time: 2:00 p.m. project: west campus dorms mechanical … documents/fo500078... · 4e) group 6:...

120
BID CLARIFICATION #1 January 8, 2020 DUE DATE: January 23, 2020 TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical Room Repairs Project Number: FO500078 LOCATION: University of Connecticut Capital Projects & Facilities Procurement 3 Discovery Drive Storrs, CT 06269 Attn: Walt Dalia Please note the following information must be incorporated into your proposal for the West Campus Dorms Mechanical Room Repairs, Project #FO500078: 1) Attached is the Pre-Bid Sign In Sheet 2) Attached are the CT Department of Labor Wage and Workplace Standards Division, Minimum Rates and Classifications for Building Construction dated December 30, 2019 3) Attached for use on bidding are updated Drawings, Project Manual and Bid Submission Sheet. Please use this sheet as the cover sheet for your Bid Submission. End of Bid Clarification #1

Upload: others

Post on 06-Feb-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

BID CLARIFICATION #1 January 8, 2020 DUE DATE: January 23, 2020 TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical Room Repairs Project Number: FO500078 LOCATION: University of Connecticut Capital Projects & Facilities Procurement 3 Discovery Drive Storrs, CT 06269 Attn: Walt Dalia Please note the following information must be incorporated into your proposal for the West Campus Dorms Mechanical Room Repairs, Project #FO500078:

1) Attached is the Pre-Bid Sign In Sheet 2) Attached are the CT Department of Labor Wage and Workplace Standards Division, Minimum Rates

and Classifications for Building Construction dated December 30, 2019 3) Attached for use on bidding are updated Drawings, Project Manual and Bid Submission Sheet.

Please use this sheet as the cover sheet for your Bid Submission.

End of Bid Clarification #1

Page 2: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal
Page 3: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

Project: W. Campus Dorms Mechanical Room Repair

Minimum Rates and Classifications for Building Construction Connecticut Department of Labor ID# : B 26817 Wage and Workplace Standards Division

By virtue of the authority vested in the Labor Commissioner under provisions of Section 31-53 of the General Statutes of Connecticut, as amended, the following are declared to be the prevailing rates and welfare payments and will apply only where the contract is advertised for bid within 20 days of the date on which the rates are established. Any contractor or subcontractor not obligated by agreement to pay to the welfare and pension fund shall pay this amount to each employee as part of his/her hourly wages.

Project Number: Project Town: Mansfield State# FAP#:

Project: West Campus Dorms Mechanical Room Repairs

CLASSIFICATION Hourly Rate Benefits

1a) Asbestos Worker/Insulator (Includes application of insulating materials, 38.25 27.96 protective coverings, coatings, & finishes to all types of mechanical systems; application of firestopping material for wall openings & penetrations in walls, floors, ceilings

1b) Asbestos/Toxic Waste Removal Laborers: Asbestos removal and encapsulation (except its removal from mechanical systems which are not to be scrapped), toxic waste removers, blasters.**See Laborers Group 7**

1c) Asbestos Worker/Heat and Frost Insulator 40.21 30.99

As of: Monday, December 30, 2019

Page 4: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

Project: NE Dorm Security Camera 300020

2) Boilermaker 38.34 26.01

3a) Bricklayer, Cement Mason, Concrete Finisher (including caulking), 34.72 32.55 + a Stone Masons

3b) Tile Setter 34.90 25.87

3c) Terrazzo Mechanics and Marble Setters 31.69 22.35

3d) Tile, Marble & Terrazzo Finishers 26.70 21.75

3e) Plasterer 33.48 32.06

As of: Monday, December 30, 2019

Page 5: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

Project: NE Dorm Security Camera 300020

------LABORERS------

4) Group 1: Laborers (common or general), acetylene burners, concrete 30.75 20.84 specialists, wrecking laborers, fire watchers.

4a) Group 2: Mortar mixers, plaster tender, power buggy operators, 31.00 20.84 powdermen, fireproofer/mixer/nozzleman (Person running mixer and spraying fireproof only).

4b) Group 3: Jackhammer operators/pavement breaker, mason tender 31.25 20.84 (brick), mason tender (cement/concrete), forklift operators and forklift operators (masonry).

4c) **Group 4: Pipelayers (Installation of water, storm drainage or sewage 31.75 20.84 lines outside of the building line with P6, P7 license) (the pipelayer rate shall apply only to one or two employees of the total crew who primary task is to actually perform the mating of pipe sections) P6 and P7 rate is $26.80.

4d) Group 5: Air track operator, sand blaster and hydraulic drills. 31.50 20.84

As of: Monday, December 30, 2019

Page 6: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

Project: NE Dorm Security Camera 300020

4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84

4f) Group 7: Asbestos/lead removal and encapsulation (except it's removal 31.75 20.84 from mechanical systems which are not to be scrapped).

4g) Group 8: Bottom men on open air caisson, cylindrical work and boring 29.03 20.84 crew.

4h) Group 9: Top men on open air caisson, cylindrical work and boring 28.49 20.84 crew.

4i) Group 10: Traffic Control Signalman 18.00 20.84

5) Carpenter, Acoustical Ceiling Installation, Soft Floor/Vinyl Floor/Carpet 33.53 25.66 Laying, Metal Stud Installation, Form Work and Scaffold Building, Drywall Hanging, Modular-Furniture Systems Installers, Lathers, Piledrivers, Resilient Floor Layers.

As of: Monday, December 30, 2019

Page 7: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

Project: NE Dorm Security Camera 300020

5a) Millwrights 34.04 26.09

6) Electrical Worker (including low voltage wiring) (Trade License required: 40.00 27.67+3% of E1,2 L-5,6 C-5,6 T-1,2 L-1,2 V-1,2,7,8,9) gross wage

7a) Elevator Mechanic (Trade License required: R-1,2,5,6) 53.37 33.705+a+b

-----LINE CONSTRUCTION----

Groundman 26.50 6.5% + 9.00

Linemen/Cable Splicer 48.19 6.5% + 22.00

As of: Monday, December 30, 2019

Page 8: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

Project: NE Dorm Security Camera 300020

8) Glazier (Trade License required: FG-1,2) 38.18 21.80 + a

9) Ironworker, Ornamental, Reinforcing, Structural, and Precast Concrete 36.67 35.77 Erection

----OPERATORS----

Group 1: Crane handling or erecting structural steel or stone, hoisting 40.97 24.80 + a engineer 2 drums or over, front end loader (7 cubic yards or over), work boat 26 ft. and over and Tunnel Boring Machines. (Trade License Required)

Group 2: Cranes (100 ton rate capacity and over); Excavator over 2 cubic 40.64 24.80 + a yards; Piledriver ($3.00 premium when operator controls hammer); Bauer Drill/Caisson. (Trade License Required)

Group 3: Excavator; Backhoe/Excavator under 2 cubic yards; Cranes (under 39.88 24.80 + a 100 ton rated capacity), Grader/Blade; Master Mechanic; Hoisting Engineer (all types of equipment where a drum and cable are used to hoist or drag material regardless of motive power of operation), Rubber Tire Excavator (Drott-1085 or similar);Grader Operator; Bulldozer Fine Grade. (slopes, shaping, laser or GPS, etc.). (Trade License Required)

As of: Monday, December 30, 2019

Page 9: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

Project: NE Dorm Security Camera 300020

Group 4: Trenching Machines; Lighter Derrick; Concrete Finishing 39.48 24.80 + a Machine; CMI Machine or Similar; Koehring Loader (Skooper).

Group 5: Specialty Railroad Equipment; Asphalt Paver; Asphalt 38.87 24.80 + a Reclaiming Machine; Line Grinder; Concrete Pumps; Drills with Self Contained Power Units; Boring Machine; Post Hole Digger; Auger; Pounder; Well Digger; Milling Machine (over 24" Mandrell)

Group 5 continued: Side Boom; Combination Hoe and Loader; Directional 38.87 24.80 + a Driller; Pile Testing Machine.

Group 6: Front End Loader (3 up to 7 cubic yards); Bulldozer (rough grade 38.55 24.80 + a dozer).

Group 7: Asphalt roller, concrete saws and cutters (ride on types), 38.20 24.80 + a vermeer concrete cutter, Stump Grinder; Scraper; Snooper; Skidder; Milling Machine (24" and under Mandrell).

Group 8: Mechanic, grease truck operator, hydroblaster; barrier mover; 37.79 24.80 + a power stone spreader; welding; work boat under 26 ft.; transfer machine.

As of: Monday, December 30, 2019

Page 10: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

Project: NE Dorm Security Camera 300020

Group 9: Front end loader (under 3 cubic yards), skid steer loader 37.34 24.80 + a regardless of attachments, (Bobcat or Similar): forklift, power chipper; landscape equipment (including Hydroseeder).

Group 10: Vibratory hammer; ice machine; diesel and air, hammer, etc. 35.24 24.80 + a

Group 11: Conveyor, earth roller, power pavement breaker (whiphammer), 35.24 24.80 + a robot demolition equipment.

Group 12: Wellpoint operator. 35.18 24.80 + a

Group 13: Compressor battery operator. 34.58 24.80 + a

Group 14: Elevator operator; tow motor operator (solid tire no rough 33.41 24.80 + a terrain).

As of: Monday, December 30, 2019

Page 11: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

Project: NE Dorm Security Camera 300020

Group 15: Generator Operator; Compressor Operator; Pump Operator; 32.99 24.80 + a Welding Machine Operator; Heater Operator.

Group 16: Maintenance Engineer/Oiler. 32.32 24.80 + a

Group 17: Portable asphalt plant operator; portable crusher plant operator; 36.76 24.80 + a portable concrete plant operator.

Group 18: Power safety boat; vacuum truck; zim mixer; sweeper; 34.26 24.80 + a (Minimum for any job requiring a CDL license).

------PAINTERS (Including Drywall Finishing)------

10a) Brush and Roller 34.62 21.80

As of: Monday, December 30, 2019

Page 12: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

Project: NE Dorm Security Camera 300020

10b) Taping Only/Drywall Finishing 35.37 21.80

10c) Paperhanger and Red Label 35.12 21.80

10e) Blast and Spray 37.62 21.80

11) Plumber (excluding HVAC pipe installation) (Trade License required: 43.62 32.06 P-1,2,6,7,8,9 J-1,2,3,4 SP-1,2)

12) Well Digger, Pile Testing Machine 37.26 24.05 + a

13) Roofer (composition) 37.60 20.65

As of: Monday, December 30, 2019

Page 13: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

Project: NE Dorm Security Camera 300020

14) Roofer (slate & tile) 38.10 20.65

15) Sheetmetal Worker (Trade License required for HVAC and Ductwork: 37.98 38.31 SM-1,SM-2,SM-3,SM-4,SM-5,SM-6)

16) Pipefitter (Including HVAC work) (Trade 43.62 32.06 License required: S-1,2,3,4,5,6,7,8 B-1,2,3,4 D-1,2,3,4, G-1, G-2, G-8 & G-9)

------TRUCK DRIVERS------

17a) 2 Axle 29.51 24.52 + a

17b) 3 Axle, 2 Axle Ready Mix 29.62 24.52 + a

As of: Monday, December 30, 2019

Page 14: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

Project: NE Dorm Security Camera 300020

17c) 3 Axle Ready Mix 29.67 24.52 + a

17d) 4 Axle, Heavy Duty Trailer up to 40 tons 29.72 24.52 + a

17e) 4 Axle Ready Mix 29.77 24.52 + a

17f) Heavy Duty Trailer (40 Tons and Over) 29.98 24.52 + a

17g) Specialized Earth Moving Equipment (Other Than Conventional Type 29.77 24.52 + a on-the-Road Trucks and Semi-Trailers, Including Euclids)

18) Sprinkler Fitter (Trade License required: F-1,2,3,4) 45.57 24.33 + a

As of: Monday, December 30, 2019

Page 15: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

Project: NE Dorm Security Camera 300020

19) Theatrical Stage Journeyman 25.76 7.34

As of: Monday, December 30, 2019

Page 16: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

Project: NE Dorm Security Camera 300020

Welders: Rate for craft to which welding is incidental. *Note: Hazardous waste removal work receives additional $1.25 per hour for truck drivers.

**Note: Hazardous waste premium $3.00 per hour over classified rate

ALL Cranes: When crane operator is operating equipment that requires a fully licensed crane operator to operate he receives an extra $4.00 premium in addition to the hourly wage rate and benefit contributions:

1) Crane handling or erecting structural steel or stone; hoisting engineer (2 drums or over)

2) Cranes (100 ton rate capacity and over) Bauer Drill/Caisson 3) Cranes (under 100 ton rated capacity) Crane with 150 ft. boom (including jib) - $1.50 extra Crane with 200 ft. boom (including jib) - $2.50 extra Crane with 250 ft. boom (including jib) - $5.00 extra Crane with 300 ft. boom (including jib) - $7.00 extra Crane with 400 ft. boom (including jib) - $10.00 extra

All classifications that indicate a percentage of the fringe benefits must be calculated at the percentage rate times the "base hourly rate".

Apprentices duly registered under the Commissioner of Labor's regulations on "Work Training Standards for Apprenticeship and Training Programs" Section 31-51-d-1 to 12, are allowed to be paid the appropriate percentage of the prevailing journeymen hourly base and the full fringe benefit rate, providing the work site ratio shall not be less than one full-time journeyperson instructing and supervising the work of each apprentice in a specific trade.

The Prevailing wage rates applicable to this project are subject to annual adjustments each July 1st for the duration of the project.

Each contractor shall pay the annual adjusted prevailing wage rate that is in effect each July 1st, as posted by the Department of Labor.

It is the contractor's responsibility to obtain the annual adjusted prevailing wage rate increases directly from the Department of Labor's website. The annual adjustments will be posted on the Department of Labor's Web page: www.ct.gov/dol. For those without internet access, please contact the division listed below.

The Department of Labor will continue to issue the initial prevailing wage rate schedule to the Contracting Agency for the project.

All subsequent annual adjustments will be posted on our Web Site for contractor access. Contracting Agencies are under no obligation pursuant to State labor law to pay any increase due to the annual adjustment provision.

As of: Monday, December 30, 2019

Page 17: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

Project: NE Dorm Security Camera 300020

Effective October 1, 2005 - Public Act 05-50: any person performing the work of any mechanic, laborer, or worker shall be paid prevailing wage

All Person who perform work ON SITE must be paid prevailing wage for the appropriate mechanic, laborer, or worker classification.

All certified payrolls must list the hours worked and wages paid to All Persons who perform work ON SITE regardless of their ownership i.e.: (Owners, Corporate Officers, LLC Members, Independent Contractors, et. al)

Reporting and payment of wages is required regardless of any contractual relationship alleged to exist between the contractor and such person.

~~Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clause (29 CFR 5.5 (a) (1) (ii)).

Please direct any questions which you may have pertaining to classification of work and payment of prevailing wages to the Wage and Workplace Standards Division, telephone (860)263-6790.

As of: Monday, December 30, 2019

Page 18: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

PRESIDENT

AREA OF RENOVATION : BLDGS 0223 - 0226

THOMAS KATSOULEAS

FACILITIES OPERATIONS - OPERATIONAL ENGINEERING

PROJECT: FO500078

BUILDINGS # 0223, 0224, 0225, 0226HILLSIDE ROADSTORRS, CT 06269

31 LEDOYT RD. UNIT 3038STORRS, CT 06269

860-486-3127

DEC 2019

PREPARED BY:

PROJECT SITE LOCATIONNO SCALE

STORRS CAMPUS

UNIVERSITY OF CONNECTICUTSTATE OF CONNECTICUT

DRAWING INDEX

MECHANICAL ELECTRICAL & PLUMBING

WEST CAMPUS DORMS

SITE

MECHANICAL ROOM REPAIRS

AutoCAD SHX Text
M-01 MECHANICAL LEGENDS AND NOTES
AutoCAD SHX Text
M-03 WC-2 REFURBISHMENT PLAN
AutoCAD SHX Text
M-04 WC-3 REFURBISHMENT PLAN
AutoCAD SHX Text
M-05 WC-4 REFURBISHMENT PLAN
AutoCAD SHX Text
M-06 WC-1 PLUMBING PIPING PLAN
AutoCAD SHX Text
M-07 WC-1 STEAM AND CONDENSATE
AutoCAD SHX Text
M-08 WC-2 PLUMBING PIPING PLAN
AutoCAD SHX Text
M-09 WC-2 STEAM AND CONDENSATE
AutoCAD SHX Text
CODE DATA
AutoCAD SHX Text
2016 CONNECTICUT STATE BUILDING CODE
AutoCAD SHX Text
BASED ON 2012 INTERNATIONAL MECHANICAL CODE
AutoCAD SHX Text
2012 INTERNATIONAL ENERGY CONSERVATION CODE
AutoCAD SHX Text
2014 NFPA 70 NATIONAL ELECTRICAL CODE
AutoCAD SHX Text
CONSTRUCTED DATE
AutoCAD SHX Text
GROSS SQUARE FEET
AutoCAD SHX Text
USE GROUP
AutoCAD SHX Text
HEIGHT
AutoCAD SHX Text
CONSTRUCTION TYPE
AutoCAD SHX Text
SPRINKLERS
AutoCAD SHX Text
1955
AutoCAD SHX Text
28,200
AutoCAD SHX Text
R-2
AutoCAD SHX Text
46 FT
AutoCAD SHX Text
2A
AutoCAD SHX Text
YES
AutoCAD SHX Text
WEST CAMPUS DORMS
AutoCAD SHX Text
2012 INTERNATIONAL PLUMBING CODE AND THE
AutoCAD SHX Text
M-10 WC-3 PLUMBING PIPING PLAN
AutoCAD SHX Text
NFPA 54 FUEL GAS CODE
AutoCAD SHX Text
M-02 WC-1 REFURBISHMENT PLAN
AutoCAD SHX Text
S-01 SITE PLAN
AutoCAD SHX Text
M-11 WC-3 STEAM AND CONDENSATE
AutoCAD SHX Text
BUILDING NUMBER
AutoCAD SHX Text
0223
AutoCAD SHX Text
DESIGNATION
AutoCAD SHX Text
WC-1
AutoCAD SHX Text
1955
AutoCAD SHX Text
28,200
AutoCAD SHX Text
R-2
AutoCAD SHX Text
46 FT
AutoCAD SHX Text
2A
AutoCAD SHX Text
YES
AutoCAD SHX Text
0224
AutoCAD SHX Text
WC-2
AutoCAD SHX Text
1955
AutoCAD SHX Text
28,200
AutoCAD SHX Text
R-2
AutoCAD SHX Text
46 FT
AutoCAD SHX Text
2A
AutoCAD SHX Text
YES
AutoCAD SHX Text
0225
AutoCAD SHX Text
WC-3
AutoCAD SHX Text
1955
AutoCAD SHX Text
28,200
AutoCAD SHX Text
R-2
AutoCAD SHX Text
46 FT
AutoCAD SHX Text
2A
AutoCAD SHX Text
YES
AutoCAD SHX Text
0226
AutoCAD SHX Text
WC-4
AutoCAD SHX Text
M-12 WC-4 PLUMBING PIPING PLAN
AutoCAD SHX Text
M-13 WC-4 STEAM AND CONDENSATE
AutoCAD SHX Text
M-14 MECHANICAL DETAILS
AutoCAD SHX Text
629.0
AutoCAD SHX Text
628.9
AutoCAD SHX Text
633.2
AutoCAD SHX Text
637.0
AutoCAD SHX Text
630.8
AutoCAD SHX Text
619.0
AutoCAD SHX Text
619.0
AutoCAD SHX Text
628.1
AutoCAD SHX Text
633.1
AutoCAD SHX Text
635.3
AutoCAD SHX Text
637.5
AutoCAD SHX Text
699.4
AutoCAD SHX Text
688.7
AutoCAD SHX Text
635.0
AutoCAD SHX Text
637.1
AutoCAD SHX Text
637.3
AutoCAD SHX Text
636.8
AutoCAD SHX Text
639.4
AutoCAD SHX Text
639.2
AutoCAD SHX Text
639.6
AutoCAD SHX Text
640.9
AutoCAD SHX Text
643.3
AutoCAD SHX Text
640.5
AutoCAD SHX Text
661.0
AutoCAD SHX Text
704.4
AutoCAD SHX Text
667.0
AutoCAD SHX Text
703.0
AutoCAD SHX Text
659.5
AutoCAD SHX Text
661.0
AutoCAD SHX Text
655.6
AutoCAD SHX Text
661.0
AutoCAD SHX Text
649.7
AutoCAD SHX Text
647.2
AutoCAD SHX Text
645.1
AutoCAD SHX Text
645.3
AutoCAD SHX Text
637.9
AutoCAD SHX Text
637.0
AutoCAD SHX Text
636.8
AutoCAD SHX Text
651.2
AutoCAD SHX Text
660.4
AutoCAD SHX Text
654.9
AutoCAD SHX Text
657.2
AutoCAD SHX Text
661.0
AutoCAD SHX Text
650.5
AutoCAD SHX Text
648.7
AutoCAD SHX Text
649.4
AutoCAD SHX Text
647.5
AutoCAD SHX Text
648.6
AutoCAD SHX Text
649.2
AutoCAD SHX Text
646.7
AutoCAD SHX Text
646.2
AutoCAD SHX Text
640.7
AutoCAD SHX Text
637.1
AutoCAD SHX Text
630.6
AutoCAD SHX Text
620.9
AutoCAD SHX Text
627.1
AutoCAD SHX Text
632.7
AutoCAD SHX Text
641.1
AutoCAD SHX Text
641.6
AutoCAD SHX Text
646.7
AutoCAD SHX Text
646.2
AutoCAD SHX Text
646.5
AutoCAD SHX Text
647.3
AutoCAD SHX Text
648.3
AutoCAD SHX Text
648.7
AutoCAD SHX Text
647.6
AutoCAD SHX Text
656.2
AutoCAD SHX Text
650.9
AutoCAD SHX Text
647.1
AutoCAD SHX Text
644.9
AutoCAD SHX Text
648.6
AutoCAD SHX Text
642.9
AutoCAD SHX Text
642.7
AutoCAD SHX Text
639.9
AutoCAD SHX Text
636.9
AutoCAD SHX Text
634.8
AutoCAD SHX Text
637.1
AutoCAD SHX Text
637.5
AutoCAD SHX Text
634.7
AutoCAD SHX Text
629.4
AutoCAD SHX Text
631.1
AutoCAD SHX Text
632.6
AutoCAD SHX Text
638.9
AutoCAD SHX Text
641.3
AutoCAD SHX Text
639.6
AutoCAD SHX Text
637.7
AutoCAD SHX Text
638.9
AutoCAD SHX Text
637.0
AutoCAD SHX Text
644.9
AutoCAD SHX Text
643.6
AutoCAD SHX Text
640.8
AutoCAD SHX Text
639.3
AutoCAD SHX Text
638.7
AutoCAD SHX Text
637.3
AutoCAD SHX Text
642.6
AutoCAD SHX Text
643.9
AutoCAD SHX Text
644.9
AutoCAD SHX Text
640.6
AutoCAD SHX Text
640.3
AutoCAD SHX Text
639.1
AutoCAD SHX Text
644.9
AutoCAD SHX Text
649.3
AutoCAD SHX Text
648.8
AutoCAD SHX Text
663.0
AutoCAD SHX Text
649.4
AutoCAD SHX Text
647.4
AutoCAD SHX Text
657.5
AutoCAD SHX Text
655.1
AutoCAD SHX Text
646.6
AutoCAD SHX Text
647.1
AutoCAD SHX Text
645.0
AutoCAD SHX Text
644.9
AutoCAD SHX Text
645.1
AutoCAD SHX Text
640.7
AutoCAD SHX Text
643.1
AutoCAD SHX Text
644.9
AutoCAD SHX Text
646.9
AutoCAD SHX Text
645.1
AutoCAD SHX Text
650.9
AutoCAD SHX Text
645.3
AutoCAD SHX Text
650.9
AutoCAD SHX Text
687.6
AutoCAD SHX Text
666.9
AutoCAD SHX Text
667.9
AutoCAD SHX Text
657.2
AutoCAD SHX Text
658.4
AutoCAD SHX Text
652.8
AutoCAD SHX Text
652.7
AutoCAD SHX Text
647.0
AutoCAD SHX Text
639.8
AutoCAD SHX Text
640.4
AutoCAD SHX Text
658.7
AutoCAD SHX Text
700.9
AutoCAD SHX Text
703.1
AutoCAD SHX Text
648.6
AutoCAD SHX Text
644.6
AutoCAD SHX Text
658.9
AutoCAD SHX Text
663.1
AutoCAD SHX Text
703.1
AutoCAD SHX Text
637.5
AutoCAD SHX Text
704.8
AutoCAD SHX Text
704.1
AutoCAD SHX Text
704.8
AutoCAD SHX Text
CB
AutoCAD SHX Text
RAMP
AutoCAD SHX Text
BASKETBALL COURT
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
RAMP
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
RAMP
AutoCAD SHX Text
VOLLEYBALL COURT
AutoCAD SHX Text
VOLLEYBALL COURT
AutoCAD SHX Text
GROUND OBSCURED
AutoCAD SHX Text
GROUND OBSCURED
AutoCAD SHX Text
GROUND OBSCURED
AutoCAD SHX Text
GROUND OBSCURED
AutoCAD SHX Text
GROUND OBSCURED
AutoCAD SHX Text
GROUND OBSCURED
AutoCAD SHX Text
GROUND OBSCURED
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
CONSTRUCTION
AutoCAD SHX Text
CONSTRUCTION
AutoCAD SHX Text
2
AutoCAD SHX Text
1
AutoCAD SHX Text
3
AutoCAD SHX Text
4
AutoCAD SHX Text
0'
AutoCAD SHX Text
20'
AutoCAD SHX Text
40'
AutoCAD SHX Text
N
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
W
AutoCAD SHX Text
60'
AutoCAD SHX Text
80'
Page 19: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

SIT

E P

LA

N

ME

CH

AN

IC

AL R

OO

M R

EP

AIR

S

AS

S

HO

WN

S-01

DE

C 2019

WE

ST

C

AM

PU

S D

OR

MS

FO

500078

AutoCAD SHX Text
629.0
AutoCAD SHX Text
628.9
AutoCAD SHX Text
633.2
AutoCAD SHX Text
637.0
AutoCAD SHX Text
630.8
AutoCAD SHX Text
619.0
AutoCAD SHX Text
619.0
AutoCAD SHX Text
628.1
AutoCAD SHX Text
633.1
AutoCAD SHX Text
635.3
AutoCAD SHX Text
637.5
AutoCAD SHX Text
699.4
AutoCAD SHX Text
688.7
AutoCAD SHX Text
635.0
AutoCAD SHX Text
637.1
AutoCAD SHX Text
637.3
AutoCAD SHX Text
636.8
AutoCAD SHX Text
639.4
AutoCAD SHX Text
639.2
AutoCAD SHX Text
639.6
AutoCAD SHX Text
640.9
AutoCAD SHX Text
643.3
AutoCAD SHX Text
640.5
AutoCAD SHX Text
661.0
AutoCAD SHX Text
704.4
AutoCAD SHX Text
667.0
AutoCAD SHX Text
703.0
AutoCAD SHX Text
659.5
AutoCAD SHX Text
661.0
AutoCAD SHX Text
655.6
AutoCAD SHX Text
661.0
AutoCAD SHX Text
649.7
AutoCAD SHX Text
647.2
AutoCAD SHX Text
645.1
AutoCAD SHX Text
645.3
AutoCAD SHX Text
637.9
AutoCAD SHX Text
637.0
AutoCAD SHX Text
636.8
AutoCAD SHX Text
651.2
AutoCAD SHX Text
660.4
AutoCAD SHX Text
654.9
AutoCAD SHX Text
657.2
AutoCAD SHX Text
661.0
AutoCAD SHX Text
650.5
AutoCAD SHX Text
648.7
AutoCAD SHX Text
649.4
AutoCAD SHX Text
647.5
AutoCAD SHX Text
648.6
AutoCAD SHX Text
649.2
AutoCAD SHX Text
646.7
AutoCAD SHX Text
646.2
AutoCAD SHX Text
640.7
AutoCAD SHX Text
637.1
AutoCAD SHX Text
630.6
AutoCAD SHX Text
620.9
AutoCAD SHX Text
627.1
AutoCAD SHX Text
632.7
AutoCAD SHX Text
641.1
AutoCAD SHX Text
641.6
AutoCAD SHX Text
646.7
AutoCAD SHX Text
646.2
AutoCAD SHX Text
646.5
AutoCAD SHX Text
647.3
AutoCAD SHX Text
648.3
AutoCAD SHX Text
648.7
AutoCAD SHX Text
647.6
AutoCAD SHX Text
656.2
AutoCAD SHX Text
650.9
AutoCAD SHX Text
647.1
AutoCAD SHX Text
644.9
AutoCAD SHX Text
648.6
AutoCAD SHX Text
642.9
AutoCAD SHX Text
642.7
AutoCAD SHX Text
639.9
AutoCAD SHX Text
636.9
AutoCAD SHX Text
634.8
AutoCAD SHX Text
637.1
AutoCAD SHX Text
637.5
AutoCAD SHX Text
634.7
AutoCAD SHX Text
629.4
AutoCAD SHX Text
631.1
AutoCAD SHX Text
632.6
AutoCAD SHX Text
638.9
AutoCAD SHX Text
641.3
AutoCAD SHX Text
639.6
AutoCAD SHX Text
637.7
AutoCAD SHX Text
638.9
AutoCAD SHX Text
637.0
AutoCAD SHX Text
644.9
AutoCAD SHX Text
643.6
AutoCAD SHX Text
640.8
AutoCAD SHX Text
639.3
AutoCAD SHX Text
638.7
AutoCAD SHX Text
637.3
AutoCAD SHX Text
642.6
AutoCAD SHX Text
643.9
AutoCAD SHX Text
644.9
AutoCAD SHX Text
640.6
AutoCAD SHX Text
640.3
AutoCAD SHX Text
639.1
AutoCAD SHX Text
644.9
AutoCAD SHX Text
649.3
AutoCAD SHX Text
648.8
AutoCAD SHX Text
663.0
AutoCAD SHX Text
649.4
AutoCAD SHX Text
647.4
AutoCAD SHX Text
657.5
AutoCAD SHX Text
655.1
AutoCAD SHX Text
646.6
AutoCAD SHX Text
647.1
AutoCAD SHX Text
645.0
AutoCAD SHX Text
644.9
AutoCAD SHX Text
645.1
AutoCAD SHX Text
640.7
AutoCAD SHX Text
643.1
AutoCAD SHX Text
644.9
AutoCAD SHX Text
646.9
AutoCAD SHX Text
645.1
AutoCAD SHX Text
650.9
AutoCAD SHX Text
645.3
AutoCAD SHX Text
650.9
AutoCAD SHX Text
687.6
AutoCAD SHX Text
666.9
AutoCAD SHX Text
667.9
AutoCAD SHX Text
657.2
AutoCAD SHX Text
658.4
AutoCAD SHX Text
652.8
AutoCAD SHX Text
652.7
AutoCAD SHX Text
647.0
AutoCAD SHX Text
639.8
AutoCAD SHX Text
640.4
AutoCAD SHX Text
658.7
AutoCAD SHX Text
700.9
AutoCAD SHX Text
703.1
AutoCAD SHX Text
648.6
AutoCAD SHX Text
644.6
AutoCAD SHX Text
658.9
AutoCAD SHX Text
663.1
AutoCAD SHX Text
703.1
AutoCAD SHX Text
637.5
AutoCAD SHX Text
704.8
AutoCAD SHX Text
704.1
AutoCAD SHX Text
704.8
AutoCAD SHX Text
CB
AutoCAD SHX Text
RAMP
AutoCAD SHX Text
BASKETBALL COURT
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
RAMP
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
CB
AutoCAD SHX Text
RAMP
AutoCAD SHX Text
VOLLEYBALL COURT
AutoCAD SHX Text
VOLLEYBALL COURT
AutoCAD SHX Text
GROUND OBSCURED
AutoCAD SHX Text
GROUND OBSCURED
AutoCAD SHX Text
GROUND OBSCURED
AutoCAD SHX Text
GROUND OBSCURED
AutoCAD SHX Text
GROUND OBSCURED
AutoCAD SHX Text
GROUND OBSCURED
AutoCAD SHX Text
GROUND OBSCURED
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
CONSTRUCTION
AutoCAD SHX Text
CONSTRUCTION
AutoCAD SHX Text
2
AutoCAD SHX Text
1
AutoCAD SHX Text
3
AutoCAD SHX Text
4
AutoCAD SHX Text
0'
AutoCAD SHX Text
20'
AutoCAD SHX Text
40'
AutoCAD SHX Text
N
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
W
AutoCAD SHX Text
60'
AutoCAD SHX Text
80'
AutoCAD SHX Text
UNIVERSITY OF CONNECTICUT
AutoCAD SHX Text
http://www.fo.uconn.edu
AutoCAD SHX Text
STORRS, CONNECTICUT
AutoCAD SHX Text
FACILITIES OPERATIONS
AutoCAD SHX Text
O
AutoCAD SHX Text
V
AutoCAD SHX Text
I
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
Y
AutoCAD SHX Text
T
AutoCAD SHX Text
T
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
8
AutoCAD SHX Text
C
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
C
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
T
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
E
AutoCAD SHX Text
R E V I S I O N S
AutoCAD SHX Text
Date
AutoCAD SHX Text
Mark
AutoCAD SHX Text
Description
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
MICHAEL J ROCCHETTI PE
AutoCAD SHX Text
MECHANICAL ENGINEER
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
Drawing Title
AutoCAD SHX Text
CAD File No.
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Drawn by
AutoCAD SHX Text
Approved by
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
Date
AutoCAD SHX Text
Scale
AutoCAD SHX Text
SITE PLAN - SCALE: 1/64" = 1'
Page 20: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

” ” ’ ”

