tramore waste water treatment plant - environmental ... · tramore waste water treatment plant is a...
TRANSCRIPT
Tramore Waste Water Treatment Plant
Annual Environmental Report 2011
February 2012
Waterford County Council
241036 00 A
\\IECORKFP01\Projects$\DESIGN\projects\241036 Dungarvan WWTP O&M - LMC\Annual Environmental Report\Annual Environmental Report -
Dungarvan WWTP.doc 28 January 2010
Tramore Waste Water Treatment Plant
Annual Environmental Report 2011
February 2012
Waterford County Council
Issued Water Services
Section
Waterford
Co. Council
Date 27th
March 2011
Originator C Flynn EE _________________ _______________
Approver Ml Quinn DOS _________________ _______________
Revision 0
Description Final draft
Date 27/03/2012
Issue and revision record
Chapter Title Page
Executive Summary i
1. Introduction 1
1.1 Licence register number ______________________________________________________________ 1 1.2 Name ____________________________________________________________________________ 1 1.3 Site location _______________________________________________________________________ 1 1.4 Description of activities at the site _______________________________________________________ 1 1.5 Company environmental policy (where available) ___________________________________________ 1 1.6 Company organisation chart for Environmental Management _________________________________ 2
2. Summary Information 3
2.1 Self-Monitoring Data (summary) ________________________________________________________ 3 2.1.1 Emissions to waters/sewer ____________________________________________________________ 3 2.1.2 Influent Monitoring Results ____________________________________________________________ 4 2.1.3 Waste Arisings _____________________________________________________________________ 5 2.2 Agency Monitoring and Enforcement ____________________________________________________ 6 2.3 Energy and Water Consumption ________________________________________________________ 6 2.3.1 Energy Consumption ________________________________________________________________ 6 2.3.2 Water Consumption _________________________________________________________________ 6 2.4 Environmental Incidents and Complaints _________________________________________________ 7 2.5 PRTR Report for 2011 _______________________________________________________________ 7 2.6 PRTR Proposals for 2012 ____________________________________________________________ 8 2.7 Improvement Programme Report _______________________________________________________ 8
3. Licence-Specific Reports 10
3.1 Summary Report on Monthly Influent Monitoring __________________________________________ 10 3.2 Treatment Capacity Report for the WWTP _______________________________________________ 12 3.3 Data Collection and Reporting Requirements under the Urban Wastewater Treatment Directive _____ 12 3.4 Storm Water Overflow Identification and Inspection Report __________________________________ 12 3.5 Network Integrity Assessment Summary Report ___________________________________________ 13 3.6 Development/Infrastructural Works Summary (completed for previous year or prepared for current
year) ____________________________________________________________________________ 13 3.7 Summary Report on Ambient Water Quality in Tramore Bay. _________________________________ 14 3.8 EPA Assessment of 2010 AER ________________________________________________________ 14
4. Environmental Liabilities 15
4.1 Annual Statement __________________________________________________________________ 15 4.2 Environmental Liabilities Risk Assessment _______________________________________________ 15
Content
i
This Annual Environmental Report is prepared in accordance with EPA guidance documents to cover the
period January 2011 to December 2011.
The report relates to Tramore Agglomeration which is subject of Discharge Licence No. D0015-01 as
issued by the EPA on the 21st December 2009. The content of the report relates primarily to the
performance of the new Wastewater treatment plant and also the plans for improvements to the
Agglomeration in order to satisfy the extensive area of environmental legislation.
Tramore Waste Water Treatment Plant is a new plant, commissioned in 2008. The sewage network main
pump station at the promenade was also modified and upgraded during the construction period of the plant
to provide for all of the Dry Weather sewage arisings in Tramore to be delivered to the treatment plant. The
Sewer Network is combined in the old Town areas, giving rise to the need for Storm Water overflows from
the system during heavy rainfall. The WWTP is operated by Veolia who are contracted to operate and
maintain the WWTP for a 20 year period.
The WWTP was largely compliant with the Licence requirements in 2011, with only a single non-
compliance for Total Oxidised Nitrogen (TON) in June. There were no complaints or incidents received or
notified in 2011. The removal efficiencies for the various parameters in the plant are better than expected
for a plant of this design. The plant is operating at 66.1% of its Biological Capacity and this loading is not
likely to be significantly increased in the short term.
The Licence requires that SW2 be upgraded by 31st December 2010 so as to be Emergency Overflows
only. As outlined in the 2010 AER, this overflow is not in use and has been replaced with an alternative
overflow that will require a Technical Amendment to the Licence. This alternative overflow discharges to a
constructed wetland that will provide detention and some level of treatment to the overflow from the
Promenade Pump Station.
Executive Summary
1
1.1 Licence register number
D0015-01
1.2 Name
Tramore Waste Water Treatment Plant
1.3 Site location
Crobally, Tramore, Co. Waterford
1.4 Description of activities at the site
The Tramore Waste Water Treatment Plant located at Crobally, commenced operation in Feb 2008 and is
designed to serve a population equivalent of 20,000. The plant was procured under a DBO contract and the
management of the facility is contracted to Veolia Water by Waterford County Council.
The Tramore Waste Water Treatment Plant treats domestic, commercial and industrial effluent from
Tramore Town. The industrial effluent loading is between small and none as Tramore is principally a
dormitory town. Wastewater is transferred to the plant via twin rising mains from the Promenade Pumping
Station, near the beach in Tramore Town and via a single rising main from the Garraun sewer Pumpstation,
near the Wastewater Treatment plant site.
Primary and Secondary treatment of waste water at Tramore is achieved by screening and grit removal at
the inlet works, settlement, secondary biological treatment (activated sludge), clarification and sludge
removal. Sludge undergoes dewatering by way of direct dewatering of Waste activated sludge from the
settlement tanks. This dewatered sludge is transported to Dungarvan for thermal drying, to produce a final
product which meets the requirements for use in agriculture.
The primary discharge (SW1) from Tramore WWTP is via an outfall pipe and diffuser system directly out
into Tramore bay for a distance of 1.5Km.
1.5 Company environmental policy (where available)
Waterford County Council is committed to environmental protection and improvement as part of it’s role in
Local Government and it’s statutory obligations. It does not have a specific environmental policy as all such
policies are included in the Councils Strategic plan, but not in a format suitable for extract to this document.
1. Introduction
2
1.6 Company organisation chart for Environmental Management
Organisational Structure.
Water Services Staff Structure: Water Quality, Pollution& Drinking Water
The above structure was developed in 2010. Waterford County Council has divided the Water
Services Operations & Maintenance Team into three relevant individual teams namely, the
Waste Water Team, the Pollution Control and River Basin District Team and the Drinking
Water Quality & Supply Team.
All of the above listed team members have duties in other areas of work under the umbrella of
Water Services Operations & Maintenance.
Michael Quinn
Director of Services
Transportation and
Infrastructure
Pat McCarthy
Senior Engineer
Water Service Operations
& Maintenance
Waste Water
Operation and
Maintenance
Pollution Control
Team
Administrative Staff
Mary
Hayes
Vacant
Declan
Halpin
Tech. Grade
2
John O’Sullivan
Senior Executive
Engineer
Conor Foley
Senior Executive
Engineer
Tim Bourke Senior
Executive
Technician
Paul
Carroll
Executive
Scientist
Drinking Water
Quality & Supply
Team
Pollution Control
and River Basin
District Team
Jimmy Mansfield
Senior Executive
Engineer
Thomas
Butler
Technician
Grade 1
Susan
Cook
Technician
Grade 2
3
2.1 Self-Monitoring Data (summary)
2.1.1 Emissions to waters/sewer
This section details the emissions to water from Tramore WWTP over the period January 2011 –
December 2011.
