sdms document 112693

146
SDMS Document 112693

Upload: others

Post on 26-Dec-2021

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SDMS Document 112693

SDMS Document

112693

Page 2: SDMS Document 112693

DRAFT

REMEDIAL ACTION MASTER PLAN

GEMS LANDFILL

Z-1-12.14

3 JANUARY 1982

k

•Hi

b o o

o o

1

Page 3: SDMS Document 112693

CONTENTS

Executive Summary

^

K I I I I i

1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9

Data

2.1 2.2

Purpose Site Location General Approach Existing Data Assessment of Existing Information Initial Remedial Measures Remedial Investigations Feasibility Study Cost Estimate and Schedule

Evaluation

Objective Background

2.2.1 Site Description

2.2.2 Site History

2.3 Environmental Setting

2.3.1 Physiography 2.3.2 Geology 2.3.3 Surface Water Hydrology 2.3.4 Hydrogeology 2.3.5 Air Quality 2.3.6 Ecology 2.3.7 Socioeconomics

2.4 Hazardous Materials Characterization

2.4.1 Groundwater 2.4.2 Surface Water 2.4.3 Air 2.4.4 Cover Material

2.5 Assessment of Potential Impacts

2.5.1 Public Health and Safety 2.5.2 Environment

2.6 Assessment of Data Limitations

1-1 1-2 1-2 1-3 1-5 1-6 1-8 1-10 1-12

2-1

2-1 2-1

2-1 2-2

2-6

2-6 2-7 2-9 2-10 2-12 2-13 2-15

2-15

2-16 2-18 2-20 2-21

2-23

2-23 2-27

2-28

3 IT"

O

o

3

Page 4: SDMS Document 112693

Q p-

I Q

a

H

i

i

Initial Remedial Measures

3.1 Objective

3.2 Recommended Measures

3.2.1 Task 1 - Initial Remedial Measures Plan 3.2.2 Task II - Install Fence 3.2.3 Task III - Post Area 3.2.4 Task IV - Sample Water Supplies

3.2.5 Task V - Replace Culverts

3.3 Cost Estimate and Schedule

Remedial Investigation Activities 4.1 4.2

Objective and Task I - Work Plan Preparation

Initial Organization 4.3 Task II - Collect and Review

Existing Data 4.4 Task III - Health and Safety

Assessment 4.5 Task IV - Topographic Survey 4.6 Task V - Geophysical Survey 4.7 Task VI - Hydrogeological Study

and Groundwater Monitoring 4.8 Task VII - Hydrological Study 4.9 Task VIII - Air Quality Monitoring 4.10 Task IX - Toxicological Review 4.11 Task X - Ecological Study 4.12 Task XT-Site Assessment Report 4.13 Costs and Schedule

Feasibility Study

5.1 Objective

5.2 Scope

5.2,1

5.2.2 5.2.3

5.2.4 5.2.5 5.2.6 5.2.7

Task I - Description of Current Situation and Proposed Response Task II - Development of Altneratives Task III - Initial Screening of Alternatives Task IV - Laboratory Studies (Optional) Task V - Evaluation of Alternatives Task VI - Conceptual Design Task VII - Final Report

5.3 Costs and Schedule

Paae

3-1

3-1

3-1

3-1 3-2 3-3 3-3 3-4

3-4

4-1

4-1

4-2

4-4

4-6 4-10 4-11

4-13 4-19 4-22 4-24 4-26 4-27 4-29

5-1

5-1

5-1

5-1 5-2

5-3 5-4 5-5 5-10 5-10

5-10

I o o

o o 4^

tl

Page 5: SDMS Document 112693

D ps Page

5.4 Source Control Remedial Actions 5-11

I D

5.4.1 Transfer of DDD-Contaminated Sludge 5-11 5.4.2 Regrading of Side Slopes 5-12 5.4.3 Landfill Cap 5-13 5.4.4 Slurry Wall 5-13 5.4.5 Pumpout and Treatment 5-14 5.4.6 Surface Runoff Collection and

Treatment 5-14

5.5 Offsite Remedial Actions 5-15

5.5.1 Potable Wells 5-15 5.5.2 Contaminated Basements 5-16 5.5.3 Holly Run and Briar Lake 5-16

6 Community Relations 6-1

Appendix A. Site Chronology Appendix B. NJDEP Report

H I

RW27/41

fl

7} 3

o o

o o NJ

Page 6: SDMS Document 112693

TABLES

Following Page

2-1 Groundwater Contaminant Identified in Vicinity of GEMS Landfill 2-16

2-2 Depths at Which Groundwater Contaminants Have

Been Identified 2-16

2-3 Leachate Contaminants Entering Holly Run 2-17

2-4 Contaminant Variation in the Hurst Well 2-18

2-5 Surface Water Contaminants Identified in Vicinity of GEMS Landfill 2-19

2-6 Sediment Contaminants Identified in Surface Water Near GEMS Landfill 2-19

2-7 GEMS Study - Contaminants Found - Interior Air Samples 2-20

2-8 Interior Air Samples - GEMS Study for Any Volatile Organic Chemicals 2-20

2-9 Exterior Air Samples - GEMS Study for Any Volatile Organic Chemicals 2-20

2-10 Frequency of Detection of Interior Air

Contaminants 2-20

2-11 Chlorinated Pesticide Screen 2-22

2-12 Analysis of March 10, 1981 Samples from Gloucester Township Landfill 2-23

2-13 RCRA Extraction Procedure (EP) Toxicity Test on March 10, 1981 Samples from 2-23 Gloucester Township Landfill

2-14 RCRA Extraction Procedure (EP) Toxicity Test on March 10, 1981 Samples from Gloucester Township Landfill 2-23 g

3-1 Estimated Cost of Initial Remedial Actions 3-4

4-1 Estimated Cost of Remedial Investigation 4-29

RW27/43

o o

o o

Page 7: SDMS Document 112693

Q

Q

FIGURES

Following Page

1-1 Approach for Remedial Action Master Plan 1-2

1-2 Cost Estimate and Schedule Through Remedial Investigation for GEMS Landfill 1-12

1-3 Critical Path Schedule Through Remedial Investigation for GEMS Landfill 1-13

2-1 Northeastern Seaboard States and Site

Location 2-1

2-2 Roadways in the Region of the Site 2-1

2-3 Site Location and Local Topography 2-1

2-4 GEMS Landfill Well Log 2-9

4-1 Cost Estimate and Schedule Through Remedial 4-30 Investigation for GEMS Landfill

4-2 Critical Path Schedule Through Remedial 4-30 Investigation for GEMS Landfill

RW27/42

3

o o M

O O i(k

Q

Page 8: SDMS Document 112693

I L Section 1

EXECUTIVE SUMMARY

This document is a Remedial Action Master Plan (RAMP) for the Gloucester

Environmental Management Services, Inc. (GEMS) landfill site, located in

Camden County, New Jersey. A RAMP is a plan for undertaking remedial

investigation activities and remedial actions in response to a hazardous

substance release, or a substantial threat of a release, into the

environment. It is based on the National Oil and Hazardous Substances

Contingency Plan promulgated by the Environmental Protection Agency (EPA)

on July 16, 1982 (47 FR 31180-31243).

1.1 PURPOSE

The purpose of this RAMP is to Identify the scope of practical remedial

investigation activities or remedial actions appropriate for the GEMS

site and to present an implementation schedule for these activities. It

is based on existing, available data only. The RAMP provides an

order-of-magnitude cost estimate and schedule for each proposed initial

remedial action or investigation activity, as well as a discussion of

data limitations, community relations strategies, and problems which may

be encountered during project implementation.

The RAMP provides the EPA with a basis on which to decide future actions

to be taken at the GEMS landfill, including remedial investigations,

feasibility studies, and other onsite or offsite remedial actions. It is ^

anticipated that the approved RAMP will serve as the primary planning

1-1

I o o

Ul

Page 9: SDMS Document 112693

I P document for all remedial activities at the site and will form the basis

of an EPA - State cooperative agreement for the site.

I I

i

i i

Li

1.2 SITE LOCATION

I The GEMS landfill is located in Gloucester Township, Camden County, New

Jersey, at the intersection of Erial and Hickstown Roads. The site

consists of approximately 60 acres in a generally triangular plan, with

the top of the landfill rising 80 to 100 feet above the surrounding land.

The site is zoned for industrial use, but much of the surrounding area is

residential. The landfill is located along a minor watershed divide

between two small streams. Both streams are tributaries of Big Timber

Creek and the Delaware River.

1.3 GENERAL APPROACH

Figure 1-1 presents a general flow schematic of the remedial action

planning approach being recommended for the GEMS landfill site. The

approach is based on three types of remedial actions:

0 Initial Remedial Measures

0 Source Control Remedial Actions

0 Offsite Remedial Actions

3 f

o o

3 O

1-2

Page 10: SDMS Document 112693

D n

IC

Col lac t & Evaluate

E x i t t l n g S l t a Data

O b t a i n

E n f o r c a m a n t Plan

Prepare Remedia l A c t i o n Master Plan ( R A M P )

I I n i t i a l Remedia l

Measures

I d e n t i f y Data

Requ i remen ts

C o n d u c t L i m i t e d Si te Inspec t ion

1 i

Figure 1—1 Approach for Remedial Action

Master Plan

( ^

I m p l e m e n t Cost E f fec t i ve A l t e r n a t i v e

N o A c t i o n

^ y ^ A r e ^ ^ H a i a r d s

^ ^ Present o r Po ten t ia

1

( ^

Remedia l Invest igat ion

I d e n t i f y A d d i t i o n a l Data Requ i rements

C o n d u c t S i te Oata l led Invest igat ion

N o A c t i o n

Design and I m p l e m e n t Remedy

Design and I m p l e m e n t Remedy

Post C losure M o n i t o r i n g

Post Closure M o n i t o r i n g

CiML 001004^

Page 11: SDMS Document 112693

u

W ^ Initial remedial measures are implemented when a problem is identified

requiring prompt attention. They are carried out prior to planned

remedial actions or planned removal of hazardous substances. The

essential criterion for determining the need for initial remedial

measures is the existence of an actual or potential significant threat to

public health or the environment. However, initial remedial measures

should require a minimum of planning, be completed in a short period of

time, and be cost-effective.

Source control remedial actions are those responses ta.ken at or near the

original source of the hazardous substances whenever natural or manmade

barriers are inadequate to retard migration. If contaminants have

migrated away from the original site, offsite remedial actions may be

appropriate.

m

il

4

Offsite remedial actions are necessary when source control remedial

actions are either inappropriate or ineffective in reducing the migration

of hazardous substances from the site.

Before either source control or offsite remedial actions can be carried

out, sufficient data and information must exist to allow development,

screening, selection, design, and implementation of the remedial actions

in a cost-effective manner. If existing information is not adequate, a

remedial investigation is undertaken to provide supplemental data. tr'

o o

n

1.4 EXISTING DATA o jk

oo

1-3

Page 12: SDMS Document 112693

r Extensive monitoring for hazardous materials has been conducted by the

New Jersey Department of Environmental Protection (NJDEP) and the Camden

County Health Department. Hazardous chemicals have been identified in

J the nearby groundwater, surface water, air, and on the surface of the

landfill. NJDEP has concluded that the GEMS landfill is responsible for

•I contamination of nearby surface water and groundwater supplying potable

water wells in the area. Although some private wells have been found to

be contaminated, NJDEP has determined none require condemnation at this

time.

i

m Most of the hazardous materials found in water and air near the site are

^ _ classified as volatile organics. Many are classified by EPA as priority

pollutants and many are toxic to humans. Several are carcinogens. The i " ^ principal hazardous substance found on the landfill surface is ODD, a

degradation product of the pesticide, DDT. Smaller amounts of DDE

(another degradation product of DDT), DDT, and several toxic heavy metals

have also been identified as contaminants. *

Several potential threats to public health and safety exist from the

presence of the GEMS landfill, including:

0 Private well contamination

3 0 Access to contaminated surface water f

^

0 Access to landfill

o o

o o

1-4

Page 13: SDMS Document 112693

n

m

m

m m m m m 1 •I

0 Flooding of contaminated surface water

0 Volatile organics in household basements

• 0 Air pollution from volatile organics

0 Long term contamination of deep aquifers

0 DDD-contaminated dust

Well contamination, access to the landfill and surrounding surface water,

and contaminated basements appear to pose the most irraninent problems

associated with the landfill. The degree of other potential health

problems has not yet been adequately evaluated and pose longer term

health impacts.

1.5 ASSESSMENT OF EXISTING INFORMATION

Several limitations apply to the GEMS landfill RAMP, including;

0 Insufficient information exists with which to assess the

magnitude of the problem and to evaluate the feasibility of

potential solutions.

0 Some groundwater monitoring data is extremely variable and

appears Inconsistent. In one potable well, volatile organics S o t-n

o

1-5

Page 14: SDMS Document 112693

D" p., concentrations varied from 890 ppb to below detectable limits

within two months.

I El

a

0 Cost estimates provided are order-of-magnitude only. They have

been prepared for guidance in project evaluation and

implementation from the information available at the time of

the estimate. The final costs of the project will depend on

actual labor and material costs, competitive market conditions,

final project scope, implementation schedule, and other

variable factors. As a result, the final project costs will

vary from the estimates presented herein. Because of this,

project feasibility and funding needs must be carefully

reviewed prior to making specific financial decisions to help

ensure proper project evaluation and adequate funding.

0 The RAMP process does not permit a complete and exhaustive

consideration of all remedial planning activities.

0 Many public agencies are related to the GEMS landfill in some

capacity, which leads to a complicated remediation process.

Extensive litigation related to the disposal of hazardous

wastes at the GEMS landfill is now in progress. Consequently,

at this point, all the involved parties are not cooperating 3

towards a common goal of site remediation. o o

1.6 INITIAL REMEDIAL MEASURES p

1-6

Page 15: SDMS Document 112693

IT

a

Several Initial remedial measures are recommended to rapidly reduce any

existing or Imminent hazards to public health or the environment,

including:

0 Erect a fence with warning signs around the landfill and

contaminated surface water surrounding the site (Holly Run,

Briar Lake and swampy area). The fence is intended to prevent

accidental direct contact with the contaminated surface water

or cover material, and to prevent access into areas which are

potentially explosive from methane gas generated.

0 As the result of highly variable analytical results in the

past, potable water wells previously indentified as containing

volatile organic compounds should be resampled to verify the

levels of contamination. Once these levels are identified,

hazards to the well users can be assessed and appropriate

actions can be Initiated.

0 Increase the hydraulic capacity of the culverts enabling

passage of Holly Run under Briar Lane, to prevent flooding of

adjacent residential properties with contaminated surface water

after heavy rains.

0 Develop a plan to review and evaluate additional data as it is

generated, to enable implementation of additional initial

remedial measures as they arise. o o

o

i 1-7

Page 16: SDMS Document 112693

I

r I J I

i

I r

I I

1.7 REMEDIAL INVESTIGATIONS

The following remedial investigation and activities are considered

necessary for the GEMS landfill site prior to conducting feasibility

studies for alternative remedial actions:

Task I - Work Plan Preparation and Initial Organization

Prepare a work plan for collecting additional field data during the

remaining tasks. Mobilize project team and equipment, and conduct an

^ investigative site visit.

Task II - Collect and Review Existing Data

Collect and review all existing data pertinent to the site.

Task III - Health and Safety Assessment

Prepare an initial Health and Safety Plan in conjunction with Task I.

Perform a field health and safety assessment of the site and update plan

I to include additional information.

Task IV - Topographic Survey 2 3 t r

I u

Review existing site topographic data and perform additional topographic °

•survey work needed to provide a detailed map for investigation and o

o design. oj

0 1-8

Page 17: SDMS Document 112693

• • El

Q

Perform a geophysical survey to obtain additional information about the

underlying geologic formations and groundwater contamination.

I Wr Task V - Geophysical Survey

r Q H Task VI - Hydrogeological Study and Groundwater Monitoring

I Q

i H Task VII - Hydrological Study

Install additional monitoring wells to better characterize groundwater

location, flow patterns and contamination limits. Implement a

groundwater monitoring program to assess contamination concentrations and

to identify contaminant sources.

Monitor surface water and sediments to further document the presence of

hazardous pollutants in Holly Run, Briar Lake, and Tom's Branch. Monitor

leachate and surface runoff to help identify sources of surface water

contamination.

Task VIII - Air Quality Monitoring

Perform air quality testing to determine the extent of air pollution

attributed to the landfill and to identify health risk areas.

Task IX - Toxicological Review

Q 3

o o

o o

D 1-9

Page 18: SDMS Document 112693

I

t

i i

Perform a toxicological review of air and water contaminants to assess

the potential impact on the exposed population at the concentrations

identified.

Task X - Ecological Study

Conduct an ecological study to identify receptors in the natural and

human environment within the vicinity of the site.

Task XI - Site Assessment Report

Compile and evaluate all pertinent data generated during the remedial

investigation and present conclusions concerning extent of contamination

and health impacts. Develop preliminary remedial action alternatives for

the site.

1.8 FEASIBILITY STUDY

Appropriate actions cannot be chosen until sufficient data have been

generated through the remedial investigation activities. When the

remedial investigation is complete, a detailed feasibility study will be

conducted to develop and evaluate alternative remedial actions. After

initial screening to Identify feasible alternatives, a detailed

evaluation will be conducted to compare each remaining alternative on the

basis of cost, reliability, implementability, operation and maintenance ^

requirements, environmental effects and safety requirements. As a result o

o o Crj

1-10

Page 19: SDMS Document 112693

I of this analysis an alternative will be recoiranended and a conceptual

design prepared.

Source Control Remedial Actions

Several source control remedial actions which may be considered include:

0 Transfer DDD-contaminated sludge to top of landfill prior to

capping.

0 Regrade side slopes of landfill to minimize erosion and to

ensure the long-term stability of the site.

0 Cap the landfill with an impermeable layer to reduce

infiltration of rainfall. A gas venting system should also be

considered.

0 Construct slurry wall to prevent horizontal migration of

leachate.

o Pump contaminated groundwater from the vicinity of the

landfill, treat and recharge to ground.

0 Install surface runoff collection system to minimize potential

for contamination of surface water.

Offsite Remedial Actions

3

o o

o o

1-11

Page 20: SDMS Document 112693

J M a M M a m m j A M a • • A m

TASKS COSTS

LOW HIGH 10 15 20 25 30

WEEKS

35 40 45 50 55 60

INITIAL REMEDIAL MEASURES

TASK I Dntlop Plan

TASK 2 -5 Fanca, Poit Araa, Ratampla, Culvartt

REMEDIAL INVESTIGATIONS

TASK I Work Plan Praparation & Initial Organiation

TASK II Collact & Raviaw Existing Data

TASK III Haalth iSi Safaty Attastmant

TASK IV Topographic Survoy

TASK V Gaophytical Sunny

TASK VI Hydrogaogical Study*

TASK VII Hydrologic Study*

TASK VIII Air Quality Monitoring*

TASK IX Toxicological Raviaw

TASK X Ecological Study

TASK XI Sita Aisattmant Raport

FEASIBILITY STUDY

COMMUNITY RELATIONS

TASK I Davalop & Implamant

Community Ralationi Plan

13,000

13S.000

13,000 : 3,000 8,000

25,000 37.000 101.000 12.000 13.000 13.000

5.000

30.000

50,000

14.000

27.000

266,000

2S.000

6.000

13.000

39.000

55.000

158.000

19.000

20,000

18,000

8.000

45.000

150.000

20.000

INITfAL REMEDIAL ACTIONS TOTAL

REMEDIAL INVESTIGATION TOTAL

FEASIBILITY STUDY TOTAL

COMMUNITY REUTIONS TOTAL

SUBTOTAL

ANALYTICAL COSTS; EPA CONTRACT LABS

TOTAL COSTS: EPA CONTRACT LABS

ANALYTICAL COSTS: INDEPENDENT LABS

TOTAL COSTS: INDEPENDENT LABS

148,000

260,000

50,000

14,000

293.000

406.000

150.000

20.000

LEGEND

Primary Activity Ongoing Activity at Raquired

472.000

62,000

534.000

869.000

71,000

940.000

230,000 282,000

(702,000 $1,151,000 'NOTE: Excluding Analytical Cott

^SOO IOO IWD

Figure 1 -2

Cost Estimate and Schedule

Through Remedial Investigation for

GEMS Landfi l l

Page 21: SDMS Document 112693

i i n

II

ta

Based on the results of the remedial investigation activities and the

problems identified, a variety of offsite actions may be appropriate,

including:

0 Discontinue use of private wells.

0 Install carbon filter units on contaminated wells or provide an

alternative supply.