ME

CH

AN

IC

AL LE

GE

ND

A

ND

N

OT

ES

ME

CH

AN

IC

AL R

OO

M R

EP

AIR

S

AS

S

HO

WN

M-01

DE

C 2019

WE

ST

C

AM

PU

S D

OR

MS

FO

500078

AutoCAD SHX Text
%%UGENERAL MECHANICAL NOTES
AutoCAD SHX Text
SCOPE OF WORK REPAIRS TO THE MECHANICAL ROOMS WILL INVOLVE THE FOLLOWING WORK REQUIREMENTS: PAINT THE WALLS, DOORS, CEILINGS, AND FLOORS. REPLACE THE SANITARY DRAIN WASTE & VENT PIPING. USE CAST IRON, GALVANIZED STEEL, OR COPPER. REFER TO SPECIFICATIONS. REPLACE WATER PIPING INCLUDING COLD WATER, HOT WATER, AND HOT WATER RETURN LINES. REPLACE ALL ASSOCIATED VALVES. REMOVE ABANDONED STEAM ZONE CONTROL VALVES AND ASSOCIATED CONTROLS. REPLACE ALL STEAM AND CONDENSATE RETURN PIPING WITHIN THE MECH ROOM, INCLUDING ALL VALVES, FITTINGS, TRAPS, AND CONTROLS. INSTALL NEW CONDENSATE RETURN PUMPS. INSULATE ALL STEAM, CONDENSATE, HOT WATER AND HOT WATER RECIRCULATING PIPES. INSTALL PVC JACKETING ON ALL HW AND HWR PIPING AND FITTINGS. WHERE INDICATED, INSTALL VERTICAL FLASH TANK FOR HIGH PRESSURE STEAM DRIP LEGS. VENT THESE FLASH TANKS INTO THE WINDOW WELLS. WHERE INDICATED, INSTALL NEW HOT WATER HEATERS. INSTALL NEW HOT WATER MIXING VALVES. REMOVE UNUSED CONCRETE PEDESTALS IN THE MECHANICAL ROOMS. REPAIR THE FLOOR DRAINS. REMOVE ABANDONED EQUIPMENT, PIPING VALVES, AND FITTINGS. CLEAN OUT THE WINDOW WELLS. PROVIDE NEW LED LIGHTING IN THE MECH ROOM. PROVIDE ELECTRICAL SERVICE FOR NEW CONDENSATE PUMPS, NEW WATER HEATERS, AND NEW HOT WATER MIXING VALVES.
AutoCAD SHX Text
SPEC
AutoCAD SHX Text
SPECIFICATION
AutoCAD SHX Text
VOLUME CONTROL DAMPER
AutoCAD SHX Text
VCD
AutoCAD SHX Text
LWT
AutoCAD SHX Text
LEAVING WATER TEMPERATURE
AutoCAD SHX Text
POUNDS
AutoCAD SHX Text
GRILLE
AutoCAD SHX Text
LOUVER
AutoCAD SHX Text
OA
AutoCAD SHX Text
OD
AutoCAD SHX Text
OC
AutoCAD SHX Text
LF
AutoCAD SHX Text
LW
AutoCAD SHX Text
NA
AutoCAD SHX Text
MC
AutoCAD SHX Text
KW
AutoCAD SHX Text
GR
AutoCAD SHX Text
NO
AutoCAD SHX Text
NC
AutoCAD SHX Text
MD
AutoCAD SHX Text
LV
AutoCAD SHX Text
NFA
AutoCAD SHX Text
NPT
AutoCAD SHX Text
NTS
AutoCAD SHX Text
MFR
AutoCAD SHX Text
MBH
AutoCAD SHX Text
LAT
AutoCAD SHX Text
HRC
AutoCAD SHX Text
HVAC
AutoCAD SHX Text
LBS
AutoCAD SHX Text
HHWS
AutoCAD SHX Text
HHWR
AutoCAD SHX Text
%%UABBREVIATIONS
AutoCAD SHX Text
LEAVING AIR TEMPERTURE
AutoCAD SHX Text
HEATING VENTILATION & AIR CONDITIONING
AutoCAD SHX Text
THOUSAND BRITISH THERMAL UNITS PER HOUR
AutoCAD SHX Text
LINEAR FOOT
AutoCAD SHX Text
LOW WALL
AutoCAD SHX Text
NET FREE AREA
AutoCAD SHX Text
NOT APPLICABLE
AutoCAD SHX Text
NOT TO SCALE
AutoCAD SHX Text
MANUFACTURER
AutoCAD SHX Text
OUTSIDE AIR
AutoCAD SHX Text
NATIONAL PIPE THREAD
AutoCAD SHX Text
MECHANICAL CONTRACTOR
AutoCAD SHX Text
OUTSIDE DIAMETER
AutoCAD SHX Text
ON CENTER
AutoCAD SHX Text
HEAT RECOVERY COIL
AutoCAD SHX Text
KILOWATTS
AutoCAD SHX Text
NORMALLY OPEN
AutoCAD SHX Text
NORMALLY CLOSED
AutoCAD SHX Text
MOTORIZED DAMPER
AutoCAD SHX Text
HEATING HOT WATER SUPPLY
AutoCAD SHX Text
HEATING HOT WATER RETURN
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
TD
AutoCAD SHX Text
SD
AutoCAD SHX Text
SA
AutoCAD SHX Text
RV
AutoCAD SHX Text
RA
AutoCAD SHX Text
P
AutoCAD SHX Text
SPR
AutoCAD SHX Text
TOP
AutoCAD SHX Text
TCC
AutoCAD SHX Text
SAN
AutoCAD SHX Text
SAD
AutoCAD SHX Text
SPIL
AutoCAD SHX Text
SAF
AutoCAD SHX Text
RAF
AutoCAD SHX Text
RPM
AutoCAD SHX Text
REG
AutoCAD SHX Text
REF
AutoCAD SHX Text
RTU
AutoCAD SHX Text
PRV
AutoCAD SHX Text
PTAC
AutoCAD SHX Text
RAH
AutoCAD SHX Text
PLC
AutoCAD SHX Text
TYPICAL
AutoCAD SHX Text
UH
AutoCAD SHX Text
V
AutoCAD SHX Text
VD
AutoCAD SHX Text
VAV
AutoCAD SHX Text
TXV
AutoCAD SHX Text
VTR
AutoCAD SHX Text
WMS
AutoCAD SHX Text
VFD
AutoCAD SHX Text
TSP
AutoCAD SHX Text
TYP
AutoCAD SHX Text
THERMAL EXPANSION VALVE
AutoCAD SHX Text
VARIABLE FREQUENCY DRIVE
AutoCAD SHX Text
UNIT HEATER
AutoCAD SHX Text
VENT THRU ROOF
AutoCAD SHX Text
VOLUME DAMPER
AutoCAD SHX Text
VALVE/VENT/VOLTS
AutoCAD SHX Text
WIRE MESH SCREEN
AutoCAD SHX Text
SOUND ATTENUATING DEVICE
AutoCAD SHX Text
REVOLUTIONS PER MINUTE
AutoCAD SHX Text
TEMPERATURE CONTROL CONTRACTOR
AutoCAD SHX Text
SANITARY
AutoCAD SHX Text
SUPPLY AIR FAN
AutoCAD SHX Text
SMOKE DAMPER
AutoCAD SHX Text
TRANSFER DUCT
AutoCAD SHX Text
SPRINKLER
AutoCAD SHX Text
SMOKE PURGE INTAKE LOUVER
AutoCAD SHX Text
TOTAL STATIC PRESSURE
AutoCAD SHX Text
TOP OF PIPE ELEVATION
AutoCAD SHX Text
RETURN AIR
AutoCAD SHX Text
RETURN AIR FAN
AutoCAD SHX Text
REGISTER
AutoCAD SHX Text
ROOF TOP UNIT
AutoCAD SHX Text
SUPPLY AIR
AutoCAD SHX Text
RELIEF VENT
AutoCAD SHX Text
PRESSURE RELIEF VALVE
AutoCAD SHX Text
ROOF EXHAUST FAN
AutoCAD SHX Text
PACKAGED TERMINAL AIR COND. UNIT
AutoCAD SHX Text
VARIABLE AIR VOLUME BOX
AutoCAD SHX Text
RELIEF AIR HOOD
AutoCAD SHX Text
PLUMBING CONTRACTOR
AutoCAD SHX Text
OV
AutoCAD SHX Text
OUTLET VELOCITY
AutoCAD SHX Text
AP
AutoCAD SHX Text
CFM
AutoCAD SHX Text
CFH
AutoCAD SHX Text
CHWS
AutoCAD SHX Text
CHWR
AutoCAD SHX Text
CP
AutoCAD SHX Text
C
AutoCAD SHX Text
BTU
AutoCAD SHX Text
BOP
AutoCAD SHX Text
BOD
AutoCAD SHX Text
BDD
AutoCAD SHX Text
BC
AutoCAD SHX Text
BTUH
AutoCAD SHX Text
AHU
AutoCAD SHX Text
AFF
AutoCAD SHX Text
CD
AutoCAD SHX Text
AD
AutoCAD SHX Text
CH
AutoCAD SHX Text
C/S
AutoCAD SHX Text
CC
AutoCAD SHX Text
B
AutoCAD SHX Text
AS
AutoCAD SHX Text
BB
AutoCAD SHX Text
BMS
AutoCAD SHX Text
BOOSTER COIL
AutoCAD SHX Text
CONVECTOR
AutoCAD SHX Text
CHILLER
AutoCAD SHX Text
CIRCUIT SETTER
AutoCAD SHX Text
COOLING COIL
AutoCAD SHX Text
BOILER
AutoCAD SHX Text
AIR SEPARATOR
AutoCAD SHX Text
BASEBOARD
AutoCAD SHX Text
EAT
AutoCAD SHX Text
FPM
AutoCAD SHX Text
FPI
AutoCAD SHX Text
FPS
AutoCAD SHX Text
FCU
AutoCAD SHX Text
F/D
AutoCAD SHX Text
FI
AutoCAD SHX Text
EC
AutoCAD SHX Text
EF
AutoCAD SHX Text
EUH
AutoCAD SHX Text
EWT
AutoCAD SHX Text
FBO
AutoCAD SHX Text
DWG
AutoCAD SHX Text
DIFF
AutoCAD SHX Text
DIA
AutoCAD SHX Text
DB
AutoCAD SHX Text
DDC
AutoCAD SHX Text
COND
AutoCAD SHX Text
CU
AutoCAD SHX Text
CUH
AutoCAD SHX Text
F
AutoCAD SHX Text
EA
AutoCAD SHX Text
CONDENSATE
AutoCAD SHX Text
DRAWING
AutoCAD SHX Text
DIAMETER
AutoCAD SHX Text
DIFFUSER
AutoCAD SHX Text
EXHAUST FAN
AutoCAD SHX Text
FINS PER INCH
AutoCAD SHX Text
FAN COIL UNIT
AutoCAD SHX Text
FIRE DAMPER
AutoCAD SHX Text
FILTER
AutoCAD SHX Text
EXHAUST AIR
AutoCAD SHX Text
FTR
AutoCAD SHX Text
HP
AutoCAD SHX Text
HW
AutoCAD SHX Text
CM
AutoCAD SHX Text
GC
AutoCAD SHX Text
HC
AutoCAD SHX Text
G
AutoCAD SHX Text
FSC
AutoCAD SHX Text
FPVBR
AutoCAD SHX Text
F/S
AutoCAD SHX Text
FPVB
AutoCAD SHX Text
GAS, NATURAL
AutoCAD SHX Text
HIGH WALL
AutoCAD SHX Text
HEATING COIL
AutoCAD SHX Text
FIN TUBE RADIATION
AutoCAD SHX Text
HORSEPOWER
AutoCAD SHX Text
CONSTRUCTION MANAGER
AutoCAD SHX Text
GENERAL CONTRACTOR
AutoCAD SHX Text
FEET PER SECOND/FIRE PROTECTION SYSTEM
AutoCAD SHX Text
ENTERING AIR TEMPERATURE
AutoCAD SHX Text
DIRECT DIGITAL CONTROL
AutoCAD SHX Text
DRY BULB TEMPERTURE
AutoCAD SHX Text
CONDENSING UNIT
AutoCAD SHX Text
CABINET UNIT HEATER
AutoCAD SHX Text
EXPANSION COMPENSATORS
AutoCAD SHX Text
ELECTRIC UNIT HEATER
AutoCAD SHX Text
FLOW INDICATOR
AutoCAD SHX Text
FEET PER MINUTE
AutoCAD SHX Text
ENTERING WATER TEMPERATURE
AutoCAD SHX Text
FURNISHED BY OTHERS
AutoCAD SHX Text
ACCESS PANEL IN WALL OR CLG.
AutoCAD SHX Text
BRITISH THERMAL UNIT PER HOUR
AutoCAD SHX Text
CUBIC FEET PER MINUTE
AutoCAD SHX Text
CUBIC FEET PER HOUR
AutoCAD SHX Text
BOTTOM OF DUCT ELEVATION
AutoCAD SHX Text
BOTTOM OF PIPE ELEVATION
AutoCAD SHX Text
BRITISH THERMAL UNIT
AutoCAD SHX Text
ABOVE FINISH FLOOR
AutoCAD SHX Text
AIR HANDLING UNIT
AutoCAD SHX Text
BACKDRAFT DAMPER
AutoCAD SHX Text
CHILLED WATER SUPPLY
AutoCAD SHX Text
CHILLED WATER RETURN
AutoCAD SHX Text
CONDENSATE PUMP
AutoCAD SHX Text
CONDENSATE DRAIN
AutoCAD SHX Text
FOOD SERVICE CONTRACTOR
AutoCAD SHX Text
FAN POWERED VARIABLE
AutoCAD SHX Text
VOLUME BOX WITH REHEAT
AutoCAD SHX Text
ACCESS DOOR IN DUCT
AutoCAD SHX Text
FIRE / SMOKE DAMPER
AutoCAD SHX Text
FAN POWERED VARIABLE VOLUME BOX
AutoCAD SHX Text
BUILDING MANAGEMENT SYSTEM
AutoCAD SHX Text
UNIT HEATER (HORIZONTAL THROW)
AutoCAD SHX Text
TEE UP
AutoCAD SHX Text
CHWS
AutoCAD SHX Text
CHWR
AutoCAD SHX Text
CHILLED WATER SUPPLY
AutoCAD SHX Text
CHILLED WATER RETURN
AutoCAD SHX Text
%%UHVAC PIPING SYMBOLS
AutoCAD SHX Text
%%UHVAC LEGENDS AND SYMBOLS
AutoCAD SHX Text
DIFFUSER TYPE
AutoCAD SHX Text
BUTTERFLY VALVE
AutoCAD SHX Text
CIRCUIT SETTER OR
AutoCAD SHX Text
BALANCING COCK
AutoCAD SHX Text
BALL VALVE
AutoCAD SHX Text
ANGLE VALVE
AutoCAD SHX Text
AUTOMATIC AIR VENT
AutoCAD SHX Text
ANCHOR
AutoCAD SHX Text
CFM
AutoCAD SHX Text
THROW
AutoCAD SHX Text
DIRECTION OF FLOW
AutoCAD SHX Text
CHECK VALVE
AutoCAD SHX Text
GAS SHUTOFF VALVE
AutoCAD SHX Text
HUMIDITY SENSOR
AutoCAD SHX Text
GLOBE VALVE
AutoCAD SHX Text
GATE VALVE
AutoCAD SHX Text
FLANGE
AutoCAD SHX Text
DRAIN WITH HOSE BIBB.
AutoCAD SHX Text
DIRECTION OF PITCH (DOWN)
AutoCAD SHX Text
EXPANSION COMPENSATOR
AutoCAD SHX Text
FLEXIBLE CONNECTION
AutoCAD SHX Text
%%UPIPING SYSTEM SYMBOLS
AutoCAD SHX Text
2 1/2" AND LARGER, BLIND FLANGE
AutoCAD SHX Text
2" AND SMALLER, CAP OR PLUG
AutoCAD SHX Text
ARROW INDICATING FAIL POSITION
AutoCAD SHX Text
ARROW INDICATING FAIL POSITION
AutoCAD SHX Text
PIPE DOWN
AutoCAD SHX Text
3-WAY DIVERTING VALVE WITH
AutoCAD SHX Text
TEE DOWN
AutoCAD SHX Text
PIPE UP
AutoCAD SHX Text
WATER METER
AutoCAD SHX Text
3-WAY MIXING VALVE WITH
AutoCAD SHX Text
3-WAY CONTROL VALVE
AutoCAD SHX Text
2-WAY CONTROL VALVE
AutoCAD SHX Text
THERMOMETER
AutoCAD SHX Text
TRIPLE DUTY VALVE
AutoCAD SHX Text
UNION
AutoCAD SHX Text
PIPE SLEEVE
AutoCAD SHX Text
MANUAL AIR VENT
AutoCAD SHX Text
PIPE GUIDES
AutoCAD SHX Text
REDUCED PRESSURE
AutoCAD SHX Text
PLUG VALVE
AutoCAD SHX Text
STRAINER
AutoCAD SHX Text
PRESSURE GAUGE
AutoCAD SHX Text
BACKFLOW PREVENTOR
AutoCAD SHX Text
PRESSURE REDUCING VALVE
AutoCAD SHX Text
PRESSURE RELIEF VALVE
AutoCAD SHX Text
X
AutoCAD SHX Text
%%UDUCT SYMBOLS
AutoCAD SHX Text
FD/AD
AutoCAD SHX Text
SD
AutoCAD SHX Text
F/S
AutoCAD SHX Text
VD
AutoCAD SHX Text
DUCT SECTION
AutoCAD SHX Text
FLEXIBLE DUCT
AutoCAD SHX Text
TURNING VANES
AutoCAD SHX Text
R
AutoCAD SHX Text
D
AutoCAD SHX Text
THERMOSTAT
AutoCAD SHX Text
(DUCT MOUNTED)
AutoCAD SHX Text
RET/EXH GRILLE OR REGISTER
AutoCAD SHX Text
SIDEWALL
AutoCAD SHX Text
SIDEWALL
AutoCAD SHX Text
SUPPLY
AutoCAD SHX Text
LINEAR
AutoCAD SHX Text
SLOT DIFFUSER
AutoCAD SHX Text
RET/EXH
AutoCAD SHX Text
REVERSE ACTING THERMOSTAT
AutoCAD SHX Text
SMOKE DETECTOR
AutoCAD SHX Text
SUPPLY DUCT SECTION
AutoCAD SHX Text
BLANKED OFF DIFFUSER
AutoCAD SHX Text
SUPPLY DIFFUSER
AutoCAD SHX Text
TEMPERATURE SENSOR
AutoCAD SHX Text
EXHAUST OR RETURN
AutoCAD SHX Text
ACOUSTICALLY LINED OR DOUBLE WALLED
AutoCAD SHX Text
PROPOSED DUCTWORK
AutoCAD SHX Text
(RETANGULAR DUCTS)
AutoCAD SHX Text
DUCT REHEAT COIL
AutoCAD SHX Text
FLEXIBLE CONNECTION
AutoCAD SHX Text
RETURN AIR (RA), RELIEF AIR OR EXHAUST AIR (EA)
AutoCAD SHX Text
(SOLID LINE UP, BROKEN LINE DOWN)
AutoCAD SHX Text
(SOLID LINE UP, BROKEN LINE DOWN)
AutoCAD SHX Text
SUPPLY AIR (SA) SUPPLY DUCT RISE & DROP
AutoCAD SHX Text
DUCT RISE/DROP W/90%%D ELBOWS
AutoCAD SHX Text
DUCT (ALSO SEE SPECIFICATIONS)
AutoCAD SHX Text
VOLUME CONTROL DAMPER
AutoCAD SHX Text
SMOKE DAMPER IN DUCT
AutoCAD SHX Text
FIRE DAMPER IN DUCT
AutoCAD SHX Text
W/ ACCESS DOOR
AutoCAD SHX Text
W/ ACCESS DOOR
AutoCAD SHX Text
IN DUCT W/ ACCESS DOOR
AutoCAD SHX Text
COMBINATION FIRE/SMOKE DAMPER
AutoCAD SHX Text
ACCESS DOOR
AutoCAD SHX Text
RET/EXH AIR FLOW
AutoCAD SHX Text
SUPPLY AIR FLOW
AutoCAD SHX Text
GRILLE
AutoCAD SHX Text
E.C.
AutoCAD SHX Text
%%USYMBOL KEY
AutoCAD SHX Text
XXX
AutoCAD SHX Text
XXX
AutoCAD SHX Text
%%uDIFFUSER
AutoCAD SHX Text
SERVICE WATER
AutoCAD SHX Text
CONDENSER WATER SUPPLY
AutoCAD SHX Text
CONDENSER WATER RETURN
AutoCAD SHX Text
CWR
AutoCAD SHX Text
CWS
AutoCAD SHX Text
UNIT HEATER (VERTICAL THROW)
AutoCAD SHX Text
BRICK VENT
AutoCAD SHX Text
BV
AutoCAD SHX Text
REQUIREMENTS
AutoCAD SHX Text
REG
AutoCAD SHX Text
COLD WATER RETURN
AutoCAD SHX Text
CW-RETURN
AutoCAD SHX Text
CW-SUPPLY
AutoCAD SHX Text
COLD WATER SUPPLY
AutoCAD SHX Text
SP
AutoCAD SHX Text
STATIC PRESSURE SENSOR
AutoCAD SHX Text
CONNECT TO EXISTING
AutoCAD SHX Text
MOTORIZED DAMPER
AutoCAD SHX Text
MD
AutoCAD SHX Text
U
AutoCAD SHX Text
DOOR UNDERCUT
AutoCAD SHX Text
FVNR
AutoCAD SHX Text
FULL VOLTAGE NON-REVERSING
AutoCAD SHX Text
SERVICE WATER
AutoCAD SHX Text
SW
AutoCAD SHX Text
ONE WAY DIFFUSER
AutoCAD SHX Text
C
AutoCAD SHX Text
DRY CONTACT
AutoCAD SHX Text
ACCUSTICAL LINING
AutoCAD SHX Text
AL
AutoCAD SHX Text
FC
AutoCAD SHX Text
FLEXIBLE CONNECTOR
AutoCAD SHX Text
S
AutoCAD SHX Text
T
AutoCAD SHX Text
T
AutoCAD SHX Text
T
AutoCAD SHX Text
P
AutoCAD SHX Text
H
AutoCAD SHX Text
M
AutoCAD SHX Text
Horizontal steel piping shall be supported in accordance with ANSI/MSS SP-69 & SP-58 Tables 3 and 4, excerpts of which follow below: Pipe Size Rod Dia Hanger Spacing Rod Dia Hanger Spacing Hanger Spacing >=1-1/4” 3/8” 7’-0” 3/8” 7’-0” 7’-0” -0” 1-1/2” 3/8” 9’-0” 3/8” 9’-0” 9’-0” -0” 2” 3/8” 10’-0” 3/8” 10’-0” 10’-0” -0” 2-1/2” 1/2” 11’-0” 1/2” 11’-0” 11’-0” -0” 3” 1/2” 12’-0” 1/2” 12’-0” 12’-0” -0” 3-1/2” 1/2” 13’-0” 1/2” 13’-0” 13’-0” -0” 4” 5/8” 14’-0” 5/8” 14’-0” 14’-0” -0” 5” 5/8” 16’-0” 5/8” 16’-0” 16’-0” -0” 6” 3/4” 17’-0” 3/4” 17’-0” 17’-0” -0” 8” 3/4” 19’-0” 3/4” 19’-0” 19’-0” -0” 10” 7/8” 22’-0” 7/8” 22’-0” 22’-0” -0” 12” 7/8” 23’-0” 7/8” 23’-0” 23’-0” -0” 14” 1” 25’-0” 1” 25’-0” 25’-0” -0” 16” 1” 27’-0”1” 27’-0”27’-0”-0”
AutoCAD SHX Text
Horizontal copper tubing shall be supported in accordance with ANSI/MSS SP-69 & SP-58 Tables 3 and 4, excerpts of which follow below: Tube Size Rod Dia Spacing Rod Dia Spacing Spacing >=3/4” 3/8” 5’-0” 3/8” 5’-0” 5’-0” -0” 1” 3/8” 6’-0” 3/8” 6’-0” 6’-0” -0” 11/4” 3/8” 7’-0” 3/8” 7’-0” 7’-0” -0” 11/2” 3/8” 8’-0” 3/8” 8’-0” 8’-0” -0” 2” 3/8” 8’-0” 3/8” 8’-0” 8’-0” -0” 21/2” 1/2” 9’-0” 1/2” 9’-0” 9’-0” -0” 3” 1/2” 10’-0” 1/2” 10’-0” 10’-0” -0” 31/2” 1/2” 11’-0” 1/2” 11’-0” 11’-0” -0” 4” 1/2” 12’-0” 1/2” 12’-0” 12’-0” -0” 5” 1/2” 13’-0” 1/2” 13’-0” 13’-0” -0” 6” 5/8” 14’-0” 5/8” 14’-0” 14’-0” -0” 8” 3/4” 16’-0”3/4” 16’-0”16’-0”-0”
AutoCAD SHX Text
350
AutoCAD SHX Text
251-350
AutoCAD SHX Text
201-250
AutoCAD SHX Text
141-200
AutoCAD SHX Text
105-140
AutoCAD SHX Text
40-60
AutoCAD SHX Text
<40
AutoCAD SHX Text
0.32-0.34
AutoCAD SHX Text
0.29-0.32
AutoCAD SHX Text
0.27-0.30
AutoCAD SHX Text
0.25-0.29
AutoCAD SHX Text
0.21-0.28
AutoCAD SHX Text
0.21-0.27
AutoCAD SHX Text
0.20-0.26
AutoCAD SHX Text
250
AutoCAD SHX Text
200
AutoCAD SHX Text
150
AutoCAD SHX Text
125
AutoCAD SHX Text
100
AutoCAD SHX Text
75
AutoCAD SHX Text
75
AutoCAD SHX Text
4.5"
AutoCAD SHX Text
3.0"
AutoCAD SHX Text
2.5"
AutoCAD SHX Text
1.5"
AutoCAD SHX Text
1.0"
AutoCAD SHX Text
0.5"
AutoCAD SHX Text
0.5"
AutoCAD SHX Text
5.0"
AutoCAD SHX Text
4.0"
AutoCAD SHX Text
2.5"
AutoCAD SHX Text
1.5"
AutoCAD SHX Text
1.0"
AutoCAD SHX Text
0.5"
AutoCAD SHX Text
1.0"
AutoCAD SHX Text
5.0"
AutoCAD SHX Text
4.5"
AutoCAD SHX Text
2.5"
AutoCAD SHX Text
2.0"
AutoCAD SHX Text
1.5"
AutoCAD SHX Text
1.0"
AutoCAD SHX Text
1.0"
AutoCAD SHX Text
5.0"
AutoCAD SHX Text
4.5"
AutoCAD SHX Text
3.0"
AutoCAD SHX Text
2.0"
AutoCAD SHX Text
1.5"
AutoCAD SHX Text
1.0"
AutoCAD SHX Text
1.0"
AutoCAD SHX Text
5.0"
AutoCAD SHX Text
4.5"
AutoCAD SHX Text
3.0"
AutoCAD SHX Text
2.0"
AutoCAD SHX Text
1.5"
AutoCAD SHX Text
1.0"
AutoCAD SHX Text
1.0"
AutoCAD SHX Text
FLUID OPERATING
AutoCAD SHX Text
TEMP RANGE (%%DF)
AutoCAD SHX Text
CONDUCTIVITY
AutoCAD SHX Text
BTU-IN/(HR FT2 %%DF)
AutoCAD SHX Text
MEAN
AutoCAD SHX Text
TEMP
AutoCAD SHX Text
<%%C1"
AutoCAD SHX Text
%%C1"<%%C1.5"
AutoCAD SHX Text
%%C1.5"<%%C4"
AutoCAD SHX Text
%%C4"<%%C8"
AutoCAD SHX Text
<%%C8"
AutoCAD SHX Text
PIPE SIZE
AutoCAD SHX Text
MINIMUM PIPE INSULATION THICKNESS
AutoCAD SHX Text
UNIVERSITY OF CONNECTICUT
AutoCAD SHX Text
http://www.fo.uconn.edu
AutoCAD SHX Text
STORRS, CONNECTICUT
AutoCAD SHX Text
FACILITIES OPERATIONS
AutoCAD SHX Text
O
AutoCAD SHX Text
V
AutoCAD SHX Text
I
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
Y
AutoCAD SHX Text
T
AutoCAD SHX Text
T
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
8
AutoCAD SHX Text
C
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
C
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
T
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
E
AutoCAD SHX Text
R E V I S I O N S
AutoCAD SHX Text
Date
AutoCAD SHX Text
Mark
AutoCAD SHX Text
Description
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
MICHAEL J ROCCHETTI PE
AutoCAD SHX Text
MECHANICAL ENGINEER
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
Drawing Title
AutoCAD SHX Text
CAD File No.
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Drawn by
AutoCAD SHX Text
Approved by
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
Date
AutoCAD SHX Text
Scale
Page 21: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

WC

-1 R

EF

UR

BIS

HM

EN

T P

LA

N

ME

CH

AN

IC

AL R

OO

M R

EP

AIR

S

AS

S

HO

WN

M-02

DE

C 2019

WE

ST

C

AM

PU

S D

OR

MS

FO

500078

AutoCAD SHX Text
B004
AutoCAD SHX Text
B006
AutoCAD SHX Text
B005
AutoCAD SHX Text
A007
AutoCAD SHX Text
ELEC
AutoCAD SHX Text
A005
AutoCAD SHX Text
B007
AutoCAD SHX Text
A006
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
SWITCH
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
BOOSTER PUMP
AutoCAD SHX Text
DISCONNECT
AutoCAD SHX Text
B008
AutoCAD SHX Text
MECH
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
BOOSTER
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
F.D.
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
WATER HEATER
AutoCAD SHX Text
WELLXTROL
AutoCAD SHX Text
TANK
AutoCAD SHX Text
FAN
AutoCAD SHX Text
SCREEN
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
2
AutoCAD SHX Text
3
AutoCAD SHX Text
4
AutoCAD SHX Text
4
AutoCAD SHX Text
FLR-TO-CLG HEIGHT
AutoCAD SHX Text
APPROX 7'-8"
AutoCAD SHX Text
$
AutoCAD SHX Text
5
AutoCAD SHX Text
5
AutoCAD SHX Text
5
AutoCAD SHX Text
0
AutoCAD SHX Text
2'
AutoCAD SHX Text
4'
AutoCAD SHX Text
6'
AutoCAD SHX Text
8'
AutoCAD SHX Text
10'
AutoCAD SHX Text
N
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
W
AutoCAD SHX Text
M
AutoCAD SHX Text
M
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
TO
AutoCAD SHX Text
6
AutoCAD SHX Text
7
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
TO
AutoCAD SHX Text
8
AutoCAD SHX Text
2
AutoCAD SHX Text
4
AutoCAD SHX Text
PAINT ALL WALLS AND CEILING IN THE MECH ROOM
AutoCAD SHX Text
CLEAN OUT THE WINDOW WELL.
AutoCAD SHX Text
REMOVE CONCRETE PEDESTALS AND PATCH FLOOR
AutoCAD SHX Text
1
AutoCAD SHX Text
REMOVE OLD FLOOR DRAIN, INSTALL NEW FLOOR DRAIN
AutoCAD SHX Text
3
AutoCAD SHX Text
UNDERNEATH.
AutoCAD SHX Text
JOSAM 32100 OR EQUAL.
AutoCAD SHX Text
5
AutoCAD SHX Text
REMOVE EXISTING LIGHTING FIXTURES AND INSTALL 4 NEW
AutoCAD SHX Text
FIXTURES - LITHONIA CNY-LED-P1-40K-MVOLT-WH
AutoCAD SHX Text
6
AutoCAD SHX Text
PROVIDE WIRING, CONDUITS, AND DISCONNECTS FOR NEW
AutoCAD SHX Text
CONDENSATE PUMPS, 2 HP, 208/3/60
AutoCAD SHX Text
7
AutoCAD SHX Text
PROVIDE WIRING, CONDUITS, AND SWITCH FOR NEW MIXING
AutoCAD SHX Text
VALVE CONTROLLER. 110/1%%C/60HZ
AutoCAD SHX Text
8
AutoCAD SHX Text
PROVIDE POWER CONNECTION (WIRING, & CONDUITS) FOR
AutoCAD SHX Text
NEW WATER HEATER. 110/1%%C/60HZ
AutoCAD SHX Text
A SOLVENT BASED, GLOSS, TWO COMPONENT, EPOXY COATING SPECIFIED FOR WALL AND FLOOR SURFACES IN MODERATE TO HEAVY TRAFFIC COMMERCIAL AND MODERATE INDUSTRIAL ENVIRONMENTS. MUST BE RESISTANT TO INCIDENTAL SPLASH AND SPILLAGE OF DILUTE (5%) SULFURIC ACID, (15%) HYDROCHLORIC ACID, (20%) SODIUM HYDROXIDE, GASOLINE AND HEAVY DUTY CLEANERS AND DETERGENTS. USED AS A SELF-PRIMING MATERIAL ON SMOOTH, LOW POROSITY CONCRETE, MASONRY AND WOOD SURFACES. MECHANICAL ROOMS INTERIOR WALLS, DOORS, FLOORS, & CEILINGS: PRIME COAT: EPOXY, GLOSS, MPI #77. INTERMEDIATE COAT: EPOXY, GLOSS, MPI #77. TOPCOAT: EPOXY, GLOSS, MPI #77. COLOR: WHITEWHITE
AutoCAD SHX Text
INTERIOR HIGH-PERFORMANCE COATINGS
AutoCAD SHX Text
UNIVERSITY OF CONNECTICUT
AutoCAD SHX Text
http://www.fo.uconn.edu
AutoCAD SHX Text
STORRS, CONNECTICUT
AutoCAD SHX Text
FACILITIES OPERATIONS
AutoCAD SHX Text
O
AutoCAD SHX Text
V
AutoCAD SHX Text
I
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
Y
AutoCAD SHX Text
T
AutoCAD SHX Text
T
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
8
AutoCAD SHX Text
C
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
C
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
T
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
E
AutoCAD SHX Text
R E V I S I O N S
AutoCAD SHX Text
Date
AutoCAD SHX Text
Mark
AutoCAD SHX Text
Description
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
MICHAEL J ROCCHETTI PE
AutoCAD SHX Text
MECHANICAL ENGINEER
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
Drawing Title
AutoCAD SHX Text
CAD File No.
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Drawn by
AutoCAD SHX Text
Approved by
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
Date
AutoCAD SHX Text
Scale
AutoCAD SHX Text
KEY PLAN (NTS)
AutoCAD SHX Text
WORK
AutoCAD SHX Text
AREA
AutoCAD SHX Text
SCALE 1/2" = 1 FT
AutoCAD SHX Text
0223 UConn WC Alsop Hall - WC-1
Page 22: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

WC

-2 R

EF

UR

BIS

HM

EN

T P

LA

N

ME

CH

AN

IC

AL R

OO

M R

EP

AIR

S

AS

S

HO

WN

M-03

DE

C 2019

WE

ST

C

AM

PU

S D

OR

MS

FO

500078

AutoCAD SHX Text
B006
AutoCAD SHX Text
B004
AutoCAD SHX Text
B005
AutoCAD SHX Text
B007
AutoCAD SHX Text
A007
AutoCAD SHX Text
A006
AutoCAD SHX Text
A005
AutoCAD SHX Text
N
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
W
AutoCAD SHX Text
ELEC
AutoCAD SHX Text
B008
AutoCAD SHX Text
MECH
AutoCAD SHX Text
WATER HEATER
AutoCAD SHX Text
F.D.
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
BOOSTER PUMP
AutoCAD SHX Text
DISCONNECT
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
BOOSTER
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
BUFFER
AutoCAD SHX Text
TANK
AutoCAD SHX Text
FAN
AutoCAD SHX Text
SCREEN
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
3
AutoCAD SHX Text
3
AutoCAD SHX Text
FLR-TO-CLG HEIGHT
AutoCAD SHX Text
APPROX 7'-8"
AutoCAD SHX Text
L
AutoCAD SHX Text
L
AutoCAD SHX Text
L
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
4
AutoCAD SHX Text
4
AutoCAD SHX Text
4
AutoCAD SHX Text
$
AutoCAD SHX Text
0
AutoCAD SHX Text
2'
AutoCAD SHX Text
4'
AutoCAD SHX Text
6'
AutoCAD SHX Text
8'
AutoCAD SHX Text
10'
AutoCAD SHX Text
M
AutoCAD SHX Text
M
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
TO
AutoCAD SHX Text
5
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
TO
AutoCAD SHX Text
6
AutoCAD SHX Text
3
AutoCAD SHX Text
PAINT ALL WALLS AND CEILING IN THE MECH ROOM
AutoCAD SHX Text
CLEAN OUT THE WINDOW WELL.
AutoCAD SHX Text
1
AutoCAD SHX Text
REMOVE OLD FLOOR DRAIN, INSTALL NEW FLOOR DRAIN
AutoCAD SHX Text
2
AutoCAD SHX Text
JOSAM 32100 OR EQUAL.
AutoCAD SHX Text
4
AutoCAD SHX Text
REMOVE EXISTING LIGHTING FIXTURES AND INSTALL 4 NEW
AutoCAD SHX Text
FIXTURES - LITHONIA CNY-LED-P1-40K-MVOLT-WH
AutoCAD SHX Text
5
AutoCAD SHX Text
PROVIDE WIRING, CONDUITS, AND DISCONNECTS FOR NEW
AutoCAD SHX Text
CONDENSATE PUMPS, 2 HP, 208/3/60
AutoCAD SHX Text
6
AutoCAD SHX Text
PROVIDE WIRING, CONDUITS, AND SWITCH FOR NEW MIXING
AutoCAD SHX Text
VALVE CONTROLLER. 110/1%%C/60HZ
AutoCAD SHX Text
A SOLVENT BASED, GLOSS, TWO COMPONENT, EPOXY COATING SPECIFIED FOR WALL AND FLOOR SURFACES IN MODERATE TO HEAVY TRAFFIC COMMERCIAL AND MODERATE INDUSTRIAL ENVIRONMENTS. MUST BE RESISTANT TO INCIDENTAL SPLASH AND SPILLAGE OF DILUTE (5%) SULFURIC ACID, (15%) HYDROCHLORIC ACID, (20%) SODIUM HYDROXIDE, GASOLINE AND HEAVY DUTY CLEANERS AND DETERGENTS. USED AS A SELF-PRIMING MATERIAL ON SMOOTH, LOW POROSITY CONCRETE, MASONRY AND WOOD SURFACES. MECHANICAL ROOMS INTERIOR WALLS, DOORS, FLOORS, & CEILINGS: PRIME COAT: EPOXY, GLOSS, MPI #77. INTERMEDIATE COAT: EPOXY, GLOSS, MPI #77. TOPCOAT: EPOXY, GLOSS, MPI #77. COLOR: WHITEWHITE
AutoCAD SHX Text
INTERIOR HIGH-PERFORMANCE COATINGS
AutoCAD SHX Text
UNIVERSITY OF CONNECTICUT
AutoCAD SHX Text
http://www.fo.uconn.edu
AutoCAD SHX Text
STORRS, CONNECTICUT
AutoCAD SHX Text
FACILITIES OPERATIONS
AutoCAD SHX Text
O
AutoCAD SHX Text
V
AutoCAD SHX Text
I
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
Y
AutoCAD SHX Text
T
AutoCAD SHX Text
T
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
8
AutoCAD SHX Text
C
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
C
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
T
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
E
AutoCAD SHX Text
R E V I S I O N S
AutoCAD SHX Text
Date
AutoCAD SHX Text
Mark
AutoCAD SHX Text
Description
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
MICHAEL J ROCCHETTI PE
AutoCAD SHX Text
MECHANICAL ENGINEER
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
Drawing Title
AutoCAD SHX Text
CAD File No.
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Drawn by
AutoCAD SHX Text
Approved by
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
Date
AutoCAD SHX Text
Scale
AutoCAD SHX Text
KEY PLAN (NTS)
AutoCAD SHX Text
WORK
AutoCAD SHX Text
AREA
AutoCAD SHX Text
SCALE 1/2" = 1 FT
AutoCAD SHX Text
0224 UConn WC Hollister Hall - WC-2
Page 23: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