Summary Table for Emissions to Waters
Licensed ELVs % compliance
Flow (m3/d)
pH 6.0-9.5 100
cBOD (mg/l) 25 100
COD (mg/l) 125 100
SS (mg/l) 35 100
Ammonia 5 100
Total Oxidised Nitrogen (TON) 20 91.66
Source: PMS reports Veolia (operator)
Tramore final effluent, average monthly values
COD mg/l
O2 BOD mg/l
O2 SS mg/l NH3-N mg/l TP TON mg/l PO4
3- mg/l Month
13/01/2011 33 7 14 0.4 0.96 9.3 0.75
10/02/2011 18 3 <5 <0.1 0.63 7.6 0.54
03/03/2011 21 <4 <5 0.2 1.52 17.8 1.36
13/04/2011 16 <2.0 <5.0 2.1 1.76 14.1 1.65
05/05/2011 43 5 <5 <0.1 1.88 15.1 1.68
02/06/2011 24 <4 <5 0.2 2.65 24.2 2.43
07/07/2011 30 6 <5 4.9 1.66 6.1 1.39
04/08/2011 48 7 5 5.7 4.15 18.0 3.64
08/09/2011 23 3 7 0.1 3.09 21.4 2.72
06/10/2011 23 3 <3 0.1 2.51 21.6 2.34
03/11/2011 17 3 5 <0.1 1.43 12.5 1.22
07/12/2011 30 1 2.5 <0.19 1.75 21.0 1.79
Average 27.16 3.58* 4.16* 1.16* 1.99 15.73 1.79
*Where the result is below the detectable limit, a value of 50% of the limit is assumed
The monitoring data presented above is the final effluent from Tramore WWTP.
2. Summary Information
4
All licensed parameters are included in the monitoring programme (under Schedule B of the Licence) and
monitoring results are complete for 2011. Metal and Organic Compounds were analysed and are included
in Appendix A. No significant results were noted in the sample taken in December 2011.
There was a single non-compliance in 2011 for Total Oxidised Nitrogen (TON). The ELV limit for TON in
the licence is 20mg/l. A result of 24.2mg/l was recorded in June 2011. This result is greater than 20%
above the ELV and is thus non-compliant, as set out in Condition 2.1.1.iv of the Licence. This non-
compliance should have been notified as an incident to the Agency when it was discovered. However, they
were not reported at that time due to a misinterpretation of Condition 2 of the Licence. It should be noted
that while three other results for TON did exceed the ELV, none of these exceedences was greater than
20% above the ELV and do not constitute a non-compliance as set out in Condition 2.1.1.iv of the Licence.
Summary of Non-compliances
Date Non-compliance Cause Corrective Action
02/06/2010 TON No Denitrification step in WWTP processes
Monitor TON results to see if pattern emerges
No corrective action was possible. System is extended aeration with no nitrogen specific reduction facilities.
Source: Operator PMS reports
The receiving water body for the discharge from the Tramore WWTP is designated as a Bathing Water
area (Tramore Main Strand). This beach complied with the regulatory requirements for Bathing Water
Quality in 2011. The Bathing Water Monitoring Results are outlined in more detail in Section 3.7 of this
report. Thus, the bathing waters at Tramore were not adversely impacted by the discharge from the
Tramore WWTP.
From the results of final effluent monitoring for 2011, it appears that the ELV of 20mg/l for TON may pose a
future compliance issue. At the current loading on the plant, the results for 4 of the months are greater than
the 20mg/l limit while the other 8 months of the year are comfortably less than the ELV. Only one of these
results constituted a non-compliance. It is still unclear if the four results above 20mg/l are typical or isolated
incidents. The loading on the plant increases during June, July and August because of the tourist nature of
Tramore, but only one of the four exceedences occur in that period. It is recommended that further
monitoring of discharged TON results in 2012 be undertaken to see if the non-compliance in June 2011 is
typical or an isolated incident. The AER for 2012 can make proposals for Improvement Works should the
TON results warrant such works. The cost of the works to upgrade the existing WWTP would be estimated
at that time also, but these costs would not be insignificant and would likely require major civil engineering
works at the plant. Such significant improvement works would likely attract funding under the DoECLG’s
Water Services Investment Programme on a Marginal Cost basis and the Council would be required to
fund part of the costs from our own resources. It is not possible to estimate the associated parametric
improvement in the discharge until the works associated with an improvement programme are defined.
Similarly, the associated water quality improvement cannot be defined at this stage.
There is only one WPA Licensed Activity in Tramore. This is for the Splash World leisure centre. The
discharges would typically be of a largely domestic nature. There has been no evidence of impacts from
their discharges on the WWTP in 2011 or heretofore.
There are no secondary discharges from the agglomeration.
2.1.2 Influent Monitoring Results
Influent Monitoring was carried out monthly in accordance with the requirements of Condition 4.15 of the
licence. The table below details the results of the monitoring for cBOD, COD, Suspended Solids, Total
Nitrogen and Total Phosphorous for 2011.
5
Date cBOD mg/l COD mg/l SS mg/l Total Nitrogen mg/l Total Phosphorous mg/l
13/01/2011 81 135 52 15.6 1.82
10/02/2011 71 121 57 13.5 1.42
03/03/2011 160 290 247 29.1 3.92
07/04/2011 200 357 136 34.3 4.94
05/05/2011 185 223 158 23.4 3.33
02/06/2011 233 301 156 37.4 5.3
07/07/2011 133 307 105 27.4 3.68
04/08/2011 255 328 171 41.5 5.96
08/09/2011 258 403 31 43.1 6.35
06/10/2011 490 1263 458 60.9 7.84
03/11/2011 99 135 146 23.2 2.9
07/12/2011 134 378 98 43.9 5.17
Source: Operator PMS reports
These results were then used to calculate the total mass of each parameter passing through the plant in
2011 and included in the PRTR report. A more detailed analysis of the mass loading and efficiency of the
WWTP is included in Section 3.1 of this AER.
2.1.3 Waste Arisings
Excess sludges from the treatment process are dewatered on site and transported to Dungarvan plant for
further treatment and eventual disposal to agriculture. Table below gives the monthly quantities of wet
sludge produced during 2011.
Tramore Sludge Outputs
Month Total Wet Sludge
kgs
Jan-11 107,040
Feb-11 94,760
Mar-11 88,000
Apr-11 88,160
May-11 83,660
Jun-11 52,740
Jul-11 85,160
Aug-11 93,600
Sep-11 95,620
Oct-11 81,220
Nov-11 115,360
Dec-11 66,560
Total 1,051,880
The plant operator carried out analysis of each individual load and informed us that the total dry solids
produced were 150,356 kg. This equates to an average dry solids content of 14.29% in the wet sludge.
6
Other Waste arisings comprise screening and grit and total quantity given below. Quantity is based on 75%
bins full on average and determined in m3. These waste streams are collected in plastic wheelie bins of
varying size.
General Process Waste
Year Description No of bins Destination 2011 Grit &
Screenings 20 x 660L
@100kg/bin Greenstar Ltd.,Carrignard, Six
Cross Road, Waterford.
11 x 700L @250kg/bin
193 x 1100L @400kg/bin
Total kg waste 85,500kg
It should be noted that the Wheelie Bins are not capable of being lifted if full of grit and screenings.
Therefore an assumption has been made as to the average weight capable of being lifted for each bin size.
2.2 Agency Monitoring and Enforcement
A site visit and audit was carried out by the Agency on November 24th 2011. The Council awaits the report
on the audit and will address the audit and any issues/recommendations in the 2012 AER for Tramore.
