STRATFORD MIDDLE SCHOOLRENOVATION AND ADDITION

ARLINGTON PUBLIC SCHOOLS

PFRCMARCH 16, 2016

Page 2: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

SCHEDULE AND MEETINGS | 1

Page 3: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 3

PROJECT SCHEDULE

BLPC (Bi-weekly) 11/9-#14 12/7-#16

12/21-#1711/23-#15

11/12-#7 12/16-#9PFRC (Monthly)

SCHOOL BOARD

SCHOOL BOARD

DEC2015/2016 JAN JUN JUL AUG SEPFEB MAR APR MAYNOV

11/16 ActionItem

11/5InfoItem

12/3CMaRPre-Cons.

12/8Historic Des.

SCHEMATIC DESIGN MEETINGS

1/4 -#18 2/1 -#20 3/10 - #22

2/22 -#211/20 -#19

1/20 -#10 2/17-#11 3/16-#12

3/17SD Info Item

4/7 SD Action Item (Tentative)

12/15 County Board approved School Board motion on Historic District designation process

2/17 - TIA available for reviewApril/May 2016: Submit Use PermitJuly/Sept 2016: County Board Hearing for Use Permit2/17 - HALRB meeting

3/9 - Safe Routes to Stratford Open House

Page 4: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 4

• HALRB 2/17

• County Joint Session 2/19

• BLPC 2/22

• 3/2 coordination meeting with Department of Parks and Recreation

• Ongoing coordination with Arlington County and Fire Department

• Safe Routes to Stratford Open House 3/9

• BLPC 3/10

• 3/16 meeting with HPP staff on historic designation and Design Guidelines

RECENT MEETINGS

Page 5: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 5

RECENT MEETINGS

HALRB 2/17

• Building design update presented

• Material palette and overall massing well-received

• Discussion about treatment of 1994 addition

County Joint Session 2/19

• APS and County presented update to School Board and County Board

“...massing and materials of the new addition are compatible with the historic building and that the proposed design preserves the viewsheds of the historic building and locations of the historic events.” [HALRB letter, 3/11/2016]

Page 6: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

SITE AND BUILDING DESIGN UPDATE | 2

Page 7: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 7

LANDSCAPE PLAN: PROGRAM

1 97 8

4 2 5 32 136

3

Page 8: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 8

BIKE NETWORK

Page 9: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 9

EXISTING ANALYSISSITE ACCESSIBILITY

STRATFORD /

HB WOODLAWN

TRAILERTR.

TRAILER

OLD DOMINION / ROUTE 29

LORCOM LANE E

23RD STREET N

N

10.3%

8.33%

STAIR ACCESS

10.55%

6.98%10.55%

11.94%

STAIR

ACCESS

1% - 5%

5.1% - 8.33%w/ HANDRAILS +LANDINGS

LEGEND5% - 8.33%w/out HANDRAILS +LANDINGS

8.34% +/=

9.1%

8.2%

According to ADA Guidelines 2010:• Existing sidewalks

along existing roads are compliant if there are no obstructions

• New paths less than 5% slope do not require handrails and landings

• New paths between 5%-8.3% require handrails and railings

Page 10: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 10

PEDESTRIAN NETWORKSITE ACCESSIBILITY

Page 11: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 11

SCHEMATIC DESIGN TREE IMPACT

• 407 trees in potential area of impact: All on APS site + trees on adjacent properties with critical root zone within or close to “Limits of Disturbance”

• 166 to be removed based on Schematic Design “LOD”

• 241 to remain

Page 12: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 12

SCHEMATIC DESIGN TREE IMPACT

• Required to replace 211 trees according to zoning calculations

Page 13: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 13

APS PROPERTY + DPR PROPERTY (555,937 SF / 12.76 AC)

Building Coverage

Roads/Parking

Walkways/Sidewalks

Fields / Amenity Open Space

EXISTING 10.4% 16.9% 5.6% 20.6% 46.5%

DRIVEWAY 12.5% 18.0% 6.0% 19.7% 43.8%

NO DRIVEWAY 12.5% 15.5% 7.4% 19.7% 44.9%

OPEN SPACE

Revised estimated percentages represent the development of the scheme(s) from Concept level into Schematic Design, particularly with regard to walkways/paved areas. It is likely that percetages will change slightly as the project moves into Design Development.

Page 14: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 14

N. VACATION

OLD DOMINION / ROUTE 29

23RD STREET N

30'

30'

DRIVEWAY OPTIONFIRE ACCESS

• Fire access to existing building does not meet code

• Removing a major fi re access point by building on west parking lot

• Portions of existing roof and addition roof are 30’ above “grade plane,” so ladder truck access is required.

