    e-Notes by D.G.Kantharaju, East Point College, Bangalore

    Network Analysis Network is a graphical representation of all the Activities and Events arranged in

    a logical and sequential order.

    Network analysis plays an important role in project management. A project is a combination of interrelated activities all of which must be executed

    in a certain order for its completion.

    Activity: Activity is the actual performance of the job. This consumes resources (Time,human resources, money, and material)

    Event: An event refers to start or completion of a job. This does not consume anyresources.

    Analyzing network, the planning, scheduling and control of a project becomes

    easier. PERT and CPM are the two most popular network analysis technique used toassist managers in planning and controlling large scale projects.

    PERT- (Programme Evaluation Review Technique) CPM - (Critical Path Method)

    Applications: -Construction of a Residential complex,

    Commercial complex,Petro-chemical complex

    Ship buildingSatellite mission developmentInstallation of a pipe line project etc...

    Historical Evolution.Before 1957 there was no generally accepted procedure to aid the management of aproject. In 1958 PERT was developed by team of engineers working on a Polaris Missileprogramme of the navy. This was a large project involved 250 prime contractors andabout 9000 job contractors. It had about 19 million components. In such projects it ispossible that a delay in the delivery of a small component might hold the progress ofentire project. PERT was used successfully and the total time of completion was reduced

    from 7 years to 5 years.

    In 1958 Du Pont Company used a technique called Critical Path Method (CPM) toschedule and control a very large project like overhauling of a chemical plant, there byreducing the shutdown period from 130hrs to 90 hrs saving the company 1 million dollar.Both of these techniques are referred to as project scheduling techniques.

    1

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    2/67

    Differences between PERT & CPM

    PERT CPM

    1. It is a technique for planningscheduling & controlling of projectswhose activities are subject touncertainty in the performance time.Hence it is a probabilistic model

    1. It is a technique for planningscheduling & controlling of projectswhose activities not subjected toany uncertainty and theperformance times are fixed. Henceit is a deterministic model

    2.It is an Event oriented system 2. It is an Activity oriented system

    3.Basically does not differentiatecritical and non-critical activities

    Differentiates clearly the criticalactivities from the other activities.

    4. Used in projects where resources(men, materials, money) are alwaysavailable when required.

    4. Used in projects where overallcosts is of primarily important.Therefore better utilized resources

    5. Suitable for Research andDevelopment projects where timescannot be predicted

    5.Suitable for civil constructions,installation, ship building etc.

    2

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    3/67

    3

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    4/67

    4

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    5/67

    5

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    6/67

    Problem 2.

    6

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    7/67

    Problem 3.

    7

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    8/67

    8

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    9/67

    9

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    10/67

    10

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    11/67

    11

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    12/67

    CRITICAL PATHMeaning: The longest path in a project network which determine the duration of theproject is known as critical path.

    Determination

    2

    Step 1. List all the p

    12

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    13/67

    Step 2.For each seq

    Determination

    2

    13

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    14/67

    Float (Slack) Float (Slack ) refers to the amount of time by which a particular event or an

    activity can be delayed without affecting the time schedule of the network. Float (Slack)

    Float (Slack) is defined as the difference between latest allowable and the earliest

    expected time.Event Float/Slack = LS ESWhere LS = Latest start time

    ES = Early start time.

    Earliest start : Denoted as ESEarliest start time is the earliest possible time by which the activity can be started.Early finish time : Denoted as EFEarly finish time is the earliest possible time by which the activity can be completed.

    Latest start time : Denoted as LS

    Latest start time is the latest possible time by which the activity can be startedLate finish time : Denoted as LSLate finish time is the latest possible time by which the activity can be completed

    Total float (TF) / Total slack (TS)Total float of the job is the differences between its Late start and Early start or Latefinish and Early finishi.e.TF( CA) = LS (CA) - ES (CA)OrTF( CA) = LF (CA) - EF (CA)CA = Current activity

    Free float (FF)Free float is the amount of time a job can be delayed without affecting the Early starttime of any other job.FF(CA) = ES(SA) EF (CA)CA = Current ActivitySA = Succeeding Activity

    Independent Float (IF)Independent Float is the amount of time that can be delayed without affecting eitherpredecessor or successor activities.IF = ES(SA) LF(PA) - Duration of CAES = Early StartLF = Late FinishSA = Succeeding ActivityPA = Preceding ActivityCA = Current Activity

    14

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    15/67

    Example 1Construct the Network for the followingProject and determine the followingi) Critical Pathii) ES,EF,LS,LF

    iii) TF,FF

    Activity Duration

    1-2 14

    1-4 3

    2-3 7

    2-4 0

    3-5 4

    4-5 3

    5-6 10

    Construction of t

    15

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    16/67

    (11)

    Determination

    DurationActivity

    16

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    17/67

    Example 2Construct the Network for the followingProject and determine the followingi) Critical Path

    ii) ES,EF,LS,LFiii) TF,FF

    Activity Duration

    1-2 2

    2-3 3

    2-4 5

    3-5 4

    3-6 1

    4-6 6

    4-7 2

    5-8 8

    6-8 7

    7-8 4

    17

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    18/67

    21-2

    DurationActivity

    In PERT model, 3 time values are associated

    with each activity. They arei) Optimistic time = to

    ii) Pessimistic time = tpiii) Most likely time = tm

    These three times provide a measure of uncertainty associated with that activity

    Optimistic Time: This is the shortest possible time in which the activity can be finished.It assumes that every thing goes well.Pessimistic Time: This is the longest time that an activity could take. It assumes thatevery thing goes wrong.Most likely Time: It is the estimate of the normal time that an activity would take. This

    assumes normal delays.

    Expected Time ( te):te can be calculated by the following formulate = (to + 4tm + tp) / 6

    Example.If a job has to = 5 days, tp = 17 days, tm = 8 daysThen Expected time for the job would be

    18

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    19/67

    te = (to + 4tm + tp) / 6= (5 + 4 x 8 + 17) / 6= 9 days

    Variability of activity times Standard deviation and Variance are commonly used in statistics to measure the

    variability of number.In PERT model, to measure the variability of an activity time duration standard deviationand variance are used.A large standard deviation represents high variability and vice-versa.

    Calculation of Standard Deviation and VarianceVariance = (Standard deviation )2Standard deviation =(t p t o) / 6

    Expected length of the Critical Path = te of all the activities along the Critical Path

    Probability of completing the project within a given date

    Z = (TS TE ) / Where TS = Scheduled time for project completionTE = Expected time for the project completion = Standard deviation for the Network

    Network = Sum of variances along theCritical Path

    = ( i-j )2Where i-j is the variance of a activity i-j along the critical path

    Example 1Construct the Network for the following project andcalculate the probability of completing the project in 25 days

    Activity to tm tp

    1-2 2 6 10

    1-3 4 8 12

    2-3 2 4 6

    2-4 2 3 4

    3-4 0 0 0

    3-5 3 6 9

    4-6 6 10 14

    5-6 1 3 5

    19

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    20/67

    1.Constructio

    2. Calculation o

    20

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    21/67

    3. Determinati

    Activity to tm tp Criticalactivities

    2 = ((t p t o) / 6)2

    1-2 2 6 10 1-2 1.78

    1-3 4 8 12 -

    2-3 2 4 6 2-3 0.44

    2-4 2 3 4 -

    3-4 0 0 0 3-4 0

    3-5 3 6 9 -

    4-6 6 10 14 4-6 1.78

    5-6 1 3 5 -

    2= 4.00

    Network = Sum of variances along theCritical Path

    = (Network )2

    21

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    22/67

    = 4= 2

    Probability of completing the project within a given dateZ = (TS TE ) / Where TS = Scheduled time for project completion

    TE = Expected time for the project completion = Standard deviation for the Network= (25 20) / 2= + 2.5

    From the Normal distribution Table, we get the probability of completing the project in25 days is 99.4%

    Example 2.The following table lists the jobs of a network along with theirtime estimates.