2.3 Energy and Water Consumption
2.3.1 Energy Consumption
Energy Consumption Summary
Energy Supply kWhr
Heavy fuel oil N/A
Light fuel oil N/A
Natural Gas N/A
Electricity 617,010 kWhrs
Coal, etc. N/A
2.3.2 Water Consumption
Water Consumption Summary
Water Source Volume (m3)
On-site ground water nil
On-site surface water nil
Municipal supply 6,343 m³
The electricity and water usage form 2011 is almost identical to 2010.
7
2.4 Environmental Incidents and Complaints
Section 6.1 of the licence states that:
“The licensee, shall notify the Agency by both telephone and facsimile, to the Agency‟s headquarters in
Wexford, or to such other Agency office as may be specified by the Agency, as soon as practicable after
the occurrence of any incident (as defined in this licence). The licensee shall include as part of the
notification, date and time of the incident, summary details of the occurrence, and where available, the
steps taken to minimise any discharges.”
“The following shall constitute an incident for the purposes of this licence:
(i) any discharge that does not comply with the requirements of this licence;
No such incidents occurred in 2011. The incidents relating to the overflow from the network to the
Backstrand in 2010 (7 No. complaints via EPA) were resolved by the construction of a wetland to
intercept and treat any future emergency overflows from the network at this location.
(ii) any incident with the potential for environmental contamination of surface water or groundwater, or
posing an environmental threat to land, or requiring an emergency response by the Relevant
Water Services Authority.”
No incidents of this type occurred during 2011.
Section 6.6 of the licence states that:
“The licensee shall record all complaints of an environmental nature related to the discharge(s) to waters
from the waste water works in accordance with the national environmental complaints procedure. Each
such record shall give details of the date and time of the complaint, the name of the complainant (if
provided), and the nature of the complaint. A record shall also be kept of the response made in the case of
each complaint.”
No complaints regarding the discharges from the WWTP were received in 2011 nor were there any
complaints for noise and/or odour to the Operator of the WWTP in the period covered by this report.
2.5 PRTR Report for 2011
A Pollutant Release and Transfer Register (PRTR) Report has been prepared for 2011. It was prepared in
conformance with the Agency’s guidelines for the PRTR. The influent monitoring data and waste arisings
data were utilised to complete the PRTR calculation tool. Priority and hazardous substances have been
estimated by the use of this PRTR calculation tool. The report was uploaded through the EPA’s on-line
system on 1st March 2012. The relevant pages from the uploaded PRTR are included in Appendix B of this
report.
There was a total of 1,538,816³ of treated effluent discharged from the WWTP in 2011 with fugitive
emissions of 7,951m³ as a result of stormwater overflows from the plant. There were no releases to sewers
or other wastewater networks nor any releases to lands from the WWTP. There was no on-site treatment of
sludges. Thickened sludges were transported off-site to the Dungarvan WWTP for further processing.
There were also off-site transfers of grit and screenings as outlined in Section 2.1.3 of this report.
8
2.6 PRTR Proposals for 2012
Since the PRTR report for 2011 was carried out using the EPA’s calculation tool and PRTR template, there
is no requirement for the Council to submit proposals for 2012
2.7 Improvement Programme Report
Report on progress made and proposals being developed to meet the improvement programme
requirements namely those set out in Schedule C of the licence. This summary report shall provide detail
on all measures proposed and undertaken under Water Services Investment Programme for
agglomeration, including progress reports on infrastructural works and a statement of compliance with
timeframes set out in this licence.
Schedule C of the licence - C.2 Improvement Programme for Secondary Discharge
Specified Improvement:
Implement a programme of works to ensure SW2 only discharges in the event of an emergency, that is,
during pump failure and/or power failure at the associated pumping station. Refer to Condition 5.6.
Completion date – 31st
December 2010.
Report: SW2 does not currently discharge, and the necessary stormwater and emergency overflow
discharge is via an unlicensed discharge. See section 3.4 below for further description of existing
operation. The unlicensed discharge has operated on a few occasions during the year, induced by heavy
rainfall and or pump blockages. We are currently upgrading the said unlicensed overflow, by the installation
of screens on same. The whole issue of overflows is addressed in a scheme report, namely Tramore
Sewerage Stage 2, where the purpose of the scheme is to reduce overflows to the Bathing area in
Tramore, in compliance with the bathing water directive. This scheme is currently at the Planning Stage of
the Water Services Investment Programme
Any other overflows notified in writing by the Agency. Completion date – as agreed.
The emergency overflow from the Promenade Pump Station as described above needs to be notified to the
Agency with details of its operation. This will be done in early 2012. The overflow does not go directly to the
Backstrand area anymore. There is now a Constructed Wetland in place to contain and treat any overflows
prior to discharge to the Backstrand.
Schedule C of the licence - C.3 Improvement Programme for Storm Water Overflows
Specified Improvement:
Upgrading of sewer network, as required to ensure Storm Water Overflows comply with the criteria outlined
in the DoEHLG ‘Procedures and Criteria in relation to Storm Water Overflows, 1995‟. Refer to Condition
4.13. Completion date – 1st
November 2012.
Report: Due to the storm water overflows at SW3 and SW4 being directly to the beach, they do not comply
with the bathing water requirement of the criteria for storm water overflows, due to their spill frequency.
Despite non compliance with criteria, the bathing water quality for Tramore bay in 2011 has complied with
the bathing water directive and actually meets the Blue Flag standard. Tramore Sewerage Scheme Stage 2
is set to address spill frequency and compliance within the network of all storm overflows. This scheme is
at planning stage on the WSIP 2010-2012. The works envisaged in the scheme amount to circa €11.0m
and cannot be provided by Waterford County Council funding alone. The provision of such a scheme is
dependent on WSIP funding. SW5 by calculation in section 3.3 below is compliant as it would only require
9
to comply with formula A criteria. Given the extent of works to the sewerage system for full compliance, the
date of Nov 2011 is not achievable.
Any other overflows notified in writing by the Agency. Completion date – as agreed.
The emergency overflow from the Promenade Pump Station as described above needs to be notified to the
Agency with details of its operation. This will be done in early 2012. The overflow does not go directly to the
Backstrand area anymore. There is now a Constructed Wetland in place to contain and treat any overflows
prior to discharge to the Backstrand.
10
3.1 Summary Report on Monthly Influent Monitoring
4.15 The licensee shall carry out monthly monitoring of the influent stream to the waste water treatment
plant for cBOD, COD, Suspended Solids, Total Nitrogen and Total Phosphorus in order to measure the
mass loadings and removal efficiencies within the treatment plant.
The following tables give the monitoring results for influent, the mass loadings for influent, effluent and the
removal efficiencies for the process.
