GOVERNMENT OF RAJASTHAN
WATER RESOURCES DEPARTMENT
QUALITY CONTROL MANUAL
March – 2011
Chief Engineer
Water Resources Department
Rajasthan, Jaipur
-
8/15/2019 Quality Control Manual WRD
2/211
-
8/15/2019 Quality Control Manual WRD
3/211
PREFACE
Status of water in Rajasthan is critical and complex. Ground water table is depleting
at fast rate across the state due to over exploitation. The availability of water is also
decreasing regularly due to abnormal growth of population. After independence,
major concentration was extended to water sector and 90% of state's water is utilized
by irrigated agriculture. But the major concerns in water sector are sustainability,
productivity, water management, pricing etc.
It will be our endeavor that the works are executed with strict quality standards
confirming to technical specifications with deployment of good constructionmodalities. To achieve the objectives of an effective Quality Control Monitoring and
Quality Assurance Management System, an independent quality control unit has
been established and made operational. The important aspect is to develop quality
concept and capacity of field engineers to be continuously vigilant on quality
control. Accordingly a manual to promote procedure and guidelines of quality
control systems on the works of Water Resources Department has been prepared,
after detailed discussions and feedback experience from the prevailing practices.
The manual shall provide in depth understanding of the need of quality control,
including prescribing the tests required to be conducted for the materials during
construction and placement activities along-with post construction scenario. The
manual is designed to introduce various formats to be followed at various stages or
construction to achieve proper quality control and to transmit necessary reports. It
also provides an opportunity for the engineering personnel for deployment of their
skills in quality control procedures to increase useful life of structures being
constructed in confirmation with the international standards.
Although every care has been taken to check mistakes and misprints, yet it is
difficult to claim perfection. Any errors, omissions and suggestions for the
improvement and corrections in the Quality Control Manual are most welcome from
all the quarters, which may please be sent to the undersigned.
-
8/15/2019 Quality Control Manual WRD
4/211
Quality Control Manual for Water Resources Department has been made under
valuable guidance and support of the Committee officers Sh.P.L.Solanki, Chief
Engineer Quality Control & Vigilance, Jaipur and Sh.G.R.Bhansali, Chief Engineer
SWRPD, Jaipur .Their valuable support for the finalization of Quality Control
Manual applicable to the construction works of Water Resources Department by
Sh. Narendra Mertia SE & TA and his team is thankfully acknowledged.
Date: 17th March, 2011 (Kundan Lal)Place: JAIPUR Chief Engineer
Water Resources Department
Rajasthan, Jaipur
-
8/15/2019 Quality Control Manual WRD
5/211
INDEX
CHAPTER NO. PARTICULARS PAGE
NO.
LIST OF INDIAN STANDARDS (i)-(iii)
CHAPTER-I QUALITY ASSURANCE AND CONTROL 1
CHAPTER-II ORGANISATIONAL SET-UP 5
CHAPTER-III GENERAL FUNCTIONS OF LABORATORIES 8
CHAPTER-IV DUTIES OF STAFF INCHARGE OFLABORATORIES
16
CHAPTER-V DUTIES OF FIELD STAFF IN RELATION TOQUALITY OF WORKS
20
CHAPTER-VI CO-ORDINATIONS 24
CHAPTER-VII QUALITY ASSURANCE 27
CHAPTER-VIII O.K. CARDS 29
CHAPTER-IX TESTS TO BE PERFORMED ON MATERIALS 39
CHAPTER-X LIST OF EQUIPMENT FOR CEMENT ANDCONCRETE TESTING
41
CHAPTER-XI FORMATS OF TEST RESULTS 43
CHAPTER-XII IMPORTANT SPECIFICATIONS 58
CHAPTER-XIII FREQUENCY OF TESTING 96
CHAPTER-XIV MONITORING THROUGH CONTROL CHARTS 102
CHAPTER-XV COMPILATION OF QUALITY CONTROL DATA 107
CHAPTER-XVI PROCEDURE FOR EXECUTING EARTH WORK 108
CHAPTER-XVII PROCEDURE FOR EXECUTING CONCRETELINING
112
CHAPTER-XVIII PROCEDURE FOR EXECUTING RCC WORK &CONCRETE FOR STRUCTURES
117
CHAPTER-XIX PROCEDURE FOR SHOT-CRETING AND
GUNITING
122
CHAPTER-XXDETERMINATION OF FIELD MOISTURE & DRYDENSITY OF COMPACTED EARTH FILL
129
CHAPTER-XXIDETERMINATION OF FIELD DENSITY BYSAND REPLACEMENT METHOD
130
CHAPTER-XXIICHECK LIST FOR QUALITY CONTROL UNIT
132
ANNEXURE-I SKETCH SHOWING THE ROLES ANDRESPONSIBILITY MATRIX
139
ANNEXURE-II ORGANISATIONAL CHART 142
ANNEXURE-III SKETCH SHOWING CONSTRUCTION – JOINTIN LINING 143
-
8/15/2019 Quality Control Manual WRD
6/211
ANNEXURE-IV INSPECTION OF TESTING ACTIVITIES 144
ANNEXURE-V-A SKETCH SHOWING AIR – WATER GUN 145
ANNEXURE-V-B AIR – MORTAR GUN 146
ANNEXURE-VI ILLUSTRATIVE SKETCH SHOWINGTREATMENT OF CANAL PRISM IN EXPANSIVESOILS WITH CNS MATERIALS
147
ANNEXURE-VII TYPICAL CROSSECTION OF A DISTRIBUTARYWITH C.N.S. SUB GRADE
148
ANNEXURE-VIII CURVE SHOWING RELATION BETWEENSPECIMEN SIZE AND STRENGTH OFCONCRETE CORE
149
ANNEXURE-IX DATA OF THE CORES TAKEN FROM IN SITUCONCRETE CANAL LINING
150
ANNEXURE-X ILLUSTRATION OF PREPARATION OFCONTROL CHARTS FOR CEMENT AND
CONCRETE
151
ANNEXURE-XI GRAPH SHOWING CORRECTION FACTOR FORHEIGHT/ DIAMETER RATIO OF A CORE
161
ANNEXURE-XII STATEMENT SHOWING CAPACITY OF PAVERAND MECHANICAL TRIMMER
162
ANNEXURE-XIII GOVERNMENT OF RAJASTHAN ,IRRIGATIONDEPPARTMENT ORDER OF DATED 4-11-96
163
ANNEXURE-XIV GOVERNMENT OF RAJASTHAN ,WRD ORDER
OF DATED 27-9-10
165
ANNEXURE-XV PHOTOGRAPHS OF KEY/CRITICALEQUIPMENTS
168
-
8/15/2019 Quality Control Manual WRD
7/211
LIST OF INDIAN STANDARDS
S.
No.Short Title
IS. to various
Standards
(A) Cement
1 Specification for 33 grade ordinary Portland cement IS:269 -1989
2 Specification for Rapid-hardening Portland cement IS:8041 -1990
3 Specification for Portland pozzolona cement IS:1489 (Part 1&2)
1991
4 Methods of physical test for hydraulic cement IS:4031 -1988
5 Method of chemical analysis of hydraulic cement IS:4032 -1985
6 Method of sampling for hydraulic cement IS:3535 -1986
7 Standard sand for testing of cement IS:650 -1991
8 Specification for 43 grade ordinary Portland cement IS:8112 -1989
9 Specification for 53 grade ordinary Portland cement IS:12269-1987
(B) Coarse / Fine Aggregate
1 Specification for coarse & fine aggregates IS:383-1970
2 Methods of test for aggregates for concrete
particle size and shape.
IS:2386 (Part I)-1963
3 Methods of test for aggregates for concrete
estimation of deleterious materials and organic
impurities.
IS:2386 (Part II)-1963
4 Methods of test for aggregates for concrete specificgravity, density, voids, absorption & bulking.
IS:2386 (Part III)- 1963
5 Methods of test for aggregates for concrete
Mechanical properties.
IS:2386 (Part IV)-1963
6 Methods of test for aggregate for concrete
Soundness.
IS:2386 (Part V)- 1963
7 Methods of test for aggregate for concrete
measuring mortar making properties of fine
aggregates.
IS:2386 (Part VI)-1963
8 Methods of test for aggregates for concrete
alkali aggregate reactivity.
IS:2386 (Part VII)-
1963
9 Methods of test for aggregates for concrete
petrographic examination.
IS:2386 (Part VIII)-
1963
(C) Bricks
1 Method for sampling of clay building bricks IS:5454 -1978
2 Method of tests of burnt-clay building bricks IS:3495 (Parts 1 to 4)-
1992
3 Common burnt clay building bricks IS:1077 -1992
-
8/15/2019 Quality Control Manual WRD
8/211
S.
No.Short Title
IS. to various
Standards
(D) Masonry Mortar
1 Specification for sand for masonry mortars IS:2116 -19802 Code of practice for preparation and use of
masonry mortar.