    Activity to tm tp

    1-4 3 9 27

    1-3 3 6 15

    1-2 6 12 30

    4-5 1 4 07

    3-5 3 9 27

    3-6 2 5 085-6 6 12 30

    2-6 4 19 28

    a) Draw the project network.b) What is the probability that the job will be completed in 35 days?c) What due date has 90% chance of being met?

    22

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    23/67

    1.Construction

    2. Calculation

    23

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    24/67

    3. Determinati

    As there are two Critical Paths, the path which gives more variance(2) is taken asCritical Path

    Path AActivity 2 = ((t p t o) / 6)2 2

    1-2 ((30 6)/6)2 16

    2-6 ((28 4)/6)2 16

    2 = 32.00

    Path B Activity 2 = ((t p t o) / 6)2 2

    1-3 ((15 3)/6)2 4

    3-5 ((27 3)/6)2 16

    5-6 ((30 6)/6)2 16

    2= 36.00

    24

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    25/67

    = 2 = 36 = 6

    Therefore the Critical Path is 1 - 3 - 5 - 6

    b)Probability of completing the project within a given dateZ = (TS TE ) / Where TS = Scheduled time for project completion

    TE = Expected time for the project completion = Standard deviation for the Network

    = (35 32) / 6= + 0.5

    From the Normal distribution Table, we get the probability of completing the project in35 days is 69.15%

    c)The due date for 90% chance of being met.Probability of completing the project within a given dateZ = (TS TE ) / The value of Z from the table for a 90% probability is +1.28TS = ? (to be calculated) ,TE = 32, = 6i.e. 1.28 = (TS 32) / 6TS = 39.68 days

    CPM ModelIn 1958 Du Pont Company used a technique called Critical Path Method (CPM) toschedule and control a very large project like overhauling of a chemical plant, there byreducing the shutdown period from 130hrs to 90 hrs saving the company 1 million dollar.Both of these techniques are referred to as project scheduling techniques.

    Cost considerations in PERT / CPMThe total cost of any project comprises of two costs.

    Direct cost - material cost, manpower loading Indirect cost - overheads such as managerial services, equipment rent, building

    rent etc.

    25

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    26/67

    t

    Example 1.

    26

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    27/67

    Find the lowest cost and optimum cost schedule for the following project, given the overhead expenses as Rs.45/-day.

    Activity Normal duration Crash

    duration

    Cost of crashing

    per day

    1-2 3 1 Rs.40

    2-3 4 2 Rs.40

    2-4 7 3 Rs.10

    3-4 5 2 Rs.20

    1.Constructio

    27

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    28/67

    1.Determinati

    13 -1

    Step 1.

    28

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    29/67

    1

    3 -1

    Step 2.

    13 -1

    Step 3.

    29

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    30/67

    1

    3 -1

    Step 3.

    30

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    31/67

    1

    1 -1

    Step 4.

    13 -1

    Step 5.

    31

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    32/67

    SIMULATION

    Simulation is to imitate reality to represent reality.

    Simulation is a technique for conducting experiments

    Simulation is descriptive and not optimizing technique

    Simulation is a process often consists of repetition of an experiment in many, many times

    to obtain an estimate of the overall effect of certain actions.

    Simulation is usually called for only when the problem under investigation is too

    complex to be treated by analytical models or by numerical optimization techniques.

    In a simulation, a given system is copied and the variables and constants associated with

    it are manipulated in that artificial environment to examine the behaviour of the system.

    In general terms, Simulation involves developing a model of some real life phenomenon

    and then performing experiments on the model evolved.

    Often we do not find a mathematical technique that; a model once constructed may

    permit us to predict what will be the consequences of taking a certain action. In particular

    we could experiment on the model by trying alternative actions or parameters and

    compare their consequences. This experimentation allow us to answer what if

    questions relating the effects of your assumption on the model response.

    The availability of the computers makes it possible for us to deal with an extraordinary

    large quantity of details which can be incorporated into a model and the ability to

    manipulate the model over many experiments (i.e. replicating all the possibilities that

    may be imbedded in the external world and events would seem to recur).

    For example,

    Testing of an aircraft model in a wind tunnel to test the aerodynamic properties of

    an the model

    A model of a traffic signal system

    Military war games

    Business games for training

    Planetarium etc.

    32

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    33/67

    Simulation defined

    A simulation of a system or an organism is the operation of a model or simulator which is

    a representation of the system or organism. The model is amenable to manipulation

    which would be impossible, too expensive or unpractical to perform on the entity it

    portrays. The operation of the model can be studied and for it, properties concerning the

    behaviour of the actual system can be inferred.

    -Shubik

    Simulation is the process of designing a model of a real system and conducting the

    experiments with this model for the purpose of understanding the behaviour (within the

    limits imposed by a criterion or set of criterion) for the operation of the system.

    - Shannon

    Steps of Simulation processStep 1: Identify the problem.

    If an inventory system is being simulated, then the problem may concern the

    determination of the size of the order (number of units to be ordered) when the inventory

    falls up to the reorder level (point).

    Step 2: Identify the decision variables, performance criterion (objective) and the decision

    rules.

    In the context of the above defined inventory problem, the demand (consumption rate),

    lead time and safety stock are identified as the decision variable. These variables shall be

    responsible to measure the performance of the system in terms of total inventory cost

    under the decision rule- when to order.

    Step 3: Construct a numerical model.

    Numerical model is constructed to be analyzed on the computer. Some times the model is

    written in a particular simulation language which is suited for the problem under the

    analysis.

    Step 4: Validate the model

    Validation is necessary to ensure whether it is truly representing the system being

    analyzed and the results will be reliable.

    Step 5: Design the experiments

    33

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    34/67

    Conduct experiments with the simulation model by listing specific values of variables to

    be tested (i.e. list courses of action for testing) at each trail (run).

    Step 6: Run the simulation model.

    Run the model on the computer to get the results in form of operating characteristics.

    Step 7: Examine the results.

    Examine the results of the problem as well as their reliability and correctness. If the

    simulation is complete, then select the best course of action (or alternative) otherwise

    make the desired changes in the model decision variables, parameters or design and

    return to step 3.

    Advantages of simulation

    1. Simulation is a straight forward and simple technique

    2. The technique is very useful to analyze large and complex problems which are notamenable to mathematical or quantitative methods.

    3. It is an interactive method, which enables the decision maker to study the changes and

    their effects on the performance of the system.

    4. The experiments in a simulation are run on the model and not on the system itself.

    Limitations of simulation

    1. At times simulation models can be very costly and expensive

    2. It is trail and error technique to produce different solutions in repeated runs.

    3. The solution obtained from the simulation may not be optimal.

    4. The simulation model needs to be examined and analyzed for decision making. It only

    creates an alternative and not an optimal solution by itself.

    Monte-Carlo techniques or Monte-Carlo simulation.

    The Monte-Carlo method is a simulation technique in which statistical distribution

    functions are created by using series of random numbers

    Random numbers.