Table 1 Analysis Results for Screened Influent 2011
Average for Month
COD mg/l O2
BOD mg/l O2
SS mg/l
NH3-N mg/l
TN mg/l
TP mg/l
Total Inflow m³
Jan 212.80 139.00 131.50 12.40 28.80 1.82 186,548
Feb 179.30 121.20 129.50 9.90 30.60 1.42 180,987
Mar 306.70 168.20 209.20 20.60 38.90 3.92 115,524
April 383.40 215.40 207.90 24.50 42.00 4.94 102,597
May 368.40 175.80 235.90 21.90 41.40 3.33 116,123
June 321.90 195.60 203.40 21.60 39.80 5.30 115,788
July 335.60 195.00 254.40 25.00 47.00 3.68 117,121
Aug 408.60 269.50 268.30 31.20 50.80 5.96 96,681
Sept 374.10 249.70 209.10 27.80 41.10 6.35 104,864
Oct 415.60 245.00 196.00 31.40 50.80 7.84 119,822
Nov 369.10 195.80 202.30 28.00 48.00 2.90 137,536
Dec 495.70 204.00 248.70 32.30 44.20 5.17 126,909
Table 2 Mass Loadings Tramore Influent 2011
Month
COD Kg
BOD Kg
SS kg
NH3-N Kg
TN Kg
TP kg
Jan 39,697 25,930 24,531 2,313 5,373 340
Feb 32,451 21,936 23,438 1,792 5,538 257
Mar 35,431 19,431 24,168 2,380 4,494 453
April 39,336 22,099 21,330 2,514 4,309 507
May 42,780 20,414 27,393 2,543 4,807 387
June 37,272 22,648 23,551 2,501 4,608 614
July 39,306 22,839 29,796 2,928 5,505 431
Aug 39,504 26,056 25,940 3,016 4,911 576
Sept 39,230 26,185 21,927 2,915 4,310 666
Oct 49,798 29,356 23,485 3,762 6,087 939
Nov 50,765 26,930 27,824 3,851 6,602 399
Dec 62,909 25,889 31,562 4,099 5,609 656
Totals 508,478 289,713 304,944 34,615 62,154 6,224
3. Licence-Specific Reports
11
Table 3 Tramore Treated Effluent Mass Loadings 2011
Month COD Kg
BOD Kg
SS kg
NH3-N Kg
TN Kg
TP kg
Jan 3,473 831 661 32 1,831 181
Feb 2,015 513 330 7 1,402 115
Mar 2,098 372 520 8 2,117 179
April 2,602 416 1,030 47 1,686 183
May 2,676 533 1,314 13 1,794 223
June 4,759 627 987 40 2,832 308
July 3,526 649 986 200 1,276 193
Aug 3,654 1,153 956 188 2,325 407
Sept 2,308 405 740 14 2,273 327
Oct 3,376 413 607 8 2,635 305
Nov 2,379 280 583 7 1,757 200
Dec 3,432 550 809 12 2,732 227
Totals 36,298 6,742 9,523 576 24,659 2,847
Table 4 Tramore Treatment Efficiencies 2011 (Influent vs. Effluent)
Month COD BOD SS NH3-N TN TP
Jan 91.25 96.80 97.31 98.60 65.92 46.63
Feb 93.79 97.66 98.59 99.61 74.69 55.09
Mar 94.08 98.08 97.85 99.65 52.89 60.52
April 93.39 98.12 95.17 98.11 60.87 63.86
May 93.75 97.39 95.20 99.51 62.69 42.44
June 87.23 97.23 95.81 98.39 38.54 49.87
July 91.03 97.16 96.69 93.18 76.82 55.33
Aug 90.75 95.58 96.31 93.77 52.67 29.36
Sept 94.12 98.45 96.63 99.52 47.27 50.95
Oct 93.22 98.59 97.41 99.79 56.71 67.55
Nov 95.31 98.96 97.90 99.81 73.39 49.82
Dec 94.54 97.87 97.44 99.71 51.30 65.46
Average 92.70 97.66 96.86 98.31 59.48 53.07
As can be seen from Table 2, the average removal efficiency for COD is 92.70%, for BOD is 97.66% and
for Suspended Solids is 96.86%. These rates of removal show that the Tramore WWTP is performing well
and treating the effluent load effectively. The treatment efficiencies are also higher than in 2010.
The removal efficiency for Ammonia (as N) is 98.31%, for Total Nitrogen is 59.48% and for Total
Phosphorous is 59.41%. The Ammonia removal efficiency is high, as would be expected for a standard
secondary treatment plant. The efficiencies s for Nitrogen and Phosphorous removal indicate that while the
plant is operating at its current capacity that Nitrogen and Phosphorous removal is adequate to meet the
requirements of this licence. It should be noted that there is no ELV for Total P in this licence. These
efficiencies may not be sufficient if the plant has to treat a load close to the full 25,000 p.e. capacity or if
there is a revision of the ELVs for the WWTP. A review of the treatment processes may be necessary at
that time.
12
3.2 Treatment Capacity Report for the WWTP
The Tramore WWTP has a design capacity of 20,000 population equivalent. This translates to a hydraulic
capacity of 12,000m³ (3 DWF) and 1,200kgs of BOD. The current population equivalent as calculated by
the PRTR tool is 13,181. This equates to 65.9% of the design capacity. The average daily flow into the
WWTP was 4,166m³. This equates to 34.7% of the design capacity. The average daily BOD load in the
influent to the WWTP was 794kg/day. This equates to 66.1% of the design capacity.
As can be seen from the foregoing, there is currently sufficient capacity left in the plant to ensure that there
is no environmental risk posed to the receiving waters with the current loading on the plant. It is extremely
unlikely that the loading will increase to the point of being a risk in the next three years.
3.3 Data Collection and Reporting Requirements under the Urban
Wastewater Treatment Directive
Data collection for Urban Waste Water Treatment returns for Tramore has been prepared for uploading via
the EDEN on-line system but cannot be uploaded until the issue with converting the information to XML
format is resolved with the LGCSB. It is anticipated that this will be resolved by the end of March 2012. The
on-line WWTP database for Waterford has been updated with respect to WWTP details and complaints for
all WWTPs including Tramore. This was completed in advance of the closing date of 26th February 2012.
3.4 Storm Water Overflow Identification and Inspection Report
4.12.1 The licensee shall, prior to the date for submission of the second AER (required under Condition
6.10), carry out an investigation for the identification and assessment of storm water overflows. A report on
the storm water overflows shall be submitted to the Agency as part of the second AER. The assessment
shall include a determination of compliance with the criteria for storm water overflows, as set out in the
DoEHLG „Procedures and Criteria in Relation to Storm Water Overflows‟, 1995 and any other guidance as
may be specified by the Agency.
Report:
The required report on Storm Water Overflows was provided in the 2010 AER as required under this
licence condition. In summary, it stated that SW2 is not yet operational and may not be required, SW3 and
SW4 are not compliant with the DoEHLG’s guidance document but are due to be upgraded as part of the
Tramore Sewerage Scheme Stage 2, which is currently in the planning stage under the current Water
Services Investment Programme, and SW5 which is compliant with the DoEHLG’s guidance document.
There is currently an unlicensed overflow from the Promenade pump station which discharged via a series
of open drains to the Backstrand. A Constructed Wetland was constructed by Waterford County Council in
2011 to intercept this overflow and to provide treatment of same. This overflow is intended to replace SW2
because it has a lower impact on the receiving waters than SW2 would have, even though SW2 would
have a lower overflow threshold under the DoEHLG’s guidelines. It should be noted that the Promenade
Pump Station can easily comply with the Formula A flows calculated under the aforementioned guidelines.
The Council will officially notify the Agency with respect to the unlicensed Storm Water Overflow in early
2012 and provide further details with respect to that overflow point.
The current project programme for the next phase of the Tramore Sewerage Scheme involves approval of
the Preliminary Report for the Stage 2 works, including the Storm Overflow upgrades. The Preliminary
Report is due to be issued to the DoECLG for approval in April 2012 and we will then await approval of this
13
before progressing to Detailed Design & Construction Stage. It is anticipated that the works for this upgrade
would commence in mid-2014, assuming timely DoECLG approvals and availability of funding.
3.5 Network Integrity Assessment Summary Report
The 2010 AER did not provide an assessment of the integrity of the existing wastewater works (WWTP and
Network), though the licence required it as part of the second AER. This was not carried out in 2011 either
and will now be carried out in 2012 and reported on in the AER for that year. The assessment will largely
relate to the network since the 20,000 p.e. WWTP is new and only became operational in 2008. There are
no issues with leaks at the WWTP nor are there infiltration problems. The sewer network was upgraded in
2003-2007 but there is a necessity to assess the integrity of the system to ensure maximum efficiency of
pump stations and separation of foul and surface water flows, as outlined in Sections 2.7 and 3.4
previously. Also, some upgrade works are identified in the Preliminary Report for the Tramore Sewerage
Scheme Stage 2 project.