WC

-3 R

EF

UR

BIS

HM

EN

T P

LA

N

ME

CH

AN

IC

AL R

OO

M R

EP

AIR

S

AS

S

HO

WN

M-04

DE

C 2019

WE

ST

C

AM

PU

S D

OR

MS

FO

500078

AutoCAD SHX Text
UP
AutoCAD SHX Text
A006
AutoCAD SHX Text
A007
AutoCAD SHX Text
B006
AutoCAD SHX Text
ELEC
AutoCAD SHX Text
WELLXTROL
AutoCAD SHX Text
TANK
AutoCAD SHX Text
BOOSTER
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
WATER HEATER
AutoCAD SHX Text
F.D.
AutoCAD SHX Text
B008
AutoCAD SHX Text
MECH
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
BOOSTER PUMP
AutoCAD SHX Text
DISCONNECT
AutoCAD SHX Text
FAN
AutoCAD SHX Text
SCREEN
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
2
AutoCAD SHX Text
3
AutoCAD SHX Text
4
AutoCAD SHX Text
4
AutoCAD SHX Text
FLR-TO-CLG HEIGHT
AutoCAD SHX Text
APPROX 7'-8"
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
$
AutoCAD SHX Text
5
AutoCAD SHX Text
5
AutoCAD SHX Text
5
AutoCAD SHX Text
0
AutoCAD SHX Text
2'
AutoCAD SHX Text
4'
AutoCAD SHX Text
6'
AutoCAD SHX Text
8'
AutoCAD SHX Text
10'
AutoCAD SHX Text
N
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
W
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
TO
AutoCAD SHX Text
8
AutoCAD SHX Text
7
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
SWITCH
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
M
AutoCAD SHX Text
M
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
TO
AutoCAD SHX Text
6
AutoCAD SHX Text
2
AutoCAD SHX Text
4
AutoCAD SHX Text
PAINT ALL WALLS AND CEILING IN THE MECH ROOM
AutoCAD SHX Text
CLEAN OUT THE WINDOW WELL.
AutoCAD SHX Text
REMOVE CONCRETE PEDESTALS AND PATCH FLOOR
AutoCAD SHX Text
1
AutoCAD SHX Text
REMOVE OLD FLOOR DRAIN, INSTALL NEW FLOOR DRAIN
AutoCAD SHX Text
3
AutoCAD SHX Text
UNDERNEATH.
AutoCAD SHX Text
JOSAM 32100 OR EQUAL.
AutoCAD SHX Text
5
AutoCAD SHX Text
REMOVE EXISTING LIGHTING FIXTURES AND INSTALL 4 NEW
AutoCAD SHX Text
FIXTURES - LITHONIA CNY-LED-P1-40K-MVOLT-WH
AutoCAD SHX Text
6
AutoCAD SHX Text
PROVIDE WIRING, CONDUITS, AND DISCONNECTS FOR NEW
AutoCAD SHX Text
CONDENSATE PUMPS, 2 HP, 208/3/60
AutoCAD SHX Text
7
AutoCAD SHX Text
PROVIDE WIRING, CONDUITS, AND SWITCH FOR NEW MIXING
AutoCAD SHX Text
VALVE CONTROLLER. 110/1%%C/60HZ
AutoCAD SHX Text
8
AutoCAD SHX Text
PROVIDE POWER CONNECTION (WIRING, & CONDUITS) FOR
AutoCAD SHX Text
NEW WATER HEATER. 110/1%%C/60HZ
AutoCAD SHX Text
A SOLVENT BASED, GLOSS, TWO COMPONENT, EPOXY COATING SPECIFIED FOR WALL AND FLOOR SURFACES IN MODERATE TO HEAVY TRAFFIC COMMERCIAL AND MODERATE INDUSTRIAL ENVIRONMENTS. MUST BE RESISTANT TO INCIDENTAL SPLASH AND SPILLAGE OF DILUTE (5%) SULFURIC ACID, (15%) HYDROCHLORIC ACID, (20%) SODIUM HYDROXIDE, GASOLINE AND HEAVY DUTY CLEANERS AND DETERGENTS. USED AS A SELF-PRIMING MATERIAL ON SMOOTH, LOW POROSITY CONCRETE, MASONRY AND WOOD SURFACES. MECHANICAL ROOMS INTERIOR WALLS, DOORS, FLOORS, & CEILINGS: PRIME COAT: EPOXY, GLOSS, MPI #77. INTERMEDIATE COAT: EPOXY, GLOSS, MPI #77. TOPCOAT: EPOXY, GLOSS, MPI #77. COLOR: WHITEWHITE
AutoCAD SHX Text
INTERIOR HIGH-PERFORMANCE COATINGS
AutoCAD SHX Text
UNIVERSITY OF CONNECTICUT
AutoCAD SHX Text
http://www.fo.uconn.edu
AutoCAD SHX Text
STORRS, CONNECTICUT
AutoCAD SHX Text
FACILITIES OPERATIONS
AutoCAD SHX Text
O
AutoCAD SHX Text
V
AutoCAD SHX Text
I
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
Y
AutoCAD SHX Text
T
AutoCAD SHX Text
T
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
8
AutoCAD SHX Text
C
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
C
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
T
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
E
AutoCAD SHX Text
R E V I S I O N S
AutoCAD SHX Text
Date
AutoCAD SHX Text
Mark
AutoCAD SHX Text
Description
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
MICHAEL J ROCCHETTI PE
AutoCAD SHX Text
MECHANICAL ENGINEER
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
Drawing Title
AutoCAD SHX Text
CAD File No.
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Drawn by
AutoCAD SHX Text
Approved by
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
Date
AutoCAD SHX Text
Scale
AutoCAD SHX Text
KEY PLAN (NTS)
AutoCAD SHX Text
WORK
AutoCAD SHX Text
AREA
AutoCAD SHX Text
SCALE 1/2" = 1 FT
AutoCAD SHX Text
0225 UConn Shakespeare/Troy - WC-3
Page 24: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

WC

-4 R

EF

UR

BIS

HM

EN

T P

LA

N

ME

CH

AN

IC

AL R

OO

M R

EP

AIR

S

AS

S

HO

WN

M-05

DE

C 2019

WE

ST

C

AM

PU

S D

OR

MS

FO

500078

AutoCAD SHX Text
B006
AutoCAD SHX Text
B008
AutoCAD SHX Text
A007
AutoCAD SHX Text
A006
AutoCAD SHX Text
MECH
AutoCAD SHX Text
ELEC
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
WATER HEATER
AutoCAD SHX Text
AIR
AutoCAD SHX Text
COMP
AutoCAD SHX Text
WELLXTROL
AutoCAD SHX Text
TANK
AutoCAD SHX Text
BOOSTER
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
F.D.
AutoCAD SHX Text
%%C4"
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
QUINCY QT-54, 5 HP WITH
AutoCAD SHX Text
60 GALLON VERTICAL RECEIVER
AutoCAD SHX Text
15.4 CFM AT 90 PSI
AutoCAD SHX Text
14.6 CFM AT 40 PSI
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
BOOSTER PUMP
AutoCAD SHX Text
DISCONNECT
AutoCAD SHX Text
FAN
AutoCAD SHX Text
SCREEN
AutoCAD SHX Text
2
AutoCAD SHX Text
2
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
3
AutoCAD SHX Text
4
AutoCAD SHX Text
4
AutoCAD SHX Text
FLR-TO-CLG HEIGHT
AutoCAD SHX Text
APPROX 7'-8"
AutoCAD SHX Text
5
AutoCAD SHX Text
5
AutoCAD SHX Text
5
AutoCAD SHX Text
$
AutoCAD SHX Text
0
AutoCAD SHX Text
2'
AutoCAD SHX Text
4'
AutoCAD SHX Text
6'
AutoCAD SHX Text
8'
AutoCAD SHX Text
10'
AutoCAD SHX Text
N
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
W
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
SWITCH
AutoCAD SHX Text
M
AutoCAD SHX Text
M
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
TO
AutoCAD SHX Text
6
AutoCAD SHX Text
7
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
TO
AutoCAD SHX Text
8
AutoCAD SHX Text
2
AutoCAD SHX Text
4
AutoCAD SHX Text
PAINT ALL WALLS AND CEILING IN THE MECH ROOM
AutoCAD SHX Text
CLEAN OUT THE WINDOW WELL.
AutoCAD SHX Text
REMOVE CONCRETE PEDESTALS AND PATCH FLOOR
AutoCAD SHX Text
1
AutoCAD SHX Text
REMOVE OLD FLOOR DRAIN, INSTALL NEW FLOOR DRAIN
AutoCAD SHX Text
3
AutoCAD SHX Text
UNDERNEATH.
AutoCAD SHX Text
JOSAM 32100 OR EQUAL.
AutoCAD SHX Text
5
AutoCAD SHX Text
REMOVE EXISTING LIGHTING FIXTURES AND INSTALL 4 NEW
AutoCAD SHX Text
FIXTURES - LITHONIA CNY-LED-P1-40K-MVOLT-WH
AutoCAD SHX Text
6
AutoCAD SHX Text
PROVIDE WIRING, CONDUITS, AND DISCONNECTS FOR NEW
AutoCAD SHX Text
CONDENSATE PUMPS, 2 HP, 208/3/60
AutoCAD SHX Text
7
AutoCAD SHX Text
PROVIDE WIRING, CONDUITS, AND SWITCH FOR NEW MIXING
AutoCAD SHX Text
VALVE CONTROLLER. 110/1%%C/60HZ
AutoCAD SHX Text
8
AutoCAD SHX Text
PROVIDE POWER CONNECTION (WIRING, & CONDUITS) FOR
AutoCAD SHX Text
NEW WATER HEATER. 110/1%%C/60HZ
AutoCAD SHX Text
A SOLVENT BASED, GLOSS, TWO COMPONENT, EPOXY COATING SPECIFIED FOR WALL AND FLOOR SURFACES IN MODERATE TO HEAVY TRAFFIC COMMERCIAL AND MODERATE INDUSTRIAL ENVIRONMENTS. MUST BE RESISTANT TO INCIDENTAL SPLASH AND SPILLAGE OF DILUTE (5%) SULFURIC ACID, (15%) HYDROCHLORIC ACID, (20%) SODIUM HYDROXIDE, GASOLINE AND HEAVY DUTY CLEANERS AND DETERGENTS. USED AS A SELF-PRIMING MATERIAL ON SMOOTH, LOW POROSITY CONCRETE, MASONRY AND WOOD SURFACES. MECHANICAL ROOMS INTERIOR WALLS, DOORS, FLOORS, & CEILINGS: PRIME COAT: EPOXY, GLOSS, MPI #77. INTERMEDIATE COAT: EPOXY, GLOSS, MPI #77. TOPCOAT: EPOXY, GLOSS, MPI #77. COLOR: WHITEWHITE
AutoCAD SHX Text
INTERIOR HIGH-PERFORMANCE COATINGS
AutoCAD SHX Text
UNIVERSITY OF CONNECTICUT
AutoCAD SHX Text
http://www.fo.uconn.edu
AutoCAD SHX Text
STORRS, CONNECTICUT
AutoCAD SHX Text
FACILITIES OPERATIONS
AutoCAD SHX Text
O
AutoCAD SHX Text
V
AutoCAD SHX Text
I
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
Y
AutoCAD SHX Text
T
AutoCAD SHX Text
T
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
8
AutoCAD SHX Text
C
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
C
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
T
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
E
AutoCAD SHX Text
R E V I S I O N S
AutoCAD SHX Text
Date
AutoCAD SHX Text
Mark
AutoCAD SHX Text
Description
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
MICHAEL J ROCCHETTI PE
AutoCAD SHX Text
MECHANICAL ENGINEER
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
Drawing Title
AutoCAD SHX Text
CAD File No.
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Drawn by
AutoCAD SHX Text
Approved by
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
Date
AutoCAD SHX Text
Scale
AutoCAD SHX Text
KEY PLAN (NTS)
AutoCAD SHX Text
WORK
AutoCAD SHX Text
AREA
AutoCAD SHX Text
0226 UConn Chandler/Lancaster Hall - WC-4
AutoCAD SHX Text
SCALE 1/2" = 1 FT
Page 25: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

WC

-1 P

LU

MB

IN

G P

IP

IN

G P

LA

N

ME

CH

AN

IC

AL R

OO

M R

EP

AIR

S

AS

S

HO

WN

M-06

DE

C 2019

WE

ST

C

AM

PU

S D

OR

MS

FO

500078

AutoCAD SHX Text
B006
AutoCAD SHX Text
B005
AutoCAD SHX Text
A007
AutoCAD SHX Text
ELEC
AutoCAD SHX Text
A005
AutoCAD SHX Text
B007
AutoCAD SHX Text
A006
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
SWITCH
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
BOOSTER PUMP
AutoCAD SHX Text
DISCONNECT
AutoCAD SHX Text
B008
AutoCAD SHX Text
MECH
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
BOOSTER
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
M
AutoCAD SHX Text
RECIRC
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
F.D.
AutoCAD SHX Text
%%C5"
AutoCAD SHX Text
%%C5"
AutoCAD SHX Text
%%C5" SANITARY
AutoCAD SHX Text
%%C4" SANITARY
AutoCAD SHX Text
%%C4" SANITARY
AutoCAD SHX Text
%%C3"
AutoCAD SHX Text
%%C3"
AutoCAD SHX Text
%%C4"
AutoCAD SHX Text
%%C3"
AutoCAD SHX Text
SPRINKLER
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
CONTROLS
AutoCAD SHX Text
BOOSTER
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
15SV3FHNF20
AutoCAD SHX Text
GOULDS e-SV
AutoCAD SHX Text
CW %%C2-1/2"
AutoCAD SHX Text
HW %%C1-1/2"
AutoCAD SHX Text
HWR %%C1"
AutoCAD SHX Text
CW %%C2-1/2"
AutoCAD SHX Text
HW %%C1-1/2"
AutoCAD SHX Text
HWR %%C1"
AutoCAD SHX Text
CW %%C2"
AutoCAD SHX Text
HW %%C1"
AutoCAD SHX Text
HWR %%C3/4"
AutoCAD SHX Text
%%C2-1/2" CW IN
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
WATER HEATER
AutoCAD SHX Text
WELLXTROL
AutoCAD SHX Text
TANK
AutoCAD SHX Text
FAN
AutoCAD SHX Text
SCREEN
AutoCAD SHX Text
0
AutoCAD SHX Text
2'
AutoCAD SHX Text
4'
AutoCAD SHX Text
6'
AutoCAD SHX Text
8'
AutoCAD SHX Text
10'
AutoCAD SHX Text
N
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
W
AutoCAD SHX Text
6
AutoCAD SHX Text
ACE MINI-PACK
AutoCAD SHX Text
MODEL: SI-H-6-SW
AutoCAD SHX Text
WATER: 60 GPM @ 100%%DF RISE
AutoCAD SHX Text
STEAM: 2,875 PPH @ 60 PSIG
AutoCAD SHX Text
EXISTING:
AutoCAD SHX Text
7
AutoCAD SHX Text
SCOPE OF WORK
AutoCAD SHX Text
1
AutoCAD SHX Text
REPLACE ALL SANITARY DRAIN WASTE & VENT PIPING WITH
AutoCAD SHX Text
NEW CAST IRON HUB & SPIGOT PIPING, OR GALVANIZED STEEL.
AutoCAD SHX Text
2
AutoCAD SHX Text
REPLACE ALL WATER LINES WITH NEW TYPE L COPPER PIPING.
AutoCAD SHX Text
REPLACE ALL WATER VALVES. INSULATE HW AND HWR LINES.
AutoCAD SHX Text
3
AutoCAD SHX Text
APPLY PVC JACKETING FOR ALL INSULATED HOT WATER AND
AutoCAD SHX Text
4
AutoCAD SHX Text
REMOVE ABANDONED EQUIPMENT, PIPING, VALVES & FITTINGS.
AutoCAD SHX Text
5
AutoCAD SHX Text
INSTALL NEW PIPE HANGERS AND SUPPORTS.
AutoCAD SHX Text
HW RECIRCULATING PIPE AND FITTINGS.
AutoCAD SHX Text
6
AutoCAD SHX Text
INSTALL NEW HW MIXING VALVE.
AutoCAD SHX Text
7
AutoCAD SHX Text
INSTALL NEW HOT WATER HEATER.
AutoCAD SHX Text
UNIVERSITY OF CONNECTICUT
AutoCAD SHX Text
http://www.fo.uconn.edu
AutoCAD SHX Text
STORRS, CONNECTICUT
AutoCAD SHX Text
FACILITIES OPERATIONS
AutoCAD SHX Text
O
AutoCAD SHX Text
V
AutoCAD SHX Text
I
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
Y
AutoCAD SHX Text
T
AutoCAD SHX Text
T
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
8
AutoCAD SHX Text
C
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
C
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
T
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
E
AutoCAD SHX Text
R E V I S I O N S
AutoCAD SHX Text
Date
AutoCAD SHX Text
Mark
AutoCAD SHX Text
Description
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
MICHAEL J ROCCHETTI PE
AutoCAD SHX Text
MECHANICAL ENGINEER
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
Drawing Title
AutoCAD SHX Text
CAD File No.
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Drawn by
AutoCAD SHX Text
Approved by
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
Date
AutoCAD SHX Text
Scale
AutoCAD SHX Text
KEY PLAN (NTS)
AutoCAD SHX Text
WORK
AutoCAD SHX Text
AREA
AutoCAD SHX Text
SCALE 1/2" = 1 FT
AutoCAD SHX Text
0223 UConn WC Alsop Hall - WC-1
Page 26: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

WC

-1 S

TE

AM

&

C

ON

DE

NS

AT

E P

IP

IN

G P

LA

N

ME

CH

AN

IC

AL R

OO

M R

EP

AIR

S

AS

S

HO

WN

M-07

DE

C 2019

WE

ST

C

AM

PU

S D

OR

MS

FO

500078

AutoCAD SHX Text
B006
AutoCAD SHX Text
B005
AutoCAD SHX Text
A007
AutoCAD SHX Text
ELEC
AutoCAD SHX Text
A005
AutoCAD SHX Text
B007
AutoCAD SHX Text
A006
AutoCAD SHX Text
B008
AutoCAD SHX Text
MECH
AutoCAD SHX Text
%%C4"
AutoCAD SHX Text
%%C4"
AutoCAD SHX Text
%%C5"
AutoCAD SHX Text
%%C3"
AutoCAD SHX Text
%%C1-1/2"
AutoCAD SHX Text
%%C2"
AutoCAD SHX Text
%%C1"
AutoCAD SHX Text
%%C4" HPS & %%C2" PUMPED CONDENSATE
AutoCAD SHX Text
IN UNDERGROUND PIPE CONDUIT
AutoCAD SHX Text
%%C2"
AutoCAD SHX Text
%%C1"
AutoCAD SHX Text
%%C2"
AutoCAD SHX Text
%%C1"
AutoCAD SHX Text
PRV
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
WATER HEATER
AutoCAD SHX Text
WELLXTROL
AutoCAD SHX Text
TANK
AutoCAD SHX Text
BOOSTER
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
M
AutoCAD SHX Text
F.D.
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
SWITCH
AutoCAD SHX Text
ACE MINI-PACK
AutoCAD SHX Text
MODEL: SI-H-6-SW
AutoCAD SHX Text
WATER: 60 GPM @ 100%%DF RISE
AutoCAD SHX Text
STEAM: 2,875 PPH @ 60 PSIG
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
BOOSTER PUMP
AutoCAD SHX Text
DISCONNECT
AutoCAD SHX Text
STERLING
AutoCAD SHX Text
42515 2HP
AutoCAD SHX Text
208/60/3
AutoCAD SHX Text
PRV
AutoCAD SHX Text
ZONE VALVE
AutoCAD SHX Text
CONTROLS
AutoCAD SHX Text
Z0NE VALVES
AutoCAD SHX Text
(INOP)
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
1
AutoCAD SHX Text
4
AutoCAD SHX Text
2
AutoCAD SHX Text
FAN
AutoCAD SHX Text
SCREEN
AutoCAD SHX Text
3
AutoCAD SHX Text
5
AutoCAD SHX Text
5
AutoCAD SHX Text
0
AutoCAD SHX Text
2'
AutoCAD SHX Text
4'
AutoCAD SHX Text
6'
AutoCAD SHX Text
8'
AutoCAD SHX Text
10'
AutoCAD SHX Text
N
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
W
AutoCAD SHX Text
EXISTING:
AutoCAD SHX Text
7
AutoCAD SHX Text
6
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
REMOVE ZONE VALVE AND REPLACE WITH A SECTION OF
AutoCAD SHX Text
STRAIGHT PIPE.
AutoCAD SHX Text
2
AutoCAD SHX Text
REMOVE ZONE VALVE CONTROL ENCLOSURES AND ALL
AutoCAD SHX Text
ASSOCIATED WIRING AND CONDUITS.
AutoCAD SHX Text
3
AutoCAD SHX Text
INSTALL NEW FLASH TANK FOR HP STEAM DRIP LEG. VENT
AutoCAD SHX Text
4
AutoCAD SHX Text
REMOVE ABANDONED EQUIPMENT, PIPING, VALVES & FITTINGS.
AutoCAD SHX Text
5
AutoCAD SHX Text
CLEAN OUT WINDOW WELL.
AutoCAD SHX Text
THROUGH THE WINDOW WELL.
AutoCAD SHX Text
SCOPE OF WORK
AutoCAD SHX Text
6
AutoCAD SHX Text
7
AutoCAD SHX Text
REPLACE CONDENSATE RECEIVER & PUMP.
AutoCAD SHX Text
8
AutoCAD SHX Text
REPLACE HOT WATER HEATER.
AutoCAD SHX Text
REPLACE ALL STEAM AND CONDENSATE PIPING INCLUDING ALL
AutoCAD SHX Text
VALVES, FITTINGS, TRAPS, & CONTROLS. INSULATE ALL.
AutoCAD SHX Text
UNIVERSITY OF CONNECTICUT
AutoCAD SHX Text
http://www.fo.uconn.edu
AutoCAD SHX Text
STORRS, CONNECTICUT
AutoCAD SHX Text
FACILITIES OPERATIONS
AutoCAD SHX Text
O
AutoCAD SHX Text
V
AutoCAD SHX Text
I
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
Y
AutoCAD SHX Text
T
AutoCAD SHX Text
T
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
8
AutoCAD SHX Text
C
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
C
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
T
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
E
AutoCAD SHX Text
R E V I S I O N S
AutoCAD SHX Text
Date
AutoCAD SHX Text
Mark
AutoCAD SHX Text
Description
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
MICHAEL J ROCCHETTI PE
AutoCAD SHX Text
MECHANICAL ENGINEER
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
Drawing Title
AutoCAD SHX Text
CAD File No.
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Drawn by
AutoCAD SHX Text
Approved by
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
Date
AutoCAD SHX Text
Scale
AutoCAD SHX Text
KEY PLAN (NTS)
AutoCAD SHX Text
WORK
AutoCAD SHX Text
AREA
AutoCAD SHX Text
SCALE 1/2" = 1 FT
AutoCAD SHX Text
0223 UConn WC Alsop Hall - WC-1
Page 27: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

WC

-2 P

LU

MB

IN

G P

IP

IN

G P

LA

N

ME

CH

AN

IC

AL R

OO

M R

EP

AIR

S

AS

S

HO

WN

M-08

DE

C 2019

WE

ST

C

AM

PU

S D

OR

MS

FO

500078

AutoCAD SHX Text
B006
AutoCAD SHX Text
B004
AutoCAD SHX Text
B005
AutoCAD SHX Text
B007
AutoCAD SHX Text
A007
AutoCAD SHX Text
A006
AutoCAD SHX Text
A005
AutoCAD SHX Text
ELEC
AutoCAD SHX Text
B008
AutoCAD SHX Text
MECH
AutoCAD SHX Text
WATER HEATER
AutoCAD SHX Text
F.D.
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
BOOSTER PUMP
AutoCAD SHX Text
DISCONNECT
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
CW %%C2-1/2"
AutoCAD SHX Text
HW %%C1-1/2"
AutoCAD SHX Text
HWR %%C1"
AutoCAD SHX Text
CW %%C2-1/2"
AutoCAD SHX Text
HW %%C1-1/2"
AutoCAD SHX Text
HWR %%C1"
AutoCAD SHX Text
%%C3"
AutoCAD SHX Text
%%C5"
AutoCAD SHX Text
%%C5" SANITARY
AutoCAD SHX Text
%%C2" VENT
AutoCAD SHX Text
BOOSTER
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
M
AutoCAD SHX Text
%%C4" SANITARY
AutoCAD SHX Text
%%C2-1/2" CW IN
AutoCAD SHX Text
BUFFER
AutoCAD SHX Text
TANK
AutoCAD SHX Text
RECIRC
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
SPRINKLER
AutoCAD SHX Text
SPRINKLER
AutoCAD SHX Text
SPRINKLER
AutoCAD SHX Text
SPRINKLER
AutoCAD SHX Text
CW %%C2"
AutoCAD SHX Text
HW %%C1"
AutoCAD SHX Text
HWR %%C3/4"
AutoCAD SHX Text
%%C4" SANITARY
AutoCAD SHX Text
ACE MINI-PACK
AutoCAD SHX Text
MODEL: SI-H-6-SW
AutoCAD SHX Text
WATER: 60 GPM @ 100%%DF RISE
AutoCAD SHX Text
STEAM: 2,875 PPH @ 65 PSIG
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
CONTROLS
AutoCAD SHX Text
BOOSTER
AutoCAD SHX Text
15SV3FHNF20
AutoCAD SHX Text
GOULDS e-SV
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
SWITCH
AutoCAD SHX Text
FAN
AutoCAD SHX Text
SCREEN
AutoCAD SHX Text
0
AutoCAD SHX Text
2'
AutoCAD SHX Text
4'
AutoCAD SHX Text
6'
AutoCAD SHX Text
8'
AutoCAD SHX Text
10'
AutoCAD SHX Text
N
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
W
AutoCAD SHX Text
6
AutoCAD SHX Text
INSTALLED 2017
AutoCAD SHX Text
1
AutoCAD SHX Text
REPLACE ALL SANITARY DRAIN WASTE & VENT PIPING WITH
AutoCAD SHX Text
NEW CAST IRON HUB & SPIGOT PIPING, OR GALVANIZED STEEL.
AutoCAD SHX Text
2
AutoCAD SHX Text
REPLACE ALL WATER LINES WITH NEW TYPE L COPPER PIPING.
AutoCAD SHX Text
REPLACE ALL WATER VALVES. INSULATE HW AND HWR LINES.
AutoCAD SHX Text
3
AutoCAD SHX Text
APPLY PVC JACKETING FOR ALL INSULATED HOT WATER AND
AutoCAD SHX Text
4
AutoCAD SHX Text
REMOVE ABANDONED EQUIPMENT, PIPING, VALVES & FITTINGS.
AutoCAD SHX Text
5
AutoCAD SHX Text
INSTALL NEW PIPE HANGERS AND SUPPORTS.
AutoCAD SHX Text
HW RECIRCULATING PIPE AND FITTINGS.
AutoCAD SHX Text
SCOPE OF WORK
AutoCAD SHX Text
6
AutoCAD SHX Text
INSTALL NEW HOT WATER MIXING VALVE.
AutoCAD SHX Text
UNIVERSITY OF CONNECTICUT
AutoCAD SHX Text
http://www.fo.uconn.edu
AutoCAD SHX Text
STORRS, CONNECTICUT
AutoCAD SHX Text
FACILITIES OPERATIONS
AutoCAD SHX Text
O
AutoCAD SHX Text
V
AutoCAD SHX Text
I
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
Y
AutoCAD SHX Text
T
AutoCAD SHX Text
T
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
8
AutoCAD SHX Text
C
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
C
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
T
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
E
AutoCAD SHX Text
R E V I S I O N S
AutoCAD SHX Text
Date
AutoCAD SHX Text
Mark
AutoCAD SHX Text
Description
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
MICHAEL J ROCCHETTI PE
AutoCAD SHX Text
MECHANICAL ENGINEER
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
Drawing Title
AutoCAD SHX Text
CAD File No.
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Drawn by
AutoCAD SHX Text
Approved by
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
Date
AutoCAD SHX Text
Scale
AutoCAD SHX Text
KEY PLAN (NTS)
AutoCAD SHX Text
WORK
AutoCAD SHX Text
AREA
AutoCAD SHX Text
SCALE 1/2" = 1 FT
AutoCAD SHX Text
0224 UConn WC Hollister Hall - WC-2
Page 28: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

WC

-2 S

TE

AM

&

C

ON

DE

NS

AT

E P

IP

IN

G P

LA

N

ME

CH

AN

IC

AL R

OO

M R

EP

AIR

S

AS

S

HO

WN

M-09

DE

C 2019

WE

ST

C

AM

PU

S D

OR

MS

FO

500078

AutoCAD SHX Text
B006
AutoCAD SHX Text
B004
AutoCAD SHX Text
A007
AutoCAD SHX Text
A006
AutoCAD SHX Text
A005
AutoCAD SHX Text
ELEC
AutoCAD SHX Text
B008
AutoCAD SHX Text
MECH
AutoCAD SHX Text
WATER HEATER
AutoCAD SHX Text
F.D.
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
BOOSTER PUMP
AutoCAD SHX Text
DISCONNECT
AutoCAD SHX Text
%%C4" HPS & %%C2" PUMPED CONDENSATE
AutoCAD SHX Text
IN UNDERGROUND PIPE CONDUIT
AutoCAD SHX Text
M
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
PRV
AutoCAD SHX Text
%%C2"
AutoCAD SHX Text
%%C1"
AutoCAD SHX Text
%%C2"
AutoCAD SHX Text
%%C1"
AutoCAD SHX Text
%%C2"
AutoCAD SHX Text
%%C1"
AutoCAD SHX Text
%%C3"
AutoCAD SHX Text
%%C1-1/2"
AutoCAD SHX Text
PRV
AutoCAD SHX Text
VENTED COND FLASH TANK
AutoCAD SHX Text
ACE MINI-PACK
AutoCAD SHX Text
MODEL: SI-H-6-SW
AutoCAD SHX Text
WATER: 60 GPM @ 100%%DF RISE
AutoCAD SHX Text
STEAM: 2,875 PPH @ 65 PSIG
AutoCAD SHX Text
STERLING
AutoCAD SHX Text
42515 2HP
AutoCAD SHX Text
208/60/3
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
SWITCH
AutoCAD SHX Text
ZONE VALVE
AutoCAD SHX Text
CONTROLS
AutoCAD SHX Text
BUFFER
AutoCAD SHX Text
TANK
AutoCAD SHX Text
Z0NE VALVES
AutoCAD SHX Text
(INOP)
AutoCAD SHX Text
5
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
4
AutoCAD SHX Text
FAN
AutoCAD SHX Text
SCREEN
AutoCAD SHX Text
FROM HP STEAM DRIP LEG
AutoCAD SHX Text
3
AutoCAD SHX Text
5
AutoCAD SHX Text
L
AutoCAD SHX Text
L
AutoCAD SHX Text
L
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
0
AutoCAD SHX Text
2'
AutoCAD SHX Text
4'
AutoCAD SHX Text
6'
AutoCAD SHX Text
8'
AutoCAD SHX Text
10'
AutoCAD SHX Text
N
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
W
AutoCAD SHX Text
INSTALLED 2017
AutoCAD SHX Text
14"X21"X20"H
AutoCAD SHX Text
7
AutoCAD SHX Text
6
AutoCAD SHX Text
1
AutoCAD SHX Text
REMOVE ZONE VALVE AND REPLACE WITH A SECTION OF
AutoCAD SHX Text
STRAIGHT PIPE.
AutoCAD SHX Text
2
AutoCAD SHX Text
REMOVE ZONE VALVE CONTROL ENCLOSURES AND ALL
AutoCAD SHX Text
ASSOCIATED WIRING AND CONDUITS.
AutoCAD SHX Text
3
AutoCAD SHX Text
INSTALL NEW FLASH TANK FOR HP STEAM DRIP LEG. VENT
AutoCAD SHX Text
4
AutoCAD SHX Text
REMOVE ABANDONED EQUIPMENT, PIPING, VALVES & FITTINGS.
AutoCAD SHX Text
5
AutoCAD SHX Text
CLEAN OUT WINDOW WELL.
AutoCAD SHX Text
THROUGH THE WINDOW WELL.
AutoCAD SHX Text
SCOPE OF WORK
AutoCAD SHX Text
6
AutoCAD SHX Text
REPLACE ALL STEAM AND CONDENSATE PIPING INCLUDING ALL
AutoCAD SHX Text
VALVES, FITTINGS, TRAPS, & CONTROLS. INSULATE ALL.
AutoCAD SHX Text
7
AutoCAD SHX Text
REPLACE CONDENSATE RETURN PUMP.
AutoCAD SHX Text
UNIVERSITY OF CONNECTICUT
AutoCAD SHX Text
http://www.fo.uconn.edu
AutoCAD SHX Text
STORRS, CONNECTICUT
AutoCAD SHX Text
FACILITIES OPERATIONS
AutoCAD SHX Text
O
AutoCAD SHX Text
V
AutoCAD SHX Text
I
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
Y
AutoCAD SHX Text
T
AutoCAD SHX Text
T
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
8
AutoCAD SHX Text
C
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
C
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
T
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
E
AutoCAD SHX Text
R E V I S I O N S
AutoCAD SHX Text
Date
AutoCAD SHX Text
Mark
AutoCAD SHX Text
Description
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
MICHAEL J ROCCHETTI PE
AutoCAD SHX Text
MECHANICAL ENGINEER
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
Drawing Title
AutoCAD SHX Text
CAD File No.
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Drawn by
AutoCAD SHX Text
Approved by
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
Date
AutoCAD SHX Text
Scale
AutoCAD SHX Text
KEY PLAN (NTS)
AutoCAD SHX Text
WORK
AutoCAD SHX Text
AREA
AutoCAD SHX Text
SCALE 1/2" = 1 FT
AutoCAD SHX Text
0224 UConn WC Hollister Hall - WC-2
Page 29: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

WC

-3 P

LU

MB

IN

G P

IP

IN

G P

LA

N

ME

CH

AN

IC

AL R

OO

M R

EP

AIR

S

AS

S

HO

WN

M-10

DE

C 2019

WE

ST

C

AM

PU

S D

OR

MS

FO

500078

AutoCAD SHX Text
UP
AutoCAD SHX Text
A006
AutoCAD SHX Text
A007
AutoCAD SHX Text
B006
AutoCAD SHX Text
ELEC
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
WELLXTROL
AutoCAD SHX Text
TANK
AutoCAD SHX Text
BOOSTER
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
CW %%C2-1/2"
AutoCAD SHX Text
HW %%C1-1/2"
AutoCAD SHX Text
HWR %%C1"
AutoCAD SHX Text
METER
AutoCAD SHX Text
%%C2-1/2" CW IN
AutoCAD SHX Text
RECIRC
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
WATER HEATER
AutoCAD SHX Text
%%C5"
AutoCAD SHX Text
%%C5" SANITARY
AutoCAD SHX Text
SAN %%C3"
AutoCAD SHX Text
SAN %%C4"
AutoCAD SHX Text
F.D.
AutoCAD SHX Text
%%C4" SANITARY
AutoCAD SHX Text
SPRINKLER
AutoCAD SHX Text
B008
AutoCAD SHX Text
MECH
AutoCAD SHX Text
CW %%C2"
AutoCAD SHX Text
HW %%C1"
AutoCAD SHX Text
HWR %%C3/4"
AutoCAD SHX Text
CW %%C2-1/2"
AutoCAD SHX Text
HW %%C1-1/2"
AutoCAD SHX Text
HWR %%C1"
AutoCAD SHX Text
%%C4" SANITARY
AutoCAD SHX Text
SPRINKLER
AutoCAD SHX Text
ACE MINI-PACK
AutoCAD SHX Text
MODEL: SI-H-5-SW
AutoCAD SHX Text
WATER: 30 GPM @ 100%%DF RISE
AutoCAD SHX Text
STEAM: 1,445 PPH @ 65 PSIG
AutoCAD SHX Text
15SV3FHNF20
AutoCAD SHX Text
7.5 HP
AutoCAD SHX Text
GOULDS e-SV
AutoCAD SHX Text
SPRINKLER
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
CONTROLS
AutoCAD SHX Text
BOOSTER
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
BOOSTER PUMP
AutoCAD SHX Text
DISCONNECT
AutoCAD SHX Text
ABANDONED
AutoCAD SHX Text
HEATER
AutoCAD SHX Text
FAN
AutoCAD SHX Text
SCREEN
AutoCAD SHX Text
4
AutoCAD SHX Text
0
AutoCAD SHX Text
2'
AutoCAD SHX Text
4'
AutoCAD SHX Text
6'
AutoCAD SHX Text
8'
AutoCAD SHX Text
10'
AutoCAD SHX Text
N
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
W
AutoCAD SHX Text
EXISTING
AutoCAD SHX Text
6
AutoCAD SHX Text
7
AutoCAD SHX Text
SCOPE OF WORK
AutoCAD SHX Text
1
AutoCAD SHX Text
REPLACE ALL SANITARY DRAIN WASTE & VENT PIPING WITH
AutoCAD SHX Text
NEW CAST IRON HUB & SPIGOT PIPING, OR GALVANIZED STEEL.
AutoCAD SHX Text
2
AutoCAD SHX Text
REPLACE ALL WATER LINES WITH NEW TYPE L COPPER PIPING.
AutoCAD SHX Text
REPLACE ALL WATER VALVES. INSULATE HW AND HWR LINES.
AutoCAD SHX Text
3
AutoCAD SHX Text
APPLY PVC JACKETING FOR ALL INSULATED HOT WATER AND
AutoCAD SHX Text
4
AutoCAD SHX Text
REMOVE ABANDONED EQUIPMENT, PIPING, VALVES & FITTINGS.
AutoCAD SHX Text
5
AutoCAD SHX Text
INSTALL NEW PIPE HANGERS AND SUPPORTS.
AutoCAD SHX Text
HW RECIRCULATING PIPE AND FITTINGS.
AutoCAD SHX Text
6
AutoCAD SHX Text
INSTALL NEW HW MIXING VALVE.
AutoCAD SHX Text
7
AutoCAD SHX Text
INSTALL NEW HOT WATER HEATER.
AutoCAD SHX Text
UNIVERSITY OF CONNECTICUT
AutoCAD SHX Text
http://www.fo.uconn.edu
AutoCAD SHX Text
STORRS, CONNECTICUT
AutoCAD SHX Text
FACILITIES OPERATIONS
AutoCAD SHX Text
O
AutoCAD SHX Text
V
AutoCAD SHX Text
I
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
Y
AutoCAD SHX Text
T
AutoCAD SHX Text
T
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
8
AutoCAD SHX Text
C
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
C
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
T
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
E
AutoCAD SHX Text
R E V I S I O N S
AutoCAD SHX Text
Date
AutoCAD SHX Text
Mark
AutoCAD SHX Text
Description
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
MICHAEL J ROCCHETTI PE
AutoCAD SHX Text
MECHANICAL ENGINEER
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
Drawing Title
AutoCAD SHX Text
CAD File No.
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Drawn by
AutoCAD SHX Text
Approved by
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
Date
AutoCAD SHX Text
Scale
AutoCAD SHX Text
KEY PLAN (NTS)
AutoCAD SHX Text
WORK
AutoCAD SHX Text
AREA
AutoCAD SHX Text
SCALE 1/2" = 1 FT
AutoCAD SHX Text
0225 UConn Shakespeare/Troy - WC-3
Page 30: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

