  • 8/3/2019 Section3 TPForms TA 15Jan08

    1/14

    Section 3 Technical Proposal Standard Forms 3-1

    Section 3. Technical Proposal - Standard Forms

    [Comments in brackets [ ] provide guidance to the shortlisted Consultants for the preparationof their Technical Proposals; they should not appear on the Technical Proposals to besubmitted.]

    Refer to Clause 4.1 of the Data Sheet for format of Technical Proposal to be submitted, and

    paragraph 4.1 of Section 2 of the RFP for Standard Forms required and number of pagespermitted.

    TECH-1 Technical Proposal Submission Form

    TECH-2 Consultants Organization and ExperienceA Consultants Organization

    B Consultants Experience

    TECH-3 Comments or Suggestions on the Terms of Reference and on Counterpart Staffand Facilities to be Provided by the Executing AgencyA On the Terms of ReferenceB On the Counterpart Staff and Facilities

    TECH-4 Description of the Approach, Methodology and Work Plan for Performing the

    Assignment

    TECH-5 Team Composition, Task Assignments, and Summary of CV Information

  • 8/3/2019 Section3 TPForms TA 15Jan08

    2/14

    TECH 6 C i l Vi (CV) f P d P f i l E

    Section 3 Technical Proposal Standard Forms 3-2

    FORM TECH-1 TECHNICAL PROPOSAL SUBMISSION FORM

    [Location, Date]

    To: [Name and address of ADB]

    Dear Sirs:

    We, the undersigned, offer to provide the consulting services for [Insert title ofassignment] in accordance with your Request for Proposal dated [ Insert Date] and ourProposal. We are hereby submitting our Proposal, which includes this Technical Proposal,and a Financial Proposal sealed under a separate envelope.1

    We are submitting our Proposal in association with/as a Joint Venture: [ Insert a listwith full name and address of each Joint Venture Partner or sub-Consultant].2 Attached is thefollowing documentation: [Joint Venture Agreement and Joint Venture power of attorney forLead Partner].3

    We hereby declare that all the information and statements made in this Proposal aretrue and accept that any misinterpretation contained in it may lead to our disqualification.

    If negotiations are held during the period of validity of the Proposal, i.e., before thedate indicated in Clause Reference 1.12 of the Data Sheet, we undertake to negotiate on thebasis of the proposed personnel. Our Proposal is binding upon us and subject to the

    modifications resulting from contract negotiations.

    We undertake, if our Proposal is accepted, to initiate the consulting services related tothe assignment not later than the date indicated in Clause Reference 9.2 of the Data Sheet.

  • 8/3/2019 Section3 TPForms TA 15Jan08

    3/14

    Section 3 Technical Proposal Standard Forms 3-3

    FORM TECH-2 CONSULTANTS ORGANIZATIONAND EXPERIENCE

    A - Consultants Organization[For Full Technical Proposals Only]

    [Provide here a brief (two pages) description of the background and organization of theConsultant and if applicable, Sub-Consultant and each Joint Venture Partner for thisassignment.]

  • 8/3/2019 Section3 TPForms TA 15Jan08

    4/14

    Section 3 Technical Proposal Standard Forms 3-4

    B - Consultants Experience[For Full Technical Proposals Only]

    [Using the format below, provide information on each assignment for which your firm, andeach Joint Venture partner or sub-Consultant for this assignment, was legally contractedeither individually as a corporate entity or as one of the major companies within a jointventure or sub-consultancy, for carrying out consulting services similar to the ones requestedunder this assignment. Use a maximum of 20 pages.]

    Assignment name: Approx. value of the contract (in current US$):

    Country:Location within country:

    Duration of assignment (months):

    Name of Client: Total No of person-months of the assignment:

    Address: Approx. value of the services provided by your firm

    under the contract (in current US$):

    Start date (month/year):Completion date (month/year):

    No. of professional person-months provided by theJoint Venture Partners or the Sub-Consultants:

    Name of joint venture partner or sub-Consultants, if any:

    Name of senior regular full time employees4ofyour firm involved and functions performed(indicate most significant profiles such as ProjectDirector/Coordinator, Team Leader):

    Narrative description of Project:

  • 8/3/2019 Section3 TPForms TA 15Jan08

    5/14

    Section 3 Technical Proposal Standard Forms 3-5

    FORM TECH-3 COMMENTSAND SUGGESTIONSONTHE TERMSOF REFERENCEANDON

    COUNTERPART STAFFAND FACILITIESTOBE PROVIDEDBYTHE EXECUTING AGENCY

    A - On the Terms of Reference[For Full Technical Proposals Only]

    [Present and justify here any modifications or improvement to the Terms of Reference youare proposing to improve performance in carrying out the assignment (such as deleting someactivity you consider unnecessary, or adding others, or proposing a different phasing of theactivities). Such suggestions should be concise and to the point, and incorporated in yourProposal.]