0 Drain contaminated water away from basements.

0 Collect, vent, and treat volatile organic gases.

0 Ventilate basements.

0 Abandon and fill basements.

0 Remove and treat water from Holly Run and Briar Lake.

0 Channelize swampy areas to enhance natural dissipation of

contaminants.

1.9 COST ESTIMATE AND SCHEDULE 3

o Cost estimates and schedules for the initial remedial actions, remedial o

investigation activities, feasibility study, and conwunity relations are ^ o

shown in Figure 1-2. Cost estimate ranges are given to account for such ^

1-12

Page 22: SDMS Document 112693

{ B B ^ j t j m 1 ^ ^ M m m m m m

s •

10 •

IS T

20 T

25 T

30

• 35 •

40

T 45

• SO

• SS T

60

Community Relations

Initial Ramadial Meaiures

/ ^ Collact & Review Existing Data

Hydrological Study

^ ^ ^ Work Plan

Topographic Survey

/i?r\

* / v \ Geophysical Survey

I Hydrogeological * | Study

Feasibility Study

T I I Sample Y Analysis rx\\

Health 8i Safaty Assessment

I /vuh

II II

A I I I I

Site Assessment Raport -

Air Quality Monitoring Ecological Study LEGEND

^•"•"••^ Primary Activity • • » • • » Sample Analysis — Ongoing Activity as Raquired

Initial Toxicological Raviaw

6S00 too awo

J ^ ^ Final Toxicological Review

F igure 1—3

Cr i t i ca l Path Schedule T h r o u g h

Remed ia l Invest igat ion f o r G E M S L a n d f i l l

Page 23: SDMS Document 112693

m

Q

PH

things as analyses by an EPA contract laboratory versus an independent

laboratory, installation of additional groundwater monitoring wells due

to geological conditions experienced during field installation of earlier

wells or due to monitoring data collected and analyzed from existing

wells, and repeat or refined sampling and analysis programs. The task

descriptions for each initial remedial action and remedial investigation

activity provide the basis for the associated cost range.

The GEMS landfill remedial investigation and feasibility study will

require approximately 58 weeks to complete. Inclement weather conditions

could adversely affect this schedule. Increasing the time required.

Estimated costs range from $534,000 to $940,000 if analytical analyses

are performed by EPA contract laboratories and $702,000 to $1,151,000 if

performed by independent laboratories.

• A critical path schedule of initial remedial actions, remedial

investigations, and feasibility study is presented in Figure 1-3.

I • I I i I

RW27/65

] 1-13

Ci 3 IT"

O o

o o O

Page 24: SDMS Document 112693

I

i

tr

Section 2 % i;'\"^Sf id"^ !%3 m

DATA EVALUATION (••1 *-.--» • T-,;','i & £ L _ . a i 1

2.1 OBJECTIVE

The purpose of this section is to assess and summarize the current status

of the Gloucester Environmental Management Services, Inc. (GEMS) landfill

site. To accomplish this, existing information regarding the site was

compiled and evaluated. This data serves as the framework for developing

the Remedial Action Master Plan (RAMP) and serves as the basis for future

data collection and recommendations. This section is intended to be a

summary of pertinent technical and non-technical information needed to

determine the seriousness of the problems at the GEMS landfill site and to

develop plans for remedial actions. It is not, however, intended to be a

complete compilation of all data which has been generated concerning the

site.

2.2 BACKGROUND

2.2.1 Site Description

I I i I ^ The GEMS landfill is located in Gloucester Township, Camden County,

New Jersey, at the intersection of Erial and Hickstown Roads. The site is g

Cj situated on Tax Map Block 357, Lot 9, with geographical coordinates 39°46'48" North and 75°01'15" West. The location of the landfill is

f

o o

o identified in Figures 2-1, 2-2, and 2-3. 5

2-1

Page 25: SDMS Document 112693

II

Figure 2—1 Northeastern Seabpard States

and Site Location

c c

o o o\ to

SOUTH CAROLINA \

/

g^2M BHILL

Page 26: SDMS Document 112693

10

SCALE IN MILES Figure 2-2 Roadways in the Region of the Site

Page 27: SDMS Document 112693

{-900 TOO awD

Page 28: SDMS Document 112693

The site consists of approximately 60 acres in a generally triangular plan

with a relief above the general topography of 80 to 100 feet. The slopes

of the landfill are steep," particularly on the west face.

Holly Run, a small stream, originates near the southeast corner of the

landfill and flows northward along the northeast side of the property.

Near its origin and adjacent to the landfill. Holly Run has been relocated

twice, creating a swampy area.

Near the southeast corner of the site is a cement manufacturing and

welding operation. Adjoining the site to the west, is a property owned by

the Gloucester Township Board of Education. A maintained, motorbike

course is also located adjacent to the west side of the landfill. Along

the northeast side are houses in close proximity to the landfill

(300 feet) and to Holly Run (200 feet).

The site is zoned for industrial use, but much of the surrounding area is

m residential. A population of approximately 6,000 live within one mile of

the landfill and approximately 38,000 live within three miles.

1 a

2.2.2 Site History

H The GEMS landfill has existed under various operators for over 20 years §

while being owned by the Township of Gloucester. Originally, the Township

was responsible for operating a small portion of the landfill. In 1969,

Anthony Amadei began contracting operation of the landfill from the

Township. He then incorporated his operation the following year into the

a 2-2

f

o

o o cn

Page 29: SDMS Document 112693

n

V

Anthony Amadei Sand and Gravel Company. In 1976, registration of the

landfill transferred to Gloucester Environmental Management Services, Inc.

(GEMS), which continued to operate the landfill until its closure in

November, 1980.

Although early operations were not well documented, reports indicated that

chemical wastes may have been disposed of beneath the water table prior to

1970; however, limited geophysical testing has not supported these

reports. Disposal of chemical wastes at the site was permitted by the

New Jersey Department of Environmental Protection (NJDEP) in 1970 for a

period of approximately three weeks. Approval was discontinued after this

time due to a chemical fire at the site. Records of occurrences, such as

fires, complaints and NJDEP inspections indicate that chemicals may have

also been dumped intermittantly between 1970 and 1976.

The NJDEP Solid Waste Administration (SWA) conducted regular inspections

of the GEMS landfill beginning in April, 1973. Often, these inspections

revealed deficiencies in sanitary landfill operating procedures, such as

use of inadequate or insufficient cover material, or failure to control

windblown paper. Over 60 separate inspection reports indicate leachate

emanating from the landfill and flowing into Holly Run.

In April, 1977, a land survey by SWA indicated that the GEMS landfill had 3"

exceeded its approved design elevations. GEMS disputed that the landfill (r*

o o had reached capacity, but supplied no evidence to NJDEP in support of

their position. A design for expansion, submitted at the end of 1976, was o o

not approved because the environmental impact statement required for the ^

2-3

Page 30: SDMS Document 112693

a n

expansion had not been conducted. Consequently, SWA issued an

Administrative Order on September 1, 1977 requiring the landfill to cease

operation within 10 days. However, the hardship that would be created by

closure for the boroughs using the landfill and for the waste haulers led

to the decision to allow expansion and continued operation, but for less

• than one year. After the GEMS lease expired in July 1978, the expanded

capacity had not yet been reached, and the Courts authorized the landfill

to continue operation because it was needed. A series of litigation

followed, concerning the closure of the site. Acceptance of solid waste

was discontinued by November, 1980.

a

a As part of the site closure operations, sludge from the City of

Philadelphia was brought in as cover material. A spill of this material

onto the road caused a road hazard and prompted testing. Examination of

the sludge revealed the presence of DDD, a degradation byproduct of the

pesticide DDT. The impacts of the contaminated sludge and responsibility

for any relocation or containment which may be necessary, are now being

litigated.

The United States Environmental Protection Agency (EPA) first identified

the potential hazardous waste problems at the GEMS landfill in November,

1979. In January of 1980, NJDEP began testing private water wells in the

area for volatile organic chemicals. In June, they expanded their testing

to include surface water, finding leachate contamination in Holly Run and §

Briar Lake. Additional monitoring of both groundwater and surface water

have continued periodically by both NJDEP and Camden County, including

o o

o

scans for priority pollutants. Geophysical testing has included surface o

2-4

Page 31: SDMS Document 112693

n electrical resistivity and terrain conductivity to determine the extent of

leachate migration.

In April 1982, the New Jersey Department of Health (NJDOH) and the Camden

County Health Department conducted a health survey of the population

living near the GEMS landfill. Increased minor respiratory problems were

identified near the landfill, particularly in nonsmoking males. Follow-up

pulmonary function testing was conducted, but data analysis has not yet

been completed. Nevertheless, preliminary results do not appear to verify

the results of the health survey.

NJDEP has determined that the contaminated ground and surface water poses

a potential health hazard to nearby residents. No potable water wells

have been condemned by the State, but HJDEP has recommended that the

Township require residents to hook up to nearby public water supply

systems. Also the State has required that development cease within the

affected area that would require new wells.

As a result of health concerns relating to possible exposure to

contaminated surface water, NJDEP recommended, as early as December 1981,

installing a fence around the entire perimeter of the landfill. Holly Run,

and the swampy area. Subsequently, in May 1982, NJDEP ordered the

Township of Gloucester to construct a perimeter fence to prevent access,

but it has not been constructed, to date. Since then, NJDEP has requested

funding for fence construction from the New Jersey Department of Treasury ,§

under the Spill Compensation and Control Act of New Jersey, and from EPA o

° o o

'k . — a oo

B

B 2-5

Page 32: SDMS Document 112693

I fl under the Comprehensive Environmental Response, Compensation, and

Liability Act (CERCLA/Superfund).

a

I I

a

a

i

a

n •

As of July 1982, the GEMS landfill site has been included on the Superfund

Interim Priority List. The site has also been submitted for inclu.sion on

the National Priorities 400 List. A site chronology, outlining important

events at the GEMS landfill, is presented in Appendix A.

2.3 ENVIRONMENTAL SETTING

2.3.1 Physiography

• The GEMS landfill site is located in the Atlantic Coastal Plain

physiographic province, which extends from Massachusetts to Florida.

Gloucester Township is described as a low lying, gently rolling plain.

Elevations in the immediate vicinity of the GEMS landfill vary from

approximately 50 to 200 feet above mean sea level. The landfill is sited

fl| on a hill, with the natural topographic high at approximately 175 feet

above mean sea level. With the addition of fill material, the top of the

GEMS landfill now has an elevation of approximately 232 feet above mean

sea level. The existing relief is 80 to 100 feet above the surrounding

area.

a

The landfill Is located on a minor watershed divide, sloping downward

towards Tom's Branch to the south and west and towards Holly Run to the ^

east and north. g

M

O

o (Tl

2-6

Page 33: SDMS Document 112693

m H 2.3.2 Geology

B

The geologic formations in Camden County are comprised primarily of

Quaternary, Tertiary and Cretaceous sediments, underlain by pre-Cretaceous

crystalline metamorphic rocks. The sediments consist of alternating

layers of mostly unconsolidated and some semiconsolidated sand, silt,

gravel, and clay. In Camden County, the Cretaceous and Tertiary sediment

layers slope downward to the southeast. The oldest, pre-Quaternary

sediment formations crop out near the Delaware River, while more recent

formations are exposed at or near the surface with increasing distance

from the river. Thin Quaternary formations often overlie the Cretaceous

and Tertiary formations in relatively horizontal layers.

At the GEMS landfill site, the surface sediments belong to the Bridgeton

Formation from the Quaternary Period. This formation consists of fine to

very coarse quartzose sand with some gravel and is typically found as

isolated patches on topographic highs, such as the GEMS landfill site.

The Bridgeton Formation is approximately 10 feet thick in the area of the

landfill.

B

Beneath the Bridgeton is the Cohansey Sand Formation, which consists of

light yellowish brown, fine to coarse, quartzose sand and fine gravel. In

places, this formation contains lenses of silt and clay which can be as

much as 30 feet thick. ^

o o M

O O

o

2-7

Page 34: SDMS Document 112693

a

m

1

Portions of both the Bridgeton and Cohansey Formations were excavated as

part of the early sand and gravel operations conducted at the landfill.

However, details of this mining are not well documented.

The Kirkwood Formation lies beneath the Cohansey Sand, and consists

primarily of sand, silt and clay. Beneath this formation are the

Vincentown and Manasquan Formations, which are often quite difficult to

differentiate. Each consists of very fine to medium, quartzose sand which

is somewhat clayey. Together, they serve as a moderately permeable

confining layer above the Hornerstown Sand Formation. Hornerstown Sand is

composed of sand and clay, contains up to 90 percent glauconite, and also

served as a leaky confining layer.

The Navesink Formation is the most recent of the Cretaceous formations and

underlies the Hornerstown Sand. It is comprised of a dark green to black

glauconitic sand and clay mixed with varying amounts of quartz sand.

Mount Laurel Sand is a gray quartz sand, and changes into the deeper

Wenowah Formation with a finer grain size, darker grain color, and a large

increase in the mica content.

The Marshalltown Formation is a confining layer of silty sand above the

Englishtown Formation, although some vertical leakage occurs. The

Woodbury Clay is a grayish-black micaceous clayey silt and the

Merchantville Formation is a dark gray micaceous clay to clayey silt with

lenses and beds of glauconite sand. The Magothy Formation, the deepest

recorded on the landfill well logs, consists of a series of alternating o

confining clayey beds and sand beds. The profile of geological formations

1 2-8

o

o o

Page 35: SDMS Document 112693

underlying the GEMS landfill is shown in the well log presented in

Figure 2-4.

2.3.3 Surface Water Hydrology

The GEMS landfill is located within the Delaware River Water Basin, which

dominates the surface hydrology in the region. The landfill is located on

a minor watershed divide between Tom's Branch and Holly Run. Holly run

drains the landfill to the east and north, while Tom's Branch drains it to

the west and south. Each stream originates in the vicinity of the

landfill, and the two combine to form South Branch, a tributary of

Big Timber Creek, which in turn flows into the Delaware River south of

Gloucester City.

1Q

Holly Run flows along the northeast side of the GEMS landfill parallel to

the landfill toe. The course of the stream has been illegally relocated

twice next to the Fox Chase II subdivision, to provide space for

additional housing development. As a result, a swampy area has formed

upstream of the >elocation adjacent to existing homes. This area is

wooded, but the roots of the trees are now submerged. Downstream,

Holly Run flows into Briar Lake, a small pond surrounded by recent

development. From there, it flows through a naturally low, swampy area

into the larger Holly Lake.

A ditch has been dug along the northeast side of the landfill, between the

landfill toe and Holly 'Run. Surface runoff that collects in the ditch

flows southeast and discharges into Holly Run. No other ditches or drains

3 t r i

o o

o o NJ

9 2-9

Page 36: SDMS Document 112693

B V B

k 1

1

i i

B

aritffKon Lifht . AaoW MMttf

o( Hi iBOMM Aa* (QwNnary). broMn, fiiM ta wry to t im, e i t u o a •

ColmiMv Smd FonmiiM a< Middh MioeiM A|i. Li|ht Y*<lo«riih brown, f iM ta Mry cMnt griiiMd q i a n i o a and with lo iM b id i of d ty Mid litt. WMtr toM* oquifir i t GEMS wid • mojor muihr in Ctmdtn Cotintv.

Kirkwood Fonnotion o4 Middle Mioenw A f . Li|ht grty to l i fht oliM p t i , i l i(htly floucanitic, riifhtly m i a e n u i , f i m to modium fioinod and with imorboddid tilt and day. A minor oquifir.

Hmooqinn Fomiatien of Eeetno A f t . OliM fray, dayoy, floueonitic quartzoa and. Modwolily yonnofbio csnfininf bod.

Vineontown FortMtion of Poltocani AfO. Olim fray to lifht fray, Hmowhit doyty, nwdium ta fino froinod quoruoa and. Contiins ioa cloy thon Mtnaquon Formotion. A M i y wnflwinf bod.

Homintown Formotion of Eotfy f Cloyoy quorttoa and with o hifh poreontofo of dor* fwwi floMi uiiito. Looky conf ininf bod.

HoMtink Formotion of Uppor Cratooooui A f i . Oork fffon to gray, modoratily to vory eoora, modoratdy floiicanitic quoruoa and and cloy, with o prominom riwll zano i t boa of formotion. A rafionol morkn torn.

Mount Laural Formotion of Uppor Cnaeoeut A f i . Lifht fray, f in i to tsora i n i n i d qua t i oa and. A miior iqui f i r , yii ldinf up to SCO gpm. Qu i l i t yo fwot i r i i f ood , butmaybohi fh in i ron. ^

Winowoh Formotion of Uppor Crotieooui Ago. Dork gray, wry micocoaui, rtty, modium ta lino frainad quortzoa and. A mojor aquifar.

Monhalltown Formotion of Uppor C IO IMMU> Apa. Dark fray, micoeoo«i,iilty glwconita and. A aonfininf t

EnfMitown Formotion of Uppar Craucaout Afa. ' « , dirlc-eolond alty and . Good to poor capabilHY to yiald wator.

VfOadbury day of Uppor CretocMut Ago. 'firayirii block, mai in i mieocooua doyoy l i l t . A canfininf bod.

Marehantvillo Formotion of Uppor Cratocoout Ago. Oork gray to f roy i# block micocoout clay to cloyay Mt with bodt ond laniai of f louconlta and. Laokyconfininf bodandaminoroquifor.

Mofothy Formation of Uppor Cratacooui Afo. A a r i n of contininf cloyoy bodt with and bodt which cwi yiold wproiimataly 1000 gpm bl tha GEMS ana. Along with Rorinn Formation, i i tho mojor oquifor in Camdan County.

Atlor "Iwfoco ond Grsvndwww In ia t lp i l o i i of tha GEMS Uadf i l l , " by NJDEP.

Figure 2—4

GEMS Landfill Well Log

Page 37: SDMS Document 112693

] -'' currently exist to collect surface runoff. Consequently, most surface

drainage from the landfill will occur by unchannelized flow, percolation

4 and evaporation.

I 2.3.4 Hydrogeology

I Several of the geologic formations described in Section 2.3.2 serve as

W^ aquifers for private and commercial water supplies in the vicinity of the

landfill and throughout Camden County. The Bridgeton Formation lies above

^ the local water table, which is located in the Cohansey Formation. Deeper

• lithologic units, including the Kirkwood, Wenowah-Mount Laurel, and

Potomac-Raritan-Magothy aquifers, are important as water supplies.

H Manasquan, Vincentown, Hornerstown, Navesink, Marshalltown, Englishtown,

Woodbury and Merchantville Formations are considered to be aquitards in

' - the area. They are generally not capable of producing enough water for

major potable uses but are able to transmit some water to lower aquifers.

These formations can be characterized as moderately permeable confining

beds.

a a • a

The aquifers are recharged by local rainfall, primarily in the region

where the ^rmation crops out near the ground surface. However, minor

recharge likely occurs through aquitards into lower water bearing

H formations. The average rainfall in the region is 42 inches per year.

B fl

Q

The general quality of groundwater varies between aquifers and throughout g

Camden County. Water from the Cohansey Sand is generally suitable for o o

potable use after treatment. Typical characteristics of water from this --J

2-10

Page 38: SDMS Document 112693

aquifer include low pH, high iron concentration, undesirable color, low

dissolved solids content, and low hardness. The Kirkwood Formation

produces water which is generally soft, but high in dissolved solids and

iron content. Water from the Wenowah-Mount Laurel aquifer generally is

suitable for potable use except for high iron concentrations. It often

has low levels of dissolved solids, sulfates and chloride, and hardness

ranges from soft to moderately hard. Local wells tap primarily into the

Cohansey Sand, Mount Laurel Sand, Magothy and Vincentown-Hornerstown

Formations.