3.6 Development/Infrastructural Works Summary (completed for
previous year or prepared for current year)
5.1 The licensee shall, as a part of the second AER (required under Condition 6.12), prepare and submit to
the Agency a programme of infrastructural improvements to maximise the effectiveness and efficiency of
the waste water works in order to:
a) achieve improvements in the quality of all discharges from the works; The WWTP is new,
commissioned in Feb 2008. There are no proposals for improvement as it is working within its
design requirements and showing compliance with the licence in most parameters, excepting TON.
b) meet the emission limit values specified in Schedule A: Discharges, of this licence; Schedule A1
relates to the treatment plant, and compliance levels are shown in section 2.1.1.
c) give effect to Regulation 2 of the Waste Water Discharge (Authorisation) Regulations 2007 (S.I. No.
684 of 2007); Section 2 of S.I.684 is a statement of the purpose of the said regulations and is quite
general. It is the Council’s opinion that there are no works currently required to give effect to this
regulation.
d) reduce Total Nitrogen loadings in the discharge to the maximum practicable extent: The nitrogen
removal from the existing plant is more effective than expected from a plant of its type. The ability of
the plant to maintain the licence ELV of TON is not expected to continue when the load on the plant
begins to approach the design capacity of the WWTP (20,000 p.e.). Compliance has been achieved
in 2011 as a result of the plant’s current operating parameters and loading. It is recommended that
further monitoring of loading and TON concentration in the discharge be carried out and, if and
when necessary, a programme of works can be prepared to upgrade the WWTP. It is anticipated
that the loading from the agglomeration will not alter significantly in the short-term as residential
development in the town has virtually stopped. Compliance has been achieved in 2011 for over 90%
of the time.
e) meet the obligations of Condition 1.7. This refers to treatment capacity at the WWTP and this is
currently within capacity on the principal determinant of biological loading. The Plant has a design
capacity of 20,000p.e. equivalent to 1,200kg of BOD per day for the year 2018. The current
average daily loading to the plant, as per tables on the mass loadings section 3.1 of this report is
794 kg/day of BOD. The plant is operating at 66.1% of its design capacity.
14
There were no other development/infrastructural works carried out in the Tramore Agglomeration in 2011.
The installation of the Constructed Wetland at the unlicensed SWO was the only improvement work carried
out in 2011.
3.7 Summary Report on Ambient Water Quality in Tramore Bay.
Condition 4.17 of the Licence requires a summary report on the ambient water quality in Tramore Bay. The
discharge from Tramore WWTP is to Tramore Bay, which has a designated beach under the Bathing Water
Directive. Table below shows the results of Bathing Water Quality monitoring in 2011. The monitoring was
carried out on the Council’s behalf by the HSE South. The water quality is compliant with the Bathing Water
Directive guide values and maintained its Blue Flag status.
Tramore Strand
Bathing Water Quality Results 2011
Sampling Location Centre of Bathing Area
Total Faecal Faecal
Coliforms Coliforms Streptococci
Date Time No./ 100
ml No./ 100 ml No./ 100 ml
24-May-11 12.35 3 3 1
21-Jun-11 11.30 9 9 2
12-Jul-11 12.40 1 1 2
08-Aug-11 11.45 6 6 0
05-Sep-11 10.25 3 3 0
The foregoing would suggest that the discharges from the agglomeration are not impacting on the Bathing
Water Quality in Tramore.
3.8 EPA Assessment of 2010 AER
With respect to the Agency’s Assessment of the 2010 AER for Tramore, the recommended actions are
dealt with in Appendix C of this report.
15
4.1 Annual Statement
7.2.1 The licensee shall as part of the AER provide an annual statement as to the measures taken or
adopted in relation to the prevention of environmental damage, and the financial provisions in place in
relation to the underwriting of costs for remedial actions following anticipated events (including closure) or
accidents/incidents, as may be associated with discharges or overflows from the waste water works.
The statement of measures and assessment of risks associated with Dungarvan treatment plant is
contained in the ELRA attached, as far as it is possible to ascertain these risks. On the issue of
underwriting costs: Waterford Co. Council has a long term contract in place for the operation of the waste
water treatment plant and is committed to financing same. Local authorities are state bodies and
dependant on Government for funding. Financial provisions for remedial works, if required, would come
from current annual revenue funds, as far as these would be available.
4.2 Environmental Liabilities Risk Assessment
7.2.2 The licensee shall arrange for the completion, by an independent and appropriately qualified
consultant, of a comprehensive and fully costed Environmental Liabilities Risk Assessment (ELRA) to
address the liabilities from present or planned discharges. A report on this assessment shall be submitted
to the Agency for agreement as part of the second AER (required under Condition 6.12). The ELRA shall
be reviewed as necessary to reflect any significant change to the volume or character of effluent
discharged, and in any case every three years following initial agreement (the results of the review shall be
notified as part of the AER).
The 2010 AER contained a copy of the ELRA for the Tramore Agglomeration. There have been no
significant changes to the volume or character of effluent discharged since that assessment was prepared,
nor are there any expected changes to the effluent discharged. Thus, there has been no requirement to
provide a new ELRA for the 2011 AER. The next revision of the ELRA will be due in 2013 and reported on
in the 2013 AER, unless otherwise recommended by the Agency.
4. Environmental Liabilities
16
APPENDIX A
PRIORITY & DANGEROUS SUBSTANCES
MONITORING RESULTS
17
18
19
APPENDIX B
POLLUTANT RELEASE & TRANSFER REGISTER
20
AER Returns Workbook Version 1.1.13
REFERENCE YEAR 2011
1. FACILITY IDENTIFICATION Parent Company Name Waterford County Council
Facility Name Tramore Waste Water Treatment Plant
PRTR Identification Number D0015
Licence Number D0015-01
Waste or IPPC Classes of Activity No. class_name
30.4 General
Address 1 Civic Offices
Address 2 Dungarvan
Address 3 County Waterford
Address 4
Waterford
Country Ireland
Coordinates of Location -7.13417 52.1655
River Basin District IESE
NACE Code 3700
Main Economic Activity Sewerage
AER Returns Contact Name Colum Flynn
AER Returns Contact Email Address [email protected]
AER Returns Contact Position Executive Engineer
AER Returns Contact Telephone Number 058-20807
AER Returns Contact Mobile Phone Number 087-2388044
AER Returns Contact Fax Number 058-20883
Production Volume 0.0
Production Volume Units
Number of Installations 0
Number of Operating Hours in Year 0
21
Number of Employees 0
User Feedback/Comments
Web Address
2. PRTR CLASS ACTIVITIES
Activity Number Activity Name
5(f) Urban waste-water treatment plants
3. SOLVENTS REGULATIONS (S.I. No. 543 of 2002) Is it applicable? No
Have you been granted an exemption ?
If applicable which activity class applies (as per Schedule 2 of the regulations) ?
Is the reduction scheme compliance route being used ?
