study period march to may environmental...

270
Prepared by M/S Udaipur Min-Tech Pvt. Ltd. 1 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine STUDY PERIOD MARCH TO MAY -2016 NON FOREST LAND ENVIRONMENTAL IMPACT ASSESSMENT & ENVIRONMENTAL MANAGEMENT PLAN FOR Satalkhedi-Pipakhedi Limestone (Building Stone) Mine Lease Area43.24 ha., M.L. No. 55/91, Near Village Satalkhedi-Pipakhedi, Tehsil Ramganj Mandi, District Kota, State - Rajasthan Purpose Environment Clearance, Proposed production 3, 21,699 TPA PROJECT COST 80.0 Lakhs CATEGORY- ΄B΄ Tor letter No- F1 (4)/SEIAA/SEAC-Raj/Sectt/Project/Cat.1 (a) B1 (7243) /14-15/752 Dated:- 06-05-2016. LESSEE EIA CONSULTANT SH PANKAJ KUMAR BAIRWA S/o - SH. SWAROOP CHAND, R/o -SATALKHEDI, THE -RAMGANJMANDI DIST- KOTA, RAJASTHAN- M/S UDAIPUR MIN-TECH PVT. LTD. 206, APEKSHA COMPLEX, SEC. -11 HIRAN MAGRI, UDAIPUR (RAJ.)-313002 PH. 91-294-2489672(OFF.) +91 9414167672 Email: [email protected] ACCREDITED BY NABET CATEGORY “A” FOR MINING SECTOR (S. No. 146)

Upload: phungnhu

Post on 06-Mar-2018

230 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

1 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

STUDY PERIOD MARCH TO MAY -2016 NON FOREST LAND

ENVIRONMENTAL IMPACT ASSESSMENT &

ENVIRONMENTAL MANAGEMENT PLAN

FOR

Satalkhedi-Pipakhedi Limestone (Building Stone) Mine

Lease Area– 43.24 ha., M.L. No. 55/91,

Near Village – Satalkhedi-Pipakhedi, Tehsil – Ramganj Mandi, District – Kota, State - Rajasthan

Purpose – Environment Clearance, Proposed production –3, 21,699 TPA

PROJECT COST – 80.0 Lakhs CATEGORY- ΄B΄

Tor letter No- F1 (4)/SEIAA/SEAC-Raj/Sectt/Project/Cat.1 (a) B1 (7243) /14-15/752 Dated:-

06-05-2016.

LESSEE EIA CONSULTANT SH PANKAJ KUMAR BAIRWA S/o - SH. SWAROOP CHAND, R/o -SATALKHEDI, THE -RAMGANJMANDI DIST- KOTA, RAJASTHAN-

M/S UDAIPUR MIN-TECH PVT. LTD. 206, APEKSHA COMPLEX, SEC. -11 HIRAN MAGRI, UDAIPUR (RAJ.)-313002 PH. 91-294-2489672(OFF.) +91 9414167672 Email: [email protected]

ACCREDITED BY NABET CATEGORY “A” FOR MINING SECTOR (S. No. 146)

Page 2: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

2 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Page 3: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

3 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Page 4: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

4 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

LIST OF ABBREVIATIONS

AMSL Above Mean Sea Level AAQ Ambient Air Quality bgl Below Ground Level

BOD Biochemical Oxygen Demand COD Chemical Oxygen Demand TDS Total Dissolve Solid

CPCB Central Pollution Control Board CSR Corporate Social Responsibility dB Decibel DO Dissolved Oxygen EAC Expert Appraisal Committee EIA Environmental Impact Assessment EMC Environmental Management Cell EMP Environment Management Plan EPA The Environment Protection Act GLC Ground Level Concentration Ha Hectare

HFL High Flood Level JIR Joint Inspection Report

KLD Kilo litre Per Day Km Kilo Meter Leq Equivalent Noise Level LFL Low Flood Level LOS Level of Service LoI Letter of Intent

MoEF Ministry of Environment and Forest NABET National Accreditation Board for

Education and Training NH National Highway

NOC No Objection Certificate OSHA Occupational Safety and Health

Administration PCU Passenger Car Unit PFR Pre- feasibility Report PM Particulate Matter PUC Pollution Under Control QCI Quality Council of India

RBM River Bed Material RL Reduced Level

Page 5: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

5 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

SH State Highway SPCB State Pollution Control Board ToR Terms of Reference TPA Tonnes Per Annum

USEPA United State Environmental Protection Agency

MT Metric tone PF/RF Protected Forest/Reserve Forest

PM10/2.5 Particulate Matter PP Project Proponent

PPE Personal Protective Equipment R & R Plan Resettlement & Rehabilitation plan

ToR Terms of Reference

Page 6: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

6 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

INDEX CHAPTER-I ............................................................................................................................................... 12

INTRODUCTION .................................................................................................................................................................. 12

1.1 PURPOSE OF THE REPORT ................................................................................................................................... 12

1.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT .......................................................................................... 12

DIST- KOTA, RAJASTHAN.................................................................................................................................................................. 13

1.3 BRIEF DESCRIPTION OF NATURE, SIZE AND LOCATION OF THE PROJECT ...................................................... 13

1.5 SCOPE OF THE STUDY ................................................................................................................................................................ 14

CHAPTER - II ............................................................................................................................................ 25

PROJECT DESCRIPTION ................................................................................................................................................... 25

2.1 TYPE OF PROJECT ......................................................................................................................................................................... 25

2.2 NEED OF THE PROJECT.............................................................................................................................................................. 25

2.3 LOCATION OF THE PROJECT ................................................................................................................................................... 25

2.2 DESCRIPTION OF LEASE AREA & MINING PROCESS.................................................................................................... 29

2.4 BASIC FACILITIES ....................................................................................................................................................................... 32

2.5PROPOSED SCHEDULE FOR APPROVAL AND IMPLEMENTATION ......................................................................... 33

CHAPTER-III ............................................................................................................................................ 34

DESCRIPTION OF THE ENVIRONMENT .................................................................................................................... 34

3.1 STUDY AREA ................................................................................................................................................................................... 34

3.2 ESTABLISHMENT OF BASELINE FOR VALUED ENVIRONMENT COMPONENT ............................................. 35

3.3 WATER ENVIRONMENT ............................................................................................................................................................ 49

3.4 AMBIENT AIR ENVIRONMENT ............................................................................................................................................... 57

3.5 NOISE ENVIRONMENT ............................................................................................................................................................... 72

3.6 TRAFFIC DENSITY: ....................................................................................................................................................................... 76

3.7 BIOLOGICAL ENVIRONMENT .................................................................................................................................................. 78

3.8 SOCIO-ECONOMIC ENVIRONMENT: ..................................................................................................................................... 86

CHAPTER - IV ....................................................................................................................................... 171

ANTICIPATED IMPACTS& MITIGATION MEASURES ......................................................................................... 171

4.1INTRODUCTION ............................................................................................................................................................................ 171

4.2 IMPACT ON LAND ENVIRONMENT AND MITIGATION MEASURES ..................................................................... 171

4.3 IMPACT ON WATER ENVIRONMENT AND MITIGATION MEASURES ................................................................. 172

4.4 IMPACT ON AIR ENVIRONMENT AND MITIGATION MEASURES ......................................................................... 173

4.5 IMPACT OF NOISE / VIBRATIONS & MITIGATION MEASURES ............................................................................. 178

4.6 IMPACT ON BIOLOGICAL ENVIRONMENT & MITIGATION MEASURE ............................................................... 179

4.7 IMPACT ON SOCIO ECONOMIC CONDITIONS................................................................................................................. 180

4.8 IMPACT ON OCCUPATIONAL HEALTH & SAFETY ....................................................................................................... 181

CHAPTER – V ........................................................................................................................................ 184

Page 7: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

7 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

ANALYSIS OF ALTERNATIVES .................................................................................................................................... 184

5.1SITE ALTERNATIVES ............................................................................................................................................................... 184

5.2TECHNOLOGY ALTERNATIVES ............................................................................................................................................. 184

CHAPTER – VI ....................................................................................................................................... 185

ENVIRONMENTAL MONITORING PROGRAMME ................................................................................................ 185

6.1 MONITORING SCHEDULE AND PARAMETERS ......................................................................................................... 185

6.2 ENVIRONMENT MONITORING CELL ............................................................................................................................. 186

6.3 FUNCTIONS OF THE MONITORING CELL .................................................................................................................... 187

6.4 ENVIRONMENTAL POLICY: ............................................................................................................................................... 188

CHAPTER - VII ...................................................................................................................................... 189

ADDITIONAL STUDIES ................................................................................................................................................... 189

7.1 INTRODUCTION ........................................................................................................................................................................... 189

7.2 PUBLIC CONSULTATION: ........................................................................................................................................................ 189

7.2 RISK ASSESSMENT ..................................................................................................................................................................... 192

7.3 IDENTIFICATION OF HAZARDS ............................................................................................................................................ 192

7.4 SCENARIOS CONSIDERED FOR RISK ASSESSMENT .................................................................................................... 192

7.5 DISASTER MANAGEMENT PLAN ......................................................................................................................................... 194

7.6 OUTLINE OF DISASTER MANAGEMENT PLAN.............................................................................................................. 195

7.8 SOCIAL IMPACT ASSESSMENT, R&R ACTION PLAN ................................................................................................... 195

CHAPTER - VIII .................................................................................................................................... 196

PROJECT BENEFITS ......................................................................................................................................................... 196

CHAPTER – IX ....................................................................................................................................... 197

ENVIRONMENT MANAGEMENT PLAN .................................................................................................................... 197

9.1 INTRODUCTION ........................................................................................................................................................................... 197

9.2 GREEN BELT DEVELOPMENT ............................................................................................................................................... 200

9.3 SOCIO ECONOMIC ENVIRONMENT ..................................................................................................................................... 202

9.4 OCCUPATIONAL SAFETY & HEALTH ................................................................................................................................. 203

9.5 TOP SOIL AND WASTE MANAGEMENT ............................................................................................................................ 205

CHAPTER – X ........................................................................................................................................ 207

SUMMARY & CONCLUSION ........................................................................................................................................... 207

10.1 INTRODUCTION ........................................................................................................................................................................ 207

10.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT: .................................................................................... 207

10.3 LOCATION OF PROJECT: ....................................................................................................................................................... 208

10.4 SIZE OR MAGNITUDE OF OPERATION: .......................................................................................................................... 208

10.5 MINING METHOD ..................................................................................................................................................................... 208

10.6 EMPLOYEE DETAIL: About 109 workers will be required. .................................................................................. 208

10.8 DESCRIPTION OF ENVIRONMENT ................................................................................................................................... 209

10.9 ENVIRONMENT MONITORING CELL ............................................................................................................................... 210

Page 8: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

8 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

10.10 ENVIRONMENT MANAGEMENT PLAN ........................................................................................................................ 210

CHAPTER – XI ....................................................................................................................................... 212

CONSULTANTS ENGAGED ............................................................................................................................................ 212

1 ................................................................................................................................................................ 205

LIST OF TABLES

TABLE 2.1: DETAIL OF YEAR WISE PROPOSED PRODUCTION ................................................. 14

TABLE 2.1: DETAIL OF YEAR WISE PROPOSED PRODUCTION ................................................. 31

TABLE 2.2: DETAIL OF PROPOSED WASTE TO BE GENERATED FOR MINING OPERATION

31

TABLE 2.3: DETAIL OF MANPOWER REQUIRED FOR MINING OPERATION ....................... 32

TABLE 2.4: DETAIL OF MACHINERY DEPLOYED OR TO BE DEPLOYED ............................... 32

TABLE 2.5WATER REQUIREMENT ....................................................................................................... 32

TABLE 3.1: STUDY AREA AT A GLANCE .............................................................................................. 34

TABLE 3.2: LAND USE PATTERN BASED ON SATELLITE IMAGE ............................................. 36

TABLE 3.3: LAND USE PLAN FOR PRE- OPERATIONAL, OPERATIONAL & POST -

OPERATIONAL PHASES (IN HECT.) ...................................................................................................... 39

TABLE 3.4: SOIL SAMPLING LOCATIONS IN THE STUDY AREA................................................ 45

TABLE 3.5: ANALYSIS RESULTS OF SOIL SAMPLES ....................................................................... 48

TABLE 3.6: LOCATION OF WATER SAMPLING IN THE STUDY AREA ..................................... 53

TABLE 3.7: ANALYSIS RESULTS OF GROUND WATER SAMPLES ............................................. 56

TABLE 3.8: LOCATION OF AMBIENT AIR MONITORING STATIONS ...................................... 59

TABLE 3.9: PROCEDURE FOR DETERMINING VARIOUS AIR QUALITY PARAMETERS ... 62

TABLE 3.10 (A): MEAN TEMPERATURE & RELATIVE HUMIDITY ........................................... 62

Sources- IMD station Jhalawar ................................................................................................................ 62

TABLE 3.10 (B): MEAN TEMPERATURE& RELATIVE HUMIDITY AT PROJECT SITE ...... 63

TABLE 3.11: AMBIENT AIR QUALITY RESULT ................................................................................. 63

TABLE 3.12: COMPARISON OF AIR MONITORING RESULTS ...................................................... 71

TABLE 3.13: LOCATION OF NOISE MONITORING STATIONS .................................................... 72

TABLE 3.14: NOISE LEVEL WITHIN THE STUDY AREA (Unit – dBA) ..................................... 75

TABLE 3.15: CPCB NOISE STANDARD ................................................................................................. 75

TABLE 3.16: LIST OF FLORAL SPECIES OBSERVED IN CORE ZONE ........................................ 82

TABLE 3.17: LIST OF FLORAL SPECIES OBSERVED IN BUFFER ZONE................................... 82

TABLE 3.18: LIST OF FAUNA SPECIES OBSERVED IN THE CORE ZONE ................................ 84

TABLE 3.19: LIST OF FAUNAL SPECIES OBSERVED IN BUFFER ZONE .................................. 85

Page 9: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

9 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

TABLE 3.20: LIST OF AVIFAUNAL SPECIES OBSERVED IN THE STUDY AREA ................... 86

TABLE 3.21 DISTRIBUTION OF POPULATION ................................................................................. 88

TABLE :- 3.22 DISTRIBUTION OF POPULATION SOCIAL STRUCTURE................................... 90

TABLE 3.23 DISTRIBUTION OF LITERATES AND LITERACY RATE ......................................... 90

TABLE 3.24 OCCUPATIONAL STRUCTURE ........................................................................................ 92

TABLE NO-4.1 PREDICTED AMBIENT AIR QUALITY CONCENTRATIONS IN OPERATION

PHASE CUMULATIVE CONCENTRATIONS (BASELINE + INCREMENTAL) FOR PM10 .. 174

TABLE 6.1: MONITORING SCHEDULE FOR ENVIRONMENTAL PARAMETERS ................ 185

TABLE 9.1: ENVIRONMENT MANAGEMENT PLAN IMPLEMENTATION ........................... 197

TABLE 9.2: COST ESTIMATES OF EMP IMPLEMENTATION .................................................... 200

TABLE 9.3: STAGE WISE PLANTATION ........................................................................................... 201

TABLE 9.4: PROPOSED PLANTATION .............................................................................................. 201

TABLE 9.5: COST OF CSR ACTIVITIES .............................................................................................. 202

TABLE 9.6: BUDGETARY PROVISION FOR WORKERS ............................................................... 204

TABLE 9.7: PROPOSED WASTE GENERATED FOR MINING ACTIVITY ............................... 205

10.7 MACHINERIES DEPLOYED: ......................................................................................................... 208

LIST OF FIGURES

FIGURE 2.1: LOCATION MAP ................................................................................................................... 26

FIGURE 2.2: KEY PLAN OF THE LEASE AREA ................................................................................... 27

FIGURE 2.3: GOOGLE IMAGE SHOWING GENERAL LOCATION OF THE LEASE AREA ..... 28

FIGURE 2.4: GOOGLE IMAGE OF THE LEASE AREA WITH BOUNDARY PILLARS .............. 28

FIGURE 3.1: LAND USE / LAND COVER MAP PATTERN OF THE STUDY AREA. ................. 37

FIGURE 3.2: SATELLITE IMAGE OF 10 KM RADIUS OF THE STUDY AREA ........................... 38

FIGURE 3.3: TOPOGRAPHY MAP OF THE STUDY AREA ............................................................... 40

FIGURE 3.4: DRAINAGE MAP OF THE STUDY AREA ...................................................................... 41

FIGURE 3.5: SURFACE GEOLOGICAL PLAN AND SECTION OF THE LEASE AREA .............. 44

FIGURE 3.6: SOIL SAMPLING LOCATIONS IN THE STUDY AREA .............................................. 46

FIGURE 3.7: PHOTOGRAPHS OF SOIL SAMPLING IN THE STUDY AREA ............................... 47

FIGURE 3.8: HYDROGEOLOGICAL MAP OF THE DISTRICT KOTA ............................................ 50

FIGURE 3.8(A): DEPTH TO WATER TABLE PRE-MONSOON ...................................................... 52

FIGURE 3.8(B): DEPTH TO WATER TABLE POST-MONSOON .................................................... 52

FIGURE 3.9: WATER SAMPLING LOCATIONS MAP IN THE STUDY AREA ............................. 54

FIGURE 3.10: PHOTOGRAPHS OF WATER SAMPLING IN THE STUDY AREA ...................... 55

Page 10: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

10 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.11: WIND ROSE DIAGRAM ................................................................................................... 57

FIGURE 3.12: AMBIENT AIR SAMPLING LOCATION IN THE STUDY AREA .......................... 60

FIGURE 3.13: PHOTOGRAPHS OF AMBIENT AIR MONITORING IN THE STUDY AREA ... 61

FIGURE 3.14: NOISE MONITORING LOCATION MAP ..................................................................... 73

FIGURE 3.15: PHOTOGRAPHS OF NOISE & TRAFFIC MONITORING IN THE STUDY ARE74

FIGURE 3.16: TRANSPORTATION ROUT MAP .................................................................................. 77

FIGURE 3.17: BIOLOGICAL SAMPLING LOCATION MAP OF THE STUDY AREA .................. 80

FIG 3.18 PHOTOGRAPHS OF VEGETAION .......................................................................................... 81

FIG.NO. 3.19 .................................................................................................................................................... 89

FIG.NO.3.20 ..................................................................................................................................................... 91

FIG.NO. 3.21 .................................................................................................................................................... 92

FIGURE 3.22: SOCIO –ECONOMIC SURVEY LOCATION MAP ................................................... 170

FIGURE 4.1: GROUND LEVEL CONCENTRATION OF AAQ DURING OPERATION PHASE IN 10

KM FOR PM10............................................................................................................................................. 175

FIGURE-4.2: GROUND LEVEL CONCENTRATION OF AAQ DURING OPERATION PHASE IN 1

KM FOR PM10 ............................................................................................................................................ 176

FIGURE 6.1: ENVIRONMENT MONITORING CELL (EMC) ......................................................... 186

A. Mine site ................................................................................................................................................. 190

Total ............................................................................................................................................................... 190

Mining Lease ............................................................................................................................................... 202

Township Site ............................................................................................................................................. 202

LIST OF ANNEXURE

ANNEXURE –I: COPY OF LEASE AGREEMENT ................................................................................................................................. 212

ANNEXURE –II: COPY OF NOMINATION LETTER .......................................................................................................................... 225

ANNEXURE –III: COPY OF LEASE EXTENSION LETTER .............................................................................................................. 226

ANNEXURE IV COPY OF APPROVAL LETTER OF MINING PLAN ............................................................................................. 227

ANNEXURE –V: COPY OF KHASRA MAP, JAMABANDI& DEMARCATION ............................................................................ 228

ANNEXURE –VI: PREVIOUS Year’s PRODUCTION .......................................................................................................................... 234

ANNEXURE –VII COPY OF ARAVALI LETTER ................................................................................................................................... 236

ANNEXURE –VIII COPY OF COMPOSITE MAP .................................................................................................................................. 237

ANNEXURE –IX COPY OF NOC ................................................................................................................................................................. 238

ANNEXURE –X: COPY OF MONITORING REPORT........................................................................................................................... 239

ANNEXURE –XI: TOR LETTER ................................................................................................................................................................. 269

ANNEXURE –XII: COPY OF MINUTES OF PUBLIC HEARING ...................................................................................................... 274

ANNEXURE –XIII: PHYTOSOCIO REPORT OF STUDY AREA ....................................................................................................... 282

Page 11: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

11 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

ENVIRONMENTAL IMPACT ASSESSMENT &

ENVIRONMENTAL MANAGEMENT PLAN

Page 12: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

12 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

CHAPTER-I

INTRODUCTION

Mining, Environment and development have become complimentary to each other. As

a result of developmental activities visible ill-effects of the environmental degradation

are clear and give signals of the concern. Therefore a sustainable development of the

area involving extraction of mineral wealth vis-à-vis protection of environment is the

ultimate solution for betterment of mankind.

1.1 PURPOSE OF THE REPORT

The Environmental Impact Assessment has been prepared to assess the current

environmental scenario of the area and then based on the activities of mining

proposed, to carry out Environmental Management Plan. The plan will identify and

address the impacts, where these are adverse in nature, and thereafter to design

mitigation measures to manage such impacts in a manner as to conserve environment

and ecology of the area. The EMP has been prepared with a view to ultimately ensure

that the adverse impacts are minimized if these cannot be prevented altogether.

Environmental clearance is a statutory requirement for the new and old establishment

of any mining project of which EIA has to be prepared and submitted to respective

agencies of state and central level in line with EIA Notification, 1994 & 2006.

As per New EIA Notification Dated 14th Sept. 2006, Environmental Clearance is

required for all old & new mining projects / enhancement of production.

1.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT

PROJECT IDENTIFICATION

This is a mining project of Satalkhedi-Pipakhedi limestone (Building Stone) Mine, near

village - Satalkhedi-Pipakhedi, Tehsil – Ramganj Mandi, District – Kota (Rajasthan)

over 43.24 ha Pvt. land.

Originally the mining lease (Area 83.87ha.) was granted in favour of Shri Ganga Ram

Bairwa S/o Sh. Kalu Ram Bairwa vide letter No-9(4) Khan/Group/-2/92 in dated

13/04/92 for 10 years (20-01-1992 to 19-01-2002). The lease deed was executed on

30/05/1992 and registered on dated 30/06/1992

Page 13: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

13 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Lease renewal order was given for 10 years on dated 20.01.1992 to 19.01.2002 after

that it has extended up to the 19.01.2012.

About 40.63 ha lease area was surrendered on dated 20.01.2001.

After the death of Ganga Ram Bairwa the lease was Nominated in favour of Shri

Pankaj kumar Bairwa S/o Shri Swaroop Chand Bairwa.

And now the lease has been renewed up to the 19.01.2022.

Mining plan with progressive mine closure plan has been approved on dated 31-12-

2013.

Project was submitted to SEIAA Raj for environment clearance and Tor was issues vide

letter No- F1/(4)/SEIAA/SEAC-Raj/Sectt/Project/Cat 1(a). B1 (7243)/14-15/752 on

dated 06/05/2016 & public hearing also conducted on dated 06/12/2016.

Ref Annexure-I Copy of lease agreement

Ref Annexure-Ii Copy of nomination letter

Ref Annexure-III Copy of lease extension letter

Ref Annexure-IV Copy of approval letter of mining plan

Ref Annexure-V Copy of khasra map & Jamabandi

Ref Annexure-XI Copy Of Tor Letter

Ref Annexure-X Minutes Of Public Hearing

IDENTIFICATION OF PROJECT PROPONENT

Sh. Pankaj Kumar Bairwa S/O - Sh. Swaroop Chand, R/O -Satalkhedi, Tehsil -Ramganjmandi

Dist- Kota, Rajasthan

1.3 BRIEF DESCRIPTION OF NATURE, SIZE AND LOCATION OF THE PROJECT

NATURE OF PROJECT:

This project is for mining of Limestone near village – Satalkhedi-Pipakhedi, Tehsil –

Ramganj Mandi, District – Kota (Rajasthan) it existing mine which produce limestone

(Building stone) from opencast method.

Previous year’s production is attached as ANNEXURE NO VI

SIZE-

The lease covers an area of 43.24 hectare and it is proposed to produce about

3, 21,699 TPA (RoM) Lime Stone (Building Stone).

Page 14: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

14 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

LOCATION

The lease area is situated at near village - Satalkhedi-Pipakhedi,, Tehsil – Ramganj

Mandi, District – Kota (Rajasthan) over 43.24ha Pvt. land.

1.5 SCOPE OF THE STUDY

The point wise compliance of the Standard TOR prescribed by the committee in the

tabular form is given as under.

S. No. Description Covered in EIA as per details

1. The study area will comprise 10

km zone around the mine lease

from lease periphery and the data

contained in the EIA with respect

to mining operations such as

conceptual pit limits, waste

generation etc. should be for the

life of the mine/lease period.

The EIA study has been carried out in the 10 km radius from the periphery of the lease area. Key plan show core zone and buffer zone of 10 km radius from lease boundary Ref figure No 2.2, Data like reserves, waste generation Up to life of mine have been incorporated in Chapter II of EIA/EMP Report.

2. Location of other industries &

mines within the study area along

with their production and

pollutants generated by them,

estimated pollution load and

cumulative impact on

environment including the

proposed project should be

submitted. The same shall be

accounted for while generating

mathematical models of pollution

dispersion for preparation of the

EMP.

There are two other mining leases exists in the periphery of 500 m

of lease area. The monitoring has been carried and cumulative

impact has been estimated including the proposed project. Detail is

given in Chapter-IV.

Isopleths is given in EIA EMP report on page no-118-119, Fig No-4.1

& 4.2.

3. Year-wise production details

clearly indicating the proposed

highest production for the life of

the mine/lease period should be

submitted.

Proposed year wise production detail TABLE 2.1: DETAIL OF YEAR WISE PROPOSED PRODUCTION

Year Production

in MT (RoM)

Saleable

Mineral

tones

Waste

generated

from the total

excavation

(MT)

Sub

grade

in MT

Over burden

form OB

benches

tonnes

I 321697 225189 80424 16084 1026432

II 321697 225189 80424 16084 712800

III 321697 225189 80424 16084 712800

IV 321697 225189 80424 16084 712800

V 321697 225189 80424 16084 712800

Page 15: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

15 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Total

1608485

1125945 402120 80420 3877632

As per approved mining plan.

4. Details of land to be used as the

designated dumping site for OB

dump should be selected and

proposed within the lease area as

per the approved mine plan. In no

case the overburden should be

dumped outside the lease area,

however proposal for utilization of

OB for construction or other

meaningful use to the extent

possible may be submitted.

The waste as OB in the area is top soil and fractured limestone . the

soil cover in the area varies from 3m fractured limestone varies

from 27 m. This OB will be dumped at mined out pit. This sub grade

material will be stacked at earmarked site.No external dump within

lease area will be created and no O/B will be dumped outside during

course of mining.

Detail is given in Chapter- II

5. Land use plan of the mine lease

area should be prepared to

encompass pre-operational,

operational and post operational

phases.

Land use pattern of the mine lease area of pre-operational phase,

operational phase & post operational phase is given below:

Note- About 15.9800 ha area has been already planted within

lease for full fill 33% plantation as per ToR compliance. At the

end of mine life about 20.77 ha area will be planted which

includes 3.5400 Ha area will be planted on statuary barrier

(7.5 Meter) & 17.2396 ha area will be backfill planted. About

6.4804 ha area will be converted as water storage.

Particulars Pre Operational (in Ha)

Operational (in Ha)

Post operational (in Ha)

Mining Activity

Mining pits 8.5215 10.5710 0.00

Road & building

2.3750 2.3750 0.00

Plantation on statuary barrier

0.0000 2.5500 3.5400

Mineral stack 1.5420 1.9540 0.0000

Water storage 1.2010 1.2010 6.4804

Reclamation & Backfilled Plantation

5.9800 5.9800 17.2396

Plantation on remaining lease area

15.9800 15.9800 15.9800

Remaining virgin land

7.6405 2.6290 0.000

Total 43.24 43.24 43.24

Page 16: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

16 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

6. The P.P. should provide a mining

plan along-with progressive mine

closer plan and implementation

plan at the time of presentation for

the EC.

