review on deliverables and forward look

22
André van Es 2 nd SKADS Workshop 10-11 October 2007 Review on Deliverables Review on Deliverables and forward look and forward look André van Es

Upload: qamar

Post on 24-Feb-2016

39 views

Category:

Documents


1 download

DESCRIPTION

Review on Deliverables and forward look. André van Es. Review of deliverables. Three levels of deliverables: Level 3: Deliverable at Tasks Level 2: Deliverable at Design Study Level 1: Deliverable at Project Level 0: Deliverable at Board Level - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

Review on DeliverablesReview on Deliverablesand forward lookand forward look

André van Es

Page 2: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

Review of deliverablesReview of deliverables

Three levels of deliverables:

Level 3: Deliverable at Tasks Level 2: Deliverable at Design Study Level 1: Deliverable at ProjectLevel 0: Deliverable at Board Level

We present progress in terms of the Level 0 deliverables

Page 3: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

DS-1DS-1ASTRONASTRON

University of University of ManchesterManchester

Observatoire Observatoire de Parisde Paris

DS-2DS-2Rijks Universiteit Rijks Universiteit

GroningenGroningenASTRONASTRONINAF-IRAINAF-IRA

MPIfRMPIfRUniversidad de ValenciaUniversidad de Valencia

CSIROCSIROSwinburneSwinburne

Leiden ObservatoryLeiden ObservatoryChalmersChalmers

OxfordOxfordUniversity of University of ManchesterManchester

Observatoire de ParisObservatoire de ParisCambridgeCambridge

University of MelbourneUniversity of MelbourneNatal UniversityNatal University

PRAO-LPIPRAO-LPIUniversity of LeedsUniversity of Leeds

University of GlasgowUniversity of GlasgowUniversity of AdelaideUniversity of Adelaide

DS-3DS-3University of University of CambridgeCambridge

ASTRONASTRON

University of University of ManchesterManchester

CSIROCSIRO

INAF-IRAINAF-IRA

University of University of OxfordOxford

Cambridge Cambridge UniversityUniversity

Observatoire Observatoire de Parisde Paris

National National Research Research

FoundationFoundation

DS-4DS-4University of University of ManchesterManchesterASTRON ASTRON

Observatoire Observatoire de Parisde ParisINAF-IRAINAF-IRAFG-IGNFG-IGN

University of University of OxfordOxfordCSIROCSIRO

National National Research Research CouncilCouncil

University of University of CambridgeCambridge

University of University of OrléansOrléansCNRSCNRS

OMMIROMMIR

DS-5DS-5ASTRONASTRON

University of University of ManchesterManchester

Observatoire Observatoire de Parisde Paris

JIVEJIVE

INAF-IRAINAF-IRA

MPIfRMPIfR

Oxford Oxford UniversityUniversity

CSIROCSIRO

National National Research Research

FoundationFoundation

UMKUMK

University of University of CambridgeCambridge

OMMICOMMIC

DS-6DS-6INAF-IRAINAF-IRA

ASTRONASTRON

JIVEJIVE

CSIROCSIRO

Univ. SydneyUniv. Sydney

DS-7: DS-7: University of Manchester, Observatoire de ParisUniversity of Manchester, Observatoire de Paris

Page 4: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS-1Review on deliverables: DS-1

Deliverable/ Milestone No

Planned (in months)

Achieved (in months)

Deliverable/Milestone Name

DS1 1. 1-oct-05 Nov-05 Organize kick-off DS1 2. 1-oct-05 1-jan-06 Implement adequate management tools DS1 - ongoing Continuous coordination and management DS1 - ongoing Continuous assessment and control DS1 3 1-Nov-05 30-June-

06 Document on outreach policy

DS1 4 1-Apr-05 1-Oct-05 Establish web-page DS1 5 1-Nov-05 1-Feb-06 Document on IPR Policy DS1 6 1-Apr-06 4-Sep-06 SKADS international workshop 2006 DS1 7 1-Apr-07 10-Oct-07 SKADS international workshop 2007 DS1 8 1-Apr-08 Sep 08 SKADS international workshop 2008 DS1 9 1-Apr-09 Sep 09 SKADS international workshop 2009