• Ladder truck access required at a maximum distance of 30’ from the building along one side

• Fire agreed to grant relief on last 50’ of new addition south facade

30’ perimeter offsetPossible fi re lane requiredAerial access not required

Page 15: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 15

NO DRIVEWAY OPTIONFIRE ACCESS

30'

30'

• Without driveway, driveable surface in courtyard is required for truck to exit to Vacation Lane

30’ perimeter offsetPossible fi re lane requiredAerial access not required

Page 16: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 16

AUXILIARY GYM GLAZINGSCHEMATIC DESIGN

• Channel glass substituted with custom curtain wall

• Curtain wall glazing to have frit treatment to acheive similar eff ect

• Can still meet same design goals as with channel glass for a lower price. Th is includes reduction in heat gain and diff use natural light into the auxiliary gym.

CHANNEL GLASS CURTAIN WALL WITH FRIT

Page 17: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

| 3RECOMMENDATION TO

SCHOOL BOARD

Page 18: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 18

SCHEMATIC DESIGNRECOMMENDATION TO SCHOOL BOARD

• Schematic Design proposal meets the program for 1,000 students• Proposal is for 40,000 gsf addition within the budget approved at Concept Design• Presenting scheme with driveway, as was approved at Concept Design

Page 19: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 19

SCHEMATIC DESIGN AERIAL VIEW

• 40,000 sf addition• Exit only driveway

connection from Vacation Ln to Old Dominion Dr

• Expanded surface parking off Vacation Lane

• Renovation of existing building to accomodate new program

• 144 parking spaces

Page 20: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 20

DESIGN PRINCIPLES

• Accommodates program and provides quality learning environments• Creates opportunity for new “heart of school”• Connects to existing building circulation network• Leaves existing historic building intact while interior renovations provide a unifi ed

Middle School • Preserves views of historic south facades of existing building • Maintains fl ow from classroom wing to fi eld• Improves site circulation and accessibility for vehicles, bicycles and all pedestrians• Minimizes impact to Stratford Park renovation plan and schedule

Page 21: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 21

SITE PLANDRIVEWAY CONNECTION TO OLD DOMINION

N. VA

CATIO

N LA

NE

N 23RD ST

OLD DOMINION DRIVE

Page 22: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 22

ALTERNATE SITE PLAN NO DRIVEWAY CONNECTION TO OLD DOMINION

N. VA

CATIO

N LA

NE

N 23RD ST

OLD DOMINION DRIVE

Page 23: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 23

BASEMENT PLAN

��

0’20’ 40’

N

LIBRARYFOOD SERVICEPHYSICAL EDUCATIONTHEATER/ARTSMUSICTECHNOLOGYWORK & FAMILY STUDYBUILDING SUPPORT

TEACHER & STORAGEADMINCOUNSELING/CLINICCORE CLASSROOMSSPECIAL EDUCATIONELECTIVE CLASSROOMSCIRCULATIONENTRANCE

Page 24: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 24

FIRST FLOOR PLAN

��

��

0’20’ 40’

N

LIBRARYFOOD SERVICEPHYSICAL EDUCATIONTHEATER/ARTSMUSICTECHNOLOGYWORK & FAMILY STUDYBUILDING SUPPORT

TEACHER & STORAGEADMINCOUNSELING/CLINICCORE CLASSROOMSSPECIAL EDUCATIONELECTIVE CLASSROOMSCIRCULATIONENTRANCE

Page 25: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 25

SECOND FLOOR PLAN

0’20’ 40’

N

LIBRARYFOOD SERVICEPHYSICAL EDUCATIONTHEATER/ARTSMUSICTECHNOLOGYWORK & FAMILY STUDYBUILDING SUPPORT

TEACHER & STORAGEADMINCOUNSELING/CLINICCORE CLASSROOMSSPECIAL EDUCATIONELECTIVE CLASSROOMSCIRCULATIONENTRANCE

Page 26: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 26

��

��

��

��

��

��

��

THIRD FLOOR PLAN

0’20’ 40’

N

LIBRARYFOOD SERVICEPHYSICAL EDUCATIONTHEATER/ARTSMUSICTECHNOLOGYWORK & FAMILY STUDYBUILDING SUPPORT

TEACHER & STORAGEADMINCOUNSELING/CLINICCORE CLASSROOMSSPECIAL EDUCATIONELECTIVE CLASSROOMSCIRCULATIONENTRANCE

Page 27: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 27

VIEW FROM OLD DOMINION

Page 28: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 28

VIEW FROM EAST

Page 29: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 29

SOUTH FACADE

Page 30: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 30

ENTRYHEART OF SCHOOL

Page 31: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 31

COMMONSHEART OF SCHOOL

Page 32: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 32

MEDIA CENTERHEART OF SCHOOL

Page 33: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal
Page 34: STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION · Arlington Public Schools Stratford Middle School - 18 SCHEMATIC DESIGN RECOMMENDATION TO SCHOOL BOARD • Schematic Design proposal

QUINN EVANS ARCHITECTSArlington Public Schools

Stratford Middle School - 34

SCHEMATIC DESIGNVACATION LANE IMPROVEMENTS