    The underlying theory in random number is that, each number has an equal opportunity

    of being selected.

    34

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    35/67

    There are various ways in which random numbers may be generated. These could be:

    result of some device like coin or die; published table of random numbers, mid-square

    method, or some other sophisticated method.

    It may be mentioned here that random numbers generated by some method may not be

    really random in nature. In fact such numbers are called pseudo-random-numbers.

    Rand corporation (of USA): A million random digits, is a random number table used in

    simulation situations. The numbers in these tables are in random arrangement.

    The Monte-Carlo simulation technique consists of the following steps.

    1. Setting up a probability distribution for variables to be analyzed.

    2. Building a cumulative probability distribution for each random variable.

    3. Generating random numbers. Assign an appropriate set of random numbers to

    represent value or range (interval) of values for each random variable.4. Conduct the simulation experiment by means of random sampling

    5. Repeat Step 4 until the required number of simulation runs has been generated.

    6. Design and implement a course of action and maintain control.

    Example 1.

    A bakery keeps stock of popular brand of cake. Previous experience shows the daily

    demand pattern for the item with associated probabilities, as given below:

    Daily demand(number) 0 10 20 30 40 50Probability 0.01 0.20 0.15 0.50 0.12 0.02

    Use the following sequence of random numbers to simulate the demand for next 10 days.

    Random Numbers 40 19 87 83 73 84 29 09 02 20

    Also estimate the daily average demand for the cakes on the basis of simulated data.

    Solution:

    Using the daily demand distribution, we obtain a probability distribution as shown in the

    following Table.

    Daily demand distribution

    35

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    36/67

    Daily Demand Probability Cumulative Probability Random Number Interval0 0.01 0.01 0010 0.20 0.21 01-2020 0.15 0.36 21-3530 0.50 0.86 36-85

    40 0.12 0.98 86-9750 0.02 1.00 98-99

    By conducting the simulation experiment for demand by taking a sample of 10 random

    numbers from the table of random numbers we get,

    Days Random Number Demand1 40 30 Because 0.36 < 0.40 < 0.852 19 10 Because 0.01 < 0.19 < 0.203 87 40 and so on

    4 83 305 73 306 84 307 29 208 09 109 02 1010 20 10

    Total = 220

    Expected demand = 220/10 = 22 units per day.

    Example 2.

    XYZ spare parts company wishes to determine the level of stock it should carry for items

    in its range. Demand is not certain and there is a lead time for stock replenishment. For

    one item X, the following information is obtained.

    Demand

    (Units/day)

    3 4 5 6 7

    36

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    37/67

    Probability 0.10 0.20 0.30 0.30 0.10Carrying

    cost(Per unit

    per day)

    Rs.2

    Orderingcost(per

    order)

    Rs.50

    Lead time for

    replenishment

    3 days

    Stock on hand at the beginning of the simulation exercise was 20 units.

    Carry out a simulation run over a period of 10 days with the objective of evaluating the

    inventory rule:

    Order 15 units when present inventory plus outstanding falls below 15 units.The sequence of random numbers to be used is :0,9,1,1,5,1,8,6,3,5,7,1,1,2,9 using the

    first number for day one.

    Solution:

    Let us begin the simulation by assuming that

    i) orders are placed at the end of the day and received after 3 days at the end of the day.

    ii) back orders are accumulated in case of short supply and are supplied when stock is

    available.

    The cumulative probability distribution and the random number range for daily demand is

    shown in the table.

    Daily Demand Distribution

    Daily Demand Probability Cumulative

    Probability

    Random Number

    Range

    3 0.10 0.10 004 0.20 0.30 01-025 0.30 0.60 03-056 0.30 0.90 06-087 0.10 1.00 09The results of the simulation experiment conducted are as shown below.

    Days Opening Random Resulting Closing Order Order Average stock

    37

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    38/67

    Stock Number Demand Stock Placed Delivered in the evening1 20 0 3 17 - - 18.52 17 9 7 10 15 - 13.53 10 1 4 6 - - 84 6 1 4 2 - - 4

    5 2 5 5 0(-3)* 15 15 16 12 1 4 8 - - 107 8 8 6 2 - - 58 2 6 6 0(-4)* 15 15 19 11 3 5 6 - - 8.5

    10 6 5 5 1 - - 3.5*Negative figure indicates back orders.

    Average ending stock = 73/10 = 7.3 units/day

    Daily ordering cost = (Cost of placing one order) x (Number of orders placed per

    day)= 50 x 0.3 = Rs.15

    Daily carrying cost = (Cost of carrying one unit per day) x (Average ending stock)

    = 2 x 7.3 = Rs.14.6

    Total daily inventory cost = Daily ordering cost + Daily carrying cost

    = 15 + 14.6

    = Rs.29.6

    Example 3.

    A small retailer deals in a perishable commodity, the daily demand and supply of which

    are random variables. The past 500 days data show the following:

    Supply DemandAvailable ( kg ) Number of Days Demand (kg ) Number of Days

    10 40 10 5020 50 20 11030 190 30 20040 150 40 10050 70 50 40

    The retailer buys the commodity at Rs.20 per kg and sells at Rs.30 per kg. If anycommodity remains at the end the day it has no resale value and is a dead loss. Moreover,

    the loss on any unsatisfied demand is Rs.8 per kg

    Given the following random numbers. Simulate six day sales.

    31 18 63 84 15 79 07 32 43 75 81 27

    38

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    39/67

    Using the random numbers alternatively, for example, first pair (31) to simulate supply

    and second pair (18) to simulate demand, etc.

    Solution:

    Probability and Random Number Interval for Daily Demand and Supply

    Available

    (kg)

    Probability Random

    Number

    Demand

    (kg)

    Probability Random

    Number10 40/500=0.08 00-07 10 50/500=0.10 00-0920 50/500=0.10 08-17 20 110/500=0.22 10-3130 190/500=0.38 18-55 30 200/500=0.40 32-7140 150/500=0.30 56-85 40 100/500=0.20 72-9150 70/500=0.14 85-99 50 40/500=0.08 92-99

    Simulation Experimentation Sheet

    Day Random

    Number

    Supply

    (kg)

    Random

    Number

    Demand

    (kg)

    Cost

    (Rs)

    Revenue

    (Rs)

    Shortage

    (Loss)

    Profit

    1 31 30 18 20 600 600 - -2 63 40 84 40 800 1,200 - 4003 15 20 79 40 400 600 160 404 07 10 32 30 200 300 160 -605 43 30 75 40 600 900 80 2206 81 40 27 20 800 600 - -200

    The above table shows that during these six days period retailer makes a net profit

    of Rs.400.

    Example 4.

    A sample of 100 arrivals of a customer at a retail sales depot is according to the following

    distribution.

    Time between arrival(Minutes) Frequency0.5 21.0 61.5 102.0 252.5 20

    39

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    40/67

    3.0 143.5 104.0 74.5 45.0 2

    A study of the time required to service customers by adding up the bills, receiving

    payments and placing packages, yields the following distribution

    Time between service(Minutes) Frequency0.5 121.0 211.5 362.0 192.5 73.0 5

    Estimate the average percentage of customer waiting time and average percentage of idle

    time of the server by simulation for the next 10 arrivals.

    Solution:Arrival

    Arrivals Frequency Probability Cumulative

    Probability

    Random No.