IS:2250 -1981
(E) Cement Concrete
1. Specification for coarse and fine aggregate IS:383 - 1970
2 Specification for compressive strength, flexural
strength.
IS:516 -1959
3 Code of practice for plain & reinforced concrete IS:456 -2000
4 Methods of sampling and analysis of concrete IS:1199 - 1959
5 Recommended guide lines for concrete mix design IS:10262 - 1982
(F) Curing Compound
1 Standard test method for water retention & day
light reflection test on concrete.
ASTM-C-156809
2 Standard method of test for effect of organic
materials in fine aggregate on strength of mortar.
ASTM-C-87-69
3 Standard specification for liquid membranes
forming compounds.
ASTM- C-309-89
(G) PVC Water Stops
1 Code of practice for provision of water stops IS:12200 - 1987
2 Procedure for Testing Parts of IS:8543
3 Standard Test methods for Tensile properties of
Plastics.
ASTM : D 638-1991
4 Standard Test methods for Thermoplastic
Elastomers Tension.
ASTM : D 412-1992
(H) HYSD BARS
1 Specifications for HYSD bars. IS:1786 - 1985
2 Specification for Mild Steel and Medium Tensile
steel bars for concrete reinforcement.
IS:432 (Part I) -1982
3 Method for Tensile testing of steel wires IS:1521 - 1972
4 Hard drawn steel wire for concrete reinforcement IS:432 (Part II) -1982
5 Method for Tensile testing of Steel IS:1608 - 1995
6 Code of practice for bending & fixing of bars for
concrete reinforcement.
IS:2502 - 1963
(I) Precast R.C.C. Pipes
1 Specifications for precast concrete pipes IS:458 - 1988
2 Methods of test for concrete pipes IS:3597 – 1985
-
8/15/2019 Quality Control Manual WRD
9/211
S.
No.Short Title
IS. to various
Standards
1 Preparation of dry soil samples IS:2720 (Part I) -1983
2 Determination of water content (moisture content) IS:2720 (Part II) -1973
3 Determination of specific gravity of fine grained
soils.
IS:2720 (Part III) -1980
Sect/1
4 Determination of specific gravity of fine, medium
& coarse grained soils.
IS:2720 (Part III) -1980
Sect/2
5 Grain size analysis IS:2720 (Part IV) -1985
6 Determination of liquid and plastic limit IS:2720 (Part V)- 1985
7 Determination of shrinkage factors IS: 2720 (Part VI)- 1972
8 Determination of water content -dry density
relation using light compaction.
IS:2720 (Part VII) -1980
9 Determination of water content -dry densityrelation using heavy compaction.
IS:2720 (Part VIII) -1983
10 Determination of water content -dry density
relation using constant weight of soil method.
IS:2720 (Part IX) -1971
11 Determination of unconfined compressive strength IS:2720 (Part X) -1973
12 Determination of shear strength parameters
(tri-axial) without measurement of pore water
pressure (tri-axial compaction).
IS:2720 (Part XI) -1971
13 Determination of shear strength parameters with
measurement of pore water pressure.
IS:2720 (Part XII)- 1981
14 Direct shear test IS:2720 (Part XIII) -1986
15 Determination of density index (relative density)
of cohesionless soils.
IS:2720 (Part XIV)-
1983
16 Determination of consolidation properties IS:2720 (Part XV) -1986
17 Determination of permeability IS:2720 (Part 17)- 1986
18 Determination of dry density of soils, in- place by
the sand replacement method.
IS:2720 (Part 28)- 1974
19 Determination of dry density of soils, in- place by
core-cutter method.
IS:2720 (Part 29)- 1975
20 Laboratory vane shear test. 1S:2720 (Part 30) -198021 Determination of the density in place by the ring
and water replacement method.
IS:2720 (Part 33)- 1971
22 Determination of free swell index of soils IS: 2720 (Part 40)- 1977
23 Measurement of swelling pressure of soils IS: 2720 (Part 41)- 1977
24 Classification and identification of soils for
general engineering purposes.
IS:1498-1970
-
8/15/2019 Quality Control Manual WRD
10/211
-
8/15/2019 Quality Control Manual WRD
11/211
1
CHAPTER – I
QUALITY ASSURANCE AND CONTROL
1. INTRODUCTION
Evaluation of water resources projects involves enormous expenditure. They are
time bound programme and require assistance from various technical bodies for
investigation, design, planning and execution. To have a safe durable structure, it is
necessary that the materials and standard of execution fully satisfy the
specifications. It is to be recognized that the ultimate efficiency of the performance
of a project will depend upon proper layout and designs, the ultimate health of the
project during life scale of its operational phase will depend largely on the quality
achieved during its construction.
Each and every job whether big or howsoever small shall require to be executed to
acceptable construction quality duly confirming to sound design principles,
specifications and deployment of good methodology or modern technique and
procedures. To achieve the requisite objectives, it is essential to introduce a result
oriented quality management system.
This system is planned to orient the whole range of quality effort on a continuous
basis covering quality assurance and quality control, broadly out lined below
including steps initiated for its meticulous implementation.
1.1 Orientation and training of construction supervision/quality control
staff
A capable and functional construction supervision (CS) and quality control / quality
assurance team is needed to ensure implementation of contract specifications. To
achieve this objective intensive training will be given to all related staff of
construction / quality control in suitable batches covering specifications for the
works to be executed and also the procedure to conduct various tests in the field and
laboratories. Recommendation of I.S. codes will be explained in the training so as to
cover key construction and QC / QA aspects.
-
8/15/2019 Quality Control Manual WRD
12/211
2
1.2 Laboratory system for testing of Input and Outputs
Looking to the overall quantum of work and the scattered area in different
zones, establishment of laboratories at different levels and places forms an
important link of project organisation for quality control. The system is
required to provide reliable and accurate testing support to fulfill the
objectives. Accuracy and reliability in testing will depend upon the
competence of testing personal, accuracy of apparatus, quality of reagents
used, and maintenance of requisite environmental conditions. Introduction of
"Mobile testing laboratory system" will prove to be highly result-oriented.
This can be supplemented by adequate nos. of site labs, field laboratories and
zonal laboratories.
1.3 O.K. Card System
It provides a systematic approach towards assuring quality construction and
has proved to be practical mechanism for enforcement of technical
specifications. For the purpose, each work is divided in various activities in
proper sequence/order of construction and listed in chronological order of
occurrence in O.K. Card. The cards are maintained in 2 colors (Pink and
Green) to be operated by construction and quality control units separately.
During execution of work both cards are operated simultaneously and will be
kept on record by Executive Engineer concerned.
2. OBJECTIVES AND SCOPE OF QUALITY CONTROL
The objective of quality control management is to collect, process and thencommunicate the data related to the quality of inputs and outputs as well as
finished item of work to those who are responsible for the quality. Any
programme of quality control seeks to ensure adequacy and uniformity of
quality through the following operations.
1. To ensure that the works are being executed in conformity with the
prescribed specification.
-
8/15/2019 Quality Control Manual WRD
13/211
3
2. Inspection of storage, handling and processing facilities for all materials
in conformity with accepted or specified practice.
3. Monitoring the variation in specification of the materials and quantities
used in the operation of production and in the final product by suitable
observation, measurements or tests.
4. In order to achieve the common goal – Construction quality in the
execution of project, the roles and responsibility matrix, as depicted in
Annexure-I shall be broadly followed by :
1. GOR 2. Contractor 3. Project Construction Team
4. Project QC/QA Team and 5. Project Design Team
5. Analysis of the observed variations by statistical or other techniques.
6. Feed-back of the results of analysis for exercise of control at each stage
and to take corrective steps for maintaining the variations within
specified limits.
7. Indicating expeditiously the possible remedial measures, wherever
warranted to ensure execution of works as per drawings / specifications.
8. Rejecting, where warranted, the material or the product at any
intermediate or final stage in case acceptance criteria is not satisfied. The
rejected material should be removed from work site immediately.
3. QUALITY CONTROL MANUAL
It is very important constituent of the quality management system. It is a
document encompassing specific requirement, which if fulfilled, shall help in
effectively implementing the quality control system to achieve the objective
of good construction quality. It covers broadly, the objectives, functions and
operations of the Q.C. organisation; duties and responsibilities of Q.C.
personnel; Q.C. Laboratory System; O.K. Cards; Monitoring through Control
Charts; Control on workmanship; Tests on materials; Important
specifications; Standards to be adopted for materials and works; Frequency
of testing and reporting; Compilation of Q.C. Data and Statistical Analysis
etc.; Documentation and Feed-back; Inspection etc.
-
8/15/2019 Quality Control Manual WRD
14/211
4
4. CONFIGURATION OF QUALITY MANAGEMENT SYSTEM
QUALITY MANAGEMENT SYSTEM
Quality planning,
Q.C. Manual;
Training of Q.C./Q.A.
Staff, Infrastructure
etc.