  • 8/3/2019 Section3 TPForms TA 15Jan08

    6/14

    Section 3 Technical Proposal Standard Forms 3-6

    B On Counterpart Staff and Facilities

    [For Full Technical Proposals Only]

    [Comment here on Counterpart Staff and Facilities to be provided by the ADB according toClause Reference 1.4 of the Data Sheet including: administrative support, office space, localtransportation, equipment, data, etcetera.]

  • 8/3/2019 Section3 TPForms TA 15Jan08

    7/14

    Section 3 Technical Proposal Standard Forms 3-7

    FORM TECH-4 DESCRIPTIONOF APPROACH, METHODOLOGYAND WORK PLANFORPERFORMINGTHE ASSIGNMENT

    (For Biodata Technical Proposals, omit the following text in Italic)

    [Technical approach, methodology and work plan are key components of the TechnicalProposal. You are suggested to present your Technical Proposal (maximum of 50 pages,

    inclusive of charts and diagrams for Full Technical Proposal and maximum of 10 pages if aSimplified Technical Proposal is used) divided into the following three chapters:

    a) Technical Approach and Methodology,b) Work Plan, and

    c) Organization and Personnel,

    a) Technical Approach and Methodology. In this chapter you should explain your understanding ofthe objectives of the assignment, approach to the services, methodology for carrying out the activities

    and obtaining the expected output, and the degree of detail of such output. You should highlight theproblems being addressed and their importance, and explain the technical approach you would adoptto address them. You should also explain the methodologies you propose to adopt and highlight thecompatibility of those methodologies with the proposed approach.

    b) Work Plan. In this chapter you should propose the main activities of the assignment, their contentand duration, phasing and interrelations, milestones (including interim approvals by the ADB), anddelivery dates of the reports. The proposed work plan should be consistent with the technicalapproach and methodology, showing understanding of the TOR and ability to translate them into afeasible working plan. A list of the final documents, including reports, drawings, and tables to be

    delivered as final output, should be included here. The work plan should be consistent with the WorkSchedule of Form TECH-8.

    c) Organization and Personnel. In this chapter you should propose the structure and composition ofyour team You should list the main disciplines of the assignment the key expert responsible and

  • 8/3/2019 Section3 TPForms TA 15Jan08

    8/14

    Section 3 Technical Proposal Standard Forms 3-8

    FORM TECH-5 TEAM COMPOSITION, TASK ASSIGNMENTS, AND SUMMARYOF CV INFORMATION

    Family Name, First Name Firm

    Acronym

    Area of

    Expertise

    Position

    Assigned

    Task

    Assigned

    International or

    NationalExpert

    Citi-zensh

    ip

    EmploymentStatus with Firm

    (full-time, orother)

    Education/Degree

    (Year/Institution)

    No. of years ofrelevant project

    experience

    CV signature (byexpert/by other)

    SURENDER KUMAR F

    u

    l

    l

    T

    i

    me

    D

    e

    g

    r

    e

    e

    83987122.doc

  • 8/3/2019 Section3 TPForms TA 15Jan08

    9/14

    Section 3 Technical Proposal Standard Forms 3-9

    FORM TECH- 6 CURRICULUM VITAE (CV) FOR PROPOSED INTERNATIONALORNATIONAL EXPERTS

    1. Proposed Position [only one candidate shall be nominated for each position]:

    2. Name of Firm [Insert name of firm proposing the expert]: National Power Training Institute

    3. Name of Expert [Insert full name]: SURENDER KUMAR

    4. Date of Birth: 10/05/1968 Citizenship: INDIAN

    5. Education [Indicate college/university and other specialized education of expert, givingnames of institutions, degrees obtained, and dates of obtainment]:

    S.No Degree Obtained Institution Date of Obtainment

    1 Associate Member of Institution of

    Engineers (India) in Electronics and

    Communication Engg

    Institutions of engineers

    (India)

    13/06/1995

    2 Master of Technology in

    Environment Science and

    Engineering

    Jamia Milia Islamia, New

    Delhi

    12/12/2005

    3 Certified Energy Auditor Bureau of Energy

    Efficiency, India

    5/02/2008

    6. Membership in Professional Associations MIE,Member of Institution of Engineers (India)

    7. Other Training [Indicate significant training since degrees under 5 - Education wereobtained]:(31/01-04/02/2011), PMI,NTPC,NOIDA on 660 MW Supercritical, once through

  • 8/3/2019 Section3 TPForms TA 15Jan08

    10/14

  • 8/3/2019 Section3 TPForms TA 15Jan08

    11/14

    Section 3 Technical Proposal Standard Forms 3-11

    From (Year): 1989 To (Year): 1996

    Employer: Haryana State ElectricityBoard

    Position held: Junior Engineer

    From (Year): 1996 To (Year): 2006

    Employer: National Power Training

    Institute

    Position held: Assistant Director

    From (Year): 2006 To (Year): Till Date

    Employer: National Power TrainingInstitute

    Position held: Deputy Director

    NOTE: Maximum of 5 pages.

    11. Detailed Tasks

    Assigned[List all tasks to be

    performed under thisassignment]

    Enhancement of TechnicalExpertise, Generation; CoalGeneration

    12. Work Undertaken that Best Illustrates Capability toHandle the Tasks Assigned[Among theassignments in which the expert has beeninvolved, indicate the following information forthoseassignments that best illustrate the experts capability tohandle the tasks listed in line 11.]

    Name of assignment or project: Enhancement of Technical

    Expertise of engineers from STPGL, Sudan

    Year: 2011

    Location: Faridabad (India)

  • 8/3/2019 Section3 TPForms TA 15Jan08

    12/14

    Section 3 Technical Proposal Standard Forms 3-12

    13. Certification:

    I, the undersigned, certify to the best of my knowledge and belief Yes No

    (i) this CV correctly describes my qualifications and my experience

    (ii) I am employed by the Executing or the Implementing Agency

    (iii) I am a close relative of a current ADB staff member

    (iv) I am the spouse of a current ADB staff member

    (v) I am former ADB staff member.

    If yes, I retired from ADB over 12 months ago

    (vi) I was part of the team who wrote the terms of reference for thisconsulting services assignment .

    (vii) I am sanctioned (not eligible for engagement) by ADB.

    I understand that any willful misstatement described herein may lead to disqualification or dismissal,and/or any other disciplinary action being taken by ADB.

    Date:[Signature of expert or authorized representative of the firm]5 Day/Month/Year

    Full name of authorized representative:

  • 8/3/2019 Section3 TPForms TA 15Jan08

    13/14

    Section 3 Technical Proposal Standard Forms 3-13

    FORM TECH-7 PERSONNEL SCHEDULE1

    NName of Expert

    /Position

    Expert input (in the form of a bar chart)2 Total person-month

    input1 2 3 4 5 6 7 8 9 10 11 12 n Home Field

    3 Total

    International

    1[Home]

    [Field]

    2

    3

    n

    Subtotal

    National

    1[Home]

    [Field]

    2

    n

    Subtotal

    Total

    1 For international experts the input should be indicated individually; for national experts it should be indicated individually, or, if appropriate, by category (e.g.economists, financial analysts, etc.).

    2 Months are counted from the start of the assignment. For each expert indicate separately the input for home and field work.3 Field work means work carried out at a place other than the Consultant's home office.

    Full time inputPart time input

    83987122.doc

  • 8/3/2019 Section3 TPForms TA 15Jan08

    14/14

    Section 3 Technical Proposal Standard Forms 3-14

    FORM TECH-8 WORK SCHEDULE

    N Activity1

    Months2

    1 2 3 4 5 6 7 8 9 10 11 12 n

    1

    2

    3

    4

    5

    n

    1 Indicate all main activities of the assignment, including delivery of reports (e.g.: inception, interim, and final reports), and other benchmarks such as ADBapprovals. For phased assignments indicate activities, delivery of reports, and benchmarks separately for each phase.

    2 Duration of activities shall be indicated in the form of a bar chart.

    83987122.doc