substation equipment

Upload: chinnarao

Post on 10-Feb-2018

223 views

Category:

Documents


1 download

TRANSCRIPT

  • 7/22/2019 Substation Equipment

    1/38

  • 7/22/2019 Substation Equipment

    2/38

  • 7/22/2019 Substation Equipment

    3/38

    SF6 Gas Auto Puffer interrupter

    Load current operation.

  • 7/22/2019 Substation Equipment

    4/38

    Main contacts copper with silverplated.

    Arcing contacts Tungsten copper. Nozzle is made up of Teflon.

    Commutation of current Current

    moving from main to arc contacts.

  • 7/22/2019 Substation Equipment

    5/38

    Operation time

    SF6 gas leakage

    Contact resistance measurement Visual checks

    Density monitor reading. (Compensatestemp change).

    Rated pressure 7 Bar absolute pressure.

    Check anti pumping feature

    Wiring according to schematic.

  • 7/22/2019 Substation Equipment

    6/38

  • 7/22/2019 Substation Equipment

    7/38

    In test chamber for arching chamberpressurization test. 1.5 times max workingpressure( 10.5 Bar to 7 bar)

    1 close open operation at this pressure. Resistance of control coils checked. One

    closing coil and 2 trip coils with auxcontactors, heaters and relays.

    Operation of motor, motor current andspring charging time.

    Closing at control voltages (110% to 80%)

    Tripping at control voltages ( >70%)

  • 7/22/2019 Substation Equipment

    8/38

    Breaker Timing Tests

    Breaker Analyser (eg ELCON make)

    Open time, close time, close open COtime and open close OC time.

    Important of gang operated breakerwhere all three phase poles are different.

    Main contact resistance measurement.

    SF6 gas tightness test. SF6 gas leaksensing meter.

  • 7/22/2019 Substation Equipment

    9/38

    High Voltage tests (140 kV applied)

  • 7/22/2019 Substation Equipment

    10/38

    Close time : max 75 ms , Close velocity : 1.7to 2.0 m/s

    Open Time : 35 to 45 ms , open velocity : 2.2to 2.6 m/s

    CO Time : max 65 ms

    Stroke : 84 to 87 mm

    Motor Current : 4.5 A (220 V) and 8 A (110V)

    Spring charging time : 15 sec max

    Contact resistance : 46 (at 20C)

  • 7/22/2019 Substation Equipment

    11/38

    Paper + Oil insulation

    Paper dried till last traces of moisture.

    Then impregnated with oil containing less

    than 7 ppm of water. High breakdown strength + any shape.

    Electrical stress on the insulation is high nearthe earthed end.

    If conducting foils are introduced inbetween the insulation, then stress acrossthe insulation is uniform. This is calledcapacitive grading.

  • 7/22/2019 Substation Equipment

    12/38

  • 7/22/2019 Substation Equipment

    13/38

  • 7/22/2019 Substation Equipment

    14/38

    Tan is the end point of primary insulation. It isformed on the bend end limb of the conductor bywrapping tinned copper strip over last main

    grading foil and then soldered to it. The other endof the strip is terminated at terminal box.

  • 7/22/2019 Substation Equipment

    15/38

    Integrated insulation quality between highvoltage terminal to tan delta terminal.

    It can be explained by considering insulation

    as a capacitor. Resultant current is made up of resistive current

    and capacitive current.

    Resistive current due to impurities and moisture.

    Insulation made by capacitive grading orlayers. Each layer is contributing nano farad.

    Equivalent capacitance of complete insulationis in pico farad.

  • 7/22/2019 Substation Equipment

    16/38

    Increase in capacitance in comparisonto original reference value at 5 kV or 10kV indicates void and cavity in theinsulation.

    Indicates presence of partial dischargesand deterioration of the insulation.

    Increase in Tanvalue and no increasein capacitance means partial dischargeactivity has initiated near the HV terminalor near to tanor earthing terminal.

  • 7/22/2019 Substation Equipment

    17/38

  • 7/22/2019 Substation Equipment

    18/38

    Measurment of voltage.

