the project for the planning of the nadi river flood ... · the project for the planning of the...

65
THE REPUBLIC OF FIJI MINISTRY OF AGRICULTURE, RURAL AND MARITIME DEVELOPMENT AND NATIONAL DISASTER MANAGEMENT THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD CONTROL STRUCTURES VOLUMEMAIN REPORT PART: FEASIBILITY STUDY JULY 2016 JAPAN INTERNATIONAL COOPERATION AGENCY (JICA) YACHIYO ENGINEERING CO., LTD. CTI ENGINEERING INTERNATIONAL CO., LTD. GE CR(1) 16-091

Upload: others

Post on 18-Apr-2020

11 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

THE REPUBLIC OF FIJI MINISTRY OF AGRICULTURE, RURAL AND MARITIME DEVELOPMENT AND NATIONAL DISASTER MANAGEMENT

THE PROJECT FOR THE PLANNING OF

THE NADI RIVER FLOOD CONTROL

STRUCTURES

VOLUMEⅡ MAIN REPORT

PARTⅡ: FEASIBILITY STUDY

JULY 2016

JAPAN INTERNATIONAL COOPERATION AGENCY (JICA)

YACHIYO ENGINEERING CO., LTD. CTI ENGINEERING INTERNATIONAL CO., LTD. GE

CR(1)

16-091

Page 2: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

THE REPUBLIC OF FIJI

THE PROJECT FOR THE PLANNING OF

THE NADI RIVER FLOOD CONTROL STRUCTURES

COMPOSITION OF FINAL REPORT

VOLUME I SUMMARY

VOLUME II MAIN REPORT

PartⅠ MASTER PLAN STUDY

PartⅡ FEASIBILITY STUDY

VOLUME I Ⅲ DATA BOOK

PartⅠ DATA BOOK (1)

PartⅡ DATA BOOK (2)

Exchange Rate: FJD 1 = JPY 54.5, 1 USD=FJD 2.17

(As of April, 2016)

Page 3: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

<Map of Project Area>

(出典)Integrated Water Resource Management Demonstration Project

(ビチレブ島)

Namosi River

Nawaka River

Malakua River

Nadi River

Nadi Bay

Page 4: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

Photo

Photo-1 Inception Report Meeting Photo-2 Nadi River Basin (Upstream)

Photo-3 Nadi River Basin(Panoramic view) Photo-4 Nadi River (River Mouth)

Photo-5 Central of Nadi Town Photo-6 Nadi River (Middle Stream)

Photo-7 Nadi River (Upstream) Photo-8 Vaturu Dam (Nadi River Upstream)

Nadi River River Mouth

Nadi Bay

Denarau Area Central of Nadi Town

Nadi River

Page 5: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

Photo-9 Nadi River(Nadi Town Bridge) Photo-10 Nadi River(Nadi Town Bridge)during Flood

Photo-11 Nadi River(Old Queens Road Bridge) Photo-12 Nadi River(Old Queens Road Bridge)during Flood

Photo-13 Nawaka River Photo-14 Retention Dam(Nawaka River)

Photo-15 Counterpart Training in Japan Photo-16 Seminar in Fiji

Nadi River

Water Level Gauge

Nadi River

Nadi River Nadi River

Page 6: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Yachiyo Engineering Co., Ltd. July 2016

i

Executive Summary of

Flood Control Master Plan and Priority Project

in Nadi River Basin

1. Master Plan

【Basic Concept of Master Plan】

- In the Master Plan, based on the flood and river basin characteristics as well as properties in the

upstream, midstream and downstream of the Nadi River, taking into account measures in an entire

basin, comprehensive flood control plan consisting of dam, river improvement, retarding basins and

ring dikes are proposed.

- Taking into account a long term and the large budget to complete the structural measures, and also

taking into account the risk due to flood exceeding design scale, perfect protection measures for

flood inundation are not feasible. Therefore, structural measures and non-structural measures such

are proposed in the Master Plan..

- In the formulation of the Master Plan, it is an important to clarify priority protected areas from the

view point of clarification on the contents of flood control plan and addressing a road map for the

integration of short, middle and long term flood control plan. Therefore, Important Protected Area is

set and it is prioritized to be mitigated from damage by flood.

- The Master Plan is formulated considering Environmental and Social Considerations and Social

Acceptance for flood control

【Target Area of Master Plan】

Target area of Master Plan is Nadi River Basin with catchment area of 516 km2.

【Target Scale of Master Plan】

Design flood scale for Master Plan is set as 1/50 with regard to previous maximum flood event occurred

in March 2012.

【Components of Master Plan】

(1) Structural Measures

Structural Measures as shown in Figure1 and Table1 are proposed in order to mitigate flood damage by

targeted flood in Nadi River Basin.

Page 7: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Yachiyo Engineering Co., Ltd. July 2016

ii

Figure 1 Components of Master Plan (Structural Measures)

Table 1 Components of Master Plan (Structural Measures)

1. Nadi River Downstream (1) Retarding Basin and River

Improvement in downstream

A=725 ha

V=9,715 千m3-

(2) Ring Dike L=1.8 km -Middlestream (3) River Widening

2) L=13 km

(4) Retarding Basin A A=35 ha

V=795 千m3

Retarding Basin B A=178 ha

V=6,920 千m3

Upstream (5) Dam and River improvement in

upstream 1

2. Tributaries (6) River Improvement L=21 km

Retarding Basins (13 sites) A=340 ha

V=11,600 千m3

River, LocationComponent of

the Master PlanQuantities Remarks

Structural

Measures

Including rebuilding of 2

(two) bridges

Nawaka

Maralua

Namosi

River

Including rebuilding of 4

(four) bridges in

tributaries

(2)

(3)

(4)

(5)

(6)

(1) :Retarding Basin in downstream incl. surrounding dike of retarding basin in downstream:River Improvement in downstream

:Ring Dike

:River Widening incl. Rebuilding of 2(two) bridges

:Retarding Basin A,B in upstream

:Dam

:River improvement in upstream

:Retarding Basins in Tributaries incl. surrounding dike

:River Improvement in Tributaries incl. Rebuilding of 4(four) bridges

Page 8: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Yachiyo Engineering Co., Ltd. July 2016

iii

(2) Non-Structural Measures

Non-Structural Measures as shown in Table2 are proposed in order to corroborate and complement structural

measures and mitigate damage by targeted flood.

Table 2 Components of Master Plan (Non-Structural Measures)

Effect of Measure

(Large Classification) Major components

Non-Structural

Measures

(1) Understanding disaster risk and risk

avoidance

1-1) Strengthening of understanding flood risk with flood

hazard map

1-2) Strengthening flood forecasting technology

(2) Enhancing disaster preparedness for

effective response

2-1) Strengthening disaster management system

(3) Disaster risk management, risk

avoidance

3-1) Technical assistant for land-use regulation

3-2) Strengthening river basin management

(4) Economic disaster risk management 4-1) Strengthening economic disaster risk management by

regional BCP

(5) Evaluation and feedback 5-1) Establishing a system of evaluation of Pre-disaster

activity / existing measures and feedback

【Implementation Schedule of Master Plan】

Proposed entire implementation schedule of the Master Plan projects is shown in Table3. Target

implementation period of Master Plan is proposed as 30 years from the project commencement.

Page 9: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Yachiyo Engineering Co., Ltd. July 2016

iv

Table 3 Components of Master Plan and Implementation Schedule (Proposed)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Study on M/P

Detailed Design

1 River channel widening works in midstream section

1) River channel widening works in midstream section, L=13km

2 Retarding basin works in upstream section

1) Retarding basin (A) works in right bank side in Nadi River, A=35ha

2) Retarding basin (B) works in left bank side in Nadi River, A=178ha

3 Ring dike

1) Ring dike, L=1.8km

4 Shortcut in tributaries / Surrounding dike works in Nadi River

1) Shortcut in tributaries, A=0.5km

2) Surrounding dike, L=4.5km

1 Retarding Basin in downstream section (A=km2)

1) Retarding Basin in downstream section, A=725ha

2 River improvement in tributaries

1) Nawaka River, L=8.5km

2) Malakua River , L=8.5km

3) Namosi River , L=4.0km

1 Dam construction in upstream in Nadi River (H= m)

1) Dam construction in upstream in Nadi River

1 Understanding disaster risk and risk avoidance

1-1) Strengthening of understanding flood risk with flood hazard map

1-2) Strengthening flood forecasting technology

2 Enhancing disaster preparedness for effective response

2-1) Strengthening disaster management system

2-2) Strengthening emergency assistance system

3 Disaster risk management, risk avoidance

3-1) Land use regulations

3-2) Strengthening river basin management

4 Economic disaster risk management

4-1) Strengthening economic disaster risk management by regional BCP

5 Establishing a system of evaluation of Pre-disaster activity / existing measures and feedback

5-1) Establishing a system of evaluation of Pre-disaster activity / existing measures and feedback

Note: *including loan agreement, EIA, land acquisition, procurement of consultant (D/D, C/S), detailed design, preparation of PQ and tender document and so on.

20XX-20XX 20XX-20XX

I. Structural Measures

I-B. Middle Term Measures

I-C. Long Term Measures

II. Non-structural Measures

I-A. Priority Project (Short Term Measures)

Work Item

Page 10: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Yachiyo Engineering Co., Ltd. July 2016

v

2.Priority Project

【Basic Concept for selection of Priority Project】

- Taking into account a long term and the large budget to complete the structural measures, and also

taking into account the risk due to flood exceeding design scale, perfect protection measures for

flood inundation are not feasible. Therefore, Priority Project is selected in order to protect important

area and mitigate flood damage.

- Regarding structural measures of Priority Project, components which mitigate flood damage in

Important Protected Area is selected after setting Important Protected Area.

- Regarding non-structural measures of Priority Project, protection of human lives, understanding of

disaster risks and evacuation are considered as a top priority. Based on this concept, components for

understanding of disaster risks and evacuation are selected as Priority Project.

【Components of Priority Project】

(1) Structural Measures

Structural Measures as shown in Figure 3 and Table 4 are proposed in order to mitigate flood damage in

Important Protected Area (Figure 2).

Figure 2 Important Protected Area

Page 11: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Yachiyo Engineering Co., Ltd. July 2016

vi

S

Malakua River

⑥Rebuilding of Bridge ①River Widening: L=13km

① River Widening

② Retarding Basin A, B

③ Surrounding Dike

④ Ring Dike

⑤ Shortcut of tributaries

⑥ Rebuilding of Bridge (Nadi town bridge)

⑦ Rebuilding of Bridge (Old Queens Road bridge)

Component

②Retarding Basin A: A=35haRetarding Basin B: A=178ha

(Water Surface Area in flooding)

⑥Rebuilding of Bridge: L=108m

⑦Rebuilding of Bridge: L=96m

③Surrounding Dike: L=4.5km

④Ring Dike: L=1.8km

⑤Shortcuts: L=0.5km

Figure 3 Components of Priority Project (Structural Measures)

Table 4 Components of Priority Project (Structural Measures)

Quantities

1. Nadi River Downstream (1) Retarding Basin and River

Improvement in downstream - -

(2) Ring Dike ④ Ring Dike L=1.8 km -Middlestream (3) River Widening

2) ① River Widening

Rebuilding of Nadi TOwn Bridge

Rebuilding of Old Queens Road Bridge

L=13 km

L=108 m

L= 96 m

(4) Retarding Basin A ② Retarding Basin A A=35 ha

V=795 千m3

Retarding Basin B ② Retarding Basin B A=178 ha

V=6,920 千m3

Upstream (5) Dam and River improvement in

upstream -

2. Tributaries (6) River Improvement ⑤③-2

Shortsut of Tributaries

Surrounding Dike of Nadi Town

L=0.5 km

L=4.5 km

Retarding Basins (13 sites)-

Shortcut and Surrounding dike in

tributaries are preceded to

construction as part of the master

plan―

Component of the Priority ProjectRemarks

Main Component

Structural

Measures ―

Nawaka

Maralua

Namosi

River

River, LocationComponent of

the Master Plan

(2) Non-Structural Measures

Protection of human lives, understanding of disaster risks and evacuation are considered as a top priority,

under condition that the progress of structural measures project will be at initial phase. Therefore, activities

accompanied with development and disclosure of hazard maps and development of hydrological devices for

awareness of flood risks are proposed as Priority project. In addition, in order to evaluate the effect of

non-structural measures in the past or priority projects, and in order to connect to “Better disaster prevention”,

evaluation and feedback system on the past projects is also proposed as Priority Project.

Component

① River Widening

② Retarding Basin A, B

③ Srrounding Dike

④ Ring Dike

⑤ Shortcut in tributaries

⑥ Rebuilding of Bridges

Page 12: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Yachiyo Engineering Co., Ltd. July 2016

vii

Table 5 Components of Priority Project (Non-Structural Measures)

Category Measures Non-structural Measures

Understanding disaster risk and risk avoidance

Strengthening of understanding flood risk with flood hazard map

Strengthening flood forecasting technology, such as expansion of rainfall gauge, water level gauge and introduction of real-time monitoring camera

Better Disaster Prevention Establishing a system of evaluation of Pre-disaster activity / existing measures and feedback

【Selection of Implementation Project】

Integrated flood control facilities considering whole river basin have not been installed yet in spite of effectiveness of structural measures and implementation of structural measures such as dam, retarding basin, and river are required urgently. Therefore, structural measures of Priority Project are selected as Implementation Project.

【Objective of Implementation Project】

Objective of Implementation Project is to improve of vulnerability to flood in Nadi River Basin, mitigate flood damage specially in Important Protected Area and contribute to improve living environment of residents by developing flood control facilities such as river widening and retarding basin in Nadi River Basin, which has been damaged by severe flood.

【Components of Implementation Project】

Components of Implementation Project is as shown in Figure 4 and Table 6, which are as same as structural measures of Priority Project.

Page 13: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Yachiyo Engineering Co., Ltd. July 2016

viii

S

Malakua River

⑥Rebuilding of Bridge ①River Widening: L=13km

① River Widening② Retarding Basin A, B③ Surrounding Dike④ Ring Dike⑤ Shortcut of tributaries⑥ Rebuilding of Bridge (Nadi town bridge)⑦ Rebuilding of Bridge (Old Queens Road bridge)

Component

②Retarding Basin A: A=35haRetarding Basin B: A=178ha

(Water Surface Area in flooding) ⑥Rebuilding of Bridge: L=108m

⑦Rebuilding of Bridge: L=96m③Surrounding Dike: L=4.5km

④Ring Dike: L=1.8km

⑤Shortcuts: L=0.5km

Figure 4 Components of Implementation Project (Structural Measures)

Table 6 Components of Implementation Project (Structural Measures)

Quantities1. Nadi River Downstream (1) Retarding Basin and River

Improvement in downstream - -

(2) Ring Dike ④ Ring Dike L=1.8 km -

Middlestream (3) River Widening2) ① River WideningRebuilding of Nadi TOwn BridgeRebuilding of Old Queens Road Bridge

L=13 kmL=108 mL= 96 m

(4) Retarding Basin A ② Retarding Basin A A=35 haV=795 千m3

Retarding Basin B ② Retarding Basin B A=178 haV=6,920 千m3

Upstream (5) Dam and River improvement inupstream -

2. Tributaries (6) River Improvement ⑤③-2

Shortsut of TributariesSurrounding Dike of Nadi Town

L=0.5 kmL=4.5 km

Retarding Basins (13 sites)-

Shortcut and Surrounding dike intributaries are preceded toconstruction as part of the masterplan―

Component of the Priority ProjectRemarks

Main ComponentStructuralMeasures ―

NawakaMaraluaNamosiRiver

River, Location Component ofthe Master Plan

【Implementation Schedule of Implementation Project】

Implementation Schedule of Implementation Project is as shown in Table 8.

【Implementation Project 】

Implementation Project Cost is as shown in Table 9.

Component① River Widening② Retarding Basin A, B③ Srrounding Dike④ Ring Dike⑤ Shortcut in tributaries⑥ Rebuilding of Bridges

Page 14: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Yachiyo Engineering Co., Ltd. July 2016

ix

【Economic Feasibility of Implementation Project】

Total cost of the priority project is JPY21.0 billion (F$385million) and the average annual benefit is JPY 1.88billion (F$34.5million). These figures lead to EIRR 12.0%, B/C=1.2 and NPV JPY1.8billion (F$33million) respectively. This economic valuation is beyond the target investment rate of 10% in Fiji and show the adequate economic effect.

Table 7 Result of Economic Evaluation

Economic indicator Result Evaluation

Economic internal rate of return (EIRR)

12.0% Since EIRR is well over 10% which is applied to the development assistance project in Fiji, the economic effectiveness is high.

Benefit-cost (B/C) ratio 1.20 Since the B/C ratio is over 1.0, the cost-effectiveness is high.

Net present value (NPV) JPY 1.8 billion (FJD33 million)

Since the value is plus, the cost-effectiveness is high.

Source: JICA study team

【Conclusion and Recommendation】

Implementation Project proposed as one of the Priority Project is evaluate appropriate since it could mitigate severe flood damage and it is feasible technically, economically, socially and environmentally. Therefore, next steps such as securing budget and request for technical assistance as follows are recommended to be conducted by Fiji Government as soon.

