status of horizontal test stand (htsstatus of horizontal test … · 2011-11-09 · status of...
TRANSCRIPT
Status of Horizontal Test Stand (HTS-2)Status of Horizontal Test Stand (HTS 2) Development Efforts
Pradeep Kush, Prashant Khare, RRCAT, India,
Team Members:Team Members:
S.Gilankar, Rupul Ghosh, R.Chaube, Abhishek Jain, A.Laxminarayanan
2-Nov-11 1
1. Introduction to HTS Design Effortg
2-Nov-11 2
Introduction to the Task
A Horizontal Test Stand (HTS-2) is needed to test dressed SCRF cavities before they are finally placed in the cryomodule.before they are finally placed in the cryomodule.
HTS-1 is working at FNAL (Tests: One 1.3GHz cavity at a time).
HTS-2 has to be designed, It is significantly different from HTS-1 as
1 Two SCRF cavities of 650 MHz at a time (other combinations also)1. Two SCRF cavities of 650 MHz at a time (other combinations also).
2. The 650MHz cavities will operate in CW mode, heat load many times up.
3. Operational problems of HTS-1 should be addressed.
The task has become tough because:A) Apart from document on engineering design of vacuum vessel no other
report / design note etc is available on HTS-1.
11/2/2011 3
p gB) Subsystems like power coupler and feed box have not been finalized.
Status
• 3-D Model completed to visualize component assembly.
• Vacuum vessel design almost complete. Engineering Design noteprepared which takes into account pressure vessel calculations as perASME dASME code.
• First level thermal load calculations are over. Thermal Shield analyzedfor steady state and initial runs of transient.
• Cryogenic Support post designed & Scaled down prototype tested.y g pp p g p yp
• Cryogenic circuit is being designed for cryogenic loads.
• Drawings for fabrication have been started.
CHRONOLOGY
2009 : HTS-2 development efforts initiated at RRCAT.
A. Cross cultural study of horizontal test facilities carried out in 2009-2010 .
Aim: To include best features from all facilities . Get design related info.
B. Initiated design for HTS-2, based on literature survey & available
information and drawings from FNAL on HTS-1 for 1.3 GHz cavity.
C. Discussions started with FNAL team for development of FRS document
- A Functional Requirement specification document was prepared by us and submitted to FNAL in Jan 2010.
2-Nov-11 5
- We have received FNAL’s FRS document in Aug 2010.
CHRONOLOGY
D. Somewhere at the end of Feb 2010, it was decided at FNAL that HTS-
2 facility should be capable of testing beta= 0 6 & 0 9 650 MHz CW2 facility should be capable of testing beta= 0.6 & 0.9 650 MHz CW
cavities also with different testing scenarios.
Thi i li hThis implies that :
- Larger diameter of vacuum vessel for testing larger sized 650 MHz CW
iticavities.
- Increased cryogenic refrigeration to test CW 650 MHz cavities, requiring
hi h d i l d t 2 K d t l d itivery high dynamic load at 2 K, compared to pulsed cavities.
2-Nov-11 6
Importance of HTS in SCRF Tech. Development
HTS will be useful for development of following Subsystems
•Check tuner and cavity tuning stability y g y
•Test fundamental power coupler
•Test HOM couplers p
• Measure Q0 Cavity quality measurements; Qo V/s Eacc (MV/m) with all ancillary equipments
• The attainable fields under different conditions• The attainable fields under different conditions
•An excellent system to study cryogenic engineering issues. & Many other Tests
2 Literature Survey2. Literature Survey
2-Nov-11 8
A. Cross Cultural Study of HTS in other labs.
We were looking information on testing 2 Cavities at a time and CW mode operation and different cavities of different type !Refer :Peculiarities of Existing Horizontal Test Facilities: C th t t RF t t f diff t d i ? Can they test RF structures of different design? Pulsed and/or CW operation mode testing? Testing two cavities at a time?
BESSY
Supported from top or bottom?