    Isolation between high voltage and low

    voltage. Inputs to relay

    PLCC

    Parts of CVT: Capacitor part capacitor stack, insulator

    EMU PT, HV choke and FR circuit.

  • 7/22/2019 Substation Equipment

    19/38

    Tapping 110 V from C2 with primary voltage being220 kV is a problem since effective burden will thenonly be 0.22 VA.

    Any attempt to load this system will lead touneven voltage distribution between C1 and C2and inaccurate output.

  • 7/22/2019 Substation Equipment

    20/38

    CVT is a tuned device and hence the errors areprone to change with frequency but willremain in a specified accuracy class.

    Standards specify that errors of meteringwinding are to be guaranteed from 25% to100% of the rated burden and for a frequencyrange of 49.5 to 50.5 Hz. However, CVT cancater same accuracy at 49 to 51 Hz because

    of reduced burden requirement nowadays. Frequency of large systems always tend to godown below 49 Hz, thus it also preventsunnecessary under frequency tripping. Thus,they are tuned at 49 Hz.

  • 7/22/2019 Substation Equipment

    21/38

  • 7/22/2019 Substation Equipment

    22/38

  • 7/22/2019 Substation Equipment

    23/38

    Carry out visual inspection of oil level.

    Clean the insulator periodically. No oil change or oil filtration is required as CTs and

    CVTs are hermetically sealed. During annual inspection on denergized CT

    tightening of primary and ground connections to bechecked with tightening torques.

    Online checks of hotspots on primary connections bythermo vision cameras.

    Tan to be measured every year. Acceptable valuesfor CTs are 145 kV 2%, 245 kV 1%, 420 kV 0.8%,

    And for CVTs 0.5%. Abrupt changes in Tanare alarming.

  • 7/22/2019 Substation Equipment

    24/38

    Tanbeyond acceptable range should bechecked by DGA and oil analysis.

    In case of fuse failures in CVTs, fault

    checking to be done. If secondary voltage output change in

    CVTs, carry out measurement of C1 and C2.

    Sec voltage increases

    element in C1 failsor primary turns of PT gets shorted.

    Sec voltage decreases element in C2 failsor secondary turns of PT gets shorted.

  • 7/22/2019 Substation Equipment

    25/38

    Composite hollow insulator is made up oftwo insulating parts.

    Consists of filament wound epoxy fiberglass

    tube and extruded silicone sheds on thesurface of the tube with metal flanges atboth the ends.

    Sheds are produced by helical extrusionwith HTV silicone.

    Applications are in surge arresters, bushings,circuit breakers, isolators and instrumenttransformers.

  • 7/22/2019 Substation Equipment

    26/38

    High resistance against pollution. Reduced maintenance.

    Very good electrical properties.

    Resistance to PD. Hardly inflammable.

    Self quenching No carbon chain. Inert to ozone, superior stability to UV. Water repellent

    Less necessity of washing in pollution.

    Resistance against mechanical shocks. Low weight

    Non-brittle. High surface resistance compared to porcelain. No danger of particles during explosions.

  • 7/22/2019 Substation Equipment

    27/38

    Vandalizing proof against impactvelocity of 10 m/s.

  • 7/22/2019 Substation Equipment

    28/38

  • 7/22/2019 Substation Equipment

    29/38

  • 7/22/2019 Substation Equipment

    30/38

  • 7/22/2019 Substation Equipment

    31/38

  • 7/22/2019 Substation Equipment

    32/38

    Made from tubular aluminum sections

    Joints are welded

    Cu-Al joints are bolted and press fitted. Hot zinc metalizing to avoid galvanic

    corrosion between Al and Cu.

    3 phase gang operated isolators withmotor drive and manual drive.

  • 7/22/2019 Substation Equipment

    33/38

    A bushing is used to run a current at high potentialthrough a ground barrier.

    Designed as per IEC 60137

  • 7/22/2019 Substation Equipment

    34/38

    These types of bushings are also called condenser bushings.

    They have uniform stress on insulation, oil and porcelain.

  • 7/22/2019 Substation Equipment

    35/38

  • 7/22/2019 Substation Equipment

    36/38

  • 7/22/2019 Substation Equipment

    37/38

  • 7/22/2019 Substation Equipment

    38/38