Page 5: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

Page 6: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS-2Review on deliverables: DS-2

Nominal

Completion Date

Actual/ Planned

completion Date

Milestone

DS2 1 1-jun-07 1-jun-07 Conclusion on Science Drivers

DS2 2 1-dec-08 1-dec-08 Conclusion on Year in the Life for different SKA realizations

DS2 3 1-jul-08 1-jul-08 Optimised Configuration for the SKA

DS2 4 1-mei-09 1-mei-09 Demonstration of new calibration and imaging Techniques

Page 7: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

A Report and Proceedings...A Report and Proceedings...

Page 8: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS-3Review on deliverables: DS-3

Nominal

Completion Date

Actual/ Planned

completion Date

Milestone

DS3 1 30-jun-08 31-dec-08 Delivery of prototype phase transfer link DS3 2 31-dec-08 31-dec-08 Development cost of model for the network DS3 3 30-mei-09 30-mei-09 Report on technology roadmapping and costing DS3 4 1-jul-07 1-jul-07 Delivery of framework for functional simulator DS3 5 30-mei-09 30-mei-09 Report on network achtitecture DS3 6 30-jun-08 30-jun-08 Overview reports on site selection DS3 7 31-dec-08 31-dec-08 Final reports on site selection DS3 8 30-jun-08 30-jun-08 Reports on SKA for the user

DS3 9 30-dec-05 30-dec-05 Model driven architecture specification of control and data processing

DS3 10 30-jun-08 30-jun-08 Report MDA constructs, interfaces and platforms DS3 11 30-dec-07 30-dec-07 report on scalable platform specific composition DS3 12 30-jun-08 30-jun-08 MDA assessment and scalability recommendations

Page 9: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

SKADS Design & Costing SKADS Design & Costing Paper (SKA Memo 93)Paper (SKA Memo 93)

Page 10: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS-4Review on deliverables: DS-4

Nominal

Completion Date

Planned Completion Milestone

DS4 1 30-dec-06 done SiGe band pass filter using PIC technology prototype DS4 2 30-dec-07 31-dec-08 ADC performance evaluation

DS4 3 1-jul-07 1-jul-08 Hybrid LNA first devices

DS4 4 1-jul-06 1-jul-08 Inventory of RFI mitigation techniques and applicability to SKA

DS4 5 1-jul-07 1-jul-08 Evaluation of impact of moving interference sources on SKA DS4 6 31-okt-07 1-mrt-08 Characterised antenna element DS4 7 1-mrt-08 1-jul-08 antenna element with integrated MMIC prototype

DS4 8 1-jul-07 1-mrt-08 Simulated Digital beamformer for 2-PAD

DS4 9 30-dec-06 done Prototype low cost SiGe analogue beamformer DS4 10 29-dec-08 2-feb-09 Prototype complete 2-PAD digital tile

DS4 11 30-jun-09 30-jun-09

Final reports on semiconductor technologies, RFI mitigation strategies, antenna element design, digital beamformer design 2-PAD performance (T1-T6)

Page 11: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

Prototype of Low Cost SiGe Prototype of Low Cost SiGe BeamformerBeamformer

Page 12: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS-5Review on deliverables: DS-5

Nominal

Completion Date

Planned Completion Milestone

DS5 1 30-dec-05 30-dec-05 Completion of System Requirements DS5 2 1-mrt-06 15 May-06 Design Review of First Tile

DS5 3 1-jul-06 1-jul-06 Delivery of first manufactured tile

DS5 4 1-mrt-07 1-okt-07 completion of 10 tile system DS5 5 31-mei-08 1-sept-2008 completion of first 100 tiles DS5 6 1-jan-09 1-jan-2009 completion of m anufacturing of all tiles