    Interval

    0.5 2 0.02 0.02 00-01

    1.0 6 0.06 0.08 02-07

    1.5 10 0.10 0.18 08-17

    2.0 25 0.25 0.43 18-42

    2.5 20 0.20 0.63 43-62

    3.0 14 0.14 0.77 63-76

    3.5 10 0.10 0.87 77-86

    4.0 7 0.07 0.94 87-93

    4.5 4 0.04 0.98 94-97

    40

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    41/67

    5.0 2 0.02 1.00 98-99

    Service

    Time between

    service(Minutes)

    Frequency Probability Cumulative

    Probability

    Random No.

    Interval

    0.5 12 0.12 0.12 00-11

    1.0 21 0.21 0.33 12-32

    1.5 36 0.36 0.69 33-68

    2.0 19 0.19 0.88 69-872.5 7 0.07 0.95 88-94

    3.0 5 0.05 1.00 95-99

    Arrival

    No.

    Random

    No.

    Inter

    Arrival

    Time

    (Mins.)

    Arrival

    Time

    (Mins)

    Random

    No.

    Service

    Time

    (Mins)

    Service

    Start

    Service

    End

    Wt.time

    of the

    end

    customer

    Wt.time

    of the

    Server

    1 93 4.0 4.0 78 2.0 4 6 - 4.02 22 2.0 6.0 76 2.0 6 8 - -3 53 2.5 8.5 58 1.5 8.5 10.0 - 0.54 64 3.0 11.5 54 1.5 11.5 13 - 1.55 39 2.0 13.5 74 2.0 13.5 15.5 - 0.56 07 1.0 14.5 92 2.5 15.5 18 1.0 -7 10 1.5 16.0 38 1.5 18.0 19.5 2.0 -8 63 3.0 19.0 70 2.0 19.5 21.5 0.5 -9 76 3.0 22.0 96 3.0 22.0 25.0 - 0.510 35 2.0 24.0 92 2.5 25.0 27.5 1.0 -

    Total 4.5 7.0

    Average waiting time per customer is 4.5/10 = 0.45 minutes

    Average waiting time or idle time of the server = 7.0/10 = 0.7 minutes.

    41

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    42/67

    Example 5.

    A tourist car operator finds that during the past few months the cars use has varied so

    much that the cost of maintaining the car varied considerably. During the past 200 days

    the demand for the car fluctuated as below.

    Trips per week Frequency0 161 242 303 604 405 30

    Using the random numbers simulate the demand for a 10 week period.

    Solution:

    Trips per

    week/

    Demand per

    week

    Frequency Probability Cumulative

    Probability

    Random

    Number

    Interval

    0 16 0.08 0.08 00-071 24 0.12 0.20 08-192 30 0.15 0.35 20-343 60 0.30 0.65 35-644 40 0.20 0.85 65-845 30 0.15 1.00 85-99

    The simulated demand for the cars for the next 10 weeks period is given in the table

    below

    42

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    43/67

    Week Random Number Demand1 82 42 96 53 18 14 96 55 20 26 84 47 56 38 11 19 52 310 03 0

    Total 28

    Average Demand = 28/10 = 2.8 cars per week

    Example 6.

    An automobile production line turns out about 100 cars a day, but deviations occur owing

    to many causes. The production is more accurately described by the probability

    distribution given below.

    Production per day Probability95 0.03

    43

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    44/67

    96 0.0597 0.0798 0.1099 0.15100 0.20

    101 0.15102 0.10103 0.07104 0.05105 0.03

    Finished cars are transported across the bay at the end of each day by the ferry. If the

    ferry has space for only 101 cars, what will be the average numbers of waiting to be

    shipped and what will be the average number of empty space on the ship?

    Solution:

    Production per day Probability CumulativeProbability

    Random NumberInterval

    95 0.03 0.03 00-0296 0.05 0.08 03-0797 0.07 0.15 08-1498 0.10 0.25 15-2499 0.15 0.40 25-39100 0.20 0.60 40-59101 0.15 0.75 60-74102 0.10 0.85 75-84

    103 0.07 0.92 85-91104 0.05 0.97 92-96105 0.03 1.00 97-99

    The simulated production of cars for the next 15 days is given in the following table.

    Day Random

    Number

    Production per

    day

    No. of cars

    waiting

    No. of empty

    space in the

    ship1 97 105 4 -

    2 02 95 - 63 80 102 1 -4 66 101 - -5 96 104 3 -6 55 100 - 17 50 100 - 18 29 99 - 29 58 100 - 1

    44

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    45/67

    10 51 100 - 111 04 96 - 512 86 103 2 -13 24 98 - 314 39 99 - 2

    15 47 100 - 1Total 10 23

    Average number of cars waiting to be shipped = 10/15 = 0.67 per day

    Average number of empty space on the ship = 23/15 = 1.53 per day

    Example 7.

    A company manufactures 30 units per product. The sale of these items depends upon

    demand which has the following distribution.

    Sale (units) Probability27 0.1028 0.1529 0.2030 0.35

    31 0.1532 0.05

    The production cost and sale price of each unit are Rs.40 and Rs.50 respectively. Any

    unsold product is to be disposed off at a loss of Rs.15 per unit. There is a penalty of Rs.5

    per unit if the demand is not met. Using the following random numbers, estimate the total

    profit/loss for the company for the next 10 days.

    Random Numbers: 10, 99, 65,99,95,01,79,11,16 and 20.

    If the company decides to produce 29 units per day, what is the advantage ordisadvantage to the company?

    Sale (units) Probability Cumulative

    Probability

    Random Number

    Interval27 0.10 0.10 00-0928 0.15 0.25 10-24

    45

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    46/67

    29 0.20 0.45 25-4430 0.35 0.80 45-7931 0.15 0.95 80-9432 0.05 1.00 95-99

    Set up the simulation for next 10 days

    Day Random

    Number

    Simulated

    Sales

    Number of

    units Unsold

    Number of

    units short1 10 28 30-28=2 02 99 32 0 32-30=23 65 30 0 04 99 32 0 25 95 32 0 26 01 27 30-27=3 07 79 30 0 08 11 28 30-28=2 09 16 28 2 0

    10 20 28 2 0Total 11 6

    At the production rate of 30 per day, total number of units produced in 10 days = 30 X 10

    = 300 Nos, since the production cost is Rs.40 and the sales price is Rs.50, the per unit

    profit is Rs.10

    Day Demand Actual Sales Profit on

    Actual sales

    Loss due to

    the unsold

    units

    Loss due to

    penalty for

    shortage

    1 10 28 280 2 X 15 = 30 -2 99 30 300 - 2 X 5 = 103 65 30 300 - -4 99 30 300 - 2 X 5 = 105 95 30 300 - 2 X 5 = 106 01 27 270 3 X 15 = 45 07 79 30 300 0 0

    46

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    47/67

    8 11 28 280 2 X 15 = 30 09 16 28 280 2 X 15 = 30 010 20 28 280 2 X 15 = 30 0

    289 Rs.2890 Rs.165 Rs.30

    (a) Total profit for next 10 days when production is 30 units per day = (2890) (165 +30)

    = 2890-195

    = 2695

    (b) If the company decides to produce 29 units per day. The calculation of profit and loss

    is as shown below.

