the future of wixom lake
DESCRIPTION
The Future of Wixom Lake. “We’re all in this together”. Why the Lakes exist. The dams at Sanford, Edenville, Smallwood and Secord were built by Frank Wixom in 1925 Wixom owned all the upstream lands that were flooded The flooding created four reservoirs and lots of waterfront real estate - PowerPoint PPT PresentationTRANSCRIPT
The Future of Wixom Lake
“We’re all in this together”
The dams at Sanford, Edenville, Smallwood and Secord were built by Frank Wixom in 1925◦ Wixom owned all the upstream lands that were
flooded◦ The flooding created four reservoirs and lots of
waterfront real estate◦ Hydroelectric power was a relatively new industry
and in its heyday in the 1920s◦ Dams provide recreational opportunities and flood
control that would not exist without them
Why the Lakes exist
The Federal Power Act of 1920:◦ Established government oversight over power
producing dams on “navigable waterways” of the United States
◦ Established the Federal Power Commission to regulate them
Today that agency is the Federal Energy Regulatory Commission (FERC)
Federal Government Oversight
FERC licenses power producing dams FERC’s regulations require the dams’ owner
to perform frequent engineering studies, monitoring, environmental and emergency management and to comply with its dam safety standards
Federal Government Oversight
The Probable Maximum Flood (PMF) is an event calculated by FERC to occur once every 10,000 years ◦ By comparison, the flood of September, 1986 was
a between a 50- and 100-year flood event The FERC requires all “high hazard” dams to
be able to safely pass the 10,000-year flood without failing (overtopping)◦ The Edenville Dam is considered a “high hazard”
dam because its failure would likely result in loss of life and property downstream at Sanford Lake
What is the “PMF”?
Six spillways will be reconstructed to double their capacity to pass flood water◦ There are 3 spillways at the Tobacco River side of
the dam and 3 spillways adjacent to the Edenville powerhouse on the Tittabawassee River side
The total capacity of the six spillways is currently 32,000 cubic feet per second (cfs) (or 14,400,000 gallons per minute)
To comply with FERC’s mandate, the capacity of the six spillways will have to be increased to 64,000 cfs (or 28,800,000 gpm)
What needs to be done?
Spillway ComparisonCurrent configuration of spillways
Tittabawassee side adjacent to powerhouse shown; Tobacco spillway is similar
Spillway comparisonFERC-Mandated alteration of spillways
Tittabawassee side adjacent to powerhouse shown; Tobacco spillway is similar
Spillway constructionExample of cofferdam construction
Spillway constructionExample of cofferdam construction
Spillway constructionExample of cofferdam construction
Spillway constructionExample of Cofferdam construction
3-Dimensional ViewsExisting spillway construction
3-Dimensional ViewsFirst concrete pour inside spillway (summer 2013)
3-Dimensional ViewsNew concrete pier extensions (summer 2014)
This work takes place “in the dry” behind a sheet pile cofferdam
3-Dimensional ViewsStoplogs are placed between piers & rest on new concrete sills
Once stoplogs are in place water levels can be returned to normal
3-Dimensional ViewsConstruction work taking place between 2015 and 2016
More concrete is
poured in the base of the
spillway
Existing gate and bridge are
removed
3-Dimensional ViewsConstruction work taking place between 2015 and 2016
Concrete rollaway slabs and most of upstream barrel arches are removed
3-Dimensional ViewsConstruction work taking place between 2015 and 2016
New concrete crest is poured
3-Dimensional ViewsConstruction work taking place between 2015 and 2016
Concrete overlay is placed over entire pier structure
3-Dimensional ViewsConstruction work taking place between 2015 and 2016
New bridge is constructed
3-Dimensional ViewsTobacco Spillway to be completed in 2016
New gate is installed and stoplogs are removed
3-Dimensional ComparisonExisting spillway Modified spillway
Half of the dam’s spillway capacity will be out of service while the sheet pile cofferdam is in place
The drawdown provides a “buffer” as a precaution so that the spillway structure that is still open can be used to pass enough flood water to avoid dam failure
30 years of data show that rainfall is least in July, August and September◦ While rare, floods have been known to happen in
summer FERC requires it for dam safety
Why will the lake be lowered?
Starting in June, 2014 Wixom Lake will be drawn down 8 feet for five months (until October) then returned to normal levels
The reservoir will be maintained at normal levels during 2015 and 2016 while construction continues behind the stoplogs
The second draw down will start in June, 2017 when construction begins on the pier extensions for the Tittabawasse spillway for five months, then Wixom Lake will be returned to normal levels in the fall and maintained thereafter
When will the lake be lowered?
No. The PMF spillway modification will only increase the dam’s ability to pass flood waters◦ During the drawdown for the Tobacco spillway
construction in the summer of 2014, production and income at the Edenville powerhouse will actually be significantly reduced
◦ The turbines are not able to run at full capacity with so little head water
Will this construction increase the production and income of the dam?
No. When the Edenville (Tittabawassee) spillway is under construction in 2017, electrical production will be shut down completely; there will be no income during this time from the Edenville dam◦ The entire spillway and powerhouse structure will
be blocked off with a cofferdam for five months◦ A powerhouse is designed at the Tobacco spillway,
but its cost is not included in the spillway alteration construction estimates this could be privately financed due to its income-
production capacity
Will this construction increase the production and income of the dam?
Yes. Boyce complies with all FERC-mandated dam safety requirements
The Edenville dam is well maintained and is structurally sound
Dam stability improvements and reinforcing are ongoing for the safety and longevity of the dam◦ Boyce has spent over $1.3 million over the past
six years on these improvements at Edenville Dam alone
Is the dam safe?
Boyce Hydro Power has negotiated with FERC for more than seven years to reduce the PMF requirement◦ Engineers succeeded in reducing the requirement,
but FERC will not eliminate it There is no Federal funding or grant money
available to Boyce to pay for the PMF alterations◦ The PMF Spillway alteration does not qualify for
federal or state grants
The PMF is an “unfunded federal mandate”
Net income after expenses from the operation of the Edenville dam is less than $200,000 per year
The cost of operations continues to rise, i.e. materials, gasoline and diesel fuel, and employee benefits such as health insurance
Private financing is unavailable◦ The dam is already encumbered with debt◦ The PMF spillway alteration does not increase
income
Why can’t Boyce pay for the PMF?
Boyce is paid 30% less by Consumers than the average of all the other 14 independent hydroelectric power producers in the state
The rates being paid to Boyce by Consumers Energy for energy production have not increased in the last seven years◦ There is continued downward pressure from
Consumers on rates, despite increases in energy prices to end users
Why can’t Boyce pay for the PMF?
The cost of this federally-mandated spillway modification project is currently estimated to exceed $8 million
Boyce does not have the capital to support such a massive expense
Grants are also unavailable at this time◦ The State provides some grant money to remove
or repair smaller dams, but not to comply with Federal mandates
We’re all in this together
We all want the same thing: the guaranteed future of Edenville dam and Wixom Lake
Boyce, waterfront residents, and other businesses depend on the reservoir
Public financing is one alternative to pursue Let’s work together to find a solution to this
looming problem
We’re all in this together
Strive to obtain and distribute accurate information
Get involved with local task forces that have been established to work with our elected representatives
We will overcome these issues and ensure the future of Wixom Lake for generations to come by working together
Call to Action