(1) Implementation of the Priority Project and establishment of Implementation Structure

(2) Formulation consensus of Government and residents for the Implementation

(3) Commencement of loan procedure for project fund

(4) Commencement of negotiation for land acquisition and compensation

(5) Commencement of consultant procurement and environmental monitoring

(6) Establishment of legislation of flood control

(7) Preparation and consolidation of organization responsible for flood control and capacity building

(8) Preparation of criteria and standard

(9) Permanent securement of maintenance budget for flood control

Page 15: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Yachiyo Engineering Co., Ltd. July 2016

x

Table 8 Implementation Schedule of Implementation Project (Proposed)

Implementation ScheduleMonth

8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7

1

1

1 1 1 1 1 1 1 1 1 1 1 1

1 1 1 1 1 1 1 1 1 1 1 1

1 1 1

1 1

1 1

1

1 1

1

1

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

1 1 1 1 1 1 1 1 1 1 1 1

1 1 1 1 1 1 1 1 1 1 1 1

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

501 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

261 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

261 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

381 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

7 0 0 0 0 0

0 6 12 12 8 0Package 4 Surrounding Dike

0 0 0 0

6 12 8 0 0Package 3 Ring Dike

0 0 0 0 0

6 12 8 0 0 0Package 2 Retarding Basin

0 0 0 0

12 12 12 8 0Package 1 River Widening

0 0 0 0 6

Land Acquisition 350 4 12 12

Construction Supervision (50 months) 50

Project Management Unit Supporting (84 months) 84

0

Consulting Services (84 months) 84

Detailed Design (12 months) 12

Tender Assistance (12 months) 12

Pledge 1

Signing of Loan Agreement 1

0

Opening of L/C and Ussurance of L/Com (1 month) 1

Selection of Consultant (12 months) 12

0

2021 2022 2023 20242015 2016 2017 2018 2019 2020

Tender Assistance (12 months) 12

Preparation of Bid Document & JICA Concurrence (3 months) 3

Tender Period (2 months) 2

JICA Approval of Contract (1 month) 1

Evaluation of Bids (2months) 2

JICA Concurrence of Bid Evaluation (1 month) 1

Contract Negotiation (2 months) 2

Defect Liability Period

Defect Liability Period

Defect Liability Period

Defect Liability Period

*Year in above table shows the fiscal year of Fiji (August 1st to July 31th of following year)

Page 16: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Yachiyo Engineering Co., Ltd. July 2016

xi

Table 9 Project Cost of Implementation Project

(FC&Total: Million JPY, LC: Million FJD)

FC LCmillion(Yen)

million(F$)

million(Yen)

million(F$)

A. ELIGIBLE PORTIONⅠ) Procurement / Construction 6,778 134 14,074 258

Package 1 River Widening, Rebuilding of Bridge 4,213 77 8,432 155

Package 2 Retarding Basin 1,281 19 2,299 42

Package 3 Ring Dike 40 1 76 1

Package 4 Surrounding Dike 392 5 657 12

Base cost for JICA financing 5,926 102 11,464 210

Price escalation 529 26 1,940 36

Physical contingency 323 6 670 12

Ⅱ) Consulting services 933 18 1,893 35

Base cost 828 14 1,579 29

Price escalation 60 3 223 4

Physical contingency 44 1 90 2

Total (Ⅰ+Ⅱ) 7,711 151 15,967 293

B. NON ELIGIBLE PORTIONa Procurement / Construction 0 0 0 0

Base cost for JICA financing 0 0 0 0

Price escalation 0 0 0 0

Physical contingency 0 0 0 0

b Land Acquisition 0 38 2,093 38

Base cost 0 34 1,845 34

Price escalation 0 3 148 3

Physical contingency 0 2 100 2

c Administration cost 0 17 903 17

d VAT 0 30 1,625 30

e Import Tax 0 0 0 0

Total (a+b+c+d+e) 0 85 4,621 85

TOTAL (A+B) 7,711 236 20,588 3780

C. Interest during Construction 351 0 351 6

Interest during Construction(Const.) 350 0 350 6

Interest during Construction (Consul.) 1 0 1 0

D. Front End Fee 32 0 32 1

GRAND TOTAL (A+B+C+D) 8,094 236 20,971 385

E. JICA finance portion (A) 7,711 151 15,967 293

TotalItem

Total

US$1=2.17 F$, 1F$= JPY 54.5

Page 17: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

略 語

ADB Asian Development Bank アジア開発銀行

ADRA Adventist Development and Relief Agency アドベンチスト開発救助機関

AusAID Australian Agency for International Development オーストラリア国際開発庁

BCP Business Continuity Plan 事業継続計画

BOM Bureau Of Meteorology オーストラリア気象局

CBD Convention on Biological Diversity 生物多様性条約

CCA Climate Change Adaptation 気候変動適応

CCL Climate Change Loan 気候変動対策円借款

CCM Climate Change Mitigation 気候変動緩和

CHARM Comprehensive Hazard And Risk Management 統合的ハザード・リスク管理

C/P Counterpart カウンターパート

CRED Centre for the Research on the Epidemiology of Disaster 災害の疫学に関する研究センター

CWO Commissioner Western Office 西部地域長官室

DEM Digital Elevation Model デジタル標高モデル

DF/R Draft Final Report ドラフトファイナルレポート

DIS Drainage & Irrigation Section 排水・灌漑部門

DISMAC Disaster Management Centre 災害管理センター

DMP Disaster Management Plan 防災計画書

DOE Department of Environment 環境局

DOFi Department of Fishery 漁業局

DOF0 Department of Forest 森林局

DOL Department of Lands 土地局

DO-N / DO District Nadi Office / District Office ナンディ地区事務所/地区事務所

DOW Department of Works 公共事業局

DRCC Disaster Ready Community Committee 災害自立型コミュニティ委員会

DRR Disaster Risk Reduction 災害リスク軽減

DRRDM Disaster Risk Reduction & Disaster Management 災害リスク軽減・災害管理

DTCP Department of Town & Country Planning 都市/地方計画局

EDF European Development Fund ヨーロッパ開発基金

EIA Environmental Impact Assessment 環境影響評価

EiE Education in Emergencies 緊急時の教育

EOC Emergency Operation Center 緊急対策室

EPGA Environmental Programme Grant Aids 環境プログラム無償資金協力

EU European Union 欧州連合

EWS Early Warning System 早期警報システム

FBS Fiji Bureau of Statistics フィジー統計局

FMS Fiji Meteorological Service フィジー気象局

F/R Final Report ファイナルレポート

Page 18: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

FRA Fiji Road Authority フィジー道路公社

F/S Feasibility Study フィジビリティ調査

FSC Fiji Sugar Corporation フィジー砂糖会社

GDP Gross National Product 国民総生産

GEF Global Environmental Facility 地球環境ファシリティ

GGP Grant Assistance for Grassroots Human Security Projects 草根の無償/草の根・人間の安全保障

無償資金協力

GIS Geographical Information System 地理情報システム

GNI Gross National Income 国民総所得

HFA Hyogo Framework for Action 兵庫行動枠組み

IC/R Inception Report インセプションレポート

IDA Initial Damage Assessment 初期損害評価

IDD Irrigation & Drainage Division 灌漑・排水部門

IDM Introduction of Disaster Management 災害管理の導入

IEE Initial Environmental Examination 初期環境調査

IRC International Red Cross 国際赤十字

IT/R Interim Report インテリムレポート

IWRM Integrated Water Resource Management 統合水資源管理

JCC Joint Coordination Committee 合同調整委員会

JICA Japan International Cooperation Agency 独立行政法人 国際協力機構

KP Kyoto Protocol 京都議定書

LRPD Department of Land Resource Planning & Development 土地資源計画・開発局

LWRM Land &Water Resource Management 土地水資源管理部

MDGs Millennium Development Goals ミレニアム開発目標

MFA&IC Ministry of Foreign Affairs & International Co-operation 外務・国際協力省

MFSPNDS Ministry of Finance Strategic Planning, National Development & Statistics 財務戦略計画・国家開発・統計省

MLGUDHE Ministry of Local Government, Urban Development, Housing &Environment

地方行政・都市開発・住宅・環境省

MLMR Ministry of Lands & Mineral Resources 土地鉱物資源省

M/M Minutes of Meeting 会議議事録

MOA Ministry of Agriculture 農業省

MOU Memorandum Of Understanding 覚書

M/P Master Plan 基本計画

MP Radar Multi Parameter Radar マルチパラメータ気象レーダ

MRMSNDM Ministry of Rural & Maritime Safety & National Disaster Management 地域・海上保安・国家災害管理省

MTCP Ministry of Town and Country Planning 都市計画省

MWTPU Ministry of Works, Transport & Public Utilities 公共事業・運輸・公益事業省

NBCC Nadi Basin Catchment Committee ナンディ流域委員会

NCCP National Climate Change Policy 国家気候変動政策

NDMC National Disaster Management Council 国家災害管理評議会

Page 19: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

NDMO National Disaster Management Office 国家災害管理室

NEOC National Emergency Operation Centre 国家緊急オペレーション・センター

NIWA The National Institute of Water and Atmospheric Research 水・大気研究国立機関

NTC Nadi Town Council ナンディ町議会

NZAID New Zealand Agency for International Development ニュージーランド国際開発庁

O&M Operation and Maintenance 運用維持管理

OCHA Office for the Coordination of Humanitarian Affairs 国連人道問題調整事務所

ODA Official Development Assistance 政府開発援助

OJT On the Job Training 実地訓練

PCIDRR The Pacific Community-focused Integrated Disaster Risk

Reduction

大洋州コミュニティ統合的災害リスク削

PDM Project Design Matrix プロジェクトデザインマトリックス

PDN Pacific Disaster Net 大洋州災害ネット

PDRMP Pacific Disaster Risk Management (Training) Programme 大洋州災害リスク管理(研修)プログラム

PDRMPN Pacific Disaster Risk Management Partnership Network 大洋州災害リスク管理パートナーシップ・ネットワーク

PHT The Pacific Humanitarian Team 大洋州人道チーム

PIFACC Pacific Islands Framework for Action on Climate Change 大洋州気候変動行動枠組み

PMO Prime Minister Office 首相府

PMU Project Management Unit プロジェクト・マネジメント・ユニット

P/R Progress Report プログレスレポート

PRMS Planning & Resource Management Section 計画・資源管理部門

PRSP Poverty Reduction Strategy Paper 貧困削減戦略文書

PWD Public Works Division 公共事業部

RAP Resettlement Action Plan 住民移転計画

R/D Record of Discussion 討論議事録

RES River Engineering Section 河川エンジニアリング部門

SOP Standard Operation Procedure 標準作業手順書

SOPAC South Pacific Applied Geoscience Commission 太平洋諸島応用科学委員会

SPC Secretariat for the Pacific Community 太平洋コミュニティ事務局

SPCZ South Pacific Convergence Zone 南太平洋収束帯

SPREP South Pacific Regional Environment Programme 大洋州環境プログラム事務局

TC Tropical Cyclone 熱帯性サイクロン

TLTB iTauke Land Trust Board イ・タウケイ土地信託委員会

ToT Training of Trainers 指導員研修

UNCCD United Nations Convention to Combat Desertification 国連砂漠化防止条約

UNDP United Nations Development Programme 国連開発計画

UNESCAP United Nations Economic & Social Commission for Asia & the Pacific

国連アジア太平洋経済社会委員会

UNFCCC United Nations Framework Convention on Climate Change 国連気候変動枠組条約

UNICEF United Nations International Children's Emergency Fund 国連国際児童緊急基金

UNISDR United Nations International Strategy for Disaster 国連国際防災戦略

Page 20: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

Reduction

UNOCHA United Nations Office for Coordination of Humanitarian Affairs 国連人道問題支援室

USAID United State Agency for International Development 米国国際開発庁

WAF Water Authority of Fiji フィジー水公社

WB World Bank 世界銀行(世銀)

WMO World Meteorological Organization 世界気象機関

WMS Watershed Management Section 流域管理部門

Page 21: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

i

THE REPUBLIC OF FIJI THE PROJECT FOR THE PLANNING OF

THE NADI RIVER FLOOD CONTROL STRUCTURES

FINAL REPORT VOLUME II MAIN REPORT

Part II: Feasibility Study

Table of Contents

Map of Project Area

Photo

Executive Summary of Flood Control Master Plan and Priority Project in Nadi River Basin

Abbreviation

Chapter 17 Components of Feasibility Study .................................................................................... 17-1

Chapter 18 Preliminary Design ........................................................................................................... 18-1

18.1 River Widening ...................................................................................................................... 18-1

18.1.1 Applicable standards for design ......................................................................................... 18-1

18.1.2 Plan and Area ..................................................................................................................... 18-1

18.1.3 Longitudinal Plan ............................................................................................................... 18-7

18.1.4 Cross-Sectional Plan ........................................................................................................ 18-10

18.2 Retarding Basin A, B ........................................................................................................... 18-15

18.2.1 Retarding Basin A ............................................................................................................ 18-15

18.2.2 Retarding Basin B ............................................................................................................ 18-21

18.3 Surrounding Dike of Nadi Town .......................................................................................... 18-26

18.4 Ring Dike ............................................................................................................................. 18-29

18.5 Shortcuts of tributaries ......................................................................................................... 18-31

18.6 Rebuilding of Bridges .......................................................................................................... 18-33

18.6.1 Basic Condition for Bridge Design .................................................................................. 18-33

18.6.2 Preliminary Design of Nadi Town Bridge ........................................................................ 18-46

18.6.3 Preliminary Design of Old Queens Road Bridge ............................................................. 18-54

18.7 Approximate Construction Quantity .................................................................................... 18-64

18.7.1 Approximate Construction Quantity ................................................................................ 18-64

18.7.2 Land Acquisition and Compensation ............................................................................... 18-66

18.8 Construction Planning .......................................................................................................... 18-66

Page 22: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

ii

18.8.1 River Works ..................................................................................................................... 18-67

18.8.2 Bridge Works ................................................................................................................... 18-88

18.8.3 Whole Construction Work Schedule .............................................................................. 18-118

Chapter 19 Project Cost Estimation ................................................................................................... 19-1

19.1 Project Cost Estimation System ............................................................................................. 19-1

19.2 Project Cost Unit Price Estimation ......................................................................................... 19-3

19.3 Quantity of Each Work Item .................................................................................................. 19-7

19.4 Project Cost Estimation .......................................................................................................... 19-9

Chapter 20 Project Implementation Plan........................................................................................... 20-1

20.1 Purpose of the Project ............................................................................................................ 20-1

20.2 Target Area ............................................................................................................................. 20-1

20.3 Project Overview .................................................................................................................... 20-1

20.3.1 Overview of the Overall Project Plan ................................................................................. 20-1

20.3.2 Contents of Construction Works ........................................................................................ 20-1

20.3.3 Contents of Consulting Services ........................................................................................ 20-3

20.4 Project Cost and Financial Planning ...................................................................................... 20-4

20.4.1 Calculation of Project Cost ................................................................................................. 20-4

20.4.2 Financial Plan ..................................................................................................................... 20-6

20.5 Project Implementing Schedule .............................................................................................. 20-8

20.6 Procurement Method ............................................................................................................ 20-10

20.6.1 Procurement of Consultants ............................................................................................. 20-10

20.6.2 Procurement of Contractors .............................................................................................. 20-10

20.7 Project Implementing Structure............................................................................................ 20-11

20.7.1 Borrower........................................................................................................................... 20-11

20.7.2 Project Implementing Organization ................................................................................. 20-11

20.7.3 Project Management Unit (PMU) .................................................................................... 20-12

20.8 Operation and Maintenance System ..................................................................................... 20-12

20.9 Performance Indicator .......................................................................................................... 20-13

Chapter 21 Economic Feasibility of the Project ................................................................................ 21-1

21.1 Purpose of economic evaluation .................................................................................................... 21-1

21.2 Preconditions ................................................................................................................................. 21-1

21.2.1 Evaluation Period ................................................................................................................ 21-1

21.2.2 Price level, price escalation ................................................................................................. 21-1

21.2.3 Economic Price ................................................................................................................... 21-2

Page 23: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

iii

21.2.4 Social Discount Rate (SDR) ................................................................................................ 21-2

21.3 Project Cost .................................................................................................................................... 21-2

21.4 Benefits .......................................................................................................................................... 21-2

21.4.1 Method for calculating benefits ........................................................................................... 21-2

21.4.2 Asset data gathering and organizing ................................................................................... 21-3

21.5 Damage and loss calculation ......................................................................................................... 21-6

21.5.1 Method of damage and loss calculation .............................................................................. 21-6

21.5.2 Damage ............................................................................................................................... 21-9

21.5.3 Loss ................................................................................................................................... 21-11

21.6 Economic evaluation ................................................................................................................... 21-18

21.7 Sensitivity analysis ...................................................................................................................... 21-21

21.7.1 Purpose of sensitivity analysis .......................................................................................... 21-21

21.7.2 Considerations for sensitivity analysis .............................................................................. 21-21

21.7.3 Result of sensitivity analysis ............................................................................................. 21-21

Chapter 22 Environmental and Social Considerations ..................................................................... 22-1

22.1 Project Descriptions ............................................................................................................... 22-1

22.1.1 Project Area ........................................................................................................................ 22-1

22.1.2 Project Components ........................................................................................................... 22-1

22.1.3 Outline of Flood Control Measures (Structural Measures) ............................................. 22-1

22.1.4 Outline of Flood Control Measures (Non-Structural Measures) .................................... 22-2

22.1.5 Examination of Alternatives ............................................................................................... 22-2

22.1.6 Construction Plan and Schedule ......................................................................................... 22-6

22.2 Survey Results on Environmental and Social Considerations ................................................ 22-8

22.2.1 Air quality .......................................................................................................................... 22-8

22.2.2 Water Pollution ................................................................................................................ 22-10

22.2.3 Wastes (including excavated materials) ........................................................................... 22-12

22.2.4 Soil Contamination (Riverbed materials) ......................................................................... 22-13

22.2.5 Noise and Vibration ......................................................................................................... 22-15

22.2.6 Offensive Odor ................................................................................................................. 22-17

22.2.7 Hydrological Situation (River flow) ................................................................................. 22-17

22.2.8 Fresh Water Ecology ........................................................................................................ 22-19

22.2.9 Land Area Ecology and Vegetation ................................................................................. 22-21

22.2.10 Ecosystem......................................................................................................................... 22-26

22.2.11 Topography ...................................................................................................................... 22-26

22.2.12 Involuntary Resettlement ................................................................................................. 22-27

22.2.13 Poverty Group .................................................................................................................. 22-31

22.2.14 Indigenous groups ............................................................................................................ 22-32

Page 24: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

iv

22.2.15 Local Economy such as Employment and Livelihood ..................................................... 22-32

22.2.16 Land Use and Utilization of Local Resources .................................................................. 22-33

22.2.17 Water Utilization .............................................................................................................. 22-33

22.2.18 Existing Social Infrastructures and Services .................................................................... 22-34

22.2.19 Misdistribution of Benefits and Damage .......................................................................... 22-35

22.2.20 Cultural Heritage .............................................................................................................. 22-35

22.2.21 Landscape ......................................................................................................................... 22-36

22.2.22 Infectious Diseases such as HIV/AIDS ............................................................................ 22-36

22.2.23 Labor Environment (Including Occupational Safety) / Accident ..................................... 22-37

22.3 Impact Assessment ............................................................................................................... 22-38

22.3.1 Comparison of Scoping and Impact Assessment based on Survey Results ..................... 22-38

22.3.2 Conclusion of Environmental Impact Assessment ........................................................... 22-45

22.4 Environmental Management Plan ........................................................................................ 22-46

22.4.1 Environmental Management Plan during Construction ................................................... 22-46

22.4.2 Environmental Management Plan during Operation ........................................................ 22-50

22.4.3 Organization Chart for Environmental Management and Monitoring ............................. 22-54

22.5 Environmental Monitoring Plan ........................................................................................... 22-56