Quality Control Quality Assurance
5.1 QUALITY CONTROL: (Q.C.)
The operational techniques and activities that are used to fulfill the
requirements for quality.
5.2 QUALITY ASSURANCE: (Q.A.)
All the planned and systematic activities implemented within the quality
system and demonstrated as needed to provide adequate confidence that an
entity will fulfill requirements for quality; and making sure that the quality of
a product is what it should be. Purpose of Quality Assurance is to prevent
problems before they occur, to identify and correct them swiftly if they occurand to uncover the root cause.
5.3 QUALITY MANAGEMENT
All activities of the overall management function that determine the quality
policy, objectives and responsibilities, and implement them by means such as
Quality Planning, Quality Control, Quality Assurance, and Quality
Improvement within the quality system.
The QUALITY CONTROL MANUAL being adopted for Water Resources
Department (the salient requirements of which are being outline in the
various chapters) aims at a “System Approach” to ensure that upon
implementation , the quality levels as set and defined in the specifications
and contract documents and relevant Indian Standards would be met in the
execution of project works.
-
8/15/2019 Quality Control Manual WRD
15/211
5
CHAPTER – II
ORGANISATIONAL SET-UP
GENERAL
I. Anyone connected with quality control work, should possess adequate
knowledge and experience of quality control works and be well conversant
with testing of construction materials. The object of quality control should be
clearly understood by them in letter and spirit so as to help in construction
and achieve high order of quality as laid down in specifications for works by
controlling various factors responsible for deterioration in quality,investigating reasons therefore and suggesting ways and means for
improvement.
II. To have proper and independent quality, quality control formation shall
consist of an independent unit headed by Chief Engineer Quality Control.
The C.E. shall have three S.E.'s in-charge of Quality Control Circle for the
various construction activities of different zones and the S.E.'s shall have a
team of E.E.'s to look after the work of different circles. Thus there will be
separate streams of construction and quality control assurance respectively
up to the level of C.E. (Organisational Chart attached at Annexure-II).
III. Every Q/C Circle shall be divided in number of division and each division
shall be headed by the Executive Engineer for the purpose of effective
quality control, every divisional jurisdiction shall be sub-divided in number
of units and each unit is to be put under the charge of A.En. The E.E. quality
control shall make all arrangements for the demarcating the areas of
operation of every quality control staff and issue a duty chart for each
member after approval from the C.E / S.E. Field Laboratory will be situated
at important nodal points which shall cover all the adjoining works and in-
charge will be T.A. to Executive Engineer. Site Laboratories as per
requirement in field shall be maintained by concerned site in-charge
(construction) and also utilized by Assistant Engineer Q/C for carrying out
necessary tests whenever site is inspected by him.
-
8/15/2019 Quality Control Manual WRD
16/211
6
IV. One of the fundamental principles to be understood and kept in mind is that
the overall responsibility for achieving construction quality in each sub-
project – rests with the execution unit and construction staff shall be fully
responsible for quality of work. Requisite assistance is to be provided by the
Q.C. Staff for ensuring construction quality.
Functions of Quality Control Units
The main function of Q.C. units is to have independent checking and control
of works. Since the works in the zones are of scattered nature, the quality
control units can not exercise concurrent quality control, but it has been
planned that these units should act in such a manner that necessary quality
control requirements are fulfilled jointly with the execution staff. It will be
the responsibility of quality control staff to ensure that all-requisite test as
per IS / relevant standards and specifications are carried out in site / field /
zonal or central laboratories. The quality control units will carry out periodic
inspections of works and conduct field tests so that any deficiencies in the
execution of works are properly brought to the notice of concerned
authorities and execution staff for taking corrective measures. The following
broad indications of functions of quality control units are given which may
be supplemented by issue of any further instructions by the Chief Engineer,
Quality Control, Jaipur from time to time.
(1) They should monitor that all required tests are carried out before start of
work as well as during execution. At least 10% tests are to be conducted by
the quality control units for reliability of the results and counter checking.
(2) They should ensure that all arrangements for carrying out routine field tests
in the field laboratories and site laboratories are duly made including
provisions and up-keeping of equipments, personnel etc. and record of these
field tests in prescribed formats are maintained. They should check this
record and also sign in the relevant registers in token of their inspection.
They should conduct field tests whenever they visit site of construction work
and record results of such tests in the registers maintained for the purpose.
-
8/15/2019 Quality Control Manual WRD
17/211
7
(3) They shall be empowered to order the suspension of work if deficiencies or
defects are noticed during execution. Order for stoppage of work if given by
the officer below the rank of S.E. should be got examined and confirmed by
S.E. Q.C. very promptly, preferably within 24 hours. However, order for
suspension of work can only be passed by the Chief Engineer Quality
Control.
(4) Inspection Book should be maintained at site wherein remarks should be
recorded by quality control staff whenever they visit site which should be
noted for compliance by the construction unit. They should specifically
record any deficiency noted to bring the same to the notice of appropriate
authority through remarks in the inspection book or inspection note. The
execution staff shall ensure the compliance of such deficiency and intimate
to the concerned officer of Quality Control Unit.
(5) The Chief Engineer, Quality Control shall ensure at least one test check of all
the works costing more than Rs.250.00 lacs in a year. This does not preclude
him for conducting more than one test check of any work for important
works; frequent checking is to be carried out.
The test check shall be thorough to ensure the quality of work and shall
include -
a. Observation of DBD and moisture contents of earthwork in filling
reaches.
b. Fineness modulus of sand, grading of sand and coarse aggregate.
c. Checking of water cement ratio for concrete.
d. Checking of lining work / masonry work / concrete work.
e. Any other requisite tests as per case.
-
8/15/2019 Quality Control Manual WRD
18/211
-
8/15/2019 Quality Control Manual WRD
19/211
8
CHAPTER – III
GENERAL FUNCTIONS OF LABORATORIES
The laboratory system, in addition to evaluate and monitor the inputs and outputs,
would also evaluate and monitor the workmanship as well as construction plant,
machinery and equipment. This would, thus, be accompanied by testing as well as
inspection.
FUNCTIONS OF CENTRAL LABORATORY AT JAIPUR
I. To conduct laboratory tests on samples of sand, coarse aggregate, stone,
cement and steel for use in masonry and concrete works.
II. To conduct laboratory tests for foundation soil, and for selection of soils
from proposed borrow areas, for use in the various zones of embankment as
per specifications, proctor density & optimum moisture content of soils
before start of earth work.
III. For masonry and concrete, the strength of mortar and concrete has to be as
specified in agreement. Laboratory has to design the proportions of different
ingredients through tests for the specified strength. The proportioning shall
be done by weight. It should be co-related with volume for volumetric
batching of concrete where quantity of concrete to be placed is of small
magnitude. Volume batching may be allowed by the Engineer-in-charge
where weight batching is not practical and provided accurate bulk densities
of materials to be actually used in concrete have been established. Allowance
for bulking shall be made in accordance with IS: 2386 (Part III)-1963. The
mass volume relationship shall be checked at periodical frequency to ensure
that specified grading is maintained.
IV. For concrete and mortars where strength is not given and only proportions
have been specified, the strength should be treated as standard for execution.
V. When controlled concrete is specified, it is essential that mix design is to be
done.
VI. Since the strength of cement varies from batch to batch in a cement factory
itself, it is essential that a relation between strength of cement versus strength
-
8/15/2019 Quality Control Manual WRD
20/211
9
of concrete may be worked out in the lab, well in advance of the starting of
the work. This would facilitate in furnishing the proper proportion of the mix
for adopting in the field and also it entails adding or reducing cement content
based on the strength of the cement.
VII. Results of tests performed in central laboratory should be documented in
prescribed Performa pertaining to following tests.
A. SOIL :
Disturbed grain size analysis IS: 2720 (Part IV) -1985.
Proctors compaction IS: 2720 (Part VII & VIII).
Atterberg's limit IS: 2720 (Part V) -1985.
Permeability IS: 2720 (XVII) - 1986 (at OMC. MDD)
Shear test (remoulded at OMC. MDD drained / undrained) IS: 2720 (Part
XIII) -1986.
Specific gravity IS: 2720 (Part III) -1980. Undisturbed density and natural
moisture content, permeability, consolidation, shear test (drained/undrained)
at OMC or saturation.
Free swell index; Swelling pressure of soil sample.
Dispersibility of soils.
Total Soluble salts.
Chemical test for carbonates & sulphates (Chlorides Gypsum test).
B. SAND :
For IS: 383-1970 Grading, IS: 2386 (Part I) Fineness Modulus, IS: 2386
(Part III) Bulkage , IS: 2386 (Part II) Organic and silt content.
Deleterious material and mica content, and presence of organic impurities, if
any.
C. Cohesive – Non-Swelling Soils
Requirement should broadly confirm to IS: 9451-1994
D. CEMENT
Fineness, consistency, specific gravity, compressive strength, setting time,
soundness by Le-Chatelier test.