22
4.1 RELEASES TO AIR Link to previous years emissions data
| PRTR# : D0015 | Facility Name : Tramore Waste Water Treatment Plant | Filename : D0015_2011 rev 0.xls | Return Year : 2011 |
26/03/2012 15:51
SECTION A : SECTOR SPECIFIC PRTR POLLUTANTS
RELEASES TO AIR Please enter all quantities in this section in KGs
POLLUTANT METHOD QUANTITY
Method Used
No. Annex II Name
M/C/E
Method Code
Designation or Description Emission Point 1
T (Total) KG/Year
A (Accidental) KG/Year
F (Fugitive) KG/Year
03 Carbon dioxide (CO2) E ESTIMATE 0.0 210755.8 0.0 210755.8
01 Methane (CH4) E ESTIMATE 0.0 0.0 0.0 0.0
02 Carbon monoxide (CO) E ESTIMATE 0.0 0.0 0.0 0.0
05 Nitrous oxide (N2O) E ESTIMATE 0.0 1.4 0.0 1.4
07 Non-methane volatile organic compounds (NMVOC) E ESTIMATE 0.0 0.0 0.0 0.0
08 Nitrogen oxides (NOx/NO2) E ESTIMATE 0.0 0.0 0.0 0.0
11 Sulphur oxides (SOx/SO2) E ESTIMATE 0.0 0.0 0.0 0.0
SECTION B : REMAINING PRTR POLLUTANTS RELEASES TO AIR Please enter all quantities in this section in KGs
POLLUTANT METHOD
QUANTITY
Method Used
No. Annex II Name
M/C/E Method Code Designation or Description Emission Point 1
T (Total) KG/Year
A (Accidental) KG/Year
F (Fugitive) KG/Year
0.0 0.0 0.0 0.0
SECTION C : REMAINING POLLUTANT EMISSIONS (As required in your Licence) RELEASES TO AIR Please enter all quantities in this section in KGs
POLLUTANT METHOD
QUANTITY
Method Used
Pollutant No. Name
M/C/E Method Code Designation or Description Emission Point 1
T (Total) KG/Year
A (Accidental) KG/Year
F (Fugitive) KG/Year
0.0 0.0 0.0 0.0
23
4.2 RELEASES TO WATERS Link to previous years emissions data
| PRTR# : D0015 | Facility Name : Tramore Waste Water Treatment Plant | Filename : D0015_2011 rev 0.xls | Return Year : 2011 |
26/03/2012 15:51
SECTION A : SECTOR SPECIFIC PRTR POLLUTANTS
Data on ambient monitoring of storm/surface water or groundwater, conducted as part of your licence requirements, should NOT be submitted under AER / PRTR Reporting as this only concerns Releases from your facility
RELEASES TO WATERS Please enter all quantities in this section in KGs
POLLUTANT QUANTITY
M/C/E Method Used
No. Annex II Name
Method Code Designation or Description Emission Point 1 T (Total) KG/Year
A (Accidental) KG/Year
F (Fugitive) KG/Year
44 1,2,3,4,5,6-hexachlorocyclohexane(HCH) E ESTIMATE EPA WWTP Tool V4.0 0.005 0.005 0.0 0.0
34 1,2-dichloroethane (EDC) E ESTIMATE EPA WWTP Tool V4.0 0.077 0.077 0.0 0.0
25 Alachlor E ESTIMATE EPA WWTP Tool V4.0 0.016 0.016 0.0 0.0
61 Anthracene E ESTIMATE EPA WWTP Tool V4.0 0.016 0.016 0.0 0.0
17 Arsenic and compounds (as As) E ESTIMATE EPA WWTP Tool V4.0 1.537 1.545 0.008 0.0
27 Atrazine E ESTIMATE EPA WWTP Tool V4.0 0.099 0.099 0.0 0.0
91 Benzo(g,h,i)perylene E ESTIMATE EPA WWTP Tool V4.0 0.006 0.006 0.0 0.0
18 Cadmium and compounds (as Cd) E ESTIMATE EPA WWTP Tool V4.0 0.083 0.083 0.0 0.0
28 Chlordane E ESTIMATE EPA WWTP Tool V4.0 0.003 0.003 0.0 0.0
30 Chlorfenvinphos E ESTIMATE EPA WWTP Tool V4.0 0.002 0.002 0.0 0.0
79 Chlorides (as Cl) E ESTIMATE EPA WWTP Tool V4.0 382902.9 384806.7 1903.8 0.0
31 Chloro-alkanes, C10-C13 E ESTIMATE EPA WWTP Tool V4.0 0.323 0.325 0.002 0.0
19 Chromium and compounds (as Cr) E ESTIMATE EPA WWTP Tool V4.0 0.567 0.57 0.003 0.0
20 Copper and compounds (as Cu) E ESTIMATE EPA WWTP Tool V4.0 2.728 2.742 0.014 0.0
82 Cyanides (as total CN) E ESTIMATE EPA WWTP Tool V4.0 2.689 2.702 0.013 0.0
33 DDT E ESTIMATE EPA WWTP Tool V4.0 0.017 0.017 0.0 0.0
70 Di-(2-ethyl hexyl) phthalate (DEHP) E ESTIMATE EPA WWTP Tool V4.0 1.928 1.938 0.01 0.0
36 Dieldrin E ESTIMATE EPA WWTP Tool V4.0 0.32 0.322 0.002 0.0
37 Diuron E ESTIMATE EPA WWTP Tool V4.0 0.145 0.146 0.001 0.0
38 Endosulphan E ESTIMATE EPA WWTP Tool V4.0 0.01 0.01 0.0 0.0
65 Ethyl benzene E ESTIMATE EPA WWTP Tool V4.0 0.123 0.124 0.001 0.0
88 Fluoranthene E ESTIMATE EPA WWTP Tool V4.0 0.021 0.021 0.0 0.0
24
83 Fluorides (as total F) E ESTIMATE EPA WWTP Tool V4.0 538.22 540.9 2.68 0.0
40 Halogenated organic compounds (as AOX) E ESTIMATE EPA WWTP Tool V4.0 3.673 3.691 0.018 0.0
42 Hexachlorobenzene (HCB) E ESTIMATE EPA WWTP Tool V4.0 0.002 0.002 0.0 0.0
43 Hexachlorobutadiene (HCBD) E ESTIMATE EPA WWTP Tool V4.0 0.002 0.002 0.0 0.0
89 Isodrin E ESTIMATE EPA WWTP Tool V4.0 0.09 0.09 0.0 0.0
23 Lead and compounds (as Pb) E ESTIMATE EPA WWTP Tool V4.0 1.531 1.539 0.008 0.0
45 Lindane E ESTIMATE EPA WWTP Tool V4.0 0.004 0.004 0.0 0.0
21 Mercury and compounds (as Hg) E ESTIMATE EPA WWTP Tool V4.0 0.101 0.102 0.001 0.0
68 Naphthalene E ESTIMATE EPA WWTP Tool V4.0 0.705 0.709 0.004 0.0
22 Nickel and compounds (as Ni) E ESTIMATE EPA WWTP Tool V4.0 11.931 11.99 0.059 0.0
64 Nonylphenol and Nonylphenol ethoxylates (NP/NPEs) E ESTIMATE EPA WWTP Tool V4.0 0.102 0.103 0.001 0.0
69 Organotin compounds (as total Sn) E ESTIMATE EPA WWTP Tool V4.0 0.015 0.015 0.0 0.0
48 Pentachlorobenzene E ESTIMATE EPA WWTP Tool V4.0 0.002 0.002 0.0 0.0
71 Phenols (as total C) E ESTIMATE EPA WWTP Tool V4.0 19.011 19.106 0.095 0.0
50 Polychlorinated biphenyls (PCBs) E ESTIMATE EPA WWTP Tool V4.0 0.013 0.013 0.0 0.0
72 Polycyclic aromatic hydrocarbons (PAHs) E ESTIMATE EPA WWTP Tool V4.0 1.242 1.248 0.006 0.0
52 Tetrachloroethylene (PER) E ESTIMATE EPA WWTP Tool V4.0 0.689 0.692 0.003 0.0
73 Toluene M ESTIMATE EPA WWTP Tool V4.0 0.18 0.181 0.001 0.0
12 Total nitrogen E EN ISO 11905-1:1998 23087.83 23189.1 101.27 0.0
76 Total organic carbon (TOC) (as total C or COD/3) M ESTIMATE EPA WWTP Tool V4.0 52991.6 53255.1 263.5 0.0