B. Comparative Study of HTC’s at Contemporary Labs.
HT Facilities Time Projects Purpose
1. CHECHIA (DESY) 1990 XEFEL & Serving for 20 yrs for TESLA1. CHECHIA (DESY) 1990 XEFEL & FLASH
Serving for 20 yrs for TESLA Technology R & D and FLASH (TTF) Operation
2 CRYOHOLAB 2003 CARE St d 700 MH it f2. CRYOHOLAB (Saclay)
2003 CARE Program
Study 700 MHz cavity for proton or 1.3 GHz for electrons (TESLA type)Cavity structures
3. HOBICAT (BESSY)
2004 BESSY FEL & STARS
Testing two 1.3 GHz 9-cell cavity for CW operation (can(BESSY) & STARS cavity for CW operation (can accommodate 500 MHz structures)
4. HTS (FERMI) 2006 ILC & Project X
Test ILC 3.9 GHz & 1.3 GHz Cavity as well as low Beta cavityy
5. HTC (Cornell) 2007 Cornell ERL
Helped to find many problems
3 Details of Design Effort3. Details of Design Effort
2-Nov-11 11
DESIGN EFFORT
The Design Effort can been divided in following activities
• Development of 3-D Model
D i f V V l• Design of Vacuum Vessel
• Design of Thermal Shield
• Design of Cavity Support System (Cryogenic Support Post and
Frame Bridge and Rolling Cart)
• Finalization of Cryogen supply scheme
Different activities have progressed to different levels. After
analytical calculations. Prototyping has started in some of them
2-Nov-11 12
and will start in others soon.
4 3-D Model of HTS4. 3-D Model of HTS
2-Nov-11 13
3-D MODEL OF HTS FOR SCRF CAVITIES OF 1300 / 650MHZ
3-D MODEL OF HTS WITH TWO CAVITIES, 650 MHz
HTS-2 VACUUM VESSEL
November 2, 2011 15
Cavity when supported on the trolley- Another View
3-D MODEL OF HTS WITH TWO CAVITIES 1 3 GHz3 D MODEL OF HTS WITH TWO CAVITIES, 1.3 GHz
HTS-2 SUPPORT SYSTEM
November 2, 2011 17
END VIEW OF SUPPORT SYSTEM
4K Trace LiLine
80K80K Thermal shield
Deflection pattern in HTS I type of SS structure
3 m long structure for HTS II using HTS I type box and rail section
Material SS 304
Maximum deflection 150 micron
Two Alternate schemes for HTS II structure
Material SS 304Replacing the box section of HTS‐ I by an ‘I’ section. SS 304
i d fl i l i hi
Material SS 304
Maximum deflection value in this case is about 32 microns
Replacing the box section of HTS I by a ‘Box section’
Material 6061‐T6
Replacing the box‐ section of HTS‐ I by a Box section .Al 6061‐T6
i d fl i lMaximum deflection value in this case is about 54.8 microns.
Th d t f AlThe advantage of Al comes from faster cool down
Cool down Estimates
Cool down status of HTS I type SS 304 box and rail structure at 25000 sec
Far from steady state
Cool down status of 6061‐T6 Aluminum ‘C’ section structure at 25000 sec
30
35
Nearly steady state
Variation of thermal diffusivity with
10
15
20
25
30
SS 304 BALUMINUM ALLOY 6061-T6 C
l Diff
usiv
ity m
2 /hr temperature
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
0
5
10
Ther
mal
Temperature K
5 Design of Vacuum Vessel of HTS5. Design of Vacuum Vessel of HTS
2-Nov-11 22
3‐D model of HTS‐2 vessel
Feed Can port
21
54
3
5
Main CouplerCavity pumping
Support Post Port
Final 3-D model of Vacuum Vessel with changes Final 3 D model of Vacuum Vessel with changes incorporated after feedback from FNAL
Vacuum Vessel Parameters
Preliminary vacuum vessel of HTS-2
Designed value Remark
Diameter of SS 304 Vessel* 46 inch Considering testing of 650 MHz cavity also
Overall Length of Vessel 137 7 inch Considering testing of two SCRFOverall Length of Vessel 137.7 inch Considering testing of two SCRF cavities
Nominal Thickness of 0.375 inchVessel
Verified with ASME Boiler and Pressure Vessel Code Sec.VIII Div 1,(2004)
Calculations Completed for Vacuum Vessel of HTS-2
Following Calculations Have been completed for Vacuum Vessel of HTS-2HTS-2
• Calculations for the Vacuum Vessel Cylindrical Shell Thickness
- As a external pressure vessel (as per UG-28 of ASME VIII, Div. I, Edition 2004 )
V ifi d i t l l ( UG 27 f ASME VIII - Verified as internal pressure vessel (as per UG-27 of ASME VIII, Div. I )
• The Permissible Out of Roundness of the Vessel Cylindrical Shell• The Permissible Out of Roundness of the Vessel Cylindrical ShellThickness(as per UG80 of ASME VIII Div. I Edition 2004)
• Analysis and Calculations for the Stiffening Rings(as per UG-29, ASME VIII, Div. 1)
• Calculations and Analysis for all the vessel Shell Openings/Ports- (external as well as for internal pressure)
Design Calculations Continued
• The Discussion of Multiple Openings
(as per UG42(a) of ASME, VIII, Div. I )(as per UG42(a) of ASME, VIII, Div. I )
• Calculations and Analysis for the Flanges, Bolts and Welds(as per appendix 2 and appendix Y of ASME VIII Div 1)(as per appendix 2 and appendix Y of ASME VIII, Div. 1)
Front End Flange and the Front Vessel Head Rear End Flange and the Rear Vessel Head Rear End Flange and the Rear Vessel Head Calculations for the Other Flnages of Ports
f d UW ( ) ( ) UW d ( ) Referred UW-13 (e) (2), Fig. UW-13.2, section 2-3 and Fig. 2-4 (4a), Appendix 2 of ASME VIII, Div. 1 for weld analysis and calculations of front and rear end vessel head flanges.