    Day Demand Production

    units

    Actual

    Sales

    Profit on

    Actual

    sales

    Loss due to

    the unsold

    units

    Loss due to

    penalty for

    shortage1 28 29 28 280 1 X 15 = 15 02 32 29 29 290 0 3 X 5= 153 30 29 29 290 0 1 X 5 = 54 32 29 29 290 0 3 X 5= 155 32 29 29 290 0 3 X 5= 156 27 29 27 270 1 X 15 = 15 07 30 29 29 290 0 1 X 5 = 58 28 29 28 280 1 X 15 = 15 09 28 29 28 280 1 X 15 = 15 010 28 29 28 280 1 X 15 = 15 0

    Total 284 Rs.2840 Rs.90 Rs.55

    Total profit for next 10 days when production is 29 units per day = (2840) (90 + 55)

    = Rs.2695

    Since the profit is same for both the cases there is no disadvantage to the company.

    47

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    48/67

    Linear Programming Problems Formulation

    Linear Programming is a mathematical technique for optimum allocation of limited orscarce resources, such as labour, material, machine, money, energy and so on , to several

    competing activities such as products, services, jobs and so on, on the basis of a givencriteria of optimality.

    The term Linear is used to describe the proportionate relationship of two or morevariables in a model. The given change in one variable will always cause a resultingproportional change in another variable.

    The word , programming is used to specify a sort of planning that involves theeconomic allocation of limited resources by adopting a particular course of action orstrategy among various alternatives strategies to achieve the desired objective.

    Hence, Linear Programming is a mathematical technique for optimum allocation oflimited or scarce resources, such as labour, material, machine, money energy etc.

    Structure of Linear Programming model.

    The general structure of the Linear Programming model essentially consistsof three components.

    i) The activities (variables) and their relationshipsii) The objective function andiii) The constraints

    The activities are represented by X1, X2, X3 ..Xn.

    These are known as Decision variables.The objective function of an LPP (Linear Programming Problem) is a mathematicalrepresentation of the objective in terms a measurable quantity such as profit, cost,revenue, etc.

    Optimize (Maximize or Minimize) Z=C1X1 +C2X2+ ..Cn Xn

    Where Z is the measure of performance variable

    X1, X2, X3, X4..Xn are the decision variables

    And C1, C2, Cn are the parameters that give contribution to decision variables.The constraints These are the set of linear inequalities and/or equalities which imposerestriction of the limited resources

    48

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    49/67

    Assumptions of Linear Programming

    Certainty.

    In all LP models it is assumed that, all the model parameters such as availability ofresources, profit (or cost) contribution of a unit of decision variable and consumption ofresources by a unit of decision variable must be known and constant.

    Divisibility (Continuity)The solution values of decision variables and resources are assumed to have either wholenumbers (integers) or mixed numbers (integer or fractional). However, if only integervariables are desired, then Integer programming method may be employed.

    Additivity

    The value of the objective function for the given value of decision variables and the totalsum of resources used, must be equal to the sum of the contributions (Profit or Cost)earned from each decision variable and sum of the resources used by each decisionvariable respectively. /The objective function is the direct sum of the individualcontributions of the different variables

    LinearityAll relationships in the LP model (i.e. in both objective function and constraints) must belinear.

    General Mathematical Model of an LPP

    Optimize (Maximize or Minimize) Z=C1 X1 + C2 X2 ++CnXnSubject to constraints,

    a11X1+ a 12X2++ a 1nXn () b1

    a21X1+ a 22X2++ a 2nXn () b2

    a31X1+ a 32X2++ a 3nXn () b3

    am1X1+ a m2X2++ a mnXn () bmand X1, X2 .Xn >

    Guidelines for formulating Linear Programming model

    i) Identify and define the decision variable of the problemii) Define the objective functioniii) State the constraints to which the objective function should be optimized(i.e. Maximization or Minimization)iv) Add the non-negative constraints from the consideration that the negative values of

    the decision variables do not have any valid physical interpretation

    49

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    50/67

    Example 1.A manufacturer produces two types of models M1 and M2.Each model of the type M1requires 4 hours of grinding and 2 hours of polishing; where as each model of M2requires 2 hours of grinding and 5 hours of polishing. The manufacturer has 2 grindersand 3 polishers. Each grinder works for 40 hours a week and each polisher works 60

    hours a week. Profit on M1 model is Rs.3.00 and on model M2 is Rs.4.00.Whateverproduced in a week is sold in the market. How should the manufacturer allocate hisproduction capacity to the two types of models, so that he makes maximum profit in aweek?

    i) Identify and define the decision variable of the problemLet X1 and X2 be the number of units of M1 and M2 model.

    ii) Define the objective functionSince the profits on both the models are given, the objective functionis to maximize the profit.Max Z = 3X1 + 4X2

    iii) State the constraints to which the objective function should be optimized (i.e.Maximization or Minimization)There are two constraints one for grinding and the other for polishing.The grinding constraint is given by4X1 + 2X2 < 80No of hours available on grinding machine per week is 40 hrs. There are two grinders.Hence the total grinding hour available is 40 X 2 = 80 hours.The polishing constraint is given by2X1 + 5X2 < 180No of hours available on polishing machine per week is 60 hrs. There are three grinders.Hence the total grinding hour available is 60 X 3 = 180 hours.

    Finally we have,

    Max Z = 3X1 + 4X2

    Subject to constraints,

    4X1 + 2X2 < 80

    2X1 + 5X2 < 180

    X1, X2 > 0

    Example 2.A firm is engaged in producing two products. A and B. Each unit of product A requires 2kg of raw material and 4 labour hours for processing, where as each unit of B requires 3kg of raw materials and 3 labour hours for the same type. Every week, the firm has anavailability of 60 kg of raw material and 96 labour hours. One unit of product A soldyields Rs.40 and one unit of product B sold gives Rs.35 as profit.

    50

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    51/67

    Formulate this as an Linear Programming Problem to determine as to how many units ofeach of the products should be produced per week so that the firm can earn maximumprofit.

    i) Identify and define the decision variable of the problem

    Let X1 and X2 be the number of units of product A and product B produced per week.ii) Define the objective functionSince the profits of both the products are given,the objective function is to maximize the profit.MaxZ = 40X1 + 35X2

    iii) State the constraints to which the objective function should be optimized (i.e.Maximization or Minimization)There are two constraints one is raw material constraint and the other one is labourconstraint..The raw material constraint is given by

    2X1 + 3X2 < 60The labour hours constraint is given by4X1 + 3X2 < 96

    Finally we have,MaxZ = 40X1 + 35X2Subject to constraints,2X1 + 3X2 < 604X1 + 3X2 < 96X1,X2 > 0

    Example 3.The agricultural research institute suggested the farmer to spread out atleast 4800 kg ofspecial phosphate fertilizer and not less than 7200 kg of a special nitrogen fertilizer toraise the productivity of crops in his fields. There are two sources for obtaining these mixtures A and mixtures B. Both of these are available in bags weighing 100kg each andthey cost Rs.40 and Rs.24 respectively. Mixture A contains phosphate and nitrogenequivalent of 20kg and 80 kg respectively, while mixture B contains these ingredientsequivalent of 50 kg each. Write this as an LPP and determine how many bags of eachtype the farmer should buy in order to obtain the required fertilizer at minimum cost.

    i) Identify and define the decision variable of the problemLet X1 and X2 be the number of bags of mixture A and mixture B.ii) Define the objective functionThe cost of mixture A and mixture B are given ;the objective function is to minimize the costMin.Z = 40X1 + 24X2

    iii) State the constraints to which the objective function should be optimized.The above objective function is subjected to following constraints.