13 Total phosphorus E ALT ISO 6838:2004 3098.43 3125.73 27.3 0.0
57 Trichloroethylene E ESTIMATE EPA WWTP Tool V4.0 0.117 0.118 0.001 0.0
77 Trifluralin E ESTIMATE EPA WWTP Tool V4.0 0.003 0.003 0.0 0.0
75 Triphenyltin and compounds E ESTIMATE EPA WWTP Tool V4.0 0.003 0.003 0.0 0.0
60 Vinyl chloride E ESTIMATE EPA WWTP Tool V4.0 0.077 0.077 0.0 0.0
78 Xylenes E ESTIMATE EPA WWTP Tool V4.0 0.431 0.433 0.002 0.0
24 Zinc and compounds (as Zn) E ESTIMATE EPA WWTP Tool V4.0 54.763 55.035 0.272 0.0
25
SECTION B : REMAINING PRTR POLLUTANTS
RELEASES TO WATERS Please enter all quantities in this section in KGs
POLLUTANT QUANTITY
M/C/E Method Used
No. Annex II Name Method Code Designation or Description Emission Point 1
T (Total) KG/Year
A (Accidental) KG/Year
F (Fugitive) KG/Year
0.0 0.0 0.0 0.0
SECTION C : REMAINING POLLUTANT EMISSIONS (as required in your Licence)
RELEASES TO WATERS Please enter all quantities in this section in KGs
POLLUTANT QUANTITY
M/C/E Method Used
Pollutant No. Name
Method Code Designation or Description Emission Point 1
T (Total) KG/Year
A (Accidental) KG/Year
F (Fugitive) KG/Year
238 Ammonia (as N) M OTH MEWAM 1981 556.34 740.52 0.0 184.18
303 BOD M OTH APHA 2005:5210:B 6497.27 8289.57 0.0 1792.3
306 COD M OTH APHA 2005:5220:C 35323.33 39192.1 0.0 3868.77
362 Kjeldahl Nitrogen M OTH 1135.17 1445.16 0.0 309.99
327 Nitrate (as N) M OTH 23087.83 23397.82 0.0 309.99
372 Nitrite (as N) M OTH 245.04 248.01 0.0 2.97
332 Ortho-phosphate (as PO4) M EN ISO 6878:2004 3098.43 3124.79 0.0 26.36
240 Suspended Solids M OTH APHA 2005:2450:B
26
4.3 RELEASES TO WASTEWATER OR SEWER Link to previous years emissions data
| PRTR# : D0015 | Facility Name : Tramore Waste Water Treatment Plant | Filename : D0015_2011 rev 0.xls | Return Year : 2011 |
26/03/2012 15:51
8 8 16 16 6 6 6 6 SECTION A : PRTR POLLUTANTS
OFFSITE TRANSFER OF POLLUTANTS DESTINED FOR WASTE-WATER TREATMENT OR SEWER Please enter all quantities in this section in KGs
POLLUTANT METHOD
QUANTITY
Method Used
No. Annex II Name
M/C/E
Method Code
Designation or Description Emission Point 1
T (Total) KG/Year
A (Accidental) KG/Year
F (Fugitive) KG/Year
0.0 0.0 0.0 0.0
SECTION B : REMAINING POLLUTANT EMISSIONS (as required in your Licence)
OFFSITE TRANSFER OF POLLUTANTS DESTINED FOR WASTE-WATER TREATMENT OR SEWER Please enter all quantities in this section in KGs
POLLUTANT METHOD
QUANTITY
Method Used
Pollutant No. Name
M/C/E
Method Code
Designation or Description Emission Point 1
T (Total) KG/Year
A (Accidental) KG/Year
F (Fugitive) KG/Year
0.0 0.0 0.0 0.0
27
4.4 RELEASES TO LAND
Link to previous years emissions data
| PRTR# : D0015 | Facility Name : Tramore Waste Water Treatment Plant | Filename : D0015_2011 rev 0.xls | Return Year : 2011 |
26/03/2012 15:51
8 8 16 16 6 6 6 6
SECTION A : PRTR POLLUTANTS
RELEASES TO LAND Please enter all quantities in this section in KGs
POLLUTANT METHOD QUANTITY
Method Used
No. Annex II Name
M/C/E Method Code
Designation or Description Emission Point 1
T (Total) KG/Year
A (Accidental) KG/Year
0.0 0.0 0.0
SECTION B : REMAINING POLLUTANT EMISSIONS (as required in your Licence)
RELEASES TO LAND Please enter all quantities in this section in KGs
POLLUTANT METHOD QUANTITY
Method Used
Pollutant No. Name
M/C/E Method Code
Designation or Description Emission Point 1
T (Total) KG/Year
A (Accidental) KG/Year
0.0 0.0 0.0
28
5. ONSITE TREATMENT & OFFSITE TRANSFERS OF WASTE
| PRTR# : D0015 | Facility Name : Tramore Waste Water Treatment Plant | Filename : D0015_2011 rev 0.xls | Return Year : 2011 |
26/03/2012 15:51
5 6
Please enter all quantities on this sheet in Tonnes
5
Quantity (Tonnes
per Year) Method Used
Haz Waste : Name and Licence/Permit No
of Next Destination Facility
Non Haz Waste: Name and
Licence/Permit No of Recover/Disposer
Haz Waste : Address of Next Destination Facility
Non Haz Waste: Address of Recover/Disposer
Transfer Destination
European Waste Code Hazardous
Quantity T /Year
Description of Waste
Waste Treatment Operation
M/C/E
Method Used
Location of
Treatment Name and Licence / Permi t No. of R ecoverer / Disposer / Br oker Address of R ecover er / Disposer / Broker
Within the Country 19 08 05 No 150.356
sludges from treatment of urban waste water R10 M Weighed
Offsite in Ireland
Dungarvan Wastewater Treatment Plant,D017-01
Ballinacourty,Dungarvan,Co. Waterford,.,Ireland
Within the Country 19 08 01 No 85.5 screenings D5 C
Volume Calculation
Offsite in Ireland
Greenstar Ltd.,WCP-KK-054(A)-08
Carriganard,Six Cross Roads,Waterford,.,Ireland
29
APPENDIX C
RESPONSES TO THE AGENCY’S ASSESSMENT
OF THE 2010 AER
30
The Agency provided an assessment of the 2010 Tramore Annual Environmental Report (AER) in which
they raised certain issues and requested actions in particular instances. This Appendix of the 2011 AER
provides replies to that assessment. Each assessment/action is dealt with individually below:
Metals and Organic Compounds Not Reported in 2010:
As outlined in the 2010 AER, the sample for metal and organic compound analysis were lost in transit
between the laboratory company who were carrying out the overall analysis and their contract laboratory in
the UK who were carrying out part of the analysis. No analysis was completed on the samples and 2010
had passed before the loss of sample was known.
The Metals and Organic Compounds were sampled again in 2011 and the results are reported on in this
AER in Section 2.1.1 and Appendix A.