E. COARSE AGGREGATE :
Grading IS: 2386 (Part I) -1963
-
8/15/2019 Quality Control Manual WRD
21/211
10
Soundness, crushing value, impact test.
Abrasion, Absorption, Specific gravity IS: 2386 (Part III):1963 Flakiness.
F. BOULDERS :
Soundness, weight and size, absorption, specific gravity, weathering
conditions (visual) abrasion after breaking to proper sizes.
G. FILTER MATERIALS :
Grading, uniformity co-efficient, weathering conditions (visual) and tests for
fine and coarse aggregate fulfillment of filter criteria as per I.S.Code.
H. WATER:
pH value, silt content, soluble salts and any other impurities.
H1. STEEL
Ultimate tensile strength / Elongation.
I. CONCRETE :
Air Content
Mix Proportions; Test on admixture (if used); Test on Super-plasticiser (if
used)
J.
HARDENED CONCRETE AND MORTARS :
Proportion by chemical analysis and compressive strength.
K. BRICKS :
Dimensions and physical properties including water absorption and
compressive strength.
L. TESTS FOR FOUNDATION INVESTIGATION AND INSITU
PERMEABILITY BEARING CAPACITY :
Other properties, if tested shall be reported in the remarks column or foot
note.
M. LDPE Film wherever used shall be tests.
N. IMPROVED DEVICES FOR QUALITY CONTROL :
It is planned to introduce improved devices for achieving speedy and
efficient quality control. Monitoring the characteristics of fresh concrete is
important from the point of view of quality control. The 28 days strength of
concrete is the criteria for acceptance and is the basis of quality evaluation.
-
8/15/2019 Quality Control Manual WRD
22/211
11
However, one has to wait for 28 days to get the results of compressive
strength of concrete cubes / cylinders. Even the accelerated compressive
strength tests take considerable time.
The portable electronic devices, commercially available now, have made it
possible for rapid on-site measurements of slump, temperature, water-cement
ratio (the most important factor influencing the strength of concrete) and the
likely 28 days strength of fresh concrete mixes. Software supplied with the
electronic unit also produces 'quality control certificates' based on the
measurements taken by this unit. This evidence of the properties of concrete
gives the site Q.C. /Q.A. Engineer, the confidence to accept or, if necessary,
to reject the concrete mix before it is placed.
Central laboratory at Jaipur is planned to be equipped with such a portable
electronic unit with software.
On embankment construction and compacted earth fill placement it is
planned to procure an engineering device of the type "Nuclear Guage" to
enable much more rapid and economic compaction and quality control than
the conventional methods, without any loss in accuracy. Such a device is
capable of quickly computing and displaying wet density, moisture content,
dry density, and percentage of compaction in terms of Proctor density.
The central laboratory at Jaipur is planned to be equipped with two Nuclear
Guage Device. Inspection of testing activities is illustrated in Annexure -IV.
FUNCTIONS OF ZONAL LABORATORY
To carry out tests of soils, filter materials, ingredients of concrete, tests of cement
and mortar etc. of the samples collected by the quality control staff and also such
samples collected by construction staff whose facility of testing is not available at
site as well as field laboratories. Results of tests performed will be reported to
Executive Engineer construction and Superintending Engineer and Chief Engineer
of Quality Control unit in the prescribed Performa pertaining to the following tests:
-
8/15/2019 Quality Control Manual WRD
23/211
12
SOILS:
1. Density, moisture content and compaction efficiency.
2. Sieve analysis
3. Proctor density & O.M.C.
4. Atterberg's limits
5. Specific gravity
SAND:
1. Gradation analysis & silt content.
2. Presence of deleterious materials including organic impurities.
3. Bulkage
COARSE AGGREGATE:
1. Grading
2. Specific gravity
3. Impact Value, Soundness, Crushing Value, Flakiness.
FRESH CONCRETE & MORTAR:
1. Water cement ratio, slump test
2. Compressive strength of Concrete & Mortar
3. Mix Proportions
BOULDER SAMPLE:
1. Absorption
2. Dimensions
3. Visual observation as regards weathering etc.
4. Specific gravity, impact value, soundness, specific gravity.
CEMENT:
1.
Setting time by Vicat needle test2. Strength of cement
BRICKS:
1. Dimensions and physical properties including compressive strength.
WATER:
1. Chemical
2. Cl, SO4, Organics & Inorganic Solids
3. pH value, Alkalinity, Acidity
-
8/15/2019 Quality Control Manual WRD
24/211
13
FUNCTIONS OF FIELD LABORATORIES
To carry out daily routine tests of soils, filter materials, ingredients of concrete and
mortar of the samples collected by the construction staff and report the results to
concerned J.En., A.En. & Executive Engineer of construction. The results will also
be reported to the quality control unit in the prescribed Performa pertaining to
following tests:
SOILS & EARTH WORK:
1. Density, moistures content and compaction efficiency.
2. Sieve analysis.
3. Proctor density & OMC.
CNS:
1. Gradation analysis
2. Shear Parameters
3. Index properties
SAND:
1. Gradation and Fineness Modulus.
2.
Bulkage3. Organic impurities through quick "Colour test".
CEMENT:
Casting of cubes for strength; Fineness by Sieve.
COARSE AGGREGATE:
1. Grading
2. Physical Properties
FRESH CONCRETE & MORTAR:
1. Water cement ratio & slump test
2. Physical properties of ingredients & silt content of sand.
3. Casting of concrete & mortar cubes.
BOULDER SAMPLE:
1. Water absorption
2. Dimensions
3. Physical properties including weathering etc.
-
8/15/2019 Quality Control Manual WRD
25/211
14
BRICKS:
Dimensions & physical properties including water absorption.
SITE LABORATORIES:
To carry out daily routine tests of soils, filter material, ingredients of concrete and
mortar for the on-going works and material carted at site before use. Results will be
recorded in registers kept at site for inspection purposes and will be reported to J.En.
& A.En. Construction and Quality Control, in the prescribed Performa pertaining to
the following:
SOILS & EARTH WORK:
1. D.B.D. & Moisture content layer wise.
SAND:
1. Gradation analysis & Fineness Modulus.
2. Bulkage
COARSE AGGREGATE:
1. Gradation analysis
2. Physical properties
CEMENT:
Casting of cubes for strength
FRESH CONCRETE & MORTAR:
1. Slump test
2. Physical properties of Ingredients; Proportion of cement and sand in mortar.
3. Casting of concrete / mortar cubes.
BOULDER SAMPLE:1. Dimensions & physical properties including weathering etc.
2. Water absorption
BRICKS:
1. Dimension & physical properties
2. Sampling of bricks for testing.
-
8/15/2019 Quality Control Manual WRD
26/211
15
Record of daily activities / tests will be maintained at site in the registers such as:-
1. Inspection Register
2. D.B.D. Register
3. Cement Consumption Register
4. Slump Test Register
5. Daily progress register – progress to be compared with consumption of various
ingredients including cement.
FUNCTIONS OF MOBILE LABORATORY (FIELD TESTS)
(i) To carry daily routine tests on compaction efficiency. Field density and moisture
content determination test.
(ii) To carry out daily routine tests like silt content, fineness modulus and gradation of
fine aggregates and coarse aggregates.
(iii) To carry out slump test, unit weight and temperature of concrete by using fresh
concrete in-situ testing equipment, and to take fresh concrete as per the required
frequency.
-
8/15/2019 Quality Control Manual WRD
27/211
16
CHAPTER – IV
DUTIES OF STAFF INCHARGE OF LABORATORIES
DUTIES OF ASSISTANT ENGINEER / A.R.O. INCHARGE OF
LABORATORY
i) To ensure proper up-keep and maintenance of laboratory equipment in
laboratory.
ii) To ensure proper up-keep of records of all samples being tested in the
laboratory as per prescribed norms and communication of the results to the
concerned.
iii) To supervise the testing works of Junior Engineer, Laboratory Assistants and
personally to check the tests to the extent of 25%.
iv) To prepare fortnightly review of all the tests results and submit to the
Executive Engineer, Quality Control & Construction.
v) To conduct any research work as may be assigned by the Executive
Engineer.
vi) The Central Laboratory & Zonal Laboratories have to conduct tests for the
suitability of materials proposed from various quarries, well in advance of
the actual execution of work, for which the construction staff shall send the
material to the lab well in advance.
vii) Steel rods as proposed to be used shall be tested for ultimate tensile strength
elongation and bond etc. as per standards.
viii) Samples of welded rods, welded at site shall be collected and tested to the
quality of welding.