Mining Plan along with Progressive Mine Closure Plan is submitted

along with the final EIA report.

7. Based on the study and the points

raised by the people during public

hearing, the P.P. shall work out an

effective plan to address the

environmental and socio-

economic issues identified during

the process, with suitable funds

allocation for the purpose.

Public hearing was conducted on dated 06.12.2016 at the Atal Seva

Kendra Gram Panchayat Bhawan in village Satalkhedi, Tehsil –

Ramganjmandi, Dist. – Kota, Rajasthan.

8. Certificate regarding mine lease

area not falling in the Aravalli Hills

to be issued by the Mining

Engineer/ Assistant Mining

Engineer in the prescribed format,

as per the instructions contained

in the letter no.

DMG/ADM/Env/EC/F11/06/17-

76 dt. 17.01.2011 issued by the

Director, Department of Mines and

Geology, GoR, Udaipur, should be

countersigned by the Additional

Director (Mines), DMG of

concerned Region and copy be

submitted with other required

documents.

The lease area does not falls in Aravalli hills. Copy of Aravalli letter

Attach annexure N0-VII

9. List/details within 10 km radius of

the mine lease area, the location of

human settlement, water bodies,

Reserve Forest, National Parks,

Sanctuaries, Biosphere Reserves,

Wildlife Corridors, Tiger/Elephant

reserves (existing / proposed),

shall be clearly indicated giving

the land use. Necessary clearance,

if any, as may be applicable to such

projects due to proximity of the

ecologically sensitive areas as

mentioned above shall be obtained

from the Chief Wildlife Warden

under the Wildlife (Protection)

Act’ 1972 and submitted. This

location map should also indicate

the list and location of other mine

leases existing, if any, within 10

km radius.

The nearest human settlement is village Satalkhedi & Pipakhedi

which is distance about 0.8 & 1.0 Km from mining lease area. Three

river namely Ahu, Amjar, Psadi is flowing in study area. There is no

water body exist in lease area. Drainage map (figure No.3.4) is

enclosed in the report on page No-49.

There is no National park, Sanctuaries, Biosphere reserve wild life

corridors exist within 10 km zone of lease area.

Page 17: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

17 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

10. A detailed biological study for the

study area [core zone and buffer

zone (10 km radius of the

periphery of the mine lease)] shall

be carried out. Details of flora and

fauna, duly authenticated,

separately for core and buffer zone

should be furnished based on field

survey. The details regarding flora

to include information regarding

(a) trees, shrubs, grasses, (b)

frequency, density, I V I,

abundance % of species occurring

on proposed site, (c) dominant

species of trees, shrubs , grasses

(d) endemic species, (e)

threatened species, (f) rare

species, (g) endangered species

and (h) vulnerable species. The

details of fauna to include

information regarding list and

distribution clearly indicating the

Schedule of the fauna present. In

case of any scheduled-I fauna

found in the study area, the

necessary plan for their

conservation should be prepared

in consultation with State Forest

and Wildlife Department and

details furnished. Necessary

allocation of funds for

implementing the same should be

made as part of the project cost.

A detailed biological study of the core and buffer zone has been

carried out. Detail is given in Chapter-III.

No endangered flora & fauna found in core & buffer zone.

Authentication List of flora fauna is under process.

11. Collection of one season (non-monsoon) primary baseline data on ambient air quality, water quality, noise level, soil and flora and fauna. Ambient Air quality should be determined by measuring the concentration of parameters like P.M.2.5, P.M.10, SO2, NOx according to the latest standards prescribed by CPCB. Site-specific meteorological data should also be collected. The location of the monitoring stations (minimum 6) should be justified. Date wise collected baseline AAQ data should form part of EIA and EMP report. The monitoring shall be carried out by CPCB/NABL/

One season (post monsoon season) primary base line data on

ambient air quality (PM2.5, PM10, SO2 and NOx), water quality, noise

level, soil and flora and fauna has been done and Date-wise AAQ

data is given in Chapter III, Table-3.11 & page no-58

Site-specific meteorological data has been collected and the AAQ and

other data are compiled in the EIA report. All monitoring station

along with the location map of monitoring sites are given in Chapter-

III,

Analysis report is attached as Annexure No-X

Page 18: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

18 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

MOEF/GoR approved laboratory and copy of the report submitted. The monitoring if any prior to submission of project to SEIAA for ToR will not be considered.

12. Air quality modeling should be

carried out for prediction of

impact of the project on the air

quality of the area. It should also

take into account the impact of

movement of vehicles for

transportation of mineral. The

details of the model used and input

parameters used for modeling

should be provided. The air

quality contours may be shown on

a location map clearly indicating

the location of the site, location of

sensitive receptors, if any and the

habitation. The wind roses

showing pre-dominant wind

direction may be indicated on

map. Wind Rose Diagram should

be representative and include

stability class and inversion

phenomenon of that area along

with the lapse rate.

Air quality modeling has been carried out by Fugitive Dust Model

(FDM) which is based on Gaussian Plume Model. Vehicular

movement for the transportation of the mineral will be limited.

Therefore much impact is not envisaged. However a detailed study

has been conducted for prediction of impact details given chapter-

IV, para-4.4,. Sampling location for Air Quality Monitoring is marked

on the Air sampling location map in Chapter III Figure No-3.12.

Location of the monitoring stations represent whole of the study

area keeping in view the pre-dominant wind direction. Wind rose is

given chapter-III figure No-3.11. Isopleths is given chapter-IV figure

No-4.1 & 4.2.

The incremental value about the project is given in below table-

Particular

Mine Site

A1

Monitored Maximum concentrations in µg/m3

(Core zone) 78.7*

Predicted incremental Maximum

concentrations in µg/m3 0.8

Resultant Maximum concentrations in µg/m3 79.5

NAAQS (dated 2009) 100

13. A surface and ground water study should be carryout, both pre-monsoon and post monsoon monitoring. Information about proposed working depth of mining area, groundwater table both in above MSL and below ground level (BGL) should be provided. Based on actual monitored data, it may clearly be shown whether mine working will intersect groundwater table or not. In case the mining activity intersects the ground water table then necessary permission from CGWA should be obtained. Impact of the project on the water quality both surface and groundwater should also be assessed and necessary safeguard measures, if any required should be provided. Further, submit

Ground water study has carryout during the survey. Detail is given

in Chapter-III. Groundwater water were taken to analyze the quality

of water in the study area detail is given in chapter-III with results.

Systematic representation diagram of site elevation, working depth,

ground water table is given below-

295 mRL (45mbgl Pre monsoon)

300mRL ( 40 mbgl Post monsoon)

WATER TABLE

303 mRL (37 mbgl)

ULTIMATE DEPTH

337 mRL (Lowest Contour)

GROUND LEVEL

Proposed working will not intersect Ground

water table.

340 mRL (Highest contour)

hiesest

Page 19: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

19 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

water drainage plan of the 10 km study area.

A drainage plan of the 10.0 km study area has been prepared is

given in chapter-III (figure No. 3.4).

14. The water requirement for the project, its availability and source to be furnished. A detailed water balance should also be provided. Fresh water requirement (if any) for the project should also be indicated. Necessary clearance from the Competent Authority for drawl of requisite quantity of water for the project should be provided. Details of water conservation measures including rainwater harvesting should be provided and to be adopted in the project.

WATER REQUIREMENT

S. No Particulars Quantity KLD

1. Drinking 2.0

2. Water Sprinkling 3.0

3. Green belt 3.0

Total 8.0

Water requirement for domestic/drinking, green belt & water

sprinkling purpose will be met through water tanker from dug wells

at the nearby village. There is no proposal for drawl of water within

the lease area, hence clearance for the same is not required.

Plantation is proposed along lease boundary & backfill mine out

area. Same part of work out pit will be left for rain water storage

which can be used for irrigation & other purpose & help in

recharging of ground water in near village.

15 Consumption of diesel and its storage should be provided along with an action plan for its conservation.

Total 300 lit/d diesel will be required for mining operation, there

will be not required any storage facilities of diesel. The diesel will

be providing authorized contractor on contractual basis.

16. The Conceptual post mine land use plan and Reclamation & Rehabilitation (R&R) plan of mined out area (with plans and sections at appropriate scale as per MCDR 1988 should be submitted.

The post mine land use id given under-

Particulars Position at the End of life of the mine

(post- operational in Ha)

Mining pits 0.00 Road & building 0.00

Plantation on statuary barrier

3.5400

Mineral stack 0.00

Dump Area 0.00

Water storage 6.4804

Reclamation & Backfilled Plantation

17.2396

Plantation on reaming lease area

15.98

Total 43.24 Note- About 15.9800 ha area has been already planted within lease

Page 20: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

20 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

for full fill 33% plantation as per ToR compliance. At the end of

mine life about 20.77 ha area will be planted which includes 3.5400

Ha area will be planted on statuary barrier (7.5 Meter) & 17.2396 ha

area will be backfill planted. About 6.4804 ha area will be converted

as water storage.

Conceptual mine plan is attached as plate No.5.

17. Impact on local transport and

infrastructure due to the project.

Projected increase in hauling

vehicles as a result of the project

in the present road network

(including those outside the

project area) and whether it is

capable of handling the increased

load. Arrangement for improving

the infrastructure to avoid any

conjestion especially at junctions

and mishaps throughout the route

of transportation of mineral

should be ensured and action to be

taken by other agencies such as

State Government, if any, should

be covered.

About 5-6 dumpers / day will be required for transport of mineral

from mine. Increase in truck traffic is negligible and the existing

road network is capable of handling the increased load. State govt.

conduct traffic census regularly and take action accordingly.

A detail of traffic environment is refer chapter-III, para-3.6 & page

no-89.

18. The green belt area should be developed in 33% of total lease area, provide time taken for of progressive greenbelt development, plantation and compensatory a-forestation clearly indicating the 33% area to be covered under plantation giving detail of local species, width of plantation, plantation schedule etc. along with year wise financial expenditure. The proposal for completion should be for a period of 3 years from the start of mining operation. Information regarding greenbelt development plan shall also be prepared in a tabular form, indicating the location of the area, type of tree and its number supported by a map. Further, existing mining projects should carryout plantation in 33% of lease area and thereafter come for the EC.

About 15.98 ha area is already planted & At the end of mine life

about 20.77 ha area will be planted which includes 3.5400 Ha area

will be planted on statuary barrier (7.5 Meter) & 17.2396 ha area

will be backfill planted. Details of progressive greenbelt

development program are given in Chapter-IX table no 9.3.

Plantation species already given in Chapter IX on Table No-9.4.

Page 21: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

21 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

19. Budgetary provision for the labors working in the Mine should be submitted for all necessary infrastructure facilities such as health facility, sanitation facility, and fuel for cooking, along with provision for safe drinking water, monthly medical camps and distribution of medicines, primary education and toilets for women, crèche for infants.

Salary will be given as per the norms & all the facilities like health

facility, sanitation facility, along with provision for safe drinking

water, periodic medical etc. will be provided to the workers.

Budgetary provision for the labours to be employed in the mine is

given as under:

Facility Provided for Labourers

Total amount per year

Drinking water By Tanker 30,000/- First Aid Box 20,000/- Rest Shelter 50,000/- Washroom 20,000/- Safety shoes 75,000/- Hand Gloves 75,000/- Dust Mask 50,000/- Ear Plugs / Muffler 30,000/- Helmet 50,000/- Insurance 1,00,000

Total 5,00,000

20. Details regarding Occupational

health impact of the project should

be provided. Health study in the

surrounding area be carried out

covering information regarding

prevailing diseases, mortality rate

etc. Health and Safety Plan should

be prepared and submitted.

Occupational health impact including -Physical hazard, fatal injury

include rock fall, fires, explosions, mobile equipment accidents, etc.

given in report.

Socio survey has been carried out during study period health study

in the surrounding areas is given in chapter-III on page no-

The mining will be done with all safety PPE (Dust mask, Safety

boots, Helmet Ear muffs.) under the supervision of Qualified Staff.

Regular Water sprinkling will be done on haul roads, regular health

check-up two times in one year of the mine workers will be done

and all mitigation measure will be adopted. Vocational training will

be provided to the workers.

Details about, Occupational Health impacts, person protective

measures, pre-placement medical examination and periodical

medical examination schedules, management plan has been

furnished in Chapter-IV, and Chapter IX.

21. The P.P. will carry out proper Socio-economic survey of the villages situated in the study area. The details of survey are given if format J. Based upon its findings and also as per public hearing issues and keeping in view the felt needs of local populations, the P.P. will provide adequate budget for carrying out CSR/ESR activities including provision for toilets for girls in nearby schools, monthly medical camps, distribution of medicines and improvement in

Socio economic survey of the villages situated within the study area

has been carried out and detail is given in Chapter – III. The mining

activity in this area will have positive impact on socio economic

condition of the area & providing employment to the local people.

Wages paid to them will increase the per capital income. Thus

project will have positive impact on the surrounding local

community.

Propose CSR activities are given in Chapter-IX .

Page 22: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

22 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

educational facilities in the nearby schools. Further, existing mining projects should carryout ESR/CSR for a period of at least one year and thereafter come for the EC.

22. Measures for socio economic

influence on the local community

due to proposed project to be

provided by project proponent. As

far as possible, appropriate

quantitative dimension to be

given. Analysis of Job

requirements vis-à-vis,

employability of local population

need to be provided.

This mining project will create opportunity of direct as well as

indirect employment to the local people. There will be direct

employment opportunities in the mine and also the secondary

employment by contract jobs associated with mining works.

Proposed project will provide employment to about 109 people and

preference will be given to local people.

Propose CSR activities are given in Chapter-IX.

23. Detailed environmental

management plan to mitigate the

environmental impacts which,

should inter-alia also include the

impact due to change of land use,

due to loss of agricultural land and

grazing land, if any, besides other

impacts of the projects. The

budgetary provision (both capital

and recurring) for implementing

the proposed EMP should be

clearly spelt out.

A well laid Mitigation Plan is prepared with respect to impact of the

project (Environmental protection measures including green belt

development, water sprinkling on haul roads, regular monitoring for

air quality, and Water quality monitoring, maintenance of Noise

generating sources) on the surrounding environment. For detail

refer Chapter IV & Chapter IX. About Rs. 3.5 lac per year will be

spent for EMP.

24. The points raised during Public hearing and commitment of the project proponent on the same along with time bound action plan to implement the commitments and the necessary allocation of funds for the same to be provided.

Public hearing was conducted on dated 06.12.2016 at the Atal Seva

Kendra Gram Panchayat Bhawan in village Satalkhedi, Tehsil –

Ramganjmandi, Dist. – Kota, Rajasthan.

25. Any litigation pending against the

project and /or any direction

/order passed by any Court of Law

against the project, if so, details

thereof should be submitted.

No litigation pending against this project.

26 The P.P. should ensure compliance

of the order of the Hon’ble

Rajasthan High Court, Jodhpur, in

D. B. Civil writ petition no. 1536 of

2003 in the matter of Abdul

Rahman vs State of Rajasthan and

others and submit a brief note

regarding compliance of the court

order.

The P.P has ensured the compliance of the order of the Hon’ble

Rajasthan High Court, Jodhpur.

27. That the Project Proponent shall

not use any explosive and blasting

Controlled blasting shall be done by the blasting contractor. The

explosives will be handled by the blasting contractor hence no

Page 23: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

23 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

for mining activity without proper

permissions from competent

authorities.

storage of explosives is required at site. Detail of blasting is given in

Chapter-II.

28. Provide details about

transfer/allotment of mining lease,

extension of lease period etc. along

with authenticated copies of

orders for lease allotment /

transfer / extension of validity

period.

Originally the mining lease (Area 83.87ha.) was granted in favour of

Shri Ganga Ram Bairwa S/o Sh. Kalu Ram Bairwa resident of

Satalkheri, Tehsil- Ramganj Mandi District Kota.(Rajasthan)

Lease renewal order was given for 10 years on dated 20.01.1992 to

19.01.2002 after that it has extended up to the 19.01.2012.

About 40.63 ha lease area was surrendered on dated 20.01.2001.

After the death of Ganga Ram Bairwa the lease was transfer in

favour of Shri Pankaj kumar Bairwa S/o Shri Swaroop Chand

Bairwa.

And now the lease has been renewed up to the 19.01.2022.

(Annexure-I Office Order)

29. A balance sheet certified by a

Authorized Financial Expert to

clearly indicate the provision

made / amount spent for

EMP/ERP/CSR/ESR/

Safety/Labour welfare/ Legal

Obligations etc to be enclosed.

Balance sheet will be provided after getting EC, at the time of

submitting the compliance report.

30. PP should clearly mention in the

documents whether there is any

violation of provisions of EIA

Notification and inform at the start

of presentation (to be a part of

computer presentation also).

No any violation in respect to the EIA notification.

31. Used filter papers (Air monitoring)

along with photographs of the site

showing Air / Water sampling /

monitoring activity / equipment

used at each station should be

submitted. Original copies of

analysis report of all the relevant

data referred in the documents

should be enclosed.

Filter paper will be submitted at the time presentation. Photographs of Air/water/soil are enclosed in Chapter-III.

32 The information regarding the

work order/agreement issued by

the P.P. to the consultant

(Accredited from QCI/ NABET for

proposed project Sector) should

be submitted:-

1. Dispatch No. of the work

QCI-NABET Scheme for accreditation of EIA consultant organization.

Incorporate EIA report given page no-2.

Monitoring has been start on dated 4/3/2016

Postal Address is given in front page of report.

Page 24: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

24 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

order/agreement. 2. Date of issue of work

order. 3. Date of start of

air/water/other monitoring work (as applicable).

4. Postal address/ Email Address/ Fax Number/ Mobile Number and Landline Number of the P.P.

Page 25: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

25 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

CHAPTER - II

PROJECT DESCRIPTION

2.1 TYPE OF PROJECT

The proposed project is mining unit & it is proposed to produce 3, 21,699 TPA (ROM)

Limestone (building Stone) by opencast Mechanized method of mining.

2.2 NEED OF THE PROJECT

The proposed mining project falls in the area of the district Kota, Rajasthan devoid of

sufficient agriculture activities and other industrial growth. The earning sources of the

region are limited. Mineral wealth of this region as well as state Rajasthan provides the

employment opportunity to the people of the region /state. Mining is one of the major

core sector industries which play a crucial role in the process of country economic

development. Being a decorative stone, the principle use of this lime stone (Building

stone) is in flooring and wall tiles. There is sufficient demand in this region for the

purpose.

2.3 LOCATION OF THE PROJECT

The lease area falls on survey of India Toposheet No. 45P/14 & 54 D/2 and is situated

between:

Latitude N Longitude E

24°00'00"N to 24°39'30"N 76°12'96.0"E to 75°59'55.7"E

The project site is located 1.0 km from village Satalkhedi in S direction & 0.8 Km NE

direction from Pipakhedi. Tehsil headquarter Ramganj Mandi is as distance about 8.8

Km by road & district headquarter Kota is 70.8 km in North direction connected by

road. The nearest state highway of SH-9 B about 2.0 km in South direction from the

lease area. & NH- 12, 8.0 km in NE direction. Ramganj Mandi railway station is about

4.9 km from lease area & Nearest Airport Indore is about 251 km from the lease area.

(Refer Annexure-VII, copy of Aravalli letter)

Refer Annexure –VIII Copy of composite map

(Refer figure: 2.1 and 2.2 Location map and Key Plan)

Page 26: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

26 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 2.1: LOCATION MAP

Page 27: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

27 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 2.2: KEY PLAN OF THE LEASE AREA

Page 28: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

28 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 2.3: GOOGLE IMAGE SHOWING GENERAL LOCATION OF THE LEASE AREA

FIGURE 2.4: GOOGLE IMAGE OF THE LEASE AREA WITH BOUNDARY PILLARS.

Page 29: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

29 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

2.2 DESCRIPTION OF LEASE AREA & MINING PROCESS

Nature of deposit

The lime stone deposit is sedimentary deposit. Bedding of lime stone area located in

the area. The upper layer of the lime stone is hard and weathered due to sum crack

and shrinkage cracks. The soil is varying in thickness from 3.0 m located at places over

the limestone (Building stone) deposit. The useable limestone layer is about 12meter

in thickness fractured limestone varying from 27 meter located above the hard

limestone layer. The recovery seems around 70% at places in the sanctioned area in

the belt.

Reserves available for proposed mining:

As per approved mining plan the reserves available for mining is given as under:

Mineable reserves

UNFC Quantity in Tonnes

Mineable proved

mineral 111

6098022.9

Mineable probable

mineral. 121

508168.8

Total 6606191.7

Life of mine- we are considering annual production of 3, 21,699 TPA (RoM)

Anticipated life = Minable reserve (Proved + Probable)/ Annual Production

=6606191.7/321699= 21 year.

Existing Working- The mining is being started from the existing pit. The Satalkhedi-

Pipakhedi limestone mine is being developed by opencast mining mechanized with

drilling and blasting. The mineral is lying on the sub surface therefore open cast

mining is obvious choice.

The bench parameters shall be for mineral-

1. Height-6m to 9m

2. Width – more than 6m-9m.

Page 30: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

30 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

The bench parameters shall be for O/B/Fracture-

1. Height-1m- 9m

2. Width – More than 1-9m.

Blasting:

Blasting with low charge of holes just to loosen the rocks is proposed in upper layers

to remove the hard overburden. The blasting shall be done by the authorized

contractor on contractual basis. These contractors have their own safety explosive

container as well as Explosive License

Broad blasting Parameters:

Length of Shot Holes 9.0m

Diameter of Shot Holes 4 inches

Spacing 4 m

Burden 3 m

Stemming 30 %

Sub grade drilling 1m

Types of explosive

Special gelation, Delay Detonator, Ordinary detonator, Elect detonator safety fuse

Red yet (DTH, TLD) R-Cord

Charges per hole & Powder factor Expected Powder factor(for light blasting) 8.0 tonnes kg

Quantity of ore broken per hole

=depth × Burden × spacing × Sp. Gravity

=9 × 3 × 4 ×2.7=259 tones

Explosive required per hole 259/8= 32kg

Sp. Gel. Per cartridge 9.6 kg

A.N.F.O. Per hole 22.4 kg

Page 31: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

31 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

This mine is proposed to produce Lime Stone 321699 TPA (RoM). The year wise

proposed production of mineral as per the approved mining plan is given as under:

TABLE 2.1: DETAIL OF YEAR WISE PROPOSED PRODUCTION

Year Production

in MT (RoM)

Saleable

Mineral

tones

Waste

generat

ed from

the total

excavati

on (MT)

Sub

grade

in MT

Over

burden

form OB

benches

tonnes

Over

burden+

mineral

waste

tonnes

Strippin

g ration

Mineral:

waste

I 321697 225189 80424 16084 1026432 1106856 1:4. 915

II 321697 225189 80424 16084 712800 793224 1:3.522

III 321697 225189 80424 16084 712800 793224 1:3.522

IV 321697 225189 80424 16084 712800 793224 1:3.522

V 321697 225189 80424 16084 712800 793224 1:3.522

Total 1608485 1125945 402120 80420 3877632 4279752 --

Source: Approved mining plan The waste as OB in the area is top soil and fractured limestone . The soil cover in the

area varies from 3m fractured limestone varies from 27 m. This OB will be dumped at

mined out pit. This sub grade material will be stacked at earmarked site.

The total area covered by the sub grade mineral at the end of this mining plan will be

49645 Sqm. Height 6m

TABLE 2.2: DETAIL OF PROPOSED WASTE TO BE GENERATED FOR MINING OPERATION

S. No

Year I II III IV V Total

1. Fracture + mineral waste (MT)

80424 80424 80424 80424 80424 402120

2. Over Burden(MT)

1026432 712800 712800 712800 712800 3877632

3. Total Waste (1+2) MT

1106856 1106856 793224 793224 793224 4279752

4. In Cum 461190 330510 330510 330510 330510 1370730

5. Swell volume (Cum)

553428 396612 396612 396612 396612 2139876

Page 32: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

32 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Source: Approved mining plan

Manpower required for the mining operation is given in the Table-2.3.

TABLE 2.3: DETAIL OF MANPOWER REQUIRED FOR MINING OPERATION

S. No. Manpower No’s 1 Mines Manger ( As per MMR, 1996) 1 2 Mining Mate/Foreman 2 3 Watchmen 2 4 Operators 4 4 Skilled labours/operators 50 5 Un- Skilled labours 50

Total 109 Total Man Power at the mine will be required 109 Nos.

As per approved mining plan detail of the mining machinery deployed or to be deployed is given in the Table-2.4 TABLE 2.4: DETAIL OF MACHINERY DEPLOYED OR TO BE DEPLOYED

Type of Machinery

Nos. Bucket Capacity in Cum.

Motive Power

Make H.P.

Dumper 6 10 tonner Diesel Tata 119 HP Water pump 1 - Diesel Local -

Compressor 1 75 CFM - Local - Jack Hammer 2 32 mm Diesel Local -

Excavator 2 1.2 m3 Diesel Local - JCB 1 - Diesel Escort -

Jiri Cutting m/c 8 - - --- - DG Set 2 125Kva Kriloskar

2.4 BASIC FACILITIES

Rest shelter: - Rest shelter cum office is present in lease area.

Water Requirement: - About 7.0 KLD water will be required. Which will be fulfil

through water tankers & wells.

TABLE 2.5WATER REQUIREMENT

Sr. No. Particulars Quantity KLD

1 Dust Suppression 2.0

2 Drinking 2.0

3 Green Belt 3.0

Total 7.0

Page 33: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

33 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Washroom: washroom will be provided separately for male & female.

First Aid Box: A well-equipped first aid box will be provided.

Electricity: - No electricity is required. Fuel will be obtained from authorize public fuel

station. About 300 lt/day HSD will be used.

2.5PROPOSED SCHEDULE FOR APPROVAL AND IMPLEMENTATION

Following key approval has been taken from the concerned departments.

Approved Mining Plan with progressive mine closure plan for Limestone (M.L. 55/91)

over an area of 43.24 hect., near village-Satalkhedi-Pipakhedi, Tehsil –Ramganj Mandi &

District – Kota(Raj.) has been approved on 31/12/2013. (Refer Annexure III)

The project has applied for environment clearance as per requirements of EIA

notification SO 1533(E) dated 14.9.2006 and amendments made thereof and will be

implemented after the environment clearance is obtained.

**********

Page 34: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

34 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

CHAPTER-III

DESCRIPTION OF THE ENVIRONMENT

3.1 STUDY AREA

In order to study the environmental baseline status of the prevailing conditions,

geographic area within 10 km radius from the lease area is defined as study area,

which is comprised of core zone and Buffer zone. Core zone is the total lease area of

43.24 ha, where mining has to be carried out whereas area around the lease periphery

is Buffer zone.

TABLE 3.1: STUDY AREA AT A GLANCE

S. No. Particulars Details General Particulars

1.1 Village Satalkhedi-Pipakhedi 1.2 Tehsil & District H.Q. Ramganjmandi 1.3 Latitude 24°39'27.45"N to 24°40'02.57"N

1.4 Longitude 75°59'56.64"E to 75°00'27.81"E

1.5 Toposheet No. 45P/14 & 54D/2 Demography

2.1 Total Population Male 77390 Female 70095

2.2 Literates 56327 2.3 No. of Household 30178 2.4 No. of Villages 34

Land use pattern (area in hectare) 3.1 Built up land 481.76 3.2 Crop land 9702.28 3.3 Fallow land 8203.53 3.4 Forest 10573.97 3.5 Scrub land 5358.53 3.6 Water Bodies 625.08 3.7 Grazing land 895.45 3.8 Mining area 1107.57

Total 36947.97 Climatology

4.1 Maximum temp. °C 47.0

4.2 Minimum temp. °C 13.4

4.3 Relative humidity % 12-78%

Page 35: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

35 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

3.1.1 STUDY PERIOD

The baseline environmental monitoring was carried out during summer season of year

March to May 2016

3.1.2 ENVIRONMENTAL COMPONENTS

The various environmental components which are thoroughly studied during the

study period include:

Land Environment

Water Environment

Air Environment

Noise Environment

Biological Environment

Socio- Economic Environment

3.1.3 METHODOLOGY

The methodology for collection of baseline data for different environmental

component is based on the MoEF & CC and CPCB guidelines. The baseline information

on micro meteorology, ambient air quality, water quality, noise levels, soil quality and

floristic descriptions was collected by primary sampling / field studies during study

period. However secondary data have been obtained from government agencies and

other published sources.