NJDEP conducted geophysical investigations in the fall of 1980 to

determine the extent of the contaminated plume emanating from the

landfill. Both surface electrical resistivity and terrain conductivity

tests were conducted, in conjunction with chemical analyses for volatile

organics. The results of these studies are presented in a January, 1981

report entitled, "Surface and Groundwater Investigation of the Gloucester

Environmental Management Services, Inc. (GEMS) Landfill."

From these results, NJDEP concluded that the GEMS landfill is responsible

for both ground and surface water contamination and that contamination is

emanating from all sides of the landfill. Also, water from the Kirkwood

and Mount Laurel aquifers contains volatile organic chemicals similar to

those detected in leachate and stream samples near the GEMS landfill.

Consequently, NJDEP has concluded that the GEMS landfill is a contributing 3

factor in the contamination of these aquifers. o o i->

o o cn

2-11

Page 39: SDMS Document 112693

i |(L An abbreviated groundwater elevation survey was conducted in the vicinity

of the Fox Chase II development in October, 1980 by NJDEP. The survey

I indicated that groundwater elevations of the water table (shallow) aquifer

reflect topographic elevations and that contaminants are emanating from

the landfill rather than being carried from another upstream point in

Holly Run. 1 I m 2.3.5 Air Quality

I a

Air sampling has been conducted several times in the vicinity of the GEMS

landfill to determine air contaminant exposure by nearby residents.

Sampling was conducted during January and February, 1982 by EPA/Technical

ajl Assistance Team in the Briar Lake development. No volatile organics were

recorded immediately exterior to the-dwellings. However, total volatile

organics were detected in the house basements at levels between 5 and

^ - 975 ppb. Because this study did not rule out the possibility that

household items were the sources of contamination, additional studies are

being conducted. Volatile organics were also measured on top of the

landfill in August, 1982, finding up to 100 ppm intermittantly being

released through vent cracks in the cover material.

At the GEMS site, NJDEP monitored ambient air quality in June, 1982.

Measurements were conducted using an HNU Detector, calibrated for benzene.

The background reading was found to be 3 ppm benzene. At one location, ^ 3

two-thirds the way up a 60 percent slope on the landfill, measurements of o

5 ppm benzene were recorded at ground, waist, and overhead levels. ^

o

o

2-12

Page 40: SDMS Document 112693

[] P^ Testing for explosion risk in the vicinity of the landfill was conducted

in May, 1981 by NJDEP. An MSA explosive gas meter probe was used to

detect explosion hazard 3 feet deep in the ground. Readings of

100 percent of the lower explosion limit, calibrated as methane, in air

were detected in several locations including along Holly Run, within

• 100 feet of Fox Chase II residences, along the south and west sides of the

landfill, and near the swamp at the end of Holly Run Drive.

I I

I ]

a

A health survey (April, 1982) has been conducted on the population living

near the GEMS landfill by the State Department of Health in cooperation

B with the Camden County Health Department. A standard set of questions was

asked of 122 households in the immediate vicinity of the landfill as well

as a control group of residents living several miles from the landfill.

Statistical analyses of the questionnaire results were performed

separately by sex and smoking status. Results of the study indicated an

increase in minor respiratory ailments of residents near the landfill,

particularly in nonsmoking males. However, because a difference was found

between affects on males and females, the researchers could not conclude

definitively that the respiratory problems were associated solely with

local air pollution. Pulmonary function testing has been conducted to

determine whether the symptoms reported are associated with a decrement in

breathing function. Preliminary results do not support the earlier

questionnaire results.

a a I a I 1 I

o 3

2.3.6 Ecology o o

o o ^ •

2-13

Page 41: SDMS Document 112693

n

m

n

Land use in the vicinity of the GEMS landfill varies considerably. Much

of the surrounding area consists of recent suburban development. Near the

southeast corner of the site is a cement manufacturing and welding

operation. Much of the surrounding area remains undeveloped and wooded.

Nearby, to the north, is an area of maintained motorbike trails. The

trees from this area have been removed and the ground remains mostly

barren.

The landfill, itself, rises above the surrounding landscape by 80 to

100 feet. Most of the landfill is vegetated by a variety of annual and

perrenial weeds and grasses. Some larger shrubs have begun to take hold

in areas. Nevertheless, a substantial portion of the landfill remains

unvegetated. The brushy habitat is ideal for supporting rabbits and other

rodents, and their predators, such as hawks and foxes. In a NJDEP

evaluation of the site using the Mitre Model, critical environments for

the Cooper's hawk and the bog turtle have been Identified.

In the area that Holly Run has been relocated, the ground is sparsely

covered by grasses, bush clovers and other weedy vegetation capable of

growing in sandy, relatively infertile soil. Upstream of the relocation,

decidous trees are how located with their roots submerged beneath the

water. Many of these trees have been adversely affected and denuded by

the stream relocation, either by the increase in water level or by the

presence of volatile organics. Other trees along the stream bank which ^ t r

have not been affected by an increased water table have also been denuded,

indicating that the volatile organics are contributing to the foliage o o

D

shock. o o

CO

2-14

Page 42: SDMS Document 112693

II

n

I

D

2.3.7 Socioeconomics

Possible impacts of a hazardous landfill in residential areas include

lowered property values, decreased dwelling occupancy, discontinued

development, or lost work days due to illness. Further development in the

vicinity of the landfill has been ordered to cease by NJDEP if individual

wells would be required to supply potable water.

Citizens and public officials in the area of the landfill are aware of the

potential health problems, and are concerned about the spreading of

chemicals via groundwater to their wells and into their basements. This

acute public awareness is evidenced by the number of complaints and

requests for information received by local and state officials, and the

extensive press coverage of the landfill concerns.

If the landfill is properly closed and leachate migration can be

controlled, then local social and economic conditions can be revitalized.

However, until this occurs, negative impacts will continue.

2.4 HAZARDOUS MATERIALS CHARACTERIZATION

Extensive monitoring for hazardous chemicals has been conducted by NJDEP

and the Camden County Health Department. Hazardous chemicals have been

identified in the groundwater, surface water, air, and landfill surface 3

soils. The nature of the hazards in each vary and are discussed

separately below.

2-15

o o

o o

Page 43: SDMS Document 112693

axrmt. uui i ^ '- .-:.<i3KliH

1 J

2.4.1 Groundwater

Extensive monitoring of the-groundwater in the vicinity of the GEMS

landfill has taken place by NJDEP and the Camden County Health Department.

Analysis of samples has been performed by the NJDOH Laboratory and a

variety of private laboratories. Samples have been collected from 22

potable water wells and from 13 monitoring wells installed specifically

for this testing. Most samples were tested using only a volatile organic

scan. However, a complete priority pollutant scan was conducted on

samples collected March 9, 1982.

A summary of contaminants identified in groundwater near the landfill is

presented in Table 2-1. Maximum concentrations are presented for each

general compass direction from the landfill. A distinction has been made

between potable water wells and monitoring wells, because the monitoring

wells are generally closer to the landfill and draw samples of shallower

groundwater than do the potable wells. Also, contaminants in potable

wells indicate a more immediate public health concern than when found in

monitoring wells.

A summary of the depths at which specific contaminants have been

identified is presented in Table 2-2. Wells exist only at a limited

number of depths in each direction from the landfill. Consequently,

contamination by specific compounds could range considerably beyond those 3 f

o depths which have been identified. o

o o 00 o

2-16

Page 44: SDMS Document 112693

1

I 1 I I 1 a a

a a a a a a •

Table 2-1 GROUNDWATER CONTAMINANTS IDENTIFIED IN VICINITY OF GEMS LANDFILL

Maximum Concentration Identified (ppb)^ Potable Monitoring Well Type

Direction from Landfill East

Chemical

Benzene Chlorobenzene Carbon Tetrachloride 1,1,1-Trichloroethane 1,1,2-Trichloroethane Tetrachloroethane 1,1-Dichloroethylene 1,2-Dichloroethylene Trichloroethylene Tetrach1oroethy1ene Chloroform 1,2-Dichloropropane Cumene Decane Ethylbenzene Mesitylene Methylene Chloride Toluene Xylenes (m-, o-, p-)

0.8 1.4 70

360

17.6

3.0 10 20

7.1 440

South

4.8 10.0

1.8

40 22.4 0.6 2.1 7.1

West North East South

6.7 14.3 12.7

6.2

0.7 10.1

7.1

Total Volatile Organics 890

1.9 2.6

45.4

2.4

32.3 19.8

* * * * * * * * * * *

* * * * * * *

136

8.4

18

6.3

5.0 2.2 1.1 1.3

2.3 6.9

200

West

57

31

- Not detected * Not analyzed

Data derived from "Summary of Surface and Groundwater in the Vicinity of the GEMS landfill." by NJDEP, June 1982 (see Appendix B).

RW27/18

260 144

110

210 53 180

947

o o CO

a

Page 45: SDMS Document 112693

Table 2-2 DEPTHS AT WHICH GROUNDWATER CONTAMINAN

HAVE BEEN IDENTIFIED

i^£J 'Mi JI

Range of Depths (feet)

Direction From Landfill

Chemical

Benzene Chlorobenzene Carbon Tetrachloride 1,1,1-Tri chloroethane 1,1,2-Trichloroethane Tetrachloroethane 1,1-Dichloroethylene 1,2-Dichloroethylene Trichloroethylene Tetrachloroethylene Chloroform 1,2-Dichloropropane Cumene Decane Ethylbenzene Mesitylene Methylene Chloride Toluene Xylenes (m-, o-, p-)

Total Volatile Organics

- Not Detected

East

250 250 250

250

250 250

70-250 70 250

250 250

20-250

South

17-234

West

60-90 60-90

17-70

17-37 60-90

60-234 • -

17-234 17-90

17-37 17-37 17-37 17-37

17-234 17-70 17-37

15-90 90

15-30

«, -

175-350 15-30 15-350 90-350

.

-

15-30 -

15-350 15-30 15-30

13-350

North

205

205

205

NOTE: Wells do not exist in the entire depth range (0 - 350 feet) in all directions from the landfill.

RW27/70

c. 3 tr>

o o

o o bo

i

Page 46: SDMS Document 112693

II

t

The sources of these chemicals prior to disposal at the landfill is not

known, and a list of companies which have deposited chemicals at the

landfill was not available for the preparation of this RAMP. For

approximately three weeks in 1970, the landfill was authorized to accept

chemical wastes from Rohm and Haas, but permission was revoked after a

chemical fire occurred that was related to these wastes. In 1973, arsenic

and salt wastes were brought to the landfill from the Vineland Chemical

Company.

Evidence exists indicating that chemicals may have been deposited at other

times in the landfill. In January 1977, SWA issued a Notice of

Prosecution to GEMS for their disposing of unauthorized chemical wastes in

the landfill. Incomplete records suggest that chemical wastes may have

been deposited beneath the groundwater table during operations of the

landfill prior to 1970. Also, numerous fires have broken out at the

landfill, some showing evidence of being chemically related. In March

1973, during a fire, a NJDEP Inspector noted two 55 gallon drums that were

spilled on the ground. The liquid was observed to look like #6 Bunker "C"

o n and smell like acetone and toluene.

A major source of groundwater contamination is likely leachate from the

landfill. Testing of leachate near Holly Run on three separate dates

shows that it is also highly contaminated by volatile organics. Results

of these analyses are presented in Table 2-3. Many of the pollutants

identified in the leachate are the same as those found in groundwater. o

However, 1,1,2-trlchloroethane, 1,1-dichloroethylene, 1,2-dichoroethylene, ^ o

and 1,2-dichloropropane have been identified in groundwater but not in S

2-17

Ti

o

Page 47: SDMS Document 112693

a m

B B B B B B B

B

B

Table 2-3 LEACHATE CONTAMINANTS ENTERING HOLLY RUN

Date Sampled

Parameter

Total Conforms (MPN/100 ml) Fecal Conforms (MPN/100 ml) Fecal Streptococci (MPN/lOOml) Chemical Oxygen Demand (mg/1) Total Dissolved Solids (mg/1) Chloride (mg/1) 5-Day BOD (mg/1) Dissolved Oxygen (mg/1) Iron (mg/1)

Volatile Organics (ppb)

Benzene Bromodichloromethane Chlorobenzene . . 1,2-Dichloroethane 1,1,1-Tri chloroethane Tetrachloroethane Trichloroethylene Tetrachloroethylene Chloroform

Volatile Organics (ppb)

Cumene Decane Ethylbenzene Mesitylene Methylene Chlori de Propylbenzene Toluene M-Xylene + P-Xylene O-Xylene PCBs Pesticides

Maximum Concentration Identified

6/24/80°

540 49 79

2903 2158 63

7520 0.2

36.02

592

9/18/80^ 11/6/80'

>50,000

>50,000 >50,000 >50,000

* *

479 954 453

* *

289

22 245 18 18 36

6.3 144

5.0 2.2

3.1 62 34 598 78 58

* * * *

* * * *

84 853 17

25,153 59

67 27

270

54

- Not detected * Not analyzed t r

^

One leachate sample

'TWO leachate samples

'Three leachate samples

RW27/19

o

o o 00 •Ck.

Page 48: SDMS Document 112693

I 1-^ leachate. Of these four compounds, only 1,2-dichloroethylene, and

1,2-dichloropropane have been identified in the same area that leachate

sampling took place. I !

i I E

a

q a a a a

These data should not be considered a complete summary of all groundwater

monitoring to date, because NJDEP and Camden County continue to conduct

testing around the GEMS landfill. A summary report of monitoring data,

prepared by NJDEP, is Included in Appendix B, which gives more specific

information concerning sampling locations and dates.

It should be noted that the levels of contamination have not been

consistent between sampling times. In particular, a private well (Hurst)

I was sampled on five separate occasions. The result of this sampling is

^ presented in Table 2-4. In three samples, volatile organics were not

detected. In one sample, total volatile organics were found at a level of

29 ppb, and in another, at 890 ppb. Also, the specific compounds

identified change considerably. These variations are much greater than

I normally expected from groundwater monitoring. NJDEP has concluded that

the results from the sample taken March 9,.1982 is inconsistent with other

data available, and have referred to it as a "statistical anomaly".

Additional groundwater sampling should be conducted to better characterize

contaminant concentrations in potable water wells.

a

2.4.2 Surface Water Q 3 f

o

Contamination of the surface water is apparent from a visual inspection of 3

Holly Run and the swampy area near Fox Chase II. Inspection reports by o

o 00 Ul

2-18

Page 49: SDMS Document 112693

m

Sample Date

09/22/80

11/17/80

10/27/81

03/09/82

Table 2-4 CONTAMINANT VARIATION IN THE HURST WELE

Chemical

fk M i "^-^ M Ta '

04/29/82

1,2-Di chloroethylene Methylene Chloride Tetrachloroethylene Chlorobenzene Toluene Benzene Trichloroethylene

Total Volatile Organics

Volatile Organics

Volatile Organics

Carbon Tetrachloride 1,1,2-Tri chloroethane Toluene 1,2-Dichloropropane

Total Volatile Organics

Volatile Organics

Concentration(ppb)

17.6 7.1 0.9 1.4 0.7 0.8 0.6

29.1

N.D.

N.D.

70 360 440 20

890

N.D.

N.D. - Not Detected

Data from "Summary of Surface and Groundwater in the Vicinity of the GEMS Landfill," by NJDEP, June 1982 (see Appendix B)

RW27/17

k 3 IT*

o o

o o oo

Page 50: SDMS Document 112693

]

i Surface water testing has been conducted at several points along Holly Run

WT' which runs parallel to the northeast side of the landfill. Samples have

I i i

a

a a a B B

NJDEP have indicated at times a red oily sheen has covered the entire

width of the stream. Strong odors emitted from the stream are a further

indication of volatile organic contamination.

also been taken from Briar Lake, located to the north of the landfill, and

through which Holly Run flows. Only one sample has been taken from Tom's

Branch, a stream located south of the landfill. A summary of analytical

results is shown in Table 2-5.

Many of the major contaminants are the same as those found in the

• groundwater and leachates, including benzene, chlorobenzene,

1,1,1-trichloroethane, trichlorethylene» chloroform, cumene, decane, ethyl

^ benzene, mesitylene, methylene chloride, toluene and xylenes. However,

there are also many contaminants found in surface water but not identified

in leachate, including benzofuran, carbon tetrachloride,

H 1,2-d1chlorobenzene, 1,3-dlchlorobenzene, 1,1-dichloroethane,

1,1,2-tri chloroethane,1,2-di chloroethane, 1,1-di chloroethylene,

2,2,2-trifluorotoluene, heptane, nonane and octane. The only compound

identified in leachate but not in the surface water is

bromodichloromethane.

c During metals testing, cadium and lead were found in Holly Run, while very ^

high concentrations of iron were found in Briar Lake and downstream in o o

Holly Run. o o CO

2-19

Page 51: SDMS Document 112693

I .

Table 2-5 SURFACE WATER CONTAMINANTS IDENTIFIED IN VICINITY OF

Chemical

Volatile Chemicals Benzene Benzofuran Carbon Tetrachloride Chlorobenzene 1,2-Di chlorobenzene 1,3-Di chlorobenzene 1,1-Dichloroethane 1,2-Dichloroethane 1,1,1-Trichlorothane 1,1,2-Trichloroethane Tetrachloroethane 1,2-Dichloroethane 1,1-Dichloroethylene Trichloroethylene Tetrachloroethylene Chloroform Cumene Decane Ethylbenzene 2,2,2-Trifluorotoluene Heptane Mesitylene Methylene Chloride Naphthalene Nonane Octane Propylbenzene Toluene M-Xylene + P-Xylene 0-Xylene

Total Volatile Organics

Metals Cadmium Lead Iron

Not detected

Maximum Concentration Identified (ppb)

One sample only

^Downstream from Briar Lake

Holly Run

251

240 37 110

250 155 102 53

750 110 10

936 9.5 146 60

67 1.4 152

212 95 20

816 172 77

2162

30

' 2 14880

Briar Lake

2400 10

130 6 8 48 80 30 70 320 8 5

34 2 7

90 34 2

46

8 4000 163 92 86

3300 16 6

10,378

37,760

Tom's Branch

40

80

120

3

o o

o o 00 00

• Data from "Summary of Surface and Groundwater Monitoring in the Vicinity of the GEMS Landfill," NJDEP, June 1982 (see Appendix B).

RW27/20

Page 52: SDMS Document 112693

D f/t- Volatile organics were also identified in the sediment from Holly Run and

Briar Lake, as shown in Table 2-6. Only one compound was identified in

each, and the two sediment samples contained different chemicals. B n B

n B B " ^

B

ia ia t

ia

i

2.4.3 Ai£

Air sampling was conducted in the area of GEMS landfill during December

1982 and January 1982 by the New Jersey State Department of Health

(NJDOH). The interiors of 26 homes and a Catholic retreat house were

tested, as well as 15 exterior locations, 4 of which were at the landfill

itself. The samples were analyzed by the NJDOH, Division of Laboratories

for volatile organics. A listing of those contaminants and the

concentrations found is shown in Table 2-7, Sampling was done using

charcoal tubes and constant flow air sampling pumps at a sample rate of no

more than 1 liter of air per minute with a minimum of 200 liters of air

collected per sample. Interior samples were taken in the basements or

otherwise at the lowest level of the homes.

Table 2-8 indicates the number and percent of homes with one or more

contaminants detected. No contaminants were detected in the outdoor air

samples (Table 2-9). Table 2-10 shows the frequency of detection in

interior samples for each specific contaminant.

Standards for the workplace environment are available thru OSHA and NIOSH.