DUTIES OF ASSISTANT ENGINEERS / A.R.O. / S.R.A. (LABORATORY)
Shall perform important tests as mentioned below:
A) CEMENT :
1. Fineness by Blaine
2. Normal Consistency
3. Setting time
-
8/15/2019 Quality Control Manual WRD
28/211
17
4. Soundness
5. Specific gravity
6. Compressive strength
7. Adulteration test
B) SAND :
1. Sieve Analysis & Fineness Modulus
2. Test for organic impurities silt & clay
3. Decantation test for silt
4. Specific gravity
5. Unit weight and bulkage factor
C)
COARSE AGGREGATE :
1. Sieve Analysis and gradation
2. Specific gravity
3. Water absorption
4. Examination of deleterious materials
5. Crushing strength
6. Impact
7. Abrasion
8. Flakiness index
9. Alkali – Silicate reactivity
D) CONCRETE :
1. Consistency – slump or compaction factor
2. Compressive strength
3. Air content
4.
Yield per unit quantity of cement5. Mix design test
6. Cement content
E) MORTAR :
1. Consistency
2. Compressive Strength
3. Yield per unit quantity of cement
4. Cement Content
-
8/15/2019 Quality Control Manual WRD
29/211
18
F) SOILS :
1. Gradation (Grain size analysis)
2. Consistency limits
3. Porosity & Voids ratio
4. Specific gravity
5. Swell pressure
DUTIES OF LABORATORY TECHNICIANS / JUNIOR RESEARCH
ASSISTANTS
i) To assist Assistant Engineer / Executive Engineers whenever required in
laboratory and field work.ii) To perform tests in laboratory such as :
a) Compaction tests
b) Limit tests
c) Analysis of fine & coarse aggregates
d) Silt in fine aggregate
e) Slump test
f) Collection of samples of concrete and mortars for filling moulds for
compaction test.
DUTIES OF LABORATORY ATTENDANTS
a) To keep instruments clean.
b) To assist Assistant Engineer / Executive Engineer and Laboratory
Technicians in conducting tests.
c) To prepare samples for test.
d) To arrange samples systematically.
CONTROL OF INSPECTION, TESTING AND MEASURING EQUIPMENT
The identification, calibration, and adjustment of all inspection, measuring and test
equipment and devices will be done at prescribed intervals as stated below against
certified equipment having a known valid relationship to nationally recognised
standards. The equipment will be capable of controlling the delivery of material for
weighing so that in accuracies in feeding and measuring during normal operation
-
8/15/2019 Quality Control Manual WRD
30/211
19
will not exceed 1% for water and 3% for all aggregates. Periodical test will be made
at least once in a month in case of equipment for measuring water, cement,
admixtures, sand and coarse aggregate. Other measuring equipments will be tested
once in a year unless some defects are noticed earlier, in which case these will be
attended immediately.
Documents will be established and calibration procedures will be maintained
including details of the following:
1. Equipment type 2. Identification number
3. Location 4. Frequency of Checks
5. Check method 6. Acceptance criteria
7. Action to be taken for unsatisfactory results, to ensure that the inspection,
measuring, and test equipment are capable of the required accuracy and
precision.
-
8/15/2019 Quality Control Manual WRD
31/211
20
CHAPTER – V
DUTIES OF FIELD STAFF IN RELATION TO QUALITY OF
WORKS DUTIES OF ASSISTANT ENGINEER
ASSISTANT ENGINEER
CONSTRUCTION
ASSISTANT ENGINEER QUALITY
CONTROL
1. Shall see that the markout of the area
to be tackled is properly given,
shuttering, centering, reinforcement
are done as per drawing and
technical specifications, to record the
Pre levels / foundation levels, and tosee that mark-out for canal
excavation is perfectly given as per
drawings. Pre levels, classification
levels and final levels of canal shall
be taken as per specification.
1. Shall check the markout of
foundation and centering/ shuttering
reinforcement arrangement and
inform the Assistant Engineer
construction to rectify the defects if
any.
2. Shall see that the construction
equipment like mixers, vibrators,
compaction equipment, pumping
arrangements for curing / watering
are arranged before starting of any
work.
2. Shall check the adequacy of the
construction equipment and curing/
watering arrangements before start of
work and during excavation.
3. Shall see that sufficient quantities of
input materials as per agreement
specifications are made available at
site of work and to arrange testing
equipment, men and material
required for conducting field tests,
sending samples of input materials
for testing to central lab, field
laboratories as per norms.
3. Shall conduct / get conducted by
different laboratories the field tests
on input materials and record the
results and to inform the Assistant
Engineer construction to rectify the
defects if any.
4. Shall write O.K. Cards after area is
ready to start the work and to inform
the Assistant Engineer Quality
Control and Executive Engineer
construction and take permission to
start the work on O.K. Card. Shall
also permit OK in case quality control
A.En. is not available.
4. Shall check and write the O.K.
card and record the deviations,
defects if any or otherwise to record
the final OK and to inform
Executive Engineer quality control
and to permit to start the work.
5. Shall supervise and ensure that
correct quantities of input materials as
per mix design communicated by the
5. Shall make regular checks of the
feeding of input materials mixing
time and suggest the quantity of
-
8/15/2019 Quality Control Manual WRD
32/211
21
ASSISTANT ENGINEER
CONSTRUCTION
ASSISTANT ENGINEER QUALITY
CONTROL
central laboratory are fed into the
mixers/batching plants etc., and shall
ensure specified mixing time.
(minimum 2½ minutes)
water depending on the moisture
content of sand as and when
required.
6. Shall ensure proper vibration, rolling
etc., during course of day to day
work. Shall conduct D.B.D. test of
earth work, gradation of material,
slump test, core drill test and to
extract field samples of material and
finished products to be sent to
different laboratories also provide
men and material required forextracting samples of finished product
for quality control staff.
6. Shall ensure slump test, core tests,
proctor density etc., conducted as
per norms by the construction and
quality control staff and to extract
field samples of finished product to
be sent to central laboratory later.
7. Shall ensure proper curing of samples
extracted till the curing time is over
and to make arrangements to send the
samples to central lab or other
suitable lab.
7. Shall assist the Assistant Engineer in
Proper handling / transport of
samples to central lab.
8. Shall ensure timely green cutting of
concrete with proper air – water gun;
nicking & chipping (wherever so
warranted) so as to prepare the
surface for next concrete lift for
effective bond at the lift / construction
joints.
8. Shall check and see that the
preparation of the surface is
adequately done for starting the next
lift.
9. Shall ensure proper curing / watering
and allow removal of shuttering only
after the time limit prescribed in the
specifications and to see that the
surface are finished to the
plumb/straight lines etc., afterremoval shuttering.
9. Shall check the adequacy of
curing/watering and see that the final
surfaces are finished neatly
plumb/straight lines etc.
10. Shall maintain (1) mark-out register
(2) OK Card files (3) Load Register.
10. Shall maintain registers of field tests
conducted.
-
8/15/2019 Quality Control Manual WRD
33/211
22
DUTIES OF EXECUTIVE ENGINEER
EXECUTIVE ENGINEER
CONSTRUCTION
EXECUTIVE ENGINEER QUALITY
CONTROL
1. Shall supervise, check, advice, andinstruct the J.E.N. /A.E.N.
Construction regarding discharge
of their functions properly.
1. Shall supervise, check, advice andinstruct the A.E.N. Quality Control
regarding discharge of their
functions properly.
2. Shall intimate the Executive
Engineer quality control regarding
signing of agreement for starting of
any new work, duly endorsing a
copy of work order. Shall supply
copies of contract documents,
drawings construction programmeetc., to Executive Engineer Quality
Control, and Superintending
Engineer.
2. Shall maintain copies of approved
Designs, reports, contract
document, drawings, construction
programme, extracts of inspection
notes etc., and shall see that his
subordinates go through the above
documents.
3. Shall get all ingredients of
concrete, masonry got tested
before use. Shall see that the soils
are tested for various properties
like OMC, MDD, etc., before
starting of Embankment work.
3. Shall remind and verify whether
test results are available or not
before starting up of any new work
and during execution of work.
4. Shall see that all the Machinery/Equipment being used by the
contractor is got periodically
calibrated.
4. Shall assist in upkeep andcalibration of equipment.
5. Shall see that OK Cards are written
and kept at site of work before
starting of any work. Also will
ensure rectification of work before
releasing payments.
5. Shall inspect and sign on OK Cards
during field visits. Defects of
construction will be pointed out and
remedies suggested for achieving
good quality construction.
6. Shall order the suspension of work
if any defects are noticed orreported by quality control staff
and resume the work only after
rectification of defects in the
presence of quality control staff.
6. Shall order the stopping of work if
major defects are noticed orreported by quality control staff and
intimate his counterpart to see that
defects are rectified. Also defects
noted during construction are to be
reported to the S.E./Quality Control
& Construction.
7. Foundations and reinforcement,
shuttering, centering where heavy
reinforcement is involved is to be
checked by Executive Engineer
7. Foundations and reinforcement,
shuttering, centering where heavy
reinforcement is involved is to be
tallied by Executive Engineer
-
8/15/2019 Quality Control Manual WRD
34/211
23
EXECUTIVE ENGINEER
CONSTRUCTION
EXECUTIVE ENGINEER QUALITY
CONTROL
invariably before starting the work. invariably before starting the work,
during his field visits.
8. Shall personally see that the
samples to the laboratories are sent
regularly, obtain the results and
communicate the same to
Executive Engineer quality
control.
8. Shall pursue and keep track of
sending of samples various
laboratories and to keep record of
results received.
9. Shall take the help of quality
control Executive Engineer
whenever a dispute is referred.
9. Shall co-ordinate with the EE/
Construction division render
assistance in resolving the issues
referred to him.10. Shall jointly inspect the site with
quality control Executive Engineer
in case variation in classification is
less than 10% (+/-) and finalize the
classification.
10. Shall jointly inspect the site with
Construction Executive Engineer in
case variation in classification is
less than 10% (+/-) and finalize the
classification.
-
8/15/2019 Quality Control Manual WRD
35/211
24
CHAPTER – VI
CO-ORDINATIONS
The construction staff and quality control staff must act in tandem to achieve good
quality of the finished product and construction as per the contract specifications.
Construction staff should make it a point to inform the quality control staff, the date
of starting of any activities or component of the work well in advance so as to enable
the quality control staff to schedule their work plan and attend the particular work on
the particular date.
In turn quality control staff should schedule their programme, so as to attend to the
work on the dates required by the construction staff and ensure that, the progress of
work is not hampered.
The quality control staff shall be responsible for exercising the various field checks
with reference to drawing and specifications laid down in respective I.S. code during
construction and carrying out all the laboratory and field tests on materials used for
construction and reporting through their higher officer, to the field staff for ensuring
quality.
The Assistant Engineer / Executive Engineer (Quality Control) can address Assistant
Engineer / Executive Engineer construction regarding defects, rectification testing
etc.
As far as possible the defects are to be rectified in the presence of the Quality
Control staff and the payment shall be effected only after the Quality Control Staff
are fully satisfied with the rectification and quality of work. Any rectification done
subsequently any intimation and presence of Quality Control Staff shall be at the
sole responsibility of the construction staff.
The defects, if any, noticed by the quality control staff during their course of
inspection shall be brought to the notice of the construction staff then and there. It is
the primary responsibility of the Quality Control & Inspections staff to draw the
attention of the construction staff, whenever they notice defective work during their
course of inspection. It is duty of the construction staff to attend to the rectification
and maintain proper specifications as pointed out by their counter part of the Quality
Control organisation.
-
8/15/2019 Quality Control Manual WRD
36/211
25
Quality Control staff will monitor that all tests required as per agreement and I.S.
Codes are carried out in different laboratories by the field staff they will also test
check to the extent of minimum 10% (or as decided by Chief Engineer QC) of the
required tests and co-relate with the other tests conducted in different laboratories.
All observations regarding substandard or below specification work will be dully
recorded in the inspection / visit books kept at site by inspecting officer. Such
substandard or below specification works should be got stopped / dismantled
immediately by execution unit. The defects pointed out by Quality Control Unit will
be communicated to the execution unit for compliance immediately. The compliance
report should be sent by execution unit within ten days.
The quality control staff cannot supervise the placement of concrete on a mix to mix
basis continuously. They can only conduct random check of input materials, mixing
time, placement of concrete, vibration etc. It's the primary responsibility of the
construction staff to ensure adequate supervision of mix to mix placement of
concrete.
The Operations of the Quality Control Staff shall not interfere in any way, with the
executive powers vested with the officers in-charge of execution. They will also inno way diminish the responsibility of the officers in-charge of execution. The field
officers in-charge of works are primarily responsible for the quality of all works and
to carry out the work as per the technical specifications.
In case of difference of opinion between quality control staff and construction staff,
it should be sorted out by way of discussions in cordial atmosphere and mutual trust
as per the guide lines indicated below. In case it involves any design feature /
problem / aspect, the design office should be duly consulted and the advice given by
the designer should be accepted.
In case of difference of opinion between Executive Engineer, Construction and
Executive Engineer, Quality Control it would be referred to Superintending
Engineer, Construction, who would discuss the matter with Superintending
Engineer, Quality Control and settle the issue. Similarly, when the Superintending
Engineer, Quality Control is not readily available, the Superintending Engineer,
Construction can over-rule after recording the reasons in writing. In such cases the
-
8/15/2019 Quality Control Manual WRD
37/211
26
Superintending Engineer, Construction has to discuss with Superintending Engineer,
Quality Control at the earliest opportunity and modify his earlier orders, if
necessary. Similar action will be taken in case of difference of opinion on the
comments of Superintending Engineer, Quality Control.
In case there is a difference of opinion between both the Chief Engineer /Additional
Chief Engineer, Construction and Quality Control the matter would be referred to
Chief Engineer Water Resources Jaipur, whose decision shall be final and binding
on all. Work should immediately be suspended and not allowed to resume until the
defects pointed out by Quality Control and Inspection staff are rectified.
The construction and quality control staff shall keep a regular liaison with theGeologist in respect of all Geo-technical problems and enlist his input on
foundations of structures & dams; Cut Off Trenches, tunneling; contract/
consolidation/curtain grouting; Rock / Excavation Slopes (stability of slopes);
protection measures; permeability / Water loss tests etc., as well as any geological
problem. The advice rendered by the Geologist should be discussed with the
Designers and duly respected and implemented.
-
8/15/2019 Quality Control Manual WRD
38/211
-
8/15/2019 Quality Control Manual WRD
39/211
27
CHAPTER – VII
QUALITY ASSURANCE
All planned and systematic strategies and actions necessary to generate adequate
confidence that Input and Output product will satisfy given requirements of quality
and all the components of works perform satisfactory during life period of service,
adequate quality checks as analysed during construction is a record which speaks of
"Quality Assurance". It comprises planning and policies, education and training
standards and specifications, contracts and agreements, and quality control. Quality
assurance is to assume that the materials as per standard and as per the requirements
have gone into the production of concrete, earth, masonry work etc. This is achieved
by evaluating the quality checks during construction and post construction tests
made and compared.
LIST OF DOCUMENTS
Each QC laboratory should hold the following documents:
Quality control manual.
Technical Records: Specification, Contract documents, inspection and Test
Procedures, relevant standards / code of practice.
Mill Certificates.
Material test reports, test reports of cores.
Inspection Reports.
Photographic / Video film records of construction which may not remain
accessible after commissioning of the project.
Non-conformance reports.
Statistical evaluation reports. Technical Literature.
Standardization of records.
Quality Control Personnel should hold the following Documents:
Data of test.
Area where material is used.
Test method with reference to standards.
Testing results, including those of cores of concrete.
-
8/15/2019 Quality Control Manual WRD
40/211
28
Acceptance criteria.
Remarks
Test personnel signature.
Junior Engineer and Assistant Engineer (Site In-charge at site) should always have a
kit consisting of equipments i.e. measuring tapes, scale, Vernier – calipers, Plumb
rule & bob, spirit level, square, Gunia (small), hammer, measuring glass etc. to
facilitate quality checking at site.
-
8/15/2019 Quality Control Manual WRD
41/211
29
CHAPTER – VIII
O.K. CARDS
Since O.K. Cards contain important entries/information on execution of works at all
stages and are liable to be referred/perused at a later stage also, the O.K. Cards shall
be maintained in duplicate in two colours. The green coloured card shall form a part
of the record of Q.C. /Q.A. Wing and the pink coloured card remains in the custody
of Construction wing. The O.K. Cards, relating to any particular work, shall be put
in a round shaped tin box and placed right at the construction site. The exterior of
the tin box shall be painted red. Senior officers shall also check the O.K. Cards
during their field inspections to ensure that those are being maintained and
proper/genuinely filled.
An O.K. Card is a condensed form of specifications and essential requirements for
achieving specified workmanship and quality level of output. Each work is sub-
divided into various construction activities in proper sequence / order of
construction. Such activities are listed in chronological order on the O.K. Cards.
For various stages of construction activities where laboratory tests or checks with
reference to drawing and specification are required from quality control unit, O.K.
Cards System shall be followed. The O.K. Cards should be made available on the
site in regular manner. Approval of the component of work in progress at the times
of inspection should be recorded by the inspecting officer.
The O.K. Card consists of two parts for each work. Part first covers the initial
preparedness for the work and indicates pre-requisites where as the second part
covers the daily performance of activities based on pre-requisites and also giving
permission to perform the job by the construction as well as Quality Control staff.
Besides the location and type of work, the first column of O.K. Card is to be filled
by the construction agency (contractor) by preparing each feature and making it
ready for inspection by the project construction engineer who Okay through his
signatures and then puts up to the Q.C. /Q.A. Engineer is not available at site then
O.K. given by construction Engineer will be treated as final. If anything otherwise is
-
8/15/2019 Quality Control Manual WRD
42/211
30
not observed. Should anything otherwise be found, the O.K. Card shall not be signed
by him and ask the Construction Engineer / agency for necessary rectification.