    51

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    52/67

    20X1 + 50X2 >4800 Phosphate requirement80X1 + 50X2 >7200 Nitrogen requirementX1, X2 >0

    Finally we have,

    Min.Z = 40X1 + 24X2is subjected to three constraints20X1 + 50X2 >480080X1 + 50X2 >7200X1, X2 >0

    Example 4.A firm can produce 3 types of cloth, A , B and C.3 kinds of wool are required Red, Greenand Blue.1 unit of length of type A cloth needs 2 meters of red wool and 3 meters of blue

    wool.1 unit of length of type B cloth needs 3 meters of red wool, 2 meters of green wooland 2 meters of blue wool.1 unit type of C cloth needs 5 meters of green wool and 4meters of blue wool. The firm has a stock of 8 meters of red, 10 meters of green and 15meters of blue. It is assumed that the income obtained from 1 unit of type A is Rs.3, fromB is Rs.5 and from C is Rs.4.Formulate this as an LPP.( December2005/January 2006)

    i) Identify and define the decision variable of the problemLet X1, X2 and X3 are the quantity produced of cloth type A,B and C respectively.ii) Define the objective functionThe incomes obtained for all the three types of cloths are given; the objective function isto maximize the income.Max Z = 3X1 + 5X2 + 4X3iii) State the constraints to which the objective function should be optimized.The above objective function is subjected to following three constraints.2X1 + 3X2 < 8

    2X2 + 5X3 < 103X1 + 2X2 + 4X3 < 15X1, X2 X3 >0

    Finally we have,Max Z = 3X1 + 5X2 + 4X3is subjected to three constraints2X1 + 3X2 < 82X2 + 5X3 < 103X1 + 2X2 + 4X3 < 15X1, X2 X3 >0

    52

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    53/67

    Example 5.A Retired person wants to invest upto an amount of Rs.30,000 in fixed income securities.His broker recommends investing in two Bonds: Bond A yielding 7% and Bond Byielding 10%. After some consideration, he decides to invest at most of Rs.12,000 inbond B and atleast Rs.6,000 in Bond A. He also wants the amount invested in Bond A to

    be atleast equal to the amount invested in Bond B. What should the broker recommend ifthe investor wants to maximize his return on investment? Solve graphically.(January/February 2004)

    i) Identify and define the decision variable of the problemLet X1 and X2 be the amount invested in Bonds A and B.ii) Define the objective functionYielding for investment from two Bonds are given; the objective function is to maximizethe yielding.Max Z = 0.07X1 + 0.1X2

    iii) State the constraints to which the objective function should be optimized.

    The above objective function is subjected to following three constraints.X1 + X2 < 30,000X1 > 6,000X2 < 12,000X1 -- X2 >0X1, X2 >0

    Finally we have,MaxZ = 0.07X1 + 0.1X2is subjected to three constraintsX1 + X2 < 30,000X1 > 6,000X2 < 12,000X1 -- X2 >0X1, X2 >0

    Minimization problems

    Example 5.A person requires 10, 12, and 12 units chemicals A, B and C respectively for his garden.A liquid product contains 5, 2 and 1 units of A,B and C respectively per jar. A dryproduct contains 1,2 and 4 units of A,B and C per carton.If the liquid product sells for Rs.3 per jar and the dry product sells for Rs.2 per carton,how many of each should be purchased, in order to minimize the cost and meet therequirements?

    i) Identify and define the decision variable of the problemLet X1 and X2 be the number of units of liquid and dry products.ii) Define the objective functionThe cost of Liquid and Dry products are given ; the objective function is to minimize thecost

    53

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    54/67

    Min. Z = 3X1 + 2X2iii) State the constraints to which the objective function should be optimized.The above objective function is subjected to following three constraints.5X1 + X2 >102X1 + 2X2 >12

    X1 + 4X2 >12X1, X2 >0

    Finally we have,Min. Z = 3X1 + 2X2is subjected to three constraints5X1 + X2 >102X1 + 2X2 >12X1 + 4X2 >12X1, X2 >0

    Example 6.A Scrap metal dealer has received a bulk order from a customer for a supply of atleast2000 kg of scrap metal. The consumer has specified that atleast 1000 kgs of the ordermust be high quality copper that can be melted easily and can be used to produce tubes.Further, the customer has specified that the order should not contain more than 200 kgsof scrap which are unfit for commercial purposes. The scrap metal dealer purchases thescrap from two different sources in an unlimited quantity with the following percentages(by weight) of high quality of copper and unfit scrap

    Source A Source B

    Copper 40% 75%

    Unfit Scrap 7.5% 10%

    The cost of metal purchased from source A and source B are Rs.12.50 and Rs.14.50 perkg respectively. Determine the optimum quantities of metal to be purchased from the twosources by the metal scrap dealer so as to minimize the total cost (February 2002)

    i) Identify and define the decision variable of the problemLet X1 and X2 be the quantities of metal to be purchased from the two sources A and B.ii) Define the objective functionThe cost of metal to be purchased by the metal scrap dealer are given;

    the objective function is to minimize the costMin. Z = 12.5X1 + 14.5X2iii) State the constraints to which the objective function should be optimized.The above objective function is subjected to following three constraints.X1 + X2 >2,000

    0.4X1 + 0.75X2 >1,0000.075X1 + 0.1X2 + 4X3 < 200X1, X2 >0

    54

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    55/67

    Finally we have,Min. Z = 12.5X1 + 14.5X2is subjected to three constraintsX1 + X2 >2,0000.4X1 + 0.75X2 >1,000

    0.075X1 + 0.1X2 + 4X3 < 200X1, X2 >0

    Example 7.A farmer has a 100 acre farm. He can sell all tomatoes, lettuce or radishes and can raisethe price to obtain Rs.1.00 per kg. for tomatoes , Rs.0.75 a head for lettuce and Rs.2.00per kg for radishes. The average yield per acre is 2000kg.of tomatoes, 3000 heads oflettuce and 1000 kgs of radishes. Fertilizers are available at Rs.0.50 per kg and theamount required per acre is 100 kgs for each tomatoes and lettuce and 50kgs forradishes. Labour required for sowing, cultivating and harvesting per acre is 5 man-daysfor tomatoes and radishes and 6 man-days for lettuce. A total of 400 man-days of labour

    are available at Rs.20.00 per man-day. Formulate this problem as LP model to maximizethe farmers profit.

    i) Identify and define the decision variable of the problemLet X1 and X2 and X3 be number acres the farmer grows tomatoes, lettuce and radishesrespectively.ii) Define the objective functionThe objective of the given problem is to maximize the profit.

    The profit can be calculated by subtracting total expenditure from the total salesProfit = Total sales Total expenditure

    The farmer produces 2000X1 kgs of tomatoes, 3000X2 heads of lettuce, 1000X3 kgs ofradishes.Therefore the total sales of the farmer will be= Rs. (1 x 2000X1 + 0.75 x 3000X2 + 2 x 100X3)Total expenditure (fertilizer expenditure) will be= Rs.20 ( 5X1 + 6X2 + 5X3 )Farmers profit will beZ = (1 x 2000X1 + 0.75 x 3000X2 + 2 x 100X3) { [0.5 x 100 x X1+0.5 x 100 x X2 + 50X3]+ [20 x 5 x X1+20 x 6 x X2 + 20 x 5 x X3]}=1850X1 + 2080X2 + 1875X3

    Therefore the objective function isMaximise Z = 1850X1 + 2080X2 + 1875X3

    iii) State the constraints to which the objective function should be optimized.The above objective function is subjected to following constraints.Since the total area of the firm is 100 acresX1 + X2 + X3 < 100The total man-days labour is 400 man-days

    55

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    56/67

    5X1 + 6X2 + 5X3 < 400Finally we have,Maximise Z = 1850X1 + 2080X2 + 1875X3is subjected to three constraintsX1 + X2 + X3 < 100

    5X1 + 6X2 + 5X3 < 400X1, X2 X3 >0

    Example 8.An electronics company produces three types of parts for automatic washing machines .Itpurchases castings of the parts from a local foundry and then finishes the part on drilling,shaping and polishing machines. The selling prices of parts A, B, and C respectively areRs 8, Rs.10 and Rs.14.All parts made can be sold. Castings for parts A, B and Crespectively cost Rs.5, Rs.6 and Rs.10.The shop possesses only one of each type of machine. Cost per hour to run each of thethree machines are Rs.20 for drilling, Rs.30 for shaping and Rs.30 for polishing. The

    capacities (parts per hour) for each part on each machine are shown in the followingtable.

    MachineCapacities Per Hour

    Part A Part B Part C

    Drilling 25 40 25

    Shaping 25 20 20

    Polishing 40 30 40

    The management of the shop wants to know how many parts of each type itshould produce per hour in order to maximize profit for an hours run. Formulatethis problem as an LP model so as to maximize total profit to the company.

    i) Identify and define the decision variable of the problemLet X1 and X2 and X3 be the number of types A, B and C parts produced per hourrespectively .ii) Define the objective functionWith the information given, the hourly profit for part A, B, and C would be as followsProfit per type A part = (8 5) (20/25 +30/25 + 30/40) = 0.25Profit per type B part = (10 6) (20/40 + 30/20 + 30/30) = 1Profit per type C part = (14 10) (20/25 + 30/20 + 30/40) = 0.95Then,Maximize Z = 0.25 X1 + 1X2 + 0.95X3

    iii) State the constraints to which the objective function should be optimized.The above objective function is subjected to following constraints.

    56

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    57/67

    i) The drilling machine constraintX1/25 + X2/40 + X3/24 < 1ii) The shaping machine constraintX1/25 + X2/20 + X3/20 1iii) The polishing machine constraint

    X1/40 + X2/30 + X3/40 1X1, X2, X3 0

    Finally we have,Maximize Z = 0.25 X1 + 1X2 + 0.95X3Subject to constraintsX1/25 + X2/40 + X3/24 < 1ii) The shaping machine constraintX1/25 + X2/20 + X3/20 1iii) The polishing machine constraintX1/40 + X2/30 + X3/40 1

    X1, X2, X3 0Example 9.A city hospital has the following minimal daily requirements for nurses.

    PeriodClock time (24

    hours day)Minimum

    number of nursesrequired

    1 6 a.m. 10 a.m. 2

    2 10 a.m. 2 p.m. 7

    3 2 p.m. 6 p.m. 15

    4 6 p.m. 10 p.m. 85 10 p.m. 2 a.m. 20

    6 2 a.m. 6 a.m. 6

    Nurses report at the hospital at the beginning of each period and work for 8 consecutivehours. The hospital wants to determine the minimal number of nurses to be employed sothat there will be a sufficient number of nurses available for each period.Formulate this as a linear programming problem by setting up appropriate constraintsand objective function.

    i) Identify and define the decision variable of the problemLet X1, X2, X3, X4, X5 and X6 be the number of nurses joining duty at thebeginning of periods 1, 2, 3, 4, 5 and 6 respectively.

    ii) Define the objective functionMinimize Z = X1 + X2 + X3 + X4 + X5 + X6iii) State the constraints to which the objective function should be optimized.The above objective function is subjected to following constraints.X1 + X2 7

    57

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    58/67

    X2 + X3 15X3 + X4 8X4 + X5 20X5 + X6 6X6 + X1 2

    X1, X2, X3, X4, X5, X6 0

    Linear Programming: Graphical Solution

    Example 1.Solve the following LPP by graphical methodMaximize Z = 5X1 + 3X2Subject to constraints2X1 + X2 1000X1 400X1 700

    X1, X2 0Solution:

    The first constraint 2X1 + X2 1000 can be represented as follows.We set 2X1 + X2 = 1000When X1 = 0 in the above constraint, we get,2 x 0 + X2 = 1000X2 = 1000

    Similarly when X2 = 0 in the above constraint, we get,2X1 + 0 = 1000X1 = 1000/2 = 500The second constraint X1 400 can be represented as follows,We set X1 = 400The third constraint X2 700 can be represented as follows,We set X2 = 700

    58

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    59/67

    The constraints are shown plotted in the above figure

    Point X1 X2 Z = 5X1 +3X2

    0 0 0 0

    A 0 700 Z = 5 x 0 + 3 x 700 = 2,100

    B 150 700 Z = 5 x 150 + 3 x 700 = 2,850*Maximum

    C 400 200 Z = 5 x 400 + 3 x 200 = 2,600

    D 400 0 Z = 5 x 400 + 3 x 0 = 2,000

    The Maximum profit is at point BWhen X1 = 150 and X2 = 700Z = 2850

    Example 2.

    Solve the following LPP by graphical methodMaximize Z = 400X1 + 200X2Subject to constraints18X1 + 3X2 8009X1 + 4X2 600X2 150X1, X2 0

    Solution:

    The first constraint 18X1 + 3X2 800 can be represented as follows.We set 18X1 + 3X2 = 800

    When X1 = 0 in the above constraint, we get,18 x 0 + 3X2 = 800X2 = 800/3 = 266.67Similarly when X2 = 0 in the above constraint, we get,18X1 + 3 x 0 = 800X1 = 800/18 = 44.44

    The second constraint 9X1 + 4X2 600 can be represented as follows,We set 9X1 + 4X2 = 600When X1 = 0 in the above constraint, we get,9 x 0 + 4X2 = 600

    X2 = 600/4 = 150Similarly when X2 = 0 in the above constraint, we get,9X1 + 4 x 0 = 600X1 = 600/9 = 66.67The third constraint X2 150 can be represented as follows,We set X2 = 150

    59

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    60/67

    Point X1 X2 Z = 400X1 + 200X2

    0 0 0 0

    A 0 150Z = 400 x 0+ 200 x 150 = 30,000*

    MaximumB 31.11 80 Z = 400 x 31.1 + 200 x 80 = 28,444.4

    C 44.44 0 Z = 400 x 44.44 + 200 x 0 = 17,777.8

    The Maximum profit is at point AWhen X1 = 150 and X2 = 0

    Z = 30,000

    Example 3.Solve the following LPP by graphical methodMinimize Z = 20X1 + 40X2Subject to constraints36X1 + 6X2 1083X1 + 12X2 36

    20X1 + 10X2 100X1 X2 0

    Solution:

    The first constraint 36X1 + 6X2 108 can be represented as follows.We set 36X1 + 6X2 = 108When X1 = 0 in the above constraint, we get,36 x 0 + 6X2 = 108

    60

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    61/67

    X2 = 108/6 = 18Similarly when X2 = 0 in the above constraint, we get,36X1 + 6 x 0 = 108X1 = 108/36 = 3

    The second constraint3X1 + 12X2 36 can be represented as follows,We set 3X1 + 12X2 = 36When X1 = 0 in the above constraint, we get,3 x 0 + 12X2 = 36X2 = 36/12 = 3Similarly when X2 = 0 in the above constraint, we get,3X1 + 12 x 0 = 36X1 = 36/3 = 12

    The third constraint20X1 + 10X2 100 can be represented as follows,We set 20X1 + 10X2 = 100