WC

-3 S

TE

AM

&

C

ON

DE

NS

AT

E P

IP

IN

G P

LA

N

ME

CH

AN

IC

AL R

OO

M R

EP

AIR

S

AS

S

HO

WN

M-11

DE

C 2019

WE

ST

C

AM

PU

S D

OR

MS

FO

500078

AutoCAD SHX Text
UP
AutoCAD SHX Text
A006
AutoCAD SHX Text
A007
AutoCAD SHX Text
B006
AutoCAD SHX Text
ELEC
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
WELLXTROL
AutoCAD SHX Text
TANK
AutoCAD SHX Text
BOOSTER
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
WATER HEATER
AutoCAD SHX Text
F.D.
AutoCAD SHX Text
%%C4" HPS & %%C2" PUMPED CONDENSATE
AutoCAD SHX Text
IN UNDERGROUND PIPE CONDUIT
AutoCAD SHX Text
%%C2"
AutoCAD SHX Text
%%C1-1/2"
AutoCAD SHX Text
%%C3"
AutoCAD SHX Text
%%C1-1/2"
AutoCAD SHX Text
PRV
AutoCAD SHX Text
PRV
AutoCAD SHX Text
B008
AutoCAD SHX Text
MECH
AutoCAD SHX Text
%%C1"
AutoCAD SHX Text
%%C1-1/4"
AutoCAD SHX Text
%%C2"
AutoCAD SHX Text
%%C1-1/2"
AutoCAD SHX Text
%%C1-1/2"
AutoCAD SHX Text
%%C5"
AutoCAD SHX Text
%%C1"
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
SWITCH
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
BOOSTER PUMP
AutoCAD SHX Text
DISCONNECT
AutoCAD SHX Text
METER
AutoCAD SHX Text
STERLING
AutoCAD SHX Text
42515 2HP
AutoCAD SHX Text
208/60/3
AutoCAD SHX Text
ZONE VALVE
AutoCAD SHX Text
CONTROLS
AutoCAD SHX Text
ZONE
AutoCAD SHX Text
ABANDONED
AutoCAD SHX Text
HEATER
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
VALVE
AutoCAD SHX Text
ZONE
AutoCAD SHX Text
VALVE
AutoCAD SHX Text
3
AutoCAD SHX Text
4
AutoCAD SHX Text
FAN
AutoCAD SHX Text
SCREEN
AutoCAD SHX Text
6
AutoCAD SHX Text
5
AutoCAD SHX Text
5
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
0
AutoCAD SHX Text
2'
AutoCAD SHX Text
4'
AutoCAD SHX Text
6'
AutoCAD SHX Text
8'
AutoCAD SHX Text
10'
AutoCAD SHX Text
N
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
W
AutoCAD SHX Text
ACE MINI-PACK
AutoCAD SHX Text
MODEL: SI-H-5-SW
AutoCAD SHX Text
WATER: 30 GPM @ 100%%DF RISE
AutoCAD SHX Text
STEAM: 1,445 PPH @ 65 PSIG
AutoCAD SHX Text
EXISTING
AutoCAD SHX Text
8
AutoCAD SHX Text
7
AutoCAD SHX Text
9
AutoCAD SHX Text
1
AutoCAD SHX Text
REMOVE ZONE VALVE AND REPLACE WITH A SECTION OF
AutoCAD SHX Text
STRAIGHT PIPE.
AutoCAD SHX Text
2
AutoCAD SHX Text
REMOVE ZONE VALVE CONTROL ENCLOSURES AND ALL
AutoCAD SHX Text
ASSOCIATED WIRING AND CONDUITS.
AutoCAD SHX Text
3
AutoCAD SHX Text
INSTALL NEW FLASH TANK FOR HP STEAM DRIP LEG. VENT
AutoCAD SHX Text
4
AutoCAD SHX Text
REMOVE ABANDONED PIPING, VALVES & FITTINGS.
AutoCAD SHX Text
5
AutoCAD SHX Text
CLEAN OUT WINDOW WELL.
AutoCAD SHX Text
THROUGH THE WINDOW WELL.
AutoCAD SHX Text
6
AutoCAD SHX Text
REMOVE ABANDONED HEATER
AutoCAD SHX Text
SCOPE OF WORK
AutoCAD SHX Text
7
AutoCAD SHX Text
8
AutoCAD SHX Text
REPLACE CONDENSATE RECEIVER & PUMP.
AutoCAD SHX Text
9
AutoCAD SHX Text
REPLACE HOT WATER HEATER.
AutoCAD SHX Text
REPLACE ALL STEAM AND CONDENSATE PIPING INCLUDING ALL
AutoCAD SHX Text
VALVES, FITTINGS, TRAPS, & CONTROLS. INSULATE ALL.
AutoCAD SHX Text
UNIVERSITY OF CONNECTICUT
AutoCAD SHX Text
http://www.fo.uconn.edu
AutoCAD SHX Text
STORRS, CONNECTICUT
AutoCAD SHX Text
FACILITIES OPERATIONS
AutoCAD SHX Text
O
AutoCAD SHX Text
V
AutoCAD SHX Text
I
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
Y
AutoCAD SHX Text
T
AutoCAD SHX Text
T
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
8
AutoCAD SHX Text
C
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
C
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
T
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
E
AutoCAD SHX Text
R E V I S I O N S
AutoCAD SHX Text
Date
AutoCAD SHX Text
Mark
AutoCAD SHX Text
Description
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
MICHAEL J ROCCHETTI PE
AutoCAD SHX Text
MECHANICAL ENGINEER
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
Drawing Title
AutoCAD SHX Text
CAD File No.
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Drawn by
AutoCAD SHX Text
Approved by
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
Date
AutoCAD SHX Text
Scale
AutoCAD SHX Text
KEY PLAN (NTS)
AutoCAD SHX Text
WORK
AutoCAD SHX Text
AREA
AutoCAD SHX Text
SCALE 1/2" = 1 FT
AutoCAD SHX Text
0225 UConn Shakespeare/Troy - WC-3
Page 31: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

WC

-4 P

LU

MB

IN

G P

IP

IN

G P

LA

N

ME

CH

AN

IC

AL R

OO

M R

EP

AIR

S

AS

S

HO

WN

M-12

DE

C 2019

WE

ST

C

AM

PU

S D

OR

MS

FO

500078

AutoCAD SHX Text
UP
AutoCAD SHX Text
B006
AutoCAD SHX Text
B008
AutoCAD SHX Text
A007
AutoCAD SHX Text
A006
AutoCAD SHX Text
MECH
AutoCAD SHX Text
ELEC
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
WATER HEATER
AutoCAD SHX Text
AIR
AutoCAD SHX Text
COMP
AutoCAD SHX Text
WELLXTROL
AutoCAD SHX Text
TANK
AutoCAD SHX Text
BOOSTER
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
%%C2-1/2" CW IN
AutoCAD SHX Text
METER
AutoCAD SHX Text
RECIRC
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
F.D.
AutoCAD SHX Text
%%C4"
AutoCAD SHX Text
%%C5"
AutoCAD SHX Text
%%C5" SANITARY
AutoCAD SHX Text
%%C4" SANITARY
AutoCAD SHX Text
%%C4" SANITARY
AutoCAD SHX Text
%%C3"
AutoCAD SHX Text
%%C3"
AutoCAD SHX Text
%%C4"
AutoCAD SHX Text
%%C3"
AutoCAD SHX Text
SPRINKLER
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
CONTROLS
AutoCAD SHX Text
BOOSTER
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
ACE MINI-PACK
AutoCAD SHX Text
MODEL: SI-H-6-SW
AutoCAD SHX Text
WATER: 60 GPM @ 100%%DF RISE
AutoCAD SHX Text
STEAM: 2,875 PPH @ 65 PSIG
AutoCAD SHX Text
QUINCY QT-54, 5 HP WITH
AutoCAD SHX Text
60 GALLON VERTICAL RECEIVER
AutoCAD SHX Text
15.4 CFM AT 90 PSI
AutoCAD SHX Text
14.6 CFM AT 40 PSI
AutoCAD SHX Text
15SV3FHNF20
AutoCAD SHX Text
7.5 HP
AutoCAD SHX Text
GOULDS e-SV
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
BOOSTER PUMP
AutoCAD SHX Text
DISCONNECT
AutoCAD SHX Text
CW %%C2-1/2"
AutoCAD SHX Text
HW %%C1-1/2"
AutoCAD SHX Text
HWR %%C1"
AutoCAD SHX Text
CW %%C2-1/2"
AutoCAD SHX Text
HW %%C1-1/2"
AutoCAD SHX Text
HWR %%C1"
AutoCAD SHX Text
CW %%C2"
AutoCAD SHX Text
HW %%C1"
AutoCAD SHX Text
HWR %%C3/4"
AutoCAD SHX Text
FAN
AutoCAD SHX Text
SCREEN
AutoCAD SHX Text
0
AutoCAD SHX Text
2'
AutoCAD SHX Text
4'
AutoCAD SHX Text
6'
AutoCAD SHX Text
8'
AutoCAD SHX Text
10'
AutoCAD SHX Text
N
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
W
AutoCAD SHX Text
EXISTING
AutoCAD SHX Text
6
AutoCAD SHX Text
7
AutoCAD SHX Text
SCOPE OF WORK
AutoCAD SHX Text
1
AutoCAD SHX Text
REPLACE ALL SANITARY DRAIN WASTE & VENT PIPING WITH
AutoCAD SHX Text
NEW CAST IRON HUB & SPIGOT PIPING, OR GALVANIZED STEEL.
AutoCAD SHX Text
2
AutoCAD SHX Text
REPLACE ALL WATER LINES WITH NEW TYPE L COPPER PIPING.
AutoCAD SHX Text
REPLACE ALL WATER VALVES. INSULATE HW AND HWR LINES.
AutoCAD SHX Text
3
AutoCAD SHX Text
APPLY PVC JACKETING FOR ALL INSULATED HOT WATER AND
AutoCAD SHX Text
4
AutoCAD SHX Text
REMOVE ABANDONED EQUIPMENT, PIPING, VALVES & FITTINGS.
AutoCAD SHX Text
5
AutoCAD SHX Text
INSTALL NEW PIPE HANGERS AND SUPPORTS.
AutoCAD SHX Text
HW RECIRCULATING PIPE AND FITTINGS.
AutoCAD SHX Text
6
AutoCAD SHX Text
INSTALL NEW HW MIXING VALVE.
AutoCAD SHX Text
7
AutoCAD SHX Text
INSTALL NEW HOT WATER HEATER.
AutoCAD SHX Text
UNIVERSITY OF CONNECTICUT
AutoCAD SHX Text
http://www.fo.uconn.edu
AutoCAD SHX Text
STORRS, CONNECTICUT
AutoCAD SHX Text
FACILITIES OPERATIONS
AutoCAD SHX Text
O
AutoCAD SHX Text
V
AutoCAD SHX Text
I
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
Y
AutoCAD SHX Text
T
AutoCAD SHX Text
T
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
8
AutoCAD SHX Text
C
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
C
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
T
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
E
AutoCAD SHX Text
R E V I S I O N S
AutoCAD SHX Text
Date
AutoCAD SHX Text
Mark
AutoCAD SHX Text
Description
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
MICHAEL J ROCCHETTI PE
AutoCAD SHX Text
MECHANICAL ENGINEER
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
Drawing Title
AutoCAD SHX Text
CAD File No.
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Drawn by
AutoCAD SHX Text
Approved by
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
Date
AutoCAD SHX Text
Scale
AutoCAD SHX Text
KEY PLAN (NTS)
AutoCAD SHX Text
WORK
AutoCAD SHX Text
AREA
AutoCAD SHX Text
0226 UConn Chandler/Lancaster Hall - WC-4
AutoCAD SHX Text
SCALE 1/2" = 1 FT
Page 32: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

WC

-4 S

TE

AM

&

C

ON

DE

NS

AT

E P

IP

IN

G P

LA

N

ME

CH

AN

IC

AL R

OO

M R

EP

AIR

S

FO

500078

AS

S

HO

WN

M-13

DE

C 2019

WE

ST

C

AM

PU

S D

OR

MS

AutoCAD SHX Text
B006
AutoCAD SHX Text
A007
AutoCAD SHX Text
A006
AutoCAD SHX Text
ELEC
AutoCAD SHX Text
%%C4"
AutoCAD SHX Text
%%C4"
AutoCAD SHX Text
%%C5"
AutoCAD SHX Text
%%C3"
AutoCAD SHX Text
%%C1-1/2"
AutoCAD SHX Text
%%C2"
AutoCAD SHX Text
%%C1"
AutoCAD SHX Text
%%C4" HPS & %%C2" PUMPED CONDENSATE
AutoCAD SHX Text
IN UNDERGROUND PIPE CONDUIT
AutoCAD SHX Text
%%C2"
AutoCAD SHX Text
%%C1"
AutoCAD SHX Text
%%C2"
AutoCAD SHX Text
%%C1"
AutoCAD SHX Text
%%C2"
AutoCAD SHX Text
%%C1"
AutoCAD SHX Text
PRV
AutoCAD SHX Text
PRV
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
WATER HEATER
AutoCAD SHX Text
AIR
AutoCAD SHX Text
COMP
AutoCAD SHX Text
WELLXTROL
AutoCAD SHX Text
TANK
AutoCAD SHX Text
BOOSTER
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
METER
AutoCAD SHX Text
F.D.
AutoCAD SHX Text
COND
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
SWITCH
AutoCAD SHX Text
ACE MINI-PACK
AutoCAD SHX Text
MODEL: SI-H-6-SW
AutoCAD SHX Text
WATER: 60 GPM @ 100%%DF RISE
AutoCAD SHX Text
STEAM: 2,875 PPH @ 60 PSIG
AutoCAD SHX Text
BSMT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
BOOSTER PUMP
AutoCAD SHX Text
DISCONNECT
AutoCAD SHX Text
STERLING
AutoCAD SHX Text
42515 2HP
AutoCAD SHX Text
208/60/3
AutoCAD SHX Text
ZONE VALVE
AutoCAD SHX Text
CONTROLS
AutoCAD SHX Text
ZONE VALVE
AutoCAD SHX Text
ZONE VALVE
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
LIGHT
AutoCAD SHX Text
B008
AutoCAD SHX Text
MECH
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
3
AutoCAD SHX Text
4
AutoCAD SHX Text
FAN
AutoCAD SHX Text
SCREEN
AutoCAD SHX Text
5
AutoCAD SHX Text
5
AutoCAD SHX Text
0
AutoCAD SHX Text
2'
AutoCAD SHX Text
4'
AutoCAD SHX Text
6'
AutoCAD SHX Text
8'
AutoCAD SHX Text
10'
AutoCAD SHX Text
N
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
W
AutoCAD SHX Text
EXISTING
AutoCAD SHX Text
7
AutoCAD SHX Text
6
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
REMOVE ZONE VALVE AND REPLACE WITH A SECTION OF
AutoCAD SHX Text
STRAIGHT PIPE.
AutoCAD SHX Text
2
AutoCAD SHX Text
REMOVE ZONE VALVE CONTROL ENCLOSURES AND ALL
AutoCAD SHX Text
ASSOCIATED WIRING AND CONDUITS.
AutoCAD SHX Text
3
AutoCAD SHX Text
INSTALL NEW FLASH TANK FOR HP STEAM DRIP LEG. VENT
AutoCAD SHX Text
4
AutoCAD SHX Text
REMOVE ABANDONED EQUIPMENT, PIPING, VALVES & FITTINGS.
AutoCAD SHX Text
5
AutoCAD SHX Text
CLEAN OUT WINDOW WELL.
AutoCAD SHX Text
THROUGH THE WINDOW WELL.
AutoCAD SHX Text
SCOPE OF WORK
AutoCAD SHX Text
6
AutoCAD SHX Text
7
AutoCAD SHX Text
REPLACE CONDENSATE RECEIVER & PUMPS.
AutoCAD SHX Text
8
AutoCAD SHX Text
REPLACE HOT WATER HEATER.
AutoCAD SHX Text
REPLACE ALL STEAM AND CONDENSATE PIPING INCLUDING ALL
AutoCAD SHX Text
VALVES, FITTINGS, TRAPS, & CONTROLS. INSULATE ALL.
AutoCAD SHX Text
UNIVERSITY OF CONNECTICUT
AutoCAD SHX Text
http://www.fo.uconn.edu
AutoCAD SHX Text
STORRS, CONNECTICUT
AutoCAD SHX Text
FACILITIES OPERATIONS
AutoCAD SHX Text
O
AutoCAD SHX Text
V
AutoCAD SHX Text
I
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
Y
AutoCAD SHX Text
T
AutoCAD SHX Text
T
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
8
AutoCAD SHX Text
C
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
C
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
T
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
E
AutoCAD SHX Text
R E V I S I O N S
AutoCAD SHX Text
Date
AutoCAD SHX Text
Mark
AutoCAD SHX Text
Description
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
MICHAEL J ROCCHETTI PE
AutoCAD SHX Text
MECHANICAL ENGINEER
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
Drawing Title
AutoCAD SHX Text
CAD File No.
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Drawn by
AutoCAD SHX Text
Approved by
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
Date
AutoCAD SHX Text
Scale
AutoCAD SHX Text
KEY PLAN (NTS)
AutoCAD SHX Text
WORK
AutoCAD SHX Text
AREA
AutoCAD SHX Text
0226 UConn Chandler/Lancaster Hall - WC-4
AutoCAD SHX Text
SCALE 1/2" = 1 FT
Page 33: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

ME

CH

AN

IC

AL D

ET

AILS

ME

CH

AN

IC

AL R

OO

M R

EP

AIR

S

FO

500078

AS

S

HO

WN

M-14

DE

C 2019

WE

ST

C

AM

PU

S D

OR

MS

AutoCAD SHX Text
%%C2-1/2" VENT
AutoCAD SHX Text
%%C2" INLET
AutoCAD SHX Text
%%C1-1/2" OUT
AutoCAD SHX Text
VERTICAL FLASH TANK
AutoCAD SHX Text
ARMSTRONG AFT-6
AutoCAD SHX Text
CONDENSATE
AutoCAD SHX Text
RETURN
AutoCAD SHX Text
CONDENSATE
AutoCAD SHX Text
FROM HP
AutoCAD SHX Text
DRIP LEG
AutoCAD SHX Text
INVERTED
AutoCAD SHX Text
BUCKET
AutoCAD SHX Text
TRAP
AutoCAD SHX Text
4'-3.00"
AutoCAD SHX Text
-Z OUTLET SHOWN
AutoCAD SHX Text
FLOOR DRAIN DETAIL
AutoCAD SHX Text
JOSAM 32100 (OR EQUAL)
AutoCAD SHX Text
2"
AutoCAD SHX Text
5/8"
AutoCAD SHX Text
-Z = 5-3/4"
AutoCAD SHX Text
-Y = 5-7/8"
AutoCAD SHX Text
-X = 6-1/2"
AutoCAD SHX Text
-T = 4-3/4"
AutoCAD SHX Text
8 3/16"
AutoCAD SHX Text
AutoCAD SHX Text
PIPE
AutoCAD SHX Text
SIZE
AutoCAD SHX Text
9"
AutoCAD SHX Text
AutoCAD SHX Text
12 5/8"
AutoCAD SHX Text
AutoCAD SHX Text
W/STAINLESS STEEL
AutoCAD SHX Text
MESH LINER BUCKET
AutoCAD SHX Text
SUPPORT FROM ROOF
AutoCAD SHX Text
JOIST, SEE DETAIL
AutoCAD SHX Text
3/8"%%d THREADED
AutoCAD SHX Text
ROD
AutoCAD SHX Text
CLEVIS HANGER
AutoCAD SHX Text
(SIZE AS REQ'D)
AutoCAD SHX Text
INSULATION
AutoCAD SHX Text
SADDLE
AutoCAD SHX Text
SINGLE PIPE RUN
AutoCAD SHX Text
MULTIPLE PIPE RUNS
AutoCAD SHX Text
STEEL PIPE STRAP
AutoCAD SHX Text
BOLT & CLAMPING NUT (TYP)
AutoCAD SHX Text
1 5/8"x 1 5/8"x 12 GA.
AutoCAD SHX Text
STEEL CHANNEL
AutoCAD SHX Text
PIPE SUPPORT DETAILS
AutoCAD SHX Text
INSULATION
AutoCAD SHX Text
SADDLE
AutoCAD SHX Text
LENGTH AS REQ'D
AutoCAD SHX Text
N.T.S.
AutoCAD SHX Text
SUPPORT FROM ROOF JOISTS
AutoCAD SHX Text
A
AutoCAD SHX Text
A
AutoCAD SHX Text
PIPE PENETRATION THROUGH CONCRETE WALL
AutoCAD SHX Text
N.T.S.
AutoCAD SHX Text
FIBERGLASS
AutoCAD SHX Text
PACK WITH
AutoCAD SHX Text
FB-3000 WT
AutoCAD SHX Text
CAULKING 3M
AutoCAD SHX Text
EXTERIOR
AutoCAD SHX Text
INTERIOR
AutoCAD SHX Text
%%USECTION A-A
AutoCAD SHX Text
3. CR LINE TO ENTER AT TOP OF MAIN
AutoCAD SHX Text
2. PIPING SIZE SAME AS INLET
AutoCAD SHX Text
NOTES:
AutoCAD SHX Text
STEAM & CONDENSATE MAIN AS POSSIBLE
AutoCAD SHX Text
1. LOCATE SHUT-OFF VALVES AS TO
AutoCAD SHX Text
STEAM MAIN
AutoCAD SHX Text
BUCKET TRAP
AutoCAD SHX Text
CONDENSATE
AutoCAD SHX Text
RETURN MAIN
AutoCAD SHX Text
DRIP LEG TO BE STEAM
AutoCAD SHX Text
MAIN SIZE
AutoCAD SHX Text
STEAM TRAP INSTALLATION
AutoCAD SHX Text
N.T.S.
AutoCAD SHX Text
12" MIN
AutoCAD SHX Text
3" MIN
AutoCAD SHX Text
HANGER DETAILS - INSULATED PIPE
AutoCAD SHX Text
N.T.S.
AutoCAD SHX Text
(60 F & HIGHER)
AutoCAD SHX Text
*
AutoCAD SHX Text
*
AutoCAD SHX Text
COLD PIPE - ALL SIZES
AutoCAD SHX Text
HOT PIPE - UNDER 4" DIA.
AutoCAD SHX Text
HOT PIPE - 4" DIA. AND LARGER
AutoCAD SHX Text
TYPE 1 CLEVIS HANGER
AutoCAD SHX Text
HANGER ROD W/JAM NUT
AutoCAD SHX Text
PIPE INSULATION-UPPER
AutoCAD SHX Text
HALF OF PIPE
AutoCAD SHX Text
TYPE 40 PROTECTION
AutoCAD SHX Text
HIGH DENSITY INSULATION
AutoCAD SHX Text
INSERT-LOWER HALF OF
AutoCAD SHX Text
IN SADDLE CAVITY
AutoCAD SHX Text
INSULATION INSERTED
AutoCAD SHX Text
TYPE 39 SADDLE
AutoCAD SHX Text
PROTECTION SADDLE
AutoCAD SHX Text
FIT AROUND TYPE 39
AutoCAD SHX Text
PIPE INSULATION-CUT TO
AutoCAD SHX Text
HANGER ROD W/JAM NUT
AutoCAD SHX Text
TYPE 1 CLEVIS HANGER
AutoCAD SHX Text
PIPE
AutoCAD SHX Text
SHIELD
AutoCAD SHX Text
HW
AutoCAD SHX Text
HWR
AutoCAD SHX Text
CW
AutoCAD SHX Text
TYPICAL RISER DETAIL
AutoCAD SHX Text
CW, HW, AND HWR
AutoCAD SHX Text
FIRE CAULK
AutoCAD SHX Text
3M C-AJ-5001
AutoCAD SHX Text
N.T.S.
AutoCAD SHX Text
PUMP & RECEIVER DETAIL
AutoCAD SHX Text
DUPLEX CONDENSATE
AutoCAD SHX Text
RETURN LINE
AutoCAD SHX Text
CONDENSATE
AutoCAD SHX Text
TO FLOOR DRAIN
AutoCAD SHX Text
OVERFLOW LINE
AutoCAD SHX Text
SCREEN
AutoCAD SHX Text
ON PUMP DISCHARGE
AutoCAD SHX Text
PROVIDE BALANCING VALVE
AutoCAD SHX Text
6" CONCRETE PAD
AutoCAD SHX Text
RETURN HEADER FOR
AutoCAD SHX Text
MULTIPLE RETURNS
AutoCAD SHX Text
CONDENSATE
AutoCAD SHX Text
STRAINER W/REMOVABLE
AutoCAD SHX Text
GAUGE GLASS
AutoCAD SHX Text
WATER LEVEL
AutoCAD SHX Text
RECEIVER W/INLET
AutoCAD SHX Text
CAST-IRON OR STEEL
AutoCAD SHX Text
CONTROL CABINET
AutoCAD SHX Text
LINE TO FLOOR DRAIN
AutoCAD SHX Text
X/X" OVERFLOW
AutoCAD SHX Text
FLOAT
AutoCAD SHX Text
INTEGRAL
AutoCAD SHX Text
CONDENSATE PUMP
AutoCAD SHX Text
FLANGE (3" & OVER)
AutoCAD SHX Text
UNION (UP TO 2-1/2")
AutoCAD SHX Text
W/HOSE COUPLING
AutoCAD SHX Text
3/4" GATE VALVE
AutoCAD SHX Text
FLOAT-SWITCH
AutoCAD SHX Text
GATE VALVE
AutoCAD SHX Text
RETURN HEADER
AutoCAD SHX Text
CONDENSATE
AutoCAD SHX Text
RETURN LINE
AutoCAD SHX Text
CONDENSATE
AutoCAD SHX Text
UP THRU WALL
AutoCAD SHX Text
VENT LINE
AutoCAD SHX Text
CONNECTION AS REQ'D
AutoCAD SHX Text
THREADED OR FLANGED
AutoCAD SHX Text
REDUCER (IF REQ'D)
AutoCAD SHX Text
WITH GAUGECOCK
AutoCAD SHX Text
PRESSURE GAUGE
AutoCAD SHX Text
SYSTEM
AutoCAD SHX Text
TO DISTRIBUTION
AutoCAD SHX Text
(EACH PUMP)
AutoCAD SHX Text
CHECK VALVE
AutoCAD SHX Text
(EACH PUMP)
AutoCAD SHX Text
GATE VALVE
AutoCAD SHX Text
CAP FOR PIPE 2-1/2"
AutoCAD SHX Text
& LESS. BLIND FLANGE
AutoCAD SHX Text
FOR PIPE 3" & LARGER
AutoCAD SHX Text
BALANCING
AutoCAD SHX Text
VALVE
AutoCAD SHX Text
STERLING MODEL 42515-JD
AutoCAD SHX Text
PUMP
AutoCAD SHX Text
HW OUT
AutoCAD SHX Text
140%%DF
AutoCAD SHX Text
TO FLOOR
AutoCAD SHX Text
DRAIN
AutoCAD SHX Text
DRAIN
AutoCAD SHX Text
WATER HEATER
AutoCAD SHX Text
NTS
AutoCAD SHX Text
CW IN
AutoCAD SHX Text
HWR
AutoCAD SHX Text
BLDG RECIRC
AutoCAD SHX Text
COND
AutoCAD SHX Text
DOMESTIC HOT
AutoCAD SHX Text
MODEL PK08SH
AutoCAD SHX Text
P-K COMPACT
AutoCAD SHX Text
STEAM IN
AutoCAD SHX Text
TEMP
AutoCAD SHX Text
PILOT
AutoCAD SHX Text
MAIN
AutoCAD SHX Text
VALVE
AutoCAD SHX Text
%%C2"
AutoCAD SHX Text
%%C3"
AutoCAD SHX Text
65 PSI
AutoCAD SHX Text
%%C2"
AutoCAD SHX Text
TRAP
AutoCAD SHX Text
MFG: ARMSTRONG INTERNATIONAL
AutoCAD SHX Text
MODEL: DMC40 FLEX 1-1/2 NPT 1-1/2 NPT 1 NPT
AutoCAD SHX Text
COPPER TYPE "L"
AutoCAD SHX Text
PIPING
AutoCAD SHX Text
ITEM
AutoCAD SHX Text
1-1/2" NPT
AutoCAD SHX Text
DRV40
AutoCAD SHX Text
6
AutoCAD SHX Text
1" NPT
AutoCAD SHX Text
RETURN TO HEATER
AutoCAD SHX Text
5
AutoCAD SHX Text
1" NPT
AutoCAD SHX Text
RECIRC RETURN INLET
AutoCAD SHX Text
4
AutoCAD SHX Text
1-1/2" NPT
AutoCAD SHX Text
HOT WATER INLET
AutoCAD SHX Text
3
AutoCAD SHX Text
1-1/2" NPT
AutoCAD SHX Text
MIXED WATER OUTLET
AutoCAD SHX Text
2
AutoCAD SHX Text
1-1/2" NPT
AutoCAD SHX Text
COLD WATER INLET
AutoCAD SHX Text
1
AutoCAD SHX Text
CONNECTION
AutoCAD SHX Text
DESCRIPTION
AutoCAD SHX Text
ITEM
AutoCAD SHX Text
6
AutoCAD SHX Text
3
AutoCAD SHX Text
2
AutoCAD SHX Text
1
AutoCAD SHX Text
4
AutoCAD SHX Text
5
AutoCAD SHX Text
HOT WATER MIXING VALVE DETAILS
AutoCAD SHX Text
NTS
AutoCAD SHX Text
120%%DF
AutoCAD SHX Text
140%%DF
AutoCAD SHX Text
PRESSURE STEAM
AutoCAD SHX Text
SUPPLY
AutoCAD SHX Text
RETURN
AutoCAD SHX Text
%%C1-1/2" COND.
AutoCAD SHX Text
GATE VALVE
AutoCAD SHX Text
GAUGE
AutoCAD SHX Text
ECCENTRIC
AutoCAD SHX Text
DISCHARGE ELBOW
AutoCAD SHX Text
SAFETY VALVE
AutoCAD SHX Text
BYPASS LINE
AutoCAD SHX Text
AS REQUIRED
AutoCAD SHX Text
UNION OR FLANGE
AutoCAD SHX Text
FULL SIZE
AutoCAD SHX Text
BLOW-OFF VALVE
AutoCAD SHX Text
PIPE 3" & LARGER
AutoCAD SHX Text
BLIND FLANGE FOR
AutoCAD SHX Text
2-1/2" & LESS.
AutoCAD SHX Text
CAP FOR PIPE
AutoCAD SHX Text
VALVE
AutoCAD SHX Text
REDUCING
AutoCAD SHX Text
6" MINIMUM
AutoCAD SHX Text
LINE SLOPE DOWN
AutoCAD SHX Text
PRESSURE SENSING
AutoCAD SHX Text
STEAM PRESSURE REDUCING STATION DETAIL
AutoCAD SHX Text
Y-STRAINER W/
AutoCAD SHX Text
PRESSURE
AutoCAD SHX Text
PRESSURE
AutoCAD SHX Text
CHECK VALVE
AutoCAD SHX Text
10 PIPE DIA'S
AutoCAD SHX Text
20 PSIG A.S.M.E.
AutoCAD SHX Text
SAFETY RELIEF
AutoCAD SHX Text
N.T.S.
AutoCAD SHX Text
MINIMUM
AutoCAD SHX Text
TO OUTSIDE
AutoCAD SHX Text
REDUCER (TYP.)
AutoCAD SHX Text
F & T TRAP
AutoCAD SHX Text
200 LBS/HOUR
AutoCAD SHX Text
VALVE
AutoCAD SHX Text
SUPPLY, 65 PSI
AutoCAD SHX Text
W/GAGECOCK
AutoCAD SHX Text
%%C4" STEAM
AutoCAD SHX Text
15 PSI REDUCED
AutoCAD SHX Text
%%C2" VENT LINE
AutoCAD SHX Text
%%C1-1/2"
AutoCAD SHX Text
%%C5"
AutoCAD SHX Text
2,200 PPH
AutoCAD SHX Text
GLOBE VALVE
AutoCAD SHX Text
TO FLASH TANK
AutoCAD SHX Text
SUPPLY, 65 PSI
AutoCAD SHX Text
%%C2.5" STEAM
AutoCAD SHX Text
TO WTR HTR
AutoCAD SHX Text
UNIVERSITY OF CONNECTICUT
AutoCAD SHX Text
http://www.fo.uconn.edu
AutoCAD SHX Text
STORRS, CONNECTICUT
AutoCAD SHX Text
FACILITIES OPERATIONS
AutoCAD SHX Text
O
AutoCAD SHX Text
V
AutoCAD SHX Text
I
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
Y
AutoCAD SHX Text
T
AutoCAD SHX Text
T
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
8
AutoCAD SHX Text
C
AutoCAD SHX Text
U
AutoCAD SHX Text
N
AutoCAD SHX Text
C
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
T
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
E
AutoCAD SHX Text
R E V I S I O N S
AutoCAD SHX Text
Date
AutoCAD SHX Text
Mark
AutoCAD SHX Text
Description
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
MICHAEL J ROCCHETTI PE
AutoCAD SHX Text
MECHANICAL ENGINEER
AutoCAD SHX Text
Architect/Engineer
AutoCAD SHX Text
Drawing Title
AutoCAD SHX Text
CAD File No.
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Drawn by
AutoCAD SHX Text
Approved by
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
Date
AutoCAD SHX Text
Scale
Page 34: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

PROJECT MANUAL

Project: FO500078

West Campus Dorms Mechanical Room Repairs

State of Connecticut

University of Connecticut Facilities Operations – Operational Engineering

Thomas Katsouleas

President

Prepared By: Michael J Rocchetti PE

December 2019

Page 35: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

Dwg# Drawing Name COV COVER S-01 SITE PLAN M-01 MECHANICAL LEGENDS AND NOTES M-02 WC-1 REFURBISHMENT PLAN M-03 WC-2 REFURBISHMENT PLAN M-04 WC-3 REFURBISHMENT PLAN M-05 WC-4 REFURBISHMENT PLAN M-06 WC-1 PLUMBING PIPING PLAN M-07 WC-1 STEAM AND CONDENSATE M-08 WC-2 PLUMBING PIPING PLAN M-09 WC-2 STEAM AND CONDENSATE M-10 WC-3 PLUMBING PIPING PLAN M-11 WC-3 STEAM AND CONDENSATE M-12 WC-4 PLUMBING PIPING PLAN M-13 WC-4 STEAM AND CONDENSATE M-14 MECHANICAL DETAILS

Page 36: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents SPECIFICATIONS SECT NO. SECTION TITLE DIVISION 01 – GENERAL 010000 – General Requirements 012300 – Alternates DIVISION 09 – FINISHES 090000 – General Requirements DIVISION 22 – PLUMBING 220719 – Plumbing Piping Insulation 221116 – Domestic Water Piping 221316 – Sanitary Waste and Vent Piping 221319 – Sanitary Waste Piping Specialties 222500 – Domestic Water Heat Exchanger DIVISION 23 – MECHANICAL 230719 – HVAC Piping Insulation 232213 – Steam and Condensate Heating Piping 232216 – Steam and Condensate Piping Specialties 232223 – Steam Condensate Pumps DIVISION 26 – ELECTRICAL 260000 – Electrical Specifications APPENDIXES

Page 37: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

GENERAL REQUIREMENTS 010000 - 1/3

SECTION 010000 – GENERAL REQUIREMENTS

PART 1 - GENERAL

1.1 PROJECT INFORMATION

A. Project Identification: West Campus Dorms – Mechanical Room Repairs.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists of the following:

1. Paint the walls, doors, ceilings, and floors. 2. Replace the sanitary drain waste & vent piping with cast-iron or galvanized steel piping. 3. Replace the water piping including cold water, hot water, and hot water return lines.