3.2 ESTABLISHMENT OF BASELINE FOR VALUED ENVIRONMENT COMPONENT

Land Environment-

Land is the most vital resource for sustenance of the life and degradation of land due to

industrialization, urbanization and population growth is a matter of concern.

Therefore, it is necessary to establish the existing land use pattern to optimize land use

as well as minimize degradation due to development activities. The basic idea of land

use classification for the purpose of EIA study is to define the distribution of the

existing land according to its actual use. The land use pattern use indicated the manner

in which different part of land in the study area is being utilized and un-utilized. It is an

important indicator of environmental health and human activity.

Page 36: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

36 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

(A) Land use of study area (buffer zone)

The existing land use pattern in the study area has been studied through satellite

imagery and is divided into following categories:-

TABLE 3.2: LAND USE PATTERN BASED ON SATELLITE IMAGE

S. No. Class Names Area (Ha.) % (Area) i Built up land 481.76 1.31 ii Crop land 9702.08 26.26 iii Fallow land 8203.53 22.21 iv Forest 10573.97 28.62 v Scrub land 5358.53 14.51 Vi Water Bodies 625.08 1.68 vii Grazing land 895.45 2.42 Viii Mining area 1107.57 2.99

Total 36947.97 100 Refer Figure 3.1: Land Use / Land Cover Map Pattern of the Study Area.

Refer Figure 3.2: Satellite Image of 10 km Radius of the Study Area

Page 37: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

37 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.1: LAND USE / LAND COVER MAP PATTERN OF THE STUDY AREA.

Page 38: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

38 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.2: SATELLITE IMAGE OF 10 KM RADIUS OF THE STUDY AREA

Page 39: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

39 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

(B) Land use of lease area (Core Zone)

The detail of present land use of the lease area and proposed utilization for different

purpose of mining during operational and post operational phase is given in the table

below.

TABLE 3.3: LAND USE PLAN FOR PRE- OPERATIONAL, OPERATIONAL & POST -

OPERATIONAL PHASES (IN HECT.)

Note- About 15.9800 ha area has been already planted within lease for full fill 33%

plantation as per ToR compliance. At the end of mine life about 20.77 ha area will be

planted which includes 3.5400 Ha area will be planted on statuary barrier (7.5 Meter)

& 17.2396 ha area will be backfill planted. About 6.4804 ha area will be converted as

water storage.

(C) Topography& Drainage:

The area is having flat topography highest elevation of the area is 340 mRL and lowest

is 337 mRL. There is no river/nallah exist within the lease area. However general

drainage in the study area is defined by the Amjar Nadi- 9.3 km in NE direction, Ahu

Nadi-6.4 km in SE direction & Psadi Nadi 7.5 km in SW direction from mine site.

S. No. Particulars Pre Operational

(In Ha)

Operational (In Ha)

Post operational

(In Ha) A) Mining Activity 1 Mining pits 8.5215 10.5710 0.00 2 Road & building 2.3750 2.3750 0.00

3 Plantation on statuary barrier

0.0000 2.5500 3.5400

4 Mineral stack 1.5420 1.9540 0.0000 5 Water storage 1.2010 1.2010 6.4804

6 Reclamation & Backfilled Plantation

5.9800 5.9800 17.2396

7 Plantation on remaining lease area

15.9800 15.9800 15.9800

B) Remaining virgin land

7.6405 2.6290 0.000

Total 43.24 43.24 43.24

Page 40: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

40 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.3: TOPOGRAPHY MAP OF THE STUDY AREA

Page 41: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

41 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.4: DRAINAGE MAP OF THE STUDY AREA

Page 42: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

42 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

(D) Regional Geology

The area from part of Kota & Chittorgarh district of Rajasthan. The NH-12 passes

through Mandana & Suket in the eastern part of the area & western Railway main line

also runs parallel with NH-12 Satalkhedi Village is connected to railhead at

Ramganjmandi.

Era/period Geological

Cycle

Group Sub

Group

Formation Litho logy

Meso

Neo-

Proterozoic

Vindhya

Super group

Lower Bhander

(Lakheri-Singoli)

Limestone formation

Limestone

(Dolomitic)

Ganurgarh Shale

Formation upper Rewa

(Taragarh fort-Umar)

Sandstone

Shale with

Limestone

Bands

Formation Quartzitic

Sandstone

Sandstone with

gritty &

conglomerate

bands

Rewa

Group

Jhiri (Ratangarh) Shale Shale with

Limestone

Kaimpur

Group

Chittaurgarh fort

(Dicken) Sandstone

formation

Quartzitic

Sandstone

Semi

Group

Suket shale formation Shale,

Limestone

interbeds,

Sandstone

Page 43: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

43 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

The temperature falls below 100 C in winter while it reached 450 C in the summer.

The Vindhya Super group of Meso to Neo-Proterozoic age, represented by its four

group is exposed in the area. The oldest Semri Group is subdivided into the Khorip

sub-group, and is represented by the Suket Shale Formation, which is an assemblage of

shale with interbeds of lime stone.

The Rewa group, represented by the Jhiri Shale (Ratangarh Shale) and the upper Rewa

Sandstone (=Taragharh Fort Sandstone) Formations, Conformably overlies the kaimur

Sandstone.

The Jhiri/Ratangar Shale is thinly bedded to laminate splintery in nature and pale

yellow to khaki greeincolour. It contains thin bands and lenses of clay and dolomitic

Limestone. The limestone is often stromatolitic in pokets.

Local Geology: Bedding of lime stone area located in the area. The upper layer of the

lime stone is hard and weathered due to sum crack and shrinkage cracks. The soil is

varying in thickness from 3.0 m located at places over the limestone (Building stone)

deposit. The useable limestone layer is about 12meter in thickness fractured limestone

varying from 27 meter located above the hard limestone layer.

Local Geological succession for the area may be summarized -

Recent Group Litho logy

Lower Vindhyan Group Khorip Group

(Semri Group)

Upper Jhalrapatan (Suket) Shale/

limestone.

Source- Approved Mining Plan

(Refer figure3.5: surface geological plan and section of the lease area).

Page 44: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

44 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.5: SURFACE GEOLOGICAL PLAN AND SECTION OF THE LEASE AREA

Page 45: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

45 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

(e) Soil quality

The soils of the district are alluvial in nature. The soils in the district have been

classified as deep black clayey soils, deep brown clayey soils, deep brown loamy soils,

medium black clayey soils.

Methodology for soil monitoring

Soil samples from depth (0-15 cm) were collected from different sites in the study area

for estimation of the physicochemical characteristics of soil. Air-dried and Sieved

samples have been used for determination of physical properties of soil. Standard

methods were followed for the analysis of soil samples. Soil sampling location is given

in the table below.

TABLE 3.4: SOIL SAMPLING LOCATIONS IN THE STUDY AREA

S. No. Station Code. Station Name

1 S1 Pipakheri

2 S2 Satalkheri

3 S3 Suket

4 S4 Naharsingh

5 S5 Khairabad

6 S6 Savad khurd.

Refer Figure 3.6: Soil Sampling Location map of the study area.

Page 46: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

46 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.6: SOIL SAMPLING LOCATIONS IN THE STUDY AREA

Page 47: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

47 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.7: PHOTOGRAPHS OF SOIL SAMPLING IN THE STUDY AREA

Pipakhedi Village

Naharsingh Village

Page 48: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

48 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Soil Analysis Results

Soil analysis was carried out and the results are given in table below.

TABLE 3.5: ANALYSIS RESULTS OF SOIL SAMPLES

S. No

Parameters unit S1 S2 S3 S4 S5

S6

1 pH (1:2.5) -- 7.94 8.21 7.69 7.82 7.91 8.04

2

Electrical Conductivity of Saturation Extract (1:2)

µmhos/cm

317 293 241 329 314 286

3 Bulk Density gm/cc 1.15 1.24 1.34 1.42 1.23 1.21

4 Organic Matter

% 0.23 0.31 0.14 0.18 0.21 0.13

5 Available Nitrogen

Kg/Hect.

15.0

8 13.13 12.12 15.77

13.5

6 11.45

6 Available Phosphorus

Kg/Hect.

23.4

2 18.98 24.03 20.56

20.3

6 19.31

7 Available Potassium

Kg/Hect.

19.1

6 20.07 27.78 21.34

23.3

4 17.03

STANDARD SOIL CLASSIFICATION

S.NO. Parameter Classification 1. PH <4.5 extremely acidic

4.51-5.0 very strong acidic 5.01-5.5 strongly acidic 5.51-6.0 slightly acidic 6.51-7.3 Neutral 7.31-7.8 slightly alkaline 7.81-8.5 moderately alkaline 8.51-9.0 strongly alkaline >9.0 Very strongly alkaline

2. Salinity Electrical conductivity (mho/cm)

1 mho/cm=640 ppm

Up to 1.0 average 1-2 harmful to germination 2-3 harmful to crops

3. Nitrogen (Kg/ha) Up to 50 very less 51-100 less 110-150 good 151-300 better >300 sufficient

4. Phosphorus (kg/ha) Up to 15very less 15-30 less 31-50medium 51-65 on average sufficient 66-80 sufficient

Page 49: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

49 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

>80 more than sufficient 5. Potassium (kg/ha) 0-120 very less

120-180 less 180-240 medium 241-300 average 301-360 better >360 more than sufficient

Results:

The result shows that soil is moderately alkaline in nature and less fertile.

3.3 WATER ENVIRONMENT

The assessment of present status of water quality within the study area was conducted

by collecting water from ground water & surface water sources during the period of

March 16 to May ’16. There is no perennial source of surface water body in the core

zone, however two rivers flows in study area. (Refer in drainage map of the study

area).

Surface Water- proposed waste rock dump sites are away from any seasonal water

stream. Thus there will be no impact of the mining in the natural flow of water and

drainage system in the existing area. The lessee shall make garland drain, retaining

walls, setting tank all around the pits and dumps. The rain water shall be utilized by

harvesting techniques.

Ground water- the water table in the area is 40m (in rainy season) 45m (in dry

season). Mining will be not intersecting in ultimate pit limit (303 mRL). The ground

water in the area is not likely to be effected at all.

HYDROGEOLOGY- Occurrence of ground water depends upon topography, physio

graphy and structural features of the geological formations. In Kota district, ground

water occurs in mainly four hydro geological formations. These hydro geological

formations are alluvium, sandstone, shale and limestone and among these formations

alluvium is the most important formation as it covers the maximum area and also it is

the most potential among different hydro-geological formations.

Source: CGWB Kota District Rajasthan

Page 50: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

50 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.8: HYDROGEOLOGICAL MAP OF THE DISTRICT KOTA

Page 51: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

51 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Depth to Water Level (Pre & Post Monsoon)

The ground water level of the mine is much below the level of the working thus,

groundwater table will not be intersected till reach to ultimate depth of working. The

ground water table in the lease area is 40m (in rainy season) to 45m (in dry season) &

highest elevation of the lease area 340 mRL and lowest elevation of the lease area is

337 mRL. The ground water in the area is not likely to be affected at all.

295 mRL (45mbgl Pre monsoon)

300mRL ( 40 mbgl Post monsoon)

WATER TABLE

303 mRL (37 mbgl)

ULTIMATE DEPTH

337 mRL (Lowest Contour)

GROUND LEVEL

Proposed working will not intersect Ground

water table.

340 mRL (Highest contour)

hiesest

Page 52: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

52 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.8(A): DEPTH TO WATER TABLE PRE-MONSOON

FIGURE 3.8(B): DEPTH TO WATER TABLE POST-MONSOON

Page 53: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

53 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

3.5.1 Ground water monitoring methodology

The quality of groundwater near the lease area and within the 10 km radius was

established. Six ground water samples were collected during the winter season and

characterized for physico-chemical parameters. The samples were taken as grab

sample and were analysed for various parameters and compared with standards IS:

10500. The locations of water sampling stations are given in table below.

TABLE 3.6: LOCATION OF WATER SAMPLING IN THE STUDY AREA

Station Code Location Remarks

GW1 Pipakhedi Ground Water GW2 Satalkhedi Ground Water GW3 Suket Ground Water GW4 Naharsinghi Ground Water GW5 Khairabad Ground Water GW6 Saavad khurd Ground Water

Refer Figure 3.9: Water sampling locations in the study area

Page 54: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

54 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.9: WATER SAMPLING LOCATIONS MAP IN THE STUDY AREA

Page 55: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

55 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.10: PHOTOGRAPHS OF WATER SAMPLING IN THE STUDY AREA

Pipakhedi Village

Naharsinghi Village

Page 56: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

56 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

3.5.2 Analysis Report of Water Quality

TABLE 3.7: ANALYSIS RESULTS OF GROUND WATER SAMPLES

S. No. Parameter Unit IS Standard 10500

GW1 GW2 GW3 GW4 GW5 GW6 Acceptable Permissible

1 Color -- <5 <5 <5 <5 <5 <5 5 15

2 Odour -- Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable

3 Turbidity NTU <2 <2 <2 <2 <2 <2 1 5

4 pH value -- 7.35 7.28 7.36 7.67 7.59 7.55 6.5-8.5 No relaxation

5 Total Hardness (as CaCO3)

mg/l

314 276 312 348 286 334 200

600

6 Total Dissolved solids

mg/l

928 840 1048 1240 904 1068 500

2000

7 Alkalinity mg/l 230 220 250 320 180 229 200 600

8 Chlorides (as Cl)

mg/l 119.54 149.3 179.07 164.71 213.4 199.34 250 1000

9 Calcium (as Ca)

mg/l 67.38 67.42 112.12 122.49 64.37 87.16 75 200

10 Magnesium (as Mg)

mg/l 23.07 32.56 26.47 26.76 22.81 32.55 30 100

11 Sulphate (So4)

mg/l 45.27 60.87 51.19 41.38 47.26 66.08 200 400

12 Iron (as Fe) mg/l BDL BDL 0.34 BDL BDL BDL 0.3 No relaxation

13 Nitrate (as NO3)

mg/l 33.19 40.18 32.56 34.09 30.54 33.6 45 No relaxation

14 Fluoride (as F)

mg/l 0.45 0.13 0.57 0.67 0.78 1.04 1.0 1.5

Page 57: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

57 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Conclusion:

Analysis of samples revels that water parameter like total hardness, TDS , calcium

magnesium, sulphate, nitrate, fluoride are within acceptable limit.

3.4 AMBIENT AIR ENVIRONMENT

3.4.1 Meteorology -Meteorological factors such as wind speed, direction variation in

temperature, humidity etc. play a direct role in dispersion of pollutants atmospheric

pressure, rainfall and cloud cover also govern this activity. In order to establish the

prevailing climatic condition, a meteorological monitoring station was installed in the

study area during the study period. Based on the site meteorological information

gathered during the monitoring period, wind rose diagram was generated to

understand the prevailing wind direction so as to anticipate the dispersion of

pollutants in the wind direction. Refer Figure 3.11: Wind Rose Diagram

FIGURE 3.11: WIND ROSE DIAGRAM

Page 58: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

58 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

3.4.2 Climatology

Climate of the district can be classified as semi arid type. Normal rainfall in the district

for the period 1951- 2000 is 807.9 mm. However, average annual rainfall for the

period 2001 to 2011 is 652.17 mm.The summers are hot and dry and winters are cold.

The cold season prevails from December to February followed by hot season from

March to mid of June. After summers the rainy season starts with the onset of

monsoon rains lasting till the end of September. The period September to November

constitutes post monsoon period. . January is the coldest month with mean daily

maximum temperature at 24.3°C and a mean daily minimum temperature at 10.6°C.

Mean daily maximum temperature during summers is 43°C to 47 °C and mean daily

minimum temperature is 25°C to 29 °C & 2°C to 5°C in winter. The average rainfall is

900 mm most of the rain falls during the period of July to September.

3.4.3 Seismicity of the area:-

Many parts of the Indian Subcontinent have historically high Seismicity. Seven

catastrophic earth quakes of magnitude greater than 8 (Richter scale) have occurred in

the western, northern and eastern parts of India and adjacent countries in the past 100

years.

The mine site as well as study area lies in Zone –II of Seismic Zoning Map, and thus can

be said to be located in an area of low seismic hazard by national standards. Hence the

risk of earthquake at the site is minimal and so the site is safe.

Page 59: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

59 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

3.4.4 Ambient air quality monitoring

Ambient air quality monitoring was carried out during the study period (March to May

2016) to establish the ambient air quality. Sampling was carried out with the help of

reparable particulate matter Sampler “Reparable Dust Sampler” (RDS). The data

generated by M/s Udaipur Min-Tech Pvt. Ltd. for ambient air quality status within 10

km. radius of the lease area has been compiled along with meteorological conditions.

3.4.5 Location of Ambient Air Sampling Stations

Sampling locations were established for ambient air monitoring in and around the core

zone within a radius of 10.0 km, to study the present quality of the air. The monitoring

locations are marked in the map presented as fig.3.12. Location of sampling points

along with distance and direction with respect to lease area are given as under:

TABLE 3.8: LOCATION OF AMBIENT AIR MONITORING STATIONS

Station Code.

Station Name

Location with respect to Site

Distance (Km)

Direction

A1 Near Mine Site -- --

A2 500 D/w -- --

A3 Pipakhedi 0.8km NE

A4 Satalkhedi 1.0 km

S

A5 Suket 5.0 km

SE

A6 Naharsinghi 8.5 km

SE

A7 Khairabad 6.0 km SW

A8 Salvad khurd 5.5km NE

Refer Figure 3.12: Ambient air sampling location in the study area.

Page 60: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

60 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.12: AMBIENT AIR SAMPLING LOCATION IN THE STUDY AREA

Page 61: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

61 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.13: PHOTOGRAPHS OF AMBIENT AIR MONITORING IN THE STUDY AREA

Naharsinghi Village

Satalkhedi Village

Page 62: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

62 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

3.4.5 Sampling Schedule

Sampling was done 24/8 hourly from each station round the clock, twice a week for

continuous three month (Study period).

3.5.4. Air quality parameter

The following parameters were analysed for each sample.

- Particulate Matter (PM2.5)

- Particulate Matter (PM10)

- Sulphur dioxide (SO2)

- Nitrogen dioxide (NO2)

The sampling and testing of ambient air quality parameters were carried out as

per relevant parts of IS 5182. The brief details of testing method are given in below

table.

TABLE 3.9: PROCEDURE FOR DETERMINING VARIOUS AIR QUALITY PARAMETERS

Parameters Testing method

PM2.5 Lab SOP UM-A-10

PM10 IS: 5182 (P-23) 2006 RA 2012

SO2 IS: 5182 (P-2) 2006 (DL=3μg/m3 )

NO2 IS: 5182 (P-6) 1975 RA 2006

The detailed results of ambient air quality are given in table below:

TABLE 3.10 (A): MEAN TEMPERATURE & RELATIVE HUMIDITY

Month

Temperature

(°C)

Relative Humidity

(%)

Wind speed

Max. Min. Max. Min. Max. Min.

March, 16 38.2 13.0 78.0 20.0 16 0.2

April, 16 44.6 19.0 76.0 16.0 22 0.4

May, 16 46.6 24.2 74.0 14.0 32 0.6

Sources- IMD station Jhalawar

Page 63: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

63 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

TABLE 3.10 (B): MEAN TEMPERATURE& RELATIVE HUMIDITY AT PROJECT SITE

Month

Temperature (°C)

Relative Humidity (%)

Wind Speed (m/hr.)

Max. Min. Max. Min. Max. Min.

March, 16 40.0 13.4 78.0 18.0 18 0.2 April, 16 44.0 18.0 74.0 16.0 21 0.1 May, 16 47.0 25.0 72.0 12.0 34 0.6

TABLE 3.11: AMBIENT AIR QUALITY RESULT

Result for Test parameter PM10/ PM2.5/ SO2/ NO2 A1) Near Mine Site S.No. Date PM2.5

(µg/m3 ) PM10 (µg/m3) SO2 (µg/m3) NO2 (µg/m3)

1. 02.03.16 23.51 61.11 3.0 5.17 2. 03.03.16 22.18 64.95 3.84 4.23 3. 10.03.16 20.23 58.49 4.11 5.18 4. 11.03.16 22.73 70.51 4.3 4.62 5. 18.03.16 24.48 71.03 4.08 5.31 6. 19.03.16 23.66 70.72 4.58 6.99 7. 26.03.16 25.84 67.67 3.19 4.75 8. 27.03.16 21.93 74.45 4.08 3.83 9. 03.04.16 21.02 69.29 3.18 4.02 10. 04.04.16 23.61 74.13 3.66 4.78 11. 11.04.16 23.84 62.18 4.43 6.53 12. 12.04.16 23.85 65.03 3.93 4.09 13. 19.04.16 25.52 68.08 3.07 7.14 14. 20.04.16 23.71 66.06 BDL 3.19 15. 27.04.16 22.64 78.7 5.05 6.25 16. 28.04.16 21.25 67.16 4.18 4.81 17. 01.05.16 21.77 76.2 3.32 3.93 18. 02.05.16 23.89 64.98 3.52 7.1 19. 10.05.16 20.32 68.44 4.22 6.39 20. 11.05.16 23.47 71.24 BDL 6.89 21. 18.05.16 24.61 66.81 4.74 6.1 22. 19.05.16 22.67 65.88 4.91 5.7 23. 26.05.16 25.61 73.88 3.74 4.1 24. 27.05.16 23.09 66.69 3.52 6.47

Min. 20.23 58.49 BDL 3.19 Max. 25.84 78.7 5.05 7.14 Avg. 23.14 68.49 3.82 5.32

Method

Reference Lab-SOP UM-

A-10 IS: 5182 (P-23)

2006 IS: 5182 (P-2)

2001 ( DL=3.0 µg/m3)

IS: 5182 (P-6) 2006

Page 64: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

64 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Result for Test parameter PM10/ PM2.5/ SO2/ NO2 A2) 500 m D/w S.No. Date PM2.5

(µg/m3 ) PM10 (µg/m3) SO2 (µg/m3) NO2 (µg/m3)

1. 02.03.16 23.73 71.21 BDL 4.72 2. 03.03.16 22.56 69.51 3.85 5.13 3. 10.03.16 23.09 72.45 3.19 4.9 4. 11.03.16 21.35 69.72 4.23 5.03 5. 18.03.16 20.28 62.76 4.07 3.83 6. 19.03.16 21.31 58.8 4.02 4.98 7. 26.03.16 25.05 74.49 3.47 4.92 8. 27.03.16 25.73 63.37 4.84 5.97 9. 03.04.16 24.55 70.53 3.03 3.23 10. 04.04.16 23.96 59.65 4.43 4.69 11. 11.04.16 21.03 68.32 3.11 5.23 12. 12.04.16 20.05 63.67 4.04 4.84 13. 19.04.16 24.47 62.08 BDL 6.04 14. 20.04.16 25.96 68.9 4.33 4.58 15. 27.04.16 20.79 74.94 3.8 5.82 16. 28.04.16 23.21 63.84 4.23 4.09 17. 05.05.16 22.48 69.62 3.11 3.35 18. 06.05.16 19.75 59.67 3.08 4.16 19. 13.05.16 23.13 67.04 4.27 4.36 20. 14.05.16 21.04 64.88 BDL 3.05 21. 21.05.16 22.13 63.98 4.38 4.04 22. 22.05.16 25.21 61.47 4.43 4.52 23. 29.05.16 20.89 66.78 3.04 5.14 24. 30.05.16 23.44 65.19 4.51 6.37

Min. 19.75 58.8 BDL 3.05 Max. 25.96 74.94 4.84 6.37 Avg. 22.72 66.37 3.75 4.71

Method Reference

Lab-SOP UM-A-10

IS: 5182 (P-23) 2006

IS: 5182 (P-2) 2001

( DL=3.0 µg/m3)

IS: 5182 (P-6) 2006

Page 65: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

65 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Result for Test parameter PM10/ PM2.5/ SO2/ NO2 A3) “ Pipakhedi Village” S.No. Date PM2.5

(µg/m3 ) PM10 (µg/m3) SO2 (µg/m3) NO2 (µg/m3)

1. 01.03.16 24.54 69.65 3.03 4.03 2. 02.03.16 22.63 69.05 BDL 6.19 3. 09.03.16 24.96 75.47 BDL 5.45 4. 10.03.16 20.87 69.11 3.64 7.91 5. 17.03.16 24.93 68.84 4.18 4.98 6. 18.03.16 19.48 59.54 4.69 5.01 7. 25.03.16 23.85 67.41 3.73 4.28 8. 26.03.16 21.84 65.91 4.25 3.10 9. 02.04.16 24.7 67.28 4.33 5.98 10. 03.04.16 25.11 74.68 BDL 4.49 11. 10.04.16 22.95 66.01 4.18 6.35 12. 11.04.16 21.99 67.06 3.57 3.29 13. 18.04.16 23.6 68.78 BDL 7.01 14. 19.04.16 22.85 65.36 4.49 4.75 15. 26.04.16 20.22 60.08 3.00 5.58 16. 27.04.16 23.67 65.22 5.08 6.35 17. 03.05.16 24.65 70.81 4.27 7.10 18. 04.05.16 22.37 68.38 BDL 3.61 19. 10.05.16 23.88 65.25 3.52 5.62 20. 11.05.16 24.73 74.06 BDL 3.12 21. 17.05.16 20.59 66.74 4.91 4.46 22. 18.05.16 20.05 60.43 5.15 5.33 23. 25.05.16 22.13 67.52 4.79 6.17 24. 26.05.16 23.28 65.73 3.52 4.57

Min. 19.48 59.54 BDL 3.1 Max. 25.11 75.47 5.15 7.91 Avg. 22.91 67.43 3.74 5.20

Method Reference

Lab-SOP UM-A-10

IS: 5182 (P-23) 2006

IS: 5182 (P-2) 2001

( DL=3.0 µg/m3)

IS: 5182 (P-6) 2006

Page 66: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

66 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Result for Test parameter PM10/ PM2.5/ SO2/ NO2 A4) “Satalkhedi Village ” S.No. Date PM2.5

(µg/m3) PM10 (µg/m3) SO2 (µg/m3) NO2 (µg/m3)

1. 04.03.16 26.05 62.18 BDL 3.13 2. 05.03.16 23.79 66.25 3.39 4.74 3. 12.03.16 25.06 65.53 4.10 3.99 4 13.03.16 19.9 62.53 BDL 6.96 5 20.03.16 24.24 70.51 4.26 4.56 6 21.03.16 25.3 70.71 3.35 6.04 7 28.03.16 23.61 68.61 BDL 5.57 8 29.03.16 25.06 66.47 3.51 5.04 9 02.04.16 23.67 63.93 3.11 5.16

10 03.04.16 20.37 62.71 4.54 6.90 11 10.04.16 24.46 70.27 3.03 3.02 12 11.04.16 21.72 68.45 BDL 7.20 13 18.04.16 23.82 64.21 3.80 5.78 14 19.04.16 25.06 77.47 4.23 7.98 15 26.04.16 25.62 69.16 3.80 6.20 16 27.04.16 23.09 70.47 BDL 5.98 17 06.05.16 26.09 69.49 3.61 5.33 18 07.05.16 23.09 67.09 4.17 4.46 19 13.05.16 20.19 64.66 BDL 6.54 20 14.05.16 24.59 67.08 4.79 5.36 21 2105.16 22.69 70.48 3.57 3.13 22 22.05.16 25.31 75.37 4.91 4.46 23 29.05.16 21.03 66.66 BDL 7.10 24 30.05.16 19.67 62.18 3.44 5.70

Min. 19.67 77.47 BDL 3.02 Max. 26.09 67.76 4.91 7.98 Avg. 23.48 3.46 5.43

Method Reference

Lab-SOP UM-A-10

IS: 5182 (P-23) 2006

IS: 5182 (P-2) 2001

( DL=3.0 µg/m3)

IS: 5182 (P-6) 2006

Page 67: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

67 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Result for Test parameter PM10/ PM2.5/ SO2/ NO2 A5) “Suket ”

S.No. Date PM2.5

(µg/m3) PM10 (µg/m3) SO2 (µg/m3) NO2 (µg/m3)

1. 02.03.16 23.64 72.83 BDL 5.74 2. 03.03.16 25.06 78.78 4.07 4.89 3. 10.03.16 21.87 68.62 3.10 7.52 4 11.03.16 24.24 71.51 4.95 3.02 5 18.03.16 22.82 69.55 3.27 6.19 6 19.03.16 20.32 62.59 BDL 5.55 7 26.03.16 21.94 66.25 4.18 3.92 8 27.03.16 24.36 64.30 3.43 4.86 9 03.04.16 21.76 75.89 3.11 3.30

10 04.04.16 22.85 66.44 BDL 5.18 11 11.04.16 23.89 67.60 4.23 6.23 12 12.04.16 24.91 67.73 4.33 4.38 13 19.04.16 20.11 68.79 3.11 8.06 14 20.04.16 19.86 61.56 2.28 4.87 15 27.04.16 24.61 68.65 3.00 7.97 16 28.04.16 19.03 62.63 4.23 3.11 17 05.05.16 19.94 63.04 4.17 3.85 18 06.05.16 24.13 65.36 BDL 7.18 19 13.05.16 23.44 65.52 4.17 4.46 20 14.05.16 25.06 73.93 BDL 3.13 21 21.05.16 21.91 66.68 3.36 4.96 22 22.05.16 22.09 65.15 3.48 6.80 23 29.05.16 24.32 67.93 BDL 3.85 24 30.05.16 20.55 64.49 4.03 5.90

Max. 19.03 61.56 BDL 3.02 Min. 25.06 78.78 4.95 8.06 Avg. 22.61 67.74 3.39 5.21 Method

Reference Lab-SOP UM-

A-10 IS: 5182 (P-23)

2006 IS: 5182 (P-2)

2001 ( DL=3.0 µg/m3)

IS: 5182 (P-6) 2006

Page 68: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

68 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Result for Test parameter PM10/ PM2.5/ SO2/ NO2 A6) “Naharsinghi ” S. No. Date PM2.5

(µg/m3) PM10 (µg/m3) SO2 (µg/m3) NO2 (µg/m3)

1. 04.03.16 22.51 69.17 3.05 3.06 2. 05.03.16 25.18 67.27 3.22 4.89 3. 12.03.16 24.1 67.35 4.08 4.13 4 13.03.16 25.17 75.48 4.10 5.70 5 20.03.16 25.68 66.63 5.01 5.10 6 21.03.16 19.62 62.00 3.03 8.06 7 28.03.16 25.17 67.82 4.91 4.58 8 29.03.16 23.83 67.66 BDL 4.46 9 02.04.16 22.38 67.28 3.03 3.23

10 03.04.16 25.25 62.78 BDL 4.81 11 10.04.16 26.01 69.82 4.60 7.20 12 11.04.16 23.69 70.95 BDL 3.89 13 18.04.16 22.85 69.37 5.05 6.45 14 19.04.16 21.18 67.28 3.07 4.10 15 26.04.16 24.66 62.60 4.49 4.75 16 27.04.16 20.14 60.92 BDL 6.89 17 01.05.16 23.88 62.83 BDL 4.05 18 02.05.16 25.4 61.83 4.27 6.89 19 09.05.16 22.43 62.78 3.44 3.02 20 10.05.16 25.67 80.77 4.08 4.16 21 17.05.16 19.68 62.72 3.32 5.69 22 18.05.16 25.81 65.72 4.22 8.26 23 25.05.16 22.95 63.80 3.84 7.49 24 26.05.16 24.94 59.45 4.33 6.54

Min. 19.62 59.45 BDL 3.02 Max. 26.01 80.77 5.05 8.26 Avg. 23.67 66.43 3.68 5.28 Method

Reference Lab-SOP UM-

A-10 IS: 5182 (P-23)

2006 IS: 5182 (P-2)

2001 ( DL=3.0 µg/m3)

IS: 5182 (P-6) 2006

Page 69: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

69 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Result for test parameter PM10/ PM2.5/ SO2/ NO2 A7) “Khairabad ” S. No. Date PM2.5

(µg/m3) PM10 (µg/m3) SO2 (µg/m3) NO2 (µg/m3)

1 02.03.16 24.65 62.07 3.24 3.56 2 03.03.16 22.37 66.24 3.39 4.74 3 10.03.16 23.88 68.04 4.10 3.99 4 11.03.16 24.73 73.45 BDL 6.96 5 18.03.16 20.59 64.83 4.26 4.56 6 19.03.16 20.05 64.58 3.35 6.04 7 26.03.16 22.13 64.28 BDL 5.57 8 27.03.16 23.28 65.69 3.51 5.04 9 01.04.16 22.38 64.49 3.09 3.25

10 02.04.16 25.25 69.70 4.18 4.43 11 9.04.16 26.01 68.00 3.22 6.88 12 10.04.16 23.69 67.08 3.30 4.07 13 17.04.16 22.85 70.48 5.02 6.19 14 18.04.16 21.18 75.37 BDL 5.16 15 25.04.16 24.66 66.66 4.23 5.50 16 26.04.16 20.14 65.68 3.10 5.31

17 03.05.16 24.54 62.98 3.09 3.35 18 04.05.16 22.63 61.72 3.61 4.23 19 11.05.16 24.96 64.97 3.17 4.81 20 12.05.16 20.87 68.07 3.81 5.20 21 18.05.16 24.93 65.46 4.79 3.89 22 19.05.16 19.48 76.65 3.57 5.45 23 26.05.16 23.85 65.31 4.41 5.10 24 27.05.16 21.84 66.53 3.02 4.75

Min. 19.48 61.72 BDL 3.25 Max. 26.01 76.65 5.02 6.96 Avg. 22.96 67.01 3.46 4.94

Method

Reference Lab-SOP UM-

A-10 IS: 5182 (P-23)

2006 IS: 5182 (P-2)

2001 ( DL=3.0 µg/m3)

IS: 5182 (P-6) 2006

Page 70: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

70 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Result for Test parameter PM10/ PM2.5/ SO2/ NO2 A8) “Salvad khurd” S. No. Date PM2.5

(µg/m3) PM10 (µg/m3) SO2 (µg/m3) NO2 (µg/m3)

1. 04.03.16 21.73 65.21 3.57 4.72 2. 05.03.16 22.56 62.51 3.85 5.13 3. 12.03.16 23.09 62.45 3.19 4.9 4 13.03.16 21.35 69.72 4.23 7.03 5 20.03.16 20.28 62.76 3.07 3.83 6 21.03.16 21.31 58.8 4.02 4.98 7 28.03.16 25.05 74.49 BDL 4.92 8 29.03.16 25.73 63.37 4.84 5.97 9 02.04.16 24.55 70.53 3.03 3.23

10 03.04.16 23.96 59.65 4.43 4.69 11 10.04.16 21.03 68.32 3.11 7.23 12 11.04.16 20.05 63.67 4.04 4.84 13 18.04.16 24.47 62.08 BDL 6.04 14 19.04.16 25.96 68.9 4.33 4.58 15 26.04.16 20.79 74.94 3.8 6.82 16 27.04.16 23.21 63.84 3.23 4.09 17 06.05.16 22.48 69.62 3.11 3.35 18 07.05.16 19.75 59.67 3.08 4.16 19 13.05.16 23.13 67.04 4.27 4.36 20 14.05.16 21.04 64.88 BDL 8.05 21 2105.16 22.13 63.98 3.38 4.04 22 22.05.16 25.21 71.47 4.43 4.52 23 29.05.16 20.89 66.78 3.04 5.14 24 30.05.16 23.44 65.19 4.51 6.37

Min. 19.75 58.8 BDL 3.23 Max. 25.96 74.94 5.07 8.05

Avg. 22.63 65.83 3.66 5.12 Method

Reference Lab-SOP UM-

A-10 IS: 5182 (P-23)

2006 IS: 5182 (P-2)

2001 ( DL=3.0 µg/m3)

IS: 5182 (P-6) 2006

Source: M/S Udaipur Min- Tech Pvt. Ltd. (Analytical & Testing division NABL approved Lab T-3257)

The observed range of various parameters recorded, have been compared with the

National Ambient Quality Standards laid down by the Central Pollution Control Board.

Page 71: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

71 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

TABLE 3.12: COMPARISON OF AIR MONITORING RESULTS

S. No

Result A1 A2 A3 A4 A5 A6 A7 A8

PM2.5 1 Minimum 20.23 19.75 19.48 19.67 19.03 19.62 19.48 19.75 2 Maximum 25.84 25.96 25.11 26.09 25.06 26.01 26.01 25.96 3 Average 23.14 22.72 22.91 23.48 22.61 23.67 22.96 22.63 4 98% 25.34 25.44 24.60 25.56 24.55 25.48 25.48 25.44

PM10 1 Minimum 58.49 58.80 59.54 62.18 61.56 59.45 61.72 58.8 2 Maximum 78.70 74.94 75.47 77.47 78.78 80.77 76.65 74.94 3 Average 68.49 66.37 67.43 67.76 67.74 66.43 67.01 65.83 4 98% 77.12 73.44 73.96 75.92 77.20 79.15 75.11 73.44

SO2 1 Minimum BDL BDL BDL BDL BDL BDL BDL BDL 2 Maximum 5.05 4.84 5.15 4.91 4.95 5.05 5.05 5.07 3 Average 3.82 3.75 3.74 3.46 3.39 3.68 3.46 3.66 4 98% 4.94 4.74 5.04 4.81 4.85 4.94 4.94 4.96

NO2 1 Minimum 3.19 3.05 3.1 3.02 3.02 3.02 3.25 3.23 2 Maximum 7.14 6.37 7.91 7.98 8.06 8.26 6.96 8.05 3 Average 5.32 4.71 5.20 5.43 5.21 5.28 4.94 5.12 4 98% 6.99 6.24 7.75 7.82 7.89 8.09 6.82 7.88

3.4.6 Interpretation of Ambient Air quality.

PM10 level in the study area:

The minimum value of PM10 recorded in the core zone is 58.49µg/m3 and maximum

80.77 µg/m3 at Naharsinghi village in buffer zone.

PM2.5 level in the study area:

The minimum value of PM2.5 recorded in the core zone is 19.03 µg/m3 at Suket village

and maximum 26.09µg/m3 in buffer zone at Satalkhedi village.

SO2 level in the study area:

During study period, the concentration of sulphur dioxide is BDL & maximum 5.15

µg/m3 at Pipakhedi village.

NO2 level in the study area:

The concentration of nitrogen dioxide recorded in core zone ranges between 3.02

µg/m3 & 8.26 µg/m3 Naharsinghi village.

Page 72: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

72 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

3.5 NOISE ENVIRONMENT

The noise level monitoring in the study area was done at the ambient air monitoring

locations. Monitoring was done as per the CPCB guideline. The noise monitoring

results were compared with the Ambient Noise Quality Standard notified under

Environment (Protection) Act, 1986.

3.5.1 Monitoring Methodology of Noise Level

Noise standards have been designated for different types of land use, i.e. residential,

commercial, industrial and silence zones, as per ‘The Noise Pollution (Regulation and

Control) Rules, 2000, Notified by the Ministry of Environment and Forests, New Delhi

on February 14, 2000’. Different standards have been stipulated during day time (6 am

to 10 pm) and night time (10 pm to 6 am). The noise analysis within the study area

was recorded using Lutron sound level meter.

The noise rating method as Leq i.e. equivalent sound pressure level has been adopted

for the measurement of noise level in various selected sampling locations of this

region. It is the energy means of the noise level over a specified period and is

expressed in terms of decibels.

3.5.2 Location of noise monitoring stations

The location of Noise level monitoring is presented in below table.

TABLE 3.13: LOCATION OF NOISE MONITORING STATIONS

Station Code.

Station Name Location with respect to Site Distance (Km) Direction

N1 Near Mine Site -- -- N2 500 D/w -- -- N3 Pipakhedi 0.8km NE N4 Satalkhedi 1.0 km S N5 Suket 5.0 km SE N6 Naharsinghi 8.5 km SE N7 Khairabad 6.0 km SW N8 Salvad khurd 5.5km NE

Refer Figure 3.14: Map for noise monitoring& traffic density station in the study

Area.

Page 73: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

73 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.14: NOISE MONITORING LOCATION MAP

Page 74: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

74 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.15: PHOTOGRAPHS OF NOISE & TRAFFIC MONITORING IN THE STUDY ARE

Satalkhedi Village

Naharsinghi Village

Page 75: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

75 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

3.5.3 Noise Level Results

The noise monitoring within the study area was recorded using sound level meter

and results are given in the table below:

TABLE 3.14: NOISE LEVEL WITHIN THE STUDY AREA (Unit – dBA)

Source: M/S Udaipur Min-Tech Pvt. Ltd. TABLE 3.15: CPCB NOISE STANDARD

Category of Zones Leq in dB (A) Day Night

Industrial 75 70 Commercial 65 55 Residential 55 45

Silence Zone 50 40 a. Day time is from 6.00 Am to 10.00PM. b. Night time is reckoned between 10.00 PM to 6.00AM c. Silence zone is defined as an area up to 100m around premises of hospitals, educational institution and courts. Use of vehicle horn, loudspeaker and bursting of crackers is banned in these zones. Note: Mixed categories of areas be declared as one of the four above mentioned categories by the competent Authority and the corresponding standards shall apply.

Conclusion

During the study period ambient noise level were monitored and observed maximum

level was: 53.7dB at Suket village during day time & minimum was 41.9 at Khairabad

during night time.

All monitoring reports are attached as ANNEXURE-X

S. No

Location Average Day noise level (dBA)

Average Night noise level (dBA)

A1 Near Mine Site 50.6 42.8 A2 500 D/w 49.3 41.5 A3 Pipakhedi 51.5 42.7 A4 Satalkhedi 52.2 43.1 A5 Suket 53.7 44.3 A6 Naharsinghi 51.8 43.5 A7 Khairabad 52.4 41.9 A8 Salvad khurd 51.6 42.6

Page 76: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

76 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

3.6 TRAFFIC DENSITY:

One route shall be taken for transported the material from mine site.

EXISTING TRAFFIC SCENARIO & LOS S. No.

Road V C Existing V/C

Ratio LOS

1 Satalkhedi 450 3,000 0.15 A

2 SH 9B to NH-12 1500 8,000 0.15 A

V= Volume of Vehicles in PCU’s/day & C = Capacity of Highway in PCU’s/ day.

V/C LOS Performance 0.0 - 0.2 A Excellent 0.2 - 0.4 B Very Good 0.4 - 0.6 C Good / Average / Fair 0.6 - 0.8 D Poor 0.8 - 1.0 E Very Poor

Note: Capacity as per IRC: 64-199

DURING MINE OPERATION Particulars Details Proposed Capacity of mine/annum 3,21,699TPA No. of working days 300 Proposed Capacity of mine/day 1072 TPD Dumper Capacity 10 Tones No. of dumper deployed/day 6 No of trips 17 Considering both loaded & empty tractor trolleys Increase in PCU/day will be

102PCUs

MODIFIED TRAFFIC SCENARIO & LOS

Road V C Modified V/C Ratio

LOS

Chechat 552 3,000 0.18 A SH 9B to NH-12 1602 8,000 0.2 A

From the above analysis it can be seen that the V/C ratio is likely to change to 0.18 & 0.2

with LOS being A’’ which is Excellent, as per classification. So the additional load on the

carrying capacity of the concerned roads is not likely to have any adverse effect.

Page 77: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

77 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.16: TRANSPORTATION ROUT MAP

Page 78: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

78 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

3.7 BIOLOGICAL ENVIRONMENT

The biological study of the area has been conducted in order to understand the

ecological status of the existing flora and fauna to generate baseline information and

evaluate the probable impacts on the biological environment.

The objectives of this study were as follows:

To conduct detail study for floral/faunal/avifaunal elements in the study area of proposed project site.

To assess scheduled species in the proposed site. (Rare, endangered, critically

endangered, endemic and vulnerable).

To identify locations and features of ecological significance

To collect Baseline data for the study area along with a description of the existing terrestrial, wetland and aquatic vegetation.

Type of forest in area- Mixed Miscellaneous Forests is found in regions. The main

species found in this kind of forest are Anogeissus pendula, Anogeissus latifolia,

Terminalia tomentosa, Terminalia arjuna, Terminalia chebula, Albizia lebbeck,

Dalbergia paniculata etc. and its associates.

FOREST WITHIN 10 KM RADIUS

Sr. NO.

RESERVED & PROTECTED

FOREST

DIRECTION DISTANCE

1. Kuttepur PF NW 6.1 KM. 3. Suket RF E 7.0KM 4. Salvad RF NE 3.9KM 2. Basyaheri PF SE 5.3 Km

Flora: The floral study is done by quadrate method. In core zone 5 quadrate is taken

and in buffer zone 25 quadrate depending upon density, frequency and abundance of

trees, shrubs etc. Further the percentage values of relative frequency, density and

abundance are summed up together and this value is designates as IVI.

The present study on the floral assessment for the proposed project activity is based

on extensive field survey of the area. The study has been conducted in winter season.

The plant species were identified with the help of taxonomists of related fields and

Page 79: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

79 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

nearby Institutions. Besides the collection of plant species, information was also

collected with vernacular names of plant species made by local inhabitants. In this

process the whole study area was divided into different sections to get the maximum

diversity of plant species. The sampling sites were selected based on land use pattern,

topography and floristic composition of the study area. Data on forest type legal

status and their extent in the study area has been collected from forest department.

The other relevant data on bio-diversity, like economically important plant species

and medicinal plant, Rare and endangered species in the study area have been

collected from secondary sources like forest and wild life departments.

In the core zone vegetation is dominated by Calotropis Procera, Zizyphus nummularia

Page 80: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

80 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIGURE 3.17: BIOLOGICAL SAMPLING LOCATION MAP OF THE STUDY AREA

Page 81: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

81 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

FIG 3.18 PHOTOGRAPHS OF VEGETAION

Calotropis procera

Accacia nilotica

Page 82: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

82 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

TABLE 3.16: LIST OF FLORAL SPECIES OBSERVED IN CORE ZONE

S. No BOTANICAL NAME COMMON NAME FAMILY

1 Prosopis juliflora Babool Fabaceae 2 Zizyphus nummularia Bor Rhamnaceae 3 Calotropis procera Akdo Asclepiadaceae 4 Echinops echinatus Untkantili Asterales 5 Acacia nilotica Desi babool Fabaceae 6 Azadirachta indica Neem Meliaceae

Source: By Field Expert during study period.

TABLE 3.17: LIST OF FLORAL SPECIES OBSERVED IN BUFFER ZONE

S. No BOTANICAL NAME COMMON NAME FAMILY

Trees 1. Acacia leucophloea Harmo Fabaceae 2. Acacia nilotica Desi baval Fabaceae 3. Aegle marmelos Bel patra Rutaceae 4. Ailanthus excels Arduso Simaroubaceae 5. Albizia lebbeck Siras Fabaceae 6. Albizia procera Kala Siras Fabaceae 7. Anogeissus latifolia Dhavdo Combretaceae 8. Azadirachta indica Limdo Meliaceae 9. Bauhinia racemosa Asitaro Fabaceae 10. Bombax ceiba Simlo Bombacaceae 11. Cassia fistula Garmalo Caesalpiniaceae 12. Cassia siamea Kesia Fabaceae 13. Dalbergia sissoo Shisham Fabaceae 14. Emblica officinalis Amla Euphorbiaceae 15. Ficus benghalensis Vad Moraceae 16. Ficus religiosa Piplo Moraceae 17. Mangifera indica Aam Anacardiaceae 18. Polyalthia longifolia Ashoka Annonaceae 19. Prosopis juliflora Gandobaval Fabaceae 20. Syzygium cumini Jambun Myrtaceae 21. Tamarindus indica Khati Amli Fabaceae 22. Zizyphus mauritiana Bor Rhamnaceae 23. Phoenix sylvestris Khajur Arecaceae 24. Butea monosperma Khakhra Fabaceae

Shrubs 25. Annona squamosa Sitafal Annonaceae 26. Argemone Mexicana Pila Dhatura Papaveraceae 27. Calotropis gigantean Shivark, Akdo Apocynaceae 28. Calotropis procera Mudar Asclepiadaceae

Page 83: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

83 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

S. No BOTANICAL NAME COMMON NAME FAMILY

29. Ipomoea fistulosa Beshram Convolvulaceae 30. Jatropha curcas Ratanjyot Euphorbiaceae

31. Lantana camara Lantana Verbenaceae

32. Bougainvillea spectabilis Nyctaginaceae Boganvel

Herbs 33. Cassia tora Puwad, Panwar Fabaceae 34. Datura inoxia Dhatura Solanaceae 35. Parthenium hysterophorus Gajar Ghaas Asteraceae 36. Tribulus terrestris Gokharu Zygophyllaceae 37. Tridax procumbens Kumru Asteraceae 38. Zizyphus nummulaira Ber Rhamnaceae 39. Echinops echinatus Untkantili Asterales

Grass 40. Cymbopogon martini Lemon grass Poaceae 41. Cynodon dactylon Dub Poaceae 42. Sida cordifolia Bala Malvaceae 43. Cenchrus ciliaris Jhino dhamramnu Poaceae

Fauna: The study of fauna takes substantial amount of time to understand the specific

faunal characteristics of the area. The assessment of fauna have been done on the bases

secondary data collected from different government offices like forest department,

wildlife department etc. The presence of wildlife was also confirmed from the local

inhabitants depending on the animal sightings and the frequency of their visits in the

project area. In addition review of secondary data was another source of information

for studying the fauna of the area. In addition the following sources were also used.

Sighting during ecological studies

Animal call

Foot mark and excreta

Page 84: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

84 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

TABLE 3.18: LIST OF FAUNA SPECIES OBSERVED IN THE CORE ZONE

S. No. Scientific

Name

Common

Name Family

Status in

Wildlife

Protection

Act-1972

Status in

IUCN

Category

1. Funambulus

pennanti

Five Striped

Palm Squirrel

Sciuridae Schedule IV Least Concern

2. Herpestes

edwardsi

Mongoose Herpestidae Schedule II Least Concern

3. Lepus nigricollis Indian Hare Leporidae Schedule IV Least Concern

4. Hanuman langur Semnopithecu

s entellus

Cercopithecid

ae

Schedule II Least Concern

5. Rattus rattus Black Rat Muridae Schedule V Least Concern

6. Rousettus

leschenaulti

Chamgadar Pteropodidae Schedule V Least Concern

7. Hemidactylus

brooki gray

House lizard Gekkonidae Not Enlisted Not Evaluated

8. Hemidactylus

maculates

Rock gaeko Gekkonidae Not Enlisted Not Evaluated

09. Acridotheres

ginginianus

Bank Myna Sturnidae Schedule IV Least Concern

10

Acridotheres

tristis

Common Myna Sturnidae Schedule IV Least Concern

11. Corvus

macrorhynchos

Jungle Crow Corvidae Not Enlisted Least Concern

12. Columba livia Blue Rock

Pigeon

Columbidae Not Enlisted Least Concern

Page 85: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

85 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

TABLE 3.19: LIST OF FAUNAL SPECIES OBSERVED IN BUFFER ZONE

S.

No. Scientific Name

Common

Name Family

Status in

Wildlife

Protection

Act-1972

Status in

IUCN

Category

1. Boselaphus

tragocamelus

Nilgai Bovidae Schedule III Least Concern

2. Canis aureus Jackal Canidae Schedule III Least Concern

3. Funambulus

pennanti

Five Striped

Palm Squirrel

Sciuridae Schedule IV Least Concern

4. Herpestes

edwardsi

Mongoose Herpestidae Schedule II Least Concern

5. Lepus nigricollis Indian Hare Leporidae Schedule IV Least Concern

6. Hanuman langur Semnopithecu

s entellus

Cercopithecid

ae

Schedule II Least Concern

7. Rattus rattus Black Rat Muridae Schedule V Least Concern

8. Rousettus

leschenaulti

Chamgadar Pteropodidae Schedule V Least Concern

9. Sus scrofa Wild boar Suidae Schedule III Least Concern

11. Hemidactylus

brooki gray

House lizard Gekkonidae Not Enlisted Not Evaluated

12 Bufo bufo Toad Bufonidae Not Enlisted Least Concern

13 Ptyas mucosus Common Rat

Snake

Colubridae Schedule IV Not Evaluated

Avifauna

During Birds survey actual counts of birds were made following the standard survey

technique. Observations were made during a walk through in the chosen transect for

sighting birds. The number of birds observed in each sampling location was directly

counted and listing was made. Birds were noted, counted and identified with the help of

8X40 “Optima Zenith” binocular and standard field identification guides

Page 86: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

86 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

TABLE 3.20: LIST OF AVIFAUNAL SPECIES OBSERVED IN THE STUDY AREA

S. No. Scientific Name Common Name

Conservation Status as Per WL(P)A1972

Birds

1. Passer domesticus indicus

Indian House-Sparrow Sch. IV

2. Columba livia Rock Pigeon Sch. IV 3. Sturnia pagodarum Brahminy Starling Sch. IV 4. Bubulcus ibis Cattle Egret Sch. IV 5. Acridotheres tristis Common Myna Sch. IV 6. Centropus sinensis Greater Coucal Sch. IV 7. Francolinus

pondicerianus Grey Francolin Sch. IV

8. Upupa epops Hoopoe Sch. IV 9. Streptopelia decaocto Collared Dove Sch. IV 10. Vanellus indicus Red-wattled Lapwing Sch. IV 11. Psittacula krameri Rose-ringed Parakeet Sch. IV 12. Athene brama Spotted Owlet Sch. IV 13. Ardeola grayii Paddy bird Sch. IV

Source: Field expert during study period consultation with concern state forest officials, Secondary sources and also discussed with local people.

3.8 SOCIO-ECONOMIC ENVIRONMENT:

Introduction

Under Clause 6 of S.O.1533 of Environment Impact Assessment Notification, 2006)

The study is aimed to identify & predication likely impacts on socio-economic and

parameters of human interest due to proposed project. Socio-economic study of the

study area comprising of 10km. buffer zone. It shall be collect primary data through

air, soil, water, Biology & Biodiversity (Flora &Fauna) wild life, socioeconomic status

etc. it is main component of the project. The project of Satalkhedi Pipakhedi

Limestone mine area 43.24 hect. M.L. No. 55/91 Tehsil Ramganj Mandi Dist. Kota

RAJ.

Page 87: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

87 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Socio-Economic Profile

Demography & Socio-Economics: The growths of mining and industrial sectors

and infrastructure developments in and around the agriculture dominant areas,

villages and towns are bound to create its impact on the Socio-Economic aspects of

the local population of the area experiencing development. The impacts may be

positive or negative depending upon the developmental activity. To assess the

anticipated impacts of the mining and industrial growth on the socio-economic

aspects of people, it is necessary to study the existing socio-economic status of the

local population, which will be helpful for making efforts to further improve the

quality of life in the area under study. For assessing the prevailing Socio-Economic

aspects of people in the study area around the existing mine, the required data has

been collected from various secondary sources and analyzed.

Methodology Adopted for the Study: The methodology adopted for the study is

based on the following points:-

Review of Secondary Data, such as District Primary Census Statistical Hand Book of

Kota district, 2011 within the study area around the mine lease area:

Conducting Focus Group Discussions school, local person in the villages for eliciting

the general information of the study area, to support or supplement the information

collected through secondary and primary surveys.

Review of Demographic and Socio-Economic Profile - 2011

The sociological aspects of this study include human settlements, demography, social

structure such as Scheduled Castes and Scheduled Tribes and literacy levels besides

infrastructure facilities available in the study area. The economic aspects include

occupational structure of workers. The information on socio-economic aspects of the

study area has been collected from secondary sources, which mainly include District

Primary Census Handbook 2011 Kota Districts.

Page 88: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

88 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

The village-wise Provisional demographic data as per Census 2011. The salient

features of the demographic and Socio-Economic aspects of the study area are

described in the following sections.

Demographic Aspects: The study area total population consisted of 30178 people.

The males and females constitute varies from 53.15 to 52.47 % and 46.84 to 52.47

% of the study area population respectively. The distribution of population in study area

is presented in Table-3.21

TABLE 3.21 DISTRIBUTION OF POPULATION

Particulars 0-3km. 3-7 km. 7-10 km. 0-10 km. Name of Village 1-Pipakheri

2-Salwadkhurd 3-Kudala 4-Umedpura 5-Satalkheri 6-Mayla 7-Durjanpura

1-Nimana 2-Amarpura 3-Sandpur 4-Suket 5-Kumbhkot 6-Chousala 7-Hiriyakheri 8-Atraliya 9-Kalyakui 10-Semalkheri 11-Nalodiya 12-Parli 13-Charyakheri

1-Deoli 2-Barodiya Antri 3-Lahariya 4-Udpura 5-Modak 6-Naharsinghi 7-Nayagaon 8-Jamunya 9-Jhalara 10-Basyaheri 11-Julmi 12-Bhavpura 13-Khairabad 14-Ramganjmandi

No. of Household 5771 8679 15728 30178 Male Population 14178 21880 41332 77390 Female Population 12497 19800 37798 70095 Total Population 26675 41680 79130 147485 Male Population (0-6 Year) 2189 3559 5676 11424 Female Population (0-6 Year) 2002 3138 5119 10259 Total Population (0-6 Year) 4191 6697 10795 21683 % of Average household size TP 5 5 6 5 % of male to total Population 53.15 52.49 52.23 52.47 % of female to total Population 46.84 47.50 47.76 52.47 Sex Ratio (M:F) 1000:881 1000:904 1000:914 1000:905

NOHH=Number Of Household

Page 89: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

89 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

TP=Total Population

TM=Total Male, Female

SC=Schedule Caste

ST=Schedule Tribe

FIG.NO. 3.19

Average Household Size: The average household size varies from 5 to 6 the low

family size could be attributed to a high degree of urbanization with migration of

people with higher literacy levels who generally for smaller family size and family

welfare measures.

Sex Ratio: The Sex Ratio of Male and Female indicates that the males constitute to

about 52.47% and females 52.7% of the total population. The sex ratio i.e. the number

of females 905 males per 1000 indirectly reveals certain sociological aspects in

relation with female births, infant mortality among female children and single person

family structure, a resultant of migration of industrial workers. The study area on an

average has 1000 females per 1000 males. high female in 0-6 year’s age groups is

alarming and indicate the impact of urban population

Social Structure: Various religion groups consisting of Hindus, Muslim and

Christians inhabit the study area. The percentage of Schedule Caste population varies

between 28.70 % in study area. The highest percentage of Schedule Caste population

Page 90: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

90 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

recorded in 0-3km.radius and lowest in 7-10 Km. radius. The percentage of Schedule

Tribe population varies between0- 8% in study area. The highest percentage of

Schedule Tribe population recorded in 0-3km. radius and lowest in 3-7 km. radius.

The distribution of population by caste and tribe is shown in Table3.22

TABLE :- 3.22 DISTRIBUTION OF POPULATION SOCIAL STRUCTURE

Particulars 0-3km. 3-7 km 7-10 km 0-10 km

Schedule Caste 13988 11964 16377

42329

% of SC to total population 52.43 28.70 20.69 28.70 Schedule Tribes

2762 2351 6598

11711 % of ST to total population 10.35 6.12% 8.33 8% Total SC & ST Population 16750 14315 22975

54040

% to total

population 62.79 34.34 29.03 36.64

Literacy Levels: The study area experiences a considerably medium literacy rate

of 38.19%. The level of literacy near mining area in general quite low and female

literacy in particular is below state and National literacy level. The distribution of

literate and literacy rate in the study area is given in Table3.23

TABLE 3.23 DISTRIBUTION OF LITERATES AND LITERACY RATE

Particulars O-3km. 3-7 km. 7-10 km. 0-10 km.

Male Literates 4642

7171 10228 22041

Female Literates 7185 10652 16449 34286

Total Literate 11827 17823 26677 56327

Total Literacy Rate of TP

(%) 44.33 42.76 33.71 38.19

Page 91: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

91 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Male Literacy Rate of TP (%) 17.40% 17.20% 12.92% 15%

Female Literacy Rate of TP (%) 26.93 25.55 20.78 23.24

TL=Total Literate, Male, Female

FIG.NO.3.20

Occupational Structure: The occupational structure of residents in the study area

is studied with reference to main workers, marginal workers and non-workers. The

main workers include 10 categories of workers defined by the Census Department

consisting of cultivators, agricultural labours, those engaged in livestock, forestry,

mining and quarrying; manufacturing, processing and repairs in household

industry; and other than household industry, construction, trade and commerce,

transport and communication and other services.

The marginal workers are those workers engaged in some work for a period of less

than six months during the reference year prior to the census survey. The non-

workers include those engaged in unpaid household duties, students, retired

persons, dependents, beggars, vagrants etc; institutional inmates or all other non-

workers who do not fall under the above categories.

Together the Main Workers work out to be 31.22% of the total population. The

Marginal workers 8 % and Non-workers constitute 60.78% of the total population

Page 92: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

92 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

respectively. The distribution of workers by occupation indicates that the non-

workers are the predominant population. The occupational distribution of the

population of study area is shown in Table –3.24

TABLE 3.24 OCCUPATIONAL STRUCTURE

Particulars 0-3km 3-7 km 7-10 km 0-10 km

Total Population 26675 41680 79130 147485

Total Workers 11233 17270 29336 57839

Total Main workers 9111 12663 24279 46053

% of MW to TP 34.15 30.38 30.68 31.22

Marginal worker 2122 4607 5057 11786

% of MRW to TP 8% 11.05% 6.39% 8%

Non-workers 15442 24410 49794 89646

% of NW to TP 57.88 58.56 62.92 60.78

FIG.NO. 3.21

Page 93: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

93 Sh. Pankaj Kumar Bairwa Satalkhedi- Pipakhedi Limestone mine

Base line Data of Study Area:

Base line data are collected and prepared by conducting a survey by Team Members.

Minimum 20%of the villages under Buffer zone have been surveyed by proportional

random sampling method, multi household survey conducted by our team.

preferably the village falling from the Core Zone to 3 Km, secondly of the villages

falling 3 to 7 km and 7-10 km of buffer zone.

Study Village Pipakhedi

Pipakhedi is a medium size large village located in Ramganj Mandi of Kota District,

Rajasthan. With total 324 families residing. The Pipakhedi village has population of

1747 of which 922 are males while 825 are females as per population census 2011.

In Pipakhedi village population of children with age, 0-6 is 265, which makes up

15.17% of total population of village. Average sex ratio of Pipakhedi village is 895,

which is lower than Rajasthan state average of 928. Child Sex ratio for the Pipakhedi

as per census is 920 higher than Rajasthan average of 888.

Pipakhedi village has lower literacy rate compared to Rajasthan .in 2011, literacy

rate of Pipakhedi village was 64.37% Compared to 66.11% of Rajasthan. In

Pipakhedi Male literacy stands at 80.10% while female literacy rate was 46.70%.

Work Profile

In Pipakhedi village out of total population, 725 were engaged in work activities.

91.45% of workers describe their work as Main Work (Employment or Earning

more than 6 Months) while 8.55% were involved in Marginal activity providing

livelihood for less than 6 months. of 725 workers engaged in Main Work, 186 were

cultivators (owner or co-owner) while 24 was Agricultural labour.

Page 94: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

FIGURE 3.22: SOCIO –ECONOMIC SURVEY LOCATION MAP

Page 95: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

CHAPTER - IV

ANTICIPATED IMPACTS& MITIGATION MEASURES

4.1INTRODUCTION

Environmental impacts due to open cast mining and allied activities are very

common which degrade the quality of environment to a considerable arial extent

from the source. In this chapter the likely impacts on different environmental

components are identified and mitigation measures are proposed accordingly.

4.2 IMPACT ON LAND ENVIRONMENT AND MITIGATION MEASURES

Topography and Drainage

Anticipated Impacts: The existing mining is change the topography and drainage

pattern of the mining lease area in the form of pits. However, mining operation

confined to the core zone of 43.24 ha, hence no impact is anticipated on the

topography and drainage pattern of the buffer zone.

Mitigation measures: To minimise the impact on the drainage pattern garland

drain is proposed to be made around the working pit so as to prevent the flow of

water into the pit. Garland drain routed through adequately sized sumps for

settling of suspended particles and the runoff thus collected is being used for

afforestation.

Land use in core and buffer zone.

Anticipated Impacts: No adverse impact is anticipated on land use of buffer

zone due to the existing mining operations, as all the related activities is

being confined to the core zone. The land use of the core zone is being undergone

considerable change as arising from:

- Excavations

- Establishment of facilities in the area.

The summarized detail of land use plan for pre-operational, operational and post

operational phase as per the approved mining plan is given as under:

Page 96: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Note- About 15.9800 ha area has been already planted within lease for full fill

33% plantation as per ToR compliance. At the end of mine life about 20.77 ha area

will be planted which includes 3.5400 Ha area will be planted on statuary barrier

(7.5 Meter) & 17.2396 ha area will be backfill planted. About 6.4804 ha area will

be converted as water storage.

4.3 IMPACT ON WATER ENVIRONMENT AND MITIGATION MEASURES

Anticipated Impacts on ground water source: There is no proposal for

abstraction of groundwater for the limestone mining. Also there is no any source

of ground water in the lease area. The mining will not intersect the water table of

the area as the ultimate depth of mining will be 303 mRL and general water table

of the area is 300 mRL (40mbgl) to 295 mRL (45mbgl) as per the information

furnished in the approved mining plan.

The excavation of limestone further does not add to any harmful ingredients that

could leach down to the water table. The composition of limestone is mainly CaO

and MgO. Thus the mine workings will not affect the ground water quality.

Anticipated Impacts on ground water source including hydrogeology: There

is no abstraction of surface water. The sources of pollution generally are run-off

from waste dump and mining area.

S. No. Particulars Pre Operational

(In Ha)

Operational (In Ha)

Post operational

(In Ha) A) Mining Activity 1 Mining pits 8.5215 10.5710 0.00 2 Road & building 2.3750 2.3750 0.00

3 Plantation on statuary barrier

0.0000 2.5500 3.5400

4 Mineral stack 1.5420 1.9540 0.0000 5 Water storage 1.2010 1.2010 6.4804

6 Reclamation & Backfilled Plantation

5.9800 5.9800 17.2396

7 Plantation on remaining lease area

15.9800 15.9800 15.9800

B) Remaining virgin land

7.6405 2.6290 0.000

Total 43.24 43.24 43.24

Page 97: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

There is no any surface water body exists in the lease area or any river/nallah

flowing adjoining to the lease area which could get affected. However general

drainage in the study area is defined by the Ahu river which is flowing at a

distance of 6.4 km SE direction & Amjar Nadi at 9.3km in NE & Psadi Nadi is

flowing 7.5 Km in SW direction from the lease area. Hence the proposed mining

will not pollute the surface water.

Mitigation measures to minimize impacts on water environment: Garland

drains will be constructed on all side of quarries. All the garland drains will be

routed through settling pits to remove suspended solids from flowing into storm

water. The water collected in the pit, after settling of the suspensions, will be

used for plantation. The details are given in EMP.

4.4 IMPACT ON AIR ENVIRONMENT AND MITIGATION MEASURES

The sources of air pollution are dust generated due to excavation, blasting, loading

and unloading of material and movement of dumpers/trucks. The blasting is

carried out by using low explosives by making drill hole with compressed air

operated jackhammer drills. The dust liberated in mining and other related

operations is injurious to heath if inhaled in sufficient quantity.

The baseline data on air quality is presented in Chapter-3. The maximum values of

PM10 and PM2.5 levels during the study period are below the 24-hour NAAQ

Standard 2009 (Figure-4.1). The gases SO2 and NO2 are also well below the NAAQS

2009.

Anticipated Impacts: The impact of the operation on the air quality has been

predicated using Fugitive Dust Model (FDM), which is a computerized air

quality model specifically designed for computing concentration and

deposition impacts from fugitive dust sources. The sources may be point, line or

area sources. The model has not been designed to compute the impacts of

buoyant point sources, thus it contains no plume rise algorithm. The model is

generally based on the well-known Gaussian Plume formulation for computing

concentrations, but the model has been specifically adapted to incorporate an

improved gradient transfer deposition algorithm. Emissions for each source

Page 98: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

are apportioned by the user into a series of particle size classes. A

gravitational setting velocity and a deposition velocity are calculated by FDM

for each class. Dust emission rate from the mining area, based on the following

empirical formula.

Pa x 23.6

Dust émission (DE) = ---------------------- Wd x Wh x 1000

DE = Dust emission in kg/hr Pa = Annual Excavation in Tonnes Wd = No. of days of operation in a year

Wh = Effective working hrs in a day

About 23.6 Quantity of dust emitted in kg/for 1000 tonnes of excavation

Dust emission rate= (321699 x 23.6)/ 300x 8 x1000) = 3.16kg/hr.

The above mentioned emission rate is without adoption of dust control measures

of each blocks. The literature suggests that dust control measures reduce the

emissions and effective emission rate is one third of the computed emission i.e.

3.16/3= 1.05 kg/hr and the same is taken for modeling to compute the following:

The 24 hourly averaged incremental concentration with hourly data.

The identification of grid point having peak concentration for the

incremental values.

Preparation of isopleths of for various pollutants.

TABLE NO-4.1 PREDICTED AMBIENT AIR QUALITY CONCENTRATIONS IN OPERATION

PHASE CUMULATIVE CONCENTRATIONS (BASELINE + INCREMENTAL) FOR PM10

S. No.

Particular Mining lease

area

1. Monitored Maximum concentrations in µg/m3 78.7

2. Predicted incremental Maximum concentrations in µg/m3

0.8

3. Resultant Maximum concentrations in µg/m3 79.5 4. NAAQS (dated 2009) 100

Resultant maximum concentration with in permissible limit

Page 99: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

FIGURE 4.1: GROUND LEVEL CONCENTRATION OF AAQ DURING OPERATION

PHASE IN 10 KM FOR PM10.

Page 100: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

FIGURE-4.2: GROUND LEVEL CONCENTRATION OF AAQ DURING OPERATION

PHASE IN 1 KM FOR PM10

Page 101: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Mitigation Measures to Minimize Air Pollution

Main source of air pollution is dust from the movement of dumpers/trucks.

The road is metalled except that inside the connecting link. Paving of road is

proposed to be done this will reduce the dust level from the movement of

vehicles to a large extent.

The sprinkling of water is being done undertaken as and when required on

roads as well as stockpile.

The dust may also generate due to low level blasting. It will be very limited

to the explosion site within 100 m. It will be minimized by plantation around

the mine boundary.

Further while manual lifting of the material and dumping into truck or by

using excavator in this case being lime stone pieces, the dust generated will

be minimum. However, drivers will be trained to drop the material from

minimum height.

Proper maintenance of vehicles is being done to minimize the pollutants;

Pollution under Control certificates will be maintained for the trucks and

drivers are instructed to drive at slow speed and proper supervision is

maintained.

The trucks are being covered while moving the material and care is being

taken so that loading will be done without spillage of material during the

movement.

Effective traffic management is being done by ensuring that there are no

traffic jams on mine route by deputing manpower and by planning truck

movement.

Effective mine closure plan or post mining land use.

Ambient Air Quality Monitoring will be conducted on regular basis to assess

the quality of ambient air as per the proposed monitoring plan in Chapter-5

to have a watchful eye on dust levels and to assess the effectiveness of

mitigation measures.

Page 102: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

4.5 IMPACT OF NOISE / VIBRATIONS & MITIGATION MEASURES

There is no habitation in and around the core zone and the nearest villages

Satalkhedi & Pipakhedi is 0.8 & 1.0 km from lease area. The main source of noise

pollution and vibrations will be (i) movement of trucks (ii) Operation of excavator

(iii) Drilling of holes for blasting and (iv) Blasting itself.

Anticipated Impacts: There is no habitation in immediate vicinity. The nearest population is in village

Satalkhedi is at about 0.8 Km from the mine site. Therefore from mining activity

there will no impact on the population of the area.

Noise generated from the proposed machinery ranges between 58 to 101dB (A)

(during drill holes). The exposure time for the maximum noise level of 101dB (A)

is one hour as per the Indian Bureau of Mines. Noise levels beyond the prescribed

standards can have an impact on workers. These can have also impact, on fauna.

Mitigation measures

In order to reduce the effect of noise pollution, ear plugs /earmuffs is being

provided to workers.

The compressor used for drilling holes is being provided with proper enclosures.

The workers will not be allowed to work more than one hour in noise prone

area, and will be shifted to other places.

Plantation is being carried in mining lease in form of garden. The greenbelt

minimizes propagation of noise.

Proper maintenance of vehicles is being done.

Mine operations Proper maintenance of vehicles is being done.

limited to day time i.e. 9AM to 6 PM

Power Horns will not be allowed in trucks. Drivers will be further instructed not

to use music systems at high volumes.

The blasting is being of low impact type with a maximum impact area of 500 m

The excavator use for limited hours with breaks at regular intervals. The

excavator will be regularly serviced.

By carefully designing a blast hole using experience and deciding drilling pattern

or blast geometry with appropriate burden distance, spacing as holes, hole size,

hole depth, and stemming height, and powder factor.

Page 103: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Ambient and Source Noise level Monitoring will be conducted on regular basis to

assess the quality of ambient air w.r.t noise as per the proposed monitoring

plan in Chapter-5 to have a watchful eye on noise levels and to assess the

effectiveness of mitigation measures.

4.6 IMPACT ON BIOLOGICAL ENVIRONMENT & MITIGATION MEASURE

The lease area of 43.24 ha is Pvt. Land and there is no forest land within the lease

area. There is no interference with any first order streams. There is no release of

any effluent.

Impact on Flora and Fauna: The dust is the only major pollutant which will be

generated from different activities of mining. The effect of particulate matter on

vegetation is in the form of incrustation, plugging of stomata, and loss of

chlorophyll and reduction of photosynthesis process. Disturbance in plant

metabolism due to deposition of dust particles on foliar surfaces leads to

reduction in plant growth. The activities such as blasting including drilling holes,

operation of machinery as excavator and movement of dumpers/trucks can have

impact in terms of disturbance due to noise; interference in movement etc.

Mitigation Measures:

During setting up and operation phase of mine following measures will be taken

up to mitigate impacts on surrounding biodiversity:

Mining activities will be restricted to day time so that fauna will not disturb

at night.

Tar road is being used for transportation to minimise fugitive emissions.

Material is being covered during transportation.

Plantation is being taken up in consultation with Forest department and

species local to the area shall be planted as per findings during baseline

environment which help maintain the regional ecological balance, soil and

hydrological conditions.

Water sprinkling is being done on haul roads to control fugitive emissions.

Hedge of sturdy woody shrubs along the lease area will be created.

The removal or picking of any protected/unprotected plant will not be

permitted.

Fencing around the pit mouth to prevent fall of animal.

Page 104: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

If wild life is noticed crossing the area, they will not be distributed at all.

Worker will be made aware of the importance of the wild life.

Educational and awareness programmes for mine workers will be

arranged.

4.7 IMPACT ON SOCIO ECONOMIC CONDITIONS

Mining activity has positive as well as negative environmental impacts related to

socio economic in the study area.

Positive Impacts

Mining activity will generate employment opportunity both direct and indirect

in the study area.

Increase in business opportunity with contract works, employment through

contractors, running of dumper, trucks, tractors and buses on hire basis,

running canteens, different kind of shops and other associated jobs.

Improvement in the general living standards and knowledge sharing.

Improvement in the economic growth in the region

Improvement in the general living standards and knowledge sharing.

Development of the region.

Other facilities will be provided under CSR activity.

Thus the local people will enjoy the economic upliftment. The following activities

will be followed: -

i. Rural/village & Community welfare.

ii. Healthcare of local population.

iii. Free medical camps.

iv. Literacy awareness, supports to schools etc.

v. Environment protection and Environment awareness activities like Environment awareness camps, plantation etc.

Thus the socio-economic status of the area will be improved.

Negative impacts

Dust generated from the mining activity can have negative impact on the health of the workers.

Approach roads can be damaged by the movement of trucks/dumpers.

Nearby agricultural field can also be affected by the dust generation.

Page 105: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Mitigation measures

Adequate measures will be adopted to control dust generation like water

sprinkling on unpaved road, working sites and wheel & truck wash facility at

applied site.

Construction and maintenance of approach roads.

Material will be covered during transportation.

Paving of unpaved roads.

4.8 IMPACT ON OCCUPATIONAL HEALTH & SAFETY

Healthy and safe working conditions are among the first expectations for

sustainability, i.e. the expectation that risks in mining will not deprive workers of

their livelihoods or of their quality of life. Occupational injuries and ill-health have

huge social and economic implications for individuals, their families and their

communities. They also have an adverse impact on the economy of the society as a

whole.

Occupational accidents and health hazards can also affect public health and safety,

and the environment. The effect on the health and safety of people, costs to the

economy and impacts the environment. Efforts will be made to address

occupational health and safety with broader social agenda for sustainable

development.

Hazards, which are associated with poor engineering design, contribute to

increased safety risks.

Although health risks can be avoided by implementing controls at source in the

work environment, designing such controls for mining environment presents

considerable challenges because dust and noise are generated by mining itself. A

range of control measures that act together to reduce exposure to such risks is

therefore necessary. These could include methods for minimizing dust levels by

reducing dust generation and methods for dilution, suppression, capture, and

containment.

Page 106: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

While significant uncertainties remain in controlling dust exposures and

maintaining the effectiveness of controls, the use of appropriate personal

protective equipment (PPE) is important.

Exposure to Dust

Exposure to fine particulates is associated with work in most of the dust-

generating stages notably from drilling and blasting, mineral handling, and

transportation.

Methods to prevent and control exposure to dust include the following:

Control of dust through water spraying,

Use of PPE, as appropriate (e.g. masks and respirators) to address residual

exposures.

Physical hazards

Injuries during Project operation are typically related to slips and falls contact

with falling / moving objects and lifting / over-exertion. Other injuries may occur

due to contact with, or capture in, moving machinery (e.g. trucks). In case of any

accident immediate & proper first –aid medical care shall be provided at the mine

site.

Pre-placement medical examination and periodical medical examination

schedules

The fresh employees when taken are thoroughly medically examined under initial

medical examination and thereafter during continuation of employment; the

periodic medical examination is being done as suggested by DGMS.

Measures to Control Occupational Health Hazard & Safety

The working in the lease area will be done with all safety measures under the

supervision of qualified staff. The workers will be provided dust mask, safety boot,

helmet and other safety equipment. A well-equipped first aid box will be

maintained at site.

For mitigating the aspect the following measures will be implemented:

Regular water sprinkling on haul roads.

Dust mask is being provided to the workers.

Periodical medical examinations will be carried out for the workers as per

Norms.

Medical records are being maintained.

Page 107: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Medical facilities to the workers.

Any early symptom of diseases, if observed, such workers will be taken off from

the dusty atmosphere and will be employed at other suitable place.

Personal Protective Equipment’s is being provided to the workers.

Vocational Training will be provided to the workers.

Safety of the employee during mining will be taken care as per Mine

Regulations

Details of Infrastructural Facilities for Worker

Water for drinking & other purpose will be arranged.

All the safety equipment’s such as helmets, safety shoes, goggles, dust masks etc.

A well-equipped first aid facilities,

Periodic medical health check-ups,

Rest shelter, washrooms etc. is being provided near the working blocks.

*********

Page 108: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

CHAPTER – V

ANALYSIS OF ALTERNATIVES

5.1SITE ALTERNATIVES

Mineral deposit is site specific. The lime stone deposit is sedimentary deposit.

There for as per the nature of mineral deposit and proposed rate of production the

technology chosen is suitable for mining.

5.2TECHNOLOGY ALTERNATIVES

Limestone is exposed in the area and depending upon the availability of mineral.

The usable lime stone varying in thickness from 6m located below the hard

limestone layer. Moreover small scale drilling and blasting will also be done for

excavation and loading and transportation will be carried out by excavator &

dumpers respectively. Therefore as per the nature of mineral deposit and

proposed rate of production the technology chosen is suitable for mining. Proper

use of waste generated by mining will be backfill into exhausted pit up to ground

level, leaving reaming mined out pit for water reserve and plantation on back

filled area.

=====******=====

Page 109: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

CHAPTER – VI

ENVIRONMENTAL MONITORING PROGRAMME

6.1 MONITORING SCHEDULE AND PARAMETERS

Environmental monitoring programme will be taken up after the grant of EC and

half yearly compliance report in respect of the terms and condition stipulated in

the EC letter will be submitted to the regulatory authorities.

For the present working mine good practices of EMP and monitoring schedules

are ensured to keep all the environmental parameter of the projects within

statutory levels in respects of ambient air quality, water quality, soil quality,

socio-economic improvement, noise level standard. Regular monitoring of the

environment will be done and for that an environment monitoring cell will be

formed for conduction and supervision of entire monitoring programme. The

monitoring schedule along with monitoring parameters, monitoring frequencies

and duration is given in the below table.

TABLE 6.1: MONITORING SCHEDULE FOR ENVIRONMENTAL PARAMETERS

Particulars Monitoring

Frequencies

Duration of Station

Important Monitoring Parameters

Surface water/ Ground water Sampling

Twice in a year

Grab

pH, TDS, Iron, Hardness, Alkalinity, Chlorides, Calcium, magnesium, Nitrates, Sulphate & Fluorides.

Ambient air quality monitoring

Twice in a year.

24/8 hr. PM2.5 PM10, SO2 and NO2.

Noise Monitoring Twice in a

year. 8/1 hr. Level in dB (A).

Soil Sampling Twice in a

year Grab

PH, Conductivity, organic matter permeability, water holding capacity, Alkalinity & texture.

Page 110: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

6.2 ENVIRONMENT MONITORING CELL

The monitoring will be taken up by the supervisory officers of the mine. Mine

manager will be in charge of the environment cell and will be responsible for the

effective functioning of the monitoring programme. The environmental data will

be monitored initially by using an outside agency and later an in house

monitoring cell will be developed.

FIGURE 6.1: ENVIRONMENT MONITORING CELL (EMC)

Page 111: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

6.3 FUNCTIONS OF THE MONITORING CELL

1. To carry out the environment monitoring for environmental parameters

given in the table 6.1 by an outside agency or through monitoring cell that

will be formed by the mines management. The monitoring programme

will be focused to ensure the environmental status of the core and buffer

zone will be preserved in good status as per rules.

2. To observe the effectiveness of mitigation measures.

3. Regular visit of the working site to examine the slope stability, mine faces

and waste dump.

4. Regular checking of garland drain for any blockage due to silting or

accumulation of the loose materials.

5. To ensure the green belt development in a time bound manner and also

regular monitoring of planted species for survival rate.

6. Regular water monitoring for the parameters prescribed in the consent

conditions of SPCB.

7. Monitoring of ambient air quality at the desired monitoring location

covering both up wind and downwind directions and also to make sure

that control measures are effectively implemented.

8. Health check-up of the workers is being conducted regularly for

Occupational health and safety and also concentration of reparable dust

in the workplace will be regularly measured as laid down by DGMS.

9. The information regarding the health status of the workers will be

maintained.

10. Conducting safety week programmes to create safety awareness amongst

the workers and other staff. This will educate the workers to work safely

in mine lease with different equipment along with all PPE’s.

11. To make sure that CSR activities are taken up in the proposed villages.

12. Coordinating the environment related activities within the project as well

as with outside agencies.

13. To comply with all the EC conditions effectively.

Page 112: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

6.4 ENVIRONMENTAL POLICY:

Proponent is committed to providing a quality service in a manner to ensure a

safe and healthy workplace for employees and minimize potential impact on the

environment. They will operate in compliance with all relevant environmental

legislation and strive to use pollution prevention and environmental best

practices.

To achieve this will will endeavor to-

To integrate the policy with all stages of project and activities.

Minimize the impact on various components of the environment, particularly on

Air,water,Land and Natural resources through conscious and corrected efforts.

Compliance with the applicable environmental legislation & regulations.

Continual improvement of our environmental performance through the use of

most appropriate economically viable technologies, voluntary involvement of our

employees and participation of business associates.

********

Page 113: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

CHAPTER - VII

ADDITIONAL STUDIES

7.1 INTRODUCTION

The additional studies carried out for the Satalkhedi –Pipakhedi Limestone

(Building Stone) Mine, near village- Satalkhedi-Pipakhedi, Tehsil – Ramganj Mandi,

District- Kota (Rajasthan), for the proposed production capacity 3, 21,699 TPA

(RoM) Lime stone.

7.2 PUBLIC CONSULTATION:

As per EIA Notification, 2006 Public hearing was conducted on dated 06.12.2016

at the Atal Seva Kendra Gram Panchayat Bhawan in village Satalkhedi, Tehsil –

Ramganjmandi, Dist. – Kota, Rajasthan. Notices regarding this public hearing have

been published in news paper named Dainek Bhaskar on dated 05/11/2016 &

Jabaaz Patrika on dated 04/11/2016. The public hearing had been chaired by

Miss. Sunita Dang, Additional District Collector in the presence of Sh. Amit Sharma

Regional Officer of Rajasthan State Pollution Control Board, Kota & local people.

During the process suggestion, objections were invited from the local people

regarding the project. During the public consultation, no objection regarding the

project has been received. However people are happy with the mining project as

they have been get employment and other facilities. Minutes of public hearing is

attached as Annexure No-XII.

Page 114: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Photographs of public hearing

Page 115: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 116: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

7.2 RISK ASSESSMENT

The anticipated risks in the mining operations are mentioned below:

Hazard identification and risk analysis: This deal with the hazards associated

with various mining works during operation of the mine and can happen due to

excavation, handling of material, machinery breakdown electric failures and

natural calamities.

It also presents the calculated frequencies of occurrence of different accident

scenarios for the identified potential hazard occurrence.

Risk Reducing Measures based on the calculated frequencies and consequences.

7.3 IDENTIFICATION OF HAZARDS

Technological Hazards

Technological hazards may be due to intense noise during excavation / loading,

transportation, drilling & blasting etc. fire in the excavator, and road mishap.

Structural failure

Structural failure is associated with the failure of slope, it can be bench fall, slope

failure due to undercutting and fall of machinery and workers due to fall of

bench/slope, any of the said activity can cause major injury and fatalities.

7.4 SCENARIOS CONSIDERED FOR RISK ASSESSMENT

Knowledge of work

The application of risk assessment depends upon full understanding of all aspects

of the job being undertaken. In carrying out a risk assessment in relation to a

particular task, the evaluation must include a review of the knowledge, experience

and training of those persons carrying out the work.

Personal Competence

It follows that the knowledge, experience and training of personnel involved in

work is critical to evaluate any risk assessment. A knowledgeable, experienced

well-trained and competently supervised workforce will be at a lower risk of

accidents occurring than a poorly trained and badly supervised workforce.

Co-ordination

It is essential that the coordinator ensures that everyone engaged in the work is

capable and understands the role of others and their responsibility for each other.

Page 117: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Health hazards

Health hazards are associated with the dust and noise, it is necessary to quantify

the key pollutants during surface mining operations that may result into health

hazard.

Inundation

The nearest water body is Amjar river which is flowing at a distance of 9.3 km in

the NE direction, Ahu Nadi at 6.4 km in SE direction & Psadi Nadi 7.5 km in SW

direction from the lease area. There is no possibility of inundation of mine due to

this river.

Noise

Noise is considered as a common occupational hazard in mine environment.

Prolonged exposure to noise over a period of years may cause permanent damage

to auditory nerves and its sensory components (Noise Induced Hearing Loss). In

order to avoid Noise Induced Hearing Loss (NIHL) to the operators of the HEMMs,

the cabins of these machines will be made sound proof. Also, the operators and

other workers working in the high noise generating areas are being provided with

ear plugs/ ear muffs to protect their hearing. No worker will be allowed to enter

high noise generating areas without wearing proper protection equipment’s.

Surface Fire

There are no ignitable materials in limestone deposit. However, the excavator to

be deployed in the mine may catch fire. All precautionary measures will be taken

to prevent the occurrence of such activity.

Loading

There will be no risk associated with the activity. However, precautions will be

required to be taken to remove workers away from the loading operations, to

avoid any fall of material on persons. Also, the loading operations will be

supervised by a site supervisor for properly guiding the loading machine operator.

Pit Slope Failure

The sides of the mine benches will be suitably sloped to avoid bench failure. The

bench height is planned to be kept 6 to 9m with width more than 6m to 9m of the

bench. The bench sides and edges will be regularly inspected for any signs of

failure, development of cracks, etc. Due precautionary measures will be adopted to

avoid any bench or pit slope failure.

Page 118: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Heavy Vehicles

Proper care will be taken while loading and transportation of mineral and

overburden. Good maintenance and regular testing will be done to avoid any

mishap.

Personal Protective Equipment (PPE)

The PPE should be of good construction, where ever possible ISI certified, suitable

for the hazard e.g. a dust respirator fitted with the correct filter to capture the

particular hazardous dust and maintained to recommended standards.

Traffic Movement

The mining operation will be of small scale and the machinery proposed to be

used for mining is less in number, therefore there will be no risk of accidents due

to the traffic movement. However, haulage roads will be properly maintained and

the speed limits shall be implied on the vehicles plying for mineral transport to

avoid accidents.

7.5 DISASTER MANAGEMENT PLAN

The complete mining operation will be carried out under the management

control and direction of qualified Mines Manager. The Directorate General of

Mines Safety (DGMS), Dhanbad have issued a number of standing orders,

model standing orders and circulars to be followed by the mine management:

Checking and regular maintenance of garland drains and earthen

bunds to avoid any inflow of surface water in the mine pit.

Provision of pumps for pumping out water from the mining pit.

Entry of unauthorized persons will be prohibited.

Fire fighting and first aid provision shall be kept in the mines office

complex and mining area.

Safety equipment such as safety boots, helmets, goggles etc. will be made

available to the employees and regular checked for their use.

Training and refresher courses for all the workers.

Working of mine as per approved scheme and regular updating for the

same.

Regular cleaning of mine faces.

Page 119: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Regular maintenance and testing of all mining equipment as per

manufacture’s guidelines.

Suppression of dust on the haulage roads.

Increasing the awareness of safe practices through competitions,

posters and other similar drive.

7.6 OUTLINE OF DISASTER MANAGEMENT PLAN

The purpose of disaster management plan is to restore the normalcy for early

resumption of mining operation due to an unexpected, sudden occurrence

resulting to abnormalities in the course of mining activity leading to a serious

danger to workers or any machinery or the environment. The main objectives of

preparing a disaster management plan in mining project include:

• To protect workers in mine from accident.

• To prevent or reduce the incidence and severity of injury during mining

Operations.

• To respond immediately and adequately in case of a serious accident.

First Aid & medical facilities

The mine management will provide first aid facilities for use in emergency

situation. All casualties would be registered and will be given first aid. The mine

management will provide all facilities to evacuate the injured person from the

accident site to the nearby hospital.

Care and maintenance during temporary discontinuance

In case of any temporarily discontinuance or if mine closes temporarily, then the

mining working will be in the watch of a watchman. Before reopen of the mine

maintenance working will be provide to all the machineries deployed at mine site.

Before entering the labourers into the mine working/faces the workings and faces

are proposed to be inspected by manager for safety purposes as Mines Act.

7.8 SOCIAL IMPACT ASSESSMENT, R&R ACTION PLAN

There will be the positive impact on the villagers of the nearby villages in the form

of employment. There is no human settlement in the lease area. Thus there is no

impact on the human settlement and thus no R & R plan is required.

========**************========

Page 120: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

CHAPTER - VIII

PROJECT BENEFITS

There are various aspects of this project and allied activities that are beneficial to

the locality, region and nation.

The mineral Limestone production from this mine.

There is sufficient demand in this region for the purpose. The use of this

lime stone (Building Stone) in is flooring and walls tiles.

The production of lime stone from the proposed project will benefit the

state government by the way of revenue.

At present there are 109 employers in the mine & local people will also be

preferred for contract jobs during operational stages of the project.

Improvement in the physical & social infrastructure is another benefit that

will arise from this mining project. People in the adjoining area will be

helped through the CSR activities and other funds allocation especially for

the development of the area.

Tangible benefits like improved standard of living, health and education.

This project is beneficial at all levels providing benefits to the industry, local

inhabitants and state government.

========**************========

Page 121: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

CHAPTER – IX

ENVIRONMENT MANAGEMENT PLAN

9.1 INTRODUCTION

The environmental management plan has been formulated in keeping view the

process of mine planning so that ecological balance of the area will be maintained

and identified adverse impacts that are likely to arise will be mitigated. Mitigation

measures for identified environmental impacts have already been discussed

earlier in Chapter-IV.

The main objective of environmental management plan is implementation of all

environment pollution controlling system effectively to maintain the ecological

balance of the area and also to promote the sustainable development during the

operational and post operational phase in the area.

TABLE 9.1: ENVIRONMENT MANAGEMENT PLAN IMPLEMENTATION

Environmental Issue

Mitigation measures Implementation

Air pollution Paving of road. The sprinkling of water is being undertaken as

and when required on roads as well as stockpile.

Plantation will be done around the mine lease & backfill area. Wet drilling system will be adopted. Training to driver for unloading the material

from safe height to prevent dust generation. The dumper is being covered while moving the

material and care is being taken so that loading will be done without spillage of material during the movement.

Traffic management to ensuring that there are no traffic jams on mine route by deputing manpower and by planning dumper movement.

Proper management of waste dump yard. Effective mine closure plan or post mining land

use.

Project authorities through Regular monitoring of the roads, plantation sites, random checking of equipment.

Noise pollution Plantation along mining lease area the greenbelt minimizes propagation of noise.

Proper maintenance of vehicles is being done. Mine operations is being limited to day time. Power Horns will not be allowed in dumper.

Project authorities through Regular monitoring.

Page 122: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Drivers will be further instructed not to use music systems at high volumes.

The excavator use will be for limited hours with breaks at regular intervals. The excavator will be regularly serviced.

In order to reduce the effect of noise pollution, ear plugs /earmuffs will be provided to workers.

The compressor used for drilling holes is being provided with proper enclosures.

The blasting is being of low impact type with a maximum impact area of 500 m

Ambient and Source Noise level Monitoring will be conducted on regular basis to assess the quality of ambient air w.r.t noise as per the proposed monitoring plan to have a watchful eye on noise levels and to assess the effectiveness of mitigation measures.

Water pollution Garland drains are will be constructed on all side of quarries. All the garland drains will be routed through settling pits to remove suspended solids from flowing into storm water. The water collected in the pit, after settling of the suspensions, will be used for plantation. Plantation shall further help to reduce surface water pollution.

Project authorities

through regular

monitoring.

Land degradation

Garland drain will be constructed around the excavation to prevent the inflow of water into the pit. Sumps will be made for settling of suspended particles if any. A well laid out closure plan is given in the mining plan and approved from the authorities. Detail is given for reclamation of the degraded mine lease area to the maximum possible extent by backfilling of the worked out pit and plantation in the statutory boundary barrier and over backfilled part of the lease At the end of mine life about 20.77 ha area will be planted which includes 3.5400 Ha area will be planted on statuary barrier (7.5 Meter) & 17.2396 ha area will be backfill planted. About 6.4804 ha area will be converted as water storage. At present about 15.98 Ha area already planted within lease area.

Project authorities

through regular

monitoring.

Biological Environment

Mining activities is being restricted to day time so that fauna will not disturb at night.

Tar road is being used for transportation to minimise fugitive emissions.

Project authorities

through regular

monitoring.

Page 123: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Material is being covered with tarpaulin during transportation. Plantation will be taken up in consultation with Forest department and species local to the area shall be planted as per findings during baseline environment which help maintain the regional ecological balance, soil and hydrological conditions. Water sprinkling is being done on haul roads to control fugitive emissions. Hedge of sturdy woody shrubs along the mine will be created. The removal or picking of any protected/unprotected plant will not be permitted. Proper traffic management including ban on use of pressure horns; restriction on use of music in vehicles at high volume as well as regular maintenance of vehicles shall be insisted to minimize disturbance from vehicular movement. Educational and awareness programmes for mine workers will be arranged.

Occupational health & safety & public health & safety.

Regular water sprinkling on haul roads. Dust mask is being provided to the workers. Periodical medical examinations will be carried out for the workers as per Norms. Medical records are being keep maintained. Medical facilities to the workers. Any early symptom of diseases, if observed, such workers will be taken off in the dusty atmosphere and suitable employed elsewhere. Personal Protective Equipment’s will be provided to the workers. Vocational Training will be provided to the workers. Safety of the employee during mining is being taken care as per Mine Regulations.

Vocational Training will be provided to the workers. A well-equipped first aid facility will be made available round the clock in ML area. By Project authority.

Waste management

Waste generated from the mining will be backfilled to the worked out pit

Regular monitoring by project authorities.

Page 124: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

TABLE 9.2: COST ESTIMATES OF EMP IMPLEMENTATION

The below table give overall investment on the environmental safeguards and

recurring expenditure for successful monitoring and implementation of control

measures.

(Investment and recurring cost)

S. No. Capital cost (in Rs.) Annual recurring cost (in Rs.)

Existing Proposed Existing Proposed 1 Pollution Control

(Garland Drain, Water sprinkler, Wet drilling)

- 3,00,000 - 1,00,000

2 Pollution Monitoring (Air, soil, Water, Noise)

- 5,00,000 - 1,00,000

3 Occupational Health - 5,00,000 - 1,00,000

4 Green Belt - 2,50,000 - 50,000

Total 15,50,000 3,50,000

Total investment on environmental improvement works is envisaged Rs.

15,50,000 and recurring expenditure during the stage of production is Rs.

3,50,000 per year.

9.2 GREEN BELT DEVELOPMENT

Green belt development is the most effective pollution control measures. Trees play

vital role in keeping the ground level concentration in control within the project and

its surrounding premises and also in preventing the horizontal dispersion of the

pollutants to the surrounding areas. They are very effective in trapping the pollution

causing agents viz. dust and gaseous pollutants. The green belt is being proposed for

following objectives.

Arresting of fugitive dust emission.

Noise pollution control.

Prevention of soil erosion.

Balancing eco environment.

Aesthetics.

The action plan for green belt development is given in the following table:

Page 125: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

TABLE 9.3: STAGE WISE PLANTATION

Year

Plantation barrier

Backfilled area Plantation in

lease area Dump area Total

Area (Hect.)

Trees Area

(Hect.) Trees

Area (Hect.)

Trees Area (Ha.)

Trees Area

(Hect.)

Existing -- -- - - 15.98 -- - - 15.98

I 0.051 51 - -

- - - -

II 0.051 51 - - - - - -

III 0.051 51 - -

- - - -

IV 0.051 51 - - - - - -

V 0.051 51 - -

- - - -

Up to 5th year

2.5500 255 - -

- - - - 2.550

End of life of mine

0.99 99 17.23 --

- - - - 18.22

Total 3.540 3540 17.23 --

15.98 - - - 36.75

The yearly financial expenditure for green belt development is given in the table 9.2. It

is evident that at the end of plan period green belt will be developed in 84 % of the total

lease area.

Protection of Plantation Sites

Plants will be protected from diseases by the application of proper pesticides. Soil

workings, manuring etc. will be done whenever necessary. Plants will be protected by

providing fencing and proper watch and ward.

About 15.98 ha area has already planted within lease area.

TABLE 9.4: PROPOSED PLANTATION

S. No

.

SPECIES SCIENTIFIC NAME

LOCAL NAME

1 Azadirachta indica Neem 2 Dalbargia sisso Shisham 3 Cassia fistula Amaltas 4 Accacia nilotica Babbol

Page 126: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

9.3 SOCIO ECONOMIC ENVIRONMENT

Based on the findings of the socioeconomic study, CSR proposal has been made by the

PP and it is aimed at the socio-economic up liftmen of the area. The provisions made are

particularly in the area of habitat, health and education, training programme of rural

women & men provide the kit for employment generation. The proposal also contains

budgetary provision of washroom facilities for girls in nearby schools.

Based on findings Pipakhedi village has been taken for CSR activities.

TABLE 9.5: COST OF CSR ACTIVITIES

S.No Activity Detail of Educational Institute

Facilities provided CSR Fund

1 Education Facility in

Pipakhedi village

(within 5 km)

Distance 1.0 Km.

Primary school in Pipakhedi *Washroom for girls.

*Schools shoes & stationery distribute for the poor student. *Provide drinking water

facility

Rs 75,000.

Activity Proposed Detail Training Fund

2 Skill Development\

Youth

Sport camp organization for youth

at Hathiya kheri Village ( Football,

Cricket match, volleyball,)

Rs. 50,000

Health & Sanitation

(within 5 km from the

site)

Contact person Proposed facilities CSR Fund

3 Sub Health Centre

(Distance 1.0 km.)

Smt. Mamata

(ANM)

- waste disposal facility

- Medical camp organization

-Medicine distribution

Rs. 75,000

Total 2.0 Lack

Page 127: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

9.4 OCCUPATIONAL SAFETY & HEALTH

The medical histories of all employees will be maintained in a standard format.

Thereafter, the employees are subjected to medical examination on annual basis.

The said medical examination keep upgrading the database of medical history

of the employees.

Safety of employee during mining operation and maintenance of mining

equipment will be taken to avoid any adverse effect on the health of

workers.

To avoid any adverse effect on the health of workers due to dust, heat, noise

sufficient measures will be provided in the mining project. These include:

Provision of rest shelters for mine workers with amenities like

drinking water, washrooms etc.

Provision of personal protection devices to the workers.

Rotation of workers exposed to noisy areas.

Dust suppression on haul road.

First-aid facilities in the mining area.

Additionally, the health status of workers in the mine shall be regularly

monitored under an occupational surveillance programme. Under this

programme, all the employees will be subjected to a details medical

examination at the time of employment. The medical examination covers the

following tests.

General Physical Examination and Blood Pressure.

X-ray Chest and ECG.

Detailed Routine Blood and Urine examination.

Page 128: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

BUDGETARY PROVISION FOR MINE WORKER

PP will arrange all basic facilities including required infrastructure. First Aid box,

Toilets as per the provisions of Mines Rules shall be constructed and maintained.

There will be no residential colony proposed to be set up in the lease area.

TABLE 9.6: BUDGETARY PROVISION FOR WORKERS

Facility Provided for

Labourers

Total amount per year

Drinking water By Tanker 30,000/-

First Aid Box 20,000/-

Rest Shelter 50,000/-

Washroom 20,000/-

Safety shoes 75,000/-

Hand Gloves 75,000/-

Dust Mask 50,000/-

Ear Plugs / Muffler 30,000/-

Helmet 50,000/-

Insurance 1,00,000

Total 5,00,000

1) Rest shelters: Rest shelters already present there mine site. Maintenance will

be every year.

2) First Aid Box: A first aid box with proper equipment will be provided as per

mines act and Mines Rule.

3) Washroom: Washrooms will be provided separately for male and female

worker as per rule.

Page 129: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

4) Drinking Water: Clean potable drinking water will be provided as per Mines

Rule.

TRAINING & HUMAN RESOURCES DEVELOPMENT

The training of mine personnel will be conducted regularly with respect to

environmental protection. Training facilities will be envisaged in the mine site.

Specialized courses will be arranged for afforestation, re-vegetation,

reclamation etc. in various Institutes and organizations.

Training and human resource development is not a single time function but

a continuous requirement to up-date and improve the skills of employees.

Hence, in addition to whatever statutory training is required, the company

looks forward to continue the process by way of participative training of the

personnel in various workshops, training courses organized by manufactures

/professional agencies. Budgetary provision for occupational health and safety of

the worker is given in the table 9.2.

9.5 TOP SOIL AND WASTE MANAGEMENT

The waste as overburden in the area is top soil & fractured lime stone. The soil

cover in the area from 3.0m and fractured Limestone (Waste) varies from 27m top

soil will be spread over the backfilled area for a forestation. About 1370730 cum

of overburden & fracture waste generate will be during plan period. Waste

generated will simultaneously be used for the backfill purpose of the mine out pit.

TABLE 9.7: PROPOSED WASTE GENERATED FOR MINING ACTIVITY

S. No Year I II III IV V Total

1. Fracture +

mineral

waste (MT)

8024 8024 8024 8024 8024 402120

2. Over

Burden(MT)

1026432 712800 712800 712800 712800 3877632

3. Total Waste

(1+2) MT

1106856 1106856 793224 793224 793224 4279752

4. In Cum 461190 330510 330510 330510 330510 1370730

5. Swell

volume

(Cum)

553428 396612 396612 396612 396612 2139876

Page 130: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Generation of top Soil- Top soil 3m is available shall be excavated with the

mining which shall be backfill in the pit.

Proposed to stack the sub grade material- The Sub grade mineral shall be used

in mixing with high grade to make avg. grade makeable. The generation shall be-

Year I II III IV V

Sub Grade Mineral (MT) 16084 16084 16084 16084 16084

Sub Grade Mineral M3 5957 5957 5957 5957 5957

Swell volume (M3) 7148 7148 7148 7148 7148

Avg. height of Dump 6m 6m 6m 6m 6m

***********

Page 131: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

CHAPTER – X

SUMMARY & CONCLUSION

10.1 INTRODUCTION

This report is prepared to evaluate the environmental impacts of the project

namely Satalkhedi-Pipakhedi limestone mine(Building stone) over 43.24 ha Pvt.

land, near village – Satalkhedi-Pipakhedi, Tehsil – Ramganj Mandi, District – Kota

(Rajasthan) in line with the requirements of EIA notification SO 1533(E) dated

14.9.2006 and amendments made thereof.

10.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT:

This is a mining project of Satalkhedi-Pipakhedi limestone (Building Stone) Mine,

near village - Satalkhedi-Pipakhedi, Tehsil – Ramganj Mandi, District – Kota

(Rajasthan) over 43.24 ha Pvt. land.

Originally the mining lease (Area 83.87ha.) was granted in favour of Shri Ganga

Ram Bairwa S/o Sh. Kalu Ram Bairwa vide letter No-9(4) Khan/Group/-2/92 in

dated 13/04/92 for 10 years (20-01-1992 to 19-01-2002). The lease deed was

executed on 30/05/1992 and registered on dated 30/06/1992

Lease renewal order was given for 10 years on dated 20.01.1992 to 19.01.2002

after that it has extended up to the 19.01.2012.

About 40.63 ha lease area was surrendered on dated 20.01.2001.

After the death of Ganga Ram Bairwa the lease was Nominated in favour of Shri

Pankaj kumar Bairwa S/o Shri Swaroop Chand Bairwa.

And now the lease has been renewed up to the 19.01.2022.

Project proponent:

Sh. Pankaj Kumar Bairwa S/O - Sh. Swaroop Chand, R/O -Satalkhedi, Tehsil -Ramganjmandi Dist- Kota, Rajasthan

Page 132: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

10.3 LOCATION OF PROJECT

State : Rajasthan

District : Kota

Tehsil : Ramganjmandi

Village : Satalkhedi, Pipakhedi

The lease area falls on survey of India Toposheet No. 45P/14 & 54 D/2 and is

situated between:

Latitude N Longitude E

24°00'00"N to 24°39'30"N 76°12'96.0"E to 75°59'55.7"E

10.4 SIZE OR MAGNITUDE OF OPERATION:

It existing mine and mineral is being proposed by opencast method. It is proposed

to produce 3, 21,699 TPA (ROM) from 43.24 ha.

10.5 MINING METHOD

Mine is being developed by opencast mining with drilling and blasting. The

mineral is lying on the sub surface therefore open cast mining is obvious choice.

The bench parameters shall be for mineral-

1. Height-6m to 9m

2. Width – more than 6m-9m.

The bench parameters shall be for O/B/Fracture-

1. Height-6m- 9m

2. Width – More than 6-9m.

10.6 EMPLOYEE DETAIL: About 109 workers will be required.

10.7 MACHINERIES DEPLOYED:

Type of Machinery

Nos. Bucket Capacity in Cum.

Motive Power

Make H.P.

Dumper 6 10 tonner Diesel Tata 119 HP Water pump 1 - Diesel Local -

Compressor 1 75 CFM - Local - Jack Hammer 2 32 mm Diesel Local - Excavator 2 1.2 m3 Diesel Local - JCB 1 - Diesel Escort - Jiri Cutting m/c 8 - - --- - DG Set 2 125Kva Kriloskar

Page 133: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

10.8 DESCRIPTION OF ENVIRONMENT

TOPOGRAPHY: The area is having hilly topography. The highest elevation of the

mining lease area is 340 mRL and lowest elevation is 337 mRL. No any seasonal or

perennial nallah exist in lease area. Three river name Ahu, Amjar, Pasadi nadi

flowing in Study area.

Land use of Lease area.

Note- About 15.9800 ha area has been already planted within lease for full fill

33% plantation as per ToR compliance. At the end of mine life about 20.77 ha area

will be planted which includes 3.5400 Ha area will be planted on statuary barrier

(7.5 Meter) & 17.2396 ha area will be backfill planted. About 6.4804 ha area will

be converted as water storage.

SOIL OF THE AREA: Analysis of soil in the area show that soil of the area is

slightly alkane in nature & NPK is poor in soil.

AVAILABLE GROUND WATER IN AREA: Analysis of different Samples of ground

water shows that all parameter are well within limit.

S. No. Particulars Pre Operational

(In Ha)

Operational (In Ha)

Post operational

(In Ha) A) Mining Activity 1 Mining pits 8.5215 10.5710 0.00 2 Road & building 2.3750 2.3750 0.00

3 Plantation on statuary barrier

0.0000 2.5500 3.5400

4 Mineral stack 1.5420 1.9540 0.0000 5 Water storage 1.2010 1.2010 6.4804

6 Reclamation & Backfilled Plantation

5.9800 5.9800 17.2396

7 Plantation on remaining lease area

15.9800 15.9800 15.9800

B) Remaining virgin land

7.6405 2.6290 0.000

Total 43.24 43.24 43.24

Page 134: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

AMBIENT AIR QUALITY MONITORING:

Sampling locations were established for ambient air monitoring in and around the

core zone within a radius of 10.0 km, to study the present quality of the air. From

the baseline monitoring result, it is observed that the monitored parameters

(PM10, PM2.5, SO2&NO2) are within the permissible limits as per NAAQS, 2009

during the study period.

NOISE MONITORING OF AREA: During the study period ambient noise level were

monitored and which are within CPCB Noise standard.

BIOLOGICAL ENVIRONMENT: Lease area having scattered vegetation Vilayati

babool, Babool & Aakra are mainly seen there.

SOCIO ECONOMIC ENVIRONMENT: Study has been conducted through filled survey

and results reviled that area is undeveloped, literacy rate is poor, unemployment.

Health and sanitation problems.

10.9 ENVIRONMENT MONITORING CELL

The monitoring will be taken up by the supervisory officers of the mine. Mine

manager will be in charge of the environment cell and will be responsible for the

effective functioning of the monitoring programme. The environmental data will

be monitored by an outside agency. Monitoring will be done twice in year.

10.10 ENVIRONMENT MANAGEMENT PLAN

At the end of mine 6.4804 Ha area will be used as water storage & about 17.239 ha

mine out area will used for backfill plantation.

Air pollution management:

1. Water sprinkling will be done on haul road.

2. Plantation will be done along lease boundary & with the lease area.

3. All vehicles will be regularly maintained.

4. Air quality will be regularly monitored.

Water pollution management.

1. Water conservation measures have been proposed in the project to recover

the rain water.

2. Suitable rainwater Storage is proposed at post operational phase.

3. No waste water will be generated & discharge to any water body.

Page 135: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Noise & vibration Pollution Management:

1. Proper plantation along road side.

2. Proper maintenance of Noise generating Machinery.

3. Provide PPE to workers (Ear muffs).

Solid waste management:

OB & Scree generated from mine site will be backfilled in pit area. Sub grade

material will be stacked at earmarked site.

Green belt Development:

Total plantation by the end of the mine life will be over 36.75 Ha (Total lease

area 43.24 ha) including 3.5400 ha area will be planted on statuary barrier &

17.23 ha area will be planted on mine out backfill area. At present about 15.98 ha

area has been already planted. So the total 84 % area will be planted.

Socio- Economic Environment

The proposed project would aid in the overall Social and economic development

of the region. Mine project will enhance the economic status. Apart from

employment this project shall provide medical & educational facilities to the

employees and people living within the study area.

Occupational health & safety measures

The medical histories of all employees will be maintained as per mines rules,

1955. Thereafter, the employees will be subjected to medical examination on

annual basis. Apart from that rest shelters, potable drinking water, wash room

will be provided, Personal protective devices will be provided to the workers.

Amount of Rs 3.5 lac will be spend per year for EMP

Amount of RS 2.0 lac will be spent for CSR/year

*********

Page 136: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

CHAPTER – XI

CONSULTANTS ENGAGED

(RQP/UDP/354/2009/B)

The consultant engaged for the preparation of the EIA/EMP of the project is

M/s Udaipur Min-Tech Pvt. Ltd. The information about the company with

address is as follows:

Page 137: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 138: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Questionnaire

Page 139: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

PROFORMA FOR ENVIRONMENTAL APPRAISAL OF MINING PROJECTS

(MINING SECTOR PROJECTS)

1. General Information

(i) Name of the project : Chechat Limestone (Building Stone) Mine

Name of the proponent : Sh. Pankaj Kumar Bairwa Mailing Address : R/o -Satalkhedi, Tehsil -Ramganjmandi Dist- Kota, Rajasthan-

E-mail :

Telephone :

Fax No. :

(b) Objective of the project : Mining of Limestone (Building Stone)

Note 1: All information to be given in the form of Annex/s should be properly

numbered and form part of reply to thisproforma.

Note 2: Please enter √ in appropriate box where answer is Yes / No

Note 3: No abbreviation to be used - Not available or not applicable should be

clearly mentioned.

Note 4: Core zone is the mining lease area.

Buffer zone in case of ML area up to 25 ha.is to be considered as 5 km all

around the periphery of the core zone and for ML area above 25 ha. an

area 10 km all around the periphery of the core zone.

Note 5: Adopt Scoping process in carrying out EIA study.

Note 6: Please indicate source of data.

Page 140: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

(c) Location of mine (s)

Village(s) Tehsil District State

Satalkhedi-

Pipakhedi

Ramganj Mandi Kota Rajasthan

(d) Does the proposal relate to

(i) New mine Yes No

(ii) Expansion Yes No

Increase in ML area Yes No

Increase in annual

production Yes No

(iii) Renewal of ML Yes No

(iv) Modernization Yes No

(e) Site Information

(i) Geographical Location

Latitude

Longitude

Survey of India Topo sheet number

Elevation above Mean Sea Level

24°00'00"N to 24°39'30"N

76°12'96.0"E to 75°59'55.7"E

45P/14 & 54

D/2 Lowest 337 mRL- Highest 340 mRL

Page 141: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Total mining lease area (in ha.)

(ii) Dominant nature of terrain

Flat Yes No

Undulated Yes No

Hilly Yes No

2. Land usage of the mining lease area (in ha.)

(a) Agricultural

(b) Forest

(c) Waste land

(d) Grazing

(e) Surface water bodies

(f) Others (Pvt. Land)

Total

Nil

Nil

Nil

Nil

Nil

43.24 Ha.

(Forest&govt.waste.lan

d) 43.24 Ha. (Pvt. Land)

43.24

Page 142: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

3. Indicate the seismic zone in which ML area falls. In case of zone IV & V, details of

earth quakes in last 10 years.

(a) Severity (Richter scale) - Zone II

(b) Impact i.e. Damage to

Life Yes No

Property Yes No

Existing mine Yes No

Page 143: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

4. Break-up of mining lease area (in ha.) as per approved conceptual plan:

Purpose Mining Lease Area Total Area acquired Area to be acquired

Government Private Government Private Government Private

Forest Others Agri. Others Forest Others Agri. Others Forest Others Agri. Others

1. Area to be excavated - - - - - - - - - -

2. Storage for top soil - - - - - - - - - - -

3. Overburden / Dumps - - - - - - - - - - - -

4. Mineral storage - - - - - - - - - - - -

5. Infrastructure (Workshop, Road & Building)

- - - - - - - - - - - -

6. Roads - - - - - - - - - - - -

7. Railway - - - - - - - - - - - -

8. Green Belt - - - 36.75 36.75 - - - 36.75 - - - -

9. River - - - -- -- - - - -- - - - -

10.Effluent treatment plant - - - -- -- - - - -- - - - -

12. Remaining land - - - -- -- - - - -- - - - -

13. Other (Water reserve) - - - 6.480 6.480 - - - 6.480 - - - -

TOTAL - - - 43.24 ha 43.24 ha - - - 43.24 ha - - - -

Note- About 15.9800 ha area has been already planted within lease for full fill 33% plantation as per ToR compliance. At the end of mine life about 20.77 ha

area will be planted which includes 3.5400 Ha area will be planted on statuary barrier (7.5 Meter) & 17.2396 ha area will be backfill planted. About 6.4804

ha area will be converted as water storage.

Page 144: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

5. Township (outside mining lease)

(a) Total area (in ha)

(b) No. of dwelling units

(c) Distance from mine site

6. Distance of water bodies (in km)

Distance

from

River Bank * Other Water

bodies *

Sea / creek / lake /

nalla etc. (specify)

Mining lease boundary

Amjar Nadi- 9.3 km in NE , Ahu Nadi-

6.4 km in SE, Psadi Nadi 7.5 km in SW

direction from mine site.

-

Ancillary facilities

-- --

[* From highest flood line / high tide line]

7. For projects falling within the Coastal Regulation Zone (CRZ) -

Whether the mineral to be mined is of rare

nature and not available outside CRZ? Yes No

if yes, annex a scaled location map showing low tide line (LTL), high tide line (HTL) duly demarcated by one

of the authorized agencies* [ *Director, Space Application Centre, Ahmedabad: Centre for Earth Sciences

Studies, Thiruvananthapuram: Institute of Remote Sensing, Anna University, Chennai: Institute of Wetland

Management & Ecological Designs, KolKata: Naval Hydrographers’s Office, Dehradun: National Institute of

Oceanography, Panjim, Goa: and National Institute of Ocean Technology, Chennai], boundary of mining

lease area, distance of ML area from LTL and HTL CRZ boundary and CRZ classification of the project area as

per the approved Coastal Zone Management Plan, and settlements, sand dunes, mangroves, forest

land/patches, turtles breeding and nesting sites etc., if any, in the project area.

-

-

-

Not Applicable

Page 145: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

8. Indicate aerial distance from the periphery of core zone / area from the periphery

of the buffer zone to the boundary of following (up to 10 km):

S.

No.

Areas Name Aerial distance from

(in km.)

Core * Buffer*

Zone

1. National Park / Sanctuary None Not Applicable

2. Biosphere Reserve / Tiger

Reserve / Elephant Reserve

/ any other Reserve

None Not Applicable

3. Forest (RF / PF /

unclassified)

Sr.

NO.

RESERVED &

PROTECTED

FOREST

DIRECTION DISTANCE

1 Kuttepur PF NW 6.1 KM.

2 Suket RF E 7.0KM

3 Salvad RF NE 3.9KM

4. Habitat for migratory birds Not Applicable

5. Corridor for animals of

schedule I & II of the

Wildlife (Protection) Act,

1972

Not Applicable

6. Archaeological sites

* Notified * Others

None Not Applicable

7.

Defence Installation None Not Applicable

7. Industries / Thermal Power

Plants

None Not Applicable

8. Other Mines

Two Other mines present in the 500m radius in the lease

area and covered 20.859 ha area around periphery.

9. Airport Indore Airport 251 km from mine

Page 146: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

site

10. Railway Lines

Ramganj Mandi 4.9 km in SW from lease

area

11. National / State Highways

SH-9 B

NH-12

2.0 km in S direction

8.0 NE direction

[* Buffer zone in case of ML area up to 25 ha. is to be considered as 5 km all around the periphery of the

core zone and for ML area above 25 ha. an area 10 km all around the periphery of the core zone].

9. Description of flora & fauna separately in the core and buffer zones.*

[* Consult the Wildlife (Protection) Act, 1972 as amended subsequently and list species with (1)

Common name (2) Scientific name and (3) under which schedule of the Wildlife (Protection) Act

the identified species fall. Get the list authenticated by an Expert in the field / credible scientific

institute / University / Chief Wildlife Warden office. Information to be based on field survey.]

A. Flora Core Zone Buffer Zone

1. Agricultural crops Ni Soybean, Maize, Black Gram,

Green Gram, Lentil, Wheat,

Jawar, Groundnut.

2. Commercial crops Nil Soybean, Oilseeds & Mustard.

3. Plantation Orange tree, Neem, babool,

Imli Trees, Shrubs & herbs

Page 147: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

4. Natural vegetation /

forest type

Prosopis juliflora

Zizyphus nummularia

Calotropis procera

Echinops echinatus

Acacia nilotica

Azadirachta indica

Trees

Acacia leucophloea

Acacia nilotica

Aegle marmelos

Ailanthus excels

Albizia lebbeck

Albizia procera

Anogeissus latifolia

Azadirachta indica

Bauhinia racemosa

Bombax ceiba

Cassia fistula

Cassia siamea

Dalbergia sissoo

Emblica officinalis

Ficus benghalensis

Ficus religiosa

Mangifera indica

Polyalthia longifolia

Prosopis juliflora

Syzygium cumini

Tamarindus indica

Zizyphus mauritiana

Page 148: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Phoenix sylvestris

Page 149: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Butea monosperma

Shrubs

Annona squamosa

Argemone Mexicana

Calotropis gigantean

Calotropis procera

Ipomoea fistulosa

Jatropha curcas

Lantana camara

Bougainvillea spectabilis

Herbs

Cassia tora

Datura inoxia

Parthenium hysterophorus

Tribulus terrestris

Tridax procumbens

Zizyphus nummulaira

Echinops echinatus

Grass

Cymbopogon martini

Cynodon dactylon

Sida cordifolia

Cenchrus ciliaris

Page 150: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

5. Grass lands None None

6. Endangered species None None

7. Endemic species None None

8. Others (Specify) None None

B. Fauna

1. Total listing of

faunal elements

Funambulus pennanti

Herpestes edwardsi

Lepus nigricollis

Hanuman langur

Rattus rattus

Rousettus leschenaulti

Hemidactylus brooki gray

Hemidactylus maculates

Acridotheres ginginianus

Acridotheres tristis

Corvus macrorhynchos

Columba livia

Boselaphus tragocamelus

Canis aureus

Funambulus pennanti

Herpestes edwardsi

Lepus nigricollis

Hanuman langur

Rattus rattus

Rousettus leschenaulti

Sus scrofa

Hemidactylus brooki gray

Bufo bufo

Ptyas mucosus

2. Endangered species None None

3. Endemic species None None

4. Migratory species None None

5. Details of aquatic

fauna, if applicable

None None

Page 151: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

10. Details of mineral reserves (as per approved Mining Plan)

Quantity (in MT)

(a) Proved

(b) Indicated

(c) Inferred

(d) Mineable reserves

11. Major geological formation / disturbances in the mining lease area (a) Geological maps submitted Yes No

(b) Geological sections submitted Yes No

(c) Contour map submitted Yes No

(d) Whether the presence, if any,

Noted of

(i) Faults Yes No

(ii) Dykes Yes No

(iii) Shear Zone Yes No

(iv) Folds Yes No

(v) Other weak zones Yes No

6098022

-

--

6606191.7

Page 152: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

(e) Source of data (Indicate)

12. Production of mineral(s) and life of mine

(a) Rated capacity of mine mineral wise (MT / annum)

(b) Life of mine at proposed capacity (Years)

(c) Lease period (Years)

(d) Date of expiry of lease (D /M /Y)

(e) Indicate in case of existing mines

(i) Date of opening of mine

(ii) Production in the last 5 years 1syear 5th year

from year 2010 to year 2015

in million tonnes.

(iii) Projected production for the next 1th to 5th year

5 years in million tonnes.

DETAIL OF YEAR WISE PROPOSED PRODUCTION

Year Saleable

Mineral

tones

Waste

generated from

the total

excavation

(MT)

Sub grade

in MT

Over

burden

form OB

benches

tonnes

Over

burden+

mineral

waste

tonnes

Stripping

ration

Mineral:

waste

I 225189 80424 16084 1026432 1106856 1:4. 915

II 225189 80424 16084 712800 793224 1:3.522

III 225189 80424 16084 712800 793224 1:3.522

IV 225189 80424 16084 712800 793224 1:3.522

321699 TPA

21 year

19/01/2022

30 year (20/01/1992 to 19/01/2022)

20/01/1992

By 1) Survey & Field works

32, 75,635 Sq feet 27,71,255 Sq feet

3,21,697 TPA (ROM) 3,21,697 TPA (ROM)

Page 153: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

V 225189 80424 16084 712800 793224 1:3.522

Total 1125945 402120 80420 3877632 4279752

(iv) Whether mining was suspended after Yes No Opening of the mine?

If yes, details thereof including last production figure and reason for the same.

(f) Whether plans & sections provided? Yes No

13. Type and method of mining operations

TYPE METHOD

Opencast √

Manual

Underground Semi-mechanized

Both Mechanized √

14. Details of ancillary operations for mineral processing

DETAIL OF MACHINERY DEPLOYED OR TO BE DEPLOYED

Type of Machinery

Nos. Bucket Capacity in Cum.

Motive Power

Make H.P.

Dumper 6 10 tonner Diesel Tata 119 HP Water pump 1 - Diesel Local -

Compressor 1 75 CFM - Local - Jack Hammer 2 32 mm Diesel Local - Excavator 2 1.2 m3 Diesel Local - JCB 1 - Diesel Escort - Jiri Cutting m/c 8 - - --- - DG Set 2 125Kva Kriloskar

Not Applicable

Page 154: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

15. Mine details

(a) Opencast mine

(i) Stripping ratio (mineral in tonnes to over burden in m3)

(ii) Ultimate working depth (in m bgl)

(iii) Indicate present working depth in case of

Existing mine (in m bgl)

(iv) Thickness of top soil (in m.)

Minimum

Maximum

Average

(v) Thickness of overburden (in m.) No-O/B Not applicable

Minimum

Maximum

Average

(vi) Mining Plan

Height and width of the bench in Overburden / waste. Height & width of the bench in ore body /

coal seam.

Proposed inclination / slope of the sides of the opencast mine (separately for overburden, coal / ore and overall slope of the pit sides) both while operating the mine as well as at the time of closure of the mine.

37mbgl

1.0

3.00

2.00

1:3.522

--

1.0

3.0

2.0

Height-6m- 9m & Width –

more than -6m- 9m.

--

450

Page 155: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Whether transverse sections across the Yes No opencast mine at the end of fifth year

and at the end of the life of the mine have been submitted? (vii)Type of blasting, if any, to be adopted.

(b) Underground mine - Not applicable

(i) Seam / Ore body Min. Depth (m) Max. Depth (m) Avg. thickness (m)

Rate of dip Direction of dip

in degree

(ii) Mode of entry into the mine

Shaft

Adit

Incline

Small blasting with low charge of

holes

Page 156: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

(iii) Details of machinery

On surface

At Face

For transportation

Others

(iv) Method of stopping (metalliferrous mines)

Open

Filled

Shrinkage

Caving

Combination of above

Others (Specify)

(v) Extraction method

Caving

Stowing

Partial extraction

Page 157: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

(vi) Subsidence

Predicted max. subsidence (in m)

Max. value of tensile strain (in mm/m)

Max. slope change (in mm/m)

Whether identified possible subsidence Area superimposed on Surface Yes No Plan has been submitted?

Major impacts on surface features like natural drainage pattern, houses,

Buildings, water bodies, roads, forest,

etc.

Salient features of subsidence Management (monitoring and control).

16. Surface drainage pattern at mine site (Figure-3.4)

(a) Whether the pre-mining surface drainage plan Yes No

Submitted?

(b) Do you propose any modification / diversion Yes No

in the existing natural drainage pattern at any

stage? If yes, when. Provide location map

indicating contours, dimensions of water body to be

diverted, direction of flow of water and proposed

route / changes, if any i.e. realignment of river / nallah /

any other water body falling within core zone and

its impact.

Page 158: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

17. Embankment and / or weir construction - Not applicable

(a) Do you propose, at any stage, construction of

(i) Embankment for protection against flood Yes No

(ii) Weir for water storage for the mine? Yes No

(b) If so, provide details thereof.

( C) Impact of embankment on HFL and settlement

around.

(d) Impact of weir on downstream users of water.

18. Vehicular traffic density (outside the ML area)

Type of vehicles No. of vehicles per day

(a) Existing

(b) After the proposed activity

(c) Whether the existing road Yes No

Network is adequate? If no, provide details of alternative proposal?

19. Loading, transportation and unloading of mineral and waste rocks on surface:

(a) Manual Yes No

(b) Tubs, mine cars, etc. Yes No

LMV/HMV

350/200

400/220 LMV/HMV

Page 159: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

(c) Scraper, shovels, dumpers / trucks. Yes No

(d) Conveyors (belt, chain, etc.) Yes No

(e) Others (specify).

20. Mineral(s) transportation outside the ML area

Qty. (in TPD) Percentage (%) Length (in km)

(a) Road

(b) Rail

(c) Conveyors

(d) Rope way

(e) Water ways

(f) Pipeline

(g) Others (Specify)

Total

1072

1072

100

100

Excavator

Page 160: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

21. Baseline Meteorological and Air Quality data- EIA & EMP Report enclosed

(a) Micro-meteorological data

[Continuous monitoring through autographic instrument for one full season other than monsoon]

(i) Wind rose pattern for one full season (16 points of compass i.e. N, NNE, NE, ---) based on 24-hourly data. For coastal area also furnish

day-time and night time data.

Day time- Day time wind direction max. towards N to S

Night time- 24 – hours period from N to S

(ii) Site specific monitored data

Month

Temperature (°C) Relative Humidity

(%)

Prominent wind

speed(Km./Hr.)

Max. Min. Max. Min. Max. Min.

March, 16 38.2 13.0 78.0 20.0 16 0.2

April, 16 44.6 19.0 76.0 16.0 22 0.4

May, 16 46.6 24.2 74.0 14.0 32 0.6

* 24-hour’s rainfall should be reported from 08:30 hrs. IST of previous day to 08:30 hrs.IST of the day. * Rainy day is considered when 24 hrs. rainfall is 2.5 mm.

** Visual observations of cloud cover should be recorded four times a day at regular intervals.

(iii) Indicate name and distance of the nearest IMD meteorological Station from which climatological data have been obtained for

reporting in the EIA report, if any.

Page 161: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

(b) Ambient air quality data* (RPM, SPM, SO2, and NOx)

[*Monitoring should be carried out covering one full season except monsoon – same season as in 21 (a) (i)]

[*Frequency of sampling: Sampling to be done twice a week for the entire season 24 hourly for SPM & RPM. For gaseous pollutants 24- hourly data be given irrespective of

the sampling period. ]

(i) Season and period for which monitoring has been carried out.-Summer season period (March to May 2016)

(ii) No. of samples collected at each monitoring station follows-

Name of monitoring equipment used

PM2.5 PM10 SO2 Nox Pb**

High volume High volume High volume -- Equipment sensitivity --

Permissible AAQ standard (CPCB) R I S

60 100 80 80 --

60 100 80 80 --

60 100 80 80 --

Monitoring Location

No. of Samples Drawn

Category* (R, I, S)

Min. Max. 98%

Min. Max. 98%

Min. Max. 98%

Min. Max. 98%

--

Core zone

24 Mining 20.23 25.84

25.34 58.49

78.70 77.12 BDL 5.05 4.94 3.19 7.14 6.99 --

Buffer zone

500 D/w 24 - 19.75 25.96 25.44 58.80 74.94 73.44 BDL 4.84 4.74 3.05 6.37 6.24 Pipakheri 24 - 19.48 25.11 24.60 59.54 75.47 73.96 BDL 5.15 5.04 3.1 7.91 7.75 --

Satalkheri 24 R 19.67 26.09 25.56 62.18 77.47 75.92 BDL 4.91 4.81 3.02 7.98 7.82 --

Suket 24 R 19.03 25.06 24.55 61.56 78.78

77.20 BDL 4.95 4.85 3.02 8.06

7.89 --

Naharsinghi 24 R 19.62 26.01 25.48 59.45 80.77 79.15 BDL 5.05 4.94 3.02 8.26 8.09 --

Khairabad 24 R 19.48 26.01 25.48 61.72 76.65 75.11 3.00 5.05 4.94 3.25 6.96 6.82 --

Salvad khurd 24 R 19.75 25.96 25.44 58.8 74.94 73.44 BDL 5.07 4.96 3.23 8.05 7.88 --

*R = Residential; I = Industrial; S = Sensitive (Source-Primary data collected by M/s Udaipur Min-Tech Pvt. Ltd)

**Pb for mineral specific sites only.# Annex a location map indicating location of AAQ stations, their direction and distance with respect to project site.

Page 162: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

22. Stack and emission details, if any* Not applicable

Sl.

No.

Process / unit

of operation

(e.g. DG Set,

Boiler)

Height of

stack

(m)

Internal

top dia.

(m)

Flue gas

exit

velocity

(m/sec)

Emission rate (kg/hr) Heat

emission

rate from

top of

stack

(K.cal/hr)

Exhaust / Flue gas

SPM SO2 NOx CO Temp

OC

Densit

y

Specific

Heat

Volumetric

flow rate

(m3/hr.)

23. Details of fugitive emissions during mining operations* Not applicable

Page 163: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

24. Air Quality Impact Prediction (AQIP)* - Not applicable

(a) Details of model(s) used for AQIP including grid

size, terrain features, and input meteorological data

(b) Maximum incremental GLC values of pollutants based on

prediction exercise

(inμg/m3)

S. No. Pollutants

Incremental Value Ambient Air Quality Resultant Air Quality

1. PM10 0.8 78.7 79.5

2**. SO2 -- -- --

3**. NOX -- -- --

[* Question Number 22, 23 & 24 need not be filled-in for mines having ML area of 25 ha. or less.]

[**Information on item no. 2 & 3 to be provided in cases with captive power generation of 500 KVA and above]

Page 164: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

25. Water requirement (m3/day)

Purpose Avg. Demand Peak Demand

A. Mine site

1. Mine operation

2. Land reclamation

3. Dust suppression

4. Drinking

5. Green Belt

6. Beneficiation

7. Washeries

8. Fire Service

9. Others (specify)

B. Township

1. Green Belt

2. Domestic

3. Other (specify)

Nil

Nil

2.0

3.0

2.0

Nil

Nil

Nil

Nil

Nil

Nil

Nil

Nil

Nil

2.0

3.0

2.0

Nil

Nil

Nil

Nil

Nil

Nil

Nil

Total 7.0 7.0

26. Source of water supply*

S. No. Source m3/day

1 River (name) Nil

2 Ground water 7.0 KLD

3 Mine water (sump / pit) Nil

4 Other surface water bodies (specify) Nil

[*Annex a copy of sanction letter / permission from the concerned authority (Central Ground

Water Authority in case of ground water abstraction is from notified area / State Ground Water

Board in case of non-notified area / State Irrigation Department for surface water pumping) for

drawing water.]

Page 165: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

27. Lean season flow in case of pumping from river / nalla (cumecs)

28. Ground water potential of the study area

28.1. Ground water availability

(a) Range of water table (m bgl)

(i) Pre-monsoon (April/May)

Core Zone

Buffer zone

(ii) Post-monsoon (November)

Core Zone

Buffer zone

(b) Total annual replenishable recharge (million m3/ year)

By ground water table fluctuation method

By rainfall infiltration factor method

(c) Annual draft excluding estimated draft through

mine discharge (million m3/ year)

(d) Estimated draft through mine discharge (million m3/ year)

(e) Net annual ground water availability (million m3/ year)

(f) Stage of ground water development in %

-

Not Applicable

38-40m

40-42m

40-45m

45-50m

-

-

10.38BCM

125%

-

11.56BCM

Page 166: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

28.2 Water demand - Competing users of the water source

S. No. Usage Present Consumption

(m3/day)

Additional proposed

as per local plan

(m3/day)

Total

(m3/day)

Surface Ground Surface Ground Surface Ground

1 Domestic -- -- -- -- -- --

2 Plantation --- -- -- 3.0 -- 3.0

3 Industry -- -- -- -- -- --

4 Mining -- -- -- -- -- --

5 Dust

Suppression

-- -- --

2.0 -- 2.0

6 Sanitation &

Drinking --

-- -- 2.0 --

2.0

Total -- -- -- 7.0 -- 7.0

29. Water quality*

(a) Physico -chemical analysis of water at intake point **

Water quality testing is an important part of environmental monitoring. This section

details all of the physical & chemical parameters that affect the quality of water in the

environment. Physical properties of water quality include Color, Order, Turbidity and

Total Dissolved Solids. The chemical characteristics involve parameters such as pH,

Alkalinity, Chlorides, Total Hardness, Calcium, Magnesium, Sulphate, Iron, Nitrate and

Fluoride etc.

Water quality analysis result is attached as EIA/EMP report

** All parameters as per BIS 10500. Method- IS:2488.

(b) In case of existing mine, annex report on quality of water discharge

i.e. complete physico - chemical analysis** - Water quality analysis result is attached as

EIA/EMP report.

[*For non-discharging mines at least four ground water samples to be taken preferably

from downstream direction of the mine in pre-monsoon and post-monsoon periods

and analysed. For discharging mines six samples are to be analysed]

Page 167: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

**All parameters as per BIS 10500. Indicate name of Methodology, Equipment used for analysis, and Detection Level (DL) for each parameter. *** Wherever any analytical parameter is below detection level, “BDL” (Below Detection Level) should be written instead of ‘NIL’.

30. Impact on ground water regime / stream / lake / springs due to mine dewatering * -

Ground water will not be intersected during the course of mining operation,

(a) Radius of influence (in m)

[To be estimated based on analysis of pumping

test data and application of empirical formula]

(b) Whether saline water ingress will take place? Yes No

(Applicable to coastal areas)

(c) Impact on stream / lake / springs

[* Provide a comprehensive hydro-geological assessment report if the average mine

dewatering is more than 100 m3/day and or going below water table in non-monsoon period.

The report should be based on preferably latest one year pre-monsoon and post-monsoon

baseline data covering information on ground water situation, aquifer characteristics, water level

conditions (April – May and November), estimate of ground water resources, predicted impact of

the project on ground water regime and detailed remedial / conservation measures such as

artificial recharge of ground water etc. The report should be based on actual field inventory out

of existing wells, at least 30 observation wells in the buffer zone with supplementary information

from secondary sources (mention name). For estimation** of ground water resource (refer

question no. 28 above) be designated study area of the buffer zone may be sub-divided into

command and non-command areas, watershed-wise (in case of hard rock / consolidated

formations) / block-wise / mandal-wise in case of alluvial / unconsolidated formations)]

[**For estimating ground water resources in the area follow the Ground Water

Estimation Committee recommendations of 1997]

Page 168: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

31. Waste Water Management-Not applicable

Mine

(a) Daily average discharge (m3/day) from different sources

(i) Mine water discharge during

Lean period Monsoon period

(ii) Workshop

(iii) Domestic (mine site)

(iv) Beneficiation / Washeries

(v) Coal Handling Plant

(vi) Tailings pond

(vii) Others (Specify)

Total

(b) Waste water treatment plant; flow

sheet for treatment process attached. Yes No

(c) Quantity of water recycled / reused / to be recycled in

(i) Percentage

(ii) m3/day

NIL

NIL

NIL

NIL

NIL

NIL

NIL

NIL

NIL

Not Applicable

Not Applicable

Page 169: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

(d) Point of final discharge -Not Applicable

Final Point Quantity discharged (in m3/day)

1. Surface

(i) Agricultural land

(ii) Waste land

(iii) Forest land

(iv) Green belt

Not Applicable

2. River / nallah Not Applicable

3. Lake Not Applicable

4. Sea Not Applicable

5. Others (specify) Not Applicable

Total Not Applicable

(e) Users of discharge water

(i) Human Yes No

(ii) Livestock Yes No

(iii) Irrigation Yes No

(iv) Industry Yes No

(v) Others (specify)

Details of the river / nalla, if final effluent is / will be discharged (cumecs)– Not Applicable

(i) Average flow rate

(ii) Lean season flow rate

(iii) Aquatic life

Not application

Not Applicable

Not Applicable

Page 170: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

(iv) Analysis of river water 100 meters Yes No Upstream and 100 meters downstream

of discharge point submitted. Township – Not Applicable

(a) Waste water generation from

Township (m3/day) (b) Are you planning to provide sewage Yes No

treatment plant? (c) Usage of treated water 32. Attach water balance statement in the form of a flow diagram indicating source (s), consumption (Section-wise) and output.