• Calculations for the Vacuum Formed Head Shell Thickness(as per UG-33 (a) (1) (a) and UG-32 (d) of ASME VIII, Div. 1)
Design Calculations (Contd.)
• Discussions on the Saddle Support DesignDiscussions on the Saddle Support DesignReferred “Pressure Vessel Handbook” 7th edition by E. Megyesy
• Initial Relief System Calculations• Initial Relief System Calculations
Referred Vacuum vessel engineering note for SMTA Horizontal test C t t (CGA 1 3 1995)Cryostat (CGA-1.3-1995)
• Two more analysis to be performed as per feedback Two more analysis to be performed as per feedback from FNAL
Some Design Calculations Results
Calculation made for
Parameter
Nominal /Actual Value (inch)
Calculated minimum value
required
Remark
Parameter required (inch)
1. Vacuum vessel
0.25 –External pressurevessel
cylindrical shell thickness
0.375 pressure0.029-Internal pressure
Verified
2 Out of Difference between2. Out of Roundness for Cylindrical shell of Vessel
0.2437Difference between max. dia. and min. dia. at any cross section shall not exceed 1%;of Vessel shall not exceed 1%;
3. Calculation and Analysis for the Front and Available Moment Required moment
of inertia ofthe Front and Rear End Flanges as stiffening rings
of inertia of front/rear ring flanges of vessel,I = 2 2236 in4
of inertia of front/rear ring flanges of vessel,
Ireq = 0.968 in4
No stiffening rings required
g gunder external pressure
Iavailable = 2.2236 in4 req
Some Design Calculations Results (contd.)
Calculation made for Parameter
Nominal /Actual Value
(inch)
Calculated minimum value required (inch)
Remark
( ) q ( )
4 Multipule
No additional reinforcement for multiple openings4. Multipule
Openings/ports Verified by calculations multiple openings are required under current design
fi ticonfiguration5. Calculations and Analysis Verified thickness of flanges
d i d & il bl b ltand Analysis for the Flanges, Bolts and Welds
and required & available bolt area as per Appendix 2 and appendix Y of ASME VIII, Div. 1
Verified
Welds6. Calculation of Vacuum 0 315 in 0.0199 in VerifiedFormed Head Shell Thickness
0.315 in Verified
Working on Mechanized End Closure
6 Design of Thermal Shield of HTS6. Design of Thermal Shield of HTS
2-Nov-11 31
Transient Thermal Analysis
First Point
Second Point
Assumption: The cooling pipe is instantaneously filled with 80 K Helium
Geometric Model Meshed Model
The cooling pipe is instantaneously filled with 80 K Helium,neglecting any longitudinal temperature gradient in the pipe.
Boundary Conditions: 1 gm/sec Helium flow in 10 mm diameter cooling pipe 1 gm/sec Helium flow in 10 mm diameter cooling pipe H= 280 W/m2.K Constant radiation heat flux from 300 K vacuum vessel =1.5 W/m2 Conduction heat in leak of from each support post = 2 62 Watt Conduction heat in leak of from each support post = 2.62 Watt
Transient Thermal Analysis
Results: It is found that 80 K shield
takes 3 h 15 min to attainsteady statey
The max. temp differenceof ~60K after 30 Min.
At steady state temp At steady state, tempdifference is found to be2-3 K
7 Design of Cavity support system7. Design of Cavity support system
2-Nov-11 34
Cavity Support System
Comprises of Two Major SubsystemsComprises of Two Major SubsystemsA. Cryogenic Support PostB. Frame Bridge and Rolling Cart
Present Task
Functional Requirements from HTS-2
1. Total Structural Load Less about 1000 kg (includes 2 Cavities, Frame bridge, Rolling Cart, Thermal Shield)(more than 2 times of what was with HTS-1)
2 Total thermal load through Support Post should be comparable with2. Total thermal load through Support Post should be comparable with what is there in HTS-1(Dimensions of the present CSP of HTS-1 is maintained so that this value does not change)
3. Design is Necessary to Check for Additional Load CapabilityComplete Understanding of Design Necessary for Modification ifComplete Understanding of Design Necessary for Modification if needed.
