THE INDUS HOSPITAL Construction of Grey Structure (Core & Shell)

Extension Phase 1

Technical Proposal Package

                                                           

2  

CONTENT  

SHEET NO  DESCRIPTION

01 ~ 04  PROJECT METHODOLOGY 

05 ~ 08  PROJECT SCHEDULE  

09  DEPLOYMENT SCHEDULE OF STAFF  

10 ~ 11  DEPLOYMENT SCHEDULE OF EQUIPMENT 

12   PROJECT ORGANOGRAM  

13  TOWER CRANES WORKING ENVELOP 

14  TOWER CRANES IN ELEVATION 

15  SITE ESTABLISHMENT PLAN  

16  PROPRIETARY RMD SYSTEM FORMWORK 

3

PROJECT METHODOLOGY SITE ESTABLISHMENT:

SITE OFFICE, STORES, SITE WORKSHOPS:

It is proposed to use three 20ft and two 40ft office containers to accommodate the Project Manager, Construction Managers, Site Engineers, Accounts and Other Officers. Two 40ft container will be used as tools and general items store as well as store office. Bulk items, scaffolding, timber, steel forms will be stored in an adjacent Open Store Area levelled and prepared for the purpose. Site workshop will comprise of scaffold frame and corrugated G.I. sheeting sheds with adjacent prepared open work areas.

ELECTRIC POWER:

Diesel generators, along with the requisite mains switches, cabling and distribution boards will be installed to supply electric power.

WATER:

Potable water acquired in 5000 gallon tankers, and stored in PVC or steel overhead tanks in the camp areas. The water will be distributed through PVC piping to toilets, showers and kitchens. The water will be filtered for drinking purposes. Also Water for earth fill works and concrete works will be obtained, in 5000 gallon tankers through water purchase agreements with the existing suppliers.

MANAGEMENT PLAN

SITE ORGANIZATION CHART:

Please refer to attached Site Organization Chart.

COMMUNICATION & COORDINATION PLAN: Site Coordinating Person:

Project manager will be the key coordinating person for the project.

4

Highest Coordinating Person:

For owner representative, contact reference will be the Project Director (Mr. Hamid Naqvi). Project Manager reports directly to the Project Director.

In-house Communication:

Telephone/ Internet facilities will be installed at the Site and will be used for voice / data communications..

INVOICES, SHOP DRAWINGS & SUBMITTALS:

Invoice Raising:

Quantity Surveyor will work on invoices and it will be raised by Project Manager to owner representative.

Drawings & Documents / As Built Drawings:

Drawings & Documents will be received at site by the Planning Engineer from the owner representative in accordance with a mutually agreed procedure. All data received will be distributed, filed, and periodically updated by the draftsman under the supervision of the Planning Engineer. "As built" drawings will be prepared by Draftsman working under Planning Engineer, who will report to Project Manager.

Submittals:

All submittals will be raised by Project Manager through the Planning Engineer. Planning Engineer will be responsible to handle the submittals.

TRANSPORT:

Well maintained vehicles will be used for site supervision, staff transport, and materials procurement duties. It is proposed to use owned / hired vehicles. All vehicles shall be driven only by licensed and trained drivers.

CONSTRUCTION/SITE HEALTH & SAFETY:

There will be a permanent health & safety supervisor on site. Safety facilities on site will include: 1. Personal protective equipment. 2. Firefighting equipment. 3. First aid facilities. 4. Arrangements for injury and other treatment with Indus Hospital. 5. Housekeeping facilities including waste drums, collection, and disposals in a safe manner. 6. Safe drinking water and sanitation facilities.

CONSTRUCTION QUALITY CONTROL:

There will be QA / QC supervisors to implement the Project Quality Control Plan. They will work under Project Manager. The project specific quality plan will be prepared prior to start of work at site. As a sample please refer to attach Construction Quality Control Plan.

5

SECURITY:

Security for the work sites, site facilities area, and staff / labor camps will be provided through day and night watchmen, entry posts and adequate area lighting for night time use.