These limits, PEL (Permissible Exposure Limit) and TLV-TWA (Threshold

o 3

o o

m

Limit Value-Time Weighted Average), are the maximum allowable o CO

concentrations of contaminants that a worker may be exposed to over an ^

2-20

Page 53: SDMS Document 112693

n

H "Tab e 2-6 ^ SEDIMENT CONTAMINANTS IDENTIFIED IN SURFACE WATER NEAR GEMS LANDFILL mm Maximum Concentration Identified (ppb) m Chemical Holly Run' Briar Lake"

B Chlorobenzene - 7.2

1,1,1-Trichloroethane 1.8

- Not detected

Data from "Summary of Surface and Groundwater Monitoring in the Vicinity of the GEMS Landfill," NJDEP, June 1982 (see Appendix B).

o 3 tr

o o

RW27/21 g o

Page 54: SDMS Document 112693

L •il-^g-^^ j i - jr-'M^WrWrWrm-w-m Table 2-7

GEMS STUDY-CONTAMINANTS FOUND In ter io r Air Samples In ppm

o 3

o o

o o

S I u -8 s

01

c:

a.

0) c «

n U J

V

V •

> i

M

£

¥

« o o

>» J!

«

1 o J Z u

• -0 - »

) - l

^ a , ••-» c II

1

cn o ^ u u t i J u

? <« a.

e M

C

N C

B O

u a 1

£

1 -

2

3

4

5

6

7

B

9

10

11

12

13

14

15

16

17

18-

19

20"

21

22

23

Z4

25

2fi

Z7

- . O M

" 0 0 4

.013

.005

.005

.032

.005

" . 0 8 0

" . 0 0 4

- . 0 0 5 •

.008

- . 0 0 5

- . 0 0 5

.008

.005

.005

.029

.007

.041

.005

.006

.027

. 0 0 9

. 0 0 9

.116

. 008

.007

. 008

. 0 1 9

. 048

.008

.004 •

. 0 5 7

.039

.007

.097

.106

.035

. 0 8 3

. 308

.107

. 028

. 048

. 0 7 3

.056

. 108

. 108

.024

.1130

.009

, 033

.007

.010

.012

. 041

.018

.004

.004

. 0 0 5

.034

.016

•s;; ..,

7008'

.013

.038

.014

-

.012

.023 :

.012

.004

.152

.022

.001

.007 •

•.014""

.007

.004

.002

.057

.003

. 0 1 4 " "

.003

.006

.008

.006

. 0 0 7

.017

:oi7

.075

.045

.041

.016

.005

.008

.013

.015

.DID

.019

.019

.008

.005

.025

.286

.411

.006

.025

".015

.039

.331

.023

.012

.061

.113

.007 •

.102"

.106

.082

.035

.329

.431

.115

.298

.051

.011

.008

.340

.056

.114

".005

TOOS

.056

.412

" : i i i

.497

• .015

.475

.009

. . - k r O T - ^ ^ ' . - . t . ; / , ,

fclSlSii^

^ ^ ^ ^

mim.^.i^rfiM

Page 55: SDMS Document 112693

n B

B Location

Elevation Upper Lower Other

Table 2-8 INTERIOR AIR SAMPLES-GEMS STUDY

FOR ANY VOLATILE ORGANIC CHEMICALS

#Households With ND To 10 ppb

3 1 4

#Households With 10 ppb

8 3 7

' / f

11 4 11

Total % > 10 ppb

73% 75% 64%

Total 18 26 69%

Table 2-9 EXTERIOR AIR SAMPLES-GEMS STUDY

FOR ANY VOLATILE ORGANIC CHEMICALS

Location

Elevation Upper Lower Other

Total

#Household With ND To < 10 ppb

3 1

11

15

#Households With z 10 ppb

0 0 0

0

Total

3 1

11

15

%_ 10 > ppb

0 0 0

0

Data from report by NJDOH.

la Ci 3 t r

o o

RW27/23

o o " . NJ

Page 56: SDMS Document 112693

Table 2-10 FREQUENCY OF DETECTION OF INTERIOR

AIR CONTAMINANTS

Chemical

TLV/10 TLV/100* Detected Frequency of Detection in ppm or or Range in None

PEL/10 PEL/100 ppm Detected .01 .01-.09 .1-.9

Toluene 20 ppm 2 ppm 0-.080 17

Pentane

Butane

Hexane

Xylene

Octane

Decane

Undecane

Benzene

Nonane

1,2,4-1 nmethyl-benzene

Propylbenzene

Ethylbenzene

Mesitylene

Methyl Cyclo Hexane

1,1,1-Trichloro­ethane

C15 1,3-Dimethyl Cyclo Hexane

Isopropanol

Para-Dichloro-benzene

100 ppm

80 ppm

50 ppm

10 ppm

50 ppm

1 ppm

2.5 ppm

10 ppm

10 ppm

35 ppm

7.5 ppm

10 ppm

8 ppm

5 ppm

1 ppm

5 ppm

.1 ppm

.25 ppm

1 ppm

1 ppm

3.5 ppm

.75 ppm

0-.116

0-.306

0-.033

0-.041

0-.038

0-.1S2

0-.057

0-.008

0-.075

0-.045

0-.013

O-.OlS

0-.019

0-.008

0-.411

0-.025

0-.331

IS

12

23

17

23

21

18

23

23

24

25

25

25

24

24

24

26

24

g

1

1

4

1

1

6

4

1

0

1

0

0

2

0

1

0

0

3

d

3

6

3

4

3

0

3

3

1

2

2

0

1

2

1

2

1

5

0

0

0

1

0

0

0

0

0

0

0

0

2

0

0

1

* TLV/100 or PEL/100 is an arbitrary figure to show an additional safety factor. Above data from interior air samples from 26 homes and a catholic retreat house.

Data from report by NJDOH.

RW27/24

a 3 tr

o o

o o CO

Page 57: SDMS Document 112693

il

il

eight hour shift and 40 hour work week without any adverse health effects.

The American Society of Heating, Refrigerating and Air Conditioning

Engineers (ASHRAE) has typically specified that air used for ventilation

purposes in the indoor environmental must not contain contaminants at

concentrations greater than one-tenth the TLV-TWA. The TLV is chosen

because it provides a good margin of safety for an 8-hour daily exposure.

ASHRAE has added additional and substantial safety margins using the TLV

divided by 10 formula. From the comparison of these limits to levels

found in homes near the GEMS landfill (Table 2-10), NJDOH has made the

preliminary conclusion that concentrations found are not expected to cause

serious health problems. NJDOH has resampled air from the earlier test

locations, but the results are not available for the preparation of this

RAMP. Results from both sampling episodes should be evaluated by a

toxicologist before final conclusions are drawn.

Ambient air sampling by NJDEP detected background readings of 3 ppm

benzene. On one slope of the landfill, benzene concentrations increased

to 5 ppm at ground, waist, and overhead levels. At other locations, no

benzene was detected.

2.4.4 Cover Material

Several old Imhoff Tanks were demolished in the process of upgrading o

Philadelphia's Northeast Water Pollution Control Plant (NEWPCP). The

debris from demolition of these tanks was transported to the GEMS landfill

2-21

f

o o

beginning in October, 1980, and used as landfill cover material. o

Page 58: SDMS Document 112693

n The Imhoff tanks were designed to remove and anaerobically digest

settleable wastewater solids. After 1951, the Imhoff tanks at NEWPCP were

abandoned and used only in emergencies when the treatment plant was not

operating properly. However, sewage sludge remained in the tanks until

its removal in 1980. Periodically, between 1951 and 1980, sewage grit,

bar screenings, sewer inlet debris, and small amounts of municipal refuse

were added to the tanks.

Material transported to the GEMS site included approximately 30,500 cubic

yards of steel reinforced concrete and approximately 40,000 cubic yards of

tank contents. It was estimated that the tank contents included

approximately 4,000 cubic yards of municipal refuse and 36,000 cubic yards

of stabilized sludge and grit.

On December 29, 1980, sludge being transported to the GEMS landfill from

the Philadelphia Imhoff tanks was spilled near the landfill, causing a

road hazard. The spilled material was sampled by state inspectors and

found to be contaminated by DDD. Subsequently, material deposited on the

landfill was tested and found to contain^DDD and DDE, which are metabolic

products of the pesticide DDT.

Twelve locations on the landfill, including the top edge and side slopes

around the entire perimeter, have been identified as having Philadelphia a 3

sludge deposited on them. The results of NJDEP testing for chlorinated t

pesticides are shown in Table 2-11. o (-1

o o vo cn

2-22

Page 59: SDMS Document 112693

II

B n

a

Constituent

Aldrin Chlordane Endrin Lindane p,p' - DDD o,p' P.P'

DDD DDE

o,p' - DDE DDT Toxaphene Methoxychlor

Site 1

1.7 0.86 0.67 0.060

Table 2-11 CHLORINATED PESTICIDE SCREEN

Sample & Designation Site 2 Site 3 Site 4 Site 5 Site 6

8.4 2.8 2.2 0.88

4.4 1.8 1.4 0.10

2.4 0.90 1.1 0.086

1.0 0.44 0.80 0.14

6.1 2.8 3.1 0.24

Constituent

Aldrin Chlordane Endrin Lindane p,p' - DDD o,p' - DDD p,p' - DDE o,p' - DDE DDT Toxaphene Methoxychlor

Site 7 Site 8 Site 9 Site 10 Site 11 Site 12

7.4 2.1 1.5 0.12

:o 5.7 6.8 0.75

4.6 1.9 1.7 0.10

3.3 1.6 1.1 0.14

4.1 2.0 3.0 0.23

1.3 0.46 0.55 0.030

All results are in micrograms of consituent per gram of sample.

- Less than 0.1 microgram of constituent per gram of sample.

Data from Stabler Reutter Test Report No. 5-1356 for NJDEP Solid Waste Division.

Ci 3 f

o o

RW27/25 o o vo <7\

Page 60: SDMS Document 112693

I

a I

flb The City of Philadelphia Water Department conducted independent sampling

(March 10, 1981) and analysis on the sludge deposited. These additional

tests confirm the presence of DDD and DDE (Table 2-12). DDT was also

identified during this analysis. However, the Soxhlet extraction

technique used for identifying these compounds is not representative of

the amounts available through leaching. Consequently, an EPA Extraction

Procedure (EP) analysis was also conducted to determine if the samples

were hazardous wastes as defined in 40 CFR Section 261.24. Results of

these EP Toxicity Tests for pesticides at four of the twelve locations are

shown in Table 2-13. DDD, DDE, and DDT could not be detected using this

procedure. Metals were also tested by the RCRA EP Toxicity Test with the

results shown in Table 2-14, Resampling by the Philadelphia Water

Department was conducted in April 1982 with similar analytical results.

2.5 ASSESSMENT OF POTENTIAL IMPACTS

2.5.1 Public Health and Safety

Several potential threats to public health and safety exist due to the

presence of the GEMS landfill. Including:

0 Private drinking well contamination

0 Access to contaminated surface water

0 Access to landfill s

0 Flooding of contaminated surface water o B

Q

0 Volatile organics in household basements

2-23

o

o 0 Air pollution from volatile organics °

Page 61: SDMS Document 112693

I

a 9 1

2 3 4 5 6 7 8 9 10 11 12

Table 2-12 ANALYSIS OF MARCH 10, 1981 SAMPLES (PPM)

FROM GLOUCESTER TOWNSHIP LANDFILL

Site No. o',p'DDE p',p'DDE o'.p'DDD p',p'DDD o',p'DDT p',p'DDT

2.5 4.7 6. 2. 2. 15. 6.9 9.3 4.4 3.2 2.6 4.1

1.5 2.5 2.2 2.7 2.7 2.9 3.6 12.0 1.7 1.0 2.5 1.4

3.2 14.0 20.0 3.2 1.3 13.0 13.0 19.0 6.3 4.0 3.8 0.8

8.7 33.0 57.0 7.9 5.4 34.0 22.0 49.0 11.0 9.0 8.3 3.3

0.8 2.4 5.3 0.8 5.3 12.0 6.0 2.9 1.5 1.1 1.6 3.2

0.4 1.8 3.1 0.4 0.4 0.8 0.9 1.9 1.0 0.6 0.8 2.6

Average 5.32 3.05 8.47 20.7 3.58 1.25

Data from City of Philadelphia

RW27/26

a 3 tr

o o

o o vo 00

B

Page 62: SDMS Document 112693

m Table 2-13

RCRA EXTRACTION PROCEDURE (EP) TOXICITY TEST ON MARCH 10, 1981 SAMPLES

FROM GLOUCESTER TOWNSHIP LANDFILL

1

Site No.

08 09 10 11

Description

Site 6 Site 7 Site 8

Composite

(p.p.m.) 2,4 D

BD .001 BD BD

Si 1 vex

BD BD BD BD

MCL 10.0 1.0

i n U o . DescHEtlon 0,^:000 ^ ^ ^ o ^ ^ ^ ^ ^ ^ ^ o ^ ^ I M ^ . ^ ^

08 09 10 11

Site 6 Site 7 Site 8 Composite

BD BD BD BD

BD BD BD BD

BD BD BD BD

BD BD BD BD

BD BD BD BD

BD BD BD BD

Site No.

08 09 10 11

Description

Site 6 Site 7 Site 8 Composite

Lindane

BD BD BD BD

Endrin

BD BD BD BD

Methoxychlor

BD BD BD BD

Toxaphene

BD BD BD BD

MCL .4 .2 10.0 0.5

BD - Below Detectable Limits MCL - Maximum Contaminant Level

Data from City of Philadelphia

Q 3 tr"

RW27/28 o o

o o vo vo

Page 63: SDMS Document 112693

a I i

a a

Table 2-14 RCRA EXTRACTION PROCEDURE (EP)

TOXICITY TEST ON MARCH 10, 1981 SAMPLES FROM GLOUCESTER TOWNSHIP LANDFILL

U d <

Site No. Ba Pb ia Cd Se Hg As

MCL - Maximum Contaminant Level

Data from City of Philadelphia

RW27/27

Cl

6

7

3

Composite of 2 Samples

MCL

0.68

1.52

1.96

1.04

100 •

0.44

0.17

0.50

0.28

5.0

0.02

0.01

0.01

0.01

5.0

0.70

0.65

0.75

0.49

1.0

0.1

0.1

0.1

0.1

1.0

0.00193

0.00073

0.00090

0.00060

0.2

0.009

0.043

0.011

0.062

5.0

0.15

0.01

0.10

0.01

5.0

Q 3 t r

o o

o o

Page 64: SDMS Document 112693

a

fl fl

n

0 Long-term contamination of deep aquifers

0 DDD-contaminated dust.

Well contamination, access to the landfill and surrounding surface water,

and contaminated basements appear to pose the most imminent problems

associated with the landfill. The degree of other potential health

problems has not yet been adequately evaluated and may pose longer term

health impacts.

Within one mile of the landfill, approximately 1000 people are served by

260 private wells for water supply. Although some draw water from deep

aquifers, other wells are relatively shallow, drawing water from the

Cohansey Sand and Kirkwood aquifers. Contamination of private wells in

the vicinity of the landfill has been indicated, but not conclusively

proven as the result of variable data.

Although no toxicological studies have been conducted to date, NJDEP has

determined that no immediate potable water emergency exists.

Consequently, NJDEP has not required the Garden State Water Company to

extend its public supply system to affected areas. However, NJDEP

considers there to be a immediate threat, and has suggested that the

Township of Gloucester require residents to tie into the public system at

their own expense. Further development near the landfill has been ^ 3 IT"

prohibited if private water wells are to be used. One private well was o

found to contain 890 ppb volatile organics, which is greater than the 3

100 ppb total organics level at which State officials can condemn a o

potable well. The well has hot been condemned because of inconsistent

2-24

o

Page 65: SDMS Document 112693

n

data, but it has been recorranended to the residents that they discontinue

using water from that well. No other wells have been found to be

contaminated at levels greater than 100 ppb total organics.

Houses exist in the subdivision of Fox Chase II, which are within 100 feet

of an open swampy area and within 250 feet of Holly Run, both of which are

heavily contaminated with volatile organics. Houses are also located

within several hundred feet of Briar Lake, which is also contaminated. A

3-foot fence exists along portions of Holly Run and the swampy area but

has fallen in places making access easy.

Culverts under Briar Lane, an unpaved road, do not have the hydraulic

capacity to carry peak flows from Holly Run after heavy rains.

Consequently, Holly Run has flooded onto adjacent residential property

with contaminated surface water.

The landfill, itself, could present both public health and safety

problems. A maintained motorbike trail is located adjacent to the site.

Bikers have easy access to the landfill and have been known to use it as

an extension of their trails. Evidence Indicates that unauthorized

dumping has occurred at the site since its closure.

The landfill is not maintained for safe use of motorbikes and may present

excessive accident potential. Riding over the sludge cover material could

result in inhalation of DDD-laden dust which could accumulate in the body.

There exists potential for explosion due to methane generated in the

a 2-25

3

t r

o

o

Page 66: SDMS Document 112693

I

I a a «

a B

landfill. This potential is enhanced by the presence of a number of

flammable chemicals deposited at the site.

A variety of volatile organic chemicals have been identified in the

basements of homes in the area of the landfill. They have created a

I nuisance odor condition for residents, although NJDOH testing has

indicated that chemical levels are below those posing immediate health

problems. Increasing migration of volatile organics could lead to health

problems in the near future.

I Wider spread air contamination was indicated by an initial health survey

conducted by NJDOH and Camden County Health Department, which suggested an

I increase in minor respiratory ailments in residents living near the

^ _ landfill. Preliminary results from pulmonary function testing conducted

by NJDOH have not shown a similar association. The long-term health

impacts on nearby residents from Increased exposure to volatile organics

is unknown.

Several of the geologic formations underlying the landfill serve as major

aquifers to Camden County and surrounding regions. Although there are

several clayey formations, that serve as leaky, slowly permeable layers

(aquitards) and which will retard the downward migration of contaminants,

H there are no truly impermeable layers (aquicludes) to prevent contaminant

flow to other aquifers. The long-term effects on deeper major aquifers is

a major concern. 3 o o

o CO

2-26

Page 67: SDMS Document 112693

0Mfmattti^\i Mmim

d

I I

1 ^ The DDD-contaminated cover material is located on the surface of the

landfill. This material has not supported vegetative growth well to date,

and will likely remain barren unless covered by better soils. Without

vegetative cover the sludge may be susceptible to dusting during dry

periods. Although most dust will not travel far from the site, inhalation

of DDD-contaminated particles may pose substantial long-term health

problems. Nevertheless, because DDD tightly binds to sludge particles and

is relatively insoluble in water, very little leaching is expected.

Consequently, long-term impacts of the sludge on groundwater quality are

expected to be minimal.

2.5.2 Environment

NJDEP has concluded that both Holly Run and Tom's Branch are contaminated

by volatile organics ("Surface and Groundwater Investigation of the GEMS

Landfill," January, 1981). They feed into Big Timber Creek and then into

the Delaware River and Delaware Bay. Foliage shock on deciduous trees has

already been observed along Holly Run where the contamination is the

greatest. Further contamination is expected to extend the range of

impacts to other plants.

Contaminated surface water is expected to have both short- and long-term

negative impacts on wildlife, as well. A few birds were observed in the

a partially denuded woods along Holly Run, but the number and variety tr

o

I

present were much lower than would be expected along a healthy woodland

stream. The effects of contaminated water and air on wildlife is expected o

to be significant. p

2-27

Page 68: SDMS Document 112693

01 2.6 ASSESSMENT OF DATA LIMITATIONS

Much data has been collected at the GEMS landfill in an attempt to

identify health hazards and potential solutions. However, most

conclusions drawn to date should be considered preliminary, because

additional testing is required to verify past results and to draw

definitive conclusions.

Monitoring of the landfill area is still underway so the data base on

which to make decisions continues to improve. Data is being collected by

several organizations, including EPA, NJDEP, NJDOH, and Camden County.

Consequently, all pertinent files must be reviewed to ensure that

conclusions and final decisions are based on all available information.

Many aspects of the GEMS landfill have not yet been adequately quantified,

but must be prior to implementing remedial actions, including:

0 General health Impacts of the landfill on local residents.

0 Health impacts of specific volatile organics identified in

nearby potable wells.

0 Health impacts of the specific volatile organics identified in

nearby basements. 3

0 Groundwater elevation and flow patterns.

o o

3 cn

2-28

Page 69: SDMS Document 112693

I P^ 0 Horizontal and vertical extent of the contaminated groundwater

plume.