Replace associated valves. 4. Insulate hot water and hot water recirculating pipes. 5. Install PVC jacketing on all HW and HWR piping and fittings. Provide aluminum

jacketing where the pipes are in close proximity to steam lines. 6. Remove abandoned steam zone control valves and associated controls. 7. Replace steam and condensate piping including all fittings, valves, and appurtenances. 8. Insulate new steam and condensate piping and fittings. 9. Install new vertical flash tanks for high pressure steam drip legs. Vent these flash tanks

into the window wells. 10. Install new hot water heaters. 11. Install new hot water mixing valves. 12. Install new condensate pumps and receivers. 13. Remove unused concrete pedestals in the mechanical rooms. 14. Repair the floor drains. 15. Remove abandoned equipment, piping valves, and fittings. 16. Clean out the window wells. 17. Provide new LED lighting in the mech rooms. 18. Provide electrical service for new condensate pumps, water heaters, and new hot water

mixing valves.

1.3 TIME OF COMPLETION

A. Work required by the project shall commence immediately upon receipt of a Notice to Proceed. Substantial Completion as defined in the Contract Documents must be achieved and evidenced by a Certificate of Substantial Completion no later than three (3) months after award of contract. Contractor shall cooperate and coordinate with the University. No Work may be conducted during University exam periods.

Page 38: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

GENERAL REQUIREMENTS 010000 - 2/3

1.4 ACCESS TO SITE

A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weather tight condition throughout construction period. Repair damage caused by construction operations. Take all precautions necessary to protect the building, installed equipment and its occupants during the construction period. Contractor’s Parking: Contractors working for the University of Connecticut at the regional campus will work with the University Representative to determine where contractors are allowed to park during the course of the Project. Contractors working for the University of Connecticut at Storrs Campus are required to obtain a parking permit through the Parking Services Office. For additional information please contact the Parking Services Office at 860-486-4930. The Contractor is responsible for payment of all fees for parking permits. Parking fees may be prorated monthly. The University will provide a maximum of three (3) contract parking places in the vicinity of the work. Additional parking required by the Contractor will be designated at a location specified by the Owner’s Representative. Construction vehicles are exempt from this requirement.

1.5 WORK RESTRICTIONS

A. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7:00 a.m. to 4:30 p.m., Monday through Friday, unless otherwise indicated. Permission must be requested and approved in writing to perform work outside the normal working hours or on a State Holiday. Owner will occupy site and building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.

1.6 MISCELLANEOUS PROVISIONS

A. Preconstruction Conference: The successful bidder shall attend a preconstruction conference and organizational meeting at the University of Connecticut Office of Architectural and Engineering Services, with the University Representative prior to any field work to review responsibilities and personnel assignments and to insure that Specifications, drawings and all conditions are understood to properly complete this Contract.

B. Temporary Heat and Hot Water: The work should be done during the summer months when the West Campus dorms are unoccupied. Temporary heat and hot water must be provided if the dorm is occupied and the work is not yet finished.

C. Noise Control: The Contractor shall make every effort to minimize noise disruption to occupants of buildings and adjacent buildings.

D. Collection and Disposal of Waste: Collect waste from construction areas and elsewhere daily.

E. Nuisance Dust Control: The following provisions shall apply during demolition or construction phases of work. The Contractor shall take all measures necessary to accomplish this goal. These measures will include as minimum polyethylene sheeting or wet methods of fugitive dust control.

Page 39: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

GENERAL REQUIREMENTS 010000 - 3/3

F. Temporary Fencing: If required, secure the jobsite with Portable Chain-Link Fencing: Minimum 2-inch, 0.148-inch- thick, galvanized-steel, chain-link fabric fencing; minimum 6 feet high with galvanized-steel pipe posts; minimum 2-3/8-inch- OD line posts and 2-7/8-inch- OD corner and pull posts, with 1-5/8-inch- OD top and bottom rails. Provide concrete bases for supporting posts.

G. Cutting and Patching, General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay. Protection: Protect in-place construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.

H. Final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 010000

Page 40: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

ALTERNATES 012300 - 1

SECTION 012300 - ALTERNATES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for alternates.

1.2 DEFINITIONS

A. Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined in the bidding requirements that may be added to or deducted from the base bid amount if Owner decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents.

1. Alternates described in this Section are part of the Work only if enumerated in the Agreement.

2. The cost or credit for each alternate is the net addition to or deduction from the Contract Sum to incorporate alternate into the Work. No other adjustments are made to the Contract Sum.

1.3 PROCEDURES

A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the alternate into Project.

1. Include as part of each alternate, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation whether or not indicated as part of alternate.

B. Notification: Immediately following award of the Contract, notify each party involved, in writing, of the status of each alternate. Indicate if alternates have been accepted, rejected, or deferred for later consideration. Include a complete description of negotiated revisions to alternates.

C. Execute accepted alternates under the same conditions as other work of the Contract.

D. Schedule: A schedule of alternates is included at the end of this Section. Specification Sections referenced in schedule contain requirements for materials necessary to achieve the work described under each alternate.

Page 41: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

ALTERNATES 012300 - 2

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 BIDDING SCHEDULE

A. Building WC-1 (Base Bid)

1. Bid Item: All work indicated in the “Scope of Work”, with the exception on the new hot water heater.

2. Bid Item: Provide a price for the installation of the new hot water heater.

B. Building WC-2

1. Bid Item: All work indicated in the “Scope of Work”, with the exception on the new hot water heater.

C. Building WC-3

1. Bid Item: All work indicated in the “Scope of Work”, with the exception on the new hot water heater.

2. Bid Item: Provide a price for the installation of the new hot water heater.

D. Building WC-4

1. Bid Item: All work indicated in the “Scope of Work”, with the exception on the new hot water heater.

2. Bid Item: Provide a price for the installation of the new hot water heater.

END OF SECTION 012300

Page 42: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

FINISHES SPECIFICATIONS 090000 - 1

SECTION 090000 – FINISHES SPECIFICATIONS

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes high performance coatings for the following: 1. Concrete vertical and horizontal surfaces

PART 2 - PRODUCTS

2.1 HIGH PREFFORMANCE COATINGS

A. MPI Standards: Provide products that comply with MPI standards indicated and are listed in "MPI Approved Products List."

B. Material Compatibility: 1. Provide materials for use within each coating system that are compatible with one

another and substrates indicated, under conditions of service and application as demonstrated by manufacturer, based on testing and field experience.

2. For each coat in a coating system, provide products recommended in writing by manufacturers of topcoat for use in coating system and on substrate indicated.

3. Provide products of same manufacturer for each coat in a coating system.

C. Colors: As selected by Architect from manufacturer's full range..

2.2 EPOXY COATINGS

A. Epoxy, Gloss: MPI #77.

PART 3 - EXECUTION

3.1 PREPARATION

A. Comply with manufacturer's written instructions and recommendations in "MPI Architectural Painting Specification Manual" applicable to substrates indicated.

B. Remove hardware, covers, plates, and similar items already in place that are removable and are not to be painted. If removal is impractical or impossible because of size or weight of item, provide surface-applied protection before surface preparation and painting.

C. After completing painting operations, use workers skilled in the trades involved to reinstall items that were removed. Remove surface-applied protection.

Page 43: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

FINISHES SPECIFICATIONS 090000 - 2

D. Clean substrates of substances that could impair bond of coatings, including dust, dirt, oil, grease, and incompatible paints and encapsulants.

E. Remove incompatible primers and reprime substrate with compatible primers or apply tie coat as required to produce coating systems indicated.

F. Concrete Substrates: Remove release agents, curing compounds, efflorescence, and chalk. Do not coat surfaces if moisture content or alkalinity of surfaces to be coated exceeds that permitted in manufacturer's written instructions.

G. Abrasive blast clean surfaces to comply with SSPC-SP 7/NACE No. 4, "Brush-Off Blast Cleaning."

3.2 APPLICATION

A. Apply high-performance coatings according to manufacturer's written instructions and recommendations in "MPI Architectural Painting Specification Manual."

B. Use applicators and techniques suited for coating and substrate indicated.

C. Coat surfaces behind movable equipment and furniture same as similar exposed surfaces. Before final installation, coat surfaces behind permanently fixed equipment or furniture with prime coat only.

D. Coat back sides of access panels, removable or hinged covers, and similar hinged items to match exposed surfaces.

E. Do not apply coatings over labels of independent testing agencies or equipment name, identification, performance rating, or nomenclature plates.

F. If undercoats or other conditions show through final coat, apply additional coats until cured film has a uniform coating finish, color, and appearance.

G. Apply coatings to produce surface films without cloudiness, spotting, holidays, laps, brush marks, runs, sags, ropiness, or other surface imperfections. Produce sharp glass lines and color breaks.

3.3 CLEANING AND PROTECTION

A. At end of each workday, remove rubbish, empty cans, rags, and other discarded materials from Project site.

B. After completing coating application, clean spattered surfaces. Remove spattered coatings by washing, scraping, or other methods. Do not scratch or damage adjacent finished surfaces.

C. Protect work of other trades against damage from coating operation. Correct damage by cleaning, repairing, replacing, and recoating, as approved by Architect, and leave in an undamaged condition.

Page 44: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

FINISHES SPECIFICATIONS 090000 - 3

D. At completion of construction activities of other trades, touch up and restore damaged or defaced coated surfaces

END OF SECTION 090000

Page 45: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

PLUMBING PIPING INSULATION 220719 - 1

SECTION 220719 - PLUMBING PIPING INSULATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes insulating the following plumbing piping services:

1. Domestic cold-water piping. 2. Domestic hot-water piping. 3. Domestic recirculating hot-water piping. 4. Roof drains and rainwater leaders.

1.3 DELIVERY, STORAGE, AND HANDLING

A. Packaging: Insulation material containers shall be marked by manufacturer with appropriate ASTM standard designation, type and grade, and maximum use temperature.

1.4 COORDINATION

A. Coordinate sizes and locations of supports, hangers, and insulation shields specified in Section 220529 "Hangers and Supports for Plumbing Piping and Equipment."

B. Coordinate clearance requirements with piping Installer for piping insulation application. Establish and maintain clearance requirements for installation of insulation and field-applied jackets and finishes and for space required for maintenance.

1.5 SCHEDULING

A. Schedule insulation application after pressure testing systems and, where required, after installing and testing heat tracing. Insulation application may begin on segments that have satisfactory test results.

B. Complete installation and concealment of plastic materials as rapidly as possible in each area of construction.

Page 46: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

PLUMBING PIPING INSULATION 220719 - 2

PART 2 - PRODUCTS

2.1 INSULATION MATERIALS

A. Comply with requirements in "Piping Insulation Schedule, General," articles for where insulating materials shall be applied.

B. Products shall not contain asbestos, lead, mercury, or mercury compounds.

C. Products that come in contact with stainless steel shall have a leachable chloride content of less than 50 ppm when tested according to ASTM C 871.

D. Insulation materials for use on austenitic stainless steel shall be qualified as acceptable according to ASTM C 795.

E. Mineral-Fiber, Preformed Pipe Insulation:

1. Type I, 850 Deg F Materials: Mineral or glass fibers bonded with a thermosetting resin. Comply with ASTM C 547, Type I, Grade A, with factory-applied ASJ.

2.2 INSULATING CEMENTS

A. Mineral-Fiber Insulating Cement: Comply with ASTM C 195.

2.3 ADHESIVES

A. Materials shall be compatible with insulation materials, jackets, and substrates and for bonding insulation to itself and to surfaces to be insulated, unless otherwise indicated.

2.4 MASTICS

A. Materials shall be compatible with insulation materials, jackets, and substrates; comply with MIL-PRF-19565C, Type II.

2.5 SEALANTS

A. Joint Sealants:

1. Materials shall be compatible with insulation materials, jackets, and substrates. 2. Permanently flexible, elastomeric sealant. 3. Service Temperature Range: Minus 100 to plus 300 deg F. 4. Color: White or gray. 5. For indoor applications, sealants shall have a VOC content of 420 g/L or less when

calculated according to 40 CFR 59, Subpart D (EPA Method 24). 6. Sealants shall comply with the testing and product requirements of the California

Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers."

Page 47: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

PLUMBING PIPING INSULATION 220719 - 3

2.6 FACTORY-APPLIED JACKETS

A. Insulation system schedules indicate factory-applied jackets on various applications. When factory-applied jackets are indicated, comply with the following:

1. ASJ: White, kraft-paper, fiberglass-reinforced scrim with aluminum-foil backing; complying with ASTM C 1136, Type I.

2. ASJ-SSL: ASJ with self-sealing, pressure-sensitive, acrylic-based adhesive covered by a removable protective strip; complying with ASTM C 1136, Type I.

3. FSK Jacket: Aluminum-foil, fiberglass-reinforced scrim with kraft-paper backing; complying with ASTM C 1136, Type II.

2.7 FIELD-APPLIED JACKETS

A. Field-applied jackets shall comply with ASTM C 921, Type I, unless otherwise indicated.

B. PVC Jacket: High-impact-resistant, UV-resistant PVC complying with ASTM D 1784, Class 16354-C; thickness as scheduled; roll stock ready for shop or field cutting and forming. Thickness is indicated in field-applied jacket schedules. 1. Adhesive: As recommended by jacket material manufacturer. 2. Color: [White] [Color-code jackets based on system. Color as selected by Architect]. 3. Factory-fabricated fitting covers to match jacket if available; otherwise, field fabricate.

a. Shapes: 45- and 90-degree, short- and long-radius elbows, tees, valves, flanges, unions, reducers, end caps, soil-pipe hubs, traps, mechanical joints, and P-trap and supply covers for lavatories.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates and conditions for compliance with requirements for installation tolerances and other conditions affecting performance of insulation application.

1. Verify that systems to be insulated have been tested and are free of defects. 2. Verify that surfaces to be insulated are clean and dry.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Surface Preparation: Clean and dry surfaces to receive insulation. Remove materials that will adversely affect insulation application.

B. Surface Preparation: Clean and prepare surfaces to be insulated. Before insulating, apply a corrosion coating to insulated surfaces as follows:

Page 48: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

PLUMBING PIPING INSULATION 220719 - 4

1. Stainless Steel: Coat 300 series stainless steel with an epoxy primer 5 mils thick and an epoxy finish 5 mils thick if operating in a temperature range between 140 and 300 deg F. Consult coating manufacturer for appropriate coating materials and application methods for operating temperature range.

2. Carbon Steel: Coat carbon steel operating at a service temperature between 32 and 300 deg F with an epoxy coating. Consult coating manufacturer for appropriate coating materials and application methods for operating temperature range.

C. Coordinate insulation installation with the trade installing heat tracing. Comply with requirements for heat tracing that apply to insulation.

D. Mix insulating cements with clean potable water; if insulating cements are to be in contact with stainless-steel surfaces, use demineralized water.

3.3 GENERAL INSTALLATION REQUIREMENTS

A. Install insulation materials, accessories, and finishes with smooth, straight, and even surfaces; free of voids throughout the length of piping including fittings, valves, and specialties.

B. Install insulation materials, forms, vapor barriers or retarders, jackets, and thicknesses required for each item of pipe system as specified in insulation system schedules.

C. Install accessories compatible with insulation materials and suitable for the service. Install accessories that do not corrode, soften, or otherwise attack insulation or jacket in either wet or dry state.

D. Install insulation with longitudinal seams at top and bottom of horizontal runs.

E. Install multiple layers of insulation with longitudinal and end seams staggered.

F. Do not weld brackets, clips, or other attachment devices to piping, fittings, and specialties.

G. Keep insulation materials dry during application and finishing.

H. Install insulation with tight longitudinal seams and end joints. Bond seams and joints with adhesive recommended by insulation material manufacturer.

I. Install insulation with least number of joints practical.

J. Where vapor barrier is indicated, seal joints, seams, and penetrations in insulation at hangers, supports, anchors, and other projections with vapor-barrier mastic.

1. Install insulation continuously through hangers and around anchor attachments. 2. For insulation application where vapor barriers are indicated, extend insulation on anchor

legs from point of attachment to supported item to point of attachment to structure. Taper and seal ends at attachment to structure with vapor-barrier mastic.

3. Install insert materials and install insulation to tightly join the insert. Seal insulation to insulation inserts with adhesive or sealing compound recommended by insulation material manufacturer.

Page 49: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

PLUMBING PIPING INSULATION 220719 - 5

4. Cover inserts with jacket material matching adjacent pipe insulation. Install shields over jacket, arranged to protect jacket from tear or puncture by hanger, support, and shield.

K. Apply adhesives, mastics, and sealants at manufacturer's recommended coverage rate and wet and dry film thicknesses.

L. Install insulation with factory-applied jackets as follows:

1. Draw jacket tight and smooth. 2. Cover circumferential joints with 3-inch-wide strips, of same material as insulation

jacket. Secure strips with adhesive and outward clinching staples along both edges of strip, spaced 4 inches o.c.

3. Overlap jacket longitudinal seams at least 1-1/2 inches. Install insulation with longitudinal seams at bottom of pipe. Clean and dry surface to receive self-sealing lap. Staple laps with outward clinching staples along edge at 4 inches o.c.

a. For below-ambient services, apply vapor-barrier mastic over staples.

4. Cover joints and seams with tape, according to insulation material manufacturer's written instructions, to maintain vapor seal.

5. Where vapor barriers are indicated, apply vapor-barrier mastic on seams and joints and at ends adjacent to pipe flanges and fittings.

M. Cut insulation in a manner to avoid compressing insulation more than 75 percent of its nominal thickness.

N. Finish installation with systems at operating conditions. Repair joint separations and cracking due to thermal movement.

O. Repair damaged insulation facings by applying same facing material over damaged areas. Extend patches at least 4 inches beyond damaged areas. Adhere, staple, and seal patches similar to butt joints.

P. For above-ambient services, do not install insulation to the following:

1. Vibration-control devices. 2. Testing agency labels and stamps. 3. Nameplates and data plates. 4. Cleanouts.

3.4 PENETRATIONS

A. Insulation Installation at Roof Penetrations: Install insulation continuously through roof penetrations.

1. Seal penetrations with flashing sealant. 2. For applications requiring only indoor insulation, terminate insulation above roof surface

and seal with joint sealant. For applications requiring indoor and outdoor insulation, install insulation for outdoor applications tightly joined to indoor insulation ends. Seal joint with joint sealant.

Page 50: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

PLUMBING PIPING INSULATION 220719 - 6

3. Extend jacket of outdoor insulation outside roof flashing at least 2 inches below top of roof flashing.

4. Seal jacket to roof flashing with flashing sealant.

B. Insulation Installation at Underground Exterior Wall Penetrations: Terminate insulation flush with sleeve seal. Seal terminations with flashing sealant.

C. Insulation Installation at Aboveground Exterior Wall Penetrations: Install insulation continuously through wall penetrations.

1. Seal penetrations with flashing sealant. 2. For applications requiring only indoor insulation, terminate insulation inside wall surface

and seal with joint sealant. For applications requiring indoor and outdoor insulation, install insulation for outdoor applications tightly joined to indoor insulation ends. Seal joint with joint sealant.

3. Extend jacket of outdoor insulation outside wall flashing and overlap wall flashing at least 2 inches.

4. Seal jacket to wall flashing with flashing sealant.

D. Insulation Installation at Interior Wall and Partition Penetrations (That Are Not Fire Rated): Install insulation continuously through walls and partitions.

E. Insulation Installation at Fire-Rated Wall and Partition Penetrations: Install insulation continuously through penetrations of fire-rated walls and partitions.

1. Comply with requirements in Section 078413 "Penetration Firestopping" for firestopping and fire-resistive joint sealers.

F. Insulation Installation at Floor Penetrations:

1. Pipe: Install insulation continuously through floor penetrations. 2. Seal penetrations through fire-rated assemblies. Comply with requirements in

Section 078413 "Penetration Firestopping."

3.5 GENERAL PIPE INSULATION INSTALLATION

A. Requirements in this article generally apply to all insulation materials except where more specific requirements are specified in various pipe insulation material installation articles.

B. Insulation Installation on Fittings, Valves, Strainers, Flanges, and Unions:

1. Install insulation over fittings, valves, strainers, flanges, unions, and other specialties with continuous thermal and vapor-retarder integrity unless otherwise indicated.

2. Insulate pipe elbows using preformed fitting insulation or mitered fittings made from same material and density as adjacent pipe insulation. Each piece shall be butted tightly against adjoining piece and bonded with adhesive. Fill joints, seams, voids, and irregular surfaces with insulating cement finished to a smooth, hard, and uniform contour that is uniform with adjoining pipe insulation.

3. Insulate tee fittings with preformed fitting insulation or sectional pipe insulation of same material and thickness as used for adjacent pipe. Cut sectional pipe insulation to fit. Butt

Page 51: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

PLUMBING PIPING INSULATION 220719 - 7

each section closely to the next and hold in place with tie wire. Bond pieces with adhesive.

4. Insulate valves using preformed fitting insulation or sectional pipe insulation of same material, density, and thickness as used for adjacent pipe. Overlap adjoining pipe insulation by not less than two times the thickness of pipe insulation, or one pipe diameter, whichever is thicker. For valves, insulate up to and including the bonnets, valve stuffing-box studs, bolts, and nuts. Fill joints, seams, and irregular surfaces with insulating cement.

5. Insulate strainers using preformed fitting insulation or sectional pipe insulation of same material, density, and thickness as used for adjacent pipe. Overlap adjoining pipe insulation by not less than two times the thickness of pipe insulation, or one pipe diameter, whichever is thicker. Fill joints, seams, and irregular surfaces with insulating cement. Insulate strainers so strainer basket flange or plug can be easily removed and replaced without damaging the insulation and jacket. Provide a removable reusable insulation cover. For below-ambient services, provide a design that maintains vapor barrier.

6. Insulate flanges and unions using a section of oversized preformed pipe insulation. Overlap adjoining pipe insulation by not less than two times the thickness of pipe insulation, or one pipe diameter, whichever is thicker.

7. Cover segmented insulated surfaces with a layer of finishing cement and coat with a mastic. Install vapor-barrier mastic for below-ambient services and a breather mastic for above-ambient services. Reinforce the mastic with fabric-reinforcing mesh. Trowel the mastic to a smooth and well-shaped contour.

8. For services not specified to receive a field-applied jacket except for flexible elastomeric and polyolefin, install fitted PVC cover over elbows, tees, strainers, valves, flanges, and unions. Terminate ends with PVC end caps. Tape PVC covers to adjoining insulation facing using PVC tape.

9. Stencil or label the outside insulation jacket of each union with the word "union." Match size and color of pipe labels.

C. Insulate instrument connections for thermometers, pressure gages, pressure temperature taps, test connections, flow meters, sensors, switches, and transmitters on insulated pipes. Shape insulation at these connections by tapering it to and around the connection with insulating cement and finish with finishing cement, mastic, and flashing sealant.

D. Install removable insulation covers at locations indicated. Installation shall conform to the following:

1. Make removable flange and union insulation from sectional pipe insulation of same thickness as that on adjoining pipe. Install same insulation jacket as adjoining pipe insulation.

2. When flange and union covers are made from sectional pipe insulation, extend insulation from flanges or union long at least two times the insulation thickness over adjacent pipe insulation on each side of flange or union. Secure flange cover in place with stainless-steel or aluminum bands. Select band material compatible with insulation and jacket.

3. Construct removable valve insulation covers in same manner as for flanges, except divide the two-part section on the vertical center line of valve body.

4. When covers are made from block insulation, make two halves, each consisting of mitered blocks wired to stainless-steel fabric. Secure this wire frame, with its attached insulation, to flanges with tie wire. Extend insulation at least 2 inches over adjacent pipe insulation on each side of valve. Fill space between flange or union cover and pipe

Page 52: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

PLUMBING PIPING INSULATION 220719 - 8

insulation with insulating cement. Finish cover assembly with insulating cement applied in two coats. After first coat is dry, apply and trowel second coat to a smooth finish.

5. Unless a PVC jacket is indicated in field-applied jacket schedules, finish exposed surfaces with a metal jacket.

3.6 INSTALLATION OF MINERAL-FIBER INSULATION

A. Insulation Installation on Straight Pipes and Tubes:

1. Secure each layer of preformed pipe insulation to pipe with wire or bands and tighten bands without deforming insulation materials.

2. Where vapor barriers are indicated, seal longitudinal seams, end joints, and protrusions with vapor-barrier mastic and joint sealant.

3. For insulation with factory-applied jackets on above-ambient surfaces, secure laps with outward clinched staples at 6 inches o.c.

4. For insulation with factory-applied jackets on below-ambient surfaces, do not staple longitudinal tabs. Instead, secure tabs with additional adhesive as recommended by insulation material manufacturer and seal with vapor-barrier mastic and flashing sealant.

B. Insulation Installation on Pipe Flanges:

1. Install preformed pipe insulation to outer diameter of pipe flange. 2. Make width of insulation section same as overall width of flange and bolts, plus twice the

thickness of pipe insulation. 3. Fill voids between inner circumference of flange insulation and outer circumference of

adjacent straight pipe segments with mineral-fiber blanket insulation. 4. Install jacket material with manufacturer's recommended adhesive, overlap seams at least

1 inch, and seal joints with flashing sealant.

C. Insulation Installation on Pipe Fittings and Elbows:

1. Install preformed sections of same material as straight segments of pipe insulation when available.

2. When preformed insulation elbows and fittings are not available, install mitered sections of pipe insulation, to a thickness equal to adjoining pipe insulation. Secure insulation materials with wire or bands.

D. Insulation Installation on Valves and Pipe Specialties:

1. Install preformed sections of same material as straight segments of pipe insulation when available.

2. When preformed sections are not available, install mitered sections of pipe insulation to valve body.

3. Arrange insulation to permit access to packing and to allow valve operation without disturbing insulation.

4. Install insulation to flanges as specified for flange insulation application.

Page 53: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

PLUMBING PIPING INSULATION 220719 - 9

3.7 FIELD-APPLIED JACKET INSTALLATION

A. Where glass-cloth jackets are indicated, install directly over bare insulation or insulation with factory-applied jackets.

1. Draw jacket smooth and tight to surface with 2-inch overlap at seams and joints. 2. Embed glass cloth between two 0.062-inch-thick coats of lagging adhesive. 3. Completely encapsulate insulation with coating, leaving no exposed insulation.

B. Where FSK jackets are indicated, install as follows:

1. Draw jacket material smooth and tight. 2. Install lap or joint strips with same material as jacket. 3. Secure jacket to insulation with manufacturer's recommended adhesive. 4. Install jacket with 1-1/2-inch laps at longitudinal seams and 3-inch-wide joint strips at

end joints. 5. Seal openings, punctures, and breaks in vapor-retarder jackets and exposed insulation

with vapor-barrier mastic.

C. Where PVC jackets are indicated, install with 1-inch overlap at longitudinal seams and end joints. Seal with manufacturer's recommended adhesive.

1. Apply two continuous beads of adhesive to seams and joints, one bead under lap and the finish bead along seam and joint edge.

D. Where metal jackets are indicated, install with 2-inch overlap at longitudinal seams and end joints. Overlap longitudinal seams arranged to shed water. Seal end joints with weatherproof sealant recommended by insulation manufacturer. Secure jacket with stainless-steel bands 12 inches o.c. and at end joints.

3.8 FINISHES

A. Insulation with ASJ, Glass-Cloth, or Other Paintable Jacket Material: Paint jacket with paint system identified below and as specified in Section 099113 "Exterior Painting" and Section 099123 "Interior Painting."

1. Flat Acrylic Finish: [Two] <Insert number> finish coats over a primer that is compatible with jacket material and finish coat paint. Add fungicidal agent to render fabric mildew proof.

a. Finish Coat Material: Interior, flat, latex-emulsion size.

B. Flexible Elastomeric Thermal Insulation: After adhesive has fully cured, apply two coats of insulation manufacturer's recommended protective coating.

C. Color: Final color as selected by Architect. Vary first and second coats to allow visual inspection of the completed Work.

D. Do not field paint aluminum or stainless-steel jackets.

Page 54: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

PLUMBING PIPING INSULATION 220719 - 10

3.9 INDOOR PIPING INSULATION SCHEDULE

A. Domestic Cold Water:

1. NPS 1 and Smaller: Insulation shall be the following: a. Mineral-Fiber, Preformed Pipe Insulation, Type I: 1 inch thick.

2. NPS 1-1/4 and Larger: Insulation shall be the following: a. Mineral-Fiber, Preformed Pipe Insulation, Type I: 1 inch thick.

B. Domestic Hot and Recirculated Hot Water:

1. NPS 1-1/4 and Smaller: Insulation shall be the following: a. Mineral-Fiber, Preformed Pipe Insulation, Type I: 1 inch thick.

2. NPS 1-1/2 and Larger: Insulation shall be the following: a. Mineral-Fiber, Preformed Pipe Insulation, Type I: 1 inch thick.

C. Roof Drain and Overflow Drain Bodies:

1. All Pipe Sizes: Insulation shall be the following: a. Mineral-Fiber, Preformed Pipe Insulation, Type I: 1 inch thick.

D. Hot Service Drains:

1. All Pipe Sizes: Insulation shall be the following: a. Mineral-Fiber, Preformed Pipe, Type I or II: 1 inch thick.

E. Hot Service Vents:

1. All Pipe Sizes: Insulation shall be the following: a. Mineral-Fiber, Preformed Pipe, Type I or II: 1 inch thick.

END OF SECTION 220719

Page 55: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

DOMESTIC WATER PIPING 221116 - 1

SECTION 221116 - DOMESTIC WATER PIPING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Aboveground domestic water pipes, tubes, and fittings inside buildings.

1.2 ACTION SUBMITTALS

A. Product Data: For transition fittings and dielectric fittings.

1.3 INFORMATIONAL SUBMITTALS

A. System purging and disinfecting activities report.

B. Field quality-control reports.

1.4 FIELD CONDITIONS

A. Interruption of Existing Water Service: Do not interrupt water service to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary water service according to requirements indicated:

1. Notify Owner no fewer than two days in advance of proposed interruption of water service.

PART 2 - PRODUCTS

2.1 PIPING MATERIALS

A. Comply with requirements in "Piping Schedule" Article for applications of pipe, tube, fitting materials, and joining methods for specific services, service locations, and pipe sizes.

B. Potable-water piping and components shall comply with NSF 14 and NSF 61 Annex G.

2.2 COPPER TUBE AND FITTINGS

A. Copper Tube: ASTM B 88, Type L water tube, drawn temper.

B. Cast-Copper, Solder-Joint Fittings: ASME B16.18, pressure fittings.

Page 56: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

DOMESTIC WATER PIPING 221116 - 2

C. Wrought-Copper, Solder-Joint Fittings: ASME B16.22, wrought-copper pressure fittings.

D. Bronze Flanges: ASME B16.24, Class 150, with solder-joint ends.

E. Copper Unions:

1. MSS SP-123. 2. Cast-copper-alloy, hexagonal-stock body. 3. Ball-and-socket, metal-to-metal seating surfaces. 4. Solder-joint or threaded ends.

F. Copper Pressure-Seal-Joint Fittings: 1. Fittings for NPS 2 and Smaller: Wrought-copper fitting with EPDM-rubber, O-ring seal

in each end. 2. Fittings for NPS 2-1/2 to NPS 4: Cast-bronze or wrought-copper fitting with EPDM-

rubber, O-ring seal in each end.

G. Copper Push-on-Joint Fittings: 1. Description:

a. Cast-copper fitting complying with ASME B16.18 or wrought-copper fitting complying with ASME B 16.22.

b. Stainless-steel teeth and EPDM-rubber, O-ring seal in each end instead of solder-joint ends.

H. Copper-Tube, Extruded-Tee Connections: 1. Description: Tee formed in copper tube according to ASTM F 2014.

I. Appurtenances for Grooved-End Copper Tubing: 1. Bronze Fittings for Grooved-End, Copper Tubing: ASTM B 75 copper tube or

ASTM B 584 bronze castings. 2. Mechanical Couplings for Grooved-End Copper Tubing:

a. Copper-tube dimensions and design similar to AWWA C606. b. Ferrous housing sections. c. EPDM-rubber gaskets suitable for hot and cold water. d. Bolts and nuts. e. Minimum Pressure Rating: 300 psig.

2.3 GALVANIZED-STEEL PIPE AND FITTINGS

A. Galvanized-Steel Pipe:

1. ASTM A 53/A 53M, Standard Weight. 2. Include ends matching joining method.

B. Galvanized-Steel Pipe Nipples: ASTM A 733, made of ASTM A 53/A 53M or ASTM A 106/A 106M, Standard Weight, seamless steel pipe with threaded ends.

C. Galvanized, Gray-Iron Threaded Fittings: ASME B16.4, Class 125, standard pattern.

D. Malleable-Iron Unions:

Page 57: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

DOMESTIC WATER PIPING 221116 - 3

1. ASME B16.39, Class 150. 2. Hexagonal-stock body. 3. Ball-and-socket, metal-to-metal, bronze seating surface. 4. Threaded ends.

E. Flanges: ASME B16.1, Class 125, cast iron.

F. Appurtenances for Grooved-End, Galvanized-Steel Pipe: 1. Fittings for Grooved-End, Galvanized-Steel Pipe: Galvanized, ASTM A 47/A 47M,

malleable-iron casting; ASTM A 106/A 106M, steel pipe; or ASTM A 536, ductile-iron casting; with dimensions matching steel pipe.

2. Fittings for Grooved-End, Galvanized-Steel Pipe:

a. AWWA C606 for steel-pipe dimensions. b. Ferrous housing sections. c. EPDM-rubber gaskets suitable for hot and cold water. d. Bolts and nuts. e. Minimum Pressure Rating:

1) NPS 8 and Smaller: 600 psig.

2.4 PIPING JOINING MATERIALS

A. Pipe-Flange Gasket Materials:

1. AWWA C110/A21.10, rubber, flat face, 1/8 inch thick or ASME B16.21, nonmetallic and asbestos free unless otherwise indicated.

2. Full-face or ring type unless otherwise indicated.

B. Metal, Pipe-Flange Bolts and Nuts: ASME B18.2.1, carbon steel unless otherwise indicated.

C. Solder Filler Metals: ASTM B 32, lead-free alloys.

D. Flux: ASTM B 813, water flushable.

E. Brazing Filler Metals: AWS A5.8/A5.8M, BCuP Series, copper-phosphorus alloys for general-duty brazing unless otherwise indicated.

2.5 TRANSITION FITTINGS

A. General Requirements:

1. Same size as pipes to be joined. 2. Pressure rating at least equal to pipes to be joined. 3. End connections compatible with pipes to be joined.

B. Fitting-Type Transition Couplings: Manufactured piping coupling or specified piping system fitting.

C. Sleeve-Type Transition Coupling: AWWA C219.

Page 58: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

DOMESTIC WATER PIPING 221116 - 4

2.6 DIELECTRIC FITTINGS

A. General Requirements: Assembly of copper alloy and ferrous materials with separating nonconductive insulating material. Include end connections compatible with pipes to be joined.

B. Dielectric Unions: 1. Standard: ASSE 1079. 2. Pressure Rating: 125 psig minimum at 180 deg F. 3. End Connections: Solder-joint copper alloy and threaded ferrous.

C. Dielectric Flanges: 1. Standard: ASSE 1079. 2. Factory-fabricated, bolted, companion-flange assembly. 3. Pressure Rating: 125 psig minimum at 180 deg F. 4. End Connections: Solder-joint copper alloy and threaded ferrous; threaded solder-joint

copper alloy and threaded ferrous.

D. Dielectric-Flange Insulating Kits: 1. Nonconducting materials for field assembly of companion flanges. 2. Pressure Rating: 150 psig. 3. Gasket: Neoprene or phenolic. 4. Bolt Sleeves: Phenolic or polyethylene. 5. Washers: Phenolic with steel backing washers.

E. Dielectric Nipples: 1. Standard: IAPMO PS 66. 2. Electroplated steel nipple complying with ASTM F 1545. 3. Pressure Rating and Temperature: 300 psig at 225 deg F. 4. End Connections: Male threaded or grooved. 5. Lining: Inert and noncorrosive, propylene.

PART 3 - EXECUTION

3.1 PIPING INSTALLATION

A. Drawing plans, schematics, and diagrams indicate general location and arrangement of domestic water piping. Indicated locations and arrangements are used to size pipe and calculate friction loss, expansion, and other design considerations. Install piping as indicated unless deviations to layout are approved on coordination drawings.

B. Install shutoff valve, hose-end drain valve, strainer, pressure gage, and test tee with valve inside the building at each domestic water-service entrance.

C. Install shutoff valve immediately upstream of each dielectric fitting.

D. Install water-pressure-reducing valves downstream from shutoff valves.

E. Install domestic water piping with 0.25 percent slope downward toward drain.

Page 59: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

DOMESTIC WATER PIPING 221116 - 5

F. Rough-in domestic water piping for water-meter installation according to utility company's requirements.

G. Install piping concealed from view and protected from physical contact by building occupants unless otherwise indicated and except in equipment rooms and service areas.

H. Install piping indicated to be exposed and piping in equipment rooms and service areas at right angles or parallel to building walls. Diagonal runs are prohibited unless specifically indicated otherwise.

I. Install piping above accessible ceilings to allow sufficient space for ceiling panel removal, and coordinate with other services occupying that space.

J. Install piping to permit valve servicing.

K. Install nipples, unions, special fittings, and valves with pressure ratings the same as or higher than the system pressure rating used in applications below unless otherwise indicated.