Page 13: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

EMBRACE 10 tile prototypeEMBRACE 10 tile prototype

Page 14: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS-5Review on deliverables: DS-5

Nominal

Completion Date

Planned Completion Milestone

DS5 1 30-dec-05 30-dec-05 Completion of System Requirements DS5 2 1-mrt-06 15 May-06 Design Review of First Tile

DS5 3 1-jul-06 1-jul-06 Delivery of first manufactured tile

DS5 4 1-mrt-07 1-okt-07 completion of 10 tile system DS5 5 31-mei-08 1-sept-2008 completion of first 100 tiles DS5 6 1-jan-09 1-jan-2009 completion of manufacturing of all tiles

Page 15: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS-6Review on deliverables: DS-6

Nominal

Completion Date

Planned Completion Milestone

DS6 1 1-jul-06 done Design Report on Analog Optical link DS6 2 30-apr-07 done Design Report on Analog and digital optical link

DS6 3 31-aug-08 31-aug-08 Report on data handling for large telescopes

DS6 4 30-sep-08 30-sep-08 Wide band high dynamic range A/D FX correlator, small

prototype DS6 5 30-sep-08 30-sep-08 Software beamforming and multibeaming on BEST-x DS6 6 30-sep-08 30-sep-08 Algorithms for RFI mitigation DS6 7 1-jul-08 1-jul-08 Calibration methods for large array DS6 8 30-sep-08 30-sep-08 report on High sensitivity astronomical tests

Page 16: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

BEST Report on optical linksBEST Report on optical links

Page 17: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS-7Review on deliverables: DS-7Task number Deliverable

No Deliverable Name Planned

(in months)

Achieved (in months)

DS7-T1 1 SKADS Quarterly Report Q4/2006

19 19

DS7-T1 2 SKADS Quarterly Report Q1/2007

22 22

DS7-T1 3 SKADS Quarterly Report Q3/2007

25 25

DS7-T1 4 SKADS Quarterly Report Q4/2007

19 19

DS7-T1 5 SKADS Quarterly Report Q1/2008

22 22

DS7-T1 6 SKADS Quarterly Report Q3/2008

25 25

DS7-T1 7 SKADS Quarterly Report Q4/2008

19 19

DS7-T1 8 SKADS Quarterly Report Q1/2009

22 22

DS7-T1 9 2007 Annual Report to International SKA Project Office

24 25

DS7-T1 10 2008 Annual Report to International SKA Project Office

24 25

DS7-T1 11 2009 Annual Report to International SKA Project Office

24 25

Page 18: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

A Quarterly Report...A Quarterly Report...

Page 19: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

Updated PlanUpdated Plan

Prior to 2nd Annual Report project planning was updatedAll Design Studies submitted new milestone/deliverable

tableNew milestone dates were discussed and agreed with DS

leadersSKADS on track to finish on 30th June 2009

Page 20: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

Deliverables/Milestones planned Deliverables/Milestones planned (update 2(update 2ndnd annual report) annual report)

Level 0 Deliverables

0

10

20

30

40

50

60

0,5 1 1,5 2 2,5 3 3,5 4

Time

Tot. N

r. of

Deli

vera

bles

Planned (DoW)Current Plan

Page 21: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

Next 18 months Next 18 months (major milestone for each DS)(major milestone for each DS)

DS2: Final Report on SKA configurationsDS 3:

– Implementation of Cost and Functional simulator tool– Selection of networking and computing technologies

DS 4: Completion of 2-PAD designDS 5: Build and first testing of EMBRACE at Westerbork

and Nancay (100 tiles)DS 6: BEST demonstrating beamforming and Hl sensitivity

astronomical testsDS 8 : First iteration of Overall System Design and Project

plan

Page 22: Review on Deliverables and forward look

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS 8Review on deliverables: DS 8

Design Study 8 produces the major deliverables of the project (the focal and cohering point of SKADS):

1. Overall System Design2. Preliminary SKA Plan3. White Paper for the ISSC

It is the collection of all activities and will show and establish the direction towards the SKA