0 Potential for deep aquifer contamination.

0 Major leachate sources within the landfill.

0 Contribution of surface runoff to surface water contamination.

0 Contamination levels for volatile organics in Tom's Branch.

0 Detailed characteristics of underlying geologic formations.

^ 0 Impacts on the environment".

I I i I a a a

2-29

RW27/16

Ci 3 tr

o o

o

Page 70: SDMS Document 112693

n B

B 01

Section 3

INITIAL REMEDIAL MEASURES

3.1 OBJECTIVE

Extensive monitoring by state and local agencies has indicated several

potential health risks due to the presence of the GEMS landfill,

including (a) direct contact with surface water containing hazardous

substances by nearby residents, (b) contamination of potable groundwater

supplies, (c) migration of hazardous chemicals into household basements,

(d) exposure to volatile organic air contaminants (e) exposure to

explosive gases, and (f) inhalation of DDD-laden dust. Initial remedial

actions are recommended to rapidly reduce any existing or irmiinent

hazards to public health or the environment. These are measures which

would be effective in accomplishing this goal, yet could be implemented

relatively quickly without developing extensive amounts of detailed

engineering data. Factors for determining appropriate initial remedial

measures are outlined In 40 CFR 300.68(e).

3.2 RECOMMENDED MEASURES

3.2.1 Task I - Initial Remedial Measures Plan

An implementation plan will be developed initially to proceed with the

proposed initial remedial measures in a timely and organized manner. As

further data is collected, additional initial remedial measures may be

a 3 tr

o

o VI

li 3-1

Page 71: SDMS Document 112693

I

m r Pi

P

n 1

1

required. Therefore, also included must be a plan to respond to these

requirements as they develop. Included should be mechanisms to rapidly:

0 Review and evaluate new data as it is gathered during the

remedial investigation.

0 Collect and analyze supplemental water and air samples.

0 Determine technical requirements for additional initial

remedial measures.

0 Communicate proposed measures to the regulatory agencies and

the affected public.

0 Identify permit requirements associated with the initial

remedial measures.

0 Implement the selected measures.

3.2.2 Task II - Install Fence

To limit access by nearby residents, children, and motorbikers to

contaminated surface water and to the landfill itself, the landfill site a

and adjacent Holly Run should be enclosed with a fence. Briar Lake, ^

located approximately one-quarter-mile from the landfill, is also highly o o

contaminated and is situated in a residential area, so it too should be o

fenced. ^ CO

3-2

Page 72: SDMS Document 112693

m m

NJDEP has developed a scope of work to construct such a fence which is

recommended for use. NJDEP has estimated approximately 10,000 feet of

fence is needed to adequately isolate the landfill and Holly Run, and

approximately 1,500 feet to surround Briar Lake. The scope calls for a

6-foot high fence with coil wire at the top and bottom. Vertical posts

will be cemented into the ground. The landfill fence is planned to have

8 driveway gates, while the Briar Lake fence is planned to have 2

walk-in gates and 1 driveway gate. NJDEP estimates this fence would

cost $170,000 to install, including the cost for surveying the property

and fence line. NJDEP has requested funding from the New Jersey

Department of Treasury for action under the Spill Compensation and

Control Act of New Jersey, and from EPA Region II through CERCLA. Funds

have not yet been committed from either source.

3.2.3 Task III - Post Area

Signs should be Installed around the entire perimeter of the fence to

provide a clear, visible warning to unauthorized persons. The signs

should state "DANGER—UNAUTHORIZED PERSONNEL KEEP OUT" in 3-inch high

letters, and be visible from a distance of 25 feet. Signs should be

placed at all gates or access points, with a minimum of two on every

side of the fence and at no greater than 300-foot intervals.

3.2.4 Task IV - Sample Water Supplies ^

A variety of volatile organics have been identified in at least 12 of

the private wells monitored (Appendix B). One sample taken from the

3-3

o o

o vo

Page 73: SDMS Document 112693

n

9

Hurst residence well contained 890 ppb total volatile organics. This is

considerably greater than the 100 ppb total organics criterion used by

New Jersey for well condemnation. Another site of major concern is the

Norcross Deli, because contaminated water from this well could Impact a

larger population than most of the wells serving individual residences.

All potable water wells in which volatile organics have been Identified

in the past should be resampled to verify levels of contamination.

Based on the results of this testing, appropriate actions would then be

taken to ensure safe drinking water to all affected users.

3.2.5 Task V - Replace Culverts

Two existing culverts on Briar Lane do not have sufficient hydraulic

capacity for peak Holly Run flows. During heavy rains. Holly Run has

overflowed onto adjacent residential property. To avoid potential

contact with contaminated surface water by local residents, the two

existing culverts should be replaced with larger ones. It has been

estimated by EPA Region II that two 30-inch equivalent oval arch

culverts will be sufficient to handle peak flows.

3.3 COST ESTIMATE AND SCHEDULE

Estimated costs for initial remedial actions are shown in Table 3-1. A g t r

schedule of initial remedial actions is shown in Figure 4-1 in

Section 4.13. It is recommended that the proposed initial solutions be o o

o

O

3-4

Page 74: SDMS Document 112693

m

Table 3-1 ESTIMATED COST OF INITIAL REMEDIAL MEASURES

Action

Task I

Develop Initial Remedial Measures Plan

Task II

Fence Landfill, Holly Run, Briar Lake & Swampy area, including access gates and site survey.

Task III

Install warning signs

Task IV

Resample and analyze water from potable wells

Task V

Replace Briar Lane culverts

Quantity

11,500 feet 9 driveway gates 2 walk-in gates

40 signs

^ ' • ; .

12 houses

2 culverts

Cost

Initial,Remedial Actions Totar

^NJDEP estimate was $170,000

Low

$ 13,000

108,000 1

2,000

16,000

9,000

$148,000

"Total cost does not include any additional Initial remedial measures determined necessary from further data collected.

•HTqF

$ 27,000

220,000

4,000

21,000

21,000

$293,000

a 3

fl a

o o

RW27/35

a

Page 75: SDMS Document 112693

a H implemented as soon as feasible to reduce the immediate health risks at

the GEMS landfill site.

I 1 I a ] a a "B

a a 1 a a a a

CW07/02

3

o o

fl

p M M to

3-5

Page 76: SDMS Document 112693

I

I ]

I I 1 I I

I I I I I I I

Section 4

REMEDIAL INVESTIGATION ACTIVITIES

A number of other actions must be taken to reduce the health risks to an

.acceptable level. These measures should be instituted as quickly as

possible, but require additional field testing before they can be

successfully implemented. For example, it is desirable to minimize the

amount of leachate generated from the landfill. However, this cannot be

done until contaminant migration is better defined through geophysical

and hydrogeological testing. Another exanqile is that facilities to

collect leachate and surface runoff cannot be installed until a suitable

treatment method can also be instituted. Additional geological and

hydrogeological information must be gathered before dikes, slurry walls,

or drainage collection systems can be constructed. To remedy these data

limitations, a remedial investigation will be conducted, compiling the

additional information necessary to proceed with all of the actions

required for remediation.

4.1 OBJECTIVE

A remedial investigation is a field-oriented effort to obtain the data

necessary to assess the merits of alternative remedial measures.

Remedial Investigation activities are structured to accomplish one or

more of the following objectives:

Qi

3

CO

o

o h-t CO

4-1

Page 77: SDMS Document 112693

fl I

I

i I

a

1. Determine if the site poses an imminent public health hazard

or environmental problem.

2. Determine the nature and extent of contamination on the

project site.

3. Define the pathways of migration from the site, as well as the

impact of contaminants on potential receptors.

4. Define onsite physical features and facilities which could

impact contaminant migration, containment, or cleanup.

Extensive testing has been conducted by NJDEP, NJDOH, and Camden County

Health Department to build a data base for fulfilling these objectives.

However, the existing information on the GEMS landfill is currently

insufficient to allow the selection, screening, and feasibility study of

remedial action alternatives. The following sections constitute a

general work plan to accomplish the above objectives for the GEMS

landfill site. Order-of-magnitude cost estimates and a schedule are

presented for each remedial investigation activity.

4.2 TASK I - WORK PLAN PREPARATION AND INITIAL ORGANIZATION

Objective o o

The scope and focus of a remedial investigation depends on the site and 3

the amount of the pertinent information available. The scope of work ''

4-2

Page 78: SDMS Document 112693

D H must therefore be tailored specifically to each site. The objective of

the work plan is to provide a detailed approach for collecting

additional data needed to determine the feasibility and effectiveness of

each potential solution. Concurrent with developing a work plan,

arrangements must be made to implement the remedial investigation and to

establish onsite investigation facilities.

B n

n

m

fe

i

Scope

Development of the work plan includes the administrative functions

necessary to implement the remedial investigation. Major aspects of the

work plan may include:

- ^ Subtask I-A—Organization and Administrative

^ M 0 Assign project team

0 Meet with regulatory personnel

I H 0 Gather background data

0 Prepare quality assurance project plan

Subtask I-B~Invest1gative Site Visit

•0 Conduct Initial site visit a

3 tr

Subtask I-C—Draft and Final Work Plan o o

0 Prepare critical path analysis o

0 Prepare draft work plan '

4-3

Page 79: SDMS Document 112693

i

I a

i i

0 Prepare final work plan

Each of the investigation tasks must have a planned approach.

Consequently, the overall work plan includes a description of the basic

approach for each of site investigations, including:

0 Detailed Review of Existing Data

0 Health and Safety Site Assessment

• 0 Topographical Study

0 Geophysical Study

0 Hydrogeological Study

0 Hydrologic Investigations

0 Stormwater and Leachate Testing

0 Soil Testing

0 Air Quality Testing

0 Ecological Study

• The work plan depends on information that is being gathered as part of

the other tasks, and consequently must be developed concurrently with

the initiation of the other tasks. Furthermore, the work plan will

require continual review, and appropriate revisions will be made as

1 additional information becomes available and the potential remedial

• solutions become better defined.

3

4.3 TASK II - COLLECT AND REVIEW EXISTING DATA o ' — o

Objective o M M

4-4

Page 80: SDMS Document 112693

1

1 i

Numerous data have been collected to develop this RAMP. The objective

of this task is to collect other data related to the GEMS landfill which

are known or suspected to exist.

Scope

A detailed data search will be conducted and all data evaluated. The

work will include the following in addition to that which is available

from the preparation of the RAMP;

0 Collect additional maps, historical photographs, and

geological, soils, surface water, and groundwater data and

reports (both published and unpublished). Sources of

additional data include USGS, Soil Conservation Service (SCS),

state geological survey (or equivalent). National Oceanic and

Atmospheric Administration (NOAA), local health departments,

stream gauging records, U.S. Weather Bureau records, and local

well drillers.

0 Review additional regulatory files that exist concerning the

GEMS landfill. Included should be files held by NJDEP Solid

Waste Administration, Camden County, Township of Gloucester,

and EPA Region II. Review files recently generated by NJDEP

Division of Hazardous Management and NJDEP Division of Water ^

Resources to update information collected during the RAMP. o

o M

4-5

Page 81: SDMS Document 112693

m

II

n

a

k

m

n

0 Collect and review additional groundwater, surface water and

air monitoring data generated by NJDEP, Camden County and EPA

not included in this RAMP.

0 Collect other data from sources such as site records,

interviews with cooperative personnel (site owners, site

operators, and nearby residents), newspaper reports, shipping

company documents, etc. Files held by GEMS and Anthony Amadei

Sand and Gravel Company should be reviewed for detailed well

logs, mining operations, and bills of lading specifying

materials disposed of at the site.

All environmental data will be evaluated for compliance with the Quality

Assurance Project Plan and enforcement support requirements. On this

basis, some data may be discarded, some may be usable as indicators of

problems and for general guidance, and some may be directly suitable for

developing and evaluating alternatives.

4.4 TASK H I - HEALTH AND SAFETY ASSESSMENT

Objective

The objective of a health and safety assessment is to determine if there Q 3

are areas on or near the landfill site which present chemical or t physical hazards to the general populace or any employees working

onsite. Such information will be useful in selecting remedial actions

o o

o

00

4-6

Page 82: SDMS Document 112693

1 I which provide local residents and remedial action investigators/workers

with adequate warnings and safeguards.

m mm Scope

H Subtask III-A—Initial Health and Safety Plan

B Results from past air, water and cover material monitoring has been

conducted which can be used as a starting point for conducting the site

health and safety assessment. Using this information, a health and

H safety plan will be developed to establish protection levels for the

B

B n

m

I

Of

investigative site visit. The plan-will specify the field tests to be

performed and the protective gear to be worn by the site visit

participants. The basis for this health and safety plan will be data

collected in Task II and other information gathered during meetings with

the EPA and state and local agencies. This plan will focus upon the use

of personal protective equipment to minimize exposure to hazardous

materials through inhalation or direct contact. Because much is still

unknown about the health and safety risks of the site at this point,

appropriate precautions will be taken. This plan will be modified as

more data is collected during the initial and subsequent visits.

Subtask III-B—Site Assessment

4-7

3

o

A trained health and safety team will perform a sweep of the site to

further define potential hazards. The safety team will use an o

appropriate level of personal protective equipment and procedures as o I-I I-" vo

Page 83: SDMS Document 112693

I I determined in Subtask III-A. A minimum of level C protection should be

used. Monitoring equipment should be used at the safety team's

discretion to obtain sufficient data to evaluate the potential for

adverse health effects from chemical exposure levels. For this

analysis, the team will use instrumentation such as the following:

r 3

r !

]

I I 1

!

0 A photoionization detector to detect localized areas of high

total hydrocarbon concentrations

0 An organic vapor analyzer (OVA)

0 A direct-reading respirable dust monitor to evaluate ambient

dust levels

0 A combustible gas and oxygen level meter to measure oxygen and

explosive gas levels In the air !

I 0 A radiation survey meter to measure radiation levels

1 I I 0 A portable high-volume sampler for particulates

0 Draeger tubes (colorimetric chemical indicators) for specific

vapors

0 A portable pH probe to check surface water.

Ci 3 tr

o o

NJ O

4-8

Page 84: SDMS Document 112693

a Q

I

The health and safety team will delineate areas of high, medium, and low

risk on the site. The team will stake areas with special potential for

risks, such as contaminated surface water, contaminated surface cover

material, explosion hazard, or high hazardous chemical concentrations in

the air to prevent inadvertent foot traffic by others.

Subtask III-C—Revised Plan

The results of the site assessment will be incorporated into the health

and safety plan and the site management team will be advised of the

appropriate level of personal protection to be used for further site

entry. A report will be prepared containing conclusions and

recommendations from the site assessment, as well as the revised plan.

Subtask III-D—Onsite Mobile Facility

Due to the extensive amount of field work which will be conducted, two

mobile onsite facilities should be established at the GEMS landfill

site. One will serve as an office and be located in the support areas

as outlined by the health and safety program. The other will be used

for decontamination and will be located in a designated decontamination

area.

The decontamination facility will be supplied by a contractor on a ' ^ 3 tr rental basis or will be purchased, whichever is more cost-effective. It

4-9

o will be equipped based on the needs identified in the health and safety 3

o (-I

Page 85: SDMS Document 112693

u IH plan, and will include a secure waste material storage facility for

temporary storage of wastes generated during the investigation.

q

q

b

4.5 TASK IV - TOPOGRAPHIC SURVEY

Objective

The objective of the topographic survey is to create a site plan showing

elevations and locations of all pertinent features. Such information is

necessary for developing, screening, and selecting remedial actions, as

well as for designing and contracting the remedial actions.

A limited amount of topographic data has been collected concerning the

GEMs landfill site. However, additional survey information is needed to

provide a detailed map for investigation and design.

Scope

Subtask IV-A—Survey Work Plan

Existing topographic data will be reviewed, followed by preparation of a

detailed work plan will be prepared to address the procedure used for

developing the topographic survey. The work plan will include the scope

of activities to be conducted, time and cost schedules, and a list of g c

subcontracted services. _ o

Subtask IV-B—Survey

4-10

Page 86: SDMS Document 112693

] " An aerial survey of the site should be performed using a scale and

contours determined in the detailed plan. It is expected that a survey

with a scale of 1 inch equals 80 feet and with 5-foot contours would be

appropriate. Accuracy should be within 0.5 foot horizontal and 0.1 foot

vertical. Ground survey techniques will be used for tieing horizontal

distances to the property boundary and vertical elevations to National

Geodetic Vertical Datum (mean sea level). Onsite features which should

be included are streams and wetland areas, roads, structures, monitoring

wells, fences, vegetation, trees, breaks, and grades. Typical offsite

features near the site that should be shown on the survey include roads,

streams, wetland areas, houses, structures, monitoring wells,

vegetation, and trees.

4.6 TASK V - GEOPHYSICAL SURVEY

Objective

A geophysical survey of the landfill will be conducted to supplement

existing geophysical data, to better define the site geology and to

better delineate the boundaries and flow direction of contaminated

groundwater plumes, A combination of geophysical techniques may be

required to gather the needed data.

Scope 3

Subtask V-A—Data Compilation and Work Plan

o o

to CO

1 4-11

Page 87: SDMS Document 112693

3

i

^ ^

Compile and evaluate all existing geophysical testing results, as well

as other pertinent information concerning subsurface geology and

hydrogeology, such as well logs. Prepare a detailed work plan to

conduct additional geophysical investigations. The plan will include

the scope of activities to be conducted, time and cost schedules, and a

list of subcontracted services.

Subtask V-B—Seismic and Resistivity Testing

I 1 a a I

Previously, the landfill site was used as part of a sand and gravel

H mining operation. To determine the existing underlying topography of undisturbed material, seismic surveys should be conducted. Seismic

surveys may also help to determine the depth to water table.

Previous surface electrical resistivity and terrain conductivity testing

has suggested that contaminated groundwater may be flowing in easterly,

southerly, and westerly directions. Better delineation of contaminated

groundwater plumes should be made through additional resistivity tests.

Subtask V-C~Report Preparation

Prepare a report covering results of previous and newly completed

geophysical tests. The report should include conclusions concerning

groundwater flow, contamination, and the potential for long-term g tr*

groundwater contamination, as well as a discussion of how the results o

, , . o impact potential solutions. •-'

NO 4^

4-12

Page 88: SDMS Document 112693

4.7 TASK VI - HYDROGEOLOGICAL STUDY AND GROUNDWATER MONITORING

Objective

The objective of conducting a hydrogeological study is to better

characterize groundwater location, flow patterns and contamination

limits. In the process of installing additional monitoring wells,

additional soils characterization data will be developed.

Scope

Subtask VI-A—Data Compilation and Work Plan

m

m

n

At least 13 monitoring wells have been installed by NJDEP or Camden

County, and have been used for groundwater sampling. Data on the

design, location, and construction of the existing monitoring wells

should be compiled and evaluated. A physical inspection of each well

should be conducted to verify Installation records and to assess the

future viability of the existing wells.

From previous monitoring activities, NJDEP files contain considerable

groundwater and well log data in the vicinity of the landfill. This

data should be compiled and reviewed, and should serve as the basis for

conducting the remainder of the hydrogeological study.

A detailed work plan should be prepared to outline the procedures to be

used in defining site hydrogeology. Existing data, and data collected

4-13

o 3 tr

o o

to U}

Page 89: SDMS Document 112693

I —

m

during Tasks IV and V should be used to prepare the scope of this

Investigation. The work plan should include the scope of activities to

be conducted, time and cost schedules, and a list of subcontracted

services.

Subtask VI-B--Existing Well Inventory

A thorough offsite potable water well inventory should be conducted to*

better identify the population at risk from contaminated drinking water.

Included should be an assessment of well depth, supplying aquifer,

distance to landfill, direction from landfill, and potential for

contaminantion. All wells located within one mile of the site should be

included. In addition, public wells, and wells affecting more than a

single household, should be Included within three miles of the site.