22.5.1 Environmental Monitoring Plan on Pollution .................................................................. 22-56

22.5.2 Environmental Monitoring Plan on Natural Environment ............................................... 22-59

22.5.3 Environmental Monitoring Plan on Social Environment ................................................. 22-60

22.6 Abbreviated Resettlement Action Plan ................................................................................ 22-62

22.6.1 Project Components ......................................................................................................... 22-62

22.6.2 Objectives of Abbreviated Resettlement Action Plan ...................................................... 22-62

22.6.3 Regal Framework for Land Acquisition and Resettlement .............................................. 22-62

22.6.4 Gaps between JICA Guideline and Fiji’s legal Frameworks............................................ 22-63

22.6.5 Scope of Resettlement Impact .......................................................................................... 22-67

22.6.6 Entitlement Matrix ........................................................................................................... 22-69

22.6.7 Responsible Institutions of Land Acquisition and Resettlement ...................................... 22-70

22.6.8 Land Acquisition and Resettlement Procedures ............................................................... 22-70

22.6.9 Implementation Organization ........................................................................................... 22-71

22.6.10 Responsible Institutions and Mechanism of Grievance Redress ...................................... 22-72

22.6.11 Resettlement Implementation Schedule ........................................................................... 22-72

22.6.12 Cost and Fund Source of Land Acquisition and Resettlement ......................................... 22-73

22.6.13 Monitoring Framework by Implementation Institutions .................................................. 22-75

22.7 Public Consultations and Stake Holders Meetings ............................................................... 22-76

22.7.1 Outline .............................................................................................................................. 22-76

22.7.2 Participants and major opinions ....................................................................................... 22-76

Page 25: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

v

Chapter 23 Project Evaluation and Recommendations .................................................................... 23-1

23.1 Project Evaluation g ............................................................................................................... 23-1

23.1.1 Economic Valuation ........................................................................................................... 23-1

23.1.2 Financial Valuation ............................................................................................................ 23-1

23.1.3 Environmental Impact Evaluation ...................................................................................... 23-1

23.2 Recommendations for the Implementation of the Project ...................................................... 23-2

23.2.1 Recommendations for the Implementation of the project ................................................... 23-2

23.2.2 Recommendations for Inland water Drainage ..................................................................... 23-3

23.2.3 Recommendations for Mitigation and Management of Disaster Risk ................................ 23-4

Chapter 24 Phasing of the Priority Project (Study for Reference) .................................................. 24-1

24.1 Basic Concept of Phasing ....................................................................................................... 24-1

24.2 Phasing ................................................................................................................................... 24-1

24.2.1 Phasing Case ...................................................................................................................... 24-1

24.2.2 Effectiveness of Phasing(Flood Analysis Result) ......................................................... 24-2

24.2.3 Project Cost of Phasing Project ........................................................................................ 24-12

24.2.4 Benefit of Phasing Project ................................................................................................ 24-12

24.2.5 Economic Evaluation after Phasing .................................................................................. 24-13

24.3 Summary .............................................................................................................................. 24-13

List of Table

Table 17 1 Components of the Feasibility Study .............................................................................................................. 17-1

Table 18 1 Longitudinal Feature (Nadi River) .................................................................................................................... 18-9

Table 18 2 Design Embankment Free-Board .................................................................................................................... 18-10

Table 18 3 Top of Bank Width.......................................................................................................................................... 18-11

Table 18 4 Inspection Passage .......................................................................................................................................... 18-11

Table 18 5 Flood Flow velocity ........................................................................................................................................ 18-14

Table 18 6 Specifications for Retarding Basin A at the Priority Project ........................................................................... 18-15

Table 18 7 Specifications for Retarding Basin B at the Priority Project ........................................................................... 18-21

Table 18 8 Longitudinal Plan of Surrounding Dike of Nadi Town ................................................................................... 18-27

Table 18 9 Major Technical Standards and Reference Documents ................................................................................... 18-33

Table 18 10 Minimum Curve Radius ................................................................................................................................ 18-35

Table 18 11 River Condition (Nadi Town Bridge) ............................................................................................................ 18-41

Table 18 12 River Condition (Old Queens Road Bridge) ................................................................................................. 18-42

Table 18 13 Load Combination for Serviceability Limit State ......................................................................................... 18-45

Table 18 14 Load Combination for Ultimate Limit State .................................................................................................. 18-45

Page 26: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

vi

Table 18 15 Draft Comparison of Bridge Type(Nadi Town Bridge) ........................................................................... 18-50

Table 18 16 Comparison & Selection of Bridge Type(Nadi Town Bridge) ................................................................. 18-51

Table 18 17 Abutment Types and Standard Heights ......................................................................................................... 18-52

Table 18 18 Selection of Foundation Type(Nadi Town Bridge) .................................................................................. 18-53

Table 18 19 Comparison of Bridge Type (Old Queens Road Bridge -Road Bridge-) ....................................................... 18-59

Table 18 20 Comparison & Selection of Bridge Type(Old Queens Road Bridge -Road Bridge-) ............................... 18-60

Table 18 21 Comparison of Bridge Type (Old Queens Road Bridge -Tramline Bridge-) ................................................. 18-60

Table 18 22 Comparison & Selection of Bridge Type(Old Queens Road Bridge -Tramline Bridge-) ......................... 18-61

Table 18 23 Abutment Types and Standard Heights ......................................................................................................... 18-62

Table 18 24 Selection of Foundation Type(Old Queens Road Bridge) ........................................................................ 18-63

Table 18 25 Approximate Construction Quantity (River Works) ..................................................................................... 18-64

Table 18 26 Approximate Construction Quantity (Bridge Works) ................................................................................... 18-65

Table 18 27 Land Acquisition Area .................................................................................................................................. 18-66

Table 18 28 Number of house relocations and affected houses......................................................................................... 18-66

Table 18 29 Main works of river works of the Priority Project ......................................................................................... 18-67

Table 18 30 Division of Construction Section .................................................................................................................. 18-68

Table 18 31 Typical specifications and work quantity of temporary cofferdam ............................................................... 18-76

Table 18 32 Comparison of Mean High Water Spring and Maximum Water Level in Non-flood Season ....................... 18-76

Table 18 33 Acceptable total volume of disposal soil (Rough Estimation) ....................................................................... 18-78

Table 18 34 Suspended days (ratio) by rainfall ................................................................................................................. 18-81

Table 18 35 Calculation of increase coefficient of workable days .................................................................................... 18-81

Table 18 36 Selected Heavy Equipment ........................................................................................................................... 18-82

Table 18 37 Construction Period (River Work) ................................................................................................................ 18-83

Table 18 38 Work Schedule(River Work) ................................................................................................................... 18-84

Table 18 39 Disposal Sites ................................................................................................................................................ 18-85

Table 18 40 Number of Transportation Days and Dump Trucks for Disposal .................................................................. 18-87

Table 18 41 Structural Dimension of Existing Bridge(Nadi Town Bridge) ................................................................. 18-94

Table 18 42 Plan of new Substructure and Foundation (Nadi Town Bridge) .................................................................... 18-97

Table 18 43 Superstructure Reconstruction Plan (Nadi Town Bridge) ............................................................................. 18-99

Table 18 44 Process Scheduling (Nadi Town Bridge) .................................................................................................... 18-102

Table 18 45 Structural Dimension of Existing Bridge (Old Queens Road Bridge) ......................................................... 18-108

Table 18 46 Estimation of Water Level and Discharge in Non-flood Season in Diversion Work .................................. 18-112

Table 18 47 Plan of new Substructure and Foundation (Old Queens Road Bridge) ....................................................... 18-113

Table 18 48 Superstructure Reconstruction Plan (Old Queens Road Bridge) ................................................................. 18-116

Table 18 49 Process Scheduling (Old Queens Road Bridge) .......................................................................................... 18-118

Table 18 50 Whole Construction Work Schedule ........................................................................................................... 18-119

Table 19-1 Ratio of foreign currency (FC) and local currency (LC) of unit prices ............................................................. 19-3

Table 19-2 Unit Prices for river work project cost estimation ............................................................................................ 19-4

Table 19-3 Unit Prices for bridge work project cost estimation (1) .................................................................................... 19-5

Table 19-4 Unit Prices for Bridge work project cost estimation (2) .................................................................................... 19-6

Table 19-5 Cost for Consulting Service .............................................................................................................................. 19-7

Table 19-6 Quantity of Each Work Item of River Improvement......................................................................................... 19-7

Table 19-7 Quantity of Each Work Item of Bridge work .................................................................................................... 19-8

Table 19-8 Quantity of Each Work Item of Site acquisition ............................................................................................... 19-9

Page 27: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

vii

Table 19-9 Number of houses to be affected and relocated by the project .......................................................................... 19-9

Table 19-10 Project Cost ................................................................................................................................................... 19-10

Table 19-11 Base Cost of Each Package ........................................................................................................................... 19-11

Table 19-12 Construction Cost (Package-1: River Widening) .......................................................................................... 19-11

Table 19-13 Construction Cost (Package-1: Rebuilding of Bridges) ................................................................................ 19-12

Table 19-14 Construction Cost (Package-2: Retarding Basin A,B) .................................................................................. 19-13

Table 19-15 Construction Cost (Package-3: Ring Dike) ................................................................................................... 19-13

Table 19-16 Construction Cost (Package-4: Surrounding Dike) ....................................................................................... 19-13

Table 19-17 Construction Cost (Package-4: Shortcut of Tributaries) ............................................................................... 19-14

Table 19-18 Land Acquisition Cost .................................................................................................................................. 19-14

Table 19-19 House Compensation Cost ............................................................................................................................ 19-14

Table 20-1 Summary of Structure Measures in the Priority Project .................................................................................... 20-3

Table 20-2 Outline of the Consulting Service Team ........................................................................................................... 20-3

Table 20-3 Total Cost of the Project ................................................................................................................................... 20-5

Table 20-4 Financial Plan of the Project ............................................................................................................................. 20-6

Table 20-5 Annual Fund Requirements and Breakdown (M JPY (& Million F$)) ............................................................. 20-6

Table 20-6 Breakdown of Annual Fund Requirements (2015-2025, FC: M JPY, LC: M FJD) .......................................... 20-7

Table 20-7 Time Periods Required for Major Processes and their Contents ....................................................................... 20-8

Table 20-8 Implementation Schedule of the Project ........................................................................................................... 20-9

Table 20-9 Procurement Methods for the Main Construction Works of the Project ......................................................... 20-10

Table 20-10 Organization of LWRM in 2015 ................................................................................................................... 20-11

Table 20-11 Operation and Effect Indicators of the Project .............................................................................................. 20-13

Table 21 1 Total appraised value and number of houses in Viti Levu Island in Fiji ........................................................... 21-3

Table 21 2 Average house price in expected inundation area in Viti Levu Island .............................................................. 21-3

Table 21 3 Appraised value of household goods(including passenger car) ................................................................... 21-4

Table 21 4 Average appraised value of household goods(including passenger car) ...................................................... 21-4

Table 21 5 Depreciable property and stocks per each worker in expected inundation area ................................................ 21-4

Table 21 6 Planting acreage, yield and gate price of major crops in expected inundation area ........................................... 21-5

Table 21 7 Summary of assets and damage/loss calculation method .................................................................................. 21-7

Table 21 8 Damage Rate by Inundation Depth ................................................................................................................... 21-9

Table 21 9 Damage ratio in each inundation depth ............................................................................................................. 21-9

Table 21 10 Damage Rate by Inundation Depth ............................................................................................................... 21-10

Table 21 11 Damage Rate by Inundation Depth ............................................................................................................... 21-10

Table 21 12 Crops Damage Rate by Inundation Depth ..................................................................................................... 21-10

Table 21 13 Damage of livestock in the expected inundation area (1/50 probability) ...................................................... 21-11

Table 21 14 Damage of public utilities and infrastructures(1/50 probability) ................................................................ 21-11

Table 21 15 Loss for business in the expected inundation area (1 / 50 probability, except tourism) ................................ 21-12

Table 21 16 Loss for tourism in the expected inundation area (1 / 50 probability) ........................................................... 21-13

Table 21 17 Loss for tourism in reduction of tourist arrivals (1 / 50 probability) ............................................................. 21-13

Table 21 18 Total loss for tourism .................................................................................................................................... 21-13

Table 21 19 Loss for public utilities and infrastructures (1 / 50 probability) .................................................................... 21-14

Table 21 20 Emergency Cost for household (1 / 50 probability) ...................................................................................... 21-14

Table 21 21 Emergency Cost for business entity in the expected inundated area (1 / 50 probability) .............................. 21-15

Page 28: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

viii

Table 21 22 Items of Damage (Without Project, 1/50 probability)................................................................................. 21-15

Table 21 23 Items of Loss (Without Project, 1/50 probability) ......................................................................................... 21-16

Table 21 24 Comparison between the floods in recent years. ........................................................................................... 21-17

Table 21 25 Expected amount of average annual damage and loss reduction with the priority project ............................ 21-17

Table 21 26 Result of Economic Evaluation ..................................................................................................................... 21-18

Table 21 27 Cash flow with the priority project (JPY, 100 million) ................................................................................. 21-18

Table 21 28 Cases subject to sensitivity analysis .............................................................................................................. 21-21

Table 21 29 Result of sensitivity analysis ......................................................................................................................... 21-21

Table 22 1 The Alternatives in Project Components ........................................................................................................... 22-2

Table 22 2 Main works of river works of the Priority Project ............................................................................................. 22-6

Table 22 3 Result of Impact Assessment for Construction of Central High Speed Railway in Japan (Air Pollution) ........ 22-8

Table 22 4 Standard for Air Quality in Japan ...................................................................................................................... 22-9

Table 22 5 Results of Water Quality Test ......................................................................................................................... 22-11

Table 22 6 Result of Riverbed (General Conditions) ........................................................................................................ 22-14

Table 22 7 Result of Riverbed (heavy metal) .................................................................................................................... 22-14

Table 22 8 Japanese Environment Quality Standard for Background Noise ..................................................................... 22-15

Table 22 9 Physical Condition of Survey Sites ................................................................................................................. 22-19

Table 22 10 Results of Inventory Survey (Benthos) ......................................................................................................... 22-20

Table 22 11 Results of Inventory Survey (Fish)................................................................................................................ 22-20

Table 22 12 Results of Inventory Survey (Plants) ............................................................................................................. 22-22

Table 22 13 Results of Inventory Survey (Insects, Birds and Mammals) ......................................................................... 22-25

Table 22 14 Number of Target Households by Community ............................................................................................. 22-28

Table 22 15 Number of Households for Resettlement by Community.............................................................................. 22-29

Table 22 16 Detail of Resettlement Target Households .................................................................................................... 22-30

Table 22 17 Detail of Households to be Relocated ........................................................................................................... 22-30

Table 22 18 Survey Results on Income of Households around the Project area ............................................................... 22-31

Table 22 19 Survey Results on Type of Livelihood of households near the Project Area ................................................ 22-32

Table 22 20 Survey Results for Energy Use around the Project Area ............................................................................... 22-34

Table 22 21 Schooling Capacity in Relate Education system, .......................................................................................... 22-34

Table 22 22 Comparison of Scoping and Impact Assessment based on Survey Results ................................................... 22-39

Table 22 23 Environmental Management Plan (EMP) during Construction ..................................................................... 22-46

Table 22 24 Environmental Management Plan (EMP) during Operation ......................................................................... 22-50

Table 22 25 Environmental Monitoring Plan on Pollution................................................................................................ 22-56

Table 22 26 Environmental Monitoring Plan on Natural Environment ............................................................................. 22-59

Table 22 27 Environmental Monitoring Plan on Social Environment............................................................................... 22-60

Table 22 28 Gaps between Land Acquisition and Resettlement Laws of Fiji and JICA Guidelines ................................. 22-63

Table 22 29 Total population of the Nadi Town and Rural Areas, 2007 Census .............................................................. 22-67

Table 22 30 Number of Project Affected Units (PAUs) and Affected Persons (APs) ....................................................... 22-67

Table 22 31 Area of Affected Lands ................................................................................................................................. 22-67

Table 22 32 Entitlement Matrix ........................................................................................................................................ 22-69

Table 22 33 Grievance Redress Process ............................................................................................................................ 22-72

Table 22 34 Implementation Schedule .............................................................................................................................. 22-72

Table 22 35 Result of Initial land acquisition cost survey ................................................................................................. 22-74

Table 22 36 Monitoring Indicators .................................................................................................................................... 22-75

Page 29: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

ix

Table 23 1 Contents of the 2000 Nadi Town Drainage Plan ............................................................................................... 23-4

Table 24 1 Phasing Case (Structural Measures) ............................................................................................................... 24-1

Table 24 2 Project Cost of Phasing Case........................................................................................................................... 24-12

Table 24 3 Expected amount of average annual damage reduction ................................................................................... 24-12

Table 24 4 Economic Evaluation after Phasing................................................................................................................. 24-13

Table 24 5 Summary of Phasing ....................................................................................................................................... 24-14

List of Figure

Figure 17 1 Components of the Feasibility Study ............................................................................................................. 17-1

Figure 18 1 Designed Discharge Distribution at the Priority Project .................................................................................. 18-1

Figure 18 2 Basic Concept of river Widening ..................................................................................................................... 18-2

Figure 18 3 Whole Plan of River Widening ........................................................................................................................ 18-3

Figure 18 4 Plan of River Widening (1) .............................................................................................................................. 18-4

Figure 18 5 Plan of River Widening (2) .............................................................................................................................. 18-5

Figure 18 6 Plan of River Widening (3) .............................................................................................................................. 18-6

Figure 18 7 Designed Discharge Distribution at the Priority Project .................................................................................. 18-7

Figure 18 8 Designed Longitudinal Plan ............................................................................................................................. 18-8

Figure 18 9 Typical Cross Section (Nadi River) ............................................................................................................... 18-12

Figure 18 10 Designed Discharge Distribution at the Priority Project .............................................................................. 18-15

Figure 18 11 Layout of Retarding Basin A ....................................................................................................................... 18-16

Figure 18 12 General Plan of Retarding Basin A .............................................................................................................. 18-17

Figure 18 13 Typical Cross Section (Retarding Basin A,B) .............................................................................................. 18-18

Figure 18 14 Typical Cross Section of Overflow Dike for Retarding Basin A ................................................................. 18-19

Figure 18 15 General Plan of Overflow Dike for Retarding Basin A................................................................................ 18-20

Figure 18 16 Layout of Retarding Basin B ....................................................................................................................... 18-22

Figure 18 17 General Plan of Retarding Basin B .............................................................................................................. 18-23

Figure 18 18 Typical Cross Section of Overflow Dike for Retarding Basin B ................................................................. 18-24

Figure 18 19 General Plan of Overflow Dike for Retarding Basin B ................................................................................ 18-25

Figure 18 20 Plan of Surrounding Dike ............................................................................................................................ 18-26

Figure 18 21 Typical Cross Section (Surrounding Dike of Nadi Town) ........................................................................ 18-28

Figure 18 22 Plan of Ring Dike ........................................................................................................................................ 18-29

Figure 18 23 Typical Cross Section (Ring Dike) .............................................................................................................. 18-30

Figure 18 24 Plan of Shortcuts of Tributaries ................................................................................................................... 18-31

Figure 18 25 Typical Cross Section (Shortcuts of Tributaries) ......................................................................................... 18-32

Figure 18 26 Routes as Importance Level 3 .................................................................................................................... 18-34

Figure 18 27 Design Cross Section ................................................................................................................................. 18-35

Figure 18 28 Cross Section of Denarau Bridge ............................................................................................................... 18-36

Figure 18 29 Location of Boring Holes (Nadi Town Bridge) ......................................................................................... 18-39

Figure 18 30 Location of Boring Holes (Old Queens Road Bridge ................................................................................ 18-40

Page 30: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

x

Figure 18 31 Vehicle Loading ......................................................................................................................................... 18-43

Figure 18 32 Design Live Load (Tramline Bridge) ......................................................................................................... 18-43

Figure 18 33 (1) Bridge Location .................................................................................................................................... 18-46

Figure 18 33 (2) Existing Bridge Side View (Nadi Town Bridge) ................................................................................ 18-46

Figure 18 34 Rebuilt Bridge Side View (Nadi Town Bridge) Source: JICA Study Team .............................................. 18-46

Figure 18 35 Design Plan and Side View (Nadi Town Bridge) ...................................................................................... 18-48

Figure 18 36 The wall type pier ...................................................................................................................................... 18-52

Figure 18 37 (1) Bridge Location .................................................................................................................................... 18-54

Figure 18 37 (2) Side View of Existing Bridge (Old Queens Road Bridge) ................................................................... 18-55

Figure 18 38 Side View of Rebuilt Bridge (Old Queens Road Bridge) .......................................................................... 18-55

Figure 18 39 Plan and Side View (Old Queens Road Bridge) ........................................................................................ 18-57

Figure 18 40 The wall type pier ........................................................................................................................................ 18-62

Figure 18 41 The Components of the Priority Project (Structural Measures) ................................................................... 18-67

Figure 18 42 Division of Construction Section ................................................................................................................. 18-69

Figure 18 43 Construction Step ......................................................................................................................................... 18-70

Figure 18 44 Excavation Method ...................................................................................................................................... 18-72

Figure18 45 Loading and Transportation Method ............................................................................................................. 18-72

Figure 18 46 Embankment Method ................................................................................................................................... 18-73

Figure 18 47 Construction Method for Foundation of Structures...................................................................................... 18-74

Figure 18 48 Construction Method for Concrete Placement ............................................................................................. 18-74

Figure 18 49 Temporary Construction Road ..................................................................................................................... 18-75

Figure 18 50 Temporary Construction Road for River-Crossing ...................................................................................... 18-75

Figure 18 51 Cross Section of Temporary Coffer Dam .................................................................................................... 18-76

Figure 18 52 Proposal Area for disposal sites ................................................................................................................... 18-78

Figure 18 53 Boundary of Nadi Town (Existing and Proposed) ....................................................................................... 18-79

Figure 18 54 Construction Step (1) ................................................................................................................................... 18-80

Figure 18 55 Construction Step (2) ................................................................................................................................... 18-80

Figure 18 56 Routes of Disposal Transportation ............................................................................................................... 18-86

Figure 18 57 Construction Flow(Nadi Town Bridge) .................................................................................................. 18-88

Figure 18 58 Construction Step (Nadi Town Bridge) ....................................................................................................... 18-92

Figure 18 59 (1) Detour Route (Nadi Town Bridge) ......................................................................................................... 18-93

Figure 18 59 (2) Detour Planning (Nadi Town Bridge) .................................................................................................... 18-93

Figure 18 60 General Drawing of Existing Bridge(Nadi Town Bridge) ...................................................................... 18-95

Figure 18 61 Removal Plan of Superstructure (Nadi Town Bridge) ................................................................................. 18-96

Figure 18 62 Access Road Plan (Nadi Town Bridge) ....................................................................................................... 18-97

Figure 18 63 General Drawing of New Bridge (Nadi Town Bridge) ................................................................................ 18-98

Figure 18 64 Example of Pile Construction (Pile driving by Diesel Hammer) ................................................................. 18-99

Figure 18 65 Example of Girder Installation by Erection Beam ..................................................................................... 18-100

Figure 18 66 Example of Supere Structure Election ....................................................................................................... 18-101

Figure 18 67 Construction Flow(Old Queens Road Bridge) ...................................................................................... 18-103

Figure 18 68 Construction Step Flow (Old Queens Road Bridge) .................................................................................. 18-106

Figure 18 69 Detour Route (Old Queens Road Bridge) .................................................................................................. 18-107

Figure 18 70 Detour Planning (Old Queens Road Bridge) .............................................................................................. 18-107

Figure 18 71 General Drawing of Existing Bridge (Old Queens Road Bridge) .............................................................. 18-109

Figure 18 72 Plan for Removal of Superstructure (Old Queens Road Bridge)................................................................ 18-110

Page 31: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

xi

Figure 18 73 Construction Access Road (Old Queens Road Bridge) .............................................................................. 18-113

Figure 18 74 General Drawing of New Bridge (Old Queens Road Bridge -Road Bridge-) ............................................ 18-114

Figure 18 75 General Drawing of New Bridge (Old Queens Road Bridge -Tramline Bridge-) ...................................... 18-115

Figure 18 76 Example of Pile Construction (Pile driving by Diesel Hammer) ............................................................... 18-116

Figure 18 77 Example of Girder Installation by Erection Beam ..................................................................................... 18-117

Figure 20-1 Components of structure measures of the priority project ............................................................................... 20-1

Figure 20-2 Design Flood Discharge of The Priority Project .............................................................................................. 20-2

Figure 20-3 Target Area of Structure Measurement on the Priority Project ........................................................................ 20-2

Figure 20-4 Draft project implementing structure ............................................................................................................. 20-11

Figure 20-5 PMU Organizations and Functions in Execution of Yen Loan and Technical Cooperation Project .............. 20-12

Figure 21 1 Division Map of Planting Acreage of Major Crops ......................................................................................... 21-6

Figure 21 2 Viti-Levu and Yasawa-Mamanuca islands in Fjji .......................................................................................... 21-12

Figure 21 3 Damage and Loss ratio................................................................................................................................... 21-15

Figure 21 4 Ratio of damage by category ......................................................................................................................... 21-16

Figure 21 5 Ratio of loss by category................................................................................................................................ 21-16

Figure 22 1 Nadi River Basin and the Project Area ............................................................................................................ 22-1

Figure 22 2 Proposal Area for disposal sites ....................................................................................................................... 22-7

Figure 22 3 Situation of water sampling (sampling for lab test and in site measurement) ................................................ 22-10

Figure 22 4 Water Sampling Sites along the Nadi River ................................................................................................... 22-10

Figure 22 5 Riverbed Material Sampling Sites along the Nadi River ............................................................................... 22-13

Figure 22 6 Example of samples (Site2) ........................................................................................................................... 22-14

Figure 22 7 Distance Depression level in Noise in Tokyo (Backhoe) ............................................................................... 22-16

Figure 22 8 Distance Depression level in Vibration in Tokyo (Backhoe) ......................................................................... 22-16

Figure 22 9 Condition of Algae in Namosi River which Identified during Water and Riverbed Survey .......................... 22-17

Figure 22 10 Survey Locations for Freshwater Inventory Survey ..................................................................................... 22-19

Figure 22 11 Survey Locations for Land Area Ecological Inventory Survey .................................................................... 22-21

Figure 22 12 The Survey Target of Social Economic Survey ........................................................................................... 22-28

Figure 22 13 The Project Implementation Organization (During Construction) (in case of Japanese Yen Loan) .......... 22-54

Figure 22 14 Area of Affected Lands ................................................................................................................................ 22-68

Figure 22 15 Implementation organization for land acquisition and resettlement ............................................................. 22-71

Figure 23 1 Drainage system of rainfall water in the central area of Nadi town ................................................................. 23-3

Figure 23 2 Nadi Town Drainage Plan (2000) .................................................................................................................... 23-4

Figure 24 1 The components of the Priority Project (Structural Measures) ...................................................................... 24-1

Figure 24 2 Phasing Case of the Priority Project ............................................................................................................... 24-2

Figure 24 3 Summary of Flood Analysis Result after Phasing (Inundation Area, Average Inundation Depth) ................ 24-3

Figure 24 4 Flood Analysis Result (Case0: Current Situation)(1/2) ............................................................................... 24-4

Figure 24 5 Flood Analysis Result (Case0: Current Situation)(2/2) ............................................................................... 24-5

Figure 24 6 Flood Analysis Result (Case1: Retarding Basin A, B)(1/2) ........................................................................ 24-6

Figure 24 7 Flood Analysis Result (Case1: Retarding Basin A, B)(2/2) ........................................................................ 24-7

Figure 24 8 Flood Analysis Result (Case2: River Widening L=13km form 5.75 to 18.75km)(1/2) ............................... 24-8

Page 32: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

xii

Figure 24 9 Flood Analysis Result (Case2: River Widening L=13km form 5.75 to 18.75km)(2/2) ............................... 24-9

Figure 24 10 Flood Analysis Result (Case3: River Widening L=8.25km form 5.75 to 14.0km)(1/2) ............................ 24-10

Figure 24 11 Flood Analysis Result (Case3: River Widening L=8.25km form 5.75 to 14.0km)(2/2) ............................ 24-11

Figure 24 12 Flood Analysis Result by Full Components of the Priority Project ............................................................. 24-14

Figure 24 13 Flood Analysis Result by Case2: River Widening L=13km form 5.75 to 18.75km ..................................... 24-15

Figure 24 14 Flood Analysis Result by River Widening L=8.25km form 5.75 to 14.0km................................................ 24-15

Appendix

Appendix-1 Flowchart of the Study ............................................................................................... A1-1

Appendix-2 Plan of Expert Assignment ......................................................................................... A2-1

Appendix-3 TOR of JCC and JCC Member List ......................................................................... A3-1

Appendix-4 TOR of TWG and Member List ................................................................................. A4-1

Appendix-5 MM of JCC .............................................................................................................. A5-1

Appendix-6 MM of TWG ............................................................................................................ A6-1

Appendix-7 MM of Meeting with MOA ........................................................................................ A7-1

Appendix-8 Drawings .................................................................................................................... A8-1

Appendix-9 Documents for cost estimation of land acquisition (MOL) ........................................ A9-1

Page 33: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Main Report II: Feasibility Study

17-1

Chapter 17 Components of Feasibility Study

The components of FS study are as shown in Table 17-1 and Figure 17-1.

The purpose of the Priority Project is to prevent inundation in Important Protected Area which is located

along the Nadi River (see area which is surrounded by yellow line in Figure 17-1 )

Table 17-1 Components of the Feasibility Study

Quantities

1. Nadi River Downstream (1) Retarding Basin and River

Improvement in downstream - -

(2) Ring Dike ④ Ring Dike L=1.8 km -Middlestream (3) River Widening

2) ① River Widening

Rebuilding of Nadi TOwn Bridge

Rebuilding of Old Queens Road Bridge

L=13 km

L=108 m

L= 96 m

(4) Retarding Basin A ② Retarding Basin A A=35 ha

V=795 千m3

Retarding Basin B ② Retarding Basin B A=178 ha

V=6,920 千m3

Upstream (5) Dam and River improvement in

upstream -

2. Tributaries (6) River Improvement ⑤③-2

Shortsut of Tributaries

Surrounding Dike of Nadi Town

L=0.5 km

L=4.5 km

Retarding Basins (13 sites)-

Shortcut and Surrounding dike in

tributaries are preceded to

construction as part of the master

plan―

Component of the Priority ProjectRemarks

Main Component

Structural

Measures ―

Nawaka

Maralua

Namosi

River

River, LocationComponent of

the Master Plan

S

Malakua River

⑥Rebuilding of Bridge ①River Widening: L=13km

① River Widening

② Retarding Basin A, B

③ Surrounding Dike

④ Ring Dike

⑤ Shortcut of tributaries

⑥ Rebuilding of Bridge (Nadi town bridge)

⑦ Rebuilding of Bridge (Old Queens Road bridge)

Component

②Retarding Basin A: A=35haRetarding Basin B: A=178ha

(Water Surface Area in flooding)

⑥Rebuilding of Bridge: L=108m

⑦Rebuilding of Bridge: L=96m

③Surrounding Dike: L=4.5km

④Ring Dike: L=1.8km

⑤Shortcuts: L=0.5km

Figure 17-1 Components of the Feasibility Study

Page 34: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-1

Chapter 18 Preliminary Design

18.1 River Widening

This project (the Priority Project) is intended to implement the river improvement project to prevent

flooding in the Important Protected Area which is located in the Nadi River Basin. the components of the

Priority Project are as described before in Chapter 18.

River Widening is intended to flow down 1,800 m3/s flood discharge which is equal to the design flood

with occurrence probability of 1/50 with the water level1 between the top of dike and HWL at the Back

Road Bridge point in the middle section

No.25 2012年3月洪水

NawakaRiver NamosiRiver

[3,650]

1,000

[900]

900

[1,450]

1,000

NadiRiverNaditownBridge BackroadBridge

[2,450]

1,400

[2,450]

1,400

[2,450]

1,600[1,750]

830

Votualevu

[上段]:基本高水

下段:整備後流量(MP)

[3,650]

2,400

B

A

-200

-40

V=6,520千m3

V=640千m3

-1400

NawakaRiver NamosiRiver

[3,650]

1,000

[900]

730

[1,450]

1,130

NadiRiverNaditownBridge BackroadBridge

[2,450]

1,800

[2,450]

1,800

[2,450]

2,450[1,750]

1,740

Votualevu

[上段]:基本高水

下段:整備後流量(優先プロジェクト)

[3,650]

2,950

B

A

-510

-80

V=7,200千m3

V=1,000千m3

NawakaRiver

[Upper]: Discharge before Flood Control

[Lower]: Design Discharge after the Priority Project

V=7,200 thousand m3

V=1,000 thousand m3

Figure 18-1 Designed Discharge Distribution at the Priority Project

18.1.1 Applicable standards for design

There are no Fiji own technical standards and guidelines for flood control and river facilities. Therefore, it

is required to refer to some sort of technical standards and guidelines for design.

In this situation, comparing river characteristics in Japan and those in Fiji, flood characteristics and river

characteristics of river basins in Japan and that of Nadi River basin in Fiji are to be similar considering that

there are mountains in upstream basin, water flows from upstream and flows out to sea through low-lying

areas in a short time. In addition, Natural science and technology and a variety of engineering required to

design (hydraulics, physics, soil, geotechnical engineering, river engineering, concrete engineering, etc.), is

considered one of the universal that does not depend on the countries and regions. Therefore, in this design,

it is considered to be applicable to refer the Japanese of design standards and guidelines1.

Therefore, in this design according to the following river facilities, [Structural Ordinance for river facilities

(1976.7.20)], [Revised Edition, Ministry of Construction, Technical Criteria for River Works, Editorial

Supervisor: River Bureau, Ministry of Construction, Editor: Japan River Association] and are referred.

18.1.2 Plan and Area

(1) Planned Area

River widening is conducted from 5.75k point near Narewa village to 24.0k point near Votualevu village.

This area is determined through flood analysis in order to prevent inundation in the Important Protected

Area. Earth dike is not included in order to mitigate negative impact by the dike of main stream to other

area including tributaries so that only river widening is conducted from 5.75k to 8.0k. Whole plan of river

widening is as described in Figure 18-3.

1 When the Master Plan will be completed, since the upstream dam is constructed, the discharge of 1,800m3/s can flow down in the river channel section with free-board. In the Priority Project the discharge is permitted to flow down with the water level between the top of dike

and HWL considering that this stage is a step to the Master Plan.

2See [Draft Final Report: Main Report, Part I: Master Plan Study, Chapter 4, 4.1.1 ]

※Flow volume after the priority project include natural

flood volume at outside section of Important Protected Area

Page 35: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-2

(2) Plan Alignment of river widening is set considering current alignment of river channel and flood flow. Width of river widening is set basically same width from center line between right bank side and left bank side from the point of view of fairness.

10.25K

Current Cross SectionCross Section after River Widening

Figure 18-2 Basic Concept of river Widening

Alignment of river channel is sifted or loosed in order not to exceed design flood water revel when flood water level exceeds design high water level due to effect by curvature at current alignment and there are important areas to be protected behind the river. (Exception-1)

Alignment is loosed to the extent that does not deviate from the current river channel alignment extremely for excessive bending portion such as a U-shaped or S-shaped curve (Exception-2) and alignment is newly set for extreme crank shape curve in light of the continuity of the upstream and downstream alignment (Exception-3).

Alignment of river channel is straighten and smoothen from 22.75k to 24.25k in order to intake flood water smoothly to the retarding basin at overflow dike securing a required length and elevation (Exeption-4).

Alignment is sifted to the other side to the extent that there is no hindrance to a safe flow of flood water from the viewpoint of reducing the number of house relocations if houses are present only one side of the river channel (Exception-5)

Based on the above, plan of river widening is as shown in from Figure 18-3 to Figure 18.6.

In Figure 18-4~Figure 18.6 there are two kind of river alignment, blue and yellow lines, the blue line shows the present river alignment and yellow line shows the alignment after river improvement.

Page 36: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-3

Figure 18-3 Whole Plan of River Widening

Nadi river

River Widening: L=13km

5.75km

18.75km

Back Road Bridge

Narewa village

Denarau

:Embankment

Page 37: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-4

Figure 18-4 Plan of River Widening (1)

(Edge of the embankment or river inspection passage at landside)

Page 38: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-5

Figure 18-5 Plan of River Widening (2)

(Edge of the embankment or river inspection passage at landside)

Page 39: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-6

Figure 18-6 Plan of River Widening (3)

(Edge of the embankment or river inspection passage at landside)

Page 40: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-7

18.1.3 Longitudinal Plan

(1) Design High Water Level

The design high water level in a section from the lower reaches to the middle reaches is roughly set up to

the inland ground level and which is set up based on the non-uniform flow calculation result at the time of

design flow discharge, and the design high water level it is set up based on the overflow depth of the

retarding basin and the non-uniform flow calculation result at the time of design flow discharge for a

section in the upper reaches. (For more information see Draft Final Report, Main Report I: Master Plan

Study, Chapter 8, 8.2.3 Longitudinal Plan). The High Water Level which is set based on the above is

shown in Figure 18-8.

The High Water Level is set for Master Plan Level, however, after priority project before the

completion of Master Plan, flood water level will exceed the High Water Level (but under designed

dike crown elevation) by target design scales level flood (2012 flood).

Designed Discharge Distribution at the Priority Project is as shown in Figure 18-7.

No.25 2012年3月洪水

NawakaRiver NamosiRiver

[3,650]

1,000

[900]

900

[1,450]

1,000

NadiRiverNaditownBridge BackroadBridge

[2,450]

1,400

[2,450]

1,400

[2,450]

1,600[1,750]

830

Votualevu

[上段]:基本高水

下段:整備後流量(MP)

[3,650]

2,400

B

A

-200

-40

V=6,520千m3

V=640千m3

-1400

NawakaRiver NamosiRiver

[3,650]

1,000

[900]

730

[1,450]

1,130

NadiRiverNaditownBridge BackroadBridge

[2,450]

1,800

[2,450]

1,800

[2,450]

2,450[1,750]

1,740

Votualevu

[上段]:基本高水

下段:整備後流量(優先プロジェクト)

[3,650]

2,950

B

A

-510

-80

V=7,200千m3

V=1,000千m3

NawakaRiver

[Upper]: Discharge before Flood Control

[Lower]: Design Discharge after the Priority Project

V=7,200 thousand m3

V=1,000 thousand m3

Figure 18-7 Designed Discharge Distribution at the Priority Project

※Flow volume after the priority project include natural

flood volume at outside section of Important Protected Area

Page 41: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-8

Nawaka River

Nadi town Bridge

OldQueensroad Bridge

Back road Bridge

Namosi River

-5.0

0.0

5.0

10.0

15.0

20.0

25.0

30.0

35.0

0.0 5.0 10.0 15.0 20.0 25.0

Ele

vati

on(

m)

km

Design Embankment Height

HWL

Design Riverbed (after improvement)

Right Bank

Left Bank

Average Riverbed

Lowest Riverbed

Calculation Water Level for Design FloodDischarge(Planned River)Left side :Water Level Rising amount due to curvatureConsidered (Planned River)Rignt side :Water Level Rising amount due to curvatureConsidered (Planned River)Calculation Water Level for Design FloodDischarge(Current River)Reference Point

After smoothing :Water Level Rising amount due tocurvature Considered (Planned River)

Gradient of Design Riverbed=1/4,200 Gradient of Design Riverbed=1/2,600 Gradient of Design Riverbed=1/1,350 Gradient of Design Riverbed=1/1,000

Gradient of HWL=1/2,150

Gradient of HWL=1/1,600

Gradient of HWL=1/700

Gradient of HWL=1/2,600

Design Flood Discharge=1,000m3/s

Design Flood Discharge=2,400m3/s

Design Flood Discharge=1,400m3/s

Design Flood Discharge=1,600m3/s Design Flood Discharge=830m3/s

Gradient of HWL=1/1000

Overflow section of Retarding Basin B

Segment3、coefficient roughness for low-water channel n=-0.015

Segment2-2、coefficient roughness for low-water channel n=-0.023Segment2-1、coefficient roughness for low-water channel n=-0.027

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

0.0 5.0 10.0 15.0 20.0 25.0

Velo

city(m

km

Flow Velocity at the time of Design Flood Discharge

(current channel:mean cross-section)

Flow Velocity at the time of Design Flood Discharge

(planned channel:average cross-section)

Figure 18-8 Designed Longitudinal Plan

Ground elevation at Right Bank Side

Ground elevation at Left Bank Side

Page 42: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-9

Table 18-1 Longitudinal Feature (Nadi River)

Structure Interval Left Bank Right BankLowest

Riverbed

Average

Riverbed

Headroom for

bridge girder -

free-board

Calculation

water level of

Design Flood

Water level

rising amount

due to

Water level

after

curvature

HWL - non-

uniform flow

calculation

Flow velocityAllocation of

Flow rateFee-board HWL

Designed

Embankment

Height

Design Riverbed

(after improvement)Design water depthDesign river width

Gradient of

HWL

Lowest Riverbed

(after

improvement)

Calculation Water

Level for Design

Flood Discharge

Water level rising

amount due to

curvature

Water level after

consideration of

curvature

HWL - non-

uniform flow

calculation

Flow velocity

0.000 0.000 0.280 0.270 -4.630 -3.963 1.19 0.00 0.00 1.91 1.0 1.19 2.19 -3.85 5.038 80 1.19 0.00 0.00 1.87

0.250 0.250 1.660 1.860 -4.270 -3.935 0.77 0.00 0.54 3.72 1.0 1.30 2.30 -3.79 5.095 80 0.99 0.00 0.31 2.89

0.500 0.250 1.550 1.700 -3.730 -3.395 0.79 0.00 0.63 4.13 1.0 1.42 2.42 -3.73 5.152 80 1.00 0.00 0.42 3.12

0.750 0.250 1.580 1.540 -3.350 -2.444 1.13 0.12 1.25 0.29 3.85 1.0 1.54 2.54 -3.67 5.208 80 1.16 0.12 1.28 0.26 2.92

1.000 0.250 2.300 1.860 -2.900 -1.994 1.24 0.12 1.37 0.29 4.18 1.0 1.65 2.65 -3.61 5.265 80 1.24 0.12 1.37 0.29 2.92

1.250 0.250 3.330 1.650 -3.642 -3.374 1.91 0.12 2.04 -0.27 2.87 1.0 1.77 2.77 -3.55 5.322 80 1.35 0.12 1.48 0.29 2.81

1.500 0.250 2.000 1.593 -4.356 -4.088 2.19 0.12 2.31 -0.42 2.03 1.0 1.89 2.89 -3.49 5.379 80 1.57 0.12 1.70 0.19 2.19

1.750 0.250 1.410 1.760 -3.420 -2.770 2.05 0.12 2.18 -0.17 2.80 1.0 2.00 3.00 -3.43 5.435 80 1.47 0.12 1.60 0.40 2.79

2.000 0.250 5.736 2.605 -2.950 -2.503 2.10 0.12 2.22 -0.10 2.94 1.0 2.12 3.12 -3.37 5.492 80 1.57 0.12 1.70 0.42 2.69

2.250 0.250 5.960 1.920 -3.354 -2.844 2.34 0.25 2.59 -0.36 2.30 1.0 2.23 3.23 -3.31 5.549 80 1.68 0.25 1.94 0.30 2.53

2.500 0.250 5.800 2.430 -3.710 -3.200 2.37 0.25 2.62 -0.27 2.40 1.0 2.35 3.35 -3.25 5.606 80 1.74 0.25 1.99 0.36 2.55

2.750 0.250 4.910 1.990 -2.730 -2.321 2.55 0.25 2.80 -0.33 1.70 1.0 2.47 3.47 -3.20 5.662 80 1.94 0.25 2.19 0.28 1.86

3.000 0.250 3.170 3.083 -2.040 -1.631 2.42 0.00 0.16 2.52 1.0 2.58 3.58 -3.14 5.719 80 1.89 0.00 0.69 2.28

3.250 0.250 7.200 2.350 -3.126 -2.665 2.52 0.00 0.18 2.38 1.0 2.70 3.70 -3.08 5.776 80 1.87 0.00 0.83 2.58

3.500 0.250 1.950 3.097 -3.560 -3.099 2.65 0.12 2.77 0.04 1.97 1.0 2.82 3.82 -3.02 5.833 80 2.01 0.12 2.13 0.69 2.27

3.750 0.250 3.080 2.440 -2.910 -1.471 2.57 0.12 2.69 0.24 2.54 1.0 2.93 3.93 -2.96 5.889 80 2.02 0.12 2.14 0.80 2.46

4.000 0.250 2.714 2.286 -2.370 -1.636 2.73 0.12 2.85 0.20 2.10 1.0 3.05 4.05 -2.90 5.946 80 2.15 0.12 2.27 0.78 2.12

4.250 0.250 3.200 3.570 -1.900 -1.374 2.80 0.00 0.36 2.28 1.0 3.16 4.16 -2.84 6.003 80 2.28 0.00 0.89 2.17

4.500 0.250 3.800 5.230 -1.770 -1.244 2.99 0.00 0.30 2.29 1.0 3.28 4.28 -2.78 6.060 80 2.53 0.00 0.76 2.10

4.750 0.250 3.520 3.970 -2.800 -2.460 3.32 0.00 0.08 2.06 1.0 3.40 4.40 -2.72 6.116 80 2.76 0.00 0.63 2.17

5.000 0.250 4.460 4.360 -3.610 -2.923 3.66 0.06 3.72 -0.21 1.92 1.0 3.51 4.51 -2.66 6.173 80 2.97 0.06 3.03 0.48 2.23

5.250 0.250 3.750 4.440 -3.490 -2.061 3.83 0.06 3.89 -0.26 1.88 1.0 3.63 4.63 -2.60 6.230 80 3.15 0.06 3.21 0.42 1.94

5.500 0.250 3.714 3.587 -2.640 -1.645 3.93 0.06 3.99 -0.25 2.29 1.0 3.75 4.75 -2.54 6.287 80 3.24 0.06 3.30 0.45 2.15

5.750 0.250 2.850 5.230 -1.390 -0.836 4.28 0.15 4.42 -0.56 1.48 1.0 3.86 4.86 -2.48 6.343 150 3.50 0.15 3.64 0.22 1.19

6.000 0.250 3.910 5.480 -1.440 -1.141 4.06 0.00 -0.08 6.41 1.2 3.98 5.18 -2.42 6.400 150 3.18 0.00 0.80 3.08

6.250 0.250 3.970 3.780 -1.645 -0.936 7.12 0.20 7.31 -3.22 3.12 1.2 4.09 5.29 -2.36 6.457 150 3.37 0.20 3.56 0.53 3.07

6.500 0.250 3.720 4.115 -1.650 -1.116 7.31 0.20 7.51 -3.30 3.74 1.2 4.21 5.41 -2.30 6.514 150 3.57 0.20 3.77 0.45 2.95

6.750 0.250 3.240 6.200 -2.340 -1.339 8.02 0.20 8.21 -3.89 2.89 1.2 4.33 5.53 -2.24 6.570 150 3.73 0.20 3.93 0.40 2.93

7.000 0.250 4.090 3.867 -2.480 -1.479 8.20 0.47 8.68 -4.23 3.39 1.2 4.44 5.64 -2.18 6.627 150 3.94 0.47 4.42 0.03 2.66

7.250 0.250 3.130 4.700 -3.027 -1.045 8.90 0.18 9.08 -4.51 1.64 1.2 4.56 5.76 -2.12 6.684 150 4.07 0.18 4.25 0.31 2.62

7.500 0.250 4.620 3.610 -3.000 -1.332 8.87 0.18 9.05 -4.37 2.44 1.2 4.68 5.88 -2.06 6.741 150 4.18 0.18 4.36 0.32 2.71

7.750 0.250 3.640 5.080 -3.300 -1.919 9.14 0.00 -4.34 1.92 1.2 4.79 5.99 -2.00 6.797 150 4.30 0.00 0.49 2.76

8.000 NavuBridge(支川) 0.250 4.525 2.624 -3.320 -2.117 9.29 0.45 9.75 -4.84 1.64 1.2 4.91 6.11 -1.95 6.854 150 4.45 0.45 4.90 0.01 2.67

8.250 0.250 4.424 5.156 -1.150 0.049 9.32 0.00 -4.29 1.92 1.0 5.03 6.11 -1.89 6.911 100 4.64 0.00 0.38 2.39

8.500 0.250 5.740 6.013 -0.820 -0.356 9.26 0.00 -4.12 2.62 1.0 5.14 6.14 -1.83 6.968 100 4.75 0.00 0.39 2.48

8.750 0.250 5.836 6.480 -1.890 -1.138 9.45 0.26 9.71 -4.45 2.57 1.0 5.26 6.26 -1.77 7.024 100 4.90 0.26 5.15 0.10 2.41

9.000 0.250 4.050 6.150 -1.430 -0.393 9.73 0.26 9.98 -4.61 2.21 1.0 5.37 6.37 -1.71 7.081 100 5.05 0.26 5.30 0.07 2.29

9.250 0.250 5.750 4.220 -0.800 0.202 9.96 0.18 10.14 -4.65 1.76 1.0 5.49 6.49 -1.65 7.138 100 5.17 0.18 5.35 0.14 2.19

9.500 0.250 6.060 6.170 -1.050 -0.600 10.05 0.00 -4.44 1.95 1.0 5.61 6.61 -1.59 7.195 100 5.26 0.00 0.34 2.25

9.750 0.250 6.360 6.290 -2.000 -1.450 10.20 0.00 -4.47 1.79 1.0 5.72 6.72 -1.53 7.251 100 5.36 0.00 0.36 2.27

9.830 NaditownBridge 0.080 6.300 6.300 -4.730 -2.131 5.300 10.29 0.00 -4.53 1.73 1.0 5.76 6.76 -1.51 7.270 100 5.51 0.00 0.25 2.16

10.000 0.170 6.310 7.020 -1.300 -0.398 10.18 0.00 -4.34 2.66 1.0 5.84 6.84 -1.47 7.308 100 5.54 0.00 0.30 2.26

10.250 0.250 6.630 6.460 -0.820 0.028 10.30 0.07 10.36 -4.41 3.51 1.0 5.96 6.96 -1.41 7.365 100 5.65 0.07 5.72 0.24 2.21

10.500 0.250 6.990 7.210 -1.250 -0.431 11.12 0.07 11.19 -5.12 1.66 1.0 6.07 7.07 -1.35 7.422 100 5.76 0.07 5.83 0.25 2.18

10.750 0.250 5.850 6.730 -0.670 -0.376 11.23 0.07 11.30 -5.11 1.56 1.0 6.19 7.19 -1.29 7.478 100 5.85 0.07 5.92 0.27 2.18

11.000 0.250 9.310 6.630 -3.610 -2.289 11.33 0.00 -5.03 1.49 1.0 6.30 7.30 -1.23 7.535 100 5.97 0.00 0.33 1.98

11.250 0.250 17.830 6.950 -1.760 -0.769 11.39 0.16 11.55 -5.13 1.73 1.0 6.42 7.42 -1.17 7.592 100 5.99 0.16 6.16 0.26 2.25

11.500 0.250 5.820 7.090 -1.460 -0.950 11.56 0.16 11.72 -5.18 1.29 1.0 6.54 7.54 -1.11 7.649 100 6.12 0.16 6.28 0.25 2.12

11.750 0.250 6.350 6.900 -0.770 -0.622 11.56 0.00 -4.90 1.90 1.0 6.65 7.65 -1.05 7.705 100 6.19 0.00 0.46 2.23

12.000 0.250 6.720 9.190 -1.080 -0.574 11.70 0.00 -4.93 1.60 1.0 6.77 7.77 -0.99 7.762 100 6.30 0.00 0.47 2.18

12.250 0.250 8.250 6.100 -1.440 -0.750 11.80 0.00 -4.92 1.43 1.0 6.89 7.89 -0.93 7.819 100 6.39 0.00 0.49 2.22

12.500 0.250 8.950 8.510 -1.950 -0.700 11.86 0.44 12.30 -5.30 1.60 1.0 7.00 8.00 -0.87 7.876 100 6.52 0.44 6.96 0.04 2.08

12.750 0.250 8.720 8.000 -2.090 -0.434 11.99 0.46 12.45 -5.33 1.25 1.0 7.12 8.12 -0.81 7.933 100 6.60 0.46 7.05 0.07 2.14

13.000 0.250 8.420 7.900 -1.000 -0.463 11.92 0.00 -4.69 2.28 1.0 7.23 8.23 -0.75 7.989 80 6.56 0.00 0.68 2.89

13.250 0.250 6.770 9.620 -2.290 -1.039 12.19 1.20 13.39 -6.00 1.75 1.0 7.39 8.39 -0.66 8.049 80 6.85 1.12 7.97 -0.58 2.69

13.500 0.250 5.320 7.780 -0.950 0.164 12.25 0.00 -4.70 2.16 1.0 7.55 8.55 -0.56 8.109 80 7.10 0.00 0.45 2.65

13.750 0.250 7.330 8.740 -1.070 -0.291 12.43 0.00 -4.72 2.11 1.0 7.70 8.70 -0.47 8.170 80 7.30 0.00 0.40 2.61

14.000 0.250 5.040 7.880 -1.010 0.022 12.65 0.00 -4.79 1.90 1.0 7.86 8.86 -0.37 8.230 80 7.44 0.00 0.42 2.69

14.250 0.250 6.510 8.510 -1.120 -0.464 12.81 0.00 -4.80 1.80 1.0 8.02 9.02 -0.27 8.290 80 7.60 0.00 0.42 2.72

14.500 0.250 9.880 9.920 -0.890 1.057 12.87 0.00 -4.70 2.13 1.0 8.17 9.17 -0.18 8.350 80 7.78 0.00 0.39 2.63

14.750 0.250 6.550 8.820 0.050 0.567 13.09 0.11 13.20 -4.87 1.48 1.0 8.33 9.33 -0.08 8.410 80 8.08 0.11 8.18 0.14 2.13

15.000 0.250 10.620 10.560 -1.190 -0.769 13.08 0.11 13.19 -4.70 2.24 1.0 8.48 9.48 0.01 8.470 80 8.16 0.11 8.27 0.22 2.48

15.250 0.250 8.290 11.190 -0.540 0.216 13.29 0.49 13.78 -5.14 2.13 1.0 8.64 9.64 0.11 8.530 80 8.30 0.49 8.79 -0.15 2.47

15.500 0.250 11.010 6.600 -1.170 -0.354 13.49 0.49 13.98 -5.18 2.00 1.0 8.80 9.80 0.21 8.590 80 8.45 0.49 8.93 -0.13 2.42

15.750 0.250 10.380 11.230 0.090 0.637 13.69 0.00 -4.74 1.70 1.0 8.95 9.95 0.30 8.650 80 8.64 0.00 0.32 2.31

16.000 0.250 11.700 7.710 0.210 0.532 13.76 0.25 14.01 -4.90 2.12 1.0 9.11 10.11 0.40 8.710 80 8.77 0.25 9.02 0.09 2.45

16.250 0.250 11.300 7.910 -0.360 1.033 13.92 0.58 14.50 -5.24 2.18 1.0 9.27 10.27 0.50 8.771 80 8.91 0.58 9.49 -0.23 2.39

16.500 0.250 6.850 8.450 -0.490 0.008 14.16 0.00 -4.74 1.74 1.0 9.42 10.42 0.59 8.831 80 9.04 0.00 0.38 2.33

16.750 0.250 5.200 5.200 0.520 1.307 14.39 0.00 -4.81 1.89 1.0 9.58 10.58 0.69 8.891 80 9.34 0.00 0.24 2.32

17.000 OldQueensRoadBridge 0.250 8.260 11.980 -0.550 -0.182 9.780 14.50 0.09 14.59 -4.86 2.22 1.0 9.73 10.73 0.78 8.951 80 9.48 0.09 9.58 0.16 2.31

17.250 0.250 8.770 11.790 0.120 0.952 14.70 0.09 14.80 -4.91 2.36 1.0 9.89 10.89 0.88 9.011 80 9.62 0.09 9.71 0.18 2.27

17.500 0.250 7.700 11.470 -0.400 0.795 15.07 0.14 15.21 -5.17 1.18 1.0 10.05 11.05 0.98 9.071 80 9.79 0.15 9.94 0.11 2.05

17.750 0.250 9.220 12.540 0.030 1.613 15.08 0.15 15.23 -5.03 1.49 1.0 10.20 11.20 1.07 9.131 80 9.86 0.16 10.02 0.18 2.27

18.000 0.250 7.330 11.630 0.720 1.442 15.20 0.15 15.35 -4.99 1.01 1.0 10.36 11.36 1.17 9.191 80 9.97 0.16 10.13 0.23 2.28

18.250 0.250 9.340 6.590 0.920 1.459 15.23 0.30 15.52 -5.01 1.26 1.0 10.52 11.52 1.26 9.251 80 10.09 0.28 10.37 0.15 2.26

18.500 0.250 6.940 7.920 1.220 1.597 15.18 0.18 15.35 -4.68 2.27 1.0 10.67 11.67 1.36 9.311 70 10.04 0.19 10.23 0.44 3.03

18.750 BackroadBridge 0.250 15.240 15.240 2.000 2.061 14.240 15.49 0.18 15.66 -4.63 1.71 1.0 11.03 12.03 1.55 9.483 70 10.43 0.19 10.61 0.42 3.16

19.000 0.250 10.020 13.290 1.460 1.727 15.50 0.34 15.84 -4.45 2.46 1.0 11.39 12.39 1.73 9.655 70 10.71 0.40 11.11 0.27 3.46

19.250 0.250 9.710 9.900 1.640 1.713 15.77 0.34 16.11 -4.37 2.23 1.0 11.74 12.74 1.92 9.827 70 11.21 0.40 11.61 0.13 3.45

19.500 0.250 10.980 17.600 1.910 2.582 15.95 0.00 -3.85 2.48 1.0 12.10 13.10 2.10 9.999 70 11.74 0.00 0.36 3.20

19.750 0.250 12.890 13.240 1.970 2.471 16.15 0.32 16.46 -4.00 2.95 1.0 12.46 13.46 2.29 10.171 70 12.09 0.35 12.43 0.02 3.10

20.000 0.250 11.300 8.550 2.130 2.231 16.57 0.16 16.72 -3.91 2.56 1.0 12.81 13.81 2.47 10.343 70 12.52 0.17 12.69 0.12 3.00

20.250 0.250 10.940 9.530 1.570 2.008 16.89 0.16 17.05 -3.87 1.97 1.0 13.17 14.17 2.66 10.515 70 12.90 0.17 13.07 0.10 2.72

20.500 0.250 10.280 12.000 2.380 2.787 17.05 0.00 -3.52 1.85 1.0 13.53 14.53 2.84 10.687 70 13.21 0.00 0.32 2.68

20.750 0.250 13.910 12.710 3.030 3.198 17.15 0.00 -3.26 2.07 1.0 13.89 14.89 3.03 10.859 70 13.50 0.00 0.39 2.85

21.000 0.250 13.770 14.420 2.860 3.516 17.36 0.00 -3.11 1.49 1.0 14.24 15.24 3.21 11.031 65 13.89 0.00 0.35 2.41

21.250 0.250 14.500 13.610 3.290 3.708 17.42 0.00 -2.82 1.63 1.0 14.60 15.60 3.40 11.203 65 13.99 0.00 0.61 3.30

21.500 0.250 14.690 12.800 3.710 4.122 17.53 0.00 -2.58 1.63 1.0 14.96 15.96 3.58 11.375 65 14.57 0.00 0.39 2.78

21.750 0.250 17.040 12.950 3.730 4.116 17.62 0.15 17.77 -2.45 1.94 1.0 15.31 16.31 3.77 11.547 65 14.89 0.15 15.05 0.27 2.88

22.000 0.250 11.510 10.250 3.630 3.745 17.80 0.15 17.95 -2.27 1.69 1.0 15.67 16.67 3.95 11.719 65 15.28 0.15 15.44 0.24 2.47

22.250 0.250 12.390 15.760 3.610 5.316 17.92 0.08 18.00 -1.97 1.29 1.0 16.03 17.03 4.14 11.891 65 15.61 0.08 15.69 0.34 1.55

22.500 0.250 13.270 14.550 4.060 4.353 17.94 0.08 18.02 -1.63 1.82 1.0 16.39 17.39 4.32 12.063 65 15.42 0.08 15.50 0.89 3.46

22.750 遊水地B越流堤 0.250 15.930 13.120 3.530 4.097 17.000 18.06 0.45 18.51 -1.77 1.96 1.0 16.74 17.74 4.51 12.235 65 16.11 0.46 16.57 0.17 2.41

23.000 0.250 12.600 14.080 3.470 4.401 18.12 0.00 -1.02 2.35 1.0 17.10 18.10 4.69 12.407 16.24 0.00 0.86 2.84

23.250 0.250 14.230 12.240 4.360 4.812 18.34 0.00 -0.99 2.03 1.0 17.35 18.35 4.88 12.471 16.61 0.00 0.74 2.43

23.500 0.250 13.170 17.840 3.950 4.254 18.47 0.27 18.74 -1.14 2.21 1.0 17.60 18.60 5.06 12.536 16.84 0.27 17.11 0.49 2.59

23.750 0.250 14.560 12.350 3.760 4.100 18.71 0.27 18.98 -1.13 1.85 1.0 17.85 18.85 5.25 12.601 17.21 0.27 17.48 0.38 2.17

24.000 0.250 12.920 13.110 5.220 5.562 18.64 0.00 -0.54 3.08 1.0 18.10 19.10 5.43 12.666 17.15 0.00 0.95 3.58

24.250 0.250 15.850 19.040 4.480 5.384 19.19 0.05 19.24 -0.89 1.83 1.0 18.35 19.35 5.62 12.731 17.93 0.05 17.98 0.37 2.13

24.500 0.250 12.750 16.240 5.510 5.928 19.25 0.05 19.30 -0.70 2.40 1.0 18.60 19.60 5.81 12.796 18.05 0.05 18.09 0.51 2.75

24.750 0.250 18.600 16.030 5.950 6.508 19.54 0.05 19.59 -0.74 1.77 1.0 18.85 19.85 5.99 12.860 18.46 0.05 18.51 0.34 1.98

25.000 0.250 30.760 16.360 4.870 5.363 19.54 0.41 19.96 -0.86 2.34 1.0 19.10 20.10 6.18 12.925 18.48 0.42 18.90 0.20 2.58

25.250 0.250 15.400 13.420 5.700 6.132 19.786 0.00 -0.44 1.73 1.0 19.35 20.35 6.36 12.990 18.789 0.00 0.56 1.90

25.500 0.250 19.000 19.210 5.310 6.107 19.919 0.00 -0.32 1.38 1.0 19.60 20.60 6.55 13.055 18.953 0.00 0.65 1.56

25.750 0.250 14.823 27.190 5.870 6.105 20.009 0.03 20.04 -0.34 1.28 1.0 19.70 20.70 6.80 12.901 19.08 0.03 19.11 0.59 1.41

26.000 0.250 16.820 27.540 6.400 7.812 20.085 0.03 20.11 -0.32 1.19 1.0 19.79 20.79 7.05 12.747 19.176 0.03 19.21 0.59 1.37

26.250 0.250 26.450 18.850 6.203 6.673 20.133 0.08 20.21 -0.32 1.40 1.0 19.89 20.89 7.30 12.593 19.254 0.08 19.34 0.55 1.55

26.500 0.250 19.220 17.730 5.930 6.847 20.241 0.08 20.32 -0.34 1.03 1.0 19.99 20.99 7.55 12.439 19.392 0.08 19.47 0.51 1.15

26.750 0.250 20.230 25.280 7.140 7.381 20.265 0.06 20.32 -0.24 1.37 1.0 20.08 21.08 7.80 12.286 19.429 0.06 19.49 0.59 1.53

27.000 0.250 31.990 21.330 7.220 7.586 20.339 0.06 20.40 -0.22 1.47 1.0 20.18 21.18 8.05 12.132 19.529 0.06 19.59 0.59 1.61

27.060 0.060 32.000 20.770 6.050 7.059 20.366 0.00 -0.17 1.42 1.0 20.20 21.20 8.11 12.095 19.565 0.00 0.64 1.55

27.250 0.190 32.840 20.220 7.512 7.687 20.466 0.09 20.56 -0.29 1.11 1.0 20.27 21.27 8.30 11.978 19.685 0.10 19.78 0.49 1.22

27.500 0.250 23.710 16.230 8.120 9.156 20.54 0.10 20.64 -0.27 0.89 1.0 20.37 21.37 8.55 11.824 19.776 0.10 19.87 0.50 0.99

27.750 0.250 25.660 21.220 8.180 8.522 20.575 0.00 -0.11 1.30 1.0 20.47 21.47 8.80 11.670 19.82 0.00 0.65 1.48

28.000 0.250 28.300 19.350 8.430 9.132 20.699 0.00 -0.14 0.96 1.0 20.56 21.56 9.05 11.516 19.987 0.00 0.58 1.06

28.250 0.250 33.570 22.178 8.566 8.908 20.699 0.11 20.81 -0.15 1.61 1.0 20.66 21.66 9.30 11.362 19.997 0.11 20.11 0.55 1.76

28.500 0.250 46.710 22.050 9.440 10.625 20.826 0.11 20.94 -0.18 1.47 1.0 20.75 21.75 9.55 11.209 20.154 0.11 20.26 0.49 1.64

28.750 0.250 25.620 30.300 9.611 10.714 20.937 0.12 21.05 -0.20 1.11 1.0 20.85 21.85 9.80 11.055 20.298 0.12 20.42 0.44 1.20

830 1/2600

1/1000

1/1000

1600

1000

2400

1400

1/1600 1/2600

1/2150 1/4200

1/700

1/1350

milepost

Current feature Design feature

Page 43: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-10

(2) Design Embankment Height (Free-Board)

In accordance with “Cabinet Order concerning Structural Standards for River Management Facilities,

etc. Chapter III Article 20”, the design embankment height is provided with a freeboard 1.0m for a

given flow rate as below.

Table 18-2 Design Embankment Free-Board

Item 1 2 3 4 5 6

Flow Rate

(m3/s) Less than 200

More than 200

Less than 500

More than 500

Less than 2000

More than 2000

Less than 5000

More than 5000

Less than 1000

More than

10000

Free Board

(m) 0.6 0.8

1 1.2 1.5 2

Source: “Cabinet Order concerning Structural Standards for River Management Facilities, etc. Chapter III Article 20”

(3) Design Riverbed Height

The design riverbed height is set up nearly the present riverbed height. The design riverbed slope is set up

nearly the present riverbed slope on due consideration of ensuring stability of the riverbed.

(4) Water Level Rise

The water level rise due to bridge pier, or due to the confluence point are considered but the water

level rising amount due to curvature is corresponded by the correction of cross-shape or planar normal

line if necessary, after checking the terrain situation behind the ground. In case that the water level is

over HWL and there are no protection objects, the water level rising is confirmed within the free-board.

This is considered a tentative situation in the step wise implementation so that the alignment is not

revised. Water Level Rise is mentioned in Table 18-1.

18.1.4 Cross-Sectional Plan

(1) Slope Gradient

a) From 8.0k(Downstream beginning point of Dike)to 18.75k(Back Road Bridge)

Although in principle the slope gradient of embankment is set loosely than 1:3 of either river side or land

side slope based on River Embankment Design Criteria in Japan, 2007, River Improvement and

Management Division, Water and Disaster Management Bureau, Ministry of Land, Infrastructure,

Transport and Tourism, Slope gradient either river side or land side for Nadi River is set as 1:2 because

1)Risk of dike breach due to riverbank erosion is low because cross-sectional shape of Nadi River after

improvement is almost engraved to existing ground, 2)Height of embankment is from 0.5m to 3m if

necessary and stability for structural and permeability is considered to be secured and 3) The present

situation of the bank are considered to be stable with almost 1:2 through field investigation.

In addition, in this project, slope of land side is hardly formed because low land area besides embankment

is filled with soil as mentioned later in "(4) Backfilling at Hinterland".

Typical Cross Section is as described in Figure 18-9.

On the other hand, slope gradient for other structures are set as below. Although details of each shape of

structure are mentioned later in each clause, only outline is described for reference in this clause.

b) Surrounding Dike of Nadi Town

Either river or land side of slope gradient is set as 1:3 because conditions do not apply to those mentioned

in above a).

c) Ring Dike

Either river or land side of slope gradient is set as 1:3 because conditions do not apply to those mentioned

in above a).

d) Surrounding Dike for Retarding Basin A,B in upstream

Either river or land side of slope gradient is set as 1:3 because conditions do not apply to those mentioned

in above a).

Page 44: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-11

e) Dike along the river for Retarding Basin A, B in upstream

Either river or land side of slope gradient is set as 1:3 because conditions do not apply to those mentioned

in above a).

(2) Top of Bank Width

In accordance with “Cabinet Order concerning Structural Standards for River Management Facilities,

etc. Chapter III Article 21”, the embankment section is provided with a bank width for a given flow

rate as mentioned in Table 18-3. Bank width is set as 4.0m

Table 18-3 Top of Bank Width

Design Discharge

(m3/s)

Bank Width

(m)

Less than 500 3

Moe than 500, Less than 2000 4

Moe than 2000, Less than 5000 5

Moe than 5000, Less than 10000 6

Moe than 10000 7 Source: “Cabinet Order concerning Structural Standards for River Management Facilities, etc. Chapter III Article 21”

(3) Inspection passage

In accordance with “Cabinet Order concerning Structural Standards for River Management Facilities,

etc. Chapter III Article 27”, the embankment is provided a inspection passage. Inspection passage

width is set as 3.0m

Table 18-4 Inspection Passage (Cabinet Order concerning Structural Standards for River

Management Facilities, etc. Chapter III Article 27 and Rules Article 15)

(Inspection Passage)

Article 27: Inspection Passage shall be installed near Embankment.

Rules Article 15: Width od Inspection Passage of Embankment is more than 3m and less than width of

crest of Embankment

Source: Edited by JICA Study Team from “Cabinet Order concerning Structural Standards for River Management Facilities,

etc. Chapter III Article 21”

Page 45: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-12

Figure 18-9 Typical Cross Section (Nadi River)

Page 46: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-13

(4) Backfilling at Hinterland

Terrain of the project area is the shape of a river terrace and the ground elevation is generally higher as

distance to land side from the river. Therefore, backfilling at hinterland is planned in order to the fill lower

area between embankment and land side if any after installation of embankment, also aiming at 1)

Improvement of safety degree for inundation (Land raising becomes hard to be inundated), 2) Cost

reduction by reducing disposal cost for soil generated by construction by utilizing them to backfilling. This

matter is already coordinated with the C/P of Fiji side.

In addition, for project costing, the backfilling cost is considered as project cost but land acquisition cost

for hinter land is not considered because whether backfilling of hinterland is conducted or not actually is

depending on intention of land owners. Land acquisition is conducted up to the land side end of

embankment.

(5) Riverbank Protection

Riverbank Protection is basically installed when flood flow velocity is more than 2.0m/s in Japan. However,

riverbank protection is not planned at the moment but considered adaptively although the flood flow

velocity is more than 2.0m/s in some sections in Nadi River after the Priority Project. Adaptively, river

bank protection is installed after extreme bank erosion occurs, and a margin in the cross section is left at

outer side of river channel curve such as leave bank as a margin for erosion considering flow capacity or

setting-back of embankment considering land acquisition cost.

<The reason for the adaptive management of riverbank protection>

1) During the past maximum flood, extreme riverbank erosion does not occur

2) River bank protection can be expected by vegetation because vegetation is flourished on the banks,

3) Installation of riverbank protection will cause riverbank erosion negatively near the installation area.

In addition, detailed planning of cross section mentioned above shall be done in Detailed Design Stage. At

this moment, typical cross section is applied for the project costing because construction cost for typical

cross section is supposed to be higher than that of cross-section mentioned in above.

Results of flood flow velocity with calculation conditions are mentioned in Table 18-5.

As the external force, the rainfall scale is same as that of design flood (1/50). The shape of river channel

and roughness coefficient (composite roughness coefficient) is assumed in the river channel after

improvement.

Page 47: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-14

Table 18-5 Flood Flow velocity

Water DepthDegree of

roughness

Energy

Gradient

Velocity

(Average)

Velocity

(left bank

side)

Velocity

(right bank

side)

Water DepthDegree of

roughness

Energy

Gradient

Velocity

(Average)

Velocity

(left bank

side)

Velocity

(right bank

side)

a) Past

damage,

bank

erosion

b) Outer

bending and

asset

existing

c) Bridge

Protection

0.000 1.19 0.015 0.000138590 1.87 1.71 1.71 1.18 0.015 0.0002002 2.11 1.92 1.91

0.250 0.99 0.015 0.000251510 2.89 2.55 2.51 0.76 0.015 0.0008487 4.26 4.15 3.94

0.500 1.00 0.015 0.000331090 3.12 2.55 2.80 0.78 0.015 0.0013184 4.83 4.69 4.44

0.750 1.16 0.015 0.000287200 2.92 2.52 2.43 1.12 0.015 0.0008716 3.98 3.73 3.68

1.000 1.24 0.015 0.000291770 2.92 2.59 2.56 1.24 0.015 0.0011985 4.31 3.95 3.97

1.250 1.35 0.015 0.000257390 2.81 2.53 2.33 1.91 0.015 0.0003348 2.87 2.78 2.81

1.500 1.57 0.015 0.000145340 2.19 2.08 1.87 2.19 0.015 0.0001361 2.03 1.98 2.00

1.750 1.47 0.015 0.000245450 2.79 2.27 2.47 2.05 0.015 0.0002684 2.80 2.37 2.59

2.000 1.57 0.015 0.000239590 2.69 2.36 2.52 2.10 0.015 0.0003398 2.94 2.65 2.79

2.250 1.68 0.015 0.000221760 2.53 2.09 2.41 2.34 0.015 0.0001839 2.30 1.95 2.24

2.500 1.74 0.015 0.000186870 2.55 2.12 2.26 2.37 0.015 0.0001650 2.40 2.18 2.22

2.750 1.94 0.015 0.000122790 1.86 1.65 1.66 2.55 0.015 0.0000982 1.70 1.54 1.56

3.000 1.89 0.015 0.000177670 2.28 1.79 1.89 2.42 0.015 0.0002533 2.53 2.07 2.21

3.250 1.87 0.015 0.000224980 2.58 2.25 2.37 2.52 0.015 0.0002073 2.39 2.23 2.20

3.500 2.01 0.015 0.000170180 2.27 1.94 2.17 2.61 0.015 0.0001576 2.20 2.05 2.14

3.750 2.02 0.015 0.000214170 2.46 2.05 1.89 2.41 0.015 0.0004063 3.19 2.48 2.49

4.000 2.15 0.015 0.000163340 2.12 2.05 1.82 2.62 0.015 0.0003415 2.83 2.65 2.50

4.250 2.28 0.027 0.000521430 2.17 1.55 1.46 2.70 0.025 0.0011568 3.30 1.63 1.64

4.500 2.53 0.027 0.000449240 2.10 1.48 1.42 3.06 0.025 0.0010959 3.37 1.80 1.93

4.750 2.76 0.028 0.000537290 2.17 1.64 1.41 3.75 0.034 0.0014862 2.93 2.50 2.35

5.000 2.97 0.024 0.000301630 2.23 1.34 1.35 4.21 0.029 0.0006503 3.07 1.89 1.95

5.250 3.15 0.026 0.000280950 1.94 1.22 1.24 4.53 0.026 0.0005348 2.74 2.04 1.95

5.500 3.24 0.026 0.000353420 2.15 1.24 1.36 4.68 0.030 0.0012565 3.10 2.20 2.35

5.750 3.50 0.024 0.000082020 1.19 0.59 0.70 5.08 0.027 0.0003608 2.49 1.36 1.55 ○6.000 3.18 0.024 0.000575440 3.08 1.59 1.59 5.35 0.027 0.0012760 1.89 1.05 1.00

6.250 3.37 0.024 0.000555110 3.07 1.58 1.58 5.37 0.027 0.0007355 2.03 1.12 1.12

6.500 3.57 0.024 0.000497220 2.95 1.52 1.52 5.41 0.027 0.0010149 2.10 1.17 1.15

6.750 3.73 0.024 0.000478540 2.93 1.55 1.51 5.45 0.031 0.0007864 2.22 1.25 1.12 ○7.000 3.94 0.024 0.000381880 2.66 1.35 1.36 5.53 0.030 0.0008455 2.17 1.17 1.18 ○7.250 4.07 0.024 0.000365560 2.62 1.30 1.37 5.58 0.038 0.0003464 2.24 1.20 1.23

7.500 4.18 0.024 0.000391170 2.71 1.60 1.32 5.62 0.027 0.0004204 2.41 1.50 1.31

7.750 4.30 0.024 0.000390020 2.76 1.42 1.44 5.66 0.031 0.0003199 2.60 1.42 1.37

8.000 4.45 0.024 0.000360710 2.67 1.22 1.25 5.74 0.036 0.0002884 2.65 1.41 1.51

8.250 4.64 0.024 0.000310630 2.39 1.40 1.53 5.87 0.025 0.0002767 2.56 1.68 1.74

8.500 4.75 0.024 0.000334810 2.48 1.51 1.55 5.96 0.024 0.0004644 2.66 1.81 1.75

8.750 4.90 0.024 0.000314510 2.41 1.47 1.47 6.10 0.027 0.0005329 2.60 1.75 1.78 ○ ○9.000 5.05 0.024 0.000269650 2.29 1.41 1.47 6.23 0.027 0.0003936 2.51 1.72 1.74

9.250 5.17 0.024 0.000251270 2.19 1.43 1.18 6.36 0.033 0.0003575 2.36 1.58 1.49 ○9.500 5.26 0.024 0.000259360 2.25 1.45 1.35 6.45 0.027 0.0002866 2.41 1.74 1.33 ○9.750 5.36 0.024 0.000260990 2.27 1.41 1.39 6.57 0.027 0.0002083 2.44 1.93 1.56 ○ ○ Riverbank Protection

9.830 5.51 0.024 0.000218160 2.16 1.13 6.72 0.026 0.0001664 2.35 1.54 0.72

10.000 5.54 0.024 0.000251240 2.26 1.41 1.43 6.74 0.026 0.0004769 2.48 1.71 1.65

10.250 5.65 0.024 0.000246870 2.21 1.37 1.36 6.86 0.028 0.0011888 2.41 1.60 1.62 ○ ○10.500 5.76 0.024 0.000233430 2.18 1.33 1.39 6.96 0.027 0.0001672 2.39 1.60 1.63 ○10.750 5.85 0.024 0.000230050 2.18 1.38 1.33 7.04 0.029 0.0001803 2.40 1.67 1.60

11.000 5.97 0.024 0.000158780 1.98 1.07 1.11 7.17 0.027 0.0001161 2.21 1.45 1.49

11.250 5.99 0.025 0.000254200 2.25 1.40 1.40 7.18 0.028 0.0002095 2.46 1.70 1.67 ○ ○11.500 6.12 0.024 0.000210810 2.12 1.35 1.34 7.30 0.032 0.0001539 2.35 1.64 1.60

11.750 6.19 0.025 0.000245230 2.23 1.40 1.38 7.37 0.029 0.0002385 2.45 1.71 1.67

12.000 6.30 0.025 0.000231890 2.18 1.35 1.36 7.47 0.026 0.0001226 2.39 1.64 1.65

12.250 6.39 0.025 0.000241600 2.22 1.38 1.38 7.55 0.030 0.0001504 2.45 1.67 1.70

12.500 6.52 0.025 0.000194970 2.08 1.28 1.32 7.67 0.027 0.0001419 2.32 1.56 1.62

12.750 6.60 0.025 0.000225310 2.14 1.27 1.32 7.76 0.029 0.0001052 2.34 1.48 1.59 ○13.000 6.56 0.025 0.000451550 2.89 1.86 1.86 7.67 0.027 0.0003192 3.18 2.23 2.23 ○13.250 6.85 0.025 0.000370880 2.69 1.78 2.01 7.95 0.032 0.0002586 2.94 2.19 2.34 ○ ○13.500 7.10 0.025 0.000377600 2.65 1.85 1.99 8.16 0.027 0.0002751 2.93 2.24 2.35

13.750 7.30 0.025 0.000333760 2.61 1.68 1.74 8.33 0.029 0.0003270 2.95 2.09 2.13

14.000 7.44 0.025 0.000354970 2.69 1.83 1.73 8.46 0.031 0.0003051 3.05 2.24 2.14

14.250 7.60 0.025 0.000338180 2.72 1.78 1.84 8.61 0.030 0.0002225 3.12 2.23 2.27

14.500 7.78 0.025 0.000333640 2.63 1.73 1.77 8.80 0.027 0.0002785 2.99 2.13 2.18

14.750 8.08 0.027 0.000286400 2.13 1.40 1.75 9.15 0.031 0.0001422 2.33 1.71 2.03

15.000 8.16 0.026 0.000284940 2.48 1.64 1.71 9.16 0.032 0.0004092 2.86 2.06 2.12

15.250 8.30 0.025 0.000273310 2.47 1.63 1.63 9.31 0.029 0.0002953 2.82 2.03 2.02 ○15.500 8.45 0.026 0.000276110 2.42 1.66 1.63 9.45 0.031 0.0003191 2.77 2.04 2.03

15.750 8.64 0.026 0.000290330 2.31 1.57 1.81 9.66 0.034 0.0002585 2.55 1.93 2.12 ○16.000 8.77 0.025 0.000278160 2.45 1.62 1.61 9.75 0.033 0.0003857 2.80 2.00 2.02

16.250 8.91 0.025 0.000251170 2.39 1.63 1.56 9.89 0.027 0.0002621 2.76 2.02 1.97

16.500 9.04 0.025 0.000237910 2.33 1.57 1.54 10.03 0.032 0.0002635 2.69 1.96 1.93

16.750 9.34 0.026 0.000245740 2.32 1.56 1.53 10.40 0.029 0.0002078 2.64 2.13 2.09 ○ Riverbank Protection

17.000 9.48 0.026 0.000241060 2.31 1.72 1.74 10.54 0.032 0.0003910 2.62 2.10 2.09

17.250 9.62 0.025 0.000218610 2.27 1.52 1.48 10.67 0.029 0.0003734 2.59 1.90 1.84

17.500 9.79 0.027 0.000221150 2.05 1.66 1.50 10.86 0.034 0.0001059 2.33 1.98 1.84

17.750 9.86 0.026 0.000231610 2.27 1.61 1.50 10.90 0.028 0.0001189 2.60 1.98 1.85

18.000 9.97 0.026 0.000233340 2.28 1.48 1.52 11.02 0.037 0.0001030 2.60 1.85 1.90

18.250 10.09 0.025 0.000205930 2.26 1.48 1.52 11.13 0.036 0.0001517 2.61 1.85 1.89

18.500 10.04 0.026 0.000441550 3.03 2.14 2.13 11.01 0.031 0.0003711 3.51 2.66 2.65

18.750 10.43 0.025 0.000526450 3.16 1.92 2.11 11.50 0.031 0.0001821 3.51 2.66 2.81

19.000 10.71 0.028 0.000704840 2.74 2.29 2.29 11.72 0.030 0.0004255 3.08 2.69 2.69

19.250 11.21 0.028 0.000678190 2.66 2.23 2.23 12.13 0.031 0.0003281 3.01 2.63 2.63

19.500 11.74 0.028 0.000585680 2.59 2.17 2.17 12.67 0.034 0.0005938 2.95 2.58 2.58

19.750 12.09 0.028 0.000496610 2.70 2.24 2.27 13.06 0.031 0.0006562 3.10 2.68 2.72

20.000 12.52 0.028 0.000468760 2.47 2.09 2.09 13.42 0.031 0.0004566 2.84 2.49 2.49

20.250 12.90 0.028 0.000378190 2.44 2.06 2.06 13.83 0.031 0.0002452 2.81 2.47 2.47

20.500 13.21 0.029 0.000442940 2.39 2.02 2.02 14.11 0.035 0.0003203 2.88 2.53 2.53

20.750 13.50 0.029 0.000438930 2.37 2.01 2.01 14.36 0.030 0.0002652 2.86 2.51 2.51

21.000 13.89 0.028 0.000312890 2.57 2.24 2.24 14.84 0.028 0.0001203 3.10 2.78 2.78

21.250 13.99 0.030 0.000682360 2.51 2.19 2.19 14.80 0.029 0.0001786 3.02 2.72 2.72

21.500 14.57 0.030 0.000455850 2.46 2.14 2.14 15.49 0.031 0.0002128 2.96 2.66 2.66

21.750 14.89 0.030 0.000484000 2.41 2.11 2.11 15.79 0.028 0.0002408 2.90 2.62 2.62

22.000 15.28 0.028 0.000269290 2.37 2.08 2.08 16.19 0.031 0.0002098 3.00 2.71 2.71

22.250 15.61 0.027 0.000105960 2.34 2.05 2.05 16.68 0.026 0.0000832 2.95 2.66 2.66

22.500 15.42 0.031 0.000767510 2.31 2.03 2.03 16.18 0.034 0.0003624 2.90 2.62 2.62

22.750 16.11 0.031 0.000323530 2.63 2.31 2.31 17.27 0.031 0.0002048 2.86 2.59 2.59

23.000 16.24 0.030 0.000425690 2.57 2.26 2.26 17.32 0.030 0.0002858 2.82 2.55 2.55

23.250 16.61 0.033 0.000368010 2.52 2.22 2.22 17.67 0.032 0.0002463 2.79 2.53 2.53

23.500 16.84 0.043 0.000743410 2.47 2.18 2.18 17.83 0.039 0.0004763 2.76 2.50 2.50

23.750 17.21 0.035 0.000339860 2.44 2.15 2.15 18.06 0.034 0.0003705 3.43 3.11 3.11

24.000 17.15 0.031 0.000754130 2.39 2.10 2.10 17.67 0.030 0.0009251 3.31 3.00 3.00

24.250 17.93 0.031 0.000259490 2.13 1.81 1.82 19.16 0.031 0.0002862 2.81 2.53 2.46

24.500 18.05 0.035 0.000567050 2.75 2.50 2.46 19.17 0.033 0.0006263 3.71 3.46 3.41

24.750 18.46 0.028 0.000160740 1.98 1.68 1.56 19.79 0.028 0.0001944 2.65 2.33 2.22

25.000 18.48 0.028 0.000254140 2.58 2.07 2.15 19.72 0.028 0.0003298 3.52 2.94 3.07

25.250 18.789 0.029 0.000141620 1.90 1.25 1.20 20.22 0.029 0.0001745 2.55 2.24 2.21

25.500 18.953 0.035 0.000190190 1.56 1.44 1.30 20.39 0.037 0.0004362 2.73 2.55 2.34

25.750 19.08 0.038 0.000159340 1.41 1.29 1.26 20.73 0.039 0.0003746 2.50 2.32 2.24

26.000 19.176 0.034 0.000154170 1.37 1.10 1.23 21.02 0.036 0.0002938 2.21 1.88 1.99

26.250 19.254 0.037 0.000199370 1.55 1.42 1.37 21.16 0.038 0.0004327 2.63 2.39 2.40

26.500 19.392 0.036 0.000100130 1.15 0.96 1.02 21.53 0.037 0.0001997 1.88 1.63 1.71

26.750 19.429 0.039 0.000233720 1.53 1.40 1.38 21.59 0.041 0.0004495 2.48 2.32 2.26

27.000 19.529 0.035 0.000188490 1.61 1.42 1.38 21.79 0.036 0.0003845 2.66 2.40 2.33

27.060 19.565 0.039 0.000209760 1.55 1.43 1.36 21.87 0.039 0.0004413 2.60 2.43 2.32

27.250 19.685 0.049 0.000242170 1.22 1.12 1.21 22.20 0.050 0.0004446 1.86 1.81 1.82

27.500 19.776 0.040 0.000107270 0.99 0.83 0.93 22.40 0.041 0.0001772 1.49 1.28 1.46

27.750 19.82 0.040 0.000311820 1.48 1.37 1.33 22.51 0.043 0.0004541 1.91 1.86 1.70

28.000 19.987 0.036 0.000104720 1.06 0.87 0.95 22.76 0.038 0.0001604 1.57 1.37 1.41

28.250 19.997 0.040 0.000341880 1.76 1.62 1.61 22.73 0.040 0.0006072 2.64 2.53 2.41

28.500 20.154 0.029 0.000165340 1.64 1.06 1.34 23.10 0.031 0.0002372 2.21 1.72 1.66

28.750 20.298 0.030 0.000085830 1.20 0.95 0.87 23.35 0.031 0.0001313 1.71 1.26 1.36

Location

Flood Flow Velocity1)

Conditions near river channel

Riverbank Protection

Master Plan Priority Project

Adaptive management of

riverbank protection2)

Adaptive management of

riverbank protection

1)At hatching section in above table, the flow rate exceeds 2.0 m/s

2) Riverbank protection is considered adaptively, if necessary in the future, river bank protection shall be installed

Adaptive management of

riverbank protection

Adaptive management of

riverbank protection

Adaptive management of

riverbank protection

Adaptive management of

riverbank protection

Vel

oci

ty(

m)

Current River Channelsection

Transitionsection

River Widening Section

Retarding basinSection

Current River Channelsection

Page 48: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-15

18.2 Retarding Basin A, B

Retarding Basin A and B temporarily storage 80 m3/s in Retarding Basin A and 510 m3/s in Retarding

Basin B of flood discharge volume 2,450 m3/s before flood control, and flow 1,800m3/s at Back Road

Bridge with full in order to prevent inundation in Important Protected Area in Nadi River Basin.

No.25 2012年3月洪水

NawakaRiver NamosiRiver

[3,650]

1,000

[900]

900

[1,450]

1,000

NadiRiverNaditownBridge BackroadBridge

[2,450]

1,400

[2,450]

1,400

[2,450]

1,600[1,750]

830

Votualevu

[上段]:基本高水

下段:整備後流量(MP)

[3,650]

2,400

B

A

-200

-40

V=6,520千m3

V=640千m3

-1400

NawakaRiver NamosiRiver

[3,650]

1,000

[900]

730

[1,450]

1,130

NadiRiverNaditownBridge BackroadBridge

[2,450]

1,800

[2,450]

1,800

[2,450]

2,450[1,750]

1,740

Votualevu

[上段]:基本高水

下段:整備後流量(優先プロジェクト)

[3,650]

2,950

B

A

-510

-80

V=7,200千m3

V=1,000千m3

NawakaRiver

[Upper]: Discharge before Flood Control

[Lower]: Design Discharge after the Priority Project

V=7,200 thousand m3

V=1,000 thousand m3

Figure 18-10 Designed Discharge Distribution at the Priority Project

Although these basins are filled with flood water when large scale flood (more than 1/10 design return

period) occurs, flood water is drained to the river after flood and after clearing, basins become like normal

condition and it also becomes possible to cultivate. In addition, the river dike (surrounding dike of retarding

basins) is constructed together with the retarding basins so that the inundation damages by small scale flood

are reduced.

18.2.1 Retarding Basin A

(1) Layout and Facilities Design

Layout and Facilities Design is conducted considering ensuring of flood control discharge at the Priority

Project and smooth intake of peak cut discharge 80m3/s to the basin. In order to secure flood control

discharge, location of overflow dike is set at 20.5km of Nadi River.

Specifications of the basin are set in order to secure peak cut discharge through hydrological analysis. Peak

cut discharge, flood control discharge and outflow rate is set as mentioned in Table 18-6. Specifications of

drainage sluice gate (the number of gates, outflow rate) are set as a scale that flood water in the basin can

be drained within 24 hours2.

2 The reason is that the second peak of rainfall occurred 24 hours later and the durable inundated hours of sugar cane is

approximately 72 hours.

Table 18-6 Specifications for Retarding Basin A at the Priority Project

Retarding Basin A

Location Leftbank Side: 18.75k~21.0k

Flood Control Discharge(1000m3) 996

Peak Cut Discharge(m3/s) 80

Peak water level in the basin by calculation(EL.m) 14.50

60m

20.455~20.5k

13.53

(20.5k HWL)

Peak water level at overflow dike by calculation(EL.m) 14.51

Overflow Depth (m) 0.98

14.53

(20.5k Design Embannkment Height)

B1.5×H1.5×1Gate

Elevation of the bottom of drainage

waterway EL. 9.59 m

Outflow Rate Q=10.9m3/s

Drainage Time t=17.0 hrs

Length and Location of Overflow Dike

Elevation of the top of Overflow Dike(EL.m)

Design Elevation of Height of Embankment

surrounding the basin(EL.m)

Specifications of dicharge.

In addition, ground elevation in the basin is high in some part (high terrace). Therefore, high-level terrace

in the basin is excavated 1.5m to the bottom such as stripping topsoil and leveling in order to secure flood

control discharge in the basin4Layout of Retarding Basin A is as shown in Figure 18-11.

※Flow volume after the priority project include natural

flood volume at outside section of Important Protected Area

Page 49: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-16

Figure 18-11 Layout of Retarding Basin A 4 In the time of this study the area inside the retarding basin is to be done an acquisition by the intension of Ministry of Land, Fiji so that the compensation for crops is not required. In the detail design stage in future , in case that the easement is set instead of land acquisition, the compensation for crops will be necessary (same as the retarding B).

(2) Cross-Sectional Plan Either river or land side of slope gradient or surrounding dike and dike along the river are set as 1:3 based on River Embankment Design Criteria in Japan, 2007, River Improvement and Management Division, Water and Disaster Management Bureau, Ministry of Land, Infrastructure, Transport and Tourism. (see 18.1.4(1)a)

Bank width is set as 4.0m based on “Cabinet Order concerning Structural Standards for River Management Facilities, etc. Chapter III Article 21” . (see 18.1.4 (2))

Typical Cross Section is mentioned in Figure 18-12.

Retarding Basin B

Votualevu

Nasau

Nadi river Over Flow Dike (Intake)

Retarding Basin A

Outlet

Outlet

Over Flow Dike (Intake)

Meiganiyah

Page 50: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-17

Figure 18-12 General Plan of Retarding Basin A

Sluiceways of Drainage

Over Flow Dike

Plan View

Typical cross section

y

p

i

c

a

l

C

r

o

s

s

SLUICEWAYS of Drainage

y

p

i

c

a

l

C

r

o

s

s

S

e

c

t

i

o

n

Overflow- Dike

y

p

i

c

a

l

C

r

o

s

s

S

e

c

t

i

o

n

▼HWL 13.53m ▼EL. 14.53m

▼Design Bank Height 14.53m

▼EL. 9.59m

▼HWL 13.53m

▼HWL 13.53m

Nadi River

Longitudinal Plan

y

p

i

c

a

l

C

r

o

s

s

S

e

c

t

i

o

n

-5.0

0.0

5.0

10.0

15.0

20.0

25.0

30.0

15.0 16.0 17.0 18.0 19.0 20.0 21.0 22.0 23.0 24.0 25.0

Eleva

tion(

m)

km

Design Embankment Height HWL

Design Riverbed (after improvement) Ground Elevation at Right Bank

Ground Elevation at Left Bank Side Average Riverbed Elevation

Lowest Riverbed Elevation Calculation Water Level for Design Flood Discharge(Planned River)

Gradient of Design Riverbed=1/2,600Gradient of Design Riverbed=1/1,350

Gradient of HWL=1/1,600 Gradient of HWL=1/700 Gradient of HWL=1/1000

Retarding Basin A

Over Flow Dike A

20.455~20.50kEL.13.53m

Drainage Sluise A19.13kEL.9.59m

Retarding Basin B

Over Flow Dike B

19.75~24.10kEL. 17.25m

Drainage Sluise B19.13kEL.8.2m

Page 51: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-18

Figure 18-13 Typical Cross Section (Retarding Basin A,B)

Page 52: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-19

(3) Overflow Dike

Specifications of overflow dike are set in order to secure peak cut discharge.

Concrete facing structure is applied for basic structure of overflow dike because it can respond to relatively

severe hydraulic conditions and have strong durability, however there are some kinds of structures type

such as asphalt facing, concrete block facing and gabion facing.

In addition, the crest elevation of overflow dike is different between the Priority Project and Master Plan

because flood control discharge is different between them. Actually, flood control discharge at Master Plan

is lower than that at the Priority Project. Therefore, the crest elevation of overflow dike at Master Plan is

lower than that at the Priority Project and it is required to lower the crest elevation of overflow dike from

the Priority Project to Master Plan. In such a situation, it is planned that basic specifications of overflow

dike follows the those at Master Plan and L-shaped retaining wall is installed on the top of overflow dike in

order to secure the crest elevation at the Priority Project and can be removed at Master Plan. Details are

verified in detailed design stage.

Typical Cross Section of overflow dike is mentioned in Figure 18-13. The basic design of the over flow

dike is as shown in Figure 18-16 in case of larger scale retarding basin B.

Figure 18-14 Typical Cross Section of Overflow Dike for Retarding Basin A

Page 53: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-20

Figure 18-15 General Plan of Overflow Dike for Retarding Basin A

Page 54: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-21

18.2.2 Retarding Basin B

(1) Layout and Facilities Design

Layout and Facilities Design is conducted considering ensuring of flood control discharge at the Priority

Project and smooth intake of peak cut discharge 510m3/s to the basin. In order to secure flood control

discharge, location of overflow dike is set at 24.0km of Nadi River.

Specifications of the basin are set in order to secure peak cut discharge through hydrological analysis. Peak

cut discharge, flood control discharge and outflow rate is set as mentioned in Table 18-7. Specifications of

drainage sluice gate (the number of gates, outflow rate) are set as a scale that flood water in the basin can

be drained within 24 hours3.

3 The reason is that the second peak of rainfall occurred 24 hours later and the durable inundated hours of sugar cane is

approximately 72 hours.

Table 18-7 Specifications for Retarding Basin B at the Priority Project

Retarding Basin B

Location Rightbank Side: 19.75k~24.10k

Flood Control Discharge(1000m3) 7,157

Peak Cut Discharge(m3/s) 510

Peak water level in the basin by calculation(EL.m) 18.50

300m

23.65k~23.95k

17.25

(23.75k HWL-0.4m)

Peak water level at overflow dike by calculation(EL.m) 18.89

Overflow Depth (m) 1.64

19.05

(23.95k Design Embannkment Height)

B2.5×H2.5×2Gates

Elevation of the bottom of drainage

waterway EL. 8.20 m

Outflow Rate Q=93.1m3/s

Drainage Time t=16.4 hrs

Length and Location of Overflow Dike

Elevation of the top of Overflow Dike(EL.m)

Design Elevation of Height of Embankment

surrounding the basin(EL.m)

Specifications of dicharge.

In addition, ground elevation in the basin is high in some part (high terrace). Therefore, high-level terrace

in the basin is excavated 1.0m to the bottom such as stripping topsoil and leveling in order to secure flood

control discharge in the basin.

Layout of Retarding Basin B is as shown in Figure 18-16.

Page 55: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-22

Figure 18-16 Layout of Retarding Basin B

(2) Cross-Sectional Plan Either river or land side of slope gradient or surrounding dike and dike along the river are set as 1:3 based on River Embankment Design Criteria in Japan, 2007, River Improvement and Management Division, Water and Disaster Management Bureau, Ministry of Land, Infrastructure, Transport and Tourism. (see 18.1.4(1)a)

Bank width is set as 4.0m based on “Cabinet Order concerning Structural Standards for River Management Facilities, etc. Chapter III Article 21” . (see 18.1.4 (2))

Typical Cross Section is mentioned before in Figure 18-12.

Retarding Basin B

Votualevu

Nasau

Nadi river Over Flow Dike (Intake)

Retarding Basin A

Outlet

Outlet

Over Flow Dike (Intake)

Meiganiyah

Page 56: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-23

Figure 18-17 General Plan of Retarding Basin B

SLUICEWAYS of Drainage

Over Flow Dike

Plan View

Typical cross section

y

p

i

c

a

l

C

r

o

s

s

▼HWL 18.05m ▼EL. 19.05m

SLUICEWAYS of Drainage

y

p

i

c

a

l

C

r

o

s

s

S

e

c

t

i

o

n

Overflow- Dike

y

p

i

c

a

l

C

r

o

s

s

S

e

c

t

i

o

n

▼Design Bank Height 19.05m

▼HWL 18.05m

▼HWL 18.05m

Nadi River

Longitudinal Plan

y

p

i

c

a

l

C

r

o

s

s

S

e

c

t

i

o

n

-5.0

0.0

5.0

10.0

15.0

20.0

25.0

30.0

15.0 16.0 17.0 18.0 19.0 20.0 21.0 22.0 23.0 24.0 25.0

Eleva

tion(

m)

km

Design Embankment Height HWL

Design Riverbed (after improvement) Ground Elevation at Right Bank

Ground Elevation at Left Bank Side Average Riverbed Elevation

Lowest Riverbed Elevation Calculation Water Level for Design Flood Discharge(Planned River)

Gradient of Design Riverbed=1/2,600Gradient of Design Riverbed=1/1,350

Gradient of HWL=1/1,600 Gradient of HWL=1/700 Gradient of HWL=1/1000

Retarding Basin A

Over Flow Dike A

20.455~20.50kEL.13.53m

Drainage Sluise A19.13kEL.9.59m

Retarding Basin B

Over Flow Dike B

19.75~24.10kEL. 17.25m

Drainage Sluise B19.13kEL.8.2m

Page 57: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-24

(3) Overflow Dike

Specifications of overflow dike are set in order to secure peak cut discharge.

Concrete facing structure is applied for basic structure of overflow dike because it can respond to relatively

severe hydraulic conditions and have strong durability, however there are some kinds of structures type

such as asphalt facing, concrete block facing and gabion facing.

In addition, the crest elevation of overflow dike is different between the Priority Project and Master Plan

because flood control discharge is different between them. Actually, flood control discharge at Master Plan

is lower than that at the Priority Project. Therefore, the crest elevation of overflow dike at Master Plan is

lower than that at the Priority Project and it is required to lower the crest elevation of overflow dike from

the Priority Project to Master Plan. In such a situation, it is planned that basic specifications of overflow

dike follows the those at Master Plan and L-shaped retaining wall is installed on the top of overflow dike in

order to secure the crest elevation at the Priority Project and can be removed at Master Plan. Details are

verified in detailed design stage.

Typical Cross Section of overflow dike is mentioned in Figure 18-15. The basic design of the over flow

dike is as shown in Figure 18-16.

Figure 18-18 Typical Cross Section of Overflow Dike for Retarding Basin B

Page 58: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-25

Figure 18-19 General Plan of Overflow Dike for Retarding Basin B

Page 59: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-26

18.3 Surrounding Dike of Nadi Town Surrounding Dike of Nadi Town is installed mainly in order to prevent flood water of Nawaka River from flowing into Important Protected Area where central of Nadi Town is located.

18.3.1 Plan Surrounding Dike of Nadi Town are embankments which are installed as a priority project ahead of other dikes in other sections at left bank side of Nadi River and at right bank side of Nawaka River in order to prevent flood water of Nawaka River from flowing into Important Protected Area.

The location of dike is determined based on the inundation analysis, the alignment is set along the present river avoiding housing relocation.

In the area of proposed right dike of Nawaka River, Nawaka River around Queens Road meanders complexly and the old river channel is also left. The area has a function of natural retarding basin at present so that retarding effect is expected in flooding time and also the review of alignments will be examined in the Master Plan in future, and it is not effective for the new dikes to meander complexly along the present river channel (from view point of construction). Therefore the alignment of new dike is determined separately from the present river channel in smooth shape avoiding the relocation of housing

Plan of Surrounding Dike is as described in Figure 18-20.

Surrounding Dike

Surrounding Dike

Nadi Town Bridge

Nadi Town

Nawaka Village

Hindu Temple

Nawaka River

Figure 18-20 Plan of Surrounding Dike

18.3.2 Longitudinal Plan The Height of surrounding dike of Nadi Town is basically set as the same height as that of Master Plan.

However, inundation depth after the Priority Project when historical maximum flood occurs will exceed the height of embankment of Nawaka River. This is why retarding basins in tributaries area which are proposed in Master Plan are not installed as the Priority Project and flood discharge of target design scale exceeds the level of embankment of Master Plan of Nawaka River just only after the Priority Project. Therefore, the height of surrounding dike along Nawaka River is set as the same height of inundation depth after the Priority Project.

The longitudinal plan is as shown in Table 18-8.

Page 60: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-27

Table 18-8 Longitudinal Plan of Surrounding Dike of Nadi Town

River Landside

1 Cross 1 6.36 5.76 - - 6.76

2 Nadi 9.75K 6.36 5.72 6.28 - 6.72

3 Nadi 9.50K 5.96 5.61 6.16 - 6.61

4 Cross 2 5.43 - - 5.73 6.67

5 Cross 3 3.31 - - 5.73 6.70

6 Cross 4 5.19 - - 5.73 6.74

7 Cross 5 5.28 - - 6.68 8.00

8 Nawaka 0.75K 5.44 5.79 6.72 6.68 8.00

9 Cross 6 6.14 - - 7.79 8.00

10 Nawaka 2.00K 6.20 7.26 - 8.68 9.00

11 Cross 7 6.24 - - 8.58 9.00

12 Nawaka 2.50K 6.50 - 8.78 8.67 9.00

13 Nawaka 2.25K 6.50 7.56 8.73 8.67 9.00

14 Cross 8 6.56 - - 8.76 9.00

15 Cross 9 6.62 - - 8.76 9.00

16 Nawaka 2.75K 6.80 8.15 8.79 8.77 9.15

17 Nawaka 3.25K 7.04 8.73 8.95 8.91 9.73

18 Nawaka 3.50K 6.23 9.03 9.09 9.02 10.03

19 Nawaka 3.75K 7.26 9.32 9.24 9.03 10.32

20 Nawaka 4.00K 6.93 9.62 9.84 9.40 10.62

21 Nawaka 4.25K 10.07 9.91 10.05 9.29 10.91

22 Nawaka 4.50K 8.25 10.20 10.85 9.73 11.20

23 Nawaka 4.75K 9.58 10.50 11.21 11.21 11.50

24 Nawaka 5.00K 10.94 10.79 11.60 11.23 11.79

25 Nawaka 5.25K 11.00 11.09 12.11 - 12.09

Setting Basis

Following the inundation depth

of landside when 1/50 flood

occurs

Following the elevation of the

crest of embankment of the

Nadi River

Following the elevation of the

crest of embankment of the

Nawaka River

No. Cross Section HWLInundation Depth by calculation when 1/50 flood occurs Proposed height of

Surrounding Dike

Existing

Ground

Level

Location of Queens Road

18.3.3 Cross-Sectional Plan

Either river or land side of slope gradient of surrounding dike and dike along the river are set as 1:3 based

on River Embankment Design Criteria in Japan, 2007, River Improvement and Management Division,

Water and Disaster Management Bureau, Ministry of Land, Infrastructure, Transport and Tourism. (see

18.1.4(1)a)

Bank width is set as 4.0m based on “Cabinet Order concerning Structural Standards for River Management

Facilities, etc. Chapter III Article 21” (see Table 18-3).

Typical Cross Section is mentioned before in Figure 18-18.

Page 61: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-28

Figure 18-21 Typical Cross Section (Surrounding Dike of Nadi Town)

Surrounding Dike

断側線位置図 Location of Cross Section

Page 62: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-29

18.4 Ring Dike Ring Dike is installed in order to prevent flood water from flowing into community which is located in downstream natural inundation area.

18.4.1 Plan Ring Dike is arranged in a way that surrounds the outer edge of the community to be protected. Access slope road from outer side of ring dike to inner side, drainage system and outlet is also installed.

Plan of Ring Dike is as shown in Figure 18-19.

Ring Dike

1.0K

CrossSection

Ring Dike

Slope

Outlet of drainage

Figure 18-22 Plan of Ring Dike

18.4.2 Longitudinal Plan The elevation of inundation in downstream retarding basin is higher than water level in the Nadi River. Therefore, the elevation of the crest of Ring Dike is set considering on the elevation of inundation. The elevation of the crest of Ring Dike is set as E.L. 4.55m in entire section.

18.4.3 Cross-Sectional Plan Either river or land side of slope gradient of Ring Dike are set as 1:3 based on River Embankment Design Criteria in Japan, 2007, River Improvement and Management Division, Water and Disaster Management Bureau, Ministry of Land, Infrastructure, Transport and Tourism. (see 18.1.4(1)a)

Bank width is set as 4.0m based on “Cabinet Order concerning Structural Standards for River Management Facilities, etc. Chapter III Article 21” . (see 18.1.4 (2))

Typical Cross Section is mentioned in Figure 18-23.

Page 63: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-30

Figure 18-23 Typical Cross Section (Ring Dike)

Page 64: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-31

18.5 Shortcuts of tributaries Surrounding Dike of Nadi Town mentioned before in Chapter 18.3 cause negative impact (Increasing of Inundation Depth) around the confluence points of Nawaka River and the Malakua River. Shortcuts of tributaries is planned in order to mitigate the negative impact and flood flow can be drained smoothly to downstream by them.

The specifications (Length, Width) of shortcuts are set through hydrological analysis. Details of election of counter measures and flood analysis result are mentioned in “Final Report: VolumeⅡ, Main Report, PartⅠ:Master Plan Sturdy, 7.7.3(3) Counter Measures for Negative Impact caused by the Priority Project”.”.

Plan and typical cross section of shortcuts are described in Figure 18-24 and Figure 18-25.

Figure 18-24 Plan of Shortcuts of Tributaries

Page 65: THE PROJECT FOR THE PLANNING OF THE NADI RIVER FLOOD ... · The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji YACHIYO ENGINEERING CO.,LTD./CTI

The Project for the Planning of the Nadi River Flood Control Structures in the Republic of Fiji

YACHIYO ENGINEERING CO.,LTD./CTI ENGINEERING INTERNATIONAL CO.,LTD. JV

Final Report, Volume II Main Report, Part II: Feasibility Study

18-32

Figure 18-25 Typical Cross Section (Shortcuts of Tributaries)