WATER BALANCE DIAGRAM

A. WATER REQUIREMENTS FOR DUST SUPPRESSION AND PLANTATION

No out flow

No outflow No out flow

No outflow

Source: well & water tanker

Plantation-2.0 KLD Water Sprinkling 2.0 KLD

– 2KLDKLKLD

Septic tank- Soak

Drinking & sanitation-

3.0KLD

Page 171: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

33.Ambient noise level leq dB (A) 1Hour Leq

Location of Sampling Stations Noise Level

Day Time Night Time

Core zone 50.6 42.8

Buffer zone

500 D/w 49.3 41.5

Pipakheri 51.5 42.7

Satalkheri 52.2 43.1

Suket 53.7 44.3

Naharsinghi 51.8 43.5

Khairabad 52.4 41.9

Salvad khurd 51.6 42.6

34. Solid Waste (a) Top soil and Solid waste quantity and quality

Name

(Lump/fines/

slurry/

Sludge/others)

Composition Quantity

(ton/year)

Method of disposal

Mining activity*

Fractured

mineral waste

and

overburden

461190

Cum/year

(Maximum)

About 1370730 cum of overburden

& fracture waste will be generated

during plan period. Waste generated

will simultaneously be used for the

backfill purpose of the mine out pit

and planted.

Effluent Treatment

Plant (sludge)

Nil Nil Nil

Total Nil 461190

Cum/year

Nil

[* Annex layout plan indicating the dump sites.]

Page 172: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

(b) (i) Does waste (s) contain any

Hazardous/toxic substance/

Radioactive materials or Yes No

heavy metals?

(ii) If yes, whether details and Yes No

Precautionary measures

provided?

(c) Recovery and recycling possibilities. NO

(d) Possible user(s) of the solid waste.

(e) (i) Is the solid waste suitable for

Backfilling? Yes No

(ii) If yes, when do you propose

to start backfilling.

(in million m3)

Solid waste (s) Already

accumulated

(A)

To be generated

(B)

% of A & B to be

backfilled

A B

Over burden

Nil About 1370730 cum

(Plane period)

-- 100%

Others (specify)

Nil - -- --

√[

activi

ty*

[

a.

Top

Soil

[

b.

Over

burd

en

[

c.

Othe

rs

(spec

ify)

Mine out area will be backfill & planted.

[

a.

Top

Soil

[

b.

Over

burd

en

[

c.

Othe

rs

(spec

ify)

[

a.

Top

Soil

[

b.

Over

burd

en

[

c.

Othe

rs

(spec

ify)

√[

a.

Top

Soil

[

b.

Over

burd

en

[

c.

Othe

rs

(spec

ify)

[

a.

Top

Soil

[

b.

Over

burd

en

[

c.

Othe

rs

(spec

ify)

activi

ty*

[

a.

Top

Soil

[

b.

Over

burd

en

[

c.

Othe

rs

(spec

ify)

Page 173: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Land reclamation Plan–

(f) In case waste is to be dumped on the ground, indicate

(i) Associated environmental problems - NO

(ii) Number & type of waste dumps

No. of external dumps

Max. projected height of dumps (in m)

No. of terraces and height of each stage

Overall slope of the dump (degree)

Proposed reclamation measures

(iii) Section of the waste dump in relation

to the adjacent ground profile attached. Yes No

35. Fuel / Energy requirements*

[*To be furnished for mines having ML area more than 25 ha. or captive power generation of

500KVA and above]

(a) Total power requirement- Not Applicable

(in MW)

S. No. Mine Site Township Others (specify) Total

1 Present

2 Proposed /

additional

Total

-

-

-

Page 174: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

(b) Source of power (in MW)

S. No. SEB/Grid* Captive power plant DG Sets

1 Present

2 Proposed

Total

[* Annex a copy of the sanction letter from the concerned authority]

(c) Details of fuels

S.No. Fuel Daily Consumption

(TPD)

Calorific

value

(Kcals/kg)

% Ash % Sulphur

Existing Proposed

1

2

3

HSD

LSHS

Other

(specify)

300Lit. /

Day

350Lit. / Day

10800 0.01 0.25

36. Storage of inflammable / explosive materials

S. No. Name Number of

Storages

Consumption

(in TPD)

Maximum Quantity at

any point of time

1 Fuels -- -- -

2 Explosives - --- -

Page 175: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

37. Human Settlement

Core Zone Buffer Zone

Population* Nil 147485

No. of villages Nil 34

Number of

households village-

wise

Nil 30178

[* As per 2001 census record or actual survey]

38. Rehabilitation & Resettlement (R&R) Plan*

[*Provide a comprehensive rehabilitation plan, if more than 1000 people are likely to be

displaced, other-wise a summary plan]

(a) Villages falling within the study area

Villages

Number Name

Core zone Nil Nil

500 m from the blasting site (s) Nil Nil

Buffer zone 34 List enclosed in EIA/EMP report

Township site Nil Nil

(b) Details of village(s) in the core zone- Not applicable

S.

No.

Village name

Population* Average Annual

Income Tribal Others

[*As per 2011 census / actual survey]

Page 176: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

(c) Population to be displaced and / or Land oustees -Not applicable

Name of village(s) falling within Number of oustees

Land

(only)

Homestead

(only)

Land and

Homestead (both)

Mining Lease

1.

Township Site

1.

(d) Whether R&R package has been finalised?

If yes, salient features of R&R plan for oustees. Not Applicable

(i) Site details where the people are proposed to

be resettled & facilities existing / to be created.

(ii) Funds earmarked for compensation package.

(iii) Agency /Authority responsible for their

Resettlement.

(iv) Time of commencement of resettlement

of Project Affected People (PAP).

(v) Period by which resettlement of PAP will

be over.

39. Lease -wise plantation details

(a) Lease area (in ha.) -43.24 Existing mine New mine

(i) Area broken up

(ii) To be broken up

(iii) Area not to be broken-up

(b) Township area (in ha.)

8.5215 Nil

18.73 Nil

15.9800 Nil

Nil

Nil

Page 177: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

(c) Area afforested and proposed (in ha.)

Peripheral Dumps Roads Township Others

(i) Existing Nil Nil Nil Nil 15.98

(Reaming land)

(ii) Proposed 3.5400 Nil Nil Nil 17.239

(Back fill planted)

(d) No. and type of trees planted and proposed

(i) Existing- Yes

When plantation was started? Month / Year

No. of plant species planted Number saplings (per ha.)

Neem, Orange Tree, Imli, --

Survival rate % ● Avg. height

(iii) Proposed

No. of plant species to be planted Number of saplings

1. Neem 2. Shisham 3. Piple, 4. Mango

-- 80%

Page 178: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

40. Environmental health and safety

(a) What major health and safety hazards are anticipated? Inhalation of dust, benches failure, explosions.

(b) What provisions have been made/proposed to be made to conform to health and safety requirements?

Dust mask, noise- ear plugs, mufflers, safety shoes, helmets, hand gloves & all

necessary medical facilities provided & medical camp conduct periodically.

(c) In case of an existing mine-

i) Comprehensive report on health status

of the workers as under the Mines Act annexed Yes No

(ii) Mineralogical composition of RPM (dust)

Free silica-Not required because lime stone is not having free silica

content.

Chromium* (Total as well as Hexavalent)

Lead**

[* Only for Chromite mines]

[**Only for Base Metal mines]

(d) Information on radiation protection measures, if applicable.

Page 179: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

41. Environmental Management Plan

Salient features of environmental protection measures

S. No.

Environmenta

l issues*

Already practiced, if

applicable

Proposed

1 Air pollution (1) Water spraying is

being done on haul road

existing in lease area

(2) Air monitoring will be

done once in 6 month

(3) dusk mask is being

provide to worker

engaged in mining activity

(4) Afforestation activities

for controlling of dust.

The same environmental protection

measure will continue in future.

2 Water pollution The garland drain are will

be made around the

working pit.

The water pump out from

the mine is utilized in

plantation area.

The same environmental protection

measure will continue in future.

3. Water

conservation

-- Rain water storage will be

developed at the end of mine life.

4. Noise pollution Proper maintenance of

transport vehicle are

being done to minimize

noise.

Adequate silencer should

be provided in all the

truck and tractor.

The same environmental protection

measure will continue in future.

5. Solid waste /

Tailings

No No generated any waste, mine only

generated small quantity of waste

will be used in plantation.

6. Land

degradation

Minimum Land has been

used for infrastructure

and other activities.

The same environmental protection

measure will continue in future

7. Erosion & Green Belt development

around the area

--

Page 180: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Sediment minimizes the impact due

to mining actives.

8. Top soil stacked separately Top should be stacked separately

that will be used in plantation

during monsoon

9. Ground

vibration

Control Blasting with low

intensity will be practiced.

Deep hole blasting will not

be carried out.

The measure will same continue in

future.

10. Wildlife

conservation

- Not required.

11. Forest

protection

Lease area does not falls

in forest area.

Not required.

12. Others

(specify)

- --

[* As applicable]

42. Compliance with environmental safeguards (For existing units)

(a) Status of the compliance of conditions of

Environmental clearance issued by MoEF, Yes No

if any, enclosed.

(b) Status of the compliance of ‘Consent to

Operate’ issued by SPCB, if any, enclosed. Yes No

(c) Latest 'environmental statement' enclosed. Yes No

Page 181: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

43. Scoping of EIA

Whether environmental impact assessment

of the project has been carried out b Yes No

Following scoping process

If yes, a copy of scoping of EIA yes No

Annexed.

44. Mine closure

(a) Have you planned mine closure? Yes No

(b) Submitted a conceptual mine Yes No

Closure plan.

(c) If yes, indicate estimated amount for

Implementing the same (in Rs. Lakhs)

(Mining Plan with progressive Mine closure Plan has been prepared and approved by IBM)

45. Capital cost of the project (in Rs. Lacks)

(Based on latest estimate)

80 Lacks

--

Page 182: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

46. Cost of environmental protection measures

(in Rs. )

S. No. Capital cost (in Rs.) Annual recurring cost (in Rs.)

Existing Proposed Existing Proposed 1 Pollution Control

(Garland Drain, Water sprinkler, Wet drilling)

- 3,00,000 - 1,00,000

2 Pollution Monitoring (Air, soil, Water, Noise)

- 5,00,000 - 1,00,000

3 Occupational Health - 5,00,000 - 1,00,000

4 Green Belt - 2,50,000 - 50,000

Total 15,50,000 3,50,000

47. Amount earmarked for socio-economic welfare measures for the nearby villages

other than R&R plans.

S.No Activity Detail of Educational Institute

Facilities provided CSR Fund

1 Education Facility in

Pipakheri village

(within 5 km)

Distance 1.0 Km.

Primary school in Pipakhedi *Washroom for girls.

*Schools shoes & stationery distribute for the poor student. *Provide drinking water

facility

Rs 75,000.

Activity Proposed Detail Training Fund

2 Skill Development\

Youth

Sport camp organization for youth

at Hathiya kheri Village ( Football,

Cricket match, volleyball,)

Rs. 50,000

Health & Sanitation

(within 5 km from the

site)

Contact person Proposed facilities CSR Fund

3 Sub Health Centre

(Distance 1.0 km.)

Smt. Mamata

(ANM)

- waste disposal facility

- Medical camp organization

-Medicine distribution

Rs. 75,000

Total 2.0 Lack

Page 183: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

48. Public Hearing

(a) Date of Advertisement

(b) Newspapers in which the advertisement appeared

(c) Date of public hearing (DD/MM/YYYY)

(d) Public Hearing Panel chaired by & members present

(e) No. of people attended the public hearing meeting

and number of people from the lease area.

(f) Summary/details of public hearing in tabular form.-

NOTE: - Copy of minutes of Public Hearing in Hindi and English is enclosed as Annexure

No.-XI

RO, District collector, Lessee,

Consultant

06/12/2016

Dainek Bhaskar & Jabaaz Patrika

49 05

05/11/16 & 04/11/2016

Page 184: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

49. Whether the following approvals* (wherever applicable) have been obtained?

A. Site clearance from MOEF – Not Required

B. Consent to establishment from the SPCB Yes

C. NOC from Atomic Energy Division – Not Required

D. Letter of mining scheme/Plan - Yes (Annexure No. IV) Approved from IBM/DMG

E. Forestry clearance under FCA, 1980 Not Required

F. NOC Chief Controller of Explosives - Not Required

G. Commitment regarding availability of Not Required

Water and power from the concerned

State Authorities

H. In case of ML area falling in notified areas Not Required of the CGWA, NOC from them

* (Annex copies)

[* Annex copies of approvals and number them]

50. Was / is there any court case relating

to the project or related activities? - NO

If so, provide details present status.

Verification: The data and information given in this proforma are true to the best of my

knowledge and belief.

Date: Signature of the applicant* with full name & address

Place: [* Owner or his authorized signatory]

Given under the seal of organization on

behalf of whom the applicant is signing

Page 185: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

ANNEXURE

Page 186: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

ANNEXURE –I: COPY OF LEASE AGREEMENT

Page 187: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 188: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 189: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 190: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 191: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 192: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 193: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 194: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 195: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 196: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 197: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 198: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 199: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

ANNEXURE –II: COPY OF NOMINATION LETTER

Page 200: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

ANNEXURE –III: COPY OF LEASE EXTENSION LETTER

Page 201: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

ANNEXURE IV COPY OF APPROVAL LETTER OF MINING PLAN

Page 202: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

ANNEXURE –V: COPY OF KHASRA MAP, JAMABANDI& DEMARCATION

Page 203: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 204: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 205: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 206: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 207: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 208: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

ANNEXURE –VI: PREVIOUS Year’s PRODUCTION

Page 209: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 210: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

ANNEXURE –VII COPY OF ARAVALI LETTER

Page 211: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

ANNEXURE –VIII COPY OF COMPOSITE MAP

Page 212: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

ANNEXURE –IX COPY OF NOC

Page 213: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

ANNEXURE –X: COPY OF MONITORING REPORT

Page 214: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 215: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 216: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 217: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 218: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 219: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 220: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 221: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 222: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 223: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 224: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 225: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 226: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 227: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 228: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 229: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 230: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 231: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 232: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 233: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 234: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 235: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 236: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 237: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 238: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 239: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 240: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 241: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 242: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 243: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

ANNEXURE –XI: TOR LETTER

Secretariat of State Level Expert Appraisal Committee (SEAC) Rajasthan

4, Institutional Area, Jhalana Doongri, Jaipur-302004

Phone: 0141-5159661 ;E-mail: [email protected]

File No. F1 (4)/SEIAA/SEAC-Raj/Sectt/Project /Cat.1(a)B1(7243) /14-15/752 Dated:-

06.05.2016

To, Sh. Pankaj Kumar Bairwa

Chechat Dist. Kota

Email: [email protected]

Sub: Submission of Application for prior Environmental Clearance (Form I along with pre

feasibility Report) of Satalkhedi Limestone Mine over an area of 43.24 hect. (ML no. 55/91) Near

Village- Satalkhedi Tehsil- Ramganjmandi & Ditrict – Kota (Raj.) in favor of Sh. Pankaj Kumar

Bairwa Production Capacity 3,21,699 TPA. (ROM) File No. 7243

Consultant – – EIA Consultant, M/s. Udaipur Mintech Pvt. Ltd. 206, Apeksha Complex, Sec. 11,

Hiram Magri, Udaipur, Rajasthan. 313002. E-mail: [email protected]

Observation of the Committee-

Keeping in view the information contained in the documents submitted and circulated to the

members by the PP, the committee. Terms of Reference including preparation of Environment

Impact Assessment Report and conduct “Public Hearing” for As above Project Name,

Proponent Name and Consultant.

1. The study area will comprise 10 km zone around the mine lease from lease periphery and the data contained in the EIA with respect to mining operations such as conceptual pit limits, waste generation etc. should be for the life of the mine/lease period.

2. Location of other industries & mines within the study area along with their production and pollutants generated by them, estimated pollution load and cumulative impact on environment including the proposed project should be submitted. The same shall be accounted for while generating mathematical models of pollution dispersion for preparation of the EMP.

3. Year-wise production details clearly indicating the proposed highest production for the life of the mine/lease period should be submitted.

4. Details of land to be used as the designated dumping site for OB dump should be selected and proposed within the lease area as per the approved mining plan. In no case the overburden should be dumped outside the lease area, however proposal for utilization of OB for construction or other meaningful use to the extent possible may be submitted and should try to work on zero waste patterns. Details regarding quantity of solid waste

Page 244: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

generation to be estimated and details for its disposal and dump management are to be provided.

5. Land use plan of the mine lease area should be prepared to encompass pre-operational, operational and post operational phases.

6. The P.P. should provide a mining plan along-with progressive mine closer plan and implementation plan at the time of submission of application for the EC.

7. Based on the study and the points raised by the people during public hearing, the P.P. shall work out an effective plan to address the environmental, socio-economic and other issues identified during the process, with suitable funds allocation for the purpose. Further PP shall implement all commitments made during public hearing, while implementing the project.

8. Certificate regarding mine lease area not falling in the Aravalli Hills to be issued by the Mining Engineer/ Assistant Mining Engineer in the prescribed format, as per the instructions contained in the letter no. DMG/ADM/Env/EC/F11/06/17-76 dt. 17.01.2011 issued by the Director, Department of Mines and Geology, GoR, Udaipur, should be submitted.

9. List/details within 10 km radius of the mine lease area, the location of human settlement, water bodies, Reserve Forest, National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors, Tiger/Elephant reserves (existing / proposed), shall be clearly indicated giving the land use. Necessary clearance, if any, as may be applicable to such projects due to proximity of the ecologically sensitive areas as mentioned above shall be obtained from the Chief Wildlife Warden under the Wildlife (Protection) Act’ 1972 and submitted. This location map should also indicate the list and location of other mine leases existing, if any, within 10 km radius.

10. A detailed biological study for the study area [core zone and buffer zone (10 km radius of the periphery of the mine lease)] shall be carried out. Details of flora and fauna, duly authenticated, separately for core and buffer zone should be furnished based on field survey. The details regarding flora to include information regarding (a) trees, shrubs, grasses, (b) frequency, density, I V I, abundance % of species occurring on proposed site, (c) dominant species of trees, shrubs , grasses (d) endemic species, (e) threatened species, (f) rare species, (g) endangered species and (h) vulnerable species. The details of fauna to include information regarding list and distribution clearly indicating the Schedule of the fauna present. In case of any scheduled-I fauna found in the study area, the necessary plan for their conservation should be prepared in consultation with State Forest and Wildlife Department and details furnished. Necessary allocation of funds for implementing the same should be made as part of the project cost.

11. Collection of one season (non-monsoon) primary baseline data on ambient air quality, water quality, noise level, soil and flora and fauna. Ambient Air quality should be determined by measuring the concentration of parameters like P.M.2.5, P.M.10, SO2, NOx according to the latest standards prescribed by CPCB. Site-specific meteorological data should also be collected. The location of the monitoring stations (minimum 6) should be justified. Date wise collected baseline AAQ data should form part of EIA and EMP report. The monitoring shall be carried out by CPCB/NABL/ MOEF&CC/GoR approved laboratory and copy of the report submitted. The monitoring if any prior to submission of project to SEIAA for ToR will not be considered.

12. Air quality modeling should be carried out for prediction of impact of the project on the air quality of the area. It should also take into account the impact of movement of vehicles for transportation of mineral. The details of the model used and input parameters used for modeling should be provided. The air quality contours may be shown on a location map clearly indicating the location of the site, location of sensitive receptors, if any and the habitation. The wind roses showing pre-dominant wind direction may be indicated on map. Wind Rose Diagram should be representative and include stability class and inversion phenomenon of that area along with the lapse rate.

13. A surface and ground water study should be carryout, both pre-monsoon and post monsoon monitoring. Information about proposed working depth of mining area, groundwater table both in above MSL and below ground level (BGL) should be provided. Based on actual

Page 245: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

monitored data, it may clearly be shown whether mine working will intersect groundwater table or not. In case the mining activity intersects the ground water table then necessary permission from CGWA should be obtained. Impact of the project on the water quality both surface and groundwater should also be assessed and necessary safeguard measures, if any required should be provided. Further, submit water drainage plan of the 10 km study area.

14. The water requirement for the project, its availability and source to be furnished. A detailed water balance should also be provided. Fresh water requirement (if any) for the project should also be indicated. Necessary clearance from the Competent Authority for drawl of requisite quantity of water for the project should be provided. Details of water conservation measures including rainwater harvesting should be provided and to be adopted in the project.

15. Consumption of diesel and its storage should be provided along with an action plan for its conservation.

16. The Conceptual post mine land use plan and Reclamation & Rehabilitation (R&R) plan of mined out area (with plans and sections at appropriate scale as per MCDR 1988 should be submitted.

17. Impact on local transport and infrastructure due to the project: Projected increase in hauling vehicles as a result of the project in the present road network (including those outside the project area) and whether it is capable of handling the increased load. Arrangement for improving the infrastructure to avoid any congestion especially at junctions and mishaps throughout the route of transportation of mineral should be ensured and action to be taken by other agencies such as State Government, if any, should be covered.

18. The green belt area should be developed in 33% of total lease area, provide time taken for of progressive greenbelt development, plantation and compensatory a-forestation clearly indicating the 33% area to be covered under plantation giving detail of local species, width of plantation, plantation schedule etc. along with year wise financial expenditure. The proposal for completion should be for a period of 3 years from the start of mining operation. Information regarding greenbelt development plan shall also be prepared in a tabular form, indicating the location of the area, type of tree and its number supported by a map. Further, existing mining projects should carryout plantation in 33% of lease area and thereafter come for the EC.

19. Budgetary provision for the labors working in the Mine should be submitted for all necessary infrastructure facilities such as health facility, sanitation facility, and fuel for cooking, along with provision for safe drinking water, monthly medical camps and distribution of medicines, primary education and toilets for women, crèche for infants.

20. Details regarding Occupational health impact of the project should be provided. Health study in the surrounding area be carried out covering information regarding prevailing diseases, mortality rate etc. Health and Safety Plan should be prepared and submitted.

21. The P.P. will carry out proper Socio-economic survey of the villages situated in the study area. The details of survey are given if format J. Based upon its findings and also as per public hearing issues and keeping in view the felt needs of local populations, the P.P. will provide adequate budget for carrying out CSR/ESR activities including provision for toilets for girls in nearby schools, monthly medical camps, distribution of medicines and improvement in educational facilities in the nearby schools. Further, existing mining projects should carryout ESR/CSR for a period of at least one year and thereafter come for the EC.

22. Measures for socio economic influence on the local community due to proposed project to be provided by project proponent. As far as possible, appropriate quantitative dimension to be given. Analysis of Job requirements vis-à-vis, employability of local population need to be provided.

23. Detailed environmental management plan to mitigate the environmental impacts which, should inter-alia also include the impact due to change of land use, due to loss of agricultural land and grazing land, if any, besides other impacts of the projects. The budgetary provision (both capital and recurring) for implementing the proposed EMP should be clearly spelt out.

Page 246: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

24. The points raised during Public hearing and commitment of the project proponent on the same along with time bound action plan to implement the commitments and the necessary allocation of funds for the same to be provided.

25. Any litigation pending against the project and /or any direction /order passed by any Court of Law against the project, if so, details thereof should be submitted.

26. The P.P. should ensure compliance of the order of the Hon’ble Rajasthan High Court, Jodhpur, in D. B. Civil writ petition no. 1536 of 2003 in the matter of Abdul Rahman vs State of Rajasthan and others and submit a brief note regarding compliance of the court order.

27. That the Project Proponent shall not use any explosive and blasting for mining activity without proper permissions from competent authorities.

28. Provide details about transfer/allotment of mining lease, extension of lease period etc. along with authenticated copies of orders for lease allotment / transfer / extension of validity period.

29. A balance sheet certified by a Authorized Financial Expert to clearly indicate the provision made / amount spent for EMP/ERP/CSR/ESR/ Safety/Labour welfare/ Legal Obligations etc to be enclosed

30. PP should clearly mention in the documents whether there is any violation of provisions of EIA Notification and inform at the start of presentation (to be a part of computer presentation also).

31. Used filter papers (Air monitoring) along with photographs of the site showing Air / Water sampling / monitoring activity / equipment used at each station should be submitted. Original copies of analysis report of all the relevant data referred in the documents should be enclosed.

32. The information regarding the work order/agreement issued by the P.P. to the consultant (Accredited from QCI/ NABET for proposed project Sector) should be submitted along with, (a) Dispatch No. of the work order/agreement, (b) Date of issue of work order (c) Date of start of air/water/other monitoring work (as applicable) and (d) Postal address/ Email Address/ Fax Number/ Mobile Number and Landline Number of the P.P.

Points included in TOR as per MoEF&CC circular no. J-11013/41/2006-IA.II(I)-Pt. dt.

19.05.2011 regarding Corporate Environmental responsibility.

1. (a) Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be detailed in the EIA report.

(b) Does the Environment Policy prescribed for standard operating process/procedures to

bring into focus any infringement/deviation/violation of the Environmental or forest norms

/conditions? If so, it may be detailed in the EIA report.

2. What is the hierarchical system or administrative order of the company to deal with the Environmental issues and for ensuring compliance with the EC conditions? Details of this system may be given.

3. Does the company have a system of reporting of non-compliances/violations of Environmental norms to the Board of Directors of the company and /or shareholders or stakeholders at large? This reporting mechanism should be detailed in the EIA report.

4. After preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the proponent shall get the public hearing conducted (strictly following the procedure laid down in the Appendix IV of the Amendment Notification dt. 01.12.2009 and MoEF circular no. J-15012/29/2010/IA.II(M) dt. 19.04.2010). In this regard due care would be taken in (i) deciding the venue of public hearing (at the project site or in its closed proximity, to ensure widest possible public participation), (ii) forwarding the Draft EIA Reports with Executive Summary Reports and notice for hearing to various authorities / offices, specifically to Urban Local Bodies/ Panchayati Raj. Institutions (i.e Zila Parishad, Panchayat Samiti & Gram Panchayat)/ Development Authorities (i.e. U.I.T., J.D.A. etc.), (iii) adequate publicity regarding date, place and time of public hearing among local public, (iv) recording requisite “certificate” at the end of public hearing proceedings / report and (v) displaying the report in the office of Gram Panchayat, Zila Parishad, Collectorate etc. After completing the public

Page 247: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

hearing process as described above, the proponent shall take further necessary action for obtaining environmental clearance in accordance with the procedure prescribed under the EIA Notification, 2006 and subsequent amendment dt. 01.12.2009.

5. A certificate should be submitted by the Regional Officer Pollution Control Board that the process followed for public hearing was adequate as required in reference to contents of MoEF O.M. no. J-15012/29/2010-IA-II(M) dt. 19.04.2010. In the final EIA /EMP report , compliance of points of ToRs should be reported point wise in

a statement of three columns as indicated below:-

Yours faithfully,

(T.S. Ranawat)

Secretary, SEAC,Rajasthan

Copy to

1. Member-Secretary, SEIAA, Rajasthan and Secretary to Government, Department of

Environment, GoR, Secretariat, Jaipur.

2 Member Secretary, RSPCB, Jaipur.

S. No Items in the letter of the ToRs Reply / Response by the PP

Page 248: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

ANNEXURE –XII: COPY OF MINUTES OF PUBLIC HEARING

Page 249: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 250: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 251: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 252: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 253: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 254: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 255: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 256: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

ANNEXURE –XIII: PHYTOSOCIO REPORT OF STUDY AREA

Page 257: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 258: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 259: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 260: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 261: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 262: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 263: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 264: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 265: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 266: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 267: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 268: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 269: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.

Page 270: STUDY PERIOD MARCH TO MAY ENVIRONMENTAL …environmentclearance.nic.in/writereaddata/EIA/02012017OM2Y7... · chapter - ii ... 4.5 impact of noise / vibrations & mitigation measures

Prepared by – M/S Udaipur Min-Tech Pvt. Ltd.