Each existing monitoring well should be checked to determine its

suitability for further groundwater sampling. Included should be a

detailed review of well installation records and a field inspection of

i« each well

Subtask VI-C~Well Installation

Additional monitoring wells should be installed to broaden the data base a

of hydrogeologic information. The exact number of monitoring wells that ^

will be necessary cannot be adequately determined at his time. The need o

for additional monitoring wells may be identified during the groundwater o

sampling program. M

4-14

Page 90: SDMS Document 112693

Q

a a a fl fl

ui

After detailed evaluation of site conditions and existing information,

NJDEP developed a scope of work for installing additional monitoring

wells and is described in the August 10, 1982 Draft Investigation

Proposal for the GEMS landfill. NJDEP recommendations have been

incorporated into the scope of the hydrogeological study proposed in

this RAMP.

The following description serves as the basis for estimating costs to

install monitoring wells and to complete the hydrogeological

investigation. The actual methodology employed will be subject to

negotiation between EPA, NJDEP, and the investigation contractor, and

will be developed as part of the sampling and analysis protocol plan.

The wells should be sited to enable Identification of the depth of water

table, perimeter of groundwater contamination, rate of contamination

movement, and direction and rate of groundwater flow. To adequately

delineate the vertical extent of the contaminant plume, the groundwater

should be monitored at multiple depths. Well log data should be

retained to help characterize the site soils and hydrogeology.

The monitoring wells should be installed in clusters, to enable

measurement of both vertical and horizontal distribution of groundwater

contaminants. At the GEMs landfill site approximately nine well Ci 3;

clusters would be appropriate. In each cluster three wells, shallow, tr-

(first water) intermediate (40-60 feet) and deep (80-100 feet), would be g

installed in the Cohansey-Kirkwood aquifer. It is anticipated, at o

several locations, existing shallow monitoring wells could be to

4-15

Page 91: SDMS Document 112693

I

1 I I I I a a

a a a a

a a

incorporated into the cluster. Furthermore, 2 wells would be installed

at depths of 280-320 feet to monitor groundwater conditions in the Mount

Laurel Formation.

Asthe wells are being installed, split spoon samples should be

collected from each of the 100-foot and 300-foot wells, every 5 feet or

at a change in geologic formation. A photoionization detector should be

used to determine total hydrocarbon concentrations during boring.

Whenever a high concentration is measured, the corresponding soil sample

should be analyzed for priority pollutants. In addition, Shelby tube

samples should be obtained from the Cohansey Formation to determine

permeability.

All monitoring wells should be constructed of PVC and joined with

threaded connections or stainless steel screws. Two-inch diameter wells

should be sufficient except for the deep wells penetrating the Mount

Laurel Formation which should have a 4-inch diameter.

Specific quality assurance procedures will be required during

installation of groundwater monitoring wells. Technical guidance to the

drilling contractor should be provided by an experienced geologist to

obtain the desired hydrogeologic information during well installation,

fl The geologist should direct the contractor during collection of soil o

samples, and should select the depth to set permanent tubing and f

screens. 2 o

Subtask VI-D--Monitoring Well Report w 00

4-16

Page 92: SDMS Document 112693

D • • A report of the well installation should be prepared to provide

documentation of data obtained during the well installation program.

This data includes all drillers logs, geophysical logs, formation sample

analyses, water quality analyses, and water level elevations. Well

construction profiles and location data, hydrogeologic profiles,

contaminant concentration maps and profiles, and a potentiometric

surface map should be presented. If additional wells are needed beyond

those constructed in this portion of the remedial investigation program,

_ ^ supporting data, recommended locations, and design details should be

r * presented.

Subtask VI-F--Groundwater Sampling Program

i n

la

i

ai

A detailed groundwater sampling program will be developed to

characterize the distribution and rate of movement of contaminated

groundwaters. Sampling locations to be included will be new and

existing monitoring wells, and private wells identified during

Task VI-B. Sampling will be conducted at a frequency to obtain

sufficient information and to assess variation differences. Sampling

times should reflect different hydrologic conditions, caused by

precipitation. When no further useful information will be obtained from

sampling a particular well, further sampling of that well may be

discontinued. o 3

Specific aspects of the groundwater sampling and analysis program will

be developed in the quality assurance protocol plan, but should include:

o o

to

vo

4-17

Page 93: SDMS Document 112693

a

0 The monitoring wells will be sampled with a stainless steel or

other comparable sampling pump. The pump discharge will be

routed through a test cell containing conductivity,

temperature, and pH electrodes. The wells will be pumped

until the electrode readings have stabilized (if possible).

0 The offsite water supply wells will be sampled from the

closest outlet to the pump.

0 Static water levels, specific conductance, temperature, pH,

and other pertinent project-specific parameters will be

determined in the field. All samples will be tested for major

anions and cations and will undergo a priority pollutant scan

at an EPA contract laboratory, state laboratory, or qualified

private laboratory using the normal schedule for turnaround

time. Special analyses may be requested based on previous

analytical results at the site.

0 Following completion of the two initial sampling episodes,

additional water table measurement and sampling episodes will

be conducted at a reduced number of wells to provide ongoing

seasonal quality data to the remedial investigation and

feasibility study teams. The analyses will be for selected o

parameters and will include compounds already Identified, ^

field testing parameters included above, and any other o o

contaminants of concern Identified in the initial scans.

B 4-18

o V-i CO

o

Page 94: SDMS Document 112693

• 0 All groundwater sampling episodes will be coordinated with

surface water sampling episodes (Subtask VII-B) to reduce

r travel time.

0 Field-generated wastes will be handled as described in the

site health and safety plan.

Subtask VI-G—Groundwater and Soils Report

A groundwater sampling and analysis technical memorandum will be

prepared at the completion of the initial two sampling/analysis

episodes, summarizing data from field studies and analytical results.

The memorandum will include the nature and thickness of strata

penetrated, identification of aquifers, water table elevation map,

aerial extent of contamination, direction and rate of groundwater flow,

and nature and concentrations of contaminants. A supplement to the

memorandum will be prepared at the completion of each of the ongoing

sampling/analysis episodes.

4.8 TASK VII - HYDROLOGICAL STUDY

Objective

The objective of the surface water investigations is to further document ^

3 the presence of hazardous pollutants in the surface water and sediments ^

o in Holly Run, Briar Lake and Tom's Branch. Other testing will indicate o

o M CO M

4-19

Page 95: SDMS Document 112693

n

''I

-<

the contributiohs of leachate and surface runoff to surface water

contamination.

Testing has previously been conducted in Holly Run on Briar Lake, but

only one sample has been collected and analyzed from Tom's Branch. The

data base from all three needs expanding to obtain sufficient

informatiOTi^ for implementing surface water contamination control

measures.

Scope

Subtask VII-A—Work Plan

A work plan for surface water, leachate, and sediment sampling and

analysis will be developed. The work plan will include the scope of

services, a time and cost schedule, and a list of subcontracted

services.

Subtask VII-B - Surface Water and Sediment Monitoring

NJDEP has used existing data to select eleven locations for collecting

additional surface water samples in Holly Run, Briar Lake and Tom's

Branch. Seven of the locations will also have sediment analyses Ci

conducted. After review of testing results for surface water, sediment ^

and groundwater samples, it may be determined that additional locations

should be sampled.

o o

CO to

4-20

Page 96: SDMS Document 112693

n All sampling and sample handling procedures should be conducted in

accordance with established quality assurance and chain-of-custody

procedures. Specific aspects of the sampling and analysis program will

be developed in the quality assurance protocol plan.

Samples will be analyzed using the total priority pollutant scan with

confirmation of organics by GC/MS methodology. The sediment samples

should be analyzed for EP (extraction procedure) toxicity as delineated

by EPA regulations (40 CFR Section 261.24). Samples can be analyzed

using EPA contract laboratories, NJDOH laboratories, or other

laboratories as required.

Following completion of the two initial sampling and analysis episodes,

additional ongoing\ampling/episodes will be conducted to provide

continuing data. The work to be performed and the analyses to be

conducted will be comparable to the continuing program for groundwater

sampling and analysis.

Subtask VII-C—Leachate and Surface Runoff Monitoring

Several leachate samples have been collected and analyzed at the

landfill site. Additional investigation of leachate contamination, as

well as the Impact of surface runoff on surface water quality is needed.

Previous leachate sampling locations should be Investigated and a g f

program for further testing should be developed. o o

CO CO

4-21

Page 97: SDMS Document 112693

Leachate samples should be taken in conjunction with surface water

samples and analyzed according to the same methodology. Sampling should

be conducted under different hydrologic conditions, as affected by

precipitation.

Surface runoff samples can be collected only during and immediately

following a heavy rainfall. Consequently, sampling of surface runoff

cannot be easily scheduled. Samples should be collected along the face

and a\t the bottom of all sides of the landfill.

Subtask VII-D—Surface Water Quality Report

After two sets of surface water and sediment samples are analyzed, a

technical memorandum will be prepared which summarizes the data from the

field work and analytical results, and which presents a preliminary

evaluation of the data. A supplement to the memorandum will be prepared

after the completion of each of the ongoing sampling/analysis episodes.

4.9 TASK VIII - AIR QUALITY MONITORING

Objective

Air quality testing is designed to confirm previous tests identifying a

high levels of volatile organics in the vicinity of the landfill and in 3

neighboring basements. A primary objective of the testing is to provide

a data base for determining the extent of air contamination attributed

to the landfill and the degree of health risk involved. The results of

4-22

o o

CO

Page 98: SDMS Document 112693

a this onsite survey should provide a baseline for future air pollution

monitoring.

Scope

Subta^sk VIII-A—Work Plan

Existing air quality monitoring data will be compiled and reviewed.

Based (m this information, a work plan will be produced for additional

testing.\ Sample locations, instrumentation and sampling schedules will

be developec

Subtask VIII-B--Air Monitoring

Air samples should be taken upwind, onsite, and immediately downwind

from the site. Samples should also be taken in and around houses in the

vicinity of the landfill, particularly in the basements. The details of

the survey will be developed in the quality assurance protocol plan but

may involve the following instrumentation at each of the ambient air

sampling stations.

0 Wind speed and wind direction instrumentation

0 A continuous high-volume particulate sampler

0 Total hydrocarbon analyzer equipped with a flame ionization

or photoionization detector

4-23

o 3 tr

00 cn

Page 99: SDMS Document 112693

n 0 Bubblers containing an organic vapor-absorbing liquid or tubes

containing activated charcoal for the specific organic vapors

identified during the initial onsite survey.

The bubbler liquid or activated charcoal will be returned to the

laboratory and analyzed. The other instrumentation will produce the

necessary analytical results in the field.

Data from the wind speed and wind direction instrumentation will be used

to help interpret the air quality data. The data will be evaluated in

light of the presence of normal and sensitive receptors (residences with

young children, hospitals, geriatric homes, and elementary schools).

During long-term remedial or site cleanup action, additional air

monitoring may be needed.

Subtask VIII-C—Air Quality Report

A technical memorandum will be prepared summarizing the monitoring

results and data evaluation.

4.10 TASK IX - TOXICOLOGICAL REVIEW

Objective

The purpose of the toxicological review is to assess the potential

health impact caused when the general populace is exposed to the

identified contaminant concentrations. Results from the review will

a 3 tr

o o

CO

4-24

Page 100: SDMS Document 112693

contribute to decisions concerning the need for additional initial

remedial measures needed before remedial source control can be

implemented.

Scope

Subtask IX-A—Review of Groundwater Data

A trained toxicologist should review all groundwater monitoring data to

determine the risk to the public through Ingestion. Specific chemical

compounds identified and their toxic, carcinogenic, mutagenic, and

teratongenic characteristics should be evaluated. Any potable wells

found to pose excessive or potentially excessive risk should be

identified.

Review should begin immediately on all data currently existing. Further

review should occur throughout the remedial investigation process as new

data are generated.

Subtask IX-B—Review of Air Quality Data

A trained toxicologist should review all air quality monitoring data and

identify locations of excessive or potentially excessive risk to the

nearby public. Special attention should be given to data from household 3

basements. Review should begin immediately with continual reassessment t-*

throughout the remedial investigation.

4-25

o o

CO

-J

Page 101: SDMS Document 112693

Subtask IX-C—Toxicology Summary Report

A technical memorandum will summarize findings, conclusions, and

recommendations from the toxicological review.

4.11 TASK X - ECOLOGICAL STUDY

Objective

An environmental study will be conducted to identify the receptors in

the natural and human environment within the vicinity of the site.

Scope

The environmental study will focus on or identify critical receptors,

determine current stresses on these receptors, and provide the necessary

background information to determine environmental impacts and

alternative remedial measures. The potential factors to be examined in

identifying receptors and impacts are as follows:

o 3 tr*

o o

CO 00

4-26

Page 102: SDMS Document 112693

w

m

B

Natural Environment

Aquatic resources

Wetlands

Flood-prone areas

Rare and endangered species

Critical habitats

Ecological communities

Visual quality

Noise

Soils

Geology

Climatology

Topography

Surface water

Groundwater

Human Environment

Sensitive receptors

Zoning

Adjacent land use

Access

Potential explosions or fires

Human population

State and local recreation areas

Odors

Economics (public welfare)

a a a a a

The study will be conducted using published literature on the above

environmental factors, contacts with knowledgeable individuals and

agencies, and a field investigation of the site and the vicinity.

A technical memorandum will be prepared at the conclusion of the work,

presenting the types and numbers of critical receptors identified, signs

of environmental stress, and other background data that will be useful

when the impacts of alternative remedial actions are developed.

4.12 TASK XI - SITE ASSESSMENT REPORT

3

o o

CO

vo

4-27

Page 103: SDMS Document 112693

Objective

| l The objective of this final task is to compile all pertinent data

^ ^ generated in the remedial investigation, to present conclusions

f ^ regarding the extent of contamination, to address possible future

contamination, and to develop preliminary remedial action alternatives

for the site, if required.

Scope

Subtask XI-A--Evaluation of Data

All data collected during the remedial Investigation will be thoroughly

evaluated. Professional judgments will be required concerning the

degree of hazards to human health or welfare or to the environment from

chemicals found in the vicinity of the GEMS landfill.

The overall evaluation of the site will be conducted in the following

steps:

fl fl

0 Evaluate the data and select the contaminants of concern,

describe the hazardous properties of the contaminants,

fl| determine the quantities of contaminants present, assess the

a extent of contamination both onsite and offsite, and determine

a the potential for future contaminant migration. Contaminants p

of concern will be identified on the basis of concentration, o o

O

4-28

Page 104: SDMS Document 112693

p

degree of hazard, and the potential for migration and receptor

impact.

0 Determine the critical environmental pathways for contaminant

migration (air, surface water, groundwater, erosion) and the

potential receptors (human, animal, fish, vegetation).

0 Assess the dangers or potential dangers to human health or .

welfare and the environment.

Subtask XI-B—Draft and Final Report

A draft report will be prepared to consolidate and summarize the data

acquired during the remedial investigation. The report will include a

discussion of the operable units and remedial actions considered,

recommendations regarding whether or not to proceed with the feasibility

study, and the 3 to 5 recommended remedial action alternatives that

should be included in the feasibility study. The draft report will be

submitted to EPA for review. Review comments will be incorporated into

the final report.

4.13 COSTS AND SCHEDULE

o o

A detailed cost estimate for the proposed remedial investigation Q 3

activities at the GEMS landfill is presented in Table 4.1. Costs may

vary depending on the sampling and analysis protocol plan agreed upon

between EPA, NJDEP and the contractor, and is reflected in the cost

4-29

Page 105: SDMS Document 112693

a

a 1 fl

Table 4-1 ESTIMATED COST OF REMEDIAL INVESTIGAT

Action

Remedial Investigation

Task 1 - Detailed Work Plan Preparation & Initial Organization

I-A - Organization & Administration I-B - Investigative Site Visit I-C - Draft and Final Work Plan

Task II Data

Collect and Review Existing

Task III - Health and Safety Assessment

III-A - Initial Health and Safety Plan III-B - Site Assessment III-C - Revised Plan • III-D - Onsite Mobile Facility

Task IV - Topographic Survey

IV-A - Topographic Work Plan IV-B - Topographic Survey

Task V - Geophysical Survey

V-A - Data Compilation and Work Plan V-B - Seismic and Resistivity Testing V-C - Report Preparation

Task VI - Hydrogeological Study and Groundwater Monitoring

VI VI

A - Data Compilation and Work Plan B - Existing Well Inventory , «

VI-C - Well Installation & Soil Samoling^'^ Soil Analysis by EPA Contract Lab" Soil Analysis by Independent Lab

VI-D - Monitoring Well & Soils Report VI-E - Groundwater Sampling Program

Analysis by EPA Contract Lab Analysis by Independent Lab

VI-F - Groundwater/Soils Report

Low

$ 3,000 1,000 9,000

3,000

Costs

"HTW

5,000 3,000 17,000

6,000

2,000 2,000 1,000 3,000

3,000 22,000

5,000 24,000 8,000

3,000 4,000 2,000 4,000

6,000 33,000

7,000 36,000 12,000

7,000 3,000

66,000 18,000 70,000 6,000

15,000 23,000 78,000 4,000

10,000 7,000

104,000 21,000 85,000 10,000 20,000 24,000 96,000

7,000

Ci 3 f l

o o M

o M

to

B

Page 106: SDMS Document 112693

a fl • I a a I I

Table 4-1 ESTIMATED COST OF REMEDIAL INVESTIGATION

(Continued)

Action

Task VII - Surface Water and Hydrologic Investigations

Vli-A - Work Plan VII-B - Surface Water and Sediment

Monitoring - 5 Analysis by EPA Contract Lab^'c Analysis by Independent Lab '

VII-C - Leachate and Surface Runoff Monitoring ^ Analysis by EPA Contract Lab Analysis by Independent Lab

VII-D - Surface Water Report

Task VIII - Air Quality Monitoring

VIII-A - Work Plan .8 VI I I -B - A i r Monitoring Q Analysis by EPA Contract Lab Analysis by Independent Lab

VI I I -C - A i r Quality Report

Task IX - Toxicological Review

IX-A - Review of Groundwater Data IX-B - Review of Air Quality Data IX-C - Toxicological Summary Report

Task X - Ecological Study

Task XI - Develop Site Assessment Report

XI-A - Evaluate Data XI-B - Prepare and Revise Site Assessment Report

Cost Excluding Analyses Analyses by EPA Contract Labs

Total Cost (Analyses by EPA Contract Labs)

Analyses by Independent labs

Total Cost Analyses by Independent Labs)

Low

$ 2,000

5,000

Costs "PTgF

$ 4,000

4,000 12,000 48,000

4,000 7,000 26,000 2,000

2,000 9,000 2,000 8,000 2,000

5,000 5,000 3,000

6,000 15,000 59,000

6,000 8,000 32,000 3,000

4,000 13,000 3,000 10,000 3,000

7,000 7,000 4,000

8,000

16,000

14,000

$260,000 $ 62,000

$332,000

$230,000

$490,000

24,000

21,000

$406,000 $ 71,000

$477,000

$282,000

$688,000

a 3

0

0

M

CO

Page 107: SDMS Document 112693

Assumes 2 wells at 300-foot depth, 9 wells at 100-foot depth, 9 wells at 60-foot depth and 3 wells at 20-foot depth. Drilling costs $45-$70/foot for 300-foot wells, $25-$40/foot for other wells.

2 Assumes 200 soil samples will be collected and 50 will be analyzed for prioirty pollutants.

Soil analysis costs for priority pollutants, $350-$425/sample by EPA contract lab, $l,400-$l,700/sample by independent lab.

Assumes 30 monitoring wells and 10 potable water wells sampled for first episode plus 50 percent resampled in a second episode (60 samples total). Costs associated with ongoing monitoring are not included.

Water analysis costs for priroity pollutants, $325-$400/sample by EPA contract lab, $l,300-$l,600/sample by independent lab.

Assumes 11 surface water and 7 sediment samples analyzed for priority pollutants, for 2 sampling episodes (22 surface water and 14 sediment samples total). Costs associated with ongoing moniotring are not included.

Assumes 5 surface runoff and 5 leachate samples analyzed for 2 sampling episodes (20 samples total).