WORK METHODOLOGY:

Survey Control and Set-out:

It is proposed to use four (4) survey teams, comprising one qualified senior surveyor and two survey assistants each, for the project works. The survey teams will establish and maintain survey monuments, temporary markers, property lines, reference base lines, and perform all survey work necessary to achieve the design formations, elevations and grades.

Plant Maintenance:

A workshop will be established for the purposes of servicing and routine maintenance of plant only. No major repairs shall be carried out on site. The workshop will be housed in a shed structure within the camp premises and equipped for lubrication, filter changes, tyre filling, and minor repairs. Diesel for the construction plant will be stored on site in a 15,00liters steel tank installed in accordance with the safety requirements for fuel storage.

Material Handling & Lifting:

1) Tower Crane It is proposed to use three (3) static tower cranes The HUH is 35 m, jib length 50m, and lifting capacity is 10 ton with 2 ton Tip load whose seems to be adequate for Project.

2) Construction Passenger Hoist single cabin with 2 ton capacity – 2 Nos. 3) Construction Cargo Hoist single cabin with 2 ton capacity – 2 Nos.

Concrete Pumps:

Two stationary pumps 60 Cu-m/Hr are proposed for concrete placement in the floor slabs. The 125mm diameter delivery line shall be attached to the building structure (columns or lift core) through steel profiles and expansion bolts. It is also proposed to use a mobile pump during ground level and low level concreting.

System Formwork:

The proposed system formwork will comprise of: 1) Panel forms for internal walls and columns. 2) Panel forms for lift cores and stair walls. 3) Slab form systems for floor slabs, drop panels & beams. 4) Site fabricated forms for staircases and special shapes.

It is proposed to use the RMD Kwikform system we already own and which has been successfully used on several high profile projects. All formwork and accessories shall be designed for the imposed loads of the concrete and for specified off-form finishes.

Formwork for Slab, Drop Panels and Beams:

We propose to have 80,000 Sft of proprietary RMD system formwork and 40,000 Sft of conventional formwork at site for Slab, Drop Panels & Beams. Form face would be 18mm thick quality plywood.

6

Formwork for Columns and Walls:

We propose to have 45 sets of Columns Formwork.

Other Equipment:

Other equipment for building construction shall include excavation and backfill compaction machinery, material handling equipment, power generating sets , dewatering equipment, re-bar fabrication equipment and conventional scaffolding for access / miscellanies uses..

Manpower Deployment / Supervision:

Efficient and productive deployment of labor and supervisory staff on building construction is achieved by: 1. Speedy transport to floor levels of personnel, tools, and materials. 2. An efficient communication system between ground facilities such as stores, laboratory, batch plants, workshops etc. 3. Easy access to facilities such as toilets and drinking water. For communication between the works crews on floor levels and the ground facilities hand-held radio sets shall be used.\ The above measures shall ensure quick deployment of work crews to floor levels, timely availability of tools and materials, and a minimum of non-productive labor time due to toilet breaks and water breaks.

Plant & Equipment Proposed:

Please refer to attach Equipment Deployment Plan.

Material Procurement:

Procurement of all permanent material will be the responsibility of the site management team. They will be responsible for submittals, approvals, ordering, delivery and warehousing.

Concrete Batch Plant:

Concrete will be delivered to the site from selected approved pre-mix concrete suppliers

Activity Name OriginalDuration

Start Finish

Total 720d 02-Nov-2015 21-Oct-2017

Construction of Gery Structure (Core 720d 02-Nov-2015 21-Oct-2017

Mobilazation 720d 02-Nov-2015 21-Oct-2017Start Of Work 0d 02-Nov-2015Mobilazation and Site Set-Up /Approval of Mix Des 45d 02-Nov-2015 16-Dec-2015Sub Structure Works 248d 07-Nov-2015 11-Jul-2016

Excavation Work 50d 07-Nov-2015 26-Dec-2015Pile Bracking 30d 12-Nov-2015 11-Dec-2015Pcc for Raft 45d 22-Nov-2015 05-Jan-2016Pile Cap Reinf 45d 02-Dec-2015 15-Jan-2016Pouring 45d 02-Dec-2015 15-Jan-2016Retaining Wall & Columns 100d 05-Dec-2015 13-Mar-2016Under Ground Water Tank 50d 24-Nov-2015 12-Jan-2016Ground Floor Slab 160d 03-Feb-2016 11-Jul-2016Ramp Slab from B-1 to Ground 25d 17-Jun-2016 11-Jul-2016Water Proofing 90d 03-Feb-2016 02-May-2016

Package-A (Basment, Hospiatl Building & He 488d 23-May-2016 22-Sep-2017F-1 & Meeznine 125d 23-May-2016 24-Sep-2016

Floor Column & Walls 40d 23-May-2016 01-Jul-2016Floor Slabe 100d 17-Jun-2016 24-Sep-2016

F-2 100d 01-Aug-2016 08-Nov-2016Floor Column & Walls 35d 01-Aug-2016 05-Sep-2016Floor Slabe 80d 21-Aug-2016 08-Nov-2016

F-3 95d 10-Oct-2016 12-Jan-2017Floor Column & Walls 30d 10-Oct-2016 08-Nov-2016Floor Slabe 80d 25-Oct-2016 12-Jan-2017

F-4 95d 24-Nov-2016 26-Feb-2017Floor Column & Walls 30d 24-Nov-2016 24-Dec-2016Floor Slabe 80d 09-Dec-2016 26-Feb-2017

F-5 85d 08-Jan-2017 02-Apr-2017Floor Column & Walls 30d 08-Jan-2017 07-Feb-2017Floor Slabe 70d 23-Jan-2017 02-Apr-2017

F-6 70d 15-Feb-2017 25-Apr-2017Floor Column & Walls 25d 15-Feb-2017 12-Mar-2017Floor Slabe 60d 25-Feb-2017 25-Apr-2017

F-7 70d 12-Mar-2017 20-May-2017Floor Column & Walls 25d 12-Mar-2017 06-Apr-2017Floor Slabe 60d 22-Mar-2017 20-May-2017

F-8 70d 06-Apr-2017 14-Jun-2017Floor Column & Walls 25d 06-Apr-2017 01-May-2017Floor Slabe 60d 16-Apr-2017 14-Jun-2017

F-9 70d 01-May-2017 09-Jul-2017Floor Column & Walls 25d 01-May-2017 26-May-2017Floor Slabe 60d 11-May-2017 09-Jul-2017

F-10 70d 26-May-2017 03-Aug-2017Floor Column & Walls 25d 26-May-2017 20-Jun-2017Floor Slabe 60d 05-Jun-2017 03-Aug-2017

Roof 95d 20-Jun-2017 22-Sep-2017Floor Column & Walls 25d 20-Jun-2017 15-Jul-2017Floor Slabe 60d 30-Jun-2017 28-Aug-2017

O N D J F March April May June July A S O N D J F March April May June July A S O N D2016 2017

-2015 21-Oct-2017

-2015 21-Oct-2017

-2015 21-Oct-2017Start Of Work

v-2015 11-Jul-2016

23-May-2016 22-Sep-201723-May-2016 24-Sep-2016

01-Aug-2016 08-Nov-2016

10-Oct-2016 12-Jan-2017

24-Nov-2016 26-Feb-2017

08-Jan-2017 02-Apr-2017

15-Feb-2017 25-Apr-2017

12-Mar-2017 20-May-2017

06-Apr-2017 14-Jun-2017

01-May-2017 09-Jul-2017

26-May-2017 03-Aug-2017

20-Jun-2017 22-Sep-2017

INDUS HOSPITAL EXTENSION PHASE-1

CONSTRUCTION OF GREY STRUCTURE (Package-A & B)

Note:-Will be Review after Reciving of IFC Drawings Actual WorkRemaining Work

Critical Remaining WorkMilestone

% Co...Sum...

Activity Name OriginalDuration

Start Finish

Upper Roof Slab Works 40d 14-Aug-2017 22-Sep-2017Package-B ( ECOL Building) 338d 12-Jun-2016 15-May-2017

F-1 100d 12-Jun-2016 19-Sep-2016Floor Column & Walls 30d 12-Jun-2016 11-Jul-2016Floor Slabe 70d 27-Jun-2016 04-Sep-2016Ramp GF to F-1 15d 05-Sep-2016 19-Sep-2016

F-2 85d 22-Jul-2016 14-Oct-2016Floor Column & Walls 25d 22-Jul-2016 16-Aug-2016Floor Slabe 60d 01-Aug-2016 29-Sep-2016Ramp F-1 ~ F-2 15d 30-Sep-2016 14-Oct-2016

F-3 85d 16-Aug-2016 08-Nov-2016Floor Column & Walls 25d 16-Aug-2016 10-Sep-2016Floor Slabe 60d 26-Aug-2016 24-Oct-2016Ramp F-2 ~ F-3 15d 25-Oct-2016 08-Nov-2016

F-4 85d 10-Sep-2016 03-Dec-2016Floor Column & Walls 25d 10-Sep-2016 05-Oct-2016Floor Slabe 60d 20-Sep-2016 18-Nov-2016Ramp F-3 ~ F-4 15d 19-Nov-2016 03-Dec-2016

F-5 85d 05-Oct-2016 28-Dec-2016Floor Column & Walls 25d 05-Oct-2016 30-Oct-2016Floor Slabe 60d 15-Oct-2016 13-Dec-2016Ramp F-4 ~ F-5 15d 14-Dec-2016 28-Dec-2016

F-6 85d 28-Oct-2016 20-Jan-2017Floor Column & Walls 25d 28-Oct-2016 22-Nov-2016Floor Slabe 60d 07-Nov-2016 05-Jan-2017Ramp Slab F-5 ~ F-6 15d 06-Jan-2017 20-Jan-2017

F-7 85d 22-Nov-2016 14-Feb-2017Floor Column & Walls 25d 22-Nov-2016 17-Dec-2016Floor Slabe 60d 02-Dec-2016 30-Jan-2017Ramp Slab F-6 ~ F-7 15d 31-Jan-2017 14-Feb-2017

F-8 70d 17-Dec-2016 24-Feb-2017Floor Column & Walls 25d 17-Dec-2016 11-Jan-2017Floor Slabe 60d 27-Dec-2016 24-Feb-2017

F-9 70d 11-Jan-2017 21-Mar-2017Floor Column & Walls 25d 11-Jan-2017 05-Feb-2017Floor Slabe 60d 21-Jan-2017 21-Mar-2017

Roof 95d 10-Feb-2017 15-May-2017Floor Column & Walls 25d 10-Feb-2017 07-Mar-2017Floor Slabe 60d 20-Feb-2017 20-Apr-2017Upper Roof Slab Works 40d 06-Apr-2017 15-May-2017

Finishing Work 557d 13-Apr-2016 21-Oct-2017Block Work 530d 13-Apr-2016 24-Sep-2017

Basment ( Hospital & ECOL) 120d 13-Apr-2016 10-Aug-2016F-1 (Hospital & ECOL) 50d 23-May-2016 11-Jul-2016F-2 (Hospital & ECOL) 50d 02-Jul-2016 20-Aug-2016F-3 (Hospital & ECOL) 50d 11-Aug-2016 29-Sep-2016F-3 (Hospital & ECOL) 50d 20-Sep-2016 08-Nov-2016F-4 (Hospital & ECOL) 50d 30-Oct-2016 18-Dec-2016F-5 (Hospital & ECOL) 50d 09-Dec-2016 27-Jan-2017F-6 (Hospital & ECOL) 50d 18-Jan-2017 08-Mar-2017F-7 (Hospital & ECOL) 50d 27-Feb-2017 17-Apr-2017

O N D J F March April May June July A S O N D J F March April May June July A S O N D2016 2017

12-Jun-2016 15-May-201712-Jun-2016 19-Sep-2016

22-Jul-2016 14-Oct-2016

16-Aug-2016 08-Nov-2016

10-Sep-2016 03-Dec-2016

05-Oct-2016 28-Dec-2016

28-Oct-2016 20-Jan-2017

22-Nov-2016 14-Feb-2017

17-Dec-2016 24-Feb-2017

11-Jan-2017 21-Mar-2017

10-Feb-2017 15-May-2017

13-Apr-2016 21-Oct-201713-Apr-2016 24-Sep-2017

INDUS HOSPITAL EXTENSION PHASE-1

CONSTRUCTION OF GREY STRUCTURE (Package-A & B)

Note:-Will be Review after Reciving of IFC Drawings Actual WorkRemaining Work

Critical Remaining WorkMilestone

% Co...Sum...

Activity Name OriginalDuration

Start Finish

F-8 (Hospital & ECOL) 50d 08-Apr-2017 27-May-2017F-9 (Hospital & ECOL) 50d 18-May-2017 06-Jul-2017F-10 (Hospital & ECOL Roof) 50d 27-Jun-2017 15-Aug-2017F-11 (Hospital Roof ) 50d 06-Aug-2017 24-Sep-2017

Plaster Work 527d 13-May-2016 21-Oct-2017Basment ( Hospital & ECOL) 130d 13-May-2016 19-Sep-2016F-1 (Hospital & ECOL) 50d 22-Jun-2016 10-Aug-2016F-2 (Hospital & ECOL) 50d 01-Aug-2016 19-Sep-2016F-3 (Hospital & ECOL) 50d 10-Sep-2016 29-Oct-2016F-3 (Hospital & ECOL) 50d 20-Oct-2016 08-Dec-2016F-4 (Hospital & ECOL) 50d 29-Nov-2016 17-Jan-2017F-5 (Hospital & ECOL) 50d 08-Jan-2017 26-Feb-2017F-6 (Hospital & ECOL) 50d 17-Feb-2017 07-Apr-2017F-7 (Hospital & ECOL) 50d 29-Mar-2017 17-May-2017F-8 (Hospital & ECOL) 50d 08-May-2017 26-Jun-2017F-9 (Hospital & ECOL) 50d 17-Jun-2017 05-Aug-2017F-10 (Hospital & ECOL Roof) 70d 27-Jul-2017 04-Oct-2017F-11 (Hospital Roof ) 47d 05-Sep-2017 21-Oct-2017Project Complate 0d 21-Oct-2017

O N D J F March April May June July A S O N D J F March April May June July A S O N D2016 2017

13-May-2016 21-Oct-2017

Project Complat

INDUS HOSPITAL EXTENSION PHASE-1

CONSTRUCTION OF GREY STRUCTURE (Package-A & B)

Note:-Will be Review after Reciving of IFC Drawings Actual WorkRemaining Work

Critical Remaining WorkMilestone

% Co...Sum...

Description M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18 M-19 M-20 M-21 M-22 M-23 M-24 Man Hours

Project Director (H.O) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,760

Planning Engineer (H.O) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,760

Project Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,760

Planning Engineer (Site) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - 5,280

Quantity Surveyor 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 10,320

Ass.Q.S/Cad Operator - 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 - 10,080

Plant /Mech Incharge 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - 5,520

Material Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - 5,520

Lab Asst. 1 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 2 2 1 1 18,480

HSE Coordinator 1 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 1 1 19,920

Safety Inspector 1 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 1 - 19,200

Admin Officer - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - 5,280

Timekeeper/Payrool - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,520

Camp /Housekeeping Supervisor - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - 5,040

Site Accountant - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,520

Account Assistant 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 - 10,320

Procurement Manager - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - 4,800

Site Purchaser - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - 5,040

StoreKeeper - 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 10,560

Construction Manager 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 10,320

Site Engineers 1 2 2 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 4 2 25,200

Asst.Site Engineers 2 4 4 8 8 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 8 4 2 48,000

Surveyor 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 11,040

Assistant Surveyor 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 2 21,120

Construction Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,520

Site Engineers 1 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 15,360

Asst.Site Engineers - 2 2 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4 28,320

Surveyor - 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 10,320

Assistant Surveyor - 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 1 19,440

TOTAL 20 40 52 66 69 71 71 71 71 71 71 71 71 71 71 71 71 71 71 69 68 57 39 19 358,320

FOR PACKAGE-A (BASMENT, HOSPITAL BUILDING, HEAD HOUSE WORKS)

FOR PACKAGE-B (ECOL BUILDING WORKS)

ASSOCIATED CONSTRUCTORS LIMITED

DEPLOYMENT SCHEDULE OF STAFF FOR INDUS HOSPITAL EXTENSION PHASE-1 PROJECT

(FOR COMMON/SHARED WORKS )

Associated constructor Ltd

M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 E.M.

1 Concrete Pump (Stationary) Owned 2 0 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 44

2 External Climbing Tower Crane Owned 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 23

3 Internal Climbing Tower Crane Owned 2 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 46

4 Hydraulic Mobile Crane Rental 2 1 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1 1 1 1 36

5 Construction Hoist

6 Passenger Owned 2 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 32

7 Cargo Owned 2 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 32

8 Generators (Diesel 250 ) Owned 3 0 1 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 2 2 62

9 Generators (Diesel 100 KVA) Owned 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24

10 Generators (Diesel 80 KVA) Owned 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24

11 Air Compressor Owned 3 1 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 1 1 1 59

12 Welding Plant Owned 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 46

13Concrete Screeding / Floating Equipment for

floors (Set)Owned 2 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 42

14Power Tools (Drills, Grinders, Breakers,

Scabblers) (Lots)Owned

As

RequiredA.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R.

15 Concrete Vibrators OwnedAs

RequiredA.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R.

16 Total Station Owned 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 45

17 Surveyors Level Owned 6 2 2 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4 2 124

19 Carpentery Shop (Set) Owned 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24

20 Proprietary Formwork System (Sft) 80,000 40,000 60,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 60,000 50,000 A.R.

21 Conventional Formwork (Sft) 40,000 20,000 30,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 30,000 30,000 A.R.

22Scaffolding Pipe & Joints for All-round &

temporary works Owned

As

RequiredA.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R.

23 Columns (Nos.) Owned 45 30 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 1065

24 Re-Bar Bending Machine Owned 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 46

25 Re-Bar Cutting Owned 3 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 1 67

* Concrete will be delivered to the site from selected approved pre-mix concrete suppliers

Steel Yard

Formwork

Max.

Concrete Works

Cranes, Access Equipment & Transport

Air Compressor & Generator

Small Power Tools & Plants

Status

ASSOCIATED CONSTRUCTORS LIMITED

DEPLOYMENT SCHEDULE OF EQUIPMENT FOR INDUS HOSPITAL EXTENSION PHASE-1 PROJECT

MONTHSS.N Description

Carpentery & Fabrication Shop

Associated constructor Ltd

PROPOSED PROJECT ORGANOGRAM FOR CONSTRUCTION OF GREY STRUCTURE (Core & Shell)INDUS HOSPITAL EXTENSION PHASE‑1 PROJECTAssociated constructor Ltd

PROJECT DIRECTOR+ 

PLANNING MANAGER

CONSTRUCTION MANAGER                                            (FOR ECOL BUILDING )

SITESUPERVISOR

ASSISTANTSITE SUPERVISOR

SURVEYORS

ASSISTANT SURVEYORS

SURVEYOR HELPERS

UN‑SKILLED WORKER GANG 

SKILLED WORKER GANG 

CARPENTER/SCAFFOLDER/ 

MASON

PLANNING ENGINEER

QUANTITY SURVEYORS

ASST  QUANTITY SURVEYORS & AUTO CAD OPERATOR

ADMINISTRATION OFFICER

CAMP /HOUSEKEEPING SUPERVISOR

TIME/PAYROLL SUPERVISOR

HSE COORDINATOR

MEDIC SAFETY INSPECTORS

QA/QC SUPERVISOR

MECH/PLANTINCHARGE

MECHANICS/ OPERATOR/ ELECTRICIAN 

PROCUREMENT MANAGER  

PURCHASERS

ACCOUNTANT  OFFICER

ASST   ACCOUNTANT

STOREINCHARGE

CONSTRUCTION MANAGER   (FOR  BASMENT,HOSPITAL BUILDING 

& HEAD HOUSE)

SITE SUPERVISOR

ASST‑SITE ENGINEERS

SURVEYORS

SURVEYOR HELPERS

UN‑SKILLED WORKER GANG 

SKILLED WORKER GANG 

CARPENTER/SCAFFOLDER/ 

MASON

SURVEYORS

PROJECT MANAGER

LABORATORY INCHARGE

ASST‑LABORATORY