4. As a Parallel Activity We Are Thinking of Simplifying the Construction to Make Assembly easy.
November 2, 2011 36
Function of CSP
Cryogenic Support Post performs following main functions
Transfers Weight of Cold Cavity at 2 K to Vacuum Vessel at 300 K while Ensuring Minimum Heat In-Leak
1. Support Load of Cold Mass.
2. Minimize Heat In-leak by using Low th l C d ti it G11 T bthermal Conductivity G11 Tube.
3. Support Load of 80 K Thermal Shield3. Support Load of 80 K Thermal Shield
November 2, 2011 2
Design of Support Post
Fi Max Axial Load Carried by Inner JointFo Max Axial Load Carried by Outer Joint
Pi Contact Pressure at Inner JointPi Contact Pressure at Inner JointPo Contact Pressure at Outer Joint
‘f’ -- Coefficient of Friction between G11 Tube and Disc/Ring
‘E’ Y ’ M d l δ Diametral Interference between Tube and Inner Disc
November 2, 2011 38
‘E’ -- Young’s Modulus ‘μ’ -- Poisson’s Ratio of Materials
δi Diametral Interference between Tube and Inner Discδo Diametral Clearance between Tube and Outer Ring
Spread Sheet for Calculation
November 2, 2011 39
Prototyping to validate the Design
•As of now there is no necessity of developing a full scale prototypeas other details of the system are being developed.
•This prototyping work is being done in order to
- Validate our calculations
- These calculations are necessary if somechange has to be made in the CSP
•As we are thinking of removing 4K shield we wanted to calculateh t i th dditi l h t l k iwhat is the additional heat leak in.
•We can also think about simplifying the assembly process for thisCSP hence this prototyping is being doneCSP hence this prototyping is being done
•OFF COURSE full scale prototyping will also be done.
November 2, 2011 40
Load bearing Capacity of Prototype
ID of Al Disc, d1 = 10mmID of G11Tube, d2 = 57.02mmOD of G11Tube, d3 = 63.02mm
Poisson's Ratio Al 6061T6c Disc μ1 = 0.33Poisson's Ratio G11 Tube μ2 = 0.2
Diametral Interference b/w Disc and
, 3OD of Al Disc, d4 = 92mmThickness of Disc/Ring, h 15mm
Poisson s Ratio G11 Tube μ2 0.2Poisson's Ratio Al 6061T6c Ring μ3 = 0.33
Young's Modulus Al 6061T6 Disc, E1 = 70GpaDiametral Interference b/w Disc and Tube, δi 0.12 mmDiametral Clearance b/w Disc and Tube, δo 0.02 mm
Young's Modulus G11 Tube, E2 = 28Gpa Young's Modulus Al 6061T6 Ring, E3 = 70Gpa
Friction Coeff b/w Al 6061T6 Disc/Ring , o
l d k b
Friction Coeff b/w Al 6061T6 Disc/Ring and G11 Tube 0.3
Max Axial Load taken by Inner Joint Fi = 2700 KgMax Axial Load taken by Outer Joint Fo = 2361 Kg
Contact pressure at Inner Joint Pi = 32.8 MPaContact Pressure at Outer Joint Po = 26 MPa
November 2, 2011 41
Prototype Fabrication
30
15
20
25
d; k
N0
5
10
15
Load
00 1 2 3
Displacement; µm
Load Testing of Inner Joint
Result: Prototype has taken load of 26 KN before slippage.
2D Drawings of Support Post Components
November 2, 2011 43
2D Drawings of Support Post Components
November 2, 2011 44
Static Thermal Load (conduction)
As Calculated by keeping the dimensions same as that for HTS-1
2 K InterfaceQ2K
0.004W
2 K
66
23
4 K InterceptQ4K
4 K
22
236 20
80 K Intercept
Q4K
1.2W
300 K
80 K
45
20
40 80 K InterceptQ80K
4W
300K 20
300 K Interface
November 2, 2011 45
8 Cryomodule Component Test Rig8. Cryomodule Component Test Rig
2-Nov-11 46
8. Cryomodule/HTS Component Test Rig
Objective
1. To experimentally validate the design of subsystems like cavity support system and cool down of thermal shield.
2. To experimentally verify newer concept of cavity support system. Specifically verify whether assumptions, boundary conditions etc as chosen were correct.
Thank YouThank You