8 Assumes air monitoring will be conducted on 2 occasions at 10 locations around the landfill and at 20 nearby homes. 20 samples total will be

^ taken for laboratory analysis. HNU, portable gas chromatographic equip-H ment and Draeger tubes will be used for field testing.

9 Air analysis cost, $100-$125/sample by EPA contract lab, $400-$500/sample by independent lab.

n B

B a a a

CW07/13

Ci 3 t r

o o

I]

Page 108: SDMS Document 112693

ranges presented. Analytical costs vary considerably depending on

whether an EPA contract laboratory or an independent laboratory is used

for analyses.

Cost estimates provided are order-of-magnitude only. They have been

prepared for guidance in project evaluation and implementation from the

information available at the time of the estimate. The final costs of

the project will depend on actual labor and material costs, competitive

market conditions, final project scope, implementation schedule, and

other variable factors. As a result, the final project costs will vary

from the estimates presented herein. Because of this, project

feasibility and funding needs must be carefully reviewed prior to making

specific financial decisions to help ensure proper project evaluation

and adequate funding.

Remedial investigation costs and schedule are summarized in Figure 4-1,

along with the costs and schedule for initial remedial measures,

feasibility study and community relations program. A critical path

schedule is presented in Figure 4-2. It should be noted that the

schedule does not allow for significant seasonal or inclement weather

delays, or time for regulatory review.

CW07/05 o 3

o o

cn ^ A

4-30

Page 109: SDMS Document 112693

)

TASKS COSTS

LOW HIGH 10 15 20 25 30

WEEKS

35 40 45 50 55 60

INITIAL REMEDIAL MEASURES

TASK I Develop Plan

TASK 2-5 Fence, Post Area, Resample, Culverts

REMEDIAL INVESTIGATIONS

TASK I Work Plan Preparation & Initial Organization

TASK II Collect & Review Existing Data

TASK III Health & Safety Assessment

TASK IV Topographic Survey

TASK V Geophysical Survey

TASK VI Hydrogaoolcal Study*

TASK VII Hydrologic Study*

TASK VIII Air Quality Monitoring*

TASK IX Toxicological Review

TASK X Ecological Study

TASK XI Site Assessment Report

FEASIBILITY STUDY

COMMUNITY RELATIONS

TASK I Develop & Implement

Community Relations Plan

13,000

135,000

13,000

3,000

8.000

25,000

37,000

101,000

12,000

13,000

13,000

5,000

30,000

50,000

14,000

27,000

266,000

25,000

6,000

13,000

39,000

55,000

158,000

19,000

20,000

18,000

8,000

45,000

150,000

20,000

INITIAL REMEDIAL ACTIONS TOTAL

REMEDIAL INVESTIGATION TOTAL

FEASIBILITY STUDY TOTAL

COMMUNITY RELATIONS TOTAL

SUB TOTAL

ANALYTICAL COSTS; EPA CONTRACT LABS

TOTAL COSTS: EPA CONTRACT LABS

ANALYTICAL COSTS: INDEPENDENT LABS

TOTAL COSTS: INDEPENDENT LABS

148,000

260,000

. 50.000

14,000

293,000

406,000

150,000

20,000

LEGEND

Primary Activity Ongoing Activity as Required

, ^ f » i f i S ^

472,000 62,000

534.000

869,000 71,000

940,000 230,000 282,000

$702,000 $1,151,000 'NOTE: Excluding Analytical Cost

Figure 4—1 Cost Estimate and Schedule

Through Remedial Investigation for GEMS Landfi l l

9frI0 TOO aw3"

Page 110: SDMS Document 112693

10 T

15 20 T

25 T

30 •

35 T

40 T

45 T

SO •

55 T

60

Community Relations

Initial Remedial Measures

ZlLl Collect 8i Review Existing Data

i vn l Hydrological Study

r^ r^ W»fk Topographic Survey " Geophysical Survey Hydrogeological* Plan

/ 1 M \

l ^v\ / \ n \

F II II

Feasibility Study

T I I Sample Y Analysis .£xF^

Site Assessment Report

Health & Safety Assessment

Air Quality Monitoring Ecological Study

. ^ T x l Initial Toxicological Review

Zlll Final Toxicological Review

Figure 4—2

Critical Path Schedule Through Remedial Investigation for

GEMS Landfil l

LEGEND ^ ^ ^ ^ Primary Activity • ^ • - » Sample Analysis

Ongoing Activity as Requirl

^ t ' T O TOO I W D "

Page 111: SDMS Document 112693

1

I I

Section 5

FEASIBILITY STUDY a 1

5.1 OBJECTIVE

The feasibility study is an integral part of the remedial planning

process. Following the remedial investigation, the feasibility study is

conducted to develop and evaluate alternatives. The data base developed

in the remedial investigation should provide the Information needed to

develop and evaluate alternatives, recommend the appropriate

cost-effective remedial action, prepare an environmental assessment, and

develop a conceptual design for recommended action.

5.2 SCOPE

5.2.1 Task I - Description of Current Situation and Proposed Response

Information on the site background, the nature and extent of the

problem, and previous response activities presented in this Remedial

Action Master Plan may be incorporated by reference. Any changes to the

original scoping decision presented in this RAMP should be discussed and

I justified based on results of the remedial investigation.

Following this summary of the current situation, a site-specific

statement of purpose for the response, based on the results of the

remedial investigation, should be presented. The statement of purpose

5-1

o 3 tr

o o

CO

Page 112: SDMS Document 112693

a

1 i

should be organized in terms of components amenable to discrete remedial

actions (e.g., a statement of purpose describing the evaluation of

alternatives for remedial actions related to controlling leachate from

the landfill).

5.2.2 Task II - Development of Alternatives

Based on the results of the remedial investigation, the Engineer shall

develop a limited number of alternatives for source control or offsite

remedial actions, or both, on the basis of objectives established for

the response.

0 Establishment of Remedial Response Objectives. Establish

site-specific objectives for the response. These objectives

shall be based on public health and environmental concerns,

the Remedial Action Master Plan and scoping decision,

information gathered during the remedial investigation.

Section 300,68 of the National Contingency Plan (NCP), EPA

interim guidance, and the requirements of any other applicable

federal statutes. Preliminary cleanup objectives shall be

developed in consultation with EPA and the State.

0 Identification of Remedial Technologies. Identify appropriate

remedial technologies as a basis for the development of o

remedial alternatives. These technologies must be identified

on a medium-specific basis, although consideration should be

tr"

o o

5-2

Page 113: SDMS Document 112693

i] a a

a

1 B B

given to the interrelationship of the media. The technologies

should be able to meet the response objectives.

0 Identification of Remedial Alternatives. Develop alternatives

to incorporate remedial technologies, response objectives, and

other appropriate considerations into a comprehensive,

site-specific approach. Alternatives should include

H non-cleanup (e.g., alternative water supply, relocation) and

no-action options. The alternatives shall be developed in

close consultation with EPA and the State.

5.2.3 Task III - Initial Screening of Alternatives

The alternatives developed in Task II will be screened by the Engineer,

EPA, and the State to eliminate alternatives, prior to detailed

development, that are clearly not feasible or appropriate.

0 Considerations to be used in Initial Screening. Three broad

considerations must be used as a basis for the initial

screening: cost, effects of the alternative, and acceptable

engineering practices. More specifically, the following

factors must be considered:

Cost. An alternative whose cost far exceeds that of

other alternatives will usually be eliminated. Total

Q 3

o cost w i l l include the cost of implementing the o alternative and the cost of operation and maintenance. ^

cn o

5-3

1

Page 114: SDMS Document 112693

a Environmental effects. Alternatives posing significant

adverse environmental effects will be excluded.

Environmental protection. Only those alternatives that

satisfy the response objectives and contribute

substantially to the protection of public health,

welfare, or the environment will be considered further.

Source control alternatives will achieve adequate control

of source materials. Offsite alternatives will minimize

or mitigate the threat of harm to public health, welfare,

or the environment.

Implementability and feasibility. Alternatives that may

prove extremely difficult to implement, that will not

achieve the remedial objectives in a reasonable time

period, or which rely on unproven technology will be

eliminated.

5.2.4 Task IV - Laboratory Studies (Optional)

The Engineer will conduct any necessary laboratory and bench scale

treatability studies required to evaluate the effectiveness of remedial

technologies and establish engineering criteria (e.g., leachate

treatment; groundwater treatment; compatability of waste/1eachate with ^ 3 ft

site barrier walls, cover, and other materials proposed for use in the o

remedy). It is expected that the scope of this Task will depend on the °

results of Tasks II and III and therefore will not be complete at the o (-1 cn )-•

5-4

Page 115: SDMS Document 112693

I a.. start of Task V. The Engineer will submit a separate work plan for any

proposed laboratory studies for EPA and State approval. This submittal

will be made in the time frame required to maintain steady progress of

the overall feasibility study. (Additional studies may also be

conducted during the design phase if needed to refine treatability

results or develop detailed design criteria.)

I I I I

i a lai

fl 0 Detailed Development of Remaining Alternatives. The detailed

H development of the remaining feasible remedial alternatives

should include as a minimum:

i B

fl

5.2.5 Task V - Evaluation of the Alternatives

The Engineer shall evaluate the alternative remedies that pass through

the initial screening in Task III and recommend the most desirable

(cost-effective) alternative to EPA and the State.

Alternative evaluation shall be preceded by a detailed development of

the remaining alternatives.

a

Description of appropriate treatment and disposal

technologies

Special engineering considerations required to implement

the alternative (e.g., pilot treatment facility,

additional studies needed to proceed with final remedial

design)

5-5

2 I? o o

cn to

Page 116: SDMS Document 112693

Environmental impacts and proposed methods for mitigating

any adverse effects

Operation, maintenance, and monitoring requirements of

the completed remedy

Offsite disposal needs and transportation plans

Temporary storage requirements

Safety requirements for remedial implementation

(including both onsite and offsite health and safety

considerations)

A description of how the alternative could be phased into

individual operable units. The description should

include a discussion of how various operable units of the

total remedy could be implemented individually or in

groups, resulting in a-significant improvement to the

environment or savings in costs.

A description of how the alternative could be segmented

into areas to allow implementation of differing phases of

the alternative 3 tr

o o

cn UJ

5-6

Page 117: SDMS Document 112693

A review of any offsite facilities provided by the State

to ensure compliance with applicable RCRA requirements,

both current and proposed

Environmental Assessment. Perform an Environmental Assessment

(EA) for each alternative. The EA should include, at a

minimum, an evaluation of each alternative's environmental

effects, an analysis of measures to mitigate adverse effects,

physical or legal constraints, and compliance with CERCLA or

other regulatory requirements.

Each alternative will be assessed in terms of the extent to

which it will mitigate damage to, or protect, public health,

welfare, and the environment, in comparison to the other

remedial alternatives. The specific considerations to be used

in the assessment will be different for source control

alternatives and for offsite alternatives, as explained in EPA

guidance. Consideration may be given to standards and

criteria developed under Federal or State environmental and

health statutes.

Cost Analysis. Evaluate the cost of each feasible remedial

action alternative (and for each phase or segment of the

alternative). The cost will be presented as a present worth

cost and will include the total cost of implementing the

alternative and the annual operating and maintenance cost.

Both monetary costs and associated non-monetary costs will be

a 3 tr-

o o

CJl

5-7

Page 118: SDMS Document 112693

Di

fl i

included. A distribution of costs over time will be provided.

Guidance is available from EPA on estimating project costs.

0 Evaluation and Recommendation of Cost-Effective Alternative.

Alternatives will be evaluated using technical, environmental,

and economic criteria. At a minimum, the following areas

should be used to evaluate alternatives:

Reliability. Alternatives that minimize or eliminate the

potential for release of wastes into the environment will

be considered more reliable than other alternatives. For

example, recycling of waste and offsite incineration

would be considered more reliable than land disposal.

Institutional concerns such as management requirements

can also be considered as reliability factors.

Implementability. The requirements of implementing the

alternatives will be considered, including phasing

alternatives into operable units and segmenting

alternatives into project areas on the site.

Operation and Maintenance Requirements. Preference will

be given to projects with lower O&M requirements, other 3

factors being equal. ^ o o

cn cn

5-8

Page 119: SDMS Document 112693

tmim^m-%»

I ^ ^ - Environmental Effects. Alternatives posing the least

impact (or greatest improvement) on the environment will

a be favored.

Safety Requirements. Onsite and offsite safety

I requirements during implementation of the alternatives

should be considered. Alternatives with lower safety

impact and cost will be favored. I I I I

Cost. The alternative with the lowest total present

worth cost will be favored. Total cost will include cost

of implementing the alternative and cost of operations

and maintenance of the proposed alternative.

The alternative determined to be the most cost-effective will

be recommended and will be justified by stating the relative

advantages over other alternatives considered. All special

considerations will be applied uniformly to each alternative.

The lowest cost alternative that is technologically feasible

and reliable, and that adequately protects (or mitigates

damage to) public health, welfare, or the environment will be

considered the cost-effective alternative.

a 3 0 Preliminary Report. Prepare a preliminary report presenting tr

the results of Tasks I through V and the recommended remedial g

alternative. Submit copies of the preliminary report to EPA

cn

5-9

Page 120: SDMS Document 112693

and the State. (Note: EPA and the State will review and

select a remedial alternative).

5.2.6 Task VI - Conceptual Design

Prepare a conceptual design of the remedial alternative selected by EPA

and the State, The conceptual design should include, but is not limited

to, the engineering approach including implementation schedule, special

Implementation requirements, institutional requirements, phasing and

segmenting considerations, design criteria, preliminary site and

facility layouts, budget cost estimate (including operation and

maintenance costs), operating and maintenance requirements and duration,

and an outline of the safety plans including cost impact on

implementation. Any additional information required as the basis for

the completion of the final remedial design should also be included.

The Engineer may also be required to revise portions of the community

relations plan to reflect the results of the conceptual design.

5.2.7 Task VII - Final Report

Prepare a final report for submission to EPA and the State. The report

should Include the results of Tasks I through VI, and should include any

supplemental information in an appendix. Submit copies to EPA and the

State.

5.3 COSTS AND SCHEDULE

Ci 3 IT*

O

o

cn -J

5-10

Page 121: SDMS Document 112693

a

I The overall cost for a Feasibility Study ranges from $50,000 to $150,000

depending on severity of problems at the site. It should take

approximately 10-20 weeks to perform this Feasibility Study. Figure 4-1

and 4-2 show the overall schedule and costs for the site.

5.4 SOURCE CONTROL REMEDIAL ACTIONS

Source control remedial actions include measures to prevent or eliminate

contamination migration by either containing the hazardous wastes in

place or removing them from the site. Appropriate actions can be

formulated only after sufficient data have been generated through the

remedial investigation activities.

A variety of source controls may be appropriate, depending on the

results of field testing. Some potential actions to be considered along

with important considerations are described below. These measures will

be refined and evaluated in the feasibility study.

5.4.1 Transfer of DDD-Contaminated Sludge

The DDD-contaminated sludge, brought from Philadelphia, has been

deposited along the perimeter and on the side slopes of the landfill.

Potential problems which have been considered during litigation are a 3"

water contamination from DDD leachate, erosion of contaminated material, tr" and DDD-laden dust. The original solution advocated by New Jersey

regulatory agencies was removal of the contaminated material. Removal

o o

cn OS

5-11

Page 122: SDMS Document 112693

a ^ was estimated to cost $1,250,000, and has been ruled out as too

expensive, and not necessary.

NJDEP now holds the position that, when adequately covered, the sludge

will not endanger the environment. They have proposed that the sludge

be relocated to the top of the landfill prior to capping.

Testing by the EP toxicity procedure on the contaminated material has

indicated that the DDD is not readily available to leaching.

Consequently, there may be little need to ensure that the contaminated

material is under the clay cap. However, to prevent human exposure to

contaminated dust, the sludge should be covered, and logically will be

placed underneath the cap. Sludge on the side slopes could be

transferred to the top of the landfill to prevent erosion and to

consolidate contaminated material. Much of it probably will be

transferred if the side slopes of the landfill are regraded to prevent

erosion. However, transferring of the sludge may create additional

hazards from the dust generated. Prior to moving any sludge, the

material should be hosed with water or a nontoxic dust inhibitor.

5.4.2 Regrading of Side Slopes

A properly designed landfill will have side slopes at a ratio of 3

3 horizontal to 1 vertical, or flatter, to prevent erosion. However, at ^

the GEMS landfill, the side slopes are much steeper than this ratio, § particularly on the south and west sides. To ensure the long-term

stability of the landfill, the side slopes should be regraded to conform

5-12

o cn vo

Page 123: SDMS Document 112693

to standard design practice. To accomplish this without extending the

landfill perimeter, material from the top corners could be relocated to

the top surface of the landfill. However, to do so may require

increasing the overall landfill height above the permitted level.

Three primary concerns must be addressed in the process of regrading the

landfill slopes. First, dust control must be used to prevent air

contamination by the DDD-contaminated sludge. Second, care must be

taken to prevent fires and possible methane explosions while cutting the

landfill. Adequate equipment must be available onsite' to extinguish any

fires that may occur. Third, efforts must be taken to reduce exposure

of landfill material to the air and stormwater. Intermediate cover

material should be added to all excavated surfaces as rapidly as

feasible.

5.4.3 Landfill Cap

To minimize leachate emanating from the landfill, it should be capped

with an impermeable layer after regrading has been completed. Above the

cap, top soil should be added, and then seeded to prevent erosion. To

prevent damage to the cap from gas, or to prevent horizontal gas

migration to nearby homes, a venting system may be required.

a B A A Slurry Wall ^

To minimize offsite migration of leachate, further containment could be

o o

o accomplished by constructing a slurry wall around the landfill. For the <?,

o

5-13

Page 124: SDMS Document 112693

m wall to serve as an effective leachate barrier between the landfill and

adjacent areas or aquifers, it must be tied to a sufficiently

impermeable geologic formation. Preliminary geologic data indicate that

no such formation exists, although this must be verified during

geophysical and geohydrologic investigations.

5.4.5 Pumpout and Treatment

A cap above the landfill would reduce the amount of leachate generated

in the landfill from percolating rainwater. To further prevent leachate

migration to offsite, wells could be drilled and the groundwater pumped

out for treatment. A lowered piezometric surface would be created,

causing groundwater to flow towards the landfill.

The water removed must then be treated and recharged to groundwater or

surface water. Treatment options for removal of volatile organics may

include air stripping or absorption onto carbon columns.

This option may be required, particularly if chemicals are found to have

been disposed of beneath the groundwater table, as is reported. By

pumping out the water, not only can the direction of groundwater flow be

changed, but it may be possible to lower the groundwater table

sufficiently, so that the chemicals are no longer underwater. If tr

chemicals have been disposed of beneath the water table, this expensive o

option may be required to continue long into the future.

5.4.6 Surface Runoff Collection and Treatment

5-14

o

o M

Page 125: SDMS Document 112693

m

'1

If studies find that surface runoff significantly contributes to

contamination of Holly Run and Tom's Branch, a runoff collection system

may be desirable. However, after regrading, capping, and reseeding,

runoff is expected to add little to the existing water pollution

problem. If collection and treatment are necessary, dikes could be

installed around the base of the landfill to collect runoff and to *

direct it to a treatment facility.

5.5 OFFSITE REMEDIAL ACTIONS

Offsite remedial actions include measures to mitigate the effects of

hazardous waste contamination that has migrated beyond the site. Based

on the results of the remedial investigation activities and the problems

found, a variety of offsite actions may be appropriate.

5.5.1 Potable Wells

If private potable wells are found to pose a health risk to residents,

the well water may require treatment by a carbon absorption column or

the wells may require abandoning. Potable water could be replaced by

extending public water supply lines which are already located in the

vicinity.

Sampling of potable water wells will be conducted as part of both the g f

initial remedial measures and the remedial investigation. Consequently,

it may be found necessary to implement individual treatment systems or

o o

NJ

5-15

Page 126: SDMS Document 112693

Mmmmmiam^m

n alternative water supplies relatively rapidly if a inmediate health

threat is identified.

5.5.2 Contaminated Basements

Volatile organics have been identified in a number of basements near the

landfill. If it is determined that a health risk to residents exists,

several options are available depending on the means of contamination.