L. Install piping free of sags and bends.

M. Install fittings for changes in direction and branch connections.

N. Install unions in copper tubing at final connection to each piece of equipment, machine, and specialty.

O. Install pressure gages on suction and discharge piping for each plumbing pump and packaged booster pump.

P. Install thermostats in hot-water circulation piping.

Q. Install thermometers on outlet piping from each water heater.

R. Install sleeves for piping penetrations of walls, ceilings, and floors.

S. Install sleeve seals for piping penetrations of concrete walls and slabs.

T. Install escutcheons for piping penetrations of walls, ceilings, and floors.

3.2 JOINT CONSTRUCTION

A. Ream ends of pipes and tubes and remove burrs. Bevel plain ends of steel pipe.

B. Remove scale, slag, dirt, and debris from inside and outside of pipes, tubes, and fittings before assembly.

C. Threaded Joints: Thread pipe with tapered pipe threads according to ASME B1.20.1. Cut threads full and clean using sharp dies. Ream threaded pipe ends to remove burrs and restore full ID. Join pipe fittings and valves as follows:

1. Apply appropriate tape or thread compound to external pipe threads.

Page 60: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

DOMESTIC WATER PIPING 221116 - 6

2. Damaged Threads: Do not use pipe or pipe fittings with threads that are corroded or damaged.

D. Brazed Joints for Copper Tubing: Comply with CDA's "Copper Tube Handbook," "Brazed Joints" chapter.

E. Soldered Joints for Copper Tubing: Apply ASTM B 813, water-flushable flux to end of tube. Join copper tube and fittings according to ASTM B 828 or CDA's "Copper Tube Handbook."

F. Pressure-Sealed Joints for Copper Tubing: Join copper tube and pressure-seal fittings with tools recommended by fitting manufacturer.

G. Push-on Joints for Copper Tubing: Clean end of tube. Measure insertion depth with manufacturer's depth gage. Join copper tube and push-on-joint fittings by inserting tube to measured depth.

H. Extruded-Tee Connections: Form tee in copper tube according to ASTM F 2014. Use tool designed for copper tube; drill pilot hole, form collar for outlet, dimple tube to form seating stop, and braze branch tube into collar.

I. Joint Construction for Grooved-End Copper Tubing: Make joints according to AWWA C606. Roll groove ends of tubes. Lubricate and install gasket over ends of tubes or tube and fitting. Install coupling housing sections over gasket with keys seated in tubing grooves. Install and tighten housing bolts.

J. Flanged Joints: Select appropriate asbestos-free, nonmetallic gasket material in size, type, and thickness suitable for domestic water service. Join flanges with gasket and bolts according to ASME B31.9.

K. Joints for Dissimilar-Material Piping: Make joints using adapters compatible with materials of both piping systems.

3.3 TRANSITION FITTING INSTALLATION

A. Install transition couplings at joints of dissimilar piping.

B. Transition Fittings in Underground Domestic Water Piping:

1. Fittings for NPS 1-1/2 and Smaller: Fitting-type coupling. 2. Fittings for NPS 2 and Larger: Sleeve-type coupling.

C. Transition Fittings in Aboveground Domestic Water Piping NPS 2 and Smaller: Plastic-to-metal transition fittings or unions.

3.4 DIELECTRIC FITTING INSTALLATION

A. Install dielectric fittings in piping at connections of dissimilar metal piping and tubing.

B. Dielectric Fittings for NPS 2 and Smaller: Use dielectric couplings or nipples.

Page 61: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

DOMESTIC WATER PIPING 221116 - 7

C. Dielectric Fittings for NPS 2-1/2 to NPS 4: Use dielectric flanges.

D. Dielectric Fittings for NPS 5 and Larger: Use dielectric flange kits.

3.5 HANGER AND SUPPORT INSTALLATION

A. Comply with requirements for pipe hanger, support products, and installation in Section 220529 "Hangers and Supports for Plumbing Piping and Equipment."

1. Vertical Piping: MSS Type 8 or 42, clamps. 2. Individual, Straight, Horizontal Piping Runs:

a. 100 Feet and Less: MSS Type 1, adjustable, steel clevis hangers. b. Longer Than 100 Feet : MSS Type 43, adjustable roller hangers. c. Longer Than 100 Feet if Indicated: MSS Type 49, spring cushion rolls.

3. Multiple, Straight, Horizontal Piping Runs 100 Feet or Longer: MSS Type 44, pipe rolls. Support pipe rolls on trapeze.

4. Base of Vertical Piping: MSS Type 52, spring hangers.

B. Support vertical piping and tubing at base and at each floor.

C. Rod diameter may be reduced one size for double-rod hangers, to a minimum of 3/8 inch.

D. Install hangers for copper tubing with the following maximum horizontal spacing and minimum rod diameters:

1. NPS 3/4 and Smaller: 60 inches with 3/8-inch rod. 2. NPS 1 and NPS 1-1/4: 72 inches with 3/8-inch rod. 3. NPS 1-1/2 and NPS 2: 96 inches with 3/8-inch rod. 4. NPS 2-1/2: 108 inches with 1/2-inch rod. 5. NPS 3 to NPS 5: 10 feet with 1/2-inch rod. 6. NPS 6: 10 feet with 5/8-inch rod. 7. NPS 8: 10 feet with 3/4-inch rod.

E. Install supports for vertical copper tubing every 10 feet.

F. Install hangers for steel piping with the following maximum horizontal spacing and minimum rod diameters:

1. NPS 1-1/4 and Smaller: 84 inches with 3/8-inch rod. 2. NPS 1-1/2: 108 inches with 3/8-inch rod. 3. NPS 2: 10 feet with 3/8-inch rod. 4. NPS 2-1/2: 11 feet with 1/2-inch rod. 5. NPS 3 and NPS 3-1/2: 12 feet with 1/2-inch rod. 6. NPS 4 and NPS 5: 12 feet with 5/8-inch rod. 7. NPS 6: 12 feet with 3/4-inch rod.

G. Install supports for vertical steel piping every 15 feet.

Page 62: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

DOMESTIC WATER PIPING 221116 - 8

H. Support piping and tubing not listed in this article according to MSS SP-69 and manufacturer's written instructions.

3.6 CONNECTIONS

A. Drawings indicate general arrangement of piping, fittings, and specialties.

B. When installing piping adjacent to equipment and machines, allow space for service and maintenance.

C. Connect domestic water piping to exterior water-service piping. Use transition fitting to join dissimilar piping materials.

D. Connect domestic water piping to water-service piping with shutoff valve; extend and connect to the following:

1. Domestic Water Booster Pumps: Cold-water suction and discharge piping. 2. Water Heaters: Cold-water inlet and hot-water outlet piping in sizes indicated, but not

smaller than sizes of water heater connections. 3. Plumbing Fixtures: Cold- and hot-water-supply piping in sizes indicated, but not smaller

than that required by plumbing code. 4. Equipment: Cold- and hot-water-supply piping as indicated, but not smaller than

equipment connections. Provide shutoff valve and union for each connection. Use flanges instead of unions for NPS 2-1/2 and larger.

3.7 IDENTIFICATION

A. Identify system components.

B. Label pressure piping with system operating pressure.

3.8 FIELD QUALITY CONTROL

A. Perform the following tests and inspections:

1. Piping Inspections:

a. Do not enclose, cover, or put piping into operation until it has been inspected and approved by authorities having jurisdiction.

b. During installation, notify authorities having jurisdiction at least one day before inspection must be made. Perform tests specified below in presence of authorities having jurisdiction:

1) Roughing-in Inspection: Arrange for inspection of piping before concealing or closing in after roughing in and before setting fixtures.

2) Final Inspection: Arrange for authorities having jurisdiction to observe tests specified in "Piping Tests" Subparagraph below and to ensure compliance with requirements.

Page 63: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

DOMESTIC WATER PIPING 221116 - 9

c. Reinspection: If authorities having jurisdiction find that piping will not pass tests or inspections, make required corrections and arrange for reinspection.

d. Reports: Prepare inspection reports and have them signed by authorities having jurisdiction.

2. Piping Tests:

a. Fill domestic water piping. Check components to determine that they are not air bound and that piping is full of water.

b. Test for leaks and defects in new piping and parts of existing piping that have been altered, extended, or repaired. If testing is performed in segments, submit a separate report for each test, complete with diagram of portion of piping tested.

c. Leave new, altered, extended, or replaced domestic water piping uncovered and unconcealed until it has been tested and approved. Expose work that was covered or concealed before it was tested.

d. Cap and subject piping to static water pressure of 50 psig above operating pressure, without exceeding pressure rating of piping system materials. Isolate test source and allow it to stand for four hours. Leaks and loss in test pressure constitute defects that must be repaired.

e. Repair leaks and defects with new materials, and retest piping or portion thereof until satisfactory results are obtained.

f. Prepare reports for tests and for corrective action required.

B. Domestic water piping will be considered defective if it does not pass tests and inspections.

C. Prepare test and inspection reports.

3.9 ADJUSTING

A. Perform the following adjustments before operation:

1. Close drain valves, hydrants, and hose bibbs. 2. Open shutoff valves to fully open position. 3. Open throttling valves to proper setting. 4. Adjust balancing valves in hot-water-circulation return piping to provide adequate flow.

a. Manually adjust ball-type balancing valves in hot-water-circulation return piping to provide hot-water flow in each branch.

b. Adjust calibrated balancing valves to flows indicated.

5. Remove plugs used during testing of piping and for temporary sealing of piping during installation.

6. Remove and clean strainer screens. Close drain valves and replace drain plugs. 7. Remove filter cartridges from housings and verify that cartridges are as specified for

application where used and are clean and ready for use. 8. Check plumbing specialties and verify proper settings, adjustments, and operation.

Page 64: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

DOMESTIC WATER PIPING 221116 - 10

3.10 CLEANING

A. Clean and disinfect potable domestic water piping as follows:

1. Purge new piping and parts of existing piping that have been altered, extended, or repaired before using.

2. Use purging and disinfecting procedures prescribed by authorities having jurisdiction; if methods are not prescribed, use procedures described in either AWWA C651 or AWWA C652 or follow procedures described below:

a. Flush piping system with clean, potable water until dirty water does not appear at outlets.

b. Fill and isolate system according to either of the following:

1) Fill system or part thereof with water/chlorine solution with at least 50 ppm of chlorine. Isolate with valves and allow to stand for 24 hours.

2) Fill system or part thereof with water/chlorine solution with at least 200 ppm of chlorine. Isolate and allow to stand for three hours.

c. Flush system with clean, potable water until no chlorine is in water coming from system after the standing time.

d. Repeat procedures if biological examination shows contamination. e. Submit water samples in sterile bottles to authorities having jurisdiction.

B. Clean non-potable domestic water piping as follows:

1. Purge new piping and parts of existing piping that have been altered, extended, or repaired before using.

2. Use purging procedures prescribed by authorities having jurisdiction or; if methods are not prescribed, follow procedures described below:

a. Flush piping system with clean, potable water until dirty water does not appear at outlets.

b. Submit water samples in sterile bottles to authorities having jurisdiction. Repeat procedures if biological examination shows contamination.

C. Prepare and submit reports of purging and disinfecting activities. Include copies of water-sample approvals from authorities having jurisdiction.

D. Clean interior of domestic water piping system. Remove dirt and debris as work progresses.

3.11 PIPING SCHEDULE

A. Transition and special fittings with pressure ratings at least equal to piping rating may be used in applications below unless otherwise indicated.

B. Flanges and unions may be used for aboveground piping joints unless otherwise indicated.

C. Fitting Option: Extruded-tee connections and brazed joints may be used on aboveground copper tubing.

Page 65: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

DOMESTIC WATER PIPING 221116 - 11

D. Aboveground domestic water piping, NPS 2 and smaller, shall be one of the following:

1. Galvanized-steel pipe and nipples; galvanized, gray-iron threaded fittings; and threaded joints.

2. Hard copper tube, ASTM B 88, Type L cast- or wrought-copper, solder-joint fittings; and soldered joints.

3. Hard copper tube, ASTM B 88, Type L copper pressure-seal-joint fittings; and pressure-sealed joints.

4. Hard copper tube, ASTM B 88, Type L copper push-on-joint fittings; and push-on joints.

E. Aboveground domestic water piping, NPS 2-1/2 to NPS 4, shall be one of the following:

1. Hard copper tube, ASTM B 88, Type L cast- or wrought-copper, solder-joint fittings; and soldered joints.

2. Hard copper tube, ASTM B 88, Type L copper pressure-seal-joint fittings; and pressure-sealed joints.

3. Hard copper tube, ASTM B 88, Type L grooved-joint, copper-tube appurtenances; and grooved joints.

4. Galvanized-steel pipe and nipples; galvanized, gray-iron threaded fittings; and threaded joints.

5. Galvanized-steel pipe; grooved-joint, galvanized-steel-pipe appurtenances; and grooved joints.

3.12 VALVE SCHEDULE

A. Drawings indicate valve types to be used. Where specific valve types are not indicated, the following requirements apply:

1. Shutoff Duty: Use ball or gate valves for piping NPS 2 and smaller. Use butterfly, ball, or gate valves with flanged ends for piping NPS 2-1/2 and larger.

2. Throttling Duty: Use ball or globe valves for piping NPS 2 and smaller. Use butterfly or ball valves with flanged ends for piping NPS 2-1/2 and larger.

3. Hot-Water Circulation Piping, Balancing Duty: Memory-stop balancing valves. 4. Drain Duty: Hose-end drain valves.

B. Use check valves to maintain correct direction of domestic water flow to and from equipment.

C. Iron grooved-end valves may be used with grooved-end piping.

END OF SECTION 221116

Page 66: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

SANITARY WASTE AND VENT PIPING 221316 - 1

SECTION 221316 - SANITARY WASTE AND VENT PIPING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Pipe, tube, and fittings. 2. Specialty pipe fittings.

1.2 PERFORMANCE REQUIREMENTS

A. Components and installation shall be capable of withstanding the following minimum working pressure unless otherwise indicated:

1. Soil, Waste, and Vent Piping: 10-foot head of water.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

1.4 INFORMATIONAL SUBMITTALS

A. Field quality-control reports.

1.5 QUALITY ASSURANCE

A. Piping materials shall bear label, stamp, or other markings of specified testing agency.

1.6 PROJECT CONDITIONS

A. Interruption of Existing Sanitary Waste Service: Do not interrupt service to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary service according to requirements indicated:

1. Notify Owner no fewer than two days in advance of proposed interruption of sanitary waste service.

Page 67: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

SANITARY WASTE AND VENT PIPING 221316 - 2

PART 2 - PRODUCTS

2.1 PIPING MATERIALS

A. Comply with requirements in "Piping Schedule" Article for applications of pipe, tube, fitting materials, and joining methods for specific services, service locations, and pipe sizes.

2.2 HUB-AND-SPIGOT, CAST-IRON SOIL PIPE AND FITTINGS

A. Pipe and Fittings: ASTM A 74, Service and Extra Heavy class(es).

B. Gaskets: ASTM C 564, rubber.

C. Calking Materials: ASTM B 29, pure lead and oakum or hemp fiber.

2.3 HUBLESS, CAST-IRON SOIL PIPE AND FITTINGS

A. Pipe and Fittings: ASTM A 888 or CISPI 301.

B. Sovent Stack Fittings: ASME B16.45 or ASSE 1043, hubless, cast-iron aerator and deaerator drainage fittings.

C. CISPI, Hubless-Piping Couplings: 1. Standards: ASTM C 1277 and CISPI 310. 2. Description: Stainless-steel corrugated shield with stainless-steel bands and tightening

devices; and ASTM C 564, rubber sleeve with integral, center pipe stop.

D. Heavy-Duty, Hubless-Piping Couplings: 1. Standards: ASTM C 1277 and ASTM C 1540. 2. Description: Stainless-steel shield with stainless-steel bands and tightening devices; and

ASTM C 564, rubber sleeve with integral, center pipe stop.

E. Cast-Iron, Hubless-Piping Couplings: 1. Standard: ASTM C 1277. 2. Description: Two-piece ASTM A 48/A 48M, cast-iron housing; stainless-steel bolts and

nuts; and ASTM C 564, rubber sleeve with integral, center pipe stop.

2.4 GALVANIZED-STEEL PIPE AND FITTINGS

A. Galvanized-Steel Pipe: ASTM A 53/A 53M, Type E, Standard Weight class. Include square-cut-grooved or threaded ends matching joining method.

B. Cast-Iron Drainage Fittings: ASME B16.12, threaded.

C. Steel Pipe Pressure Fittings:

Page 68: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

SANITARY WASTE AND VENT PIPING 221316 - 3

1. Galvanized-Steel Pipe Nipples: ASTM A 733, made of ASTM A 53/A 53M or ASTM A 106/A 106M, Schedule 40, seamless steel pipe. Include ends matching joining method.

2. Malleable-Iron Unions: ASME B16.39; Class 150; hexagonal-stock body with ball-and-socket, metal-to-metal, bronze seating surface; and female threaded ends.

3. Gray-Iron, Threaded Fittings: ASME B16.4, Class 125, standard pattern.

D. Cast-Iron Flanges: ASME B16.1, Class 125.

1. Flange Gasket Materials: ASME B16.21, full-face, flat, nonmetallic, asbestos-free, 1/8-inch maximum thickness unless thickness or specific material is indicated.

2. Flange Bolts and Nuts: ASME B18.2.1, carbon steel unless otherwise indicated.

E. Grooved-Joint, Galvanized-Steel-Pipe Appurtenances: 1. Galvanized, Grooved-End Fittings for Galvanized-Steel Piping: ASTM A 536 ductile-

iron castings, ASTM A 47/A 47M malleable-iron castings, ASTM A 234/A 234M forged steel fittings, or ASTM A 106/A 106M steel pipes with dimensions matching ASTM A 53/A 53M steel pipe, and complying with AWWA C606 for grooved ends.

2. Grooved Mechanical Couplings for Galvanized-Steel Piping: ASTM F 1476, Type I. Include ferrous housing sections with continuous curved keys; EPDM-rubber gasket suitable for hot and cold water; and bolts and nuts.

2.5 DUCTILE-IRON PIPE AND FITTINGS

A. Ductile-Iron, Mechanical-Joint Piping:

1. Ductile-Iron Pipe: AWWA C151/A21.51, with mechanical-joint bell and plain spigot end unless grooved or flanged ends are indicated.

2. Ductile-Iron Fittings: AWWA C110/A21.10, mechanical-joint, ductile- or gray-iron standard pattern or AWWA C153/A21.53, ductile-iron compact pattern.

3. Glands, Gaskets, and Bolts: AWWA C111/A21.11, ductile- or gray-iron glands, rubber gaskets, and steel bolts.

B. Ductile-Iron, Push-on-Joint Piping:

1. Ductile-Iron Pipe: AWWA C151/A21.51, with push-on-joint bell and plain spigot end unless grooved or flanged ends are indicated.

2. Ductile-Iron Fittings: AWWA C110/A21.10, push-on-joint ductile- or gray-iron standard pattern or AWWA C153/A21.53, ductile-iron compact pattern.

3. Gaskets: AWWA C111/A21.11, rubber.

C. Ductile-Iron, Grooved-Joint Piping:

1. Ductile-Iron Pipe: AWWA C151/A21.51 with round-cut-grooved ends according to AWWA C606.

2. Ductile-Iron-Pipe Appurtenances: a. Grooved-End, Ductile-Iron Fittings: ASTM A 536 ductile-iron castings with

dimensions matching AWWA C110/A 21.10 ductile-iron pipe or AWWA C153/A 21.53 ductile-iron fittings and complying with AWWA C606 for grooved ends.

Page 69: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

SANITARY WASTE AND VENT PIPING 221316 - 4

b. Grooved Mechanical Couplings for Ductile-Iron Pipe: ASTM F 1476, Type I. Include ferrous housing sections with continuous curved keys; EPDM-rubber center-leg gasket suitable for hot and cold water; and bolts and nuts.

2.6 COPPER TUBE AND FITTINGS

A. Copper DWV Tube: ASTM B 306, drainage tube, drawn temper.

B. Copper Drainage Fittings: ASME B16.23, cast copper or ASME B16.29, wrought copper, solder-joint fittings.

C. Copper Tube: ASTM B 88, Type L.

D. Copper Pressure Fittings:

1. Copper Fittings: ASME B16.18, cast-copper-alloy or ASME B16.22, wrought-copper, solder-joint fittings. Furnish wrought-copper fittings if indicated.

2. Copper Unions: MSS SP-123, copper-alloy, hexagonal-stock body with ball-and-socket, metal-to-metal seating surfaces, and solder-joint or threaded ends.

E. Copper Flanges: ASME B16.24, Class 150, cast copper with solder-joint end.

1. Flange Gasket Materials: ASME B16.21, full-face, flat, nonmetallic, asbestos-free, 1/8-inch maximum thickness unless thickness or specific material is indicated.

2. Flange Bolts and Nuts: ASME B18.2.1, carbon steel unless otherwise indicated.

F. Solder: ASTM B 32, lead free with ASTM B 813, water-flushable flux.

2.7 SPECIALTY PIPE FITTINGS

A. Transition Couplings:

1. General Requirements: Fitting or device for joining piping with small differences in OD's or of different materials. Include end connections same size as and compatible with pipes to be joined.

2. Fitting-Type Transition Couplings: Manufactured piping coupling or specified piping system fitting.

3. Unshielded, Nonpressure Transition Couplings: a. Standard: ASTM C 1173. b. Description: Elastomeric, sleeve-type, reducing or transition pattern. Include shear

ring and corrosion-resistant-metal tension band and tightening mechanism on each end.

c. Sleeve Materials:

1) For Cast-Iron Soil Pipes: ASTM C 564, rubber. 2) For Plastic Pipes: ASTM F 477, elastomeric seal or ASTM D 5926, PVC. 3) For Dissimilar Pipes: ASTM D 5926, PVC or other material compatible

with pipe materials being joined.

4. Shielded, Nonpressure Transition Couplings:

Page 70: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

SANITARY WASTE AND VENT PIPING 221316 - 5

a. Standard: ASTM C 1460. b. Description: Elastomeric or rubber sleeve with full-length, corrosion-resistant

outer shield and corrosion-resistant-metal tension band and tightening mechanism on each end.

5. Pressure Transition Couplings: a. Standard: AWWA C219. b. Description: Metal, sleeve-type same size as, with pressure rating at least equal to,

and ends compatible with, pipes to be joined. c. Center-Sleeve Material: Manufacturer's standard. d. Gasket Material: Natural or synthetic rubber. e. Metal Component Finish: Corrosion-resistant coating or material.

B. Dielectric Fittings:

1. General Requirements: Assembly of copper alloy and ferrous materials with separating nonconductive insulating material. Include end connections compatible with pipes to be joined.

2. Dielectric Unions: a. Description:

1) Standard: ASSE 1079. 2) Pressure Rating: 125 psig minimum at 180 deg F. 3) End Connections: Solder-joint copper alloy and threaded ferrous.

3. Dielectric Flanges: a. Description:

1) Standard: ASSE 1079. 2) Factory-fabricated, bolted, companion-flange assembly. 3) Pressure Rating: 125 psig minimum at 180 deg F. 4) End Connections: Solder-joint copper alloy and threaded ferrous; threaded

solder-joint copper alloy and threaded ferrous.

4. Dielectric-Flange Insulating Kits: a. Description:

1) Nonconducting materials for field assembly of companion flanges. 2) Pressure Rating: 150 psig. 3) Gasket: Neoprene or phenolic. 4) Bolt Sleeves: Phenolic or polyethylene. 5) Washers: Phenolic with steel backing washers.

5. Dielectric Nipples: a. Description:

1) Standard: IAPMO PS 66 2) Electroplated steel nipple. 3) Pressure Rating: 300 psig at 225 deg F. 4) End Connections: Male threaded or grooved. 5) Lining: Inert and noncorrosive, propylene.

Page 71: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

SANITARY WASTE AND VENT PIPING 221316 - 6

PART 3 - EXECUTION

3.1 PIPING INSTALLATION

A. Drawing plans, schematics, and diagrams indicate general location and arrangement of piping systems. Indicated locations and arrangements were used to size pipe and calculate friction loss, expansion, pump sizing, and other design considerations. Install piping as indicated unless deviations to layout are approved on coordination drawings.

B. Install piping in concealed locations unless otherwise indicated and except in equipment rooms and service areas.

C. Install piping indicated to be exposed and piping in equipment rooms and service areas at right angles or parallel to building walls. Diagonal runs are prohibited unless specifically indicated otherwise.

D. Install piping above accessible ceilings to allow sufficient space for ceiling panel removal.

E. Install piping to permit valve servicing.

F. Install piping at indicated slopes.

G. Install piping free of sags and bends.

H. Install fittings for changes in direction and branch connections.

I. Install piping to allow application of insulation.

J. Install seismic restraints on piping.

K. Make changes in direction for soil and waste drainage and vent piping using appropriate branches, bends, and long-sweep bends. Sanitary tees and short-sweep 1/4 bends may be used on vertical stacks if change in direction of flow is from horizontal to vertical. Use long-turn, double Y-branch and 1/8-bend fittings if two fixtures are installed back to back or side by side with common drain pipe. Straight tees, elbows, and crosses may be used on vent lines. Do not change direction of flow more than 90 degrees. Use proper size of standard increasers and reducers if pipes of different sizes are connected. Reducing size of drainage piping in direction of flow is prohibited.

L. Lay buried building drainage piping beginning at low point of each system. Install true to grades and alignment indicated, with unbroken continuity of invert. Place hub ends of piping upstream. Install required gaskets according to manufacturer's written instructions for use of lubricants, cements, and other installation requirements. Maintain swab in piping and pull past each joint as completed.

M. Install soil and waste drainage and vent piping at the following minimum slopes unless otherwise indicated:

1. Building Sanitary Drain: 2 percent downward in direction of flow for piping NPS 3 and smaller; 1 percent downward in direction of flow for piping NPS 4 and larger.

2. Horizontal Sanitary Drainage Piping: 2 percent downward in direction of flow.

Page 72: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

SANITARY WASTE AND VENT PIPING 221316 - 7

3. Vent Piping: 1 percent down toward vertical fixture vent or toward vent stack.

N. Install cast-iron soil piping according to CISPI's "Cast Iron Soil Pipe and Fittings Handbook," Chapter IV, "Installation of Cast Iron Soil Pipe and Fittings."

1. Install encasement on underground piping according to ASTM A 674 or AWWA C105/A 21.5.

O. Install steel piping according to applicable plumbing code.

P. Install aboveground copper tubing according to CDA's "Copper Tube Handbook."

Q. Install engineered soil and waste drainage and vent piping systems as follows:

1. Combination Waste and Vent: Comply with standards of authorities having jurisdiction. 2. Sovent Drainage System: Comply with ASSE 1043 and sovent fitting manufacturer's

written installation instructions. 3. Reduced-Size Venting: Comply with standards of authorities having jurisdiction.

R. Install underground, ductile-iron, force-main piping according to AWWA C600. Install buried piping inside building between wall and floor penetrations and connection to sanitary sewer piping outside building with restrained joints. Anchor pipe to wall or floor. Install thrust-block supports at vertical and horizontal offsets.

1. Install encasement on piping according to ASTM A 674 or AWWA C105/A 21.5.

S. Install underground, copper, force-main tubing according to CDA's "Copper Tube Handbook."

1. Install encasement on piping according to ASTM A 674 or AWWA C105/A 21.5.

T. Install force mains at elevations indicated.

U. Plumbing Specialties:

1. Install backwater valves in sanitary waster gravity-flow piping. 2. Install cleanouts at grade and extend to where building sanitary drains connect to building

sanitary sewers in sanitary drainage gravity-flow piping. Install cleanout fitting with closure plug inside the building in sanitary drainage force-main piping.

3. Install drains in sanitary drainage gravity-flow piping.

V. Do not enclose, cover, or put piping into operation until it is inspected and approved by authorities having jurisdiction.

W. Install sleeves for piping penetrations of walls, ceilings, and floors.

X. Install sleeve seals for piping penetrations of concrete walls and slabs.

Y. Install escutcheons for piping penetrations of walls, ceilings, and floors.

Page 73: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

SANITARY WASTE AND VENT PIPING 221316 - 8

3.2 JOINT CONSTRUCTION

A. Join hub-and-spigot, cast-iron soil piping with gasket joints according to CISPI's "Cast Iron Soil Pipe and Fittings Handbook" for compression joints.

B. Join hub-and-spigot, cast-iron soil piping with calked joints according to CISPI's "Cast Iron Soil Pipe and Fittings Handbook" for lead-and-oakum calked joints.

C. Join hubless, cast-iron soil piping according to CISPI 310 and CISPI's "Cast Iron Soil Pipe and Fittings Handbook" for hubless-piping coupling joints.

D. Threaded Joints: Thread pipe with tapered pipe threads according to ASME B1.20.1. Cut threads full and clean using sharp dies. Ream threaded pipe ends to remove burrs and restore full ID. Join pipe fittings and valves as follows:

1. Apply appropriate tape or thread compound to external pipe threads unless dry seal threading is specified.

2. Damaged Threads: Do not use pipe or pipe fittings with threads that are corroded or damaged. Do not use pipe sections that have cracked or open welds.

E. Join stainless-steel pipe and fittings with gaskets according to ASME A112.3.1.

F. Join copper tube and fittings with soldered joints according to ASTM B 828. Use ASTM B 813, water-flushable, lead-free flux and ASTM B 32, lead-free-alloy solder.

G. Grooved Joints: Cut groove ends of pipe according to AWWA C606. Lubricate and install gasket over ends of pipes or pipe and fitting. Install coupling housing sections, over gasket, with keys seated in piping grooves. Install and tighten housing bolts.

H. Flanged Joints: Align bolt holes. Select appropriate gasket material, size, type, and thickness. Install gasket concentrically positioned. Use suitable lubricants on bolt threads. Torque bolts in cross pattern.

3.3 SPECIALTY PIPE FITTING INSTALLATION

A. Transition Couplings:

1. Install transition couplings at joints of piping with small differences in OD's. 2. In Drainage Piping: Unshielded, nonpressure transition couplings.

B. Dielectric Fittings:

1. Install dielectric fittings in piping at connections of dissimilar metal piping and tubing. 2. Dielectric Fittings for NPS 2 and Smaller: Use dielectric unions. 3. Dielectric Fittings for NPS 2-1/2 to NPS 4: Use dielectric flanges. 4. Dielectric Fittings for NPS 5 and Larger: Use dielectric flange kits.

3.4 VALVE INSTALLATION

A. Shutoff Valves:

Page 74: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

SANITARY WASTE AND VENT PIPING 221316 - 9

1. Install shutoff valve on each sewage pump discharge. 2. Install gate or full-port ball valve for piping NPS 2 and smaller. 3. Install gate valve for piping NPS 2-1/2 and larger.

B. Check Valves: Install swing check valve, between pump and shutoff valve, on each sewage pump discharge.

C. Backwater Valves: Install backwater valves in piping subject to backflow.

1. Horizontal Piping: Horizontal backwater valves. Use normally closed type unless otherwise indicated.

2. Floor Drains: Drain outlet backwater valves unless drain has integral backwater valve. 3. Install backwater valves in accessible locations.

3.5 HANGER AND SUPPORT INSTALLATION

A. Comply with the following requirements for pipe hanger and support devices and installation.

1. Install carbon-steel pipe hangers for horizontal piping in noncorrosive environments. 2. Install carbon-steel pipe support clamps for vertical piping in noncorrosive environments. 3. Vertical Piping: MSS Type 8 or Type 42, clamps. 4. Install individual, straight, horizontal piping runs:

a. 100 Feet and Less: MSS Type 1, adjustable, steel clevis hangers. b. Longer Than 100 Feet: MSS Type 43, adjustable roller hangers. c. Longer Than 100 Feet if Indicated: MSS Type 49, spring cushion rolls.

5. Multiple, Straight, Horizontal Piping Runs 100 Feet or Longer: MSS Type 44, pipe rolls. Support pipe rolls on trapeze.

6. Base of Vertical Piping: MSS Type 52, spring hangers.

B. Support horizontal piping and tubing within 12 inches of each fitting valve, and coupling.

C. Support vertical piping and tubing at base and at each floor.

D. Rod diameter may be reduced one size for double-rod hangers, with 3/8-inch minimum rods.

E. Install hangers for cast-iron soil piping with the following maximum horizontal spacing and minimum rod diameters:

1. NPS 1-1/2 and NPS 2: 60 inches with 3/8-inch rod. 2. NPS 3: 60 inches with 1/2-inch rod. 3. NPS 4 and NPS 5: 60 inches with 5/8-inch rod. 4. NPS 6 and NPS 8: 60 inches with 3/4-inch rod. 5. Spacing for 10-foot lengths may be increased to 10 feet. Spacing for fittings is limited to

60 inches.

F. Install supports for vertical cast-iron soil piping every 15 feet.

G. Install hangers for steel piping with the following maximum horizontal spacing and minimum rod diameters:

Page 75: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

SANITARY WASTE AND VENT PIPING 221316 - 10

1. NPS 1-1/4: 84 inches with 3/8-inch rod. 2. NPS 1-1/2: 108 inche with 3/8-inch rod. 3. NPS 2: 10 feet with 3/8-inch rod. 4. NPS 2-1/2: 11 feet with 1/2-inch rod. 5. NPS 3: 12 feet with 1/2-inch rod. 6. NPS 4 and NPS 5: 12 feet with 5/8-inch rod. 7. NPS 6 and NPS 8: 12 feet with 3/4-inch rod.

H. Install supports for vertical steel piping every 15 feet.

I. Install hangers for copper tubing with the following maximum horizontal spacing and minimum rod diameters:

1. NPS 1-1/4: 72 inches with 3/8-inch rod. 2. NPS 1-1/2 and NPS 2: 96 inches with 3/8-inch rod. 3. NPS 2-1/2: 108 inches with 1/2-inch rod. 4. NPS 3 and NPS 5: 10 feet with 1/2-inch rod. 5. NPS 6: 10 feet with 5/8-inch rod. 6. NPS 8: 10 feet with 3/4-inch rod.

J. Install supports for vertical copper tubing every 10 feet.

K. Support piping and tubing not listed above according to MSS SP-69 and manufacturer's written instructions.

3.6 CONNECTIONS

A. Drawings indicate general arrangement of piping, fittings, and specialties.

B. Connect soil and waste piping to exterior sanitary sewerage piping. Use transition fitting to join dissimilar piping materials.

C. Connect drainage and vent piping to the following:

1. Plumbing Fixtures: Connect drainage piping in sizes indicated, but not smaller than required by plumbing code.

2. Plumbing Fixtures and Equipment: Connect atmospheric vent piping in sizes indicated, but not smaller than required by authorities having jurisdiction.

3. Plumbing Specialties: Connect drainage and vent piping in sizes indicated, but not smaller than required by plumbing code.

4. Install test tees (wall cleanouts) in conductors near floor and floor cleanouts with cover flush with floor.

5. Install horizontal backwater valves with cleanout cover flush with floor. 6. Equipment: Connect drainage piping as indicated. Provide shutoff valve if indicated and

union for each connection. Use flanges instead of unions for connections NPS 2-1/2 and larger.

D. Where installing piping adjacent to equipment, allow space for service and maintenance of equipment.

Page 76: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

SANITARY WASTE AND VENT PIPING 221316 - 11

E. Make connections according to the following unless otherwise indicated:

1. Install unions, in piping NPS 2 and smaller, adjacent to each valve and at final connection to each piece of equipment.

2. Install flanges, in piping NPS 2-1/2 and larger, adjacent to flanged valves and at final connection to each piece of equipment.

3.7 IDENTIFICATION

A. Identify exposed sanitary waste and vent piping.

3.8 FIELD QUALITY CONTROL

A. During installation, notify authorities having jurisdiction at least 24 hours before inspection must be made. Perform tests specified below in presence of authorities having jurisdiction.

1. Roughing-in Inspection: Arrange for inspection of piping before concealing or closing-in after roughing-in and before setting fixtures.

2. Final Inspection: Arrange for final inspection by authorities having jurisdiction to observe tests specified below and to ensure compliance with requirements.

B. Reinspection: If authorities having jurisdiction find that piping will not pass test or inspection, make required corrections and arrange for reinspection.

C. Reports: Prepare inspection reports and have them signed by authorities having jurisdiction.

D. Test sanitary drainage and vent piping according to procedures of authorities having jurisdiction or, in absence of published procedures, as follows:

1. Test for leaks and defects in new piping and parts of existing piping that have been altered, extended, or repaired. If testing is performed in segments, submit separate report for each test, complete with diagram of portion of piping tested.

2. Leave uncovered and unconcealed new, altered, extended, or replaced drainage and vent piping until it has been tested and approved. Expose work that was covered or concealed before it was tested.

3. Roughing-in Plumbing Test Procedure: Test drainage and vent piping except outside leaders on completion of roughing-in. Close openings in piping system and fill with water to point of overflow, but not less than 10-foot head of water. From 15 minutes before inspection starts to completion of inspection, water level must not drop. Inspect joints for leaks.

4. Finished Plumbing Test Procedure: After plumbing fixtures have been set and traps filled with water, test connections and prove they are gastight and watertight. Plug vent-stack openings on roof and building drains where they leave building. Introduce air into piping system equal to pressure of 1-inch wg. Use U-tube or manometer inserted in trap of water closet to measure this pressure. Air pressure must remain constant without introducing additional air throughout period of inspection. Inspect plumbing fixture connections for gas and water leaks.

5. Repair leaks and defects with new materials and retest piping, or portion thereof, until satisfactory results are obtained.

