXURE-XIII GOVERNMENT OF RAJASTHAN ,IRRIGATIONDEPPARTMENT ORDER OF DATED 4-11-96

    163

    ANNEXURE-XIV GOVERNMENT OF RAJASTHAN ,WRD ORDER

    OF DATED 27-9-10

    165

    ANNEXURE-XV PHOTOGRAPHS OF KEY/CRITICALEQUIPMENTS

    168

  • 8/15/2019 Quality Control Manual WRD

    7/211

    LIST OF INDIAN STANDARDS

    S.

    No.Short Title

    IS. to various

    Standards

    (A) Cement

    1 Specification for 33 grade ordinary Portland cement IS:269 -1989

    2 Specification for Rapid-hardening Portland cement IS:8041 -1990

    3 Specification for Portland pozzolona cement IS:1489 (Part 1&2)

    1991

    4 Methods of physical test for hydraulic cement IS:4031 -1988

    5 Method of chemical analysis of hydraulic cement IS:4032 -1985

    6 Method of sampling for hydraulic cement IS:3535 -1986

    7 Standard sand for testing of cement IS:650 -1991

    8 Specification for 43 grade ordinary Portland cement IS:8112 -1989

    9 Specification for 53 grade ordinary Portland cement IS:12269-1987

    (B) Coarse / Fine Aggregate

    1 Specification for coarse & fine aggregates IS:383-1970

    2 Methods of test for aggregates for concrete

     particle size and shape.

    IS:2386 (Part I)-1963

    3 Methods of test for aggregates for concrete

    estimation of deleterious materials and organic

    impurities.

    IS:2386 (Part II)-1963

    4 Methods of test for aggregates for concrete specificgravity, density, voids, absorption & bulking.

    IS:2386 (Part III)- 1963

    5 Methods of test for aggregates for concrete

    Mechanical properties.

    IS:2386 (Part IV)-1963

    6 Methods of test for aggregate for concrete

    Soundness.

    IS:2386 (Part V)- 1963

    7 Methods of test for aggregate for concrete

    measuring mortar making properties of fine

    aggregates.

    IS:2386 (Part VI)-1963

    8 Methods of test for aggregates for concrete

    alkali aggregate reactivity.

    IS:2386 (Part VII)-

    1963

    9 Methods of test for aggregates for concrete

     petrographic examination.

    IS:2386 (Part VIII)-

    1963

    (C) Bricks

    1 Method for sampling of clay building bricks IS:5454 -1978

    2 Method of tests of burnt-clay building bricks IS:3495 (Parts 1 to 4)-

    1992

    3 Common burnt clay building bricks IS:1077 -1992

  • 8/15/2019 Quality Control Manual WRD

    8/211

    S.

    No.Short Title

    IS. to various

    Standards

    (D) Masonry Mortar

    1 Specification for sand for masonry mortars IS:2116 -19802 Code of practice for preparation and use of

    masonry mortar.

    IS:2250 -1981

    (E) Cement Concrete

    1. Specification for coarse and fine aggregate IS:383 - 1970

    2 Specification for compressive strength, flexural

    strength.

    IS:516 -1959

    3 Code of practice for plain & reinforced concrete IS:456 -2000

    4 Methods of sampling and analysis of concrete IS:1199 - 1959

    5 Recommended guide lines for concrete mix design IS:10262 - 1982

    (F) Curing Compound

    1 Standard test method for water retention & day

    light reflection test on concrete.

    ASTM-C-156809

    2 Standard method of test for effect of organic

    materials in fine aggregate on strength of mortar.

    ASTM-C-87-69

    3 Standard specification for liquid membranes

    forming compounds.

    ASTM- C-309-89

    (G) PVC Water Stops

    1 Code of practice for provision of water stops IS:12200 - 1987

    2 Procedure for Testing Parts of IS:8543

    3 Standard Test methods for Tensile properties of

    Plastics.

    ASTM : D 638-1991

    4 Standard Test methods for Thermoplastic

    Elastomers Tension.

    ASTM : D 412-1992

    (H) HYSD BARS

    1 Specifications for HYSD bars. IS:1786 - 1985

    2 Specification for Mild Steel and Medium Tensile

    steel bars for concrete reinforcement.

    IS:432 (Part I) -1982

    3 Method for Tensile testing of steel wires IS:1521 - 1972

    4 Hard drawn steel wire for concrete reinforcement IS:432 (Part II) -1982

    5 Method for Tensile testing of Steel IS:1608 - 1995

    6 Code of practice for bending & fixing of bars for

    concrete reinforcement.

    IS:2502 - 1963

    (I) Precast R.C.C. Pipes

    1 Specifications for precast concrete pipes IS:458 - 1988

    2 Methods of test for concrete pipes IS:3597 –  1985

  • 8/15/2019 Quality Control Manual WRD

    9/211

    S.

    No.Short Title

    IS. to various

    Standards

    1 Preparation of dry soil samples IS:2720 (Part I) -1983

    2 Determination of water content (moisture content) IS:2720 (Part II) -1973

    3 Determination of specific gravity of fine grained

    soils.

    IS:2720 (Part III) -1980

    Sect/1

    4 Determination of specific gravity of fine, medium

    & coarse grained soils.

    IS:2720 (Part III) -1980

    Sect/2

    5 Grain size analysis IS:2720 (Part IV) -1985

    6 Determination of liquid and plastic limit IS:2720 (Part V)- 1985

    7 Determination of shrinkage factors IS: 2720 (Part VI)- 1972

    8 Determination of water content -dry density

    relation using light compaction.

    IS:2720 (Part VII) -1980

    9 Determination of water content -dry densityrelation using heavy compaction.

    IS:2720 (Part VIII) -1983

    10 Determination of water content -dry density

    relation using constant weight of soil method.

    IS:2720 (Part IX) -1971

    11 Determination of unconfined compressive strength IS:2720 (Part X) -1973

    12 Determination of shear strength parameters

    (tri-axial) without measurement of pore water

     pressure (tri-axial compaction).

    IS:2720 (Part XI) -1971

    13 Determination of shear strength parameters with

    measurement of pore water pressure.

    IS:2720 (Part XII)- 1981

    14 Direct shear test IS:2720 (Part XIII) -1986

    15 Determination of density index (relative density)

    of cohesionless soils.

    IS:2720 (Part XIV)-

    1983

    16 Determination of consolidation properties IS:2720 (Part XV) -1986

    17 Determination of permeability IS:2720 (Part 17)- 1986

    18 Determination of dry density of soils, in- place by

    the sand replacement method.

    IS:2720 (Part 28)- 1974

    19 Determination of dry density of soils, in- place by

    core-cutter method.

    IS:2720 (Part 29)- 1975

    20 Laboratory vane shear test. 1S:2720 (Part 30) -198021 Determination of the density in place by the ring

    and water replacement method.

    IS:2720 (Part 33)- 1971

    22 Determination of free swell index of soils IS: 2720 (Part 40)- 1977

    23 Measurement of swelling pressure of soils IS: 2720 (Part 41)- 1977

    24 Classification and identification of soils for

    general engineering purposes.

    IS:1498-1970

  • 8/15/2019 Quality Control Manual WRD

    10/211

  • 8/15/2019 Quality Control Manual WRD

    11/211

      1

    CHAPTER  –  I

    QUALITY ASSURANCE AND CONTROL 

    1.  INTRODUCTION

    Evaluation of water resources projects involves enormous expenditure. They are

    time bound programme and require assistance from various technical bodies for

    investigation, design, planning and execution. To have a safe durable structure, it is

    necessary that the materials and standard of execution fully satisfy the

    specifications. It is to be recognized that the ultimate efficiency of the performance

    of a project will depend upon proper layout and designs, the ultimate health of the

     project during life scale of its operational phase will depend largely on the quality

    achieved during its construction.

    Each and every job whether big or howsoever small shall require to be executed to

    acceptable construction quality duly confirming to sound design principles,

    specifications and deployment of good methodology or modern technique and

     procedures. To achieve the requisite objectives, it is essential to introduce a result

    oriented quality management system.

    This system is planned to orient the whole range of quality effort on a continuous

     basis covering quality assurance and quality control, broadly out lined below

    including steps initiated for its meticulous implementation.

    1.1 Orientation and training of construction supervision/quality control

    staff

    A capable and functional construction supervision (CS) and quality control / quality

    assurance team is needed to ensure implementation of contract specifications. To

    achieve this objective intensive training will be given to all related staff of

    construction / quality control in suitable batches covering specifications for the

    works to be executed and also the procedure to conduct various tests in the field and

    laboratories. Recommendation of I.S. codes will be explained in the training so as to

    cover key construction and QC / QA aspects.

  • 8/15/2019 Quality Control Manual WRD

    12/211

      2

    1.2 Laboratory system for testing of Input and Outputs 

    Looking to the overall quantum of work and the scattered area in different

    zones, establishment of laboratories at different levels and places forms an

    important link of project organisation for quality control. The system is

    required to provide reliable and accurate testing support to fulfill the

    objectives. Accuracy and reliability in testing will depend upon the

    competence of testing personal, accuracy of apparatus, quality of reagents

    used, and maintenance of requisite environmental conditions. Introduction of

    "Mobile testing laboratory system" will prove to be highly result-oriented.

    This can be supplemented by adequate nos. of site labs, field laboratories and

    zonal laboratories.

    1.3  O.K. Card System 

    It provides a systematic approach towards assuring quality construction and

    has proved to be practical mechanism for enforcement of technical

    specifications. For the purpose, each work is divided in various activities in

     proper sequence/order of construction and listed in chronological order of

    occurrence in O.K. Card. The cards are maintained in 2 colors (Pink and

    Green) to be operated by construction and quality control units separately.

    During execution of work both cards are operated simultaneously and will be

    kept on record by Executive Engineer concerned.

    2.  OBJECTIVES AND SCOPE OF QUALITY CONTROL

    The objective of quality control management is to collect, process and thencommunicate the data related to the quality of inputs and outputs as well as

    finished item of work to those who are responsible for the quality. Any

     programme of quality control seeks to ensure adequacy and uniformity of

    quality through the following operations.

    1.  To ensure that the works are being executed in conformity with the

     prescribed specification.

  • 8/15/2019 Quality Control Manual WRD

    13/211

      3

    2.  Inspection of storage, handling and processing facilities for all materials

    in conformity with accepted or specified practice.

    3.  Monitoring the variation in specification of the materials and quantities

    used in the operation of production and in the final product by suitable

    observation, measurements or tests.

    4.  In order to achieve the common goal  –   Construction quality in the

    execution of project, the roles and responsibility matrix, as depicted in

    Annexure-I shall be broadly followed by :

    1.  GOR 2. Contractor 3. Project Construction Team

    4. Project QC/QA Team and 5. Project Design Team

    5.  Analysis of the observed variations by statistical or other techniques.

    6.  Feed-back of the results of analysis for exercise of control at each stage

    and to take corrective steps for maintaining the variations within

    specified limits.

    7.  Indicating expeditiously the possible remedial measures, wherever

    warranted to ensure execution of works as per drawings / specifications.

    8.  Rejecting, where warranted, the material or the product at any

    intermediate or final stage in case acceptance criteria is not satisfied. The

    rejected material should be removed from work site immediately.

    3.  QUALITY CONTROL MANUAL

    It is very important constituent of the quality management system. It is a

    document encompassing specific requirement, which if fulfilled, shall help in

    effectively implementing the quality control system to achieve the objective

    of good construction quality. It covers broadly, the objectives, functions and

    operations of the Q.C. organisation; duties and responsibilities of Q.C.

     personnel; Q.C. Laboratory System; O.K. Cards; Monitoring through Control

    Charts; Control on workmanship; Tests on materials; Important

    specifications; Standards to be adopted for materials and works; Frequency

    of testing and reporting; Compilation of Q.C. Data and Statistical Analysis

    etc.; Documentation and Feed-back; Inspection etc.

  • 8/15/2019 Quality Control Manual WRD

    14/211

      4

    4.  CONFIGURATION OF QUALITY MANAGEMENT SYSTEM

    QUALITY MANAGEMENT SYSTEM

    Quality planning,

    Q.C. Manual;

    Training of Q.C./Q.A.

    Staff, Infrastructure

    etc.

    Quality Control Quality Assurance

    5.1 QUALITY CONTROL: (Q.C.)

    The operational techniques and activities that are used to fulfill the

    requirements for quality.

    5.2 QUALITY ASSURANCE: (Q.A.)

    All the planned and systematic activities implemented within the quality

    system and demonstrated as needed to provide adequate confidence that an

    entity will fulfill requirements for quality; and making sure that the quality of

    a product is what it should be. Purpose of Quality Assurance is to prevent

     problems before they occur, to identify and correct them swiftly if they occurand to uncover the root cause.

    5.3 QUALITY MANAGEMENT 

    All activities of the overall management function that determine the quality

     policy, objectives and responsibilities, and implement them by means such as

    Quality Planning, Quality Control, Quality Assurance, and Quality

    Improvement within the quality system.

    The QUALITY CONTROL MANUAL being adopted for Water Resources

    Department (the salient requirements of which are being outline in the

    various chapters) aims at a “System Approach” to ensure that upon

    implementation , the quality levels as set and defined in the specifications

    and contract documents and relevant Indian Standards would be met in the

    execution of project works.

  • 8/15/2019 Quality Control Manual WRD

    15/211

      5

    CHAPTER  –  II

    ORGANISATIONAL SET-UP 

    GENERAL

    I.  Anyone connected with quality control work, should possess adequate

    knowledge and experience of quality control works and be well conversant

    with testing of construction materials. The object of quality control should be

    clearly understood by them in letter and spirit so as to help in construction

    and achieve high order of quality as laid down in specifications for works by

    controlling various factors responsible for deterioration in quality,investigating reasons therefore and suggesting ways and means for

    improvement.

    II.  To have proper and independent quality, quality control formation shall

    consist of an independent unit headed by Chief Engineer Quality Control.

    The C.E. shall have three S.E.'s in-charge of Quality Control Circle for the

    various construction activities of different zones and the S.E.'s shall have a

    team of E.E.'s to look after the work of different circles. Thus there will be

    separate streams of construction and quality control assurance respectively

    up to the level of C.E. (Organisational Chart attached at Annexure-II).

    III.  Every Q/C Circle shall be divided in number of division and each division

    shall be headed by the Executive Engineer for the purpose of effective

    quality control, every divisional jurisdiction shall be sub-divided in number

    of units and each unit is to be put under the charge of A.En. The E.E. quality

    control shall make all arrangements for the demarcating the areas of

    operation of every quality control staff and issue a duty chart for each

    member after approval from the C.E / S.E. Field Laboratory will be situated

    at important nodal points which shall cover all the adjoining works and in-

    charge will be T.A. to Executive Engineer. Site Laboratories as per

    requirement in field shall be maintained by concerned site in-charge

    (construction) and also utilized by Assistant Engineer Q/C for carrying out

    necessary tests whenever site is inspected by him.

  • 8/15/2019 Quality Control Manual WRD

    16/211

      6

    IV.  One of the fundamental principles to be understood and kept in mind is that

    the overall responsibility for achieving construction quality in each sub-

     project  –   rests with the execution unit and construction staff shall be fully

    responsible for quality of work. Requisite assistance is to be provided by the

    Q.C. Staff for ensuring construction quality.

    Functions of Quality Control Units

    The main function of Q.C. units is to have independent checking and control

    of works. Since the works in the zones are of scattered nature, the quality

    control units can not exercise concurrent quality control, but it has been

     planned that these units should act in such a manner that necessary quality

    control requirements are fulfilled jointly with the execution staff. It will be

    the responsibility of quality control staff to ensure that all-requisite test as

     per IS / relevant standards and specifications are carried out in site / field /

    zonal or central laboratories. The quality control units will carry out periodic

    inspections of works and conduct field tests so that any deficiencies in the

    execution of works are properly brought to the notice of concerned

    authorities and execution staff for taking corrective measures. The following

     broad indications of functions of quality control units are given which may

     be supplemented by issue of any further instructions by the Chief Engineer,

    Quality Control, Jaipur from time to time.

    (1)  They should monitor that all required tests are carried out before start of

    work as well as during execution. At least 10% tests are to be conducted by

    the quality control units for reliability of the results and counter checking.

    (2)  They should ensure that all arrangements for carrying out routine field tests

    in the field laboratories and site laboratories are duly made including

     provisions and up-keeping of equipments, personnel etc. and record of these

    field tests in prescribed formats are maintained. They should check this

    record and also sign in the relevant registers in token of their inspection.

    They should conduct field tests whenever they visit site of construction work

    and record results of such tests in the registers maintained for the purpose.

  • 8/15/2019 Quality Control Manual WRD

    17/211

      7

    (3)  They shall be empowered to order the suspension of work if deficiencies or

    defects are noticed during execution. Order for stoppage of work if given by

    the officer below the rank of S.E. should be got examined and confirmed by

    S.E. Q.C. very promptly, preferably within 24 hours. However, order for

    suspension of work can only be passed by the Chief Engineer Quality

    Control.

    (4)  Inspection Book should be maintained at site wherein remarks should be

    recorded by quality control staff whenever they visit site which should be

    noted for compliance by the construction unit. They should specifically

    record any deficiency noted to bring the same to the notice of appropriate

    authority through remarks in the inspection book or inspection note. The

    execution staff shall ensure the compliance of such deficiency and intimate

    to the concerned officer of Quality Control Unit.

    (5)  The Chief Engineer, Quality Control shall ensure at least one test check of all

    the works costing more than Rs.250.00 lacs in a year. This does not preclude

    him for conducting more than one test check of any work for important

    works; frequent checking is to be carried out.

    The test check shall be thorough to ensure the quality of work and shall

    include -

    a.  Observation of DBD and moisture contents of earthwork in filling

    reaches.

     b.  Fineness modulus of sand, grading of sand and coarse aggregate.

    c.  Checking of water cement ratio for concrete.

    d.  Checking of lining work / masonry work / concrete work.

    e.  Any other requisite tests as per case.

  • 8/15/2019 Quality Control Manual WRD

    18/211

     

  • 8/15/2019 Quality Control Manual WRD

    19/211

      8

    CHAPTER  –  III

    GENERAL FUNCTIONS OF LABORATORIES 

    The laboratory system, in addition to evaluate and monitor the inputs and outputs,

    would also evaluate and monitor the workmanship as well as construction plant,

    machinery and equipment. This would, thus, be accompanied by testing as well as

    inspection.

    FUNCTIONS OF CENTRAL LABORATORY AT JAIPUR  

    I.  To conduct laboratory tests on samples of sand, coarse aggregate, stone,

    cement and steel for use in masonry and concrete works.

    II.  To conduct laboratory tests for foundation soil, and for selection of soils

    from proposed borrow areas, for use in the various zones of embankment as

     per specifications, proctor density & optimum moisture content of soils

     before start of earth work.

    III.  For masonry and concrete, the strength of mortar and concrete has to be as

    specified in agreement. Laboratory has to design the proportions of different

    ingredients through tests for the specified strength. The proportioning shall

     be done by weight. It should be co-related with volume for volumetric

     batching of concrete where quantity of concrete to be placed is of small

    magnitude. Volume batching may be allowed by the Engineer-in-charge

    where weight batching is not practical and provided accurate bulk densities

    of materials to be actually used in concrete have been established. Allowance

    for bulking shall be made in accordance with IS: 2386 (Part III)-1963. The

    mass volume relationship shall be checked at periodical frequency to ensure

    that specified grading is maintained.

    IV.  For concrete and mortars where strength is not given and only proportions

    have been specified, the strength should be treated as standard for execution.

    V.  When controlled concrete is specified, it is essential that mix design is to be

    done.

    VI.  Since the strength of cement varies from batch to batch in a cement factory

    itself, it is essential that a relation between strength of cement versus strength

  • 8/15/2019 Quality Control Manual WRD

    20/211

      9

    of concrete may be worked out in the lab, well in advance of the starting of

    the work. This would facilitate in furnishing the proper proportion of the mix

    for adopting in the field and also it entails adding or reducing cement content

     based on the strength of the cement.

    VII.  Results of tests performed in central laboratory should be documented in

     prescribed Performa pertaining to following tests.

    A.  SOIL :

    Disturbed grain size analysis IS: 2720 (Part IV) -1985.

    Proctors compaction IS: 2720 (Part VII & VIII).

    Atterberg's limit IS: 2720 (Part V) -1985.

    Permeability IS: 2720 (XVII) - 1986 (at OMC. MDD)

    Shear test (remoulded at OMC. MDD drained / undrained) IS: 2720 (Part

    XIII) -1986.

    Specific gravity IS: 2720 (Part III) -1980. Undisturbed density and natural

    moisture content, permeability, consolidation, shear test (drained/undrained)

    at OMC or saturation.

    Free swell index; Swelling pressure of soil sample.

    Dispersibility of soils.

    Total Soluble salts.

    Chemical test for carbonates & sulphates (Chlorides Gypsum test).

    B.  SAND :

    For IS: 383-1970 Grading, IS: 2386 (Part I) Fineness Modulus, IS: 2386

    (Part III) Bulkage , IS: 2386 (Part II) Organic and silt content.

    Deleterious material and mica content, and presence of organic impurities, if

    any.

    C.  Cohesive  –  Non-Swelling Soils

    Requirement should broadly confirm to IS: 9451-1994

    D.  CEMENT

    Fineness, consistency, specific gravity, compressive strength, setting time,

    soundness by Le-Chatelier test.

    E.  COARSE AGGREGATE :

    Grading IS: 2386 (Part I) -1963

  • 8/15/2019 Quality Control Manual WRD

    21/211

      10

    Soundness, crushing value, impact test.

    Abrasion, Absorption, Specific gravity IS: 2386 (Part III):1963 Flakiness.

    F.  BOULDERS :

    Soundness, weight and size, absorption, specific gravity, weathering

    conditions (visual) abrasion after breaking to proper sizes.

    G.  FILTER MATERIALS :

    Grading, uniformity co-efficient, weathering conditions (visual) and tests for

    fine and coarse aggregate fulfillment of filter criteria as per I.S.Code.

    H.  WATER:

     pH value, silt content, soluble salts and any other impurities.

    H1. STEEL

    Ultimate tensile strength / Elongation.

    I.  CONCRETE :

    Air Content

    Mix Proportions; Test on admixture (if used); Test on Super-plasticiser (if

    used)

    J. 

    HARDENED CONCRETE AND MORTARS :

    Proportion by chemical analysis and compressive strength.

    K.  BRICKS :

    Dimensions and physical properties including water absorption and

    compressive strength.

    L.  TESTS FOR FOUNDATION INVESTIGATION AND INSITU

    PERMEABILITY BEARING CAPACITY :

    Other properties, if tested shall be reported in the remarks column or foot

    note.

    M.  LDPE Film wherever used shall be tests. 

    N.  IMPROVED DEVICES FOR QUALITY CONTROL :

    It is planned to introduce improved devices for achieving speedy and

    efficient quality control. Monitoring the characteristics of fresh concrete is

    important from the point of view of quality control. The 28 days strength of

    concrete is the criteria for acceptance and is the basis of quality evaluation.

  • 8/15/2019 Quality Control Manual WRD

    22/211

      11

    However, one has to wait for 28 days to get the results of compressive

    strength of concrete cubes / cylinders. Even the accelerated compressive

    strength tests take considerable time.

    The portable electronic devices, commercially available now, have made it

     possible for rapid on-site measurements of slump, temperature, water-cement

    ratio (the most important factor influencing the strength of concrete) and the

    likely 28 days strength of fresh concrete mixes. Software supplied with the

    electronic unit also produces 'quality control certificates' based on the

    measurements taken by this unit. This evidence of the properties of concrete

    gives the site Q.C. /Q.A. Engineer, the confidence to accept or, if necessary,

    to reject the concrete mix before it is placed.

    Central laboratory at Jaipur is planned to be equipped with such a portable

    electronic unit with software.

    On embankment construction and compacted earth fill placement it is

     planned to procure an engineering device of the type "Nuclear Guage" to

    enable much more rapid and economic compaction and quality control than

    the conventional methods, without any loss in accuracy. Such a device is

    capable of quickly computing and displaying wet density, moisture content,

    dry density, and percentage of compaction in terms of Proctor density.

    The central laboratory at Jaipur is planned to be equipped with two Nuclear

    Guage Device. Inspection of testing activities is illustrated in Annexure -IV.

    FUNCTIONS OF ZONAL LABORATORY 

    To carry out tests of soils, filter materials, ingredients of concrete, tests of cement

    and mortar etc. of the samples collected by the quality control staff and also such

    samples collected by construction staff whose facility of testing is not available at

    site as well as field laboratories. Results of tests performed will be reported to

    Executive Engineer construction and Superintending Engineer and Chief Engineer

    of Quality Control unit in the prescribed Performa pertaining to the following tests:

  • 8/15/2019 Quality Control Manual WRD

    23/211

      12

    SOILS: 

    1.  Density, moisture content and compaction efficiency.

    2.  Sieve analysis

    3.  Proctor density & O.M.C.

    4.  Atterberg's limits

    5.  Specific gravity

    SAND: 

    1.  Gradation analysis & silt content.

    2.  Presence of deleterious materials including organic impurities.

    3.  Bulkage

    COARSE AGGREGATE: 

    1.  Grading

    2.  Specific gravity

    3.  Impact Value, Soundness, Crushing Value, Flakiness.

    FRESH CONCRETE & MORTAR:

    1.  Water cement ratio, slump test

    2.  Compressive strength of Concrete & Mortar

    3.  Mix Proportions

    BOULDER SAMPLE:

    1.  Absorption

    2.  Dimensions

    3.  Visual observation as regards weathering etc.

    4.  Specific gravity, impact value, soundness, specific gravity.

    CEMENT:

    1. 

    Setting time by Vicat needle test2.  Strength of cement

    BRICKS:

    1. Dimensions and physical properties including compressive strength.

    WATER: 

    1. Chemical

    2. Cl, SO4, Organics & Inorganic Solids

    3. pH value, Alkalinity, Acidity

  • 8/15/2019 Quality Control Manual WRD

    24/211

      13

    FUNCTIONS OF FIELD LABORATORIES 

    To carry out daily routine tests of soils, filter materials, ingredients of concrete and

    mortar of the samples collected by the construction staff and report the results to

    concerned J.En., A.En. & Executive Engineer of construction. The results will also

     be reported to the quality control unit in the prescribed Performa pertaining to

    following tests:

    SOILS & EARTH WORK:

    1.  Density, moistures content and compaction efficiency.

    2.  Sieve analysis.

    3.  Proctor density & OMC.

    CNS:

    1.  Gradation analysis

    2.  Shear Parameters

    3.  Index properties

    SAND:

    1.  Gradation and Fineness Modulus.

    2. 

    Bulkage3.  Organic impurities through quick "Colour test".

    CEMENT:

    Casting of cubes for strength; Fineness by Sieve.

    COARSE AGGREGATE:

    1.  Grading

    2.  Physical Properties

    FRESH CONCRETE & MORTAR:

    1.  Water cement ratio & slump test

    2.  Physical properties of ingredients & silt content of sand.

    3.  Casting of concrete & mortar cubes.

    BOULDER SAMPLE:

    1.  Water absorption

    2.  Dimensions

    3.  Physical properties including weathering etc.

  • 8/15/2019 Quality Control Manual WRD

    25/211

      14

    BRICKS: 

    Dimensions & physical properties including water absorption.

    SITE LABORATORIES: 

    To carry out daily routine tests of soils, filter material, ingredients of concrete and

    mortar for the on-going works and material carted at site before use. Results will be

    recorded in registers kept at site for inspection purposes and will be reported to J.En.

    & A.En. Construction and Quality Control, in the prescribed Performa pertaining to

    the following:

    SOILS & EARTH WORK: 

    1.  D.B.D. & Moisture content layer wise.

    SAND:

    1.  Gradation analysis & Fineness Modulus.

    2.  Bulkage

    COARSE AGGREGATE:

    1.  Gradation analysis

    2.  Physical properties

    CEMENT:

    Casting of cubes for strength

    FRESH CONCRETE & MORTAR: 

    1.  Slump test

    2.  Physical properties of Ingredients; Proportion of cement and sand in mortar.

    3.  Casting of concrete / mortar cubes.

    BOULDER SAMPLE:1.  Dimensions & physical properties including weathering etc.

    2.  Water absorption

    BRICKS:

    1.  Dimension & physical properties

    2.  Sampling of bricks for testing.

  • 8/15/2019 Quality Control Manual WRD

    26/211

      15

    Record of daily activities / tests will be maintained at site in the registers such as:-

    1.  Inspection Register

    2.  D.B.D. Register

    3.  Cement Consumption Register

    4.  Slump Test Register

    5.  Daily progress register  –  progress to be compared with consumption of various

    ingredients including cement.

    FUNCTIONS OF MOBILE LABORATORY (FIELD TESTS)

    (i)  To carry daily routine tests on compaction efficiency. Field density and moisture

    content determination test.

    (ii)  To carry out daily routine tests like silt content, fineness modulus and gradation of

    fine aggregates and coarse aggregates.

    (iii)  To carry out slump test, unit weight and temperature of concrete by using fresh

    concrete in-situ testing equipment, and to take fresh concrete as per the required

    frequency.

  • 8/15/2019 Quality Control Manual WRD

    27/211

      16

    CHAPTER  –  IV

    DUTIES OF STAFF INCHARGE OF LABORATORIES

    DUTIES OF ASSISTANT ENGINEER / A.R.O. INCHARGE OF

    LABORATORY 

    i)  To ensure proper up-keep and maintenance of laboratory equipment in

    laboratory.

    ii)  To ensure proper up-keep of records of all samples being tested in the

    laboratory as per prescribed norms and communication of the results to the

    concerned.

    iii)  To supervise the testing works of Junior Engineer, Laboratory Assistants and

     personally to check the tests to the extent of 25%.

    iv)  To prepare fortnightly review of all the tests results and submit to the

    Executive Engineer, Quality Control & Construction.

    v)  To conduct any research work as may be assigned by the Executive

    Engineer.

    vi)  The Central Laboratory & Zonal Laboratories have to conduct tests for the

    suitability of materials proposed from various quarries, well in advance of

    the actual execution of work, for which the construction staff shall send the

    material to the lab well in advance.

    vii)  Steel rods as proposed to be used shall be tested for ultimate tensile strength

    elongation and bond etc. as per standards.

    viii)  Samples of welded rods, welded at site shall be collected and tested to the

    quality of welding.

    DUTIES OF ASSISTANT ENGINEERS / A.R.O. / S.R.A. (LABORATORY)

    Shall perform important tests as mentioned below:

    A)  CEMENT :

    1.  Fineness by Blaine

    2.   Normal Consistency

    3.  Setting time

  • 8/15/2019 Quality Control Manual WRD

    28/211

      17

    4.  Soundness

    5.  Specific gravity

    6.  Compressive strength

    7.  Adulteration test

    B)  SAND :

    1.  Sieve Analysis & Fineness Modulus

    2.  Test for organic impurities silt & clay

    3.  Decantation test for silt

    4.  Specific gravity

    5.  Unit weight and bulkage factor

    C) 

    COARSE AGGREGATE :

    1.  Sieve Analysis and gradation

    2.  Specific gravity

    3.  Water absorption

    4.  Examination of deleterious materials

    5.  Crushing strength

    6.  Impact

    7.  Abrasion

    8.  Flakiness index

    9.  Alkali –  Silicate reactivity

    D)  CONCRETE :

    1.  Consistency –  slump or compaction factor

    2.  Compressive strength

    3.  Air content

    4. 

    Yield per unit quantity of cement5.  Mix design test

    6.  Cement content

    E)  MORTAR :

    1.  Consistency

    2.  Compressive Strength

    3.  Yield per unit quantity of cement

    4.  Cement Content

  • 8/15/2019 Quality Control Manual WRD

    29/211

      18

    F)  SOILS :

    1.  Gradation (Grain size analysis)

    2.  Consistency limits

    3.  Porosity & Voids ratio

    4.  Specific gravity

    5.  Swell pressure

    DUTIES OF LABORATORY TECHNICIANS / JUNIOR RESEARCH

    ASSISTANTS 

    i)  To assist Assistant Engineer / Executive Engineers whenever required in

    laboratory and field work.ii)  To perform tests in laboratory such as :

    a)  Compaction tests

     b)  Limit tests

    c)  Analysis of fine & coarse aggregates

    d)  Silt in fine aggregate

    e)  Slump test

    f)  Collection of samples of concrete and mortars for filling moulds for

    compaction test.

    DUTIES OF LABORATORY ATTENDANTS

    a)  To keep instruments clean.

     b)  To assist Assistant Engineer / Executive Engineer and Laboratory

    Technicians in conducting tests.

    c)  To prepare samples for test.

    d)  To arrange samples systematically.

    CONTROL OF INSPECTION, TESTING AND MEASURING EQUIPMENT

    The identification, calibration, and adjustment of all inspection, measuring and test

    equipment and devices will be done at prescribed intervals as stated below against

    certified equipment having a known valid relationship to nationally recognised

    standards. The equipment will be capable of controlling the delivery of material for

    weighing so that in accuracies in feeding and measuring during normal operation

  • 8/15/2019 Quality Control Manual WRD

    30/211

      19

    will not exceed 1% for water and 3% for all aggregates. Periodical test will be made

    at least once in a month in case of equipment for measuring water, cement,

    admixtures, sand and coarse aggregate. Other measuring equipments will be tested

    once in a year unless some defects are noticed earlier, in which case these will be

    attended immediately.

    Documents will be established and calibration procedures will be maintained

    including details of the following:

    1. Equipment type 2. Identification number

    3. Location 4. Frequency of Checks

    5. Check method 6. Acceptance criteria

    7. Action to be taken for unsatisfactory results, to ensure that the inspection,

    measuring, and test equipment are capable of the required accuracy and

     precision.

  • 8/15/2019 Quality Control Manual WRD

    31/211

      20

    CHAPTER  –  V

    DUTIES OF FIELD STAFF IN RELATION TO QUALITY OF

    WORKS DUTIES OF ASSISTANT ENGINEER  

    ASSISTANT ENGINEER

    CONSTRUCTION

    ASSISTANT ENGINEER QUALITY

    CONTROL

    1.  Shall see that the markout of the area

    to be tackled is properly given,

    shuttering, centering, reinforcement

    are done as per drawing and

    technical specifications, to record the

    Pre levels / foundation levels, and tosee that mark-out for canal

    excavation is perfectly given as per

    drawings. Pre levels, classification

    levels and final levels of canal shall

     be taken as per specification.

    1. Shall check the markout of

    foundation and centering/ shuttering

    reinforcement arrangement and

    inform the Assistant Engineer

    construction to rectify the defects if

    any.

    2.  Shall see that the construction

    equipment like mixers, vibrators,

    compaction equipment, pumping

    arrangements for curing / watering

    are arranged before starting of any

    work.

    2. Shall check the adequacy of the

    construction equipment and curing/

    watering arrangements before start of

    work and during excavation.

    3.  Shall see that sufficient quantities of

    input materials as per agreement

    specifications are made available at

    site of work and to arrange testing

    equipment, men and material

    required for conducting field tests,

    sending samples of input materials

    for testing to central lab, field

    laboratories as per norms.

    3. Shall conduct / get conducted by

    different laboratories the field tests

    on input materials and record the

    results and to inform the Assistant

    Engineer construction to rectify the

    defects if any.

    4.  Shall write O.K. Cards after area is

    ready to start the work and to inform

    the Assistant Engineer Quality

    Control and Executive Engineer

    construction and take permission to

    start the work on O.K. Card. Shall

    also permit OK in case quality control

    A.En. is not available.

    4. Shall check and write the O.K.

    card and record the deviations,

    defects if any or otherwise to record

    the final OK and to inform

    Executive Engineer quality control

    and to permit to start the work.

    5.  Shall supervise and ensure that

    correct quantities of input materials as

     per mix design communicated by the

    5. Shall make regular checks of the

    feeding of input materials mixing

    time and suggest the quantity of

  • 8/15/2019 Quality Control Manual WRD

    32/211

      21

    ASSISTANT ENGINEER

    CONSTRUCTION

    ASSISTANT ENGINEER QUALITY

    CONTROL

    central laboratory are fed into the

    mixers/batching plants etc., and shall

    ensure specified mixing time.

    (minimum 2½ minutes)

    water depending on the moisture

    content of sand as and when

    required.

    6.  Shall ensure proper vibration, rolling

    etc., during course of day to day

    work. Shall conduct D.B.D. test of

    earth work, gradation of material,

    slump test, core drill test and to

    extract field samples of material and

    finished products to be sent to

    different laboratories also provide

    men and material required forextracting samples of finished product

    for quality control staff.

    6. Shall ensure slump test, core tests,

     proctor density etc., conducted as

     per norms by the construction and

    quality control staff and to extract

    field samples of finished product to

     be sent to central laboratory later.

    7.  Shall ensure proper curing of samples

    extracted till the curing time is over

    and to make arrangements to send the

    samples to central lab or other

    suitable lab.

    7. Shall assist the Assistant Engineer in

    Proper handling / transport of

    samples to central lab.

    8. Shall ensure timely green cutting of

    concrete with proper air  –  water gun;

    nicking & chipping (wherever so

    warranted) so as to prepare the

    surface for next concrete lift for

    effective bond at the lift / construction

     joints.

    8. Shall check and see that the

     preparation of the surface is

    adequately done for starting the next

    lift.

    9. Shall ensure proper curing / watering

    and allow removal of shuttering only

    after the time limit prescribed in the

    specifications and to see that the

    surface are finished to the

     plumb/straight lines etc., afterremoval shuttering.

    9. Shall check the adequacy of

    curing/watering and see that the final

    surfaces are finished neatly

     plumb/straight lines etc.

    10. Shall maintain (1) mark-out register

    (2) OK Card files (3) Load Register.

    10. Shall maintain registers of field tests

    conducted.

  • 8/15/2019 Quality Control Manual WRD

    33/211

      22

    DUTIES OF EXECUTIVE ENGINEER

    EXECUTIVE ENGINEER

    CONSTRUCTION

    EXECUTIVE ENGINEER QUALITY

    CONTROL

    1. Shall supervise, check, advice, andinstruct the J.E.N. /A.E.N.

    Construction regarding discharge

    of their functions properly.

    1. Shall supervise, check, advice andinstruct the A.E.N. Quality Control

    regarding discharge of their

    functions properly.

    2. Shall intimate the Executive

    Engineer quality control regarding

    signing of agreement for starting of

    any new work, duly endorsing a

    copy of work order. Shall supply

    copies of contract documents,

    drawings construction programmeetc., to Executive Engineer Quality

    Control, and Superintending

    Engineer.

    2. Shall maintain copies of approved

    Designs, reports, contract

    document, drawings, construction

     programme, extracts of inspection

    notes etc., and shall see that his

    subordinates go through the above

    documents.

    3. Shall get all ingredients of

    concrete, masonry got tested

     before use. Shall see that the soils

    are tested for various properties

    like OMC, MDD, etc., before

    starting of Embankment work.

    3. Shall remind and verify whether

    test results are available or not

     before starting up of any new work

    and during execution of work.

    4. Shall see that all the Machinery/Equipment being used by the

    contractor is got periodically

    calibrated.

    4. Shall assist in upkeep andcalibration of equipment.

    5. Shall see that OK Cards are written

    and kept at site of work before

    starting of any work. Also will

    ensure rectification of work before

    releasing payments.

    5. Shall inspect and sign on OK Cards

    during field visits. Defects of

    construction will be pointed out and

    remedies suggested for achieving

    good quality construction.

    6. Shall order the suspension of work

    if any defects are noticed orreported by quality control staff

    and resume the work only after

    rectification of defects in the

     presence of quality control staff.

    6. Shall order the stopping of work if

    major defects are noticed orreported by quality control staff and

    intimate his counterpart to see that

    defects are rectified. Also defects

    noted during construction are to be

    reported to the S.E./Quality Control

    & Construction.

    7. Foundations and reinforcement,

    shuttering, centering where heavy

    reinforcement is involved is to be

    checked by Executive Engineer

    7. Foundations and reinforcement,

    shuttering, centering where heavy

    reinforcement is involved is to be

    tallied by Executive Engineer

  • 8/15/2019 Quality Control Manual WRD

    34/211

      23

    EXECUTIVE ENGINEER

    CONSTRUCTION

    EXECUTIVE ENGINEER QUALITY

    CONTROL

    invariably before starting the work. invariably before starting the work,

    during his field visits.

    8. Shall personally see that the

    samples to the laboratories are sent

    regularly, obtain the results and

    communicate the same to

    Executive Engineer quality

    control.

    8. Shall pursue and keep track of

    sending of samples various

    laboratories and to keep record of

    results received.

    9. Shall take the help of quality

    control Executive Engineer

    whenever a dispute is referred.

    9. Shall co-ordinate with the EE/

    Construction division render

    assistance in resolving the issues

    referred to him.10. Shall jointly inspect the site with

    quality control Executive Engineer

    in case variation in classification is

    less than 10% (+/-) and finalize the

    classification.

    10. Shall jointly inspect the site with

    Construction Executive Engineer in

    case variation in classification is

    less than 10% (+/-) and finalize the

    classification.

  • 8/15/2019 Quality Control Manual WRD

    35/211

      24

    CHAPTER  –  VI

    CO-ORDINATIONS

    The construction staff and quality control staff must act in tandem to achieve good

    quality of the finished product and construction as per the contract specifications.

    Construction staff should make it a point to inform the quality control staff, the date

    of starting of any activities or component of the work well in advance so as to enable

    the quality control staff to schedule their work plan and attend the particular work on

    the particular date.

    In turn quality control staff should schedule their programme, so as to attend to the

    work on the dates required by the construction staff and ensure that, the progress of

    work is not hampered.

    The quality control staff shall be responsible for exercising the various field checks

    with reference to drawing and specifications laid down in respective I.S. code during

    construction and carrying out all the laboratory and field tests on materials used for

    construction and reporting through their higher officer, to the field staff for ensuring

    quality.

    The Assistant Engineer / Executive Engineer (Quality Control) can address Assistant

    Engineer / Executive Engineer construction regarding defects, rectification testing

    etc.

    As far as possible the defects are to be rectified in the presence of the Quality

    Control staff and the payment shall be effected only after the Quality Control Staff

    are fully satisfied with the rectification and quality of work. Any rectification done

    subsequently any intimation and presence of Quality Control Staff shall be at the

    sole responsibility of the construction staff.

    The defects, if any, noticed by the quality control staff during their course of

    inspection shall be brought to the notice of the construction staff then and there. It is

    the primary responsibility of the Quality Control & Inspections staff to draw the

    attention of the construction staff, whenever they notice defective work during their

    course of inspection. It is duty of the construction staff to attend to the rectification

    and maintain proper specifications as pointed out by their counter part of the Quality

    Control organisation.

  • 8/15/2019 Quality Control Manual WRD

    36/211

      25

    Quality Control staff will monitor that all tests required as per agreement and I.S.

    Codes are carried out in different laboratories by the field staff they will also test

    check to the extent of minimum 10% (or as decided by Chief Engineer QC) of the

    required tests and co-relate with the other tests conducted in different laboratories.

    All observations regarding substandard or below specification work will be dully

    recorded in the inspection / visit books kept at site by inspecting officer. Such

    substandard or below specification works should be got stopped / dismantled

    immediately by execution unit. The defects pointed out by Quality Control Unit will

     be communicated to the execution unit for compliance immediately. The compliance

    report should be sent by execution unit within ten days.

    The quality control staff cannot supervise the placement of concrete on a mix to mix

     basis continuously. They can only conduct random check of input materials, mixing

    time, placement of concrete, vibration etc. It's the primary responsibility of the

    construction staff to ensure adequate supervision of mix to mix placement of

    concrete.

    The Operations of the Quality Control Staff shall not interfere in any way, with the

    executive powers vested with the officers in-charge of execution. They will also inno way diminish the responsibility of the officers in-charge of execution. The field

    officers in-charge of works are primarily responsible for the quality of all works and

    to carry out the work as per the technical specifications.

    In case of difference of opinion between quality control staff and construction staff,

    it should be sorted out by way of discussions in cordial atmosphere and mutual trust

    as per the guide lines indicated below. In case it involves any design feature /

     problem / aspect, the design office should be duly consulted and the advice given by

    the designer should be accepted.

    In case of difference of opinion between Executive Engineer, Construction and

    Executive Engineer, Quality Control it would be referred to Superintending

    Engineer, Construction, who would discuss the matter with Superintending

    Engineer, Quality Control and settle the issue. Similarly, when the Superintending

    Engineer, Quality Control is not readily available, the Superintending Engineer,

    Construction can over-rule after recording the reasons in writing. In such cases the

  • 8/15/2019 Quality Control Manual WRD

    37/211

      26

    Superintending Engineer, Construction has to discuss with Superintending Engineer,

    Quality Control at the earliest opportunity and modify his earlier orders, if

    necessary. Similar action will be taken in case of difference of opinion on the

    comments of Superintending Engineer, Quality Control.

    In case there is a difference of opinion between both the Chief Engineer /Additional

    Chief Engineer, Construction and Quality Control the matter would be referred to

    Chief Engineer Water Resources Jaipur, whose decision shall be final and binding

    on all. Work should immediately be suspended and not allowed to resume until the

    defects pointed out by Quality Control and Inspection staff are rectified.

    The construction and quality control staff shall keep a regular liaison with theGeologist in respect of all Geo-technical problems and enlist his input on

    foundations of structures & dams; Cut Off Trenches, tunneling; contract/

    consolidation/curtain grouting; Rock / Excavation Slopes (stability of slopes);

     protection measures; permeability / Water loss tests etc., as well as any geological

     problem. The advice rendered by the Geologist should be discussed with the

    Designers and duly respected and implemented.

  • 8/15/2019 Quality Control Manual WRD

    38/211

  • 8/15/2019 Quality Control Manual WRD

    39/211

      27

    CHAPTER  –  VII

    QUALITY ASSURANCE 

    All planned and systematic strategies and actions necessary to generate adequate

    confidence that Input and Output product will satisfy given requirements of quality

    and all the components of works perform satisfactory during life period of service,

    adequate quality checks as analysed during construction is a record which speaks of

    "Quality Assurance". It comprises planning and policies, education and training

    standards and specifications, contracts and agreements, and quality control. Quality

    assurance is to assume that the materials as per standard and as per the requirements

    have gone into the production of concrete, earth, masonry work etc. This is achieved

     by evaluating the quality checks during construction and post construction tests

    made and compared.

    LIST OF DOCUMENTS

    Each QC laboratory should hold the following documents:

      Quality control manual.

      Technical Records: Specification, Contract documents, inspection and Test

    Procedures, relevant standards / code of practice.

      Mill Certificates.

      Material test reports, test reports of cores.

      Inspection Reports.

      Photographic / Video film records of construction which may not remain

    accessible after commissioning of the project.

       Non-conformance reports.

      Statistical evaluation reports.  Technical Literature.

      Standardization of records.

    Quality Control Personnel should hold the following Documents:

      Data of test.

      Area where material is used.

      Test method with reference to standards.

     Testing results, including those of cores of concrete.

  • 8/15/2019 Quality Control Manual WRD

    40/211

      28

      Acceptance criteria.

      Remarks

      Test personnel signature.

    Junior Engineer and Assistant Engineer (Site In-charge at site) should always have a

    kit consisting of equipments i.e. measuring tapes, scale, Vernier  – calipers, Plumb

    rule & bob, spirit level, square, Gunia (small), hammer, measuring glass etc. to

    facilitate quality checking at site.

  • 8/15/2019 Quality Control Manual WRD

    41/211

      29

    CHAPTER  –  VIII

    O.K. CARDS 

    Since O.K. Cards contain important entries/information on execution of works at all

    stages and are liable to be referred/perused at a later stage also, the O.K. Cards shall

     be maintained in duplicate in two colours. The green coloured card shall form a part

    of the record of Q.C. /Q.A. Wing and the pink coloured card remains in the custody

    of Construction wing. The O.K. Cards, relating to any particular work, shall be put

    in a round shaped tin box and placed right at the construction site. The exterior of

    the tin box shall be painted red. Senior officers shall also check the O.K. Cards

    during their field inspections to ensure that those are being maintained and

     proper/genuinely filled.

    An O.K. Card is a condensed form of specifications and essential requirements for

    achieving specified workmanship and quality level of output. Each work is sub-

    divided into various construction activities in proper sequence / order of

    construction. Such activities are listed in chronological order on the O.K. Cards.

    For various stages of construction activities where laboratory tests or checks with

    reference to drawing and specification are required from quality control unit, O.K.

    Cards System shall be followed. The O.K. Cards should be made available on the

    site in regular manner. Approval of the component of work in progress at the times

    of inspection should be recorded by the inspecting officer.

    The O.K. Card consists of two parts for each work. Part first covers the initial

     preparedness for the work and indicates pre-requisites where as the second part

    covers the daily performance of activities based on pre-requisites and also giving

     permission to perform the job by the construction as well as Quality Control staff.

    Besides the location and type of work, the first column of O.K. Card is to be filled

     by the construction agency (contractor) by preparing each feature and making it

    ready for inspection by the project construction engineer who Okay through his

    signatures and then puts up to the Q.C. /Q.A. Engineer is not available at site then

    O.K. given by construction Engineer will be treated as final. If anything otherwise is

  • 8/15/2019 Quality Control Manual WRD

    42/211

      30

    not observed. Should anything otherwise be found, the O.K. Card shall not be signed

     by him and ask the Construction Engineer / agency for necessary rectification.

    Subsequently, O.K. Card should refer to the defects removed, if pointed out

     previously in O.K. Card and counter reference to the previous check and should be

    signed of Okayed.

    It must be borne in mind that work cannot be held up unduly for disposal of O'K

    Card. The Assistant Engineer (Quality Control) / Construction will be okaying

    authority for concentrated work like dam, spillway, head regulator etc. and Assistant

    Engineer / Junior Engineer construction will be okaying authority for scattered

    works like canals and small structures. Random checks by supervising officersshould be recorded on O'K Cards at site. Weekly report of O'K Cards maintained by

    construction unit should be submitted to S.E. / Q.C. of the area who has to monitor

    and ensure that adequate check is being maintained by field staff. Confirmation

    regarding rectification of defects be obtained from A.En. /Q.C. before making

     payment once in three bills and final bill of the contractor.

    After processing through various levels and entering observations and rectification

    O'K Card will be closed at the time of taking measurements for releasing paymentsto the contractor. Photocopy of the O'K Cards (pink) will be kept at site and original

    copy will be attached with the bill and will be kept on record by the division office

    while making payments to the contractor. Photo copy of O'K Card of Quality

    Control will also be enclosed with the bill & kept on record with the bill by the

    division office. However O.K. Card of Quality Control will not be closed till the

    work is finalized and will be kept on record by the Executive Engineer, Quality

    Control after the rectification is completed by the construction wing and final

    comments are recorded by both the Assistant Engineer.

    Specimen of O.K. Cards for various works such as embankment, concrete, masonry

    etc. have been enclosed below.

  • 8/15/2019 Quality Control Manual WRD

    43/211

      31

    O.K. Card No. 1

    Water Resources Department

    O.K. Card for raising / Strengthening of Earthen Embankments / Fill Placement &

    Compaction (Part-I)

     Name of Work ______________________________________________________

    Agency ____________________ Contract / Package No. ___________________

    Location ___________________ Date ___________________

    Description of Activities Remarks& DatedSignature

    ofAgency

    Remarks and DatedSignature of

    Construction staff

    Remarks &Dated

    Signature ofQC/

    InspectionEngineer

    Super-visor

    JEN AEN

    Layout / Demarcation / Fixing & checkingT.B.M.

    Removal of Vegetation, debris & Siteclearance

    Benching, stripping of base (20 cm)

    PRE-REQUISITES

    (1)  Proctor's density of borrow area

    (2)  Designation of borrow area & checking ofrequired moisture

    (3)  Excavation and shaping of rain cuts and

    its refilling

    (4)  Weather key- trench made and/or plowingof old embankments done if required

    (5)  Watering of base

    OK FOR FILL PLACEMENT

    Thickness of loose layer (cm)

    Removal of oversize (more than 7.5 cm size)layer

    Moisture content (%) –  initial

    Moisture content (%) final (OMC = %)

    Weather soil laid as per profile

    OK FOR COMMENCING COMPACTION

    Checking of Type of Compaction Equipment /Roller

    Checking of In place density (D.B.D.)

    Compaction Efficiency (%)

    Specified Compaction (%) of Proctor

    Re-Rolling / Re-compaction if required

    D.B.D. after Re-Rolling

    OK FOR NEXT LAYER

    Removal of extra/loose earth from – U/S & D/Sfaces

  • 8/15/2019 Quality Control Manual WRD

    44/211

     

       3   2

     

       O .   K .   C  a  r   d   N  o .   2

       W  a   t  e  r   R  e  s  o  u  r  c  e

      s   D  e  p  a  r   t  m  e  n   t

       S  u  p  p   l  e  m  e  n   t  a  r  y   O .   K .   C  a  r   d   f  o  r  s  u   b  s  e  q  u  e  n   t   l  a  y  e  r  s   (   P  a  r   t   I   I   )

       N  a  m  e  o   f   W  o  r   k_______________________________________________________________________________________

       A  g  e  n  c  y_____________________________________

     

       C  o  n   t  r  a  c   t   /   P  a  c   k  a  g  e   N  o .______________

    _______

       L  o  c  a   t   i  o  n____________________________________

     

       D  a   t  e______________________________________

     

       D  a   t  e

       D  e  s  c  r   i  p   t   i  o

      n  o   f   A  c   t   i  v   i   t   i  e  s

       (   C   h  a   i  n  a  g  e   l  a  y  e  r   )

       W  e  a   t   h  e  r   P  r  e  -

       R  e  q  u   i  s   i   t  e  s

       f  u   l   f   i   l   l  e   d

       W  e  a   t   h  e

      r

      s  a   t   i  s   f  a  c   t  o

      r  y

      c  o  n  s  o   l   i   d  a   t   i  o  n

      a  c   h   i  e  v  e   d

       W  e  a   t   h  e  r

      p  e  r  m   i   t   t  e   d   f  o  r

      n  e  x   t   l  a  y  e  r

       D  a   t  e   d

       S   i  g  n  a   t  u  r  e  o   f

       A  g  e  n  c  y   /

       C  o  n   t  r  a  c   t  o  r

       R  e  m  a  r   k  s  a  n   d   D  a   t  e   d

       S   i  g  n  a   t  u  r  e  o   f   C

      o  n  s   t  r  u  c   t   i  o  n

      s   t  a   f   f

       R  e  m  a  r   k  s   &

       D  a   t  e   d

       S   i  g  n  a   t  u  r  e  o   f

       Q   C   /

       I  n  s  p  e  c   t   i  o  n

       E  n  g   i  n  e  e  r

       S  u  p  e  r  -

      v   i  s  o  r

       J   E   N

       A   E   N

     

  • 8/15/2019 Quality Control Manual WRD

    45/211

      33

    O.K. Card No. 3

    Water Resources Department

    O.K. Card for Sub grade preparation for placement of lining (Part I)

     Name of Work ______________________________________________________

    Agency ____________________ Contract / Package No. ___________________

    Location ___________________ Date ___________________

    Description of Activities

    Dated

    Signatur es of

    Agency

    Remarks and DatedSignature of

    Construction staff

    Remarks &Dated

    Signature ofQC/

    InspectionEngineer

    Super-visor

    JEN AEN

    ChainageRemoval of Vegetation, debris

    Completion of dewatering

    Filling of over excavation, depressions/

    Pockets in soil/rocky strata as per

    specification

    Watering of sub-grade

    Compaction of sub-grade (bottom & sides)through slope compaction/Pneumatic rammer /

     power roller to specific density (..... %)Final Lip cutting & checking sub-grade surfaceto ensure within permissible tolerances (up to6.5 mm on sides, up to 12.5 mm on Bed)

    Laying of under-drainage arrangement(a) Porous Plugs (b) Longitudinal &Transverse Drains (c) Porous Panels

    Final wetting of sub-grade to 15 cm depth

    Checking of quantity and quality of materialstacked at site

    Cement, Aggregate, Sand, Water

    Checking of mixer, vibratos & power

    Checking of form work/ Shuttering true to lineand grade

    O.K. for lining placement

  • 8/15/2019 Quality Control Manual WRD

    46/211

     

       3   4

     

       O .   K .   C  a  r   d   N  o .   4

       W  a   t  e  r   R  e  s  o  u  r  c  e

      s   D  e  p  a  r   t  m  e  n   t

       O .   K .   C  a  r   d   f  o  r  p   l  a  c  e  m  e  n   t  o   f  c  a  s   t  -   i  n  -   S   i   t  u   C  o  n  c  r  e   t  e   l   i  n   i  n  g   (   P  a  r   t   I   I   )

       N  a  m  e  o   f   W  o  r   k_______________________________________________________________________________________

       A  g  e  n  c  y_____________________________________

     

       C  o  n   t  r  a  c   t   /   P  a  c   k  a  g  e   N  o .______________

    _______

       L  o  c  a   t   i  o  n____________________________________

     

       D  a   t  e______________________________________

     

       D  a   t  e

       D  e  s  c  r   i  p   t   i  o  n  o   f

       A  c   t   i  v   i   t   i  e  s

       &   l  o  c  a   t   i  o  n

       W  e  a   t   h  e  r   P  r  e  -

       R  e  q  u   i  s   i   t  e  s  o   f

       S  u   b  -  g  r  a   d  e

      p  r  e  p  a  r  a   t   i  o  n

       d  o  n  e

       S  a   t   i  s   f  a  c   t  o  r  y

       Q  u  a   l   i   t  y   &

       Q  u  a  n   t   i   t  y  o   f

      m  a   t  e  r   i  a   l

      s   t  a  c   k  e   d  a   t  s   i   t  e

       S   i  g  n  a   t  u  r  e  o   f

       C  o  n   t  r  a  c   t  o  r   /

       E  n  g   i  n  e  e  r

       W   h  e   t   h  e  r  s   l  u  m  p

      c   h  e  c   k  e   d   &

      c  u   b  e  s  c  a  s   t  e   d

       W   h  e   t   h  e  r

      s  p  e  c   i   f   i  e   d

      c  o  n   t  r  a  c   t   i  o  n

       j  o   i  n   t  s  p  r  o  v   i   d  e   d

       R  e  m  a  r   k  s

      a  n   d   D  a   t  e   d

       S   i  g  n  a   t  u  r  e  o   f

       C  o  n  s   t  r  u  c   t   i  o  n   S   t  a   f   f

       R  e  m  a  r   k  s   &

       D  a   t  e   d   S   i  g  n .

      o   f   Q   C   /

       I  n  s  p  e  c   t   i  o  n

       E  n  g   i  n  e  e  r

       S  u  p  e  r  -

      v   i  s  o  r

       J

       E   N

       A   E   N

     

  • 8/15/2019 Quality Control Manual WRD

    47/211

      35

    O.K. Card No. 5

    Water Resources Department

    O.K. Card for Random Rubble Stone Masonry

     Name of Work ______________________________________________________

    Agency ____________________ Contract / Package No. ___________________

    Location ___________________ Date ___________________

    Description of ActivitiesDated

    Signaturesof Agency

    Remarks and DatedSignature of Construction

    Staff

    Remarks &Dated

    Signature ofQC/

    InspectionEngineer

    Super-visor

    JEN AEN

    Stone –  Quality SizeSuitability of

    a)  Cement

     b)  Sand

    c)  Water

    Mortar

    a)  Mix measurement

     b)  Mixing, Consistency

    Pointing, thickness of joints,staggering of joints, laying of stones,hearting stones, bond stones spacing.

    Whether samples of mortar collectedin cubes for testing

    Green cutting with proper air watergun / sand blasting

    Adequacy of curing for masonrywork

    Verticality of structure check by

    using plumb bob

    Embedded Materials

    Final OK for masonry work

  • 8/15/2019 Quality Control Manual WRD

    48/211

      36

    O.K. Card No. 6

    Water Resources Department

    O.K. Card for Plain & Reinforced Cement Concrete

     Name of Work ______________________________________________________

    Agency ____________________ Contract / Package No. ___________________

    Location ___________________ Date ___________________

    Description of ActivitiesDated

    Signaturesof Agency

    Remarks and DatedSignature of

    Construction Staff

    Remarks &Dated Signature

    of QC/InspectionEngineer

    Super-visor

    JEN AEN

    Material Suitability

    i.  Cement

    ii.  Steeliii.  Aggregate 40 mm, 20 mmiv.  Sandv.  Watervi.  Admixture

    O.K. for materials

    Form work & Centering

    i)  Tightness, Stability, Smoothness

    ii)  Cleaning, oiling, perfectness ofform work.

    iii)  R.L. of Centering

    iv)  Checking of reinforcement.O.K. for reinforcement

    Tools & Plants

    i)  Mixers & Vibratorii)  Adequacy of concrete production

    / transportation, placement,consolidation.

    O.K. for Placement

    1.  Design mix, measurement2.  Mixing / Consistency3.  Slump

    4.  Compaction of Concrete5.  Joints6.  Finishing7.  Casting of Cubes8.  Curing9.  Compressive strength 28 days

    Final O.K.

     Note: Before pouring of concrete the reinforcement should be got checked by the Q.C. Unit.Working standby vibrator & mixer should be kept at site before start of concreting.

  • 8/15/2019 Quality Control Manual WRD

    49/211

      37

    O.K. Card No. 7

    Water Resources Department

    O.K. Card for PCC Slab Canal Lining

     Name of Work ______________________________________________________

    Agency ____________________ Contract / Package No. ___________________

    Location ___________________ Date ___________________

    Description of Activities

    Remarks& Dated

    Signaturesof Agency

    Remarks and DatedSignature of

    Construction Staff

    Remarks &Dated Signature

    of QC/InspectionEngineer

    Super-visor

    JEN AEN

    A. Materials Suitability :

    i.  Cement

    ii.  Aggregate 40 mm, 20 mmiii.  Sandiv.  Waterv.  Treatment of soil if any

    O.K. for materials

    B. Formation of Canal Banks :

    i)  Stripping/Removal of vegetation

    ii)  Cutting canal bed & sides to thegeometric section/shape

    iii)  Consolidation

    iv)  Trimming

    C. Casting of PCC Slabs :i)  Mix, Measurement by weight

    ii)  Mixing, consistencyiii)  Slumpiv)  Water Cement Ratiov)  Casting of PCC Slabsvi)  Casting of cubes of concrete mix

    vii)  Providing sub base if necessityviii) Laying/Placing in position PCC

    slabsix)  Construction jointsx)  Contraction joints

    xi)  Pointing with CMxii)  Curingxiii) Pressure Relief Holexiv) Flexural Strength of PCC Slabs

    Final O.K.

  • 8/15/2019 Quality Control Manual WRD

    50/211

      38

    O.K. Card No. 8

    Water Resources Department

    O.K. Card for Grouting

     Name of Work ______________________________________________________

    Agency ____________________ Contract / Package No. ___________________

    Location ___________________ Date ___________________

    S.No. Description Dated Signature of Contractor/QC Remarks

    GENERAL

    1.  R.L. and area surface to be grouted.

    2.  Classification of the rock strata.

    3.  Salient feature of the strata such

    as a fault zone cavities, fissures etc.

    4.  Permeability value of the strata before grout.

    GROUP

    5.  Pattern of Grout adopted

    6.  Depth and dia. of the hole

    7.  Pressure adopted for grout

    8.  Proportion of grouting mix

    9.  Intake of slurry mortar per unit area per unit time

    10. Total quality of intake

    11. Final permeability value of the strata after grout

    12. Whether the grout strata is OK.

  • 8/15/2019 Quality Control Manual WRD

    51/211

      39

    CHAPTER  –  IX

    TESTS TO BE PERFORMED ON MATERIALS 

    MATERIAL TEST METHOD

    Cement a)  Chemical IS:4032-1985i)  Sio2, A12O3, Fe2O3, Cao ,MgO, SO2,

    Insoluble residue & Loss on ignitionii)  Alkalies & Chloridesiii)  Free Lime

     b)  Physical IS:4031-1988i)  Specific gravityii)  Finenessiii)  Soundnessiv)  Compressive strengthv)  Drying shrinkage

    Water Chemicalsi)  Cl, SO4, Organic & Inorganic Solids, pH,

    Alkalinity / AcidityIS:3025-1987

    ii)  Setting time of mortariii)  Relative strength of concrete IS:1199-1959

    Fine Aggregate i)  Sieve Analysis & Fineness Modulus IS:383, IS:2386ii)  Test for organic impurities silt & clay (Part I & IV)

    iii)  Decantation test for silt IS:2386 (Part II)iv)  Specific gravity IS:2386 (Part III)v)  Unit weight and bulkage IS:2386 (Part III)

    IS:2386 (Part III)CoarseAggregates

    i)  Sieve Analysis IS:2386-1963

    ii)  Flakiness indexiii)  Elongation Index PART - Iiv)  Deleterious materialsv)  Specific gravity PART-IIvi)  Bulk Densityvii)  Moisture content PART-III

    viii) Absorption value

    Mechanical tests PART-IVix)  Aggregate crushing valuex)  Impact Value PART - Vxi)  Abrasion Valuexii)  Potential reactivity of aggregatexiii) Petro-graphic examinationxiv)  Alkali Aggregate reactivity test

    PART-VIPART-VII

  • 8/15/2019 Quality Control Manual WRD

    52/211

      40

    Embankment i)  Proctors compaction IS:2720 Part(vii & viii) -1980

    ii)  Atterberg‟s Limits IS:2720 Part (v)-1985iii)  Permeability IS:2720 Part (xvii)-

    1966iv)  Shear Test IS:2720 Part (xiii)-1986v)  Specific gravityvi)  Disturbed grain size analysis

    IS:2720 Part (iii)-1980IS:2720 Part (iv)-1985

    Concrete a)  Fresh Concretei)  Air Contentsii)  Vibrationiii)  Temperature measurementiv)  Mix proportionsv)  Water cement ratiovi)  Yield

     b)  Workability testi)  Slump Test Usual procedureii)  Compaction Factor test IS:CED2(CESS) ASTM

    C 597-83c)  Hardened Concrete BS: 4408i)  Compressive strengthii)  MDT Tests

    IS : 516-1959IS : CED 2 (3890)

    d)  Special Testi)  Microscopyii)   Non-destructive

    iii) Core Testing

    Admixtures i)  Bleeding IS:9103-1999ii)  Relative Strength IS:516-1959iii)  Setting Timeiv)  Relative water contentv)  Relative length change

    IS:8142-1974IS:9103-1999IS:1199-1959

    Masonry i)  Gradation of Sandii)  Slump Testiii)  Compressive strength of stones IS:1121(Part I)-1974iv)  Tests for stone - IS:1124 -1974

    -  Water absorption-  Specific gravity-  Porosity-  Weathering of natural building stone IS:1125 -1974

  • 8/15/2019 Quality Control Manual WRD

    53/211

      41

    CHAPTER  –  X

    LIST OF EQUIPMENT FOR CEMENT AND CONCRETE TESTING

    TEST EQUIPMENT

    A. CEMENT Flame Photometer

    a. Chemical

    i) Alkalies

    ii) Minor, major oxides byCalorimetry

    iii) Chloride Hot plate, Balance (Acc. 0.0002 g) Muffle

    Furnace (up to 1200 c). Platinum Crucibles‟,

    conductivity Bridge, pH Meter, physical balance

    (Cap. 150 g)

    iv) General

     b. Physical

    i) Fineness Blaine Apparatus, stop watch.

    ii) Soundness Le- Chatelier Le-Chatelier Moulds, hot water bath Autoclave

    iii) Consistency and settingtime

    iv) Heat of Hydration

    v) General

    B. AGGREGATES &

    CONCRETE 

    Vicat Apparatus, moulds, setting time needles and

     plunger compression testing machine (50 tonnes).

    vibrating machine, moulds 50 sq.cm. Area,calorimeter thermometer, flow table, stop watch,

    timer temperature controlled oven, humidity

    chamber incubator, physical balance (ACC 0.001

    g), balance (cap. 5 kg ACC 1 g), set of standard

    sieves lid and receiver.

    a) General

    i) Crushing value

    ii) Impact value

    iii) Abrasion value

    vi) Alkali Aggregate

    Reactivity

    vii)  Flakiness &

    Elongation indices

    viii)  Unit weight

    Containers

    ix)  Sampling (Sand)

    viii) Specific Gravity andAbsorption

    Electric Driver, hot plates, set of standard sieveslid and receiver, balance 10 kg (ACC 1g), 100 kg

    (ACC 0.001 kg), 200 kg (ACC 0.5 kg) scop,

    Enamel trays, balance, shovels, compression

    testing machine (200 tonnes), crusher and ball

    mill prevailing rigs 2,25,50,100 tones.

    Crushing apparatus

    Aggregate impact test machine

    Apparatus for measuring flakiness

    Minimum Capacity of Measures.

  • 8/15/2019 Quality Control Manual WRD

    54/211

      42

    TEST EQUIPMENT

    C. CONCRETE

    a.  Fresh Concrete

    Max. C.A. Size of Capacity of

    Measure dm3

    i. Vibration 2.50 6

    ii. Temperature

    measurement

    37.50 11

    iii. Mix proportions 50.00 14

    75.00 28

     b. Workability Tests:

    i. Slump Test 114.00 71

    ii. Compaction factor test 152.00 99

    c. Hardened concrete Refer sample Divideri) Compression, tension

     bending & Brinnel

    hardness tests.

    Pycnometer

    Internal Vibrator, table vibrator

    constituents, Slump cone Apparatus

    Compaction Factor apparatus, Universal Testing

    Machines with accessories (Cap. 100 tonnes),

    Concrete workability meter, Capping moulds

    Laboratory concrete mixer, Reluctance meter.

    d. Special Tests Optical microscope, grinding and polishing

    i) Microscopy equipment, ultrasonic pulse velocity, reboundii) Non-Destructive hammer core drilling machine, RCC cutting

    iii) Core Testing machine, RCC cutting machine, t