Complete Summary of Non-Compliant Results for Discharge:
The ELRA submitted with the 2010 AER highlighted 12 non-compliances with the TON ELV and 2 non-
compliances with the Ammonia ELV. The AER itself only highlighted a single non-compliance with respect
to TON. The operator at the WWTP takes daily samples of the treated effluent being discharged and
carries out tests for the various parameters at regular intervals. In the case of TON and Ammonia, analysis
is carried out approximately once a week. In 2010, there were 54 samples analysed for TON and Ammonia
and 12 of these were in excess of the TON ELV of 20mg/l and 2 samples were in excess of the Ammonia
ELV of 5mg/l.
The Licence only requires 12 samples a year to be taken and analysed. These samples are taken on a pre-
determined date which is agreed with the operator and not varied from. Only one of the 12 samples for
reporting to the Agency was in excess of the 20mg/l ELV for TON and all Ammonia results within the 12
samples were fully compliant. The other 42 samples taken were at the operator’s own discretion, but
generally once a week. They do not form any part of the licence requirement for reporting of results to the
Agency.
The reason for the high TON results is the fact that when Total Nitrogen loads in the influent are high, the
plant is not always capable of adequate denitrification of the effluent. This is due to the fact that the plant
was not designed with nutrient removal in mind. However, Nitrogen removal efficiency improved in 2011
from 38.5% to 59.5%. The Council proposes to further monitor the TON levels in the discharge in 2012 to
see if improvement works may be necessary. This will be reported on in the 2012 AER.
Summary of Nutrient Removal Efficiencies for P & N not reported in 2010:
A summary table of Nutrient Removal Efficiencies for both Total Phosphorous and Total Nitrogen were
reported in Section 3.1 of the 2010 AER. These results showed that the WWTP was reducing Total P by an
average of 49.1% and Total N by 38.5%. There was no omission in the 2010 AER for this information.
31
Provide an Assessment of the Ambient Water Quality against the relevant EQS Standard.
The requirement to provide ambient monitoring data for the Tramore Licence was for the bathing area at
the Main Strand. The Bathing Water Regulations are the relevant EQS standard for the receiving waters
from the Tramore Agglomeration. The Bathing Water Quality results were included in the 2010 AER and
have been reproduced again below along with a comment with respect to compliance with the relevant
EQS standard (Bathing Water Quality).
Tramore Main Strand
Bathing Water Quality Results 2010
Sampling Location Total Faecal Faecal
Centre of Bathing Area Coliforms Coliforms Streptococci
Date Time No./ 100
ml No./ 100 ml No./ 100 ml
18-May-10 11.35 1 1 1
08-Jun-10 12.20 5 1 3
17-Jun-10 9.15 14 8 3
24-Jun-10 9.50 1 0 0
08-Jul-10 13.05 1 0 0
22-Jul-10 11.45 3 3 0
05-Aug-10 11.55 56 56 41
12-Aug-10 14.05 4 4 8
24-Aug-10 13.30 13 136 2
Bathing water quality was in compliance with National and European requirements and also met the Blue
Flag standard. This was reported in the 2010 AER and was therefore not omitted.
Complete Summary of the Complaints Provided in the 2010 AER:
There were no complaints noted in the 2010 AER. However, one compliant was notified by the Council to
the Agency on 22nd
September 2010 with respect to an overflow to the Backstrand. While the EPA received
a total of seven complaints (some directly from the public) with regard to the Tramore agglomeration and
forwarded these to the Council, owing to a misinterpretation of the licence requirements, these were not
reported in the 2010 AER as complaints. The complaints mostly related to the overflow from an unlicensed
SWO to the Backstrand at Tramore. This overflow was notified to the Agency as an incident in 2010 and
noted in the AER. The issue was resolved by installing a constructed wetland to intercept and provide
some treatment to the overflow from this unlicensed SWO. A single compliant related to an alleged
overflow at the pier and tinkering of effluent. This complaint was investigated but nothing was found. A
further complaint forwarded by the Agency in November 2010 was found not to involve sewage.
Following the resolution of the issue as outlined above, there were no complaints in the remainder of 2010
and all of 2011.
32
Provide an Estimate of the Parametric Improvement in the Discharge with respect to the recommendations of the SWO Identification & Assessment Report:
The SWO Identification and Assessment Report indicated that there would be a need to upgrade the SW3
and SW4 as well as notify the Agency with respect to the unlicensed SWO. These upgrade works are to be
provided under the WSIP-funded Tramore Sewerage Scheme Stage 2 project. The intention is to meet the
requirements of the DoEHLG’s Guidance Document on SWOs. There are no parametric improvements that
can be estimated for such an upgrade.
Provide an Estimate of the Water Quality Improvement with respect to the recommendations of the SWO Identification & Assessment Report:
The Water Quality Improvement associated with the necessary SWO upgrades will ensure that the
requirements of the Bathing Water Directive are met. While there are no parametric improvements that can
be estimated, the fact that the SWOs will comply with the DoEHLG’s guidance document on Storm Water
Overflows means that Bathing Water Quality will be enhanced.
Provide an Assessment of the Existing WWTP Performance with respect to the Receiving Water Body Designation:
The receiving water body for the discharge from the Tramore WWTP is designated as a Bathing Water
area (Tramore Main Strand). This beach complied with the regulatory requirements for Bathing Water
Quality in 2010. The Bathing Water Monitoring Results are outlined in more detail in Section 4.5 of the
2010 AER and also in Appendix C of this report. Thus, the bathing waters at Tramore were not adversely
impacted by the discharge from the Tramore WWTP in 2010.
Provide an Assessment of the Existing WWTP Performance with respect to WPA Licensed Wastewater Discharges in the Agglomeration:
There is only 1 No. WPA Licensed Activity in Tramore. This is for the Splash World leisure centre. The
discharges would typically be of a largely domestic nature. There has been no evidence of impacts from
their discharges on the WWTP in 2010 or theretofore.
Provide an Assessment of the Integrity of the Existing Wastewater Works
The 2010 AER did not provide an assessment of the integrity of the existing wastewater works (WWTP and
Network), though the licence required it as part of the second AER. The assessment was carried out as
part of the Preliminary Report for the Tramore Sewerage Scheme Stage 2 and is being currently reviewed
prior to submission to the DoECLG. A copy of the approved assessment will be forwarded to the Agency as
soon as it is available and reported on in the 2011 AER. The assessment will largely relates to the network
since the 20,000 p.e. WWTP is new and only became operational in 2008. There are no issues with leaks
at the WWTP nor are there infiltration problems. The sewer network was upgraded in 2003-2007 but there
is a necessity to assess the integrity of the system to ensure maximum efficiency of pump stations and
separation of foul and surface water flows.
33
Provide a Network Integrity Assessment in the ELRA
This assessment could not be provided in the ELRA submitted because the integrity of the Tramore
network was not assessed as required under Condition 5.2 of the licence. The assessment will be included
in the next ELRA.
Identify the Risks Associated with Pump Stations in the ELRA
The ELRA for the 2010 AER was prepared by RPS Consulting Engineers in accordance with the Agency’s
guidelines for the preparation of this report. The Pump Stations were not specifically covered in the ELRA
but the overall risk assessment scores would not be significantly changed. The next ELRA will fully cover
all aspects of the agglomeration.
Include Operations & Maintenance Procedures in the ELRA
While the ELRA did not have a separate section relating to Operation & Maintenance Procedures, it does
state that there is an Operation & Maintenance Contract in place with Veolia, who operate the WWTP on
behalf of Waterford County Council. They have O&M procedures in place. Waterford County Council has
Operation and Maintenance Procedures in place in general for all our facilities.
Requirement for a Technical Amendment
There is a requirement to seek a Technical Amendment on the Licence with respect to the unlicensed
SWO at the Promenade Pump Station. It is proposed to seek this Technical Amendment in 2012 once all
details of this SWO as a replacement for SW2 are prepared.