    When X1 = 0 in the above constraint, we get,20 x 0 + 10X2 = 100X2 = 100/10 = 10Similarly when X2 = 0 in the above constraint, we get,20X1 + 10 x 0 = 100X1 = 100/20 = 5

    Point X1 X2 Z = 20X1 + 40X2

    0 0 0 0A 0 18 Z = 20 x 0 + 40 x 18 = 720

    B 2 6 Z = 20 x2 + 40 x 6 = 280

    C 4 2 Z = 20 x 4 + 40 x 2 = 160* Minimum

    D 12 0 Z = 20 x 12 + 40 x 0 = 240

    The Minimum cost is at point C

    61

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    62/67

    When X1 = 4 and X2 = 2Z = 160

    Example 4.Solve the following LPP by graphical method

    Maximize Z = 2.80X1 + 2.20X2Subject to constraintsX1 20,000X2 40,0000.003X1 + 0.001X2 66X1 + X2 45,000X1 X2 0

    Solution:

    The first constraint X1 20,000 can be represented as follows.We set X1 = 20,000

    The second constraint X2 40,000 can be represented as follows,We set X2 = 40,000

    The third constraint 0.003X1 + 0.001X2 66 can be represented as follows,We set 0.003X1 + 0.001X2 = 66

    When X1 = 0 in the above constraint, we get,0.003 x 0 + 0.001X2 = 66X2 = 66/0.001 = 66,000Similarly when X2 = 0 in the above constraint, we get,0.003X1 + 0.001 x 0 = 66X1 = 66/0.003 = 22,000

    The fourth constraint X1 + X2 45,000 can be represented as follows,We set X1 + X2 = 45,000

    When X1 = 0 in the above constraint, we get,0 + X2 = 45,000X2 = 45,000Similarly when X2 = 0 in the above constraint, we get,X1 + 0 = 45,000X1 =45,000

    62

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    63/67

    Point X1 X2 Z = 2.80X1 + 2.20X2

    0 0 0 0

    A 0 40,000Z = 2.80 x 0 + 2.20 x 40,000 = 88,000

    B 5,000 40,000Z = 2.80 x 5,000 + 2.20 x 40,000 =

    1,02,000

    C 10,500 34,500Z = 2.80 x 10,500 + 2.20 x 34,500 =

    1,05,300* Maximum

    D 20,000 6,000Z = 2.80 x 20,000 + 2.20 x 6,000 =

    69,200

    E 20,000 0 Z = 2.80 x 20,000 + 2.20 x 0 = 56,000

    The Maximum profit is at point CWhen X1 = 10,500 and X2 = 34,500Z = 1,05,300

    Example 5.Solve the following LPP by graphical methodMaximize Z = 10X1 + 8X2Subject to constraints2X1 + X2 20X1 + 3X2 30X1 - 2X2 -15X1 X2 0

    Solution:

    The first constraint 2X1 + X2 20 can be represented as follows.We set 2X1 + X2 = 20When X1 = 0 in the above constraint, we get,2 x 0 + X2 = 20X2 = 20Similarly when X2 = 0 in the above constraint, we get,2X1 + 0 = 20

    63

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    64/67

    X1 = 20/2 = 10

    The second constraint X1 + 3X2 30 can be represented as follows,We set X1 + 3X2 = 30When X1 = 0 in the above constraint, we get,

    0 + 3X2 = 30X2 = 30/3 = 10Similarly when X2 = 0 in the above constraint, we get,X1 + 3 x 0 = 30X1 = 30

    The third constraint X1 - 2X2 -15 can be represented as follows,We set X1 - 2X2 = -15

    When X1 = 0 in the above constraint, we get,0 - 2X2 = -15X2 = -15/2 = 7.5

    Similarly when X2 = 0 in the above constraint, we get,X1 2 x 0 = -15X1 = -15

    Point X1 X2 Z = 10X1 + 8X2

    0 0 0 0

    A 0 7.5 Z = 10 x 0 + 8 x 7.5 = 60

    B 3 9 Z = 10 x 3 + 8 x 9 = 102

    C 6 8 Z = 10 x 6 + 8 x 8 = 124* Minimum

    D 10 0 Z = 10 x 10 + 8 x 0 = 100

    The Maximum profit is at point CWhen X1 = 6 and X2 = 8Z = 124

    Duality in Linear Programming

    64

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    65/67

    Duality in Linear Programming For every LPP there is a unique LPP associated with itinvolving the same data and closely related optimal solution. The original problem is thencalled primal problem while the other is called its Dual problem

    Let the primal problem beMaximize Z = C1 X1 + C2 X2 + + CnXnSubject to constraints,a11X1+ a 12X2++ a 1nXn 22X1+ X2 + 6X3 < 6X1- X2 +3X3 = 4

    and X1, X2,X3 > 0

    Rearrange the constraints into a standard form, we getMin Z = 0X1 + 2X2+ 5X3

    Subject to constraints,X1+ X2 + 0X3> 2-2X1- X2 - 6X3 > -6X1- X2 +3X3 > 4

    65

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    66/67

    -X1 + X2 -3X3 > -4and X1, X2,X3 > 0

    The Dual of the above primal is as followsMax.G = 2W1 -6W2+ 4W3 4W4

    Subject to constraints,W 1 -2W2 + W3 W4< 0W 1 - W2 - W3 + W4 < 20W 1 - 6W2 + 3W3- 3W4 < 5W 1, W2, W3,W4 > 0

    Max.G = 2W1 -6W2+ 4(W3 W4)Subject to constraints,W 1 -2W2 + (W3 W4 ) < 0W 1 - W2 - W3 + W4 < 20W 1 - 6W2 3(W3- W4 ) < 5

    W 1, W2, W3,W4 > 0Max.G = 2W1 -6W2+ 4W5Subject to constraints,W 1 -2W2 + W5 < 0W 1 - W2 W5 < 20W 1 - 6W2 3W5 < 5W 1, W2, > 0 , W5 is unrestricted in sign

    Example.2Write the Dual of the following LPPMin Z = 4X1 + 5X2- 3X3Subject to constraints,X1+ X2 + X3 = 223X1+ 5X2 - 2X3 < 65X1+ 7X2 +4X3 > 120X1 , X2 > 0 and X3 is unrestricted

    Since X3 is Unrestricted, replace X3 with (X4 - X5 ) andbring the problem into standard form

    Min Z = 4X1 + 5X2- 3(X4 - X5)Subject to constraints,X1+ X2 + (X4 - X5) >22-X1- X2 - (X4 - X5) >- 22-3X1- 5X2 + 2(X4 - X5) > -65X1+ 7X2 +4(X4 - X5) > 120X1 , X2 , X4 ,X5 > 0

    The Dual of the above primal is as followsMax.G = 22(W1 -W2)- 65W3 + 120W4

    66

  • 8/4/2019 Quantitative Tech Compiled Kantharaju

    67/67

    Subject to constraints,W 1 -W2 - 3W3 +W4< 4W 1 - W2 - 5W3 + 7W4 < 5W 1 - W2 + 2W3+ 4W4 < -3-W 1 + W2 - 2W3- 4W4 < 3

    W 1, W2, W3,W4 > 0Max.G = 22W5 - 65W3 + 120W4Subject to constraints,W 5- 3W3 +W4< 4W5 -5W3 + 7W4 < 5W 1 - W2 + 2W3+ 4W4 < -3-W 1 + W2 - 2W3- 4W4 < 3W 1, W2, W3,W4 > 0