Subsequently, O.K. Card should refer to the defects removed, if pointed out
previously in O.K. Card and counter reference to the previous check and should be
signed of Okayed.
It must be borne in mind that work cannot be held up unduly for disposal of O'K
Card. The Assistant Engineer (Quality Control) / Construction will be okaying
authority for concentrated work like dam, spillway, head regulator etc. and Assistant
Engineer / Junior Engineer construction will be okaying authority for scattered
works like canals and small structures. Random checks by supervising officersshould be recorded on O'K Cards at site. Weekly report of O'K Cards maintained by
construction unit should be submitted to S.E. / Q.C. of the area who has to monitor
and ensure that adequate check is being maintained by field staff. Confirmation
regarding rectification of defects be obtained from A.En. /Q.C. before making
payment once in three bills and final bill of the contractor.
After processing through various levels and entering observations and rectification
O'K Card will be closed at the time of taking measurements for releasing paymentsto the contractor. Photocopy of the O'K Cards (pink) will be kept at site and original
copy will be attached with the bill and will be kept on record by the division office
while making payments to the contractor. Photo copy of O'K Card of Quality
Control will also be enclosed with the bill & kept on record with the bill by the
division office. However O.K. Card of Quality Control will not be closed till the
work is finalized and will be kept on record by the Executive Engineer, Quality
Control after the rectification is completed by the construction wing and final
comments are recorded by both the Assistant Engineer.
Specimen of O.K. Cards for various works such as embankment, concrete, masonry
etc. have been enclosed below.
-
8/15/2019 Quality Control Manual WRD
43/211
31
O.K. Card No. 1
Water Resources Department
O.K. Card for raising / Strengthening of Earthen Embankments / Fill Placement &
Compaction (Part-I)
Name of Work ______________________________________________________
Agency ____________________ Contract / Package No. ___________________
Location ___________________ Date ___________________
Description of Activities Remarks& DatedSignature
ofAgency
Remarks and DatedSignature of
Construction staff
Remarks &Dated
Signature ofQC/
InspectionEngineer
Super-visor
JEN AEN
Layout / Demarcation / Fixing & checkingT.B.M.
Removal of Vegetation, debris & Siteclearance
Benching, stripping of base (20 cm)
PRE-REQUISITES
(1) Proctor's density of borrow area
(2) Designation of borrow area & checking ofrequired moisture
(3) Excavation and shaping of rain cuts and
its refilling
(4) Weather key- trench made and/or plowingof old embankments done if required
(5) Watering of base
OK FOR FILL PLACEMENT
Thickness of loose layer (cm)
Removal of oversize (more than 7.5 cm size)layer
Moisture content (%) – initial
Moisture content (%) final (OMC = %)
Weather soil laid as per profile
OK FOR COMMENCING COMPACTION
Checking of Type of Compaction Equipment /Roller
Checking of In place density (D.B.D.)
Compaction Efficiency (%)
Specified Compaction (%) of Proctor
Re-Rolling / Re-compaction if required
D.B.D. after Re-Rolling
OK FOR NEXT LAYER
Removal of extra/loose earth from – U/S & D/Sfaces
-
8/15/2019 Quality Control Manual WRD
44/211
3 2
O . K . C a r d N o . 2
W a t e r R e s o u r c e
s D e p a r t m e n t
S u p p l e m e n t a r y O . K . C a r d f o r s u b s e q u e n t l a y e r s ( P a r t I I )
N a m e o f W o r k_______________________________________________________________________________________
A g e n c y_____________________________________
C o n t r a c t / P a c k a g e N o .______________
_______
L o c a t i o n____________________________________
D a t e______________________________________
D a t e
D e s c r i p t i o
n o f A c t i v i t i e s
( C h a i n a g e l a y e r )
W e a t h e r P r e -
R e q u i s i t e s
f u l f i l l e d
W e a t h e
r
s a t i s f a c t o
r y
c o n s o l i d a t i o n
a c h i e v e d
W e a t h e r
p e r m i t t e d f o r
n e x t l a y e r
D a t e d
S i g n a t u r e o f
A g e n c y /
C o n t r a c t o r
R e m a r k s a n d D a t e d
S i g n a t u r e o f C
o n s t r u c t i o n
s t a f f
R e m a r k s &
D a t e d
S i g n a t u r e o f
Q C /
I n s p e c t i o n
E n g i n e e r
S u p e r -
v i s o r
J E N
A E N
-
8/15/2019 Quality Control Manual WRD
45/211
33
O.K. Card No. 3
Water Resources Department
O.K. Card for Sub grade preparation for placement of lining (Part I)
Name of Work ______________________________________________________
Agency ____________________ Contract / Package No. ___________________
Location ___________________ Date ___________________
Description of Activities
Dated
Signatur es of
Agency
Remarks and DatedSignature of
Construction staff
Remarks &Dated
Signature ofQC/
InspectionEngineer
Super-visor
JEN AEN
ChainageRemoval of Vegetation, debris
Completion of dewatering
Filling of over excavation, depressions/
Pockets in soil/rocky strata as per
specification
Watering of sub-grade
Compaction of sub-grade (bottom & sides)through slope compaction/Pneumatic rammer /
power roller to specific density (..... %)Final Lip cutting & checking sub-grade surfaceto ensure within permissible tolerances (up to6.5 mm on sides, up to 12.5 mm on Bed)
Laying of under-drainage arrangement(a) Porous Plugs (b) Longitudinal &Transverse Drains (c) Porous Panels
Final wetting of sub-grade to 15 cm depth
Checking of quantity and quality of materialstacked at site
Cement, Aggregate, Sand, Water
Checking of mixer, vibratos & power
Checking of form work/ Shuttering true to lineand grade
O.K. for lining placement
-
8/15/2019 Quality Control Manual WRD
46/211
3 4
O . K . C a r d N o . 4
W a t e r R e s o u r c e
s D e p a r t m e n t
O . K . C a r d f o r p l a c e m e n t o f c a s t - i n - S i t u C o n c r e t e l i n i n g ( P a r t I I )
N a m e o f W o r k_______________________________________________________________________________________
A g e n c y_____________________________________
C o n t r a c t / P a c k a g e N o .______________
_______
L o c a t i o n____________________________________
D a t e______________________________________
D a t e
D e s c r i p t i o n o f
A c t i v i t i e s
& l o c a t i o n
W e a t h e r P r e -
R e q u i s i t e s o f
S u b - g r a d e
p r e p a r a t i o n
d o n e
S a t i s f a c t o r y
Q u a l i t y &
Q u a n t i t y o f
m a t e r i a l
s t a c k e d a t s i t e
S i g n a t u r e o f
C o n t r a c t o r /
E n g i n e e r
W h e t h e r s l u m p
c h e c k e d &
c u b e s c a s t e d
W h e t h e r
s p e c i f i e d
c o n t r a c t i o n
j o i n t s p r o v i d e d
R e m a r k s
a n d D a t e d
S i g n a t u r e o f
C o n s t r u c t i o n S t a f f
R e m a r k s &
D a t e d S i g n .
o f Q C /
I n s p e c t i o n
E n g i n e e r
S u p e r -
v i s o r
J
E N
A E N
-
8/15/2019 Quality Control Manual WRD
47/211
35
O.K. Card No. 5
Water Resources Department
O.K. Card for Random Rubble Stone Masonry
Name of Work ______________________________________________________
Agency ____________________ Contract / Package No. ___________________
Location ___________________ Date ___________________
Description of ActivitiesDated
Signaturesof Agency
Remarks and DatedSignature of Construction
Staff
Remarks &Dated
Signature ofQC/
InspectionEngineer
Super-visor
JEN AEN
Stone – Quality SizeSuitability of
a) Cement
b) Sand
c) Water
Mortar
a) Mix measurement
b) Mixing, Consistency
Pointing, thickness of joints,staggering of joints, laying of stones,hearting stones, bond stones spacing.
Whether samples of mortar collectedin cubes for testing
Green cutting with proper air watergun / sand blasting
Adequacy of curing for masonrywork
Verticality of structure check by
using plumb bob
Embedded Materials
Final OK for masonry work
-
8/15/2019 Quality Control Manual WRD
48/211
36
O.K. Card No. 6
Water Resources Department
O.K. Card for Plain & Reinforced Cement Concrete
Name of Work ______________________________________________________
Agency ____________________ Contract / Package No. ___________________
Location ___________________ Date ___________________
Description of ActivitiesDated
Signaturesof Agency
Remarks and DatedSignature of
Construction Staff
Remarks &Dated Signature
of QC/InspectionEngineer
Super-visor
JEN AEN
Material Suitability
i. Cement
ii. Steeliii. Aggregate 40 mm, 20 mmiv. Sandv. Watervi. Admixture
O.K. for materials
Form work & Centering
i) Tightness, Stability, Smoothness
ii) Cleaning, oiling, perfectness ofform work.
iii) R.L. of Centering
iv) Checking of reinforcement.O.K. for reinforcement
Tools & Plants
i) Mixers & Vibratorii) Adequacy of concrete production
/ transportation, placement,consolidation.
