the nep workshop on off–grid electrification in myanmar jan 28 – 29, 2015 state of art minihydro...
TRANSCRIPT
The NEP Workshop On
Off–grid Electrification in MyanmarJan 28 – 29, 2015
State of Art Minihydro Technologies for Electrification
ARUN KUMAR, Ph.D.Chair Professor (Renewable Energy) and CSO,
Alternate Hydro Energy Centre,Indian Institute of Technology Roorkee,Roorkee - 247 667, Uttarakhand, India
E-mail : [email protected], [email protected]
SHP New Technology• Can be installed in existing water infrastructure eg. barrages, dams,
irrigation channel falls and navigation locks;• Located close to villages to serve the users• Have a high level of local contents both in terms of materials and work
force.• Even though hydropower is over 100 years old, each of hydro projects is
unique especially for its civil works. • Efforts are to improve the efficiency of the various components of
hydropower system, • reduce the maintenance and operation cost, • increase the life of the main components, • optimise the utilisation of water especially in view of conflicting
demand, competition with other sources. • The new materials, design and construction techniques• New technologies adopted for weirs, intakes, penstock, controls,
turbines, generators
Run-of-river
Storage/Dam Toe based
Canal Fall/Barrage
In stream
Pumped Storage
Types of SHP schemesMany countries classified as:Pico/village 5 kW & belowMicro 100 kW & belowMini 2 MW & belowSmall 25 MW & belowMedium 100 MW & belowLarge above 100 MW
Types of Hydropower
Run of River: Reservoir Based Hydropower
Canal Fall BasedPumped storage
Low head power plant (90 MW) BIRSFELDEN, (head 3 to 9 m) Rhine
river, Switzerland
Low head power plant (4.5MW) Madhavmantri, (head 4.5 m) Kaveri
River, India
Examples
Social Sector SHPs- • aims to supply electricity specially in stand alone mode, • characterized with poor load factor and of small capacity• often involved in distribution also• Often are fully supported by government• O&M is recovered through user charges collection
Commercial SHPs- • aims to sell electricity to power distributing or trading
companies or for captive use, • are grid connected and are relatively larger capacity• have high load factor• Financially sound Both are required and different level of approach, subsidy, tariff etc are needed
PURPOSE of SHP
6
Transmission line
Guiding water
Rotating unit
Local hydropower on Nam Ngouang
7
Small Hydro owned by individuals
Small Hydro owned by EDC in Combodia
WATER MILLS
In stream- Japan
Hydrodynamic screws
• Example Kindberg, Austria• Head: 3.7 m (< 10 m)• Discharge: 5 m³/s (< 8 m³/s)• Power Output: 142 kW• Efficiency: ~80 %• Speed: 21 rpm• Weight: 24 t, Dia: 3.6 m,
OTHER TURBINE CONCEPTS
Steffturbine
• Head: 2.5 m and above• Discharge: 0.2-0.8 m³/s• Power Output: 5-20 kW• Efficiency: ~80 %
Typical In-Pipe Turbine Generator
[KITL, 2013]
Total Installed Cost (source: IRENA
2014)
LCOE FOR UTILITY AND OFF-GRID POWER
• Diversion weir/ barrage• Power channel/tunnel/pipe• Desilting • Forebay tank/ balancing reservoir• Penstock anchor blocks• Bye pass arrangements/spillways• Power House Building• Tail race channel
Civil worksSHP Technology Components
• EquipmentElectro mechanical works
Transmission and Distribution works• Power evacuation arrangements
• Diversion structureo Damo Spillwayo Energy dissipation arrangemento Fish passo Residual flow arrangements
• Water conveyance systemo Intakeo Canals/pipeso Tunnelso Penstocks
DIFFERENT TYPES OF WEIRS
Material Friction Weight Corrosion Cost Jointing Pressure
Ductileiron
**** * **** ** **** ****
Asbestoscement
*** **** **** *** *** *
Concrete * * ***** *** *** *Wood stave *** *** **** ** **** ***GRP ***** ***** *** * **** *****uPVC ***** ***** **** **** **** *****
Mild steel *** *** *** **** **** *****HDPE ***** ***** ***** ** ** *****
*= poor *****= Excellent
Comparison penstock material
A Plan of a gravity based water network and possible locations of turbines
Energy Recovery on gravity based water supply lines
Recovering energy at this location have no impact on the flow or pressure`
a. Electrical Equipment· Generator (Synchronous and Induction)· Control and Protections· Transformers· HT switchgear· LT switchgear
b. Mechanical Equipment· Hydraulic Turbine· Governor· Inlet control (valve/ gate)· Speed Increaser (low head application)· Advances in Governor Tech.-complete
components.
Electro mechanical equipments
Micro Hydro Quality standard
In view of quick implementation as well as to ensure quality of works “Micro Hydro Quality Standard” was prepared and issued by AHEC, IIT Roorkee India In 2005
Category A(Upto 10 kW)
Category B(Above10kW and upto 50
kW)
Category C (Above 50 kW and upto 100 kW)
Cross FlowPump as turbinePeltonTurgoAxial Flow TurbineAny other turbine meeting the technical requirement
Cross FlowPeltonTurgo ImpulseAxial Flow TurbineFrancisPump as TurbineAny other turbine meeting the technical requirement
Cross FlowPeltonTurgo ImpulseAxial Flow TurbineFrancisAny other turbine meeting the technical requirement
Synchronous/ Induction -Single Phase/3 phase
Synchronous/ Induction3 Phase
Synchronous3 Phase
240 V, 1 –phase, 50 Hz
415 V 3 phase, 50 Hz
415 V, 3 phase, 50 Hz
Standard / Special generators designed to withstand against continuous runaway condition.
CATEGORY WISE RECOMMENDATION
Insulation and Temperature Rise
Class F/H insulation and Class B Temperature rise
Minimum required Weighted Average Efficiency (T Av)0.50 x T100+0.50 T50
45% 50% 60%
Controller (Preferable/Micro processor based)
(ELC) Electronics load controller or IGC Induction Generation Controller
(ELC) Electronic Load Controller (preferred) or IGC Induction Generator Controller
(ELC) Electronic Load Controller or Flow Control Governor
Ballast Load Air heater Water Heater Water heater
Inertia and Flywheel Adequate flywheel should be provided for isolated operation.
Switchgear / Earth Fault Protection
MCB/MCCB for O.C. Protection Provide Earth Leakage Circuit Breaker (ELCB)/Residual current operated circuit breaker
Monitoring & Protection Current, voltage, frequency
Current, voltage, frequencyStator temperatureOvercurrent (stator)Maximum & minimum voltageReverse Power Over/under frequencyBearing temperature
Metering As required.
Case study of “Ramgad MHP” in District Nainital
• Installed Capacity = 100 KW• Year of Installation = 1995 • No. of Unit = 2x50 KW• Net Head = 50 m• Design Discharge = 382 LPS• No. of operators = 1x3(shifts)• Electrician = 1 No.• Electrification = 372 Households • Local Grid Network = 15 Kms. • Operation & Maintained= By Ramgad Urja Samiti having
12 Members from user villages including 30% women members.
Ramgad Micro Hydel Project
Revenue generated
Consumption of Units
Ramgad Micro Hydel Project
Total No. of Unit Generated
Units consumed by villagers
(@ Rs 2 per unit)
100 % of revenue received from Villagers being
provided to Village Energy Committee
Remaining surplus unit are supplied to grid
(Tariff as per UPCL rates @ Rs. 2.85 per unit)
25 % of revenue received from UPCL is being
provided to VEC
75 % to UREDA against capital Investments
The Present Scenario at RamgarhAs on date, the project system is effectively functional and being successfully managed by the user committee. The success is clearly visible in terms of the followings:
5 Trained Operators are operating the plant regularly.
The Plant Load Factor reached up to 80% 100% metering in all the 372 households Tariff as per the UPCL rates. All incandescent bulbs replaced with CFLs. No overloading during peak hour Surplus power generating revenue @ Rs. 2.85 per
unit from the UPCL.
29
Electricity bill collection efficiency increased up to 90%. Regular meetings of user committee. About 1.177 M units of surplus electricity has been fed
into the grid from January, 2005 for which UREDA has received an amount of Rs. 3.3544 M from UPCL.
User committee having Rs. 0. 387 M as bank balance. Replacement of 1000 traditional bulbs with LED Bulb. Installation of 100 LED Street Light in the beneficiary
villages. The project site is being developed as tourist place by
local administration with eco-friendly environment and waterfall.
The above facts display that Ramgad Small Hydro Project is working as a self sustained small hydro project.
Institutional framework
Project Identification Project Allotment
Operation and Maintenance + Capacity
Building
Construction
Clearances and Regulatory Provisions
Financial Closure
SNAs, Community or Private Developers
SNAs
Forest DepartmentIrrigation DepartmentPublic works Deptt, Water supply depttSERC (Tariff Setting)
Government Support- MNRE (CFA), MoP (DDG), RMDD (NREGA), DST, NECCredit Availability- NABARD, REC, Rural BanksPPA- Energy and Power Department
SNAs, Community, Private Developers, Technology
Suppliers , civil contractors, Power
Utilities
Community, SNAs, contractors
Grid Connectivity
State distribution or transmission utility
Off Grid
Existing Ownership Model for off-grid rural electrification
State government
• State Renewable Energy
Development Agencies , or/and • Departments
promoting renewable energy,
or/and • State Utilities,
or/and • The identified
CPSUs
Ownership Implementing agency
Gap between O &M cost and revenue recovery to be reimbursed by the
Implementing Agency out of its service charges
Project developer
State agencies, technology suppliers, Corporate houses, Equipment Manufacturers and Contractors, Self Help
Groups, Users Associations, Individuals, Registered Societies, Cooperatives,
Panchayats, Local bodies, their Consortiums / SPVs /
JVs
Construction
Capacity building for
villagers
Supply of power to villagers
Collection of tariff from villagers
O & M for 5 years (may vary)
Cross linkages with other programmes Backward linkages
Rural electrification policy Central financial Assistance REP scheme Rural Management and
Development Department
Forward linkages Rural development
programmes Use of tail race water for
irrigation as required by the village
Mini and micro hydro projects will be integrated with irrigation, education, health, drinking water, small-scale industry & ropeways
The women’s development, irrigation, drinking water, community saving, health, forests, industries, environmental conservation, road, micro-finance, literacy
campaign programmes, which are conducted at the local level will be implemented by integrating with the rural energy development programmes
Hybrid Energy Generation- power-on-demand from an energy system sourced by intermittent renewable energy source
Typical village loadand Hydro during Lean season
0:001:002:003:004:005:006:007:008:009:0010:0011:0012:0013:0014:0015:0016:0017:0018:0019:0020:0021:0022:0023:00
0
20
40
60
80
100
120
Power Demand Hydro Generation
Time (hour)
Pow
er (
KW
)
AHEC/MNRE/Sept 06 2007 DELHI
To Store
Deficit
Deficit
To Storage
To Storage
Deficit
Deficit
Challenges observed on existing small plants and recommendations
• Capacity development is the key to success for scaling up of SHP programme for planning, oversight, and monitoring; training to all project developers, facilitators, financial institutions and community members; adopting the standard equipments and designs
• Upfront public financing
• Encouraging higher participation of private sector
• Clarity in Policies and regulations
• Setting up and enhancing institutions capacity
• SHP development efforts are more of ad hoc type (lack of experience sharing, absence of business objectives)
for capacity building Areas:PlanningDesign Procurement Execution O&MFinancing Policy
Resources Required:• Human resources • Laboratory • Library • Networking for data,
experts, suppliers, institutions
• Finance
Exclusive academic center of IIT Roorkee focusing on SHP development and recognized as National Resource Centre for Small Hydropower.
Large national database for resource assessment for SHP development and rural electrification created
Real time Digital Simulator for shp plants for training and research.
Expertise for field testing and performance evaluation of SHP stations e.
Prepared the National Standards/ Code of Practices for SHP development.
Imparting training and education
Systematic state master plans for shp and remote village electrification
Alternate Hydro Energy Centre- IIT Roorkee
Real-Time Digital Simulator (RTDS) for Small Hydropower Plant
RTDS at Alternate Hydro Energy Centre IIT Roorkee
ESTABLISHMENT OF R&D HYDRAULIC TURBINE LABORATORYR&D hydro turbine Laboratory of International level at AHEC- IIT Roorkee research & development turbine-model testing, human resource development (HRD) generation of design data design validation through CFD analysis
First independent facility in the regiono Head 15-60 m and discharge 1000 lpso Building 15 x 24 m height +13.5 to – 6.5 mo Water storage 600 cubic m
Laboratory is expected to be commissioned by June 2015
Sponsor- Ministry of New & Renewable Energy, GoI