Page 77: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

SANITARY WASTE AND VENT PIPING 221316 - 12

6. Prepare reports for tests and required corrective action.

E. Test force-main piping according to procedures of authorities having jurisdiction or, in absence of published procedures, as follows:

1. Leave uncovered and unconcealed new, altered, extended, or replaced force-main piping until it has been tested and approved. Expose work that was covered or concealed before it was tested.

2. Cap and subject piping to static-water pressure of 50 psig above operating pressure, without exceeding pressure rating of piping system materials. Isolate test source and allow to stand for four hours. Leaks and loss in test pressure constitute defects that must be repaired.

3. Repair leaks and defects with new materials and retest piping, or portion thereof, until satisfactory results are obtained.

4. Prepare reports for tests and required corrective action.

3.9 CLEANING AND PROTECTION

A. Clean interior of piping. Remove dirt and debris as work progresses.

B. Protect drains during remainder of construction period to avoid clogging with dirt and debris and to prevent damage from traffic and construction work.

C. Place plugs in ends of uncompleted piping at end of day and when work stops.

3.10 PIPING SCHEDULE

A. Flanges and unions may be used on aboveground pressure piping unless otherwise indicated.

B. Aboveground, soil and waste piping NPS 4 and smaller shall be any of the following:

1. Service class, cast-iron soil pipe and fittings; gaskets; and gasketed joints. 2. Hubless, cast-iron soil pipe and fittings and sovent stack fittings; heavy-duty hubless-

piping couplings; and coupled joints. 3. Galvanized-steel pipe, drainage fittings, and threaded joints. 4. Copper DWV tube, copper drainage fittings, and soldered joints. 5. Dissimilar Pipe-Material Couplings: Unshielded, nonpressure transition couplings.

C. Aboveground, soil and waste piping NPS 5 and larger shall be any o] the following:

1. Service class, cast-iron soil pipe and fittings; gaskets; and gasketed joints. 2. Hubless, cast-iron soil pipe and fittings and sovent stack fittings; heavy-duty hubless-

piping couplings; and coupled joints. 3. Galvanized-steel pipe, drainage fittings, and threaded joints. 4. Dissimilar Pipe-Material Couplings: Unshielded, nonpressure transition couplings.

D. Aboveground, vent piping NPS 4 and smaller shall be any of the following:

1. Service class, cast-iron soil pipe and fittings; gaskets; and gasketed joints.

Page 78: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

SANITARY WASTE AND VENT PIPING 221316 - 13

2. Hubless, cast-iron soil pipe and fittings; heavy-duty hubless-piping couplings; and coupled joints.

3. Galvanized-steel pipe, drainage fittings, and threaded joints. 4. Copper DWV tube, copper drainage fittings, and soldered joints.

a. Option for Vent Piping, NPS 2-1/2 and NPS 3-1/2: Hard copper tube, Type M; copper pressure fittings; and soldered joints.

5. Dissimilar Pipe-Material Couplings: Unshielded, nonpressure transition couplings.

E. Aboveground, vent piping NPS 5 and larger shall be any of the following:

1. Service class, cast-iron soil pipe and fittings; gaskets; and gasketed joints. 2. Hubless, cast-iron soil pipe and fittings; heavy-duty hubless-piping couplings; and

coupled joints. 3. Galvanized-steel pipe, drainage fittings, and threaded joints. 4. Dissimilar Pipe-Material Couplings: Unshielded, nonpressure transition couplings.

END OF SECTION 221316

Page 79: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

SANITARY WASTE PIPING SPECIALTIES 221319 - 1

SECTION 221319 - SANITARY WASTE PIPING SPECIALTIES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: 1. Floor drains.

1.2 SUBMITTALS

A. Operation and Maintenance Data: For drainage piping specialties to include in emergency, operation, and maintenance manuals.

1.3 QUALITY ASSURANCE

A. Drainage piping specialties shall bear label, stamp, or other markings of specified testing agency.

PART 2 - PRODUCTS

2.1 FLOOR DRAINS

A. Cast-Iron Floor Drains: 1. Standard: ASME A112.6.3. 2. Pattern: Floor drain. 3. Body Material: Gray iron. 4. Outlet: Bottom. 5. Top or Strainer Material: Bronze. 6. Top of Body and Strainer Finish: bronze. 7. Top Shape: Round. 8. Top Loading Classification: Medium Duty.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Install floor drains at low points of surface areas to be drained. Set grates of drains flush with finished floor, unless otherwise indicated.

1. Position floor drains for easy access and maintenance. 2. Set floor drains below elevation of surrounding finished floor to allow floor drainage. Set

with grates depressed according to the following drainage area radii:

Page 80: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

SANITARY WASTE PIPING SPECIALTIES 221319 - 2

a. Radius, 30 Inches or Less: Equivalent to 1 percent slope, but not less than 1/4-inch total depression.

b. Radius, 30 to 60 Inches: Equivalent to 1 percent slope. c. Radius, 60 Inches or Larger: Equivalent to 1 percent slope, but not greater than 1-

inch total depression.

3. Install floor-drain flashing collar or flange so no leakage occurs between drain and adjoining flooring. Maintain integrity of waterproof membranes where penetrated.

4. Install individual traps for floor drains connected to sanitary building drain, unless otherwise indicated.

3.2 PROTECTION

A. Protect drains during remainder of construction period to avoid clogging with dirt or debris and to prevent damage from traffic or construction work.

B. Place plugs in ends of uncompleted piping at end of each day or when work stops.

END OF SECTION 221319

Page 81: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

DOMESTIC-WATER HEAT EXCHANGERS 223500 - 1

SECTION 223500 - DOMESTIC-WATER HEAT EXCHANGERS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Circulating, compact, domestic-water heat exchangers.

1.2 ACTION SUBMITTALS

A. Product Data: For each type and size of domestic-water heat exchanger indicated. Include rated capacities, operating characteristics, electrical characteristics, and furnished specialties and accessories.

B. Shop Drawings:

1. Wiring Diagrams: For power, signal, and control wiring.

1.3 INFORMATIONAL SUBMITTALS

A. Product Certificates: For circulating, domestic-water heat exchanger, from manufacturer.

B. Domestic-Water, Heat-Exchanger Labeling: Certified and labeled by testing agency acceptable to authorities having jurisdiction.

C. Field quality-control reports.

D. Warranty: Sample of special warranty.

1.4 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For domestic-water heat exchangers to include in emergency, operation, and maintenance manuals.

1.5 QUALITY ASSURANCE

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. ASME Compliance: Where ASME-code construction is indicated, fabricate and label heat-exchanger to comply with ASME Boiler and Pressure Vessel Code: Section VIII, Division 1.

Page 82: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

DOMESTIC-WATER HEAT EXCHANGERS 223500 - 2

C. NSF Compliance: Fabricate and label equipment components that will be in contact with potable water to comply with NSF 61, "Drinking Water System Components - Health Effects."

1.6 COORDINATION

A. Coordinate sizes and locations of concrete bases with actual equipment provided.

1.7 WARRANTY

A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace components of domestic-water heat exchangers that fail in materials or workmanship within specified warranty period.

1. Failures include, but are not limited to, the following:

a. Structural failures including heat exchanger, and supports. b. Faulty operation of controls. c. Deterioration of metals, metal finishes, and other materials beyond normal use.

2. Warranty Periods: From date of Substantial Completion.

a. Circulating, Storage, Domestic-Water Heat Exchangers:

1) Tube Bundle: Ten years. 2) Pressure Vessel: 20 years. 3) Controls: 20 years.

PART 2 - PRODUCTS

2.1 CIRCULATING, DOMESTIC-WATER HEAT EXCHANGERS

A. Circulating, Compact, Domestic-Water Heat Exchangers:

1. Description: Packaged, large-capacity, hot-water heat-exchanger; steam coil; circulator; controls; and specialties for heating domestic water with steam in coil.

2. Flow Pattern: Standard-flow arrangement, with circulated across heat-exchanger coil and returned to heater. Include hot-water outlet located at top of tank and temperature sensor in shell.

3. Construction: ASME-code 150-psig working-pressure rating.

a. Configuration: Horizontal. b. Materials of Construction:

1) Shell: 90/10 Copper-Nickel. 2) Tubes: 90/10 Copper-Nickel, single-wall. 3) Tube Sheet: Solid copper alloy. 4) Baffles: Teflon. 5) Shell Connections: Solid copper alloy.

Page 83: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

DOMESTIC-WATER HEAT EXCHANGERS 223500 - 3

c. Insulation: Complying with ASHRAE/IESNA 90.1.

4. Temperature Control: The controls continuously monitor heating demand to exact proportions of hot water requirements and regulates the hot water outlet temperature to a close tolerance of plus-or-minus 4 degrees F of set point, even with sudden fluctuating draws.

5. Safety Control: The unit is protected by a double solenoid temperature limit system with a hot water dump valve. Should any overheating occur, the temperature limit system immediately shuts off the heat source and dumps overheated water down the drain.

6. Relief Valves: ASME rated and stamped for combination temperature-and-pressure relief valves. Set at 150 PSIG and 210F.

7. Gages: Factory-mounted thermometer and pressure gage. 8. Circulating Pump: UL 778, all-bronze, centrifugal. 9. Energy Management System Interface: Normally closed dry contacts for enabling and

disabling heat exchanger.

PART 3 - EXECUTION

3.1 DOMESTIC-WATER, HEAT-EXCHANGER INSTALLATION

A. Install domestic-water heat exchangers level and plumb, according to layout drawings, original design, and referenced standards. Maintain manufacturer's recommended clearances. Arrange units so controls and devices needing service are accessible.

1. Install shutoff valves on domestic-water-supply piping to heat exchangers and on domestic-hot-water outlet piping.

2. Install shutoff valves on steam and condensate piping to heat exchangers.

B. Install temperature and pressure relief valves. Extend relief-valve outlet, with drain piping same as domestic-water piping in continuous downward pitch, and discharge by positive air gap onto closest floor drain.

C. Install heat-exchanger drain piping as indirect waste to spill by positive air gap into open drains or over floor drains. Install hose-end drain valves at low points.

D. Fill domestic-water heat exchangers with water.

3.2 FIELD QUALITY CONTROL

A. Perform tests and inspections.

1. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect components, assemblies, and equipment installations, including connections, and to assist in testing.

2. Leak Test: After installation, charge system and test for leaks. Repair leaks and retest until no leaks exist.

3. Operational Test: After electrical circuitry has been energized, start units to confirm proper operation.

Page 84: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

DOMESTIC-WATER HEAT EXCHANGERS 223500 - 4

4. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment.

B. Domestic-water heat exchangers will be considered defective if they do not pass tests and inspections. Prepare test and inspection reports.

3.3 DEMONSTRATION

A. Train Owner's maintenance personnel to adjust, operate, and maintain domestic-water heat exchangers.

END OF SECTION 223500

Page 85: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

HVAC PIPING INSULATION 230719 - 1

SECTION 230719 - HVAC PIPING INSULATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes insulating the following HVAC piping systems: 1. Steam and steam condensate piping, indoors.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product indicated. Include thermal conductivity, water-vapor permeance thickness, and jackets (both factory and field applied if any).

1.3 INFORMATIONAL SUBMITTALS

A. Qualification Data: For qualified Installer.

B. Material Test Reports: From a qualified testing agency acceptable to authorities having jurisdiction indicating, interpreting, and certifying test results for compliance of insulation materials, sealers, attachments, cements, and jackets, with requirements indicated. Include dates of tests and test methods employed.

C. Field quality-control reports.

1.4 QUALITY ASSURANCE

A. Installer Qualifications: Skilled mechanics who have successfully completed an apprenticeship program or another craft training program certified by the Department of Labor, Bureau of Apprenticeship and Training.

B. Surface-Burning Characteristics: For insulation and related materials, as determined by testing identical products according to ASTM E 84, by a testing and inspecting agency acceptable to authorities having jurisdiction. Factory label insulation and jacket materials and adhesive, mastic, tapes, and cement material containers, with appropriate markings of applicable testing agency.

1. Insulation Installed Indoors: Flame-spread index of 25 or less, and smoke-developed index of 50 or less.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Packaging: Insulation material containers shall be marked by manufacturer with appropriate ASTM standard designation, type and grade, and maximum use temperature.

Page 86: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

HVAC PIPING INSULATION 230719 - 2

1.6 COORDINATION

A. Coordinate sizes and locations of supports, hangers, and insulation shields.

B. Coordinate clearance requirements with piping Installer for piping insulation application. Before preparing piping Shop Drawings, establish and maintain clearance requirements for installation of insulation and field-applied jackets and finishes and for space required for maintenance.

C. Coordinate installation and testing of heat tracing.

1.7 SCHEDULING

A. Schedule insulation application after pressure testing systems and, where required, after installing and testing heat tracing. Insulation application may begin on segments that have satisfactory test results.

B. Complete installation and concealment of plastic materials as rapidly as possible in each area of construction.

PART 2 - PRODUCTS

2.1 INSULATION MATERIALS

A. Comply with requirements in "Piping Insulation Schedule, General," "Indoor Piping Insulation Schedule," "Outdoor, Aboveground Piping Insulation Schedule," and "Outdoor, Underground Piping Insulation Schedule" articles for where insulating materials shall be applied.

B. Products shall not contain asbestos, lead, mercury, or mercury compounds.

C. Products that come in contact with stainless steel shall have a leachable chloride content of less than 50 ppm when tested according to ASTM C 871.

D. Insulation materials for use on austenitic stainless steel shall be qualified as acceptable according to ASTM C 795.

E. Mineral-Fiber, Preformed Pipe Insulation:

1. Type I, 850 deg F Materials: Mineral or glass fibers bonded with a thermosetting resin. Comply with ASTM C 547, Type I, Grade A, with factory-applied ASJ-SSL. Factory-applied jacket requirements are specified in "Factory-Applied Jackets" Article.

F. Mineral-Fiber, Pipe and Tank Insulation: Mineral or glass fibers bonded with a thermosetting resin. Semirigid board material with factory-applied ASJ]complying with ASTM C 1393, Type II or Type IIIA Category 2, or with properties similar to ASTM C 612, Type IB. Nominal density is 2.5 lb/cu. ft or more. Thermal conductivity (k-value) at 100 deg F is 0.29 Btu x in./h x sq. ft. x deg F or less. Factory-applied jacket requirements are specified in "Factory-Applied Jackets" Article.

Page 87: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

HVAC PIPING INSULATION 230719 - 3

2.2 INSULATING CEMENTS

A. Mineral-Fiber Insulating Cement: Comply with ASTM C 195.

2.3 ADHESIVES

A. Materials shall be compatible with insulation materials, jackets, and substrates and for bonding insulation to itself and to surfaces to be insulated unless otherwise indicated.

B. Mineral-Fiber Adhesive: Comply with MIL-A-3316C, Class 2, Grade A.

1. For indoor applications, adhesive shall have a VOC content of 80 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24).

2. Adhesive shall comply with the testing and product requirements of the California Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers."

2.4 MASTICS

A. Materials shall be compatible with insulation materials, jackets, and substrates; comply with MIL-PRF-19565C, Type II.

1. For indoor applications, use mastics that have a VOC content of 50 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24).

2.5 LAGGING ADHESIVES

A. Description: Comply with MIL-A-3316C, Class I, Grade A and shall be compatible with insulation materials, jackets, and substrates.

1. For indoor applications, use lagging adhesives that have a VOC content of 50 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24).

2. Fire-resistant, water-based lagging adhesive and coating for use indoors to adhere fire-resistant lagging cloths over pipe insulation.

3. Service Temperature Range: 0 to plus 180 deg F. 4. Color: White.

2.6 SEALANTS

A. Joint Sealants:

1. Materials shall be compatible with insulation materials, jackets, and substrates. 2. Permanently flexible, elastomeric sealant. 3. Service Temperature Range: Minus 100 to plus 300 deg F. 4. Color: White or gray. 5. For indoor applications, sealants shall have a VOC content of 420 g/L or less when

calculated according to 40 CFR 59, Subpart D (EPA Method 24).

Page 88: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

HVAC PIPING INSULATION 230719 - 4

6. Sealants shall comply with the testing and product requirements of the California Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers."

B. ASJ Flashing Sealants, and Vinyl, PVDC, and PVC Jacket Flashing Sealants: 1. Materials shall be compatible with insulation materials, jackets, and substrates. 2. Fire- and water-resistant, flexible, elastomeric sealant. 3. Service Temperature Range: Minus 40 to plus 250 deg F. 4. Color: White. 5. For indoor applications, sealants shall have a VOC content of 420 g/L or less when

calculated according to 40 CFR 59, Subpart D (EPA Method 24). 6. Sealants shall comply with the testing and product requirements of the California

Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers."

2.7 FACTORY-APPLIED JACKETS

A. Insulation system schedules indicate factory-applied jackets on various applications. When factory-applied jackets are indicated, comply with the following: 1. ASJ-SSL: ASJ with self-sealing, pressure-sensitive, acrylic-based adhesive covered by a

removable protective strip; complying with ASTM C 1136, Type I.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates and conditions for compliance with requirements for installation tolerances and other conditions affecting performance of insulation application.

1. Verify that systems to be insulated have been tested and are free of defects. 2. Verify that surfaces to be insulated are clean and dry. 3. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Surface Preparation: Clean and dry surfaces to receive insulation. Remove materials that will adversely affect insulation application.

B. Surface Preparation: Clean and prepare surfaces to be insulated. Before insulating, apply a corrosion coating to insulated surfaces as follows:

1. Stainless Steel: Coat 300 series stainless steel with an epoxy primer 5 mils thick and an epoxy finish 5 mils thick if operating in a temperature range between 140 and 300 deg F. Consult coating manufacturer for appropriate coating materials and application methods for operating temperature range.

Page 89: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

HVAC PIPING INSULATION 230719 - 5

2. Carbon Steel: Coat carbon steel operating at a service temperature between 32 and 300 deg F with an epoxy coating. Consult coating manufacturer for appropriate coating materials and application methods for operating temperature range.

C. Coordinate insulation installation with the trade installing heat tracing. Comply with requirements for heat tracing that apply to insulation.

D. Mix insulating cements with clean potable water; if insulating cements are to be in contact with stainless-steel surfaces, use demineralized water.

3.3 GENERAL INSTALLATION REQUIREMENTS

A. Install insulation materials, accessories, and finishes with smooth, straight, and even surfaces; free of voids throughout the length of piping including fittings, valves, and specialties.

B. Install insulation materials, forms, vapor barriers or retarders, jackets, and thicknesses required for each item of pipe system as specified in insulation system schedules.

C. Install accessories compatible with insulation materials and suitable for the service. Install accessories that do not corrode, soften, or otherwise attack insulation or jacket in either wet or dry state.

D. Install insulation with longitudinal seams at top and bottom of horizontal runs.

E. Install multiple layers of insulation with longitudinal and end seams staggered.

F. Do not weld brackets, clips, or other attachment devices to piping, fittings, and specialties.

G. Keep insulation materials dry during application and finishing.

H. Install insulation with tight longitudinal seams and end joints. Bond seams and joints with adhesive recommended by insulation material manufacturer.

I. Install insulation with least number of joints practical.

J. Where vapor barrier is indicated, seal joints, seams, and penetrations in insulation at hangers, supports, anchors, and other projections with vapor-barrier mastic.

1. Install insulation continuously through hangers and around anchor attachments. 2. For insulation application where vapor barriers are indicated, extend insulation on anchor

legs from point of attachment to supported item to point of attachment to structure. Taper and seal ends at attachment to structure with vapor-barrier mastic.

3. Install insert materials and install insulation to tightly join the insert. Seal insulation to insulation inserts with adhesive or sealing compound recommended by insulation material manufacturer.

4. Cover inserts with jacket material matching adjacent pipe insulation. Install shields over jacket, arranged to protect jacket from tear or puncture by hanger, support, and shield.

K. Apply adhesives, mastics, and sealants at manufacturer's recommended coverage rate and wet and dry film thicknesses.

Page 90: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

HVAC PIPING INSULATION 230719 - 6

L. Install insulation with factory-applied jackets as follows:

1. Draw jacket tight and smooth. 2. Cover circumferential joints with 3-inch wide strips, of same material as insulation

jacket. Secure strips with adhesive and outward clinching staples along both edges of strip, spaced 4 inches o.c.

3. Overlap jacket longitudinal seams at least 1-1/2 inches. Install insulation with longitudinal seams at bottom of pipe. Clean and dry surface to receive self-sealing lap. Staple laps with outward clinching staples along edge at 4 inches o.c.

a. For below-ambient services, apply vapor-barrier mastic over staples.

4. Cover joints and seams with tape, according to insulation material manufacturer's written instructions, to maintain vapor seal.

5. Where vapor barriers are indicated, apply vapor-barrier mastic on seams and joints and at ends adjacent to pipe flanges and fittings.

M. Cut insulation in a manner to avoid compressing insulation more than 75 percent of its nominal thickness.

N. Finish installation with systems at operating conditions. Repair joint separations and cracking due to thermal movement.

O. Repair damaged insulation facings by applying same facing material over damaged areas. Extend patches at least 4 inches beyond damaged areas. Adhere, staple, and seal patches similar to butt joints.

3.4 PENETRATIONS

A. Insulation Installation at Roof Penetrations: Install insulation continuously through roof penetrations.

1. Seal penetrations with flashing sealant. 2. For applications requiring only indoor insulation, terminate insulation above roof surface

and seal with joint sealant. For applications requiring indoor and outdoor insulation, install insulation for outdoor applications tightly joined to indoor insulation ends. Seal joint with joint sealant.

3. Extend jacket of outdoor insulation outside roof flashing at least 2 inches below top of roof flashing.

4. Seal jacket to roof flashing with flashing sealant.

B. Insulation Installation at Underground Exterior Wall Penetrations: Terminate insulation flush with sleeve seal. Seal terminations with flashing sealant.

C. Insulation Installation at Aboveground Exterior Wall Penetrations: Install insulation continuously through wall penetrations.

1. Seal penetrations with flashing sealant. 2. For applications requiring only indoor insulation, terminate insulation inside wall surface

and seal with joint sealant. For applications requiring indoor and outdoor insulation,

Page 91: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

HVAC PIPING INSULATION 230719 - 7

install insulation for outdoor applications tightly joined to indoor insulation ends. Seal joint with joint sealant.

3. Extend jacket of outdoor insulation outside wall flashing and overlap wall flashing at least 2 inches.

4. Seal jacket to wall flashing with flashing sealant.

D. Insulation Installation at Interior Wall and Partition Penetrations (That Are Not Fire Rated): Install insulation continuously through walls and partitions.

E. Insulation Installation at Fire-Rated Wall and Partition Penetrations: Install insulation continuously through penetrations of fire-rated walls and partitions.

1. Comply with requirements in Section 078413 "Penetration Firestopping" for firestopping and fire-resistive joint sealers.

F. Insulation Installation at Floor Penetrations:

1. Pipe: Install insulation continuously through floor penetrations. 2. Seal penetrations through fire-rated assemblies. Comply with requirements in

Section 078413 "Penetration Firestopping."

3.5 GENERAL PIPE INSULATION INSTALLATION

A. Requirements in this article generally apply to all insulation materials except where more specific requirements are specified in various pipe insulation material installation articles.

B. Insulation Installation on Fittings, Valves, Strainers, Flanges, and Unions:

1. Install insulation over fittings, valves, strainers, flanges, unions, and other specialties with continuous thermal and vapor-retarder integrity unless otherwise indicated.

2. Insulate pipe elbows using preformed fitting insulation or mitered fittings made from same material and density as adjacent pipe insulation. Each piece shall be butted tightly against adjoining piece and bonded with adhesive. Fill joints, seams, voids, and irregular surfaces with insulating cement finished to a smooth, hard, and uniform contour that is uniform with adjoining pipe insulation.

3. Insulate tee fittings with preformed fitting insulation or sectional pipe insulation of same material and thickness as used for adjacent pipe. Cut sectional pipe insulation to fit. Butt each section closely to the next and hold in place with tie wire. Bond pieces with adhesive.

4. Insulate valves using preformed fitting insulation or sectional pipe insulation of same material, density, and thickness as used for adjacent pipe. Overlap adjoining pipe insulation by not less than two times the thickness of pipe insulation, or one pipe diameter, whichever is thicker. For valves, insulate up to and including the bonnets, valve stuffing-box studs, bolts, and nuts. Fill joints, seams, and irregular surfaces with insulating cement.

5. Insulate strainers using preformed fitting insulation or sectional pipe insulation of same material, density, and thickness as used for adjacent pipe. Overlap adjoining pipe insulation by not less than two times the thickness of pipe insulation, or one pipe diameter, whichever is thicker. Fill joints, seams, and irregular surfaces with insulating cement. Insulate strainers so strainer basket flange or plug can be easily removed and

Page 92: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

HVAC PIPING INSULATION 230719 - 8

replaced without damaging the insulation and jacket. Provide a removable reusable insulation cover. For below-ambient services, provide a design that maintains vapor barrier.

6. Insulate flanges and unions using a section of oversized preformed pipe insulation. Overlap adjoining pipe insulation by not less than two times the thickness of pipe insulation, or one pipe diameter, whichever is thicker.

7. Cover segmented insulated surfaces with a layer of finishing cement and coat with a mastic. Install vapor-barrier mastic for below-ambient services and a breather mastic for above-ambient services. Reinforce the mastic with fabric-reinforcing mesh. Trowel the mastic to a smooth and well-shaped contour.

8. Stencil or label the outside insulation jacket of each union with the word "union." Match size and color of pipe labels.

C. Insulate instrument connections for thermometers, pressure gages, pressure temperature taps, test connections, flow meters, sensors, switches, and transmitters on insulated pipes. Shape insulation at these connections by tapering it to and around the connection with insulating cement and finish with finishing cement, mastic, and flashing sealant.

D. Install removable insulation covers at locations indicated. Installation shall conform to the following:

1. Make removable flange and union insulation from sectional pipe insulation of same thickness as that on adjoining pipe. Install same insulation jacket as adjoining pipe insulation.

2. When flange and union covers are made from sectional pipe insulation, extend insulation from flanges or union long at least two times the insulation thickness over adjacent pipe insulation on each side of flange or union. Secure flange cover in place with stainless-steel or aluminum bands. Select band material compatible with insulation and jacket.

3. Construct removable valve insulation covers in same manner as for flanges, except divide the two-part section on the vertical center line of valve body.

4. When covers are made from block insulation, make two halves, each consisting of mitered blocks wired to stainless-steel fabric. Secure this wire frame, with its attached insulation, to flanges with tie wire. Extend insulation at least 2 inches over adjacent pipe insulation on each side of valve. Fill space between flange or union cover and pipe insulation with insulating cement. Finish cover assembly with insulating cement applied in two coats. After first coat is dry, apply and trowel second coat to a smooth finish.

5. Unless a PVC jacket is indicated in field-applied jacket schedules, finish exposed surfaces with a metal jacket.

3.6 INSTALLATION OF MINERAL-FIBER INSULATION

A. Insulation Installation on Straight Pipes and Tubes:

1. Secure each layer of preformed pipe insulation to pipe with wire or bands and tighten bands without deforming insulation materials.

2. Where vapor barriers are indicated, seal longitudinal seams, end joints, and protrusions with vapor-barrier mastic and joint sealant.

3. For insulation with factory-applied jackets on above-ambient surfaces, secure laps with outward-clinched staples at 6 inches o.c.

Page 93: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

HVAC PIPING INSULATION 230719 - 9

4. For insulation with factory-applied jackets on below-ambient surfaces, do not staple longitudinal tabs. Instead, secure tabs with additional adhesive as recommended by insulation material manufacturer and seal with vapor-barrier mastic and flashing sealant.

B. Insulation Installation on Pipe Flanges:

1. Install preformed pipe insulation to outer diameter of pipe flange. 2. Make width of insulation section same as overall width of flange and bolts, plus twice the

thickness of pipe insulation. 3. Fill voids between inner circumference of flange insulation and outer circumference of

adjacent straight pipe segments with mineral-fiber blanket insulation. 4. Install jacket material with manufacturer's recommended adhesive, overlap seams at least

1 inch, and seal joints with flashing sealant.

C. Insulation Installation on Pipe Fittings and Elbows:

1. Install preformed sections of same material as straight segments of pipe insulation when available.

2. When preformed insulation elbows and fittings are not available, install mitered sections of pipe insulation, to a thickness equal to adjoining pipe insulation. Secure insulation materials with wire or bands.

D. Insulation Installation on Valves and Pipe Specialties:

1. Install preformed sections of same material as straight segments of pipe insulation when available.

2. When preformed sections are not available, install mitered sections of pipe insulation to valve body.

3. Arrange insulation to permit access to packing and to allow valve operation without disturbing insulation.

4. Install insulation to flanges as specified for flange insulation application.

3.7 FIELD QUALITY CONTROL

A. All insulation applications will be considered defective Work if sample inspection reveals noncompliance with requirements.

3.8 PIPING INSULATION SCHEDULE, GENERAL

A. Acceptable preformed pipe and tubular insulation materials and thicknesses are identified for each piping system and pipe size range. If more than one material is listed for a piping system, selection from materials listed is Contractor's option.

3.9 INDOOR PIPING INSULATION SCHEDULE

A. Steam and Steam Condensate, 350 Deg F and Below:

1. NPS 3/4 and Larger: Insulation shall be the following:

Page 94: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

HVAC PIPING INSULATION 230719 - 10

a. Mineral-Fiber, Preformed Pipe, Type I

B. Steam and Steam Condensate, above 350 Deg F:

1. NPS 3/4 and larger: Insulation shall be the following: a. Mineral-Fiber, Preformed Pipe, Type I.

END OF SECTION 230719

Page 95: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

STEAM AND CONDENSATE HEATING PIPING 232213 - 1

SECTION 232213 - STEAM AND CONDENSATE HEATING PIPING

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes pipe and fittings for LP and HP steam and condensate piping:

B. Related Requirements:

1. Section 232216 "Steam and Condensate Piping Specialties" for strainers, flash tanks, special-duty valves, steam traps, thermostatic air vents and vacuum breakers, and steam and condensate meters.

1.2 INFORMATIONAL SUBMITTALS

A. Qualification Data: For Installer.

B. Welding certificates.

C. Field quality-control reports.

1.3 QUALITY ASSURANCE

A. Steel Support Welding: Qualify procedures and personnel according to AWS D1.1/D1.1M, "Structural Welding Code - Steel."

B. Pipe Welding: Qualify procedures and operators according to the following:

1. ASME Compliance: Comply with ASME B31.1, "Power Piping," and ASME B31.9, "Building Services Piping," for materials, products, and installation.

2. Certify that each welder has passed AWS qualification tests for welding processes involved and that certification is current.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Components and installation shall be capable of withstanding the following minimum working pressures and temperatures unless otherwise indicated:

1. HP Steam Piping: 65 psig. 2. LP Steam Piping: 15 psig. 3. Condensate Piping: 15 psig at 250 deg F. 4. Makeup-Water Piping: 80 psig at 150 deg F.

Page 96: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

STEAM AND CONDENSATE HEATING PIPING 232213 - 2

5. Blowdown-Drain Piping: Equal to pressure of the piping system to which it is attached. 6. Air-Vent and Vacuum-Breaker Piping: Equal to pressure of the piping system to which it

is attached. 7. Safety-Valve-Inlet and -Outlet Piping: Equal to pressure of the piping system to which it

is attached.

2.2 STEEL PIPE AND FITTINGS

A. Steel Pipe: ASTM A 53/A 53M, black steel, plain ends, welded and seamless, Grade B, and Schedule as indicated in piping applications articles.

B. Cast-Iron Threaded Fittings: ASME B16.4; Classes 125, 150, and 300 as indicated in piping applications articles.

C. Malleable-Iron Threaded Fittings: ASME B16.3; Classes 150 and 300 as indicated in piping applications articles.

D. Malleable-Iron Unions: ASME B16.39; Classes 150, 250, and 300 as indicated in piping applications articles.

E. Cast-Iron Threaded Flanges and Flanged Fittings: ASME B16.1, Classes 125 and 250 as indicated in piping applications articles; raised ground face, and bolt holes spot faced.

F. Wrought-Steel Fittings: ASTM A 234/A 234M, wall thickness to match adjoining pipe.

G. Wrought-Steel Flanges and Flanged Fittings: ASME B16.5, including bolts, nuts, and gaskets of the following material group, end connections, and facings:

1. Material Group: 1.1. 2. End Connections: Butt welding. 3. Facings: Raised face.

H. Steel Pipe Nipples: ASTM A 733, made of ASTM A 53/A 53M, black steel of same Type, Grade, and Schedule as pipe in which installed.

2.3 JOINING MATERIALS

A. Pipe-Flange Gasket Materials: Suitable for chemical and thermal conditions of piping system contents.

1. ASME B16.21, nonmetallic, flat, asbestos free, 1/8-inch maximum thickness unless otherwise indicated.

a. Full-Face Type: For flat-face, Class 125, cast-iron and cast-bronze flanges. b. Narrow-Face Type: For raised-face, Class 250, cast-iron and steel flanges.

B. Flange Bolts and Nuts: ASME B18.2.1, carbon steel, unless otherwise indicated.

C. Welding Filler Metals: Comply with AWS D10.12M/D10.12 for welding materials appropriate for wall thickness and chemical analysis of steel pipe being welded.

Page 97: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

STEAM AND CONDENSATE HEATING PIPING 232213 - 3

D. Welding Materials: Comply with Section II, Part C, of ASME Boiler and Pressure Vessel Code for welding materials appropriate for wall thickness and for chemical analysis of pipe being welded.

PART 3 - EXECUTION

3.1 LP STEAM PIPING APPLICATIONS

A. LP Steam Piping, NPS 2 and Smaller Schedule 40, Type S, Grade B, steel pipe; Class 125 cast-iron fittings; and threaded joints.

B. LP Steam Piping, NPS 2-1/2 through NPS 12: Schedule 40, Type E, Grade B, steel pipe; Class 150 wrought-steel fittings, flanges, and flange fittings; and welded and flanged joints.

C. Condensate piping above grade, NPS 2 and smaller, shall be the following:

1. Schedule 80, Type S, Grade B, steel pipe; Class 125 cast-iron fittings; and threaded joints.

D. Condensate piping above grade, NPS 2-1/2 and larger, shall be the following:

1. Schedule 80, Type E, Grade B, steel pipe; Class 150 wrought-steel fittings, flanges, and flange fittings; and welded and flanged joints.

3.2 HP STEAM PIPING APPLICATIONS

A. HP Steam Piping, NPS 2 and Smaller: Schedule 40, Type S, Grade B, steel pipe; Class 125 cast-iron fittings; and threaded joints.

B. HP Steam Piping, NPS 2-1/2 through NPS 12: Schedule 40, Type E, Grade B, steel pipe; Class 150 wrought-steel fittings, flanges, and flange fittings; and welded and flanged joints.

C. Condensate piping above grade, NPS 2 and smaller, shall be the following:

1. Schedule 80, Type S, Grade B, steel pipe; Class 125 cast-iron fittings; and threaded joints.

D. Condensate piping above grade, NPS 2-1/2 and larger, shall be the following:

1. Schedule 80, Type E, Grade B, steel pipe; Class 150 wrought-steel fittings, flanges, and flange fittings; and welded and flanged joints.

3.3 ANCILLARY PIPING APPLICATIONS

A. Blowdown-Drain Piping: Same materials and joining methods as for piping specified for the service in which blowdown drain is installed.

B. Vacuum-Breaker Piping: Outlet, same as service where installed.

Page 98: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

STEAM AND CONDENSATE HEATING PIPING 232213 - 4

C. Safety-Valve-Inlet and -Outlet Piping: Same materials and joining methods as for piping specified for the service in which safety valve is installed.

3.4 PIPING INSTALLATION

A. Install piping in concealed locations unless otherwise indicated and except in equipment rooms and service areas.

B. Install piping indicated to be exposed and piping in equipment rooms and service areas at right angles or parallel to building walls. Diagonal runs are prohibited unless otherwise indicated.

C. Install piping above accessible ceilings to allow sufficient space for ceiling panel removal.

D. Install piping to permit valve servicing.

E. Install piping free of sags and bends.

F. Install fittings for changes in direction and branch connections.

G. Install piping to allow application of insulation.

H. Select system components with pressure rating equal to or greater than system operating pressure.

I. Install groups of pipes parallel to each other, spaced to permit applying insulation and servicing of valves.

J. Install drains, consisting of a tee fitting, NPS 3/4 full port-ball valve, and short NPS 3/4 threaded nipple with cap, at low points in piping system mains and elsewhere as required for system drainage.

K. Install steam supply piping at a minimum uniform grade of 0.2 percent downward in direction of steam flow.

L. Install condensate return piping at a minimum uniform grade of 0.4 percent downward in direction of condensate flow.

M. Reduce pipe sizes using eccentric reducer fitting installed with level side down.

N. Install branch connections to mains using tee fittings in main pipe, with the branch connected to top of main pipe.

O. Install unions in piping, NPS 2 and smaller, adjacent to valves, at final connections of equipment, and elsewhere as indicated.

P. Install flanges in piping, NPS 2-1/2 and larger, at final connections of equipment and elsewhere as indicated.

Q. Install shutoff valve immediately upstream of each dielectric fitting.

Page 99: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

STEAM AND CONDENSATE HEATING PIPING 232213 - 5

R. Install strainers on supply side of control valves, pressure-reducing valves, traps, and elsewhere as indicated. Install NPS 3/4 nipple and full port ball valve in blowdown connection of strainers NPS 2 and larger. Match size of strainer blowoff connection for strainers smaller than NPS 2.