O.K. for Placement
1. Design mix, measurement2. Mixing / Consistency3. Slump
4. Compaction of Concrete5. Joints6. Finishing7. Casting of Cubes8. Curing9. Compressive strength 28 days
Final O.K.
Note: Before pouring of concrete the reinforcement should be got checked by the Q.C. Unit.Working standby vibrator & mixer should be kept at site before start of concreting.
-
8/15/2019 Quality Control Manual WRD
49/211
37
O.K. Card No. 7
Water Resources Department
O.K. Card for PCC Slab Canal Lining
Name of Work ______________________________________________________
Agency ____________________ Contract / Package No. ___________________
Location ___________________ Date ___________________
Description of Activities
Remarks& Dated
Signaturesof Agency
Remarks and DatedSignature of
Construction Staff
Remarks &Dated Signature
of QC/InspectionEngineer
Super-visor
JEN AEN
A. Materials Suitability :
i. Cement
ii. Aggregate 40 mm, 20 mmiii. Sandiv. Waterv. Treatment of soil if any
O.K. for materials
B. Formation of Canal Banks :
i) Stripping/Removal of vegetation
ii) Cutting canal bed & sides to thegeometric section/shape
iii) Consolidation
iv) Trimming
C. Casting of PCC Slabs :i) Mix, Measurement by weight
ii) Mixing, consistencyiii) Slumpiv) Water Cement Ratiov) Casting of PCC Slabsvi) Casting of cubes of concrete mix
vii) Providing sub base if necessityviii) Laying/Placing in position PCC
slabsix) Construction jointsx) Contraction joints
xi) Pointing with CMxii) Curingxiii) Pressure Relief Holexiv) Flexural Strength of PCC Slabs
Final O.K.
-
8/15/2019 Quality Control Manual WRD
50/211
38
O.K. Card No. 8
Water Resources Department
O.K. Card for Grouting
Name of Work ______________________________________________________
Agency ____________________ Contract / Package No. ___________________
Location ___________________ Date ___________________
S.No. Description Dated Signature of Contractor/QC Remarks
GENERAL
1. R.L. and area surface to be grouted.
2. Classification of the rock strata.
3. Salient feature of the strata such
as a fault zone cavities, fissures etc.
4. Permeability value of the strata before grout.
GROUP
5. Pattern of Grout adopted
6. Depth and dia. of the hole
7. Pressure adopted for grout
8. Proportion of grouting mix
9. Intake of slurry mortar per unit area per unit time
10. Total quality of intake
11. Final permeability value of the strata after grout
12. Whether the grout strata is OK.
-
8/15/2019 Quality Control Manual WRD
51/211
39
CHAPTER – IX
TESTS TO BE PERFORMED ON MATERIALS
MATERIAL TEST METHOD
Cement a) Chemical IS:4032-1985i) Sio2, A12O3, Fe2O3, Cao ,MgO, SO2,
Insoluble residue & Loss on ignitionii) Alkalies & Chloridesiii) Free Lime
b) Physical IS:4031-1988i) Specific gravityii) Finenessiii) Soundnessiv) Compressive strengthv) Drying shrinkage
Water Chemicalsi) Cl, SO4, Organic & Inorganic Solids, pH,
Alkalinity / AcidityIS:3025-1987
ii) Setting time of mortariii) Relative strength of concrete IS:1199-1959
Fine Aggregate i) Sieve Analysis & Fineness Modulus IS:383, IS:2386ii) Test for organic impurities silt & clay (Part I & IV)
iii) Decantation test for silt IS:2386 (Part II)iv) Specific gravity IS:2386 (Part III)v) Unit weight and bulkage IS:2386 (Part III)
IS:2386 (Part III)CoarseAggregates
i) Sieve Analysis IS:2386-1963
ii) Flakiness indexiii) Elongation Index PART - Iiv) Deleterious materialsv) Specific gravity PART-IIvi) Bulk Densityvii) Moisture content PART-III
viii) Absorption value
Mechanical tests PART-IVix) Aggregate crushing valuex) Impact Value PART - Vxi) Abrasion Valuexii) Potential reactivity of aggregatexiii) Petro-graphic examinationxiv) Alkali Aggregate reactivity test
PART-VIPART-VII
-
8/15/2019 Quality Control Manual WRD
52/211
40
Embankment i) Proctors compaction IS:2720 Part(vii & viii) -1980
ii) Atterberg‟s Limits IS:2720 Part (v)-1985iii) Permeability IS:2720 Part (xvii)-
1966iv) Shear Test IS:2720 Part (xiii)-1986v) Specific gravityvi) Disturbed grain size analysis
IS:2720 Part (iii)-1980IS:2720 Part (iv)-1985
Concrete a) Fresh Concretei) Air Contentsii) Vibrationiii) Temperature measurementiv) Mix proportionsv) Water cement ratiovi) Yield
b) Workability testi) Slump Test Usual procedureii) Compaction Factor test IS:CED2(CESS) ASTM
C 597-83c) Hardened Concrete BS: 4408i) Compressive strengthii) MDT Tests
IS : 516-1959IS : CED 2 (3890)
d) Special Testi) Microscopyii) Non-destructive
iii) Core Testing
Admixtures i) Bleeding IS:9103-1999ii) Relative Strength IS:516-1959iii) Setting Timeiv) Relative water contentv) Relative length change
IS:8142-1974IS:9103-1999IS:1199-1959
Masonry i) Gradation of Sandii) Slump Testiii) Compressive strength of stones IS:1121(Part I)-1974iv) Tests for stone - IS:1124 -1974
- Water absorption- Specific gravity- Porosity- Weathering of natural building stone IS:1125 -1974
-
8/15/2019 Quality Control Manual WRD
53/211
41
CHAPTER – X
LIST OF EQUIPMENT FOR CEMENT AND CONCRETE TESTING
TEST EQUIPMENT
A. CEMENT Flame Photometer
a. Chemical
i) Alkalies
ii) Minor, major oxides byCalorimetry
iii) Chloride Hot plate, Balance (Acc. 0.0002 g) Muffle
Furnace (up to 1200 c). Platinum Crucibles‟,
conductivity Bridge, pH Meter, physical balance
(Cap. 150 g)
iv) General
b. Physical
i) Fineness Blaine Apparatus, stop watch.
ii) Soundness Le- Chatelier Le-Chatelier Moulds, hot water bath Autoclave
iii) Consistency and settingtime
iv) Heat of Hydration
v) General
B. AGGREGATES &
CONCRETE
Vicat Apparatus, moulds, setting time needles and
plunger compression testing machine (50 tonnes).
vibrating machine, moulds 50 sq.cm. Area,calorimeter thermometer, flow table, stop watch,
timer temperature controlled oven, humidity
chamber incubator, physical balance (ACC 0.001
g), balance (cap. 5 kg ACC 1 g), set of standard
sieves lid and receiver.
a) General
i) Crushing value
ii) Impact value
iii) Abrasion value
vi) Alkali Aggregate
Reactivity
vii) Flakiness &
Elongation indices
viii) Unit weight
Containers
ix) Sampling (Sand)
viii) Specific Gravity andAbsorption
Electric Driver, hot plates, set of standard sieveslid and receiver, balance 10 kg (ACC 1g), 100 kg
(ACC 0.001 kg), 200 kg (ACC 0.5 kg) scop,
Enamel trays, balance, shovels, compression
testing machine (200 tonnes), crusher and ball
mill prevailing rigs 2,25,50,100 tones.
Crushing apparatus
Aggregate impact test machine
Apparatus for measuring flakiness
Minimum Capacity of Measures.
-
8/15/2019 Quality Control Manual WRD
54/211
42
TEST EQUIPMENT
C. CONCRETE
a. Fresh Concrete
Max. C.A. Size of Capacity of
Measure dm3
i. Vibration 2.50 6
ii. Temperature
measurement
37.50 11
iii. Mix proportions 50.00 14
75.00 28
b. Workability Tests:
i. Slump Test 114.00 71
ii. Compaction factor test 152.00 99
c. Hardened concrete Refer sample Divideri) Compression, tension
bending & Brinnel
hardness tests.
Pycnometer
Internal Vibrator, table vibrator
constituents, Slump cone Apparatus
Compaction Factor apparatus, Universal Testing
Machines with accessories (Cap. 100 tonnes),
Concrete workability meter, Capping moulds
Laboratory concrete mixer, Reluctance meter.
d. Special Tests Optical microscope, grinding and polishing
i) Microscopy equipment, ultrasonic pulse velocity, reboundii) Non-Destructive hammer core drilling machine, RCC cutting
iii) Core Testing machine, RCC cutting machine, t