If the organics are being carried into the basements with contaminated

groundwater, the water could be diverted by drains. However, if gas

migration is the direct source, then the source of gas could be diverted

and vented to the atmosphere. The basements themselves could be better

sealed to the migrating gases and then basement ventilation could be

improved. Alternatively, the basements could be abandoned and filled.

5.5.3 Holly Run and Briar Lake

Due to extensive contamination already existing in Holly Run, the water

may require treating to enhance cleanup even with leachate control.

NJDEP believes that water in Holly Run will require either removal and

treatment or the stream should be lined and covered, then redirected to

an uninhabited area for natural dissipation. Q 3

B Holly Run is expected to act as a hydrologic barrier to much of the

flj leachate generated from the landfill. If this is found to be true

tr

o o

a\ during the hydrogeologic investigation, then lining of Holly Run could u»

5-16

Page 127: SDMS Document 112693

V allow leachate to migrate further offsite, increasing the extent of

groundwater contamination. On the other hand, if leachate is controlled

properly at the source, then water quality in Holly Run and Briar Lake

will likely improve fairly quickly.

To enhance natural dissipation, it may be beneficial to channelize the

swampy areas upstream of the Foxchase II subdivision and downstream of

Briar Lake, increasing the stream flow. Also, the final course of Holly

Run, which has been rerouted twice, should be chosen and implemented at

the same time as the construction of channels.

CW07/06

a 3

o o

5-17

Page 128: SDMS Document 112693

ndHiil utmMmmmimmm

I

Section 6

COMMUNITY RELATIONS

The subject of uncontrolled hazardous wastes is very emotional for many

people and in particular those in a cotranunity with an identified

uncontrolled hazardous waste site. In the GEMS landfill case, this

concern has been expressed through the attention given to the problems

associated with the site by the public and the media. Through a

carefully planned community relations program, information can be

released to the public in a timely and coordinated manner. At the same

time, their input can be obtained to assess attitudes toward the program

and general concurrence with the proposed remedial action.

The overall objective of the community relations program is to establish

a cooperative and positive working relationship with local governmental

agencies, elected officials, the press, and concerned citizen groups.

EPA Region II and NJDEP should keep the residents and emergency support

service groups In the vicinity of the GEMS landfill informed of ongoing

and planned activities throughout the program. The close proximity of

homes and busineses to GEMS landfill requires greater attention than

normal to the education and notification process. Efforts to inform

those outside the area should be considered of secondary importance o

since they are only indirectly affected by the RAMP activities. tr o o M

In order to provide an active community relations program, night o

coiranunity meetings at the following program dates .are recommended: o\

6-1

Page 129: SDMS Document 112693

Q HI 1. Prior to finalizing the RAMP

B 2. Upon completion of initial remedial actions

3. Upon completion of remedial investigation activities

4. Upon completion of source control and offsite remedial

actions.

Every feasible attempt should be made to conduct the meetings as an

informal, open forum with as few constraints on the release of

information as possible. Handout materials should be in surmary form

and written in a style that the citizens can comprehend.

On a weekly basis, during the implementation of the remedial actions and

the remedial investigation activities, information sheets should be

posted and made generally available in the area noting those actions and

activities to be undertaken during the following week.

Costs for Community Relations are shown in Figure 4-1.

CW07/09 o 3 tr

o o

B 6-2

Page 130: SDMS Document 112693

•MMawMHMIII l i l i lHI iMMli lMk-uMMiiai i

n •I

Appendix A

SITE CHRONOLOGY

J

a 3 tr

o o

- J

Page 131: SDMS Document 112693

Appendix B

NJDEP REPORT

SUMMARY OF SURFACE AND GROUNDWATER MONITORING

IN THE VICINITY OF THE GEMS LANDFILL

GLOUCHESTER TOWNSHIP, CAMDEN COUNTY

JUNE 1982

a 3 tr

o o

00

Page 132: SDMS Document 112693

B

SUMMARY OF SURFACE AND GROUND WATER

MONITORING IN THE VICINITY

OF THE GEMS LANDFILL

GLOUCESTER TOWNSHIP, CAMDEN COUNTY

JUNE, 1982

NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION

Ci 3 tr

o o

o !-• (Tl

n

Page 133: SDMS Document 112693

m SAMPLING LOCATIONS

GEMS LANDFILL

o

Page 134: SDMS Document 112693

PRIVATE WELL ANALYSES

R NO.

? 5

3tes:

LOCATION

Simons 265 Erial Rd. (Well Depth 200 ft)1

Watson Box 266 - Erial Rd. (Well Depth 205 ft)l

Speigel 270 Erial Rd. (Well Depth 215 ft)i

Hurst 274 Erial Rd. (Well DepU) 250 f t) i

DATE

11/25/80

11/17/80

4/29/82

y/22/80

11/17/80

10/27/81

3/9/82

4/29/82

Muntaqim 11/17/80 Erial Rd. ,

(Wfell Depth 50 ft.r 10/27/81

1/20/82

4/29/82 Archie 11/17/80 Erial Rd. - 10/27/81 Hickstown Rd. 1/20/82 (Well Jtepth 70 ft)1 4/29/82

CCNCSTTRATION f Ppb)

N.D. (V.O.)

7.1 12.7 • 19.8 Total V.O.

N.D. (V.O.)

17.6 7.1 0.9 1.4 0.7 0.8 0.6

29.1 Total V.O.

N.D. (V.O.)

N.D. (V.O.)

70.0 360.0 440.0 20.0 890.0 Total

N.D. (V.O.)

N.D. (V.O.)

N.D. (V.O.)

N.D. (V.O.)

N.D. (V.O.)

N.D. (V.O.) N.D.(V.O.) N.D.(V.O.) 1.0 3.0 4.0 Ttotal V.O.

N.D. - Non Detectable V.O. - Volatile Organics 1 - Well depths are as reported by well ownerc

CONTAMINANT

Trichloroethylene Chlorobenzene

1,2-Dichloroethylene Methylene Chloride T«trachloroethylene Chlorobenzene Toluene Benzene Tr ichloroethylene

Carbon Tetrachloride 1,1, 2-Trichloroethant Toluene

1,2-Dichloroprcpane

Chloroform ^ Tetrachlor-oe thylene

o o

o M

Page 135: SDMS Document 112693

-2-

No.

f 12

ia

'14

Location

Watson 277 Hickstown Rd. (Well Depth 78 ft.)^-

Robinson 432D Hickstown Rd. (Well Depth 90 ft.)l

Kergides 893 Hickstown Rd.

Ennis B93A Hickstown Rd. (Well Depth 175 f t . ) l

Date

4/29/82

11/17/80

10/27/81 3/9/82

1/20/82

9/22/80

Sullivan Hickstown Rd. (Well Depth 225 ft)"^

Nicoletta 1010 Hickstown Rd. (Well Depth 350 ft) •'•

9/22/80

9/22/80

Erial Concrete Hickstown Rd.

Accurate Industries Hickstown Rd. (Well Depth 234 ft)

Morrissey Hickstown Rd. (Well Depth 68 ft.)^

10/27/81

1/20/82

10/27/81

9/22/80

10/27/81 1/20/82 4/29/82

n/17/80

C0NQ3ffRATTn^Irpph^

N.D. (V.O.)

14.3 11.3 6.7 32.3 Total V.O.

CONTAMINANT

N.D. (V.O.) N.D. (V.O.)

N.D. (V.O.)

6.2 2.4 2.0 10.6 ' Total V.O.

5.7 2.4 2.0 10.1 Total V.O.

5.7 2.3 0.7 1.3 10.0 Total

N.D. (V.O.)

N.D. (V.O.)

N.D. (V.O.)

5.6 1.9 0.9 8.4 Total V.O.

N.D. (V.O.) NJD. (V.O.) N.D. (V.O.)

N.D. (V.O.)

N.D. - Non Detectable

well Depths are as reported by well

Chlorobenzene Chloroform Benzene

1,2-Dichloroethylene Methylene Chloride Chloroform

1,2-Dichloroethylene Methylene Chloride Chloroform

1,2-Dichloroethylene Methylene Chloride Tetrachloroethylene Chloroform

1,2-Dichloroe thy .lene Methylene Chloride Tetrachloroethylene

owners

a 3 tr

o o

-J

Page 136: SDMS Document 112693

-3-

^lAF NO. LOCATION

16

po

II

McKenna Aliaerta Rd. (Well Depth 70 ft) 1

NOrcross Deli Williamstown Rd. Alberta Ave. (Well Depth 90 ft.)-^

Wilson 266A Erial Rd. (Well Depth 80 ft.)^

Britton Essex Ave. (Well Depth 60 ft.)^

Ferrante Essex Ave. (Well Depth 70 ft.)-"-

Liszewski 733 E. Essex Ave.

Santone Erial Rd. , (Well Depth 125 ft.)-^

DATE

1/24/80

11/17/80

10/27/81

3/9/82

11/17/80

11/17/80

4/29/82

11/17/80

4 /29 /82

CagCIJJTRATTnM(ppK|

2 . 1 1.8 2.6 2 .3 8.8 T o t a l V.O.

20.6 6.4 9.6 4 .5

4 1 . 1 To ta l V.O.

N.D. (V.O.)

40 .0

N.D. (V.O.)

21.9 4 .2 6 .0 8.8 , 4 . 5 45.4 T o t a l V.O.

N.D. (V.O.)

22.4 7 . 1

10.0 4 .8

44 .3 T o t a l V.O.

N.D. (V.O.O

1V25 /80 N.D. (V.O.)

CONTAMINANT

Tetrachloroethylene 1,1,1-Tr ichloroethai Toluene Chloroform

lane

1,2-Dichloroethylene Chloroform Chlorobenzene Benzene

1,1-Dichloroethylene

1f2-Dichloroethylene 1,1-Dichloroethylene Chloroform Chlorobenzene Benzene

1,2-Dichloroethylene Chloroform Chlorobenzene Benzene

k N.D. - Non Detectable

w e n depths are as reported by u.11 owners

a 3

o o

- J C«J

Page 137: SDMS Document 112693

MONITORING WELL ANALYSES

\gf NO.

li li

J

LOCATION

Landfill M.W. #1 (Screened 17-37 ft.)

lAndfill M.W. #2 (Screened 14-32 ft.)

Landfill M.W.-Wehran (Screened 40-50 ft.)

State M.W. 0 U (Screened 15-30 ft.)

State M.W. r2A (Screened 7-17 ft.)

County M.W. #1 (Screened 13-23 ft.)

County M.W. #2 (Screened 70-80 ft.)

County M.W. #3 (Screened 20-30 ft.)

N.D. - Non Detectable V.O. - Volatile Organics M.W. - Monitoring Well

DATE

9/18/80

12/12/80

9/18/80 12/12/80

11/17/80

12/12/80

11/17/80 12/12/80

5/3,4/82

5/3,4/82

5/3,4/82

OCNCEimiATION (ppb)

8.4 18.0 6.3 2.3 1.1 2.7 4.2 5.0 1.3 2.2

144.0 5.0

iOO.5 Total V.O,

N.D,

N.D. N.D.

44 27 "83 130

(V.O.)

(V.O.) (V.O.)

i84 Total V.O. 210 31 46 57 260 53 110 180 947 Total V.O.

N.D. N.D.

12.3

136.0

69.7

(V.O.) (V.O.)

OCNTAMINANT

1,1,1-Trichlorocthane Tetrachloroethane Tetrachloroethylene Toluene Ethylbenzene O-xylene M-xylene P-xylene Cunene Mesitylene Decane Qilorofonn Methylene Chloride

Benzene Toluene Ethylbenzene Total Xylenes

Methylene Chloride 1,1,l-Trichloroethane Trichloroethylene Benzene Tetrachloroethylene Toluene Ethylbenzene Total Xylenes

Total V.O.

Total V.O.

Total V.O.

a 3 tr o o M

O

Page 138: SDMS Document 112693

- 2 -

•Lpjfo. LOCATION DATE

County M.W. 04 5/3,4/82 (Screened 20-30 f t . )

county M.W. #5 5/3,4/82 (Screened 35-45 f t . )

County M.W. #6 5/3,4/82 (Screened 24-34 f t . )

County M.W. #7 5/3,4/82 (Screened 21-31 f t . )

County M.W. #8 5/3,4/82 (Screened 31-41 f t . )

OONCEyraATION pph ayTAMINAffr

10.3 Total V.O.

N.D. (V.O.)

N.D. (V.O.)

21.7

N.D. (V.O.)

Total V.O.

es: N.D. ^ ^ V.O.

M.W.

- Non Detectable - Volatile Organics - Monitoring Well

o 3 IT*

O

o

cn

Page 139: SDMS Document 112693

SURI'ACE WATER ANALYSES

^ P NO.

¥^ I 37 n

-•38

LOCATION

Holly Run at Holly Run Drive

Holly Run at Start of Fox Chase II

Holly Run across from Fox Chase II

DATE

11/25/80

9/18/80

6/24/80

9/18/80

,

3/9/82

CONCJ:NTRATION(PPb)

N.D.

70 675 112 100 816 60 172 77 80 2,162

251.0 358.0 37.0 25.0 47.0 48.0 1.4 9.5 1.4

155.0 53.0

986.3

152 153 205 430 25 59 44 15 93

1,176

750 30 70 100 200 70 10 560 1,790

(V.O.)

Total V.O.

Total V.O.

Total V.O.

Total V.O.

CONTAMINANT

Methylene Chloride 1,2-Dichloroethane 1, l,>TrichlorodJTan< Benzene Toluene Ethylbenzene M-Xylene +P-Xylene 0-Xylene Chloroform

.

Benzene Toluene Chlorobenzene Ethylbenzene M-Xylene+P-Xylene O-Xylene Octane Cumene Mesitylene 1,1,1-Tr ichlor oe than€ Tetrachloroethane

Methylene Chloride 1,2HDichloroethane Benzene Toluene Ethylbenzene M-Xylene+P-Xylene 0-Xylene Chlorobenzene Chloroform

1, l-Dichlorc?thylei Chloroform 1,2-Dichloroethane 1,1 J.-Tr ichloroethai Carbon Tetrachloric Tr ichloroethylene Tetrachloroethylene Toluene

70 Lead

) t e s : N.D. V.O.

- Non Detectable - Volatile Organics

GML 001 0176

Page 140: SDMS Document 112693

-2-

LQCATION

Holly Run at end of Gens Landfill

Holly Run at Briar Lane

6/24/80

II

• •

ii

I

11/6/80

Inlet to Briar Lake

11/6/80

CCWCDJTRATION f pph^

90 40

250 140

, 240 . 110 650 110

1,630 . T o t a l V.O.

30

936.0 15.0 22.0

3.0 2 . 1 2 .5 3.1i

984.7 T o t a l V.O.

To ta l V.O.

T o t a l V.O.

CONTAMINANT

1,1-Dichloroethylene Chloroform 1,2-Dichloroethane 1,1,l-Trichloroethane Carbon Tetrachloride Trichloroethylene Toluene 1,2-Dichlor dbenzene

Cadmium

Chloroform Benzene Toluene Chlorobenzene Ethylbenzene M-Xylene + P-Xylene 0-Xylene

Heptane Octane Nonane Decane Benzene 1,1,l-Trichloroethane Trichloroethyler.? Toluene Propylbenzene Methylene Chloride 1,1,2-Tr ichloroethane M-Xylene + P-Xylene 0-Xylene

Heptane Octane Nonane Decane Benzene 1,1,1-Trichloroethane Tr ichloroe thylene Toluen6 Ethylbenzene Cumene Propylbenzene a

3 f

rs: N.D. V.O.

- Non Detectable - Volatile Organics

o o

^ -

Page 141: SDMS Document 112693

-3-

gyP NO. LOCATION

5/26/82

Outlet from Briar 3/9/82 Lake

5/26/82

"<«es: N.D. ] V.O.

- Non Detectable - Volatile Organics

CONCUTTRATION (ppb)

80 30 70 130 2400 320 3300 48

4000 10,378 Total V.O.

37,760

5 5 5 5 10 1 8 68 4 2 2 8 4 6 6 6 10

155 Total V.O.

50 20 10

1600 . 30

2oao 3710 Total V.O.

2,933

8 5 10 7 16 2 4 74 4

CONTAMINANT

1,1-Dichloroethane 1,2-Dichloroethane 1,1,1-Tr ichloroethane Carbon Tetrachloride Berizene 1,1,2-Tr ichloroethane Toluene 1,3-Dichlorcbenzene Naphthalene

Iron

Methylene Chloride 1,1-Dichloroethane 1,2-Dichloroetheo* Chloroform 1,2-Dichloroethane Trichloroethylene U»2,2 rTetrachiroetliane Benzene Toluene Ethylbenzene J- •<'>-Tr if lorotoluene p xylene o xylene m xylene Chlorobenzene 1,2-Dichlorobenzene 2,3-Benzofuran

1,1-Dichloroethane 1,1,l-Trichloroethane Carbon Tetrachloride' Benzene 1,1,2-Trichloroethane Toluene

Iron

Methylene Chloride 1,1-Dichloroethane 1,2-Dichloroethane Chloroform 1,2-Dichloroethane-Tr ichloroethylene Benzene Toluene Ethylbenzene

Ci 3

o o

O

00

n

Page 142: SDMS Document 112693

- 4 -

NO. LOCATION DATE

Bolly Run (400 f t . -dOMt-stream from LBriAT Lake)

4/29/82

^ ' ^ ^ ^ '" " frr"- CONTAMINANT

8 6 8 5 8 9 2 176 Total V.O.

N.D. (V.O.) 14880

P xylene o xylene nJ xylene Chlorobenzene l,2^ichlorobenzene 2,3-Benzofuran Tetrachloroethylene

Iron

f l h U t Holly Run Lake 4/29/82

pDutlet Holly Run Lake 4/29/82

as Dam Branch ; (above YMCA Lake) 3/9/82

N.D. (V.O.) 10390

N.D. (V.O.) 6400

80 40 120 Total V.O.

Iron

Iron

1,1-Dichloroethylene 1,2-Dichloroethane

s?- ^

1 '" !!?? detectable '• ^i^tile Organics

O 3

SS:i- o o

&?;

-J

Page 143: SDMS Document 112693

SEDIMENT ANALYSES

Concentration Location I^^^ Micro grams

S e ^ n w r . . ^ U y Hun ^ 3 2 ^ ^ ^ ^ ^ ^ ^ O a n ^ ^ j ^

Sediaent frcn Briar I ^ e 3/9/82 ^'1»1 - Trichloroethane

^'^ Chlorobenzene

a 3 f

o o

00

o

Page 144: SDMS Document 112693

I ]

I I ] H Appendix C

COST ASSUMPTIONS

I

I I ]

I I I I

o 3 tr

o o

o 00

I

Page 145: SDMS Document 112693

n

a

APPENDIX C - COST ASSUMPTIONS

The following cost assumptions utilized to develop the cost estimates used

for the GEMS Landfill Remedial Investigations. It should be noted that

the cost estimates shown have been prepared for guidance in project

evaluation and implementation from the information available at the time

of the estimate. The final costs of the project will depend on actual

labor and material costs, competitive market conditions, final project

scope, implementation schedule, and other variable factors. As a result,

the final project costs will vary from the estimates presented herein.

Because of this, project'feasibility and funding needs must be carefully

reviewed prior to making specific financial decisions to help ensure

proper project evaluation and adequate funding.

Monitor Well Drilling Costs:

High = $70/foot

Low = $45/foot

Priority Pollutant Analysis of Water:

High = $1.600/sample

Low = $l,280/sample

3 t r

o o

CD

I

Page 146: SDMS Document 112693

EP Toxicity and Priority Pollutant Analysis of Soils and Sediments;

High * $l,400/sample.

Low = $l,120/sample

•i^^af^i

Air Quality Analysis:

High = $500/sample

Low = $400/sample

All other costs were developed using CH2M HILL's past experience in

dealing with managerial, prime contractual and subcontractual tasks

related to hazardous waste site investigations.

CW07/13

I a 3

o o

I 00 CO