S. Install drip legs at low points and natural drainage points such as ends of mains, bottoms of risers, and ahead of pressure regulators, and control valves.

1. On straight runs with no natural drainage points, install drip legs at intervals not exceeding 300 feet.

2. Size drip legs same size as main. In steam mains NPS 6 and larger, drip leg size can be reduced, but to no less than NPS 4.

3.5 STEAM AND CONDENSATE PIPING SPECIALTIES INSTALLATION

A. Comply with requirements in Section 232216 "Steam and Condensate Piping Specialties" for installation requirements for strainers, flash tanks, special-duty valves, steam traps, thermostatic air vents and vacuum breakers, and steam and condensate meters.

3.6 HANGERS AND SUPPORTS

A. Install the following pipe attachments:

1. Adjustable steel clevis hangers for individual horizontal piping less than 20 feet long. 2. Adjustable roller hangers and spring hangers for individual horizontal piping 20 feet or

longer. 3. Pipe Roller: MSS SP-58, Type 44 for multiple horizontal piping 20 feet or longer,

supported on a trapeze. 4. Spring hangers to support vertical runs.

B. Install hangers for steel steam supply piping with the following maximum spacing:

1. NPS 3/4: Maximum span, 9 feet. 2. NPS 1: Maximum span, 9 feet. 3. NPS 1-1/2: Maximum span, 12 feet. 4. NPS 2: Maximum span, 13 feet. 5. NPS 2-1/2: Maximum span, 14 feet. 6. NPS 3 and Larger: Maximum span, 15 feet.

C. Install hangers for steel steam condensate piping with the following maximum spacing:

1. NPS 3/4: Maximum span, 7 feet. 2. NPS 1: Maximum span, 7 feet. 3. NPS 1-1/2: Maximum span, 9 feet. 4. NPS 2: Maximum span, 10 feet. 5. NPS 2-1/2: Maximum span, 11 feet. 6. NPS 3 and Larger: Maximum span, 12 feet.

D. Support vertical runs at roof, at each floor, and at 10-foot intervals between floors.

Page 100: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

STEAM AND CONDENSATE HEATING PIPING 232213 - 6

E. Fiberglass Piping Hanger Spacing: Space hangers according to pipe manufacturer's written instructions for service conditions. Avoid point loading. Space and install hangers with the fewest practical rigid anchor points.

3.7 PIPE JOINT CONSTRUCTION

A. Ream ends of pipes and remove burrs. Bevel plain ends of steel pipe.

B. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before assembly.

C. Threaded Joints: Thread pipe with tapered pipe threads according to ASME B1.20.1. Cut threads full and clean using sharp dies. Ream threaded pipe ends to remove burrs and restore full ID. Join pipe fittings and valves as follows:

1. Apply appropriate tape or thread compound to external pipe threads unless dry seal threading is specified.

2. Damaged Threads: Do not use pipe or pipe fittings with threads that are corroded or damaged. Do not use pipe sections that have cracked or open welds.

D. Welded Joints: Construct joints according to AWS D10.12M/D10.12, using qualified processes and welding operators according to "Quality Assurance" Article.

E. Flanged Joints: Select appropriate gasket material, size, type, and thickness for service application. Install gasket concentrically positioned. Use suitable lubricants on bolt threads.

F. Fiberglass Bonded Joints: Prepare pipe ends and fittings, apply adhesive, and join according to pipe manufacturer's written instructions.

3.8 TERMINAL EQUIPMENT CONNECTIONS

A. Size for supply and return piping connections shall be the same as or larger than equipment connections.

B. Install traps and control valves in accessible locations close to connected equipment.

C. Install bypass piping with globe valve around control valve. If parallel control valves are installed, only one bypass is required.

D. Install vacuum breakers downstream from control valve, close to coil inlet connection.

E. Install a drip leg at coil outlet.

3.9 FIELD QUALITY CONTROL

A. Prepare steam and condensate piping according to ASME B31.1, "Power Piping," and ASME B31.9, "Building Services Piping," and as follows:

1. Leave joints, including welds, uninsulated and exposed for examination during test.

Page 101: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

STEAM AND CONDENSATE HEATING PIPING 232213 - 7

2. Provide temporary restraints for expansion joints that cannot sustain reactions due to test pressure. If temporary restraints are impractical, isolate expansion joints from testing.

3. Flush system with clean water. Clean strainers. 4. Isolate equipment from piping. If a valve is used to isolate equipment, its closure shall be

capable of sealing against test pressure without damage to valve. Install blinds in flanged joints to isolate equipment.

B. Perform the following tests and inspections:

1. Use ambient temperature water as a testing medium unless there is risk of damage due to freezing. Another liquid that is safe for workers and compatible with piping may be used.

2. Subject piping system to hydrostatic test pressure that is not less than 1.5 times the working pressure. Test pressure shall not exceed maximum pressure for any vessel, pump, valve, or other component in system under test. Verify that stress due to pressure at bottom of vertical runs does not exceed 90 percent of specified minimum yield strength.

3. After hydrostatic test pressure has been applied for at least 10 minutes, examine piping, joints, and connections for leakage. Eliminate leaks by tightening, repairing, or replacing components, and repeat hydrostatic test until there are no leaks.

C. Prepare test and inspection reports.

END OF SECTION 232213

Page 102: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

STEAM AND CONDENSATE PIPING SPECIALTIES 232216 - 1

SECTION 232216 - STEAM AND CONDENSATE PIPING SPECIALTIES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes the following piping specialties for LP and HP steam and condensate piping:

1. Strainers. 2. Flash tanks. 3. Safety valves. 4. Pressure-reducing valves. 5. Steam traps. 6. Thermostatic air vents and vacuum breakers. 7. Steam and condensate meters.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of the following:

1. Pressure-reducing and safety valve. 2. Steam trap. 3. Air vent and vacuum breaker. 4. Flash tank. 5. Meter.

1.4 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For valves, safety valves, pressure-reducing valves, steam traps, air vents, vacuum breakers, and meters to include in emergency, operation, and maintenance manuals.

1.5 QUALITY ASSURANCE

A. Pipe Welding: Qualify procedures and operators according to the following:

1. ASME Compliance: Safety valves and pressure vessels shall bear the appropriate ASME label. Fabricate and stamp flash tanks to comply with ASME Boiler and Pressure Vessel Code: Section VIII, Division 1.

Page 103: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

STEAM AND CONDENSATE PIPING SPECIALTIES 232216 - 2

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Components and installation shall be capable of withstanding the following minimum working pressures and temperatures unless otherwise indicated:

1. HP Steam Piping: 65 psig. 2. LP Steam Piping: 15 PSIG. 3. Condensate Piping: 15 psig at 250 deg F. 4. Makeup-Water Piping: 80 psig at 150 deg F. 5. Blowdown-Drain Piping: Equal to pressure of the piping system to which it is attached. 6. Air-Vent and Vacuum-Breaker Piping: Equal to pressure of the piping system to which it

is attached. 7. Safety-Valve-Inlet and -Outlet Piping: Equal to pressure of the piping system to which it

is attached.

2.2 STRAINERS

A. Y-Pattern Strainers:

1. Body: ASTM A 126, Class B cast iron, with bolted cover and bottom drain connection. 2. End Connections: Threaded ends for strainers NPS 2 and smaller; flanged ends for

strainers NPS 2-1/2 and larger. 3. Strainer Screen: Stainless-steel, 20-mesh strainer, or perforated stainless-steel basket. 4. Tapped blowoff plug. 5. CWP Rating: 250-psig working steam pressure.

B. Basket Strainers:

1. Body: ASTM A 126, Class B cast iron, with bolted cover and bottom drain connection. 2. End Connections: Threaded ends for strainers NPS 2 and smaller; flanged ends for

strainers NPS 2-1/2 and larger. 3. Strainer Screen: Stainless-steel, 20 mesh strainer, and perforated stainless-steel basket

with 50 percent free area. 4. CWP Rating: 250-psig working steam pressure.

2.3 FLASH TANKS

A. Shop or factory fabricated of welded steel according to ASME Boiler and Pressure Vessel Code, for 150-psig rating; and bearing ASME label. Fabricate with tappings for low-pressure steam and condensate outlets, high-pressure condensate inlet, air vent, safety valve, and legs.

2.4 SAFETY VALVES

A. Bronze or Brass Safety Valves: ASME labeled. 1. Disc Material: Forged copper alloy. 2. End Connections: Threaded inlet and outlet.

Page 104: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

STEAM AND CONDENSATE PIPING SPECIALTIES 232216 - 3

3. Spring: Fully enclosed steel spring with adjustable pressure range and positive shutoff, factory set and sealed.

4. Pressure Class: 250. 5. Drip-Pan Elbow: Cast iron and having threaded inlet and outlet with threads complying

with ASME B1.20.1. 6. Size and Capacity: As required for equipment according to ASME Boiler and Pressure

Vessel Code.

B. Cast-Iron Safety Valves: ASME labeled. 1. Disc Material: Forged copper alloy with bronze nozzle. 2. End Connections: Raised-face flanged inlet and threaded or flanged outlet connections. 3. Spring: Fully enclosed cadmium-plated steel spring with adjustable pressure range and

positive shutoff, factory set and sealed. 4. Pressure Class: 250. 5. Drip-Pan Elbow: Cast iron and having threaded inlet, outlet, and drain, with threads

complying with ASME B1.20.1. 6. Exhaust Head: Cast iron and having threaded inlet and drain, with threads complying

with ASME B1.20.1. 7. Size and Capacity: As required for equipment according to ASME Boiler and Pressure

Vessel Code.

2.5 PRESSURE-REDUCING VALVES

A. ASME labeled.

B. Size, Capacity, and Pressure Rating: Factory set for inlet and outlet pressures indicated.

C. Description: Pilot-actuated, diaphragm type, with adjustable pressure range and positive shutoff.

D. Body: Cast iron.

E. End Connections: Threaded connections for valves NPS 2 and smaller and flanged connections for valves NPS 2-1/2 and larger.

F. Trim: Hardened stainless steel.

G. Head and Seat: Replaceable, main head stem guide fitted with flushing and pressure-arresting device cover over pilot diaphragm.

H. Gaskets: Non-asbestos materials.

I. Capacities and Characteristics:

1. Steam Flow Rate: <Insert lb/h (kg/s)>. 2. Inlet Pressure: <Insert psig (kPa)>. 3. Outlet Set Pressure: <Insert psig (kPa)>. 4. Pressure Loss (Wide Open): <Insert psig (kPa)>.

Page 105: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

STEAM AND CONDENSATE PIPING SPECIALTIES 232216 - 4

2.6 STEAM TRAPS

A. Thermostatic Traps: 1. Body: Bronze angle-pattern body with integral union tailpiece and screw-in cap. 2. Trap Type: Balanced-pressure. 3. Bellows: Stainless steel or monel. 4. Head and Seat: Replaceable, hardened stainless steel. 5. Pressure Class: 125.

B. Thermodynamic Traps: 1. Body: Stainless steel with screw-in cap. 2. End Connections: Threaded. 3. Disc and Seat: Stainless steel. 4. Maximum Operating Pressure: 600 psig.

C. Float and Thermostatic Traps: 1. Body and Bolted Cap: ASTM A 126, cast iron. 2. End Connections: Threaded. 3. Float Mechanism: Replaceable, stainless steel. 4. Head and Seat: Hardened stainless steel. 5. Trap Type: Balanced pressure. 6. Thermostatic Bellows: Stainless steel or monel. 7. Thermostatic air vent capable of withstanding 45 deg F of superheat and resisting water

hammer without sustaining damage. 8. Vacuum Breaker: Thermostatic with phosphor bronze bellows, and stainless-steel cage,

valve, and seat. 9. Maximum Operating Pressure: 125 psig.

D. Inverted Bucket Traps: 1. Body and Cap: Cast iron. 2. End Connections: Threaded. 3. Head and Seat: Stainless steel. 4. Valve Retainer, Lever, and Guide Pin Assembly: Stainless steel. 5. Bucket: Brass or stainless steel. 6. Strainer: Integral stainless-steel inlet strainer within the trap body. 7. Air Vent: Stainless-steel thermostatic vent. 8. Pressure Rating: 250 psig.

2.7 THERMOSTATIC AIR VENTS AND VACUUM BREAKERS

A. Thermostatic Air Vents: 1. Body: Cast iron, bronze, or stainless steel. 2. End Connections: Threaded. 3. Float, Valve, and Seat: Stainless steel. 4. Thermostatic Element: Phosphor bronze bellows in a stainless-steel cage. 5. Pressure Rating: 125 psig. 6. Maximum Temperature Rating: 350 deg F.

B. Vacuum Breakers: 1. Body: Cast iron, bronze, or stainless steel.

Page 106: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

STEAM AND CONDENSATE PIPING SPECIALTIES 232216 - 5

2. End Connections: Threaded. 3. Sealing Ball, Retainer, Spring, and Screen: Stainless steel. 4. O-Ring Seal: EPR. 5. Pressure Rating: 125 psig. 6. Maximum Temperature Rating: 350 deg F.

2.8 FLEXIBLE CONNECTORS

A. Stainless-Steel Bellows, Flexible Connectors: 1. Body: Stainless-steel bellows with woven, flexible, bronze, wire-reinforced, protective

jacket. 2. End Connections: Threaded or flanged to match equipment connected. 3. Performance: Capable of 3/4-inch misalignment. 4. CWP Rating: 150 psig. 5. Maximum Operating Temperature: 250 deg F.

2.9 STEAM METERS

A. Meters shall have a microprocessor to display totalizer flow, flow rate, temperature, pressure, time, and date; alarms for high and low flow rate and temperature.

1. Computer shall have 4- to 20-mA or 2- to 10-V output for temperature, pressure, and contact closure for flow increments.

2. Independent timers to store four peak flow rates and total flow. 3. Interface compatible with direct Digital Control System. 4. Microprocessor Enclosure: NEMA 250, Type 4.

B. Sensor: Venturi, of stainless-steel construction, for insertion in pipeline between flanges. At least 10:1 turndown with plus or minus 1 percent accuracy over full-flow range.

C. Sensor: Vortex type with stainless-steel wetted parts and wafer connections; and with a piezoelectric sensor removable and serviceable without shutting down the process. At least 10:1 turndown with plus or minus 1 percent accuracy over full-flow range.

D. Sensor: Spring-loaded, variable-area flowmeter type; density compensated with stainless-steel wetted parts and wafer connections. At least 10:1 turndown with plus or minus 2 percent accuracy over full-flow range.

PART 3 - EXECUTION

3.1 VALVE APPLICATIONS

A. Install shutoff duty valves at branch connections to steam supply mains, at steam supply connections to equipment, and at the outlet of steam traps.

B. Install safety valves on pressure-reducing stations and elsewhere as required by ASME Boiler and Pressure Vessel Code. Install safety-valve discharge piping, without valves, to nearest floor

Page 107: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

STEAM AND CONDENSATE PIPING SPECIALTIES 232216 - 6

drain or as indicated on Drawings. Comply with ASME Boiler and Pressure Vessel Code: Section VIII, Division 1, for installation requirements.

3.2 PIPING INSTALLATION

A. Install piping to permit valve servicing.

B. Install drains, consisting of a tee fitting, NPS 3/4 full port-ball valve, and short NPS 3/4 threaded nipple with cap, at low points in piping system mains and elsewhere as required for system drainage.

C. Install unions in piping, NPS 2 and smaller, adjacent to valves, at final connections of equipment, and elsewhere as indicated.

D. Install flanges in piping, NPS 2-1/2 and larger, at final connections of equipment and elsewhere as indicated.

E. Install shutoff valve immediately upstream of each dielectric fitting.

F. Install strainers on supply side of control valves, pressure-reducing valves, traps, and elsewhere as indicated. Install NPS 3/4 nipple and full port ball valve in blowdown connection of strainers NPS 2 and larger. Match size of strainer blowoff connection for strainers smaller than NPS 2.

G. Flash Tank:

1. Pitch condensate piping down toward flash tank. 2. If more than one condensate pipe discharges into flash tank, install a check valve in each

line. 3. Install thermostatic air vent at tank top. 4. Install safety valve at tank top. 5. Install full-port ball valve, and swing check valve on condensate outlet. 6. Install inverted bucket or float and thermostatic trap at low-pressure condensate outlet,

sized for three times the calculated heat load. 7. Install pressure gage on low-pressure steam outlet.

3.3 STEAM-TRAP INSTALLATION

A. Install steam traps in accessible locations as close as possible to connected equipment.

B. Install full-port ball valve, strainer, and union upstream from trap; install union, check valve, and full-port ball valve downstream from trap unless otherwise indicated.

3.4 PRESSURE-REDUCING VALVE INSTALLATION

A. Install pressure-reducing valves in accessible location for maintenance and inspection.

B. Install bypass piping around pressure-reducing valves, with globe valve equal in size to area of pressure-reducing valve seat ring, unless otherwise indicated.

Page 108: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

STEAM AND CONDENSATE PIPING SPECIALTIES 232216 - 7

C. Install gate valves on both sides of pressure-reducing valves.

D. Install unions or flanges on both sides of pressure-reducing valves having threaded- or flanged-end connections, respectively.

E. Install pressure gages on low-pressure side of pressure-reducing valves after the bypass connection.

F. Install strainers upstream for pressure-reducing valve.

G. Install safety valve downstream from pressure-reducing valve station.

3.5 STEAM OR CONDENSATE METER INSTALLATION

A. Install meters with lengths of straight pipe upstream and downstream according to steam meter manufacturer's written instructions.

3.6 SAFETY VALVE INSTALLATION

A. Install safety valves according to ASME B31.9, "Building Services Piping."

B. Pipe safety-valve discharge without valves to atmosphere outside the building.

C. Install drip-pan elbow fitting adjacent to safety valve and pipe drain connection to nearest floor drain.

D. Install exhaust head with drain to waste, on vents equal to or larger than NPS 2-1/2.

3.7 TERMINAL EQUIPMENT CONNECTIONS

A. Install traps and control valves in accessible locations close to connected equipment.

B. Install bypass piping with globe valve around control valve. If parallel control valves are installed, only one bypass is required.

C. Install vacuum breakers downstream from control valve, close to coil inlet connection.

END OF SECTION 232216

Page 109: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

STEAM CONDENSATE PUMPS 232223 - 1

SECTION 232223 - STEAM CONDENSATE PUMPS

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes steam condensate pumps.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product. Include certified performance curves and rated capacities, operating characteristics, furnished specialties, and accessories for each type of product indicated. Indicate pump's operating point on curves. Include receiver capacity and material.

1.3 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For pumps to include in emergency, operation, and maintenance manuals.

PART 2 - PRODUCTS

2.1 SINGLE-STAGE, CENTRIFUGAL PUMPS WITH FLOOR-MOUNTED RECEIVER

A. Description: Factory-fabricated, packaged, electric-driven pumps; with receiver, pumps, controls, and accessories suitable for operation with steam condensate.

1. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

2. ASME Compliance: Fabricate and label steam condensate receivers to comply with ASME Boiler and Pressure Vessel Code: Section VIII, Division 1.

B. Configuration: Duplex floor-mounted pump with receiver and float switches; rated to pump 200 deg F steam condensate.

C. Receiver:

1. Floor mounted. 2. Close-grained cast iron. 3. Externally adjustable float switches. 4. Flanges for pump mounting. 5. Water-level gage and dial thermometer. 6. Pressure gage at pump discharge. 7. Bronze fitting isolation valve between pump and receiver.

Page 110: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

STEAM CONDENSATE PUMPS 232223 - 2

8. Lifting eyebolts. 9. Inlet vent and an overflow. 10. Cast-iron inlet strainer with vertical self-cleaning bronze screen and large dirt pocket.

D. Pumps:

1. Centrifugal, close coupled, vertical design. 2. Permanently aligned. 3. Bronze fitted. 4. Replaceable bronze case ring. 5. Mechanical seals rated at 250 deg F. 6. Mounted on receiver flange.

E. Motor:

1. Comply with NEMA designation, temperature rating, service factor, and efficiency requirements for motors.

2. Enclosure: Open, dripproof.

F. Control Panel:

1. Factory wired between pumps and float switches, for single external electrical connection.

2. Provide fused, control-power transformer if voltage exceeds 230 V ac. 3. NEMA 250, Type 12 enclosure with hinged door and grounding lug, mounted on pump. 4. Motor controller for each pump. 5. Electrical pump alternator to operate pumps in lead-lag sequence and allow both pumps

to operate on receiver high level. 6. Manual lead-lag control to override electrical pump alternator and manually select the

lead pump. 7. Momentary-contact "TEST" push button on cover for each pump. 8. Numbered terminal strip. 9. Disconnect switch.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine equipment foundations and anchor-bolt locations for compliance with requirements for installation tolerances and other conditions affecting performance of the Work.

B. Examine roughing-in for piping systems to verify actual locations of piping connections before pump installation.

C. Proceed with installation only after unsatisfactory conditions have been corrected.

Page 111: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

STEAM CONDENSATE PUMPS 232223 - 3

3.2 INSTALLATION

A. Install pumps to provide access for periodic maintenance including removing motors, impellers, couplings, and accessories.

B. Support pumps and piping separately so piping is not supported by pumps.

C. Install thermometers and pressure gages.

3.3 CONNECTIONS

A. Comply with requirements for piping specified in Section 232213 "Steam and Condensate Heating Piping" and Section 232216 "Steam and Condensate Piping Specialties."

B. Where installing piping adjacent to machine, allow space for service and maintenance.

C. Install a globe and check valve and pressure gage before inlet of each pump and a gate and check valve at pump outlet.

D. Pipe drain to nearest floor drain for overflow and drain piping connections.

E. Install full-size vent piping to outdoors, terminating in 180-degree elbow at point above highest steam system connection or as indicated.

F. Ground equipment according to electrical specifications.

G. Connect wiring according to electrical specifications.

3.4 DEMONSTRATION

A. Train Owner's maintenance personnel to adjust, operate, and maintain steam condensate pumps.

END OF SECTION 232223

Page 112: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

ELECTRICAL SPECIFICATIONS 260000 - 1

SECTION 260000 – ELECTRICAL SPECIFICATION

PART 1 - GENERAL

1.1 SCOPE

A. Provide complete electrical power, equipment, and wiring as indicated on the contract drawings.

B. Provide all electrical demolition and new work necessary to provide new LED lighting for the mechanical rooms. Provide all conductors, grounds, conduits, connectors, boxes, switches, disconnects, fuses, overcurrent protection, wiring devices, core drills, etc., necessary for a complete installation.

C. Systems shall be complete in all respects, tested, approved, and ready for operation.

1.2 SHOP DRAWINGS AND SUBMITTALS

A. Submit shop drawings on equipment and materials to the engineer for approval. The drawings shall include ratings, performance information, operating data and wiring diagrams. The contractor shall assume full responsibility for work performed or equipment supplied that is not in agreement with the shop drawings.

B. The following list of electrical items must be submitted by the contractor for approval: 1. Low voltage power conductors and cables 2. control voltage electrical power cables 3. Grounding and bonding 4. raceways and boxes, hangers and supports 5. wiring devices 6. enclosed switches and circuit breakers

1.3 RECORD DRAWINGS

A. Neatly and accurately, record all changes to contract documents on a record-set of drawings furnished by the general contractor. These record "as-built" drawings shall include locations of specific items as listed in the various specification divisions. Upon project completion, these record drawings shall be turned over to the engineer.

1.4 GUARANTEE

A. Materials, equipment and workmanship shall have a standard warranty against defects in material and workmanship. Failures due to defective or improper material, equipment, workmanship or design shall be corrected by and at the expense of the contractor, including damage done to areas, materials, and other systems resulting from such failures. Guarantee period shall extend for one year from the date of acceptance.

Page 113: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

ELECTRICAL SPECIFICATIONS 260000 - 2

1.5 INSPECTION

A. Contract drawings are diagrammatic and do not show every required fitting etc. The contractor shall familiarize himself with existing site conditions prior to submitting a bid, and shall include all equipment and accessories necessary for complete and operational systems.

1.6 ARRANGEMENT OF WORK

A. Work shall be coordinated between trades to prevent interference. Work shall present a neat coordinated appearance. Install work as necessary to provide maximum possible headroom, adequate clearance, and ready access for inspection, operation, safe maintenance, repair, and code conformance. If space appears inadequate, consult the engineer before proceeding with the installation.

1.7 WORKMANSHIP

A. Equipment and materials shall be new, of first quality, selected and arranged to fit properly into spaces indicated. Install equipment and materials in accordance with manufacturer's recommendations.

1.8 COORDINATION WITH OWNER

A. Work shall be scheduled with the project manager and the owner. Interruptions in owner's access to the site shall be subject to owner limitations of date and duration.

1.9 OPERATION OF SERVICES AND UTILITIES

A. Shutdown of existing services and utilities shall, without exception, be coordinated with the proper utility and with the owner as to the date, time of day, and duration before any service is interrupted. Notify the owner of estimated duration of shutdown period at least ten days in advance of the proposed shutdown.

1.10 PROTECTION

A. Close open ends of work with temporary covers or plugs during construction to prevent entry of foreign material. Protect existing property, equipment and finishes from damage. Repair, to original condition, existing property that has been damage during execution of the work.

1.11 CLEANING

A. Work site must be kept clean. Rubbish debris and leftover or excess materials shall be removed daily.

Page 114: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

ELECTRICAL SPECIFICATIONS 260000 - 3

1.12 LUBRICATION

A. No equipment shall be operated for temporary services or testing without proper lubrication. Items requiring lubrication shall be left freshly and fully lubricated at time of substantial completion. Furnish owner with one complete new set of any special lubrication devices required for servicing, e.g., grease guns, fittings, and adapters.

1.13 PAINTING

A. Equipment and materials shall have standard manufacturer's finish except where otherwise noted.

1.14 CUTTING AND PATCHING

A. Cutting and patching will be performed as necessary. Painting of finished surfaces after patching shall match adjacent finishes.

1.15 WATERPROOFING

A. Provide necessary sleeves, caulking and flashing required to make openings waterproof.

1.16 FIREPROOFING

A. At closing of each working day, openings cut between floors and through fire-rated partitions shall be provided with UL approved, Class A "noncombustible" fire stopping with ratings equal to that of adjacent construction.

1.17 BASES AND SUPPORTS

A. Provide necessary supports, pads, bases, and piers for equipment. Equipment shall be securely attached to building structure in an acceptable manner. Attachments shall be of strong and durable nature as determined by the owner.

1.18 ACCESS

A. Provide adequately sized access doors for access to concealed equipment and components requiring servicing and inspection. Doors shall have fire ratings equal to the construction in which they are located.

1.19 TESTS

A. Perform tests required by the owner, legal authorities and agencies. Each piece of equipment, including motors and controls, shall be operated continuously for minimum one hour test. Correct all defects appearing during tests until no defects are noted. Final tests shall be made in the owner's presence.

Page 115: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

ELECTRICAL SPECIFICATIONS 260000 - 4

1.20 SYSTEMS OPERATIONS AND MAINTENANCE

A. Upon completion of the work and at a time designated by the engineer, the contractor shall furnish instruction manuals including data, warranties, etc., and shall instruct the owner or his representative as to the arrangement, location and operation of all equipment and systems furnished and installed under the electrical contract.

PART 2 - PRODUCTS

2.1 WIRE CABLES AND RACEWAYS

A. Rigid galvanized steel conduit (RGS) shall be used for all exterior wiring and where subject to dampness, except as noted below or as specifically noted on the drawings. Connectors and couplings shall be galvanized steel threaded type listed for RMC use.

B. Electrical Metallic Tubing (EMT) shall be used for feeders run above ground in dry areas. EMT or RGS shall be used for all circuit homeruns. Connectors and couplings shall be galvanized steel, either compression type, listed for EMT use. Indent or crimp-style connectors are not allowed.

C. EMT or RGS shall be used for all circuit homeruns.

D. VFC Cable: 1. Conduit and EMT shall be 3/4" minimum unless otherwise noted. 2. Flexible metal conduit shall be 1/2" minimum unless otherwise noted.

E. Type MC metal-clad cable may be used for branch wiring to light fixtures, receptacles and switches. Wherever MC cable is used for light fixture wiring, leave sufficient slack for future removal or servicing of fixtures in finished ceilings. The MC cable shall be UL listed, 600V, 90 degree C rated, metal clad with THHN insulation and green insulated ground wire. Connectors and fittings shall be galvanized steel, listed for MC cable use. All cables shall be rigidly supported from the building structure at least 4' OC and within 12" from every fitting and shall run in lines parallel or perpendicular to building structural members. Cable shall not rest on the ceiling structure. Type MC cable shall not be used for homeruns. Cable sheath of interlocked aluminum is not acceptable. Type AC armored cable shall not be permitted on the job.

F. Flexible metallic conduit (FMC) or liquid-tight flexible metallic conduit (LFMC) shall be used for connections to vibrating equipment and furniture partitions. connectors, fittings and clamps for FMC shall be galvanized steel, listed for FMC use. Connectors and couplings for LFMC shall be zinc-plated malleable iron or steel, with engagement window locknut and sealing ring: Liquid, oil, and rain-tight; suitable for wet locations, listed for LFMC use; acceptable equivalent to O-Z/Gedney "Type 4Q". 1. Blue type LA LFMC shall be used for all wiring underneath raised floors. 2. Grey/Tan type LA LFMC shall be used for final connections to vibrating equipment and

to furniture partitions from underfloor duct activation fittings.

G. Conductors shall be new copper with 600 Volt gauge insulation conforming to NEC requirements. Wire #10 and smaller shall be solid conductor with THWN/THHN insulation, size #8 and larger shall be stranded conductors with THWN/THHN insulation. Size #3 and

Page 116: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

ELECTRICAL SPECIFICATIONS 260000 - 5

larger shall be stranded conductors with XHHW insulation. Minimum size wire for light and power circuits shall be #12 AWG. The contractor shall include an individual code sized green insulated ground conductor for all circuits; the use of the conduit system or cable covering as the sole means of grounding will not be permitted.

H. Common neutrals shall not be used for receptacle circuits, unless otherwise noted on plans. When used, common neutral conductor ampere rating shall be double the phase conductor rating.

I. All conduits and wiring shall be run concealed inside walls where possible. Exposed conduits where allowed, shall be run neatly in lines parallel or perpendicular to building walls.

J. All splices for #10 wires or smaller shall be made with "Scotchlok" spring connectors or equal. Splices for #8 or larger shall be made with UL approved compression connectors.

2.2 SAFETY SWITCHES

A. Safety switches shall be fused, 600 VAC, heavy-duty type in NEMA enclosures suitable for the environment in which they shall be installed. Switches shall be Square D, General Electric, or Cutler-Hammer equivalent to the following Square D types: 1. Fused disconnect 2- and 3-pole: "Type H". 2. Fused, rain tight (WP) disconnect switches in NEMA 3R enclosures: "Type H-R". 3. Provide with rejection clips as necessary for specified fusing.

2.3 FUSES

A. Fuses for circuit protection shall be UL listed, non-renewable, low peak, dual element, time delay fuses. Bussman type FRN-RK (250 Volt) or FRS-RK (460 Volt) UL class RK5 or approved equal.

2.4 OUTLET AND JUNCTION BOXES

A. Switch and receptacle outlet boxes in partitions where wiring is concealed shall be standard 4 inches square, 1-1/2 inches deep, hot-dipped, galvanized steel, with device ring for boxes installed in sheetrock walls. Use 1-1/2 inch deep square corner tile wall extension for boxes installed in tile, exposed brick or exposed block masonry walls.

B. Boxes shall be securely fastened to the building structure. Suitable means shall be provided to support outlet boxes to take the weight of the fixtures. Recessed outlet boxes or their extension covers shall be set flush with the face of finished walls, but in no case set greater than 1/4" behind finished face of the wall. The contractor shall check with other drawings for possible box interference.

C. Junction boxes shall be sized in accordance with code requirements.

D. Junction and outlet boxes where exposed to weather and wet locations shall be threaded hub type and provided with watertight screw-on covers and gaskets..

Page 117: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

ELECTRICAL SPECIFICATIONS 260000 - 6

2.5 SWITCHES RECEPTACLES AND PLATES

A. Switches and receptacles shall be as manufactured by Hubbell, Arrow-Hart, Leviton, or Pass and Seymour, and equivalent to the following specification grades, with color matching building standard: 1. Single pole switches shall be Hubbell #1221. 2. 3-way switches shall be Hubbell #1223/ 3. Momentary contact switches shall be Hubbell #5362 4. Duplex grounding receptacles shall be 20 amp Hubbell #5362. 5. Isolated ground receptacles shall be 20 amp Hubbell #G5362 6. Ground-fault type receptacles shall be Hubbell #GF-5362 feed-through receptacles.

B. Occupancy sensor switches shall be sensor switch #WSD-PDT motion and sound dual technology line voltage wall box type rated to control up to 600 watts at 277 VAC. Units shall have adjustable light level and off-time. For academic buildings, or similar buildings conducting sound sensitive research, the sound sensors shall be switched off and disabled.

C. Provide wall plates equal to building standard on all switches and receptacles. Where no standard exists, provide specification grade stainless steel (type 302).

D. Where there are multiple devices in one location, devices shall be ganged under one cover plate. All wall switches shall be flush mounted, where applicable.

E. Receptacles shall be mounted 18" above finished floor, on strike side of door, unless otherwise indicated.

F. Wall switches shall be mounted 48" above finished floor, on strike side of door, unless otherwise indicated..

2.6 CIRCUIT BREAKERS

A. All new circuit breakers shall match existing in style, manufacturer and interrupting rating for panel in which they are being installed, unless otherwise indicated. When multiple breakers in a source have differing interrupting ratings the highest rated breakers shall be used to match new equipment.

PART 3 - EXECUTION

3.1 LOAD BALANCE

A. The electrical contractor shall balance the loads on the three phases in the electrical panel board in which he does work insofar as physically possible, and report each panel loading to the engineer.

Page 118: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

ELECTRICAL SPECIFICATIONS 260000 - 7

3.2 CIRCUIT BREAKER TESTING/SETTING

A. Feeder circuit breakers shall be tested by an independent testing firm with 10 years experience prior to installation.

B. Tests shall be performed at specified trip setting to insure proper operation.

C. Results of all tests shall be furnished to the owner for record.

D. Verify final trip settings for adjustable or interchangeable circuit breaker elements. Instantaneous settings shall be minimum unless otherwise noted.

3.3 GENERAL WIRING TESTS

A. At the time of final inspection and test, all wiring and connections throughout the renovation areas must be completed, devices and equipment properly operating, lighting fixtures installed, and power and lighting circuit and control wiring clearly identified with approved tags ready for acceptance. Each system shall test free from short circuit and grounds.

B. Insulation resistance for low voltage cables and wiring shall be performed at 1000 volts DC for one (1) minute. When insulation resistance must be determined, switchboards, panel boards, fuse holders, switches, and overcurrent devices shall be in place, and the insulation resistance when tested at 1000 volts DC shall be no less than 100,000 ohms for #14 and #12 wire and 250,000 ohms for #10 wire and larger. Conceal cables in finished walls, ceilings, and floors unless otherwise indicated.

3.4 OPERATIONS TESTS

A. Each piece of electrical equipment, including lighting fixtures, motors, and controls shall be operated continuously for a minimum test period of one hour.

B. Demonstrate by operating equipment that circuits and devices are in good operating condition. Each item of control equipment shall be operated a minimum of five times. Demonstration shall be performed after wiring tests. Tighten electrical connectors and terminals according to manufacturer's published torque-tightening values. If manufacturer's torque values are not indicated, use those specified in UL 486A-486B.

3.5 MECHANICAL SYSTEM ADJUSTMENT AND TESTING

A. Be present during adjustment period and final testing of mechanical systems. Take readings necessary to ensure that electrical systems are operating properly. Test for mechanical work are detailed under DIVISION 23.

B. Take ampere readings with true RMS reading ammeter at each electrical component, such as motor and compressors, to determine proper operation.

C. Record readings and submit them to the engineer for review.

Page 119: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

West Campus Dorms Mech Room Repairs 12/23/19 Project: FO500078 Construction Documents

ELECTRICAL SPECIFICATIONS 260000 - 8

3.6 LABELING

A. Label all new disconnects, starters, motors, feeder boxes, in a manner acceptable to the engineer. Provide updated panel schedules in all panel boards within the scope of work. Label feeder raceway along path to facilitate tracing with source, destination, voltage, and isolating device. Paint all new fire alarm raceway red.

B. All manufacturer's nameplates shall be kept clean and free of paint.

C. Data/Communications wiring done under this contract shall be recorded on cable management drawings. Each outlet shall be assigned a number which shall be keyed to its punch down location. Identify and color-code conductors and cables according to Section 260553 "Identification for Electrical Systems."; or, by Engineer of University IT Department directions and standards.

END OF SECTION 260000

Page 120: TIME: 2:00 p.m. PROJECT: West Campus Dorms Mechanical … DOCUMENTS/FO500078... · 4e) Group 6: Blasters, nuclear and toxic waste removal. 33.75 20.84 4f) Group 7: Asbestos/lead removal

BID SUBMISSION FOR

WEST CAMPUS DORMS

MECHANICAL ROOM

REPAIRS

PROJECT NUMBER: FO500078

UNIVERSITY OF CONNECTICUT

STORRS CAMPUS

Storrs, Connecticut

January 23, 2020

NAME